COL Daniel L. Thomas / 301-677-4844 / [email protected] 20 Jul 09 UNCLASSIFIED Slide 1 of 34 Unchanged from initial assessment upon assuming command: Garrison doing excellent job delivering current, steady state services TODAY. Command and Organizational Assessment Customer Feedback: Units, Organizations and Individuals. BRAC in onTRAC Condition of underlying infrastructure support Posture to meet future requirements (Greatest Concern). Incremental growth (DISA/WTU/704 th /DINFOS). Updated Plans for future development (NSA/DINFOS). Infrastructure investment / upgrades need to catch up IC Commander’s Assessment Situation

27 07 09 BRAC Subcabinet Meeting Ft Meade Briefing

Embed Size (px)

DESCRIPTION

On 27 July 2009, the Maryland BRAC Subcabinet met on Fort Meade under the leadership of Lt. Governor Brown. After opening remarks by the Lt. Governor and a presentation by the Fort Meade Commander, Colonel Daniel Thomas, the Fort Meade Regional Growth Management Committee briefed the three regional areas of concern. · Fort Meade Commander Presentation (BRAC Subcabinet Meeting, FT Meade Briefing) · Transportation ( See BRAC Subcabinet Meeting Brief) · Work Force (See BRAC Subcabinet Meeting Brief, BRAC Subcabinet Briefing Notes on Work Force and BRAC Business Initiative (BBI) Information Paper · Emergency Management (See BRAC Subcabinet Meeting Brief) Formal presentations ended with the Honorable Craig A. Moe of the City of Laurel outlining the strong relationship that Laurel has had with Fort Meade and the dynamic future of his city. If you have any questions on this event, please contact Kent Menser at 410-313-6521 or [email protected]. Thanks, Theo

Citation preview

Page 1: 27 07 09 BRAC Subcabinet Meeting Ft Meade Briefing

COL Daniel L. Thomas / 301-677-4844 / [email protected] 20 Jul 09

UNCLASSIFIED

Slide 1 of 34

Unchanged from initial assessment upon assuming command:

• Garrison doing excellent job delivering current, steady state services TODAY.•Command and Organizational Assessment•Customer Feedback: Units, Organizations and Individuals.

• BRAC in on‐TRAC

•Condition of underlying infrastructure support

Posture to meet future requirements (Greatest Concern).• Incremental growth (DISA/WTU/704th/DINFOS).• Updated Plans for future development (NSA/DINFOS).• Infrastructure investment / upgrades need to catch up

IC

Commander’s Assessment Situation

Page 2: 27 07 09 BRAC Subcabinet Meeting Ft Meade Briefing

COL Daniel L. Thomas / 301-677-4844 / [email protected] 20 Jul 09

UNCLASSIFIED

Slide 2 of 34

BRAC Actions:

• Consolidation of Defense Information Systems Agency (4,272 personnel)•

Collocation of Defense/Military Adjudication Activities (10 organizations, 760 

personnel)•

Consolidation of Department of Defense media; Defense Media Activity (663 

personnel)

GDPR/AMF/Grow the Army CS/CSS:

• Activation of Asymmetric Warfare Group •

Defense Information School (DINFOS) growth (300 students projected to begin by 

2011)• 704th

MI Bde

growth (500 soldiers to begin by 2010).• New Expansion?  

Future Fort Meade Transformation

Page 3: 27 07 09 BRAC Subcabinet Meeting Ft Meade Briefing

COL Daniel L. Thomas / 301-677-4844 / [email protected] 20 Jul 09

UNCLASSIFIED

Future Fort Meade

BRAC construction

Transportation Infrastructure

Water / Wastewater

Electric Privatization

Golf Course Displacement / Replacement–

Golf Course Income

Warrior Transition Unit

New Gym–

Upgrade Current Gym

Youth Sports Complex

Hale Hall Replacement

Public Transportation

Barracks

Environment FAA–

Environment Execution

Enhanced Use Lease

AAFES Services

Jul 08 Jan 09 Aug 09

Page 4: 27 07 09 BRAC Subcabinet Meeting Ft Meade Briefing

COL Daniel L. Thomas / 301-677-4844 / [email protected] 20 Jul 09

UNCLASSIFIED

Slide 4 of 34

Graphic

• Upgrade 5 Access Control Points•Rockenbach ACP $7.1M•Mapes Rd East & ACP $5.5M•Mapes Rd West & ACP $5.8M•Reece Rd & ACP $4.8M•Llewellyn ACP $6.5M

