47

€¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 2: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 3: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 4: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 5: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 6: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 7: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 8: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 9: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 10: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 11: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 12: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 13: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 14: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 15: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 16: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 17: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 18: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 19: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 20: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 21: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 22: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 23: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 24: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 25: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 26: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 27: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 28: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 29: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 30: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 31: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational

PLANCON PART FATTACHMENT C

POST-BID OPENING CERTIFICATION

District/CTC Name: New Hope Solebury School District PDE Project No.: 3833

Project Building Name: High School / Middle School / DAO

Bid Opening Date (M/D/YYYY): 7/21/2016 (original bid opg date 6/9/2016) Bid Award Date: (M/D/YYYY): 7/28/2016

Expected Date Construction Contracts Will Be Executed by the school district (M/D/YYYY): 8/11/2016

1. Did the school district/CTC receive bids for each prime contract?

2. OCIP: If included in the project via the Quote Method or the Bid Alternate Method, indicate the Board's final decision.

Insurance by Owner X Insurance by Contractor (OCIP Project) (Non-OCIP Project)

3. How did the bids compare with estimates?

4. Indicate the number/date of the last addendum issued before the bid opening for this project.

5. Indicate the bid alternates that have been accepted.

Board Action Date: 28-Jul-16

Voting: Aye Nay Abstentions Absent

Board Secretary’s Signature:

Board Secretary’s Name, Printed: Mr. Andrew G. Lechman Date Signed:

PLANCON-F, JULY 1, 2010 FORM EXPIRES 06-30-12 PAGE 15

Yes, General Construction, HVAC, Plumbing and Electrical Construction.

The rebid of the General Construction Contract produced lower bids than previously received.(Previous)The HVAC, Plumbing and Electrical Bids were all held until the rebid of the General Construction Contract wasreceived. The overall project is now within the budget estimate.

Ded-Alt. #1: Eliminate LGI Room 153 & related work.Ded-Alt. #6: Mod-Bit roofing system by The Garland Company.Add-Alt. #14: Remove existing paint & provide EIFS on existing exterior CMU walls.

Yes. Ded-Alt. #1: Eliminate LGI Room 153 & related work.

No.

No.

No.

6. Do any of the accepted bid alternates affect reimbursable capacity, Act 34 capacity, scheduled area or architectural area?If yes, submit revised Part F documents.

7. Is a second Act 34 hearing or referendum required based on the planned bid award (base bid plus accepted alternates)?

8. Is the school district/CTC planning to rebid any prime contracts? If yes, what is the purpose, scope and timelineassociated with this rebid?

9. Have there been or could there be discussions before contract execution with any bidders about possible bid adjustmentsto the project scope through the issuance of future construction change orders following contract execution? If yes, describethe nature of those discussions.

The Board certifies that the information provided above accurately describes the actions taken by the school district/CTCprior to contract execution on the above-referenced PlanCon project. Failure to fully disclose any information pertinent to thefollowing may result in the denial of reimbursement for this project: award to the lowest responsible bidder for any primecontract; issuance of permits and approvals by local, state and other governmental agencies; computation of reimbursablecapacity, architectural area and scheduled area; and compliance with Act 34 of 1973, the 20 year rule and the 20% Rule forAlteration Costs used in determining the eligibility of building renovations for reimbursement.

Addendum 8, 19 July 2016.

Page 32: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational

PART G: PROJECT ACCOUNTING BASED ON BIDS

BOARD TRANSMITTAL

DISTRICT/CTC: New Hope Solebury School District COUNTY: BucksPRJT BLDG NAME: High School / Middle School PROJECT #: 3833ALL PRJTS PAGE #

X G02-G03 Project Accounting Based on BidsX Add't Costs Additional Project CostsX G04(a)-G04(b) Detailed CostsX G05-G07 Total Contract AwardsX G08 Prime Contractor CertificationX G09 20% Rule for Alteration Costs for Non-Vocational ProjectsX G10 Project FinancingX G11 Act 34 of 1973: Substantial Addition Determination

Justification for Contract Award to Other than Low BidderX Bid Tabulations with Bid Opening Date ThereonX Letter from insurance provider for owner controlled insurance

program or letter(s) from contractor's insurance provider(s) if insurance provided by contractor(s) using the quote method

*** FOR SITE ACQUISITION AND BUILDING PURCHASE ONLY ***

N/A Property Deed or Declaration of Taking with AttachmentsN/A Settlement Statement or Application for Payment of

