24692478 Education Mine Planning and Automation Docs48

Embed Size (px)

Citation preview

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    1/54

    Mine

    Planning

    Unit 12

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    2/54

    In this unit, you will learn about minelayout and mine planning.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    3/54

    After completing this unit, you should be able to:

    Explain the role of mine planning

    Explain mine planning process

    List some of the concerns of U/G planning

    Explain the factors of layout design

    Explain some of the strategies for U/G layout

    Explain the parts of a typical mine

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    4/54

    Mine Planning

    The classic procedure fordesigning a mine starts bydetermining the mining method(s)and probable optimum mining

    rate .

    This unit is principally devoted tothe next step determining initialmine layout or"conceptual minedesign." The procedure is alsoconsidered initial mine planning.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    5/54

    Mine Layout - Surface

    If the mining method is open pit,the layoutstarts with the basicdesignof the open pit itself. Thisincludes pit layouts in intervals

    up to the final design (ultimatepit). With the pit established, theinfrastructure is planned,including surface haul roads,stockpiles, dumps, tailings

    impoundment, utility corridors,and surface plant layout.

    The mine layout for an open

    pit mine might have to bemodified if undergroundmining is contemplated

    when the pit is exhausted.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    6/54

    Mine Layout - Underground

    If the plan includes undergroundmining, planningstarts with locatingand sizing pre-production and on-going development requirements. Theinitial planning includes determining

    level intervals, haulage ways, primaryaccess (shaft, ramp or adit), and othermajor entries. The design of majorentries requires considering therequirements for ore handling, wasterock handling, primary ventilation

    circuit, backfill, transfer, materialshandling, access for personnel, refuge

    stations, and escape route(s).

    Once the underground mineconcept is established, thesurface infrastructure isdesigned, including access

    roads, dumps, tailingsimpoundment, utility corridors,maintenance facilities,explosives storage, and surfaceplant layout.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    7/54

    Underground Mine Planning

    The planning process will, ingeneral move through four steps,irrespective of the design phase:

    baseline assessment,

    reserve determination,

    premine planning and

    subsystem design.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    8/54

    Phase I - BASELINE ASSESSMENT

    Baseline assessment of allavailable data precedes anyplanning efforts. It is acomprehensive initial review of allavailable information on thepotential reserve or mine fromgeographic, geologic,environmental, technical, andeconomic standpoints.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    9/54

    1) Baseline Assessment Geologic Factors

    Thegeologic modelis only an interpretation of the actualconditions based on the skill of geologists and the economic

    backing available to do thorough testing . Constant testing anddrilling is done as the project moves through the design phases.The data collected dictates the changes that effect the geologicmodel.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    10/54

    2) Baseline Assessment -Environmental Factors

    Today designing a mine

    requires planning forenvironmental protection andreclamationfrom the verybeginning.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    11/54

    RESERVE DETERMINATION

    The characteristics of a reserve are as crucial as the reservemagnitude or grade: the depth, inclination, geometry, type andproperties of host and deposit rocks, quality, and etc.play a keyrolein the design.

    Criteria

    A mineral deposit or resource can only be classified as an orebody only when it can bemined at a profit.The planning anddesign attempts to identify the method to make this possible.

    Demand of the ore body and mining technology can affect thefuture of a project.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    12/54

    PREMISE PLANNING

    The mine plan constantlyevolvesas the mine process changesphysical characteristics. Engineering science and technology are

    constantly evolving while the mine is locked into the physicalframework.

    An interesting fact is that equipment changes with time but the basicdesign of the mine remains the same. This is most obvious incomparing existing and newer mines.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    13/54

    Following is a list of concerns for underground mining:

    1) Regulatory and Legal Factors

    Permits and approvalsmay be at the federal, state, local, or regional. Theseare subject to continual revision or reinterpretation requiring ongoingreview of the mine plan.

    Compliance plans include:

    1) mine layout with projections 5) dust control plan

    2) strata/roof control plan 6) medical / emergency evacuation plan

    3) ventilation plan 7) fire control/mine evacuation plan

    4) fan stoppage plan 8) escapee map/plan.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    14/54

    2) Geologic/ Geotechnical Factors

    Depending on the mining methods under consideration, manygeologic and geotechnical factors must be considered. Theeconomics usually favor extraction of the best grade materials orthe lowest mining cost areas tomaximizethe return on investmentsand shorten payback period.

