21_LessonsLearned,PlanningDesConstr

Embed Size (px)

Citation preview

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    1/43

    Lessons Learned Planning, Design andConstruction of Honolulus SewerRehabilitation Projects

    Stuart Ujimori, P.E.

    Roy Abe, P.E. Mike Young, P.E. C&C of Honolulu Dept.

    HDR|Hawaii Pacific Engineers Bowers + Kubota Design & Construction

    HWEA 32nd Annual ConferenceMarch 17, 2010

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    2/43

    Presentation Objectives

    Learn from past projects to:

    Expedite projects Minimize costs

    Avoid problems and change orders

    Make Life Easier for Everyone!

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    3/43

    Challenges in Rehabilitating

    Honolulus Sewer System

    Narrow/congested roads with lots of utilities

    Substandard 6-inch sewers

    Old brittle terra-cotta sewers

    Sags and damaged sewers due to poor soils

    Many sewers in groundwater

    1,800 miles of sewer lines!

    Many Sewer Rehabilitation Challenges!

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    4/43

    6-inch Lines in Kalihi-Nuuanu

    50% are 6-inch lines!

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    5/43

    Terra Cotta Lines in Kalihi-Nuuanu

    65% are Terra Cotta sewers!

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    6/43

    Lessons Learned in Project Planning

    Analyzing flows and pipe capacities

    Evaluating pipe condition and problems

    Dealing with 6 terra cotta lines

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    7/43

    1. Analyze Flows and Pipe Capacities Carefully

    Calibrate computer models with actual field data

    Sewer lines are not always clean

    Wet weather flow data may reflect exfiltration in

    leaky surcharged lines (rehabilitation reducesexfiltration, which then increases flow)

    Check flow splits at manholes flow model may

    be inaccurate Infiltration and inflow can be concentrated in one

    area do supplemental investigations

    Try to avoid unnecessary upgrade work

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    8/43

    Avoiding the $40 million Relief Sewer on the

    Kalanianaole Highway Trunk Sewer Project

    Upgrade

    Kahala WWPS

    Clean Trunk

    Sewer

    Clean Inverted

    Siphon

    Stop 1 mgd of

    Infiltration!

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    9/43

    2. Determine What are the

    Causes of the Problems

    Find the big concentrated I/I sources

    Check for problems outside the project area

    Look for downstream sags anddefects that back up flow

    Spend extra time to clean off the old hardgrease

    Turn the 5-inch grease coated pipeback into an 8-inch pipe!

    Fix the Easy to Fix big problems.

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    10/43

    Solving the Kapiolani Grease Problem

    Partially CollapsedPipe Blocking Flow

    Upstream Lines with

    Heavy Grease

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    11/43

    3. Replacing All the 6 Terra Cotta

    Lines is Too Costly

    Challenges with 6 lines:

    Difficult to CCTV and rehab with CIPP if have morethan 0.5 offset joint

    Often in backyard easements and narrowcongested streets

    Consider rehabilitating with Cured-in-Place Pipe(CIPP) if:

    Slope is good (generally not much problems ifgreater than 1 percent)

    Limited spot repairs required (generally not more

    than three)

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    12/43

    Lessons Learned in Sewer Design

    Alignment for new sewers

    Rehabilitating cast iron sewers

    Conflicts with existing utilities

    Improving CIPP quality

    Working hours Meeting deadlines

    Obtaining good bids

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    13/43

    4. Consider Reconstructing

    Smaller Lines in the Same Location

    Advantages

    Less utility conflicts and unknowns

    Less excavation risks (such as rock) Fewer new manholes

    Disadvantages

    Need extensive flow bypass (but contractors dofigure out a way to do it!)

    Expect the Unexpected in the older areas

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    14/43

    Utility Poles are a Pain!

    Add photo

    Sewer Line Under

    Utility Poles!

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    15/43

    5. Corroded Cast Iron Sewers

    Can be Rehabilitated with CIPP

    Requires removal of corrosion

    Chain flail tool works well

    Pipe diameter wont be fully restored CIPP surface wont be smooth (but still good

    enough)

    Need to manage risk of collapse

    Monitor cleaning with CCTV watch forexcessive infiltration

    Be ready for emergency repairs!

    (bypass and spot repair)

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    16/43

    Removing Corrosion on a Cast Iron Sewer

    on Ala Moana Boulevard

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    17/43

    6. Try Really Hard to Obtain Timely Approvals

    (Easier said than done!)

    Work closely with utility and other approving

    agencies

    Understand their concerns Be responsive to their comments

    Gain their trust

    Consider special design to get over hurdles

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    18/43

    Special Reinforced Concrete Jacket Detail

    for Water Crossing due to Inadequate Clearance

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    19/43

    7. Improving Cured-in-Place Pipe (CIPP)

    Rehabilitation

    Dont require CIPP liners to be thicker thannecessary

    Adds unnecessary cost

    More wrinkles and more difficult to install Check initial work to catch problems early

    Check work crew qualifications (new workers)

    Seal annular space between liner and host pipe(stop migration of roots and infiltration)

    Fix heavy infiltration to ensure resin will reach

    curing temperature

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    20/43

    8. Seek Extended Working Hours

    Consider night work to help businesses

    and traffic

    Allow extended hours in residential areas Do traffic studies to justify extended hours

    For Kalanianaole Highway trunk sewer project,

    DOT allowed different hours for east bound andwestbound traffic and weekends.

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    21/43

    9. Do Things to Help Meet Deadlines

    Start design earlier Negotiate design work early.