Estimated Just CompensationN/A Clear Title CertificationN/A Bill for Independent Appraisal #1N/A Bill for Independent Appraisal #2

***FOR NEW BUILDINGS OR SUBSTANTIAL ADDITIONS ONLY ***

N/A G12 Act 34 of 1973: Maximum Building Construction CostN/A G13 Act 34 of 1973: Requirement for Second Public HearingN/A G14-G15 Act 34 of 1973: School Building CapacityN/A G16 Act 34 of 1973: Aggregate Building Expenditure StandardN/A Act 34 of 1973: Second Hearing Notice and Proof of PublicationN/A Act 34 of 1973: Second Hearing Minutes or TranscriptN/A Act 34 of 1973: Referendum Notice and Proof of Publication

Proof of PublicationN/A Act 34 of 1973: Official Referendum QuestionN/A Act 34 of 1973: Official Referendum Results

The architectural firm for this project is: Godshall Kane O'Rourke Architects, LLC

The architect to be contacted if there are any questions about Part G is:

Kevin Godshall, AIA, Principal 215-646-2003 215-646-5707Architect's Name and Position Phone Number Fax Number

The architect's e-mail address is: [email protected]

The architectural firm's address is: 12 East Butler Avenue, Ambler, PA 19002The school administrator to be contacted if there are any questions about Part G is:Dr. Steven M. Yanni, Superintendent 215-862-5372 215-862-2906

District/CTC Administrator's Name and Position Phone Number Fax Number

The SD/CTC administrator's e-mail address is: [email protected]

This certifies that the attached materials were approved for submission to thePennsylvania Department of Education by board action.

BOARD ACTION DATE:

VOTING: AYE NAY ABSTENTIONS ABSENT

Mr. Andrew G. LechmanSignature, Board Secretary Board Secretary's Name, Printed or Typed

New Hope Solebury School District, 180 West Bridge Street, New Hope, PA 18938District/CTC Address Date

REVISED JULY 1, 2010 FORM EXPIRES 6-30-12 PLANCON-G01

Page 33: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational

PROJECT ACCOUNTING BASED ON BIDS (1 of 2)District/CTC: Project Name: Project #:

New Hope Solebury School District High School / Middle School 3833

ROUND FIGURES TO NEAREST DOLLARPROJECT COSTS NEW EXISTING TOTAL

A. STRUCTURE COSTS (include site development)

1. General (Report costs for sanitary sewage disposal on Line E-1.) 5,145,000 7,785,000 12,930,0002. Heating and Ventilating 1,713,700 3,977,300 5,691,0003. Plumbing (Report costs for sanitary sewage disposal on Line E-1.) 239,800 560,200 800,0004. Electrical 1,442,802 2,367,198 3,810,0005. Asbestos Abatement (G04, line C-3) X X X X X

(include AHERA clearance air monitoring)

6. Building Purchase Amount X X X X X7. Other * (Exclude test borings and site survey)

(Use PlanCon-G-Add't Costs page if necessary.)

a.

b.

c.

d.

e. PlanCon-G-Add't Costs, TotalA-1 to A-7 - Subtotal 8,541,302 14,689,698 23,231,0008. Construction Insurance

a. Owner Controlled Insurance Program on Structure Costs (Exclude asbestos abatement, building purchase and other structure costs not covered by the program)

b. Builder's Risk Insurance (if not included in primes) 29,000 29,000c. Construction Insurance - Total 29,000 29,000

9. TOTAL-Structure Costs (A-1 to A-7-Subtotal plus A-8-c) 8,570,302 14,689,698 23,260,000B. ARCHITECT'S FEE (exclude fee for demoliton of entire existing bldg)

1. Architect's/Engineer's Fee on Structure 585,835 916,305 1,502,1402. EPA-Certified Project Designer's X X X X X

Fee on Asbestos Abatement X X X X X3. TOTAL - Architect's Fee 585,835 916,305 1,502,140

C. MOVABLE FIXTURES AND EQUIPMENT1. Movable Fixtures and Equipment 100,000 158,000 258,0002. Architect's Fee3. TOTAL - Movable Fixtures & Equipment 100,000 158,000 258,000

D. STRUCTURE COSTS, ARCHITECT'S FEE,MOVABLE FIXTURES & EQUIPMENT - 9,256,137 15,764,003 25,020,140TOTAL (A-9 plus B-3 plus C-3)