•Reece & Mapes Roads - 4 Lanes•Mapes Rd East $1.4M•Mapes Rd West $2.8M•Reece Rd $2.5M•Cooper Ave Improvements (DISA)

•Improvements at 6 Intersections•Reece at Ernie Pyle $1.6M•Mapes at Ernie Pyle $1.4M, Cooper $1.2M & O’Brien $1.6M •Rockenbach at Cooper $1.4M & O’Brien $1.3M

Study Recommends-

DD Form 1391 for all projects have been submitted

Future Fort Meade Transportation Infrastructure

Page 5: 27 07 09 BRAC Subcabinet Meeting Ft Meade Briefing

COL Daniel L. Thomas / 301-677-4844 / [email protected] 20 Jul 09

UNCLASSIFIED

Slide 5 of 34

Background: Modernization of system needed.  Directed to privatize.  

Action:•

Contract in Source Selection at Defense Energy Support Center (DESC)•

Source Selection Authority briefed on evaluation team’s recommendations •

Contract award by 30 Sept. 2009•

Transition period of about six months after Contract Award Date

Assessment:•

Procurement is behind original schedule•

Negotiations have taken a longer period than planned•

Award in FY 2009 is still expected to take place

Future Fort Meade Water/Wastewater Privatization

Page 6: 27 07 09 BRAC Subcabinet Meeting Ft Meade Briefing

COL Daniel L. Thomas / 301-677-4844 / [email protected] 20 Jul 09

UNCLASSIFIED

Slide 6 of 34

DPW

• Background: Modernization of systems needed.  Directed to privatize.

• Action:•Entire replacement of distribution systems started 2003•Scheduled completion of installation December 2012•Design started for distribution systems in renovated housing areas•40% building services installed and fully metered•55% of primary electric feeder lines and Gas mains installed•Site allocated for new BGE substation which is under design•Temporary Modular substation installed until new Rock Avenue Substation comes 

online in 2011

• Assessment:•Progressing well

Future Fort Meade Gas and Electric Privatization

Page 7: 27 07 09 BRAC Subcabinet Meeting Ft Meade Briefing

COL Daniel L. Thomas / 301-677-4844 / [email protected] 20 Jul 09

UNCLASSIFIED

Slide 7 of 34

• Background:•

BRAC construction consumed 9 of 36 holes.•

Operational expansion anticipated to consume 

remainder.  •

Timeline unknown. •

Anticipated replacement cost $36M.•

Have obtained consensus with Op Cmd

and IMCOM 

Cmd

on replacement strategy:•

Army has BRAC obligation to replace.•

Op requirement will provide in‐kind 

replacement funding

• Action:•

DD 1391 is signed and project is in PAX system.•

Received funding approval from FMWRC for 

feasibility study, summer 09.•

Design funding requested at NER Construction 

Conference ‐

$2.9M.•

Project validation funded by IMCOM and completed.  

Expect favorable report.

Assessment: Continued nesting and 

transparency critical

ACTIONS / RECOMMENDATIONS:•

Complete as many interim steps as 

possible to enable rapid construction 

when funded.

NSANSA

Future Fort Meade Project Descriptions/New Golf Course

Page 8: 27 07 09 BRAC Subcabinet Meeting Ft Meade Briefing

COL Daniel L. Thomas / 301-677-4844 / [email protected] 20 Jul 09

UNCLASSIFIED

Slide 8 of 34

Background: Degradation of services offered due to 

BRAC construction resulted in financial loss.

FY08 ‐$159K

FY09 projected ‐$367K

Implementing FMWRC Approved PIP

NERO FM provided Technical Assistance Visit 

in late April

Action: Increasing Revenue by revising Menu Pricing 

and Target Marketing

Decreasing Cost though Business Based  

Personnel Actions & Labor  Management

Decrease retail inventory in pro shop

Curtail offerings and reduce operating hours 

in winter Reduce Snack Bar Hours

• Assessment: 

May need to resurrect driving range.• May require elimination of Executive 9.

Completion on DISA will partially restore 

Club House as entertainment venue. 

ACTIONS / RECOMMENDATIONS:•Monitor improvements, reassess in Fall.