    While the immediate extraction of the best grade materialsenhances immediate finances it can compromise designs.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    15/54

    3) Environmental Factors

    Theimpact on the environmentmust be considered fromthe beginning of the plan design. The impacts to theenvironments can include; noise, aesthetics, air quality,water discharge and run off. The environment must remainwithin regulation during the initial data gathering to the

    reclamation process.

    Reclamation plansinclude; drainage control, segregationof waste material, erosion and sediment control, solidwaste disposal, regrading and restoration of waste andmine areas. The plan must include theeffectsof the minesubsidence, vibration ( induced by transportation, mining,processing or subsidence) and impact on surface water.The environmental items often dictatethe economics andviabilityof the mine.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    16/54

    4) Technical Factors

    Thetechnical areas of the planis the most extensive. It takes inconsideration the regulations, geologic, and and environmentalfactors to develop each part of the plan.

    The layout of the mineis determined bythe size and shape of thereserve. After the ore deposit is mapped, access development for thereserve area is figured into the plan. The size of the reserves

    determines the kinds of access and the number of access portalsneeded. Access can be vertical shafts, inclined slopes, and drifts orhorizontal entries.

    The larger the reserve, themore complicatedthe plan becomes.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    17/54

    Surface FacilitiesTheproductivity and the reserve

    sizedetermine the size andplacement of facilities.Consideration must be made for

    access, extraction, removal, andstorage of the ore, the physicalneeds of the work force, and theoperational needs of the facility.

    Land acquisition for disposal areas,

    dust, noise, safety, and layout areother design considerations.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    18/54

    Introduction to Mine Engineering

    Physical FactorsGeological mapping is used to determine the reserve depth and

    develop the best mine layout. The plan lays out the number ofbenches and designates the portion of the reserve that will bestmeet the needs of the market.Economicsdrive the design to gain

    the most profit from the mine while still maintaining plans forreclamation.

    The sequence of the extractioncan be important to maximize thereserve recovery. The mine may have multiple seams beingextracted at once or only a single vein. The plan will take this into

    consideration and plan for the most efficient method of recovery.Poor mining conditions must be factored into the analysis toaccount for changes in productivity rates and mine costs.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    19/54

    Equipment

    The equipment needed is determined bythe dimensions and the hardness of the

    mineral deposit. Other factors that needto be considered are production rates,seam or working height, and property

    extent. Ventilation, size constraints,regulations, and floor pressures mayimpact the choice of diesel-or electric-powered equipment.

    Schedules for equipment overhaul

    should be developed to assureproductivity rates. New equipmentpurchase should consider theincorporation of new technology as itbecomes available.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    20/54

    Support Systems/ Infrastructure

    As the development of the mineprogresses the mine entries, drifts,and levels become part of theinfrastructure. All parts of the systemmust be evaluated for capacity andavailability . The systems are built in a

    series so that if one of the systemsfails the whole system is halted untilsystems are corrected. A seriessystem design is usually used to keepcosts low as many systems are

    parallel or redundant. They aredesigned to be as maintenance freeas possible.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    21/54

    Transportation

    Transportation encompassesprovisions for the movement ofmaterials, personnel andequipment into and out of themine. Supplies, workers,equipment must betransportedin a timely mannerto maintainthe planned production. One ofthe main transportation plansinclude moving the minedmaterial from the face to the

    processing facility. A successfulmine design will havea smoothtransportation flow.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    22/54

    Manpower

    Staffing of the system is afunction of the required productionlevel. Typically the manpower level is inversely related to therelative level of capital spending but related to the reserve size.Adequate personnel must be provided to allow the system tofunction properly. Personnel includes the supervisory work

    force as well.

    Consideration must be made forsupport stafflevels such asadministration, engineering, financial staff. The centralization ofthe the support personnel may be more effective if centrallylocated depending on particular circumstances. The physical

    location of the mine must be considered also.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    23/54

    Ventilation

    After most of the other factors are

    laid out the ventilation is designedtoprovide the mine's life supportsystem. The first consideration isproviding clean respirable air tothe workers. The dilution ofcontaminants is next. In othercases air can used to cool also.