E. SITE COSTS1. Sanitary Sewage Disposal 45,000 45,0002. Sanitary Sewage Disposal Tap-In Fee and/or

Reserve Capacity Charges3. Owner Controlled Insurance Program/Builder's Risk

Insurance on Sanitary Sewage Disposal4. Architect's/Engineer's Fee for

Sanitary Sewage Disposal

5. Site Acquisition Costs X X X X Xa. Gross Amount Due from Settlement Statement X X X X X

or Estimated Just Compensation X X X X X

b. Real Estate Appraisal Fees X X X X X

c. Other Related Site Acquisition Costs X X X X X

d. Site Acquisition Costs - Total X X X X X

6. TOTAL - Site Costs 45,000 45,000F. STRUCTURE COSTS, ARCHITECT'S FEE,

MOVABLE FIXTURES & EQUIPMENT, AND 9,301,137 15,764,003 25,065,140SITE COSTS - TOTAL (D plus E-6)

* Type "No Fee" beside each item for which no design fee is charged.**Type "E" if any costs represent estimates.

REVISED JULY 1, 2010 FORM EXPIRES 6-30-12 PLANCON-G02

Page 34: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational

PROJECT ACCOUNTING BASED ON BIDS (2 of 2)District/CTC: Project Name: Project #:

New Hope Solebury School District High School / Middle School 3833

ROUND FIGURES TO NEAREST DOLLAR

PROJECT COSTS (CONT.) TOTAL

G. ADDITIONAL CONSTRUCTION-RELATED COSTS

1. Project Supervision (inc. Asbestos Abatement Project Supervision)

2. Construction Manager Fee and Related Costs 846,4903. Total Demolition of Entire Existing Structures and Related Asbestos Removal

to Prepare Project Site for Construction of New School Building and RelatedAHERA Clearance Air Monitoring and EPA-Certified Project Designer's Feeon Asbestos Abatement (Include costs for architect's/engineer'sfee and OCIP; exclude costs for partial demolition.)

4. Architectural Printing

5. Test Borings 10,0006. Site Surveys 10,000

7. Other (Attach PlanCon-G-Add't Costs page if needed.)

a.

b.PlanCon-G-Add't Costs, Total 1,148,870

8. Contingency 1,082,5009. TOTAL - Additional Construction-Related Costs 3,097,860

H. FINANCING COSTS BOND ISSUE/NOTE BOND ISSUE/NOTE BOND ISSUE/NOTE X X X X X X FOR THIS PROJECT ONLY SERIES OF 2014B SERIES OF 2015 SERIES OF 2016 X X X X X X

(EXCLUDE ACCRUED INTEREST)

1. Underwriter Fees 11,162 47,817 83,521 142,5002. Legal Fees 4,700 22,000 40,000 66,7003. Financial Advisor 4,700 22,500 40,000 67,2004. Bond Insurance5. Paying Agent/Trustee

Fees and Expenses 750 1,000 3,000 4,7506. Capitalized Interest

7. Printing 2,000 8,500 12,000 22,5008. CUSIP & Rating Fees 2,650 11,700 19,000 33,3509. Other

a.

b.

10. TOTAL-Financing Costs 25,962 113,517 197,521 337,000I. TOTAL PROJECT COSTS (F plus G-9 plus H-10) 28,500,000REVENUE SOURCES BOND ISSUE/NOTE BOND ISSUE/NOTE BOND ISSUE/NOTE

(EXCLUDE ACCRUED INTEREST) SERIES OF 2014B SERIES OF 2015 SERIES OF 2016 TOTAL

J. AMOUNT FINANCED 2,255,000 9,660,000 16,345,000 28,260,000FOR THIS PROJECT ONLY

K. ORIGINAL ISSUE DISCOUNT/ 95,857 95,235 33,099 224,191PREMIUM FOR THIS PROJECT ONLY

L. INTEREST EARNINGS 1,021 5,641 9,147 15,809FOR THIS PROJECT ONLY

M. BUILDING INSURANCE RECEIVED

N. PROCEEDS FROM SALE OF BUILDING OR LAND

O. LOCAL FUNDS - CASH (SEE INSTRUCTIONS)

P. OTHER FUNDS (PROVIDE DESCRIPTION ON SEPARATE SHEET)

Q. TOTAL REVENUE SOURCES 28,500,000

REVISED JULY 1, 2010 FORM EXPIRES 6-30-12 PLANCON-G03

Page 35: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational

ADDITIONAL PROJECT COSTSDistrict/CTC: Project Name: Project #:

New Hope Solebury School District High School / Middle School 3833

G02-A. STRUCTURE COSTS (incl. site dev.) NEW EXISTING TOTAL

TOTAL - STRUCTURE COSTS

* - Type "No Fee" beside each item listed above for which no design fee is charged.