Golf Course – NIBD

-500

0

500

1000

FY98 FY99 FY00 FY01 FY02 FY03 FY04 FY05 FY06 FY07 FY08 FY09

Thou

sand

s of $’s

Page 9: 27 07 09 BRAC Subcabinet Meeting Ft Meade Briefing

COL Daniel L. Thomas / 301-677-4844 / [email protected] 20 Jul 09

UNCLASSIFIED

Slide 9 of 34

Background: •

Youth sports fields are deteriorating•

State of the art MCA Project approved and 

funded at $2.65M in 1999

Broke ground in 2000 and completed 2 

fields

All funding diverted after 9/11

Action:•

ACOE/SRM ($1.8M) allocated in FY09 will 

partially fund project; must be obligated 

this fiscal year 

DPW/DOC seeking contractor•

Work projected to begin FY10

Assessment:•

Still need approximately  $500K for full 

project completion 

ACTIONS / RECOMMENDATIONS:• Developing time line for construction  • Will re‐locate sports program during construction  • Will look to ACOE or SRM for remainder of funds

Future Fort Meade Project Descriptions/Youth Sports Fields

Page 10: 27 07 09 BRAC Subcabinet Meeting Ft Meade Briefing

COL Daniel L. Thomas / 301-677-4844 / [email protected] 20 Jul 09

UNCLASSIFIED

Slide 10 of 34

FGGM has been working with AAFES 

encouraging much needed infrastructure 

upgrades.

Plans feature a larger Main Store, 

consolidate the PXtra

and Military Clothing 

Sales Store with the PX, and expand the Food 

Court and Concession Mall, and a new 

shoppette.

The Army & Air Force Exchange Service 

(AAFES) reviewed options for new Main PX at 

multiple sites.

AAFES will seek board approval for a new 

Shoppette

for FGGM February 2010, and for a 

new PX in 2011.  Anticipated construction 

mid‐2011 and 2012, respectively.   

ACTIONS / RECOMMENDATIONS: •

Continue to monitor process to ensure 

cradle to grave completion.

Future Fort Meade Project Descriptions/AAFES

Page 11: 27 07 09 BRAC Subcabinet Meeting Ft Meade Briefing

COL Daniel L. Thomas / 301-677-4844 / [email protected] 20 Jul 09

UNCLASSIFIED

Slide 11 of 34

• Background:

Master Plan requires updating•

Current plan developed in July 

2004

• Action:

New contract awarded by IMCOM

Kick‐off meeting held 11‐12 February 

2009.

Currently gathering and verifying data•

Conducting interviews, on‐site 

visits.

35% submission under review  

Final submission:  June 2010

• Assessment: On schedule

Future Fort Meade Master Plan

Page 12: 27 07 09 BRAC Subcabinet Meeting Ft Meade Briefing

COL Daniel L. Thomas / 301-677-4844 / [email protected] 20 Jul 09

UNCLASSIFIED

Slide 12 of 34

100_0075.JPG (2 MB)

Future Fort Meade Warrior Transition Unit Infrastructure Support

• Background:  

Installation postured for temporary WT population of 

appx. 50 by leveraging ACS services and facilities, 

admin space and barracks.

Population has increased to +160 and projected to 

climb to 150‐200+.

Overstraining facilities and compromising both WT 

and regular mission.

SFAC Not Providing IMCOM Mandated Level of 

Services.

Unit has outgrown available cadre admin space

WT occupancy currently fills 144 spaces in PP 

Barracks 

• Action:

Submitted a request for construction of temporary 

Admin and SFAC facilities.

IMCOM approved $1.5 million for construction of 

two temp modular facilities for Admin and SFAC   

Assessment: Temporary facilities will allow provision of support 

during interim period.

• Recommendation: 

Resolve Fort Meade's “pending”

status to allow 

permanent infrastructure resourcing to begin, if 

necessary.

Page 13: 27 07 09 BRAC Subcabinet Meeting Ft Meade Briefing

COL Daniel L. Thomas / 301-677-4844 / [email protected] 20 Jul 09

UNCLASSIFIED

Slide 13 of 34

DPW

1.

DISA (under construction);  ECC: $442M; 

ECD:  February 2011

2.

Defense Media Center (under 

construction); ECC: $56M; ECD: May 2011

3.

Adjudication Center (under construction); 

ECC: $32M; ECD:  March 2011

4.

902nd HQ (under construction); ECC:  

$31M; ECD: April 2010

5.