    Mine layout is dramaticallyimpacted by the ventilationsystem. Proper airflow requires

    proper sizing , location andnumbers of airways. Minimum andmaximum velocities, andquantities are often specified byregulations and mine condition.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    24/54

    5) Mine Closing and Reclamation

    After the deposit has been completely mined, the mine area must becleaned up andreturned to approximately it original condition.

    Permits require bonds to be set for protection against notcompleting this reclamation. Funds are allocated to cover thisprocess from the onset of the mine. Many of the reclamationprocess begin with the first breaking of the ground. Openings aresealed, pits filled and revegetated, and the structures removed.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    25/54

    Mine Plant Layout

    Mine planning is a general term for describing theprocess ofconfiguringa complex and often expensive portion of anunderground mine.

    This encompasses the placement of all development facilities suchas buildings and structures, machinery, pipelines, power lines,equipment, cables ponds, roads, rails and other auxiliary worksneeded to support any underground mine activities.

    Mine layout is the design for integrating all structures, systems or

    activities,required to support the mine for economic gain.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    26/54

    Mine plant layout is divided into three major

    subcategories:

    surface,

    shaft and

    underground plant.

    The surface plant commenced at the entrance tothe property to the mine opening site.This isgenerally seen in the form of roads, fencing,drainage, and runoff ditches, lighting / power lines,and other items needed to provide the site with

    materials and services.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    27/54

    The shaft plant subcategory begins at theshaft of the collar and consists of the

    airways and pumps, piping, watercollection structures, communication andpower lines, transportation systems andthe components between the surface andthe underground workings.

    This is generally seen in the form ofroads, fencing, drainage, and runoffditches, lighting/power lines, and otheritems needed to provide the site withmaterials and services. The shaft plant

    layout encompasses all of the equipment,buildings, yards and controlsneeded toservice the mine.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    28/54

    The underground mineplant would include , butnot be limited to,ventilation, drainage,transportation, supply

    and materials handling,mine power andcommunications.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    29/54

    There is a difference between designing theplants for large and small mines. The three basic

    parameters are :durationof the underground facility,

    the profit expectedfrom the mine,and

    the needsof the mine for auxiliaryservices.

    As a rule of thumb, the mines with a life longerthan ten years need a more detailed plan andthorough mine plant engineering. Smaller mines

    that have a life of 3-5 years need a portablesurface plant, little or no shaft plant, and a verybasic underground plant layout.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    30/54

    Strategy for Underground Mines

    Ramp Haulage

    For small ore bodies, ramp haulage is thedefault selectionbecause itnormally provides the most flexible and economical choice.

    A ramp (or adit) drive can typically be oriented to provide an underground

    diamond-drilling base and provide shorter crosscuts to the ore zone. Thecrosscuts are provided rapidly and economically because they provide asecond heading for the main drive. It is possible to sink and develop from ashaft at the same time; however, this is a difficult and expensive procedure.

    Another advantage to the ramp or adit entry isdirect accessby mobileequipment when trackless mining is to be employed. For a typical shaft, theequipment must be dismantled and reassembled underground. The set-uptime required to initiate ramp driving is usually shorter than for a shaft.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    31/54

    One to three monthsmay be

    required to provide access andcollar a ramp portal, while the collar,

    hoist, and headframe required for ashaft may takesix monthsof sitework.

    For medium sized ore bodies, ramphaulage may still be the best choicewhere the ore body is relatively flatlying. In this case, the ramp mayhave to be enlarged to

    accommodate larger trucks. Insome cases, it may be practical toprovide twin ramp entries to handletwo-way traffic.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    32/54

    Belt Conveyor

    Forlarge flat-lying ore bodies, a beltconveyor is typically the most economicalmethod of hoisting ore. The legs of theconveyor are put into a ramp that has beendriven straight (i.e. a "decline") for each legof the proposed conveyor way.

    Shaft System

    Forlarge steeply dipping ore bodies, a shaftsystem is usually best. In this scenario, itmay be advisable to have a ramp entry aswell to accelerate the pre-production

    schedule and later to provide service accessto the mine.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    33/54

    Main Entry

    The foregoing strategy determines a main entry to the

    underground on thebasis of ore transport. In manycases, this entry also serves for personnel andmaterials transfer, particularly at small operations.

    Consideration should be given to a separate entry forman and materials handling when it can be afforded.