G03 - G. ADDITIONAL CONSTRUCTION-RELATED COSTS TOTAL

Telephone System 150,000

CCTV 100,000

Completed Work: Auditorium 411,100

Indoor Air Quality Monitoring 10,000

Approvals/Permits/Utilities 100,000

Land Development Legal Assistance 15,000

HVAC TAB & Commissioning 152,770

Construction Testing 50,000

Environmental Testing & Consulting 10,000

Asbestos Abatement 88,000

Legal Fees 62,000

TOTAL - ADDITIONAL CONSTRUCTION-RELATED COSTS 1,148,870

REVISED JULY 1, 2010 FORM EXPIRES 6-30-12PLANCON-G-ADD'T COSTS

Page 36: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational

DETAILED COSTS (1 of 2)District/CTC: Project Name: Project #:

New Hope Solebury School District High School / Middle School 3833

NEW EXISTING TOTAL

A. SITE DEVELOPMENT COSTS(Exclude Sanitary Sewage Disposal)

1. General (Include Rough Grading to Receive Building) 1,795,593 150,000 1,945,593

2. Heating and Ventilating

3. Plumbing 50,000 70,000 120,000

4. Electrical 50,000 50,000 100,000

5. Other:

6. Other:

7. A-1 thru A-6 - Subtotal 1,895,593 270,000 2,165,593

8. Construction Insurance

a. Owner Controlled Insurance Program on Site Development Costs

b. Builder's Risk Insurance (if not included in primes)

c. Construction Insurance - Total

9. Site Development Costs - Total 1,895,593 270,000 2,165,593

B. ARCHITECT'S FEE ON SITE DEVELOPMENT 101,640 16,200 117,840

EXISTING

C. ASBESTOS ABATEMENT

1. Asbestos Abatement

2. AHERA Clearance Air Monitoring

3. Asbestos Abatement - Total

D. EPA-CERTIFIED PROJECT DESIGNER'S FEE ON ASBESTOS ABATEMENT

E. ROOF REPLACEMENT/REPAIR

1. Roof Replacement Repair

2. Owner Controlled Insurance Program on Roof Replacement/Repair

3. Builder's Risk Insurance (if not included in primes)

4. Roof Replacement/Repair - Total

F. ARCHITECT'S FEE ON ROOF REPLACEMENT/REPAIR

REVISED JULY 1, 2010 FORM EXPIRES 6-30-12 PLANCON-G04(a)

Page 37: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational

DETAILED COSTS (2 of 2)District/CTC: Project Name: Project #:

New Hope Solebury School District High School / Middle School 3833

COMPLETE THE SECTION BELOW ONLY IF COSTS REPORTED ON PAGE G02FOR THE TECHNOLOGY CONTRACT(S) REPRESENT ESTIMATES

NEW EXISTING TOTAL

G. ESTIMATED TECHNOLOGY CONTRACT(S)

H. ESTIMATED ARCHITECT'S/ENGINEER'S FEE ON ESTIMATED TECHNOLOGY CONTRACT(S) (Complete only if A/E fee on Page G02, line B-1 includes estimated A/E fee on the Estimated Technology Contract(s). Complete this line only if line G is completed.)

COMPLETE THE SECTION BELOW ONLY IF SPECIAL SESSION ACT 1 OF 2006 (PROPERTY TAX RELIEF) APPLIES

STRUCTURE COSTS (exclude site development) TOTAL

I. NATATORIUM

J. DISTRICT ADMINSTRATION OFFICE

K. DAY CARE / PRE-SCHOOL (non-academic)

L. NON-DISTRICT USE (health clinic, public library, etc.)

M. OWNER'S CONTROLLED INSURANCE PROGRAM ON THESE STRUCTURE COSTS

N. BUILDER'S RISK INSURANCE ON THESE STRUCTURE COSTS (if not included in primes)

O. ARCHITECT'S FEE ON THESE STRUCTURE COSTS

REVISED JULY 1, 2010 FORM EXPIRES 6-30-12 PLANCON-G04(b)

Page 38: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational

TOTAL CONTRACT AWARDSDistrict/CTC: Project Name: Project #:

New Hope Solebury School District High School / Middle School 3833

1. GENERAL CONTRACT

Date of Bid Opening (MM/DD/YY): 7/21/2016

Contractor's Name: Skepton Construction Base Bid $ 13,275,000

Accepted Alternates - Add or (Deduct):

(Attach additional information if necessary.)