TBUP Barrack 8478 & 8479 (under 

renovation); ECC: $22M; ECD: April 2010TBUP Barrack 8606 (RFP under 

development) ECC: $13M; ECD: TBD 

6.    VA Clinic; ECC: $6M; ECD: TBD

7.    SATCOM: ECC $26M (under design); ECD 

TBD

ACTIONS / RECOMMENDATIONS:  Monitor 

and facilitate progress to project 

completion.

1

2 34

5

6

7

Future Fort Meade MILCON ‐

Approved

Page 14: 27 07 09 BRAC Subcabinet Meeting Ft Meade Briefing

COL Daniel L. Thomas / 301-677-4844 / [email protected] 20 Jul 09

UNCLASSIFIED

Slide 14 of 34

DPW

ACTIONS / RECOMMENDATIONS:  

Pursue obtaining approval and funding.

AWG Complex

FY11

$42M•

Fitness Center            

FY13

$19M•

DINFOS

FY12

$35M

Nathan Hale Hall   

TBD    

$20M•

3 TBUP  Barracks 

TBD    

$45M•

3 CDC’s                

TBD   

$23M•

Chapel                  

TBD    

$9M•

WTU Complex      

TBD     

$45M

Congressional Add‐ons – FY10•

AIT Barracks,                  

$73M•

Whole Barracks              

$30M

Future Fort Meade MILCON ‐

Requested

Page 15: 27 07 09 BRAC Subcabinet Meeting Ft Meade Briefing

COL Daniel L. Thomas / 301-677-4844 / [email protected] 20 Jul 09

UNCLASSIFIED

Slide 15 of 34

DISA: 

• Program Amount/CWE: $441.7M/$441.7M• Site work began on 15 July 08• Outfitting will begin May 2010•

Relocations will commence October 2010, with 

completion July 2011. •

DISA is uncertain how many DISA employees 

will relocate to Fort Meade. •Child care and transportation capabilities at 

FGGM key to employee retention.• Overall project more than 35% complete•

No delays in construction schedule are 

anticipated. Working with DISA to address their 

concerns/issues. 

ACTIONS / RECOMMENDATIONS: •Re‐assessing capabilities to provide adequate 

childcare, physical fitness and barracks as a result 

of future growth. •Developing transportation/traffic alternatives 

for workforce travel. 

Future Fort Meade BRAC/Defense Information Systems Agency

Page 16: 27 07 09 BRAC Subcabinet Meeting Ft Meade Briefing

COL Daniel L. Thomas / 301-677-4844 / [email protected] 20 Jul 09

UNCLASSIFIED

Slide 16 of 34

PAIO

ACTIONS / RECOMMENDATIONS: •NA 

DMA: 

• Program Amount/CWE: $82M/$61M• Construction contract awarded 13 March 2009.• Construction  began April 2009. •

Contract Duration: 780 calendar days (26 

months). • Construction completed by Summer 2011• Beneficial Occupancy Date: Summer 2011•

No delays in construction schedule are 

anticipated. Working with DMA to address their 

concerns/issues. 

Future Fort Meade BRAC/Defense Media Activity

Page 17: 27 07 09 BRAC Subcabinet Meeting Ft Meade Briefing

COL Daniel L. Thomas / 301-677-4844 / [email protected] 20 Jul 09

UNCLASSIFIED

Slide 17 of 34

ACTIONS / RECOMMENDATIONS: •N/A 

DAJ:

• Program Amount/CWE: $51M/$35.8M• Construction Contract awarded 20 Feb 2009•

The duration of the contract is 730 calendar 

days (24 months)• Construction began in April 2009• Construction is to be completed by Spring 2011•

No delays in construction schedule are 

anticipated. 

Future Fort Meade BRAC/Defense Adjudications Activities

Page 18: 27 07 09 BRAC Subcabinet Meeting Ft Meade Briefing

COL Daniel L. Thomas / 301-677-4844 / [email protected] 20 Jul 09

UNCLASSIFIED

Slide 18 of 34

Background: Negotiations continue regarding 

enhanced use lease (EUL) project located along 

Reece Road.

Uses non‐excess property to leverage support 

for installation mission requirements.•

Return of “in‐kind”

services to construct new 

facilities, improve and maintain aging facilities, 

and enhance quality of life programs/facilities

•Refining the Master Agreement to Lease and a 

Single Site Lease

Project continues to move forward with focus 

on determining utilities requirements at EUL 

site and completing the Report of Availability

Site Z = 53 acres

Site Y = 107 acres

Site Z = 53 acres

Future Fort Meade Enhanced Use Lease