    For example, some mines use the production shaft forore/waste hoisting, main exhaust, and alternate escapewhile a second shaft provides cage service in the mainfresh air entry. If a shaft system is employed at anoperation of substantial capacity, it is not uncommonto find a ramp access from surface as a third entry.

    This is a logical progression when an internal rampsystem is required by the mining method to beemployed.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    34/54

    Parts of a Mine

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    35/54

    Headframe

    The headframe isthe top of themine. A hoistmotor is used toconvey men andmaterials into themine.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    36/54

    Introduction to Mine Engineering

    Ventilation Shaft

    Vertical tunnels/shafts connectthe ends of each level and

    carry fresh air into mine fromsurface. Fumes, gases, andheat are replaced by cool cleanair. In winter, the fresh air isheated to maintain an even

    year-around temperature.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    37/54

    SkipSkips are used to hoist brokenrock/ore to surface. Many metalmines use the overturning typeof skip. Curved guides in the

    headframe turn the skips overuntil the ore runs out into a binon surface. Skips are loaded at aloading pocket at the bottom ofthe main orepass.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    38/54

    CageThe Cage is a compartmentwhich is used to hoist menand material into the mine.

    The cage is built into the

    main shaft.

    A Cage can hold up to 30men and handle very heavy

    equipment.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    39/54

    Pumps

    Most mines require a de-watering system for theremoval of underground water.The water comes from naturalsources and the types of

    mining methods employed, ie.cut and fill. Usually a series ofpumping stations are requiredto lift the water out of the minein stages.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    40/54

    Sump

    Sumps are commonly installedin mines to settle out anysuspended particles in the minewater. A Sump is an

    underground pond where thesuspended material can settleout. Sumps are often used inconnection with a pumping plantso that the larger solid particles

    will not enter the pump.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    41/54

    Drift

    Levels and drifts arehorizontal tunnelsdriven the length oforebody. They arespaced at equal

    intervals down theshaft usually every 70to 100 meters. Driftsare used to tram oreand move materials

    within the mine.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    42/54

    Stope

    Stopes are the workingareas of a mine. Here theore is drilled and blasted

    by the miners. Ore isremoved from thestopes thru chutes tothe level below.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    43/54

    Chute

    An opening in theground, through whichore can pass from one

    level to another. It isalso the structure builtto load cars from astope or ore-pass.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    44/54

    Raise

    A raise is a verticalconnection between levels orinto stopes. A raise can madeof timber or steel culverts.

    Often a ladder system isinstalled to permit passage ofminers or a slide system isused to move heavyequipment into a stope.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    45/54

    Parts of a Mine

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    46/54

    Shaft

    This is the mainentrance to the minefor men and supplies.

    the shaft is dividedinto two parts, a cage(for men) and a skipfor ore. Shafts can bevertical or inclined.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    47/54

    Charging Station

    An area on the levelwhere all battery-powered equipment

    is re-charged forcontinuous use.Most trains that haulore on the level usebatteries.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    48/54

    Lunchroom

    A small isolated driftwhich has a stove,

    tables, andwashbasins.

    Also called a refugestation.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    49/54

    Warehouse

    An underground area where spare equipmentand parts are stored for the stopes. Stored

    materials include oil, drills, screen, bolts andvarious equipment items.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    50/54

    Washroom

    An underground washroom is commonly calleda GESTER. A typical gester consists of a

    modified rail car that uses chemicals, air, andwater to breakdown waste materials.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    51/54

    Ore Pass

    The ore is moved alongthe level by trains to acentral ore pass system.

    The ore falls downward toa crusher below. Here it isloaded in a skip andhoisted to surface.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    52/54

    Fuse Magazine

    Fuses and detonator capsare stored separately fromexplosives for safety

    purposes. The detonator capis ignited either by electricalmeans or by a slow burningtape fuse. The cap in turncauses the explosive to

    detonate.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    53/54

    Powder Magazine

    The powder magazine is astorage area where theexplosive agent is stored

    separate from fuses anddetonators for safetypurposes. Amex, Cilgel, andother hi-explosive are usedto break and shatter rock/ore

    in the extraction process.

  • 8/3/2019 24692478 Education Mine Planning and Automation Docs48

    54/54

    You have reached the end of Unit 12.