Alt. # Description of Alternate

# Ded-Alt. 1 : Eliminate LGI Room 153 & related work. $ -498,000# Ded-Alt. 6 : Mod-Bit roofing system by The Garland Company. $ -1,000# Add-Alt.14 : Provide EIFS on existing exterior CMU walls. $ 199,000# : $

# : $

# : $

# : $

# : $

# : $

# : $

# : $

# : $

# : $

# : $

Based Bid plus Accepted Alternates - Subtotal: $ 12,975,000

Contractor's Insurance (Complete only if insurance is not bid,but is provided by the contractor using the quote method.) $

Total Contract Award: $ 12,975,000

2. HEATING AND VENTILATING CONTRACT

Date of Bid Opening (MM/DD/YY): 6/9/2016

Contractor's Name: The Farfield Company Base Bid $ 5,790,000

Accepted Alternates - Add or (Deduct):

(Attach additional information if necessary.)

Alt. # Description of Alternate

# Ded-Alt. 1 : Eliminate LGI Room 153 & related work. $ -99,000# Ded-Alt. 6 : Mod-Bit roofing system by The Garland Company. $ 0# Add-Alt.14 : Provide EIFS on existing exterior CMU walls. $ 0# : $

Based Bid plus Accepted Alternates - Subtotal: $ 5,691,000

Contractor's Insurance (Complete only if insurance is not bid,but is provided by the contractor using the quote method.) $

Total Contract Award: $ 5,691,000

REVISED JULY 1, 2010 FORM EXPIRES 6-30-12 PLANCON-G05

Page 39: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational

TOTAL CONTRACT AWARDSDistrict/CTC: Project Name: Project #:

New Hope Solebury School District High School / Middle School 3833

3. PLUMBING CONTRACT

Date of Bid Opening (MM/DD/YY): 6/9/2016

Contractor's Name: Stan-Roch Plumbing Base Bid $ 817,500

Accepted Alternates - Add or (Deduct):

(Attach additional information if necessary.)

Alt. # Description of Alternate

# Ded-Alt. 1 : Eliminate LGI Room 153 & related work. $ -17,500# Ded-Alt. 6 : Mod-Bit roofing system by The Garland Company. $ 0# Add-Alt.14 : Provide EIFS on existing exterior CMU walls. $ 0# : $

Based Bid plus Accepted Alternates - Subtotal: $ 800,000

Contractor's Insurance (Complete only if insurance is not bid,but is provided by the contractor using the quote method.) $

Total Contract Award: $ 800,000

4. ELECTRICAL CONTRACT

Date of Bid Opening (MM/DD/YY): 6/9/2016

Contractor's Name: Boro Construction Base Bid $ 3,895,000

Accepted Alternates - Add or (Deduct):

(Attach additional information if necessary.)

Alt. # Description of Alternate

# Ded-Alt. 1 : Eliminate LGI Room 153 & related work. $ -85,000# Ded-Alt. 6 : Mod-Bit roofing system by The Garland Company. $ 0# Add-Alt.14 : Provide EIFS on existing exterior CMU walls. $ 0# : $

Based Bid plus Accepted Alternates - Subtotal: $ 3,810,000

Contractor's Insurance (Complete only if insurance is not bid,but is provided by the contractor using the quote method.) $

Total Contract Award: $ 3,810,000

5. ASBESTOS ABATEMENT

Date of Bid Opening (MM/DD/YY):

Contractor's Name: Base Bid $

Accepted Alternates - Add or (Deduct):

(Attach additional information if necessary.)

Alt. # Description of Alternate

# : $

# : $

# : $

# : $

Total Contract Award: $

REVISED JULY 1, 2010 FORM EXPIRES 6-30-12 PLANCON-G06

Page 40: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational

TOTAL CONTRACT AWARDSDistrict/CTC: Project Name: Project #:

New Hope Solebury School District High School / Middle School 3833

6. PRIME CONTRACT FOR:

Date of Bid Opening (MM/DD/YY):

Contractor's Name: Base Bid $

Accepted Alternates - Add or (Deduct):

(Attach additional information if necessary.)