    Put some pressure on reviewing agencies but be

    nice to them! Focus on getting the traffic control plans approved

    Dont forget DCABs approval

    Check and obtain required easements

    Prepare archaeological monitoring plans ifnecessary

    Dont forget the NPDES Construction Activity permit(if more than one acre)

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    22/43

    10. Getting Better Bids

    Avoid year-end avalanche of projects being bid out

    Break large projects into smaller ones

    Many small contractors are competitive, hungry and

    competent $4 to $8 million per project seems to be a good range

    Consider separating out easier open trench work fromspecialty work (microtunneling and work in groundwater)

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    23/43

    Lessons Learned Construction ofHonolulus Sewer Rehabilitation Projectsfocused on Kalihi-Nuuanu Sewer Rehabilitation Project

    HWEA 32nd Annual ConferenceMarch 17, 2010

    Mike Young, P. E.

    Bowers + Kubota Consulting

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    24/43

    Too Many Aloha Shirts & Hard Hats

    Standing Around!

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    25/43

    Presentation Outline

    1. Description of the Kalihi-Nuuanu Sewer RehabilitationProject

    2. The Lessons Learned = The challenges and issuesencountered during construction are what teach thelessonso Hope that the designers can consider these lessons to improve

    future designs

    o Help other CMs to effectively deal with these challenges andissues if or when encountered

    3. Ideas to consider for making Open Cut Trench Work Easierin the Future

    What are you talking about?!?

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    26/43

    1. Kalihi-Nuuanu Sewer Rehabilitation Project

    About Project (Short Description):

    Approximately 19,500 linear feet (3.7 miles) of sewer lines, ranging

    from 6 to 12 inches in diameter were installed or replaced via

    open-cut trenching throughout the Lower Nuuanu and Kalihi Areas

    9 separate phases/contracts with six different contractors awarded

    contracts

    Total Contracted Construction Amount is approximately $51

    Million

    Currently 6 of the 9 phases are substantially complete or being

    closed out (about 80% of the overall work complete)

    Wow, thats a lot of sewer pipe!

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    27/43

    2. Lessons Learned

    Challenges and Issues Encountered

    Utility Locate and Record Drawing informationsometimes incorrect or records not available This can create costly bids and dangerous situations in the field

    Do the research and go through the proper utility reviews Include Descriptions of Critical Underground System information on the

    plans

    Verify that Contractor Calls for Utility Locates and for a Utility Inspectoras Required

    Contractor can appropriately prepare for encountering the utility Contractor can be held responsible for damage to the utility

    Digging in the Dark!

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    28/43

    Utility Locate and Record Drawing information

    sometimes incorrect or records not available

    Contractors hoe-ram penetrated *Major UndergroundUtility System not located per record drawings

    *Specialized System causing repairs that cost over $1 Million

    and caused our contractor to pull off job for several months

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    29/43

    2. Lessons Learned

    Challenges and Issues Encountered

    Work in Easements presents unusual/difficult

    situations

    Public Relations Work is very important (Can we start

    during design). This project was a rush.

    Consider Bid Items for Specific Restoration Work (In this

    contract the work is incidental to other items)

    Youre going to do what in my yard!

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    30/43

    Work in Easements presents unusual/difficult

    construction situations

    Lima Street in Upper-Kalihi

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    31/43

    Work in Easements presents unusual/difficult

    construction situations cont.

    Booth Road in Pauoa Area

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    32/43

    Work in Easements presents unusual/difficult

    construction situations cont.

    Booth Road in Pauoa Area

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    33/43

    Work in Easements presents unusual/difficult

    construction situations cont.

    Existing Deteriorated Sewer Line to be Replaced

    Akahi Street in Upper-Kalihi

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    34/43

    Work in Easements presents unusual/difficult

    construction situations cont.

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    35/43

    2. Lessons Learned

    Challenges and Issues Encountered

    Utility Conflicts, Tight Fits, and Damage to the sewer system

    from other Utilities

    Boring of holes for Utility Poles, and installation or concrete jacketing

    of other utilities are sometimes the culprit of damage to the Cityssewer system

    Tight Utility Crossings even more tight due to upsizing of new line

    Ask the question of whether it is feasible to put the pipe back in the

    same location

    Easier said than done!

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    36/43

    Utility Conflicts, Tight Fits, and Damage to the

    Sewer System from other Utilities

    School Street at Stillman Lane

    8

    l fl h d h

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    37/43

    Utility Conflicts, Tight Fits, and Damage to the

    Sewer System from other Utilities

    Pulaa Lane in Downtown Kalihi

    l fl h d h

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    38/43

    Utility Conflicts, Tight Fits, and Damage to the

    Sewer System from other Utilities

    Pulaa Lane in Downtown Kalihi

    U ili C fli i h i d h

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    39/43

    Utility Conflicts, Tight Fits, and Damage to the

    Sewer System from other Utilities

    Pulaa Lane in Downtown Kalihi

    U ili C fli Ti h Fi d D h

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    40/43

    Utility Conflicts, Tight Fits, and Damage to the

    Sewer System from other Utilities

    Pulaa Lane in Downtown Kalihi

    U ili C fli Ti h Fi d D h

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    41/43

    Utility Conflicts, Tight Fits, and Damage to the

    Sewer System from other Utilities

    Kuakini Street

    d f k h k

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    42/43

    3. A Few Ideas for Making the Work Easier in

    the Future

    Seek Permitting for Night Work in Commercial and Industrial Areas Noise a Factor

    Contractor can work with minimal traffic impacts and inconvenience to public

    Contractor can work more efficiently

    Produce Accurate Record Drawings

    Push Contractors (with CM verification) to maintain and provide accurate recorddrawings

    Consider requiring contractors to provide Record Drawings in CAD

    Consider walking the site with a CM or Contractor

  • 8/12/2019 21_LessonsLearned,PlanningDesConstr

    43/43

    HWEA 32nd Annual ConferenceMarch 17, 2010