Alt. # Description of Alternate

# : $

# : $

# : $

# : $

Based Bid plus Accepted Alternates - Subtotal: $

Contractor's Insurance (Complete only if insurance is not bid,but is provided by the contractor using the quote method.) $

Total Contract Award: $

7. PRIME CONTRACT FOR:

Date of Bid Opening (MM/DD/YY):

Contractor's Name: Base Bid $

Accepted Alternates - Add or (Deduct):

(Attach additional information if necessary.)

Alt. # Description of Alternate

# : $

# : $

# : $

# : $

Based Bid plus Accepted Alternates - Subtotal: $

Contractor's Insurance (Complete only if insurance is not bid,but is provided by the contractor using the quote method.) $

Total Contract Award: $

8. PRIME CONTRACT FOR:

Date of Bid Opening (MM/DD/YY):

Contractor's Name: Base Bid $

Accepted Alternates - Add or (Deduct):

(Attach additional information if necessary.)

Alt. # Description of Alternate

# : $

# : $

# : $

# : $

Based Bid plus Accepted Alternates - Subtotal: $

Contractor's Insurance (Complete only if insurance is not bid,but is provided by the contractor using the quote method.) $

Total Contract Award: $

REVISED JULY 1, 2010 FORM EXPIRES 6-30-12 PLANCON-G07

Page 41: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 42: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 43: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 44: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational
Page 45: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational

20% RULE FOR ALTERATION COSTS FOR NON-VOCATIONAL PROJECTSDistrict/CTC: Project Name: PDE Project #:

New Hope Solebury School District High School / Middle School 3833

A. Alteration Costs Based on Bids $ 15,764,003(G02, Line F-EXIST)

B- 1. Building Purchase $(G02, Line A-6-EXIST)

2. Movable Fixtures & Equipment $ 158,000and Architect's Fee (G02, Line C-3-EXIST)

3. Site Development $ 270,000(G04(a), Line A-9-EXIST)

4. Architect's Fee on Site $ 16,200Development (G04(a), Line B-EXIST)

5. Asbestos Abatement $(G04(a), Line C-3-EXIST)

6. EPA-Certified Project Designer's $Fee on Asbestos Abatement (G04(a), Line D-EXIST)

7. Roof Replacement $(G04(a), Line E-4-EXIST)

8. Architect's Fee on Roof $Replacement (G04(a), Line F-EXIST)

9. Estimated Technology Contract(s) $(G04(b), Line I-EXIST)

10. Estimated Architect's Fee on $Estimated Technology Contract(s) (G04(b), Line J-EXIST)

11. Adjustment (B-1 plus B-2 through B-10) $ 444,200

C. Adjusted Alteration Costs(line A minus line B-11) $ 15,319,803

D- 1. Adjusted FTE 886(F12, ADJ ELEM-EXIST) (F12, ADJ MS/SEC-EXIST

+ NATATORIUM/DAO-EXIST)

2. Recommended Square Feet per student 92 123

3. Recommended Architectural Area (D-1 times D-2) + 108,978 = 108,978 sq. ft.

E. Median Construction Costs Per Square Foot $174

F. Replacement Costs (D-3 times E) $ 18,962,172

G. 20% Rule (F times .20) $ 3,792,434

If the Adjusted Alteration Costs (line C) are less than line G, provide information justifying a variance fromthis Departmental requirement. The justification must include an explanation as to why this is the best option

for the district. Please note that based on the provisions of Basic Education Circular (BEC) 24 P.S. § 7-733,

"School Construction Reimbursement Criteria," if the Adjusted Alteration Costs for this project fall below 20%

of the replacement value at the time this project is bid, the alteration work will be non-reimbursable, and the

project building will not be eligible for reimbursement for alterations for the next 20 years unless a request

for a variance is approved by the Department. If a variance was requested at Part A or Part D, provide an

updated justification.

REVISED JULY 1, 2010 FORM EXPIRES 6-30-12 PLANCON-G09

Page 46: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational

PROJECT FINANCINGDistrict/CTC: Project Name: PDE Project #:

New Hope Solebury School District High School / Middle School 3833PDE USE ONLY

AUN: Building Type:

Project Grades:___________ - __________ Type Work:

TO BE INPUT BY SD/CTC

Total Project Costs - Bid (G03, line I) $ 28,500,000Architectural Area for the Total Building 242,640 sq. ft.Actual Bid Opening Date (M/D/YY): 7/21/16Actual Bid Award Date (M/D/YY): 7/28/16Expected Date General Construction Contract 8/11/16 to be Executed (M/D/YY):

Expected Project Completion Date (M/YY): 09/2018Act 34 of 1973 Applies to this Project: Yes No X

PERMANENT FINANCING ONLY

Financing Method #1:G.O. Bonds Series B of 2014 Year Issued: 2014Total Issue/Note: $ 2,255,000 Orig Issue Discount/Premium: $ 95,857

LEASE #: Other PlanCon Projects Financed By This Issue/Note: n/a FY 2010-2011 Annual Rental or Debt Service: $

FY 2011-2012 Annual Rental or Debt Service: $

FY 2012-2013 Annual Rental or Debt Service: $

FY 2013-2014 Annual Rental or Debt Service: $

FY 2014-2015 Annual Rental or Debt Service: $ 11,463 FY 2015-2016 Annual Rental or Debt Service: $ 67,650 FY 2016-2017 Annual Rental or Debt Service: $ 67,650

Financing Method #2:G.O. Bonds Series of 2015 Year Issued: 2015Total Issue/Note: $ 9,660,000 Orig Issue Discount/Premium: $ 95,235

LEASE #: Other PlanCon Projects Financed By This Issue/Note: n/a FY 2010-2011 Annual Rental or Debt Service: $

FY 2011-2012 Annual Rental or Debt Service: $

FY 2012-2013 Annual Rental or Debt Service: $

FY 2013-2014 Annual Rental or Debt Service: $

FY 2014-2015 Annual Rental or Debt Service: $

FY 2015-2016 Annual Rental or Debt Service: $ 53,349 FY 2016-2017 Annual Rental or Debt Service: $ 290,993

Financing Method #3:G.O. Bonds Series of 2016 Year Issued: 2016Total Issue/Note: $ 16,345,000 Orig Issue Discount/Premium: $ 33,099

LEASE #: Other PlanCon Projects Financed By This Issue/Note: n/a FY 2010-2011 Annual Rental or Debt Service: $

FY 2011-2012 Annual Rental or Debt Service: $

FY 2012-2013 Annual Rental or Debt Service: $

FY 2013-2014 Annual Rental or Debt Service: $

FY 2014-2015 Annual Rental or Debt Service: $

FY 2015-2016 Annual Rental or Debt Service: $

FY 2016-2017 Annual Rental or Debt Service: $ 62,682

REVISED September 13, 2013 FORM EXPIRES 6-30-15 PLANCON-G10

(PDE USE ONLY)

(PDE USE ONLY)

(PDE USE ONLY)

Page 47: €¦ · 28/07/2016  · X G04(a)-G04(b) Detailed Costs X G05-G07 Total Contract Awards X G08 Prime Contractor Certification X G09 20% Rule for Alteration Costs for Non-Vocational

ACT 34 OF 1973: SUBSTANTIAL ADDITION DETERMINATIONDistrict/CTC: Project Name: Project #:

New Hope Solebury School District High School / Middle School 3833

Act 34 of 1973 applies to all new school buildings, district adminis-

tration offices and substantial building additions. A building addition

is considered substantial when its planned architectural area divided by

the existing structure's architectural area is greater than 20%. If your

project includes an addition, use the following calculations to determine

the applicability of Act 34.

A. Architectural Area - Addition 23,285 sq. ft. Part F Approval Letter

B. Architectural Area - Existing Structure 219,415 sq. ft. Part F Approval Letter

C. Act 34 Percentage (A divided by B times 100) 10.61 %

(ROUND TO 2 DEC PL)

Act 34 of 1973 requires a public hearing and the distribution of specific

project information for school construction projects involving the con-

struction of a new building or a substantial addition to an existing

structure. If Act 34 hearing requirements apply to this project, the

following pages should be completed and submitted to the Pennsylvania

Department of Education.

FIRST HEARING (if applicable)

Date Advertised

Date Hearing Conducted

REVISED JULY 1, 2010 FORM EXPIRES 6-30-12 PLANCON-G11