Upload
raymond-craig
View
217
Download
0
Embed Size (px)
DESCRIPTION
SD-2002, RAI, V.K. 3 Figure1: A Simplified View of the Effects of Schedule Pressure ++ – + Schedule pressure Errorproneness Work rate Productivity + +
Citation preview
20th InternationalSystem Dynamics Conference, 2002
Paper Title “Dynamics of Schedule Pressure on
Software Projects”Presentation by V.K.Rai
SD-2002, RAI, V.K.
2
Abstract This paper studies the dynamics of schedule pressure in software projects. It
constructs a system dynamics model of the software development process, which includes the following modules. Flow of Work, Work Being Done, Inspection, Fault Detection and Rework, and Supplementary Variables. It includes the module ‘Effect of Schedule Pressure’ and integrates it with the rest of the model. The model presents the results of two sets of schedule-related policies of a system dynamics model. The first set of policies that pertain to the base model does not consider the effect of schedule pressure on the staff productivity and errorproneness while the second set of policies pertaining to the revised model does. This study finds that effect of schedule pressure on software project is non-linear and dynamics of schedule pressure is intricately related to decision making process of the project manager, thus, making software projects management complex and counterintuitive.
Key words: Schedule pressure, software projects, productivity, errorproneness, and decision making
SD-2002, RAI, V.K.
3
Figure1: A Simplified View of the Effects of Schedule Pressure
++
– +
Schedule pressure
Errorproneness
Work rate
Productivity
+ +
SD-2002, RAI, V.K.
4
Figure 2: Work Being Done
Work to be done Work Really Done
WBDCWTDR WUF
WBDF WNR
TWCW
MARUW
NS
PNS
TWCN
FFWCNFWCN ES
PES
PCFES
PCFNS
SD-2002, RAI, V.K.
5
Abbreviations for Figure 2 WTDR: Work To be Done due to Rework WBDC: Work Being Done Correctly WBDF: Work Being Done with Fault WUF: Work with Undetected Fault MARUW: Maximum Allowable Rate of Undertaking Work WNR: Work Needing Rework TWCW: Total Work Completed per Week TWCN: Total Work Completed Normally FWCN: Faulty Work Completed
Normally FFWCN: Fault Free Work Completed Normally ES: Experienced Staff NS:
New Staff PES: Productivity of Experienced Staff PNS: Productivity of New Staff PCFES: Propensity of Fault Commitment for Experienced Staff PCFNS:Propensity of Fault Commitment for New Staff
SD-2002, RAI, V.K.
6
Figure 3: Inspection, Fault Detection and Rework
Work to be done Work Really Done
WBDCWTDR WUF
WBDF WNR
AWNR
TWNR
RMW
TRSPCT
SPCTITMW
TIW
TIWN
WIN
FFD
SD-2002, RAI, V.K.
7
Abbreviations for Figure 3
WTDR: Work To be Done due to Rework WBDC: Work Being Done Correctly WBDF: Work Being Done with Fault WUF: Work with Undetected
Fault WNR: Work Needing Rework WIN: Work being Inspected AWNR: Average Work Needing Rework TWNR: Time to smooth WNR FFD: Fraction of Faults Detected RMW: Rework Multiplier
from Work ITMW: Inspection Time Multiplier from Work TIW: Time to Inspect Work
SPCT: Schedule Project Completion Time TIWN: Time to Inspect Work Normal
TRSPCT: Time Relative to Schedule Project Completion Time
SD-2002, RAI, V.K.
8
Effect of Schedule Pressure on Productivity and Errorproneness of Staff
Table -1:
Productivity andErrorproneness
LowSchedule
Pressure (2)
MediumSchedule
Pressure (3)
HighSchedule
Pressure (4)For Exp.
Staff (PES)High3.0
Medium toLow3.0
Medium toLow2.5
Productivity(Tasks perweek perperson) For New
Staff (PNS)High2.0
Medium toLow2.0
Medium toLow1.5
For Exp.Staff
(PCFES)
Low0.15 or 15%
Medium0.2 or 20%
Medium0.2 or 20%
Errorproneness
(Dimensionless) For New
Staff(PCFNS)
Low0.25 or 25%
Medium0.4 or 40%
Medium0.4 or 40%
SD-2002, RAI, V.K.
9
Figure 4: Two Control Feedback Loops of the Effect of Schedule Pressure
Sector 1
R
Work_to_be_done
Time_Required
Time_Ratio
Schd_Pressure
Productivity
WBDC
Loop 2 (Effect of Schedule Pressure)
R
Work_to_be_done
Time_Required
Time_Ratio
Schd_Pressure
Errorproneness
WBDC
Loop 1 (Effect of Schedule Pressure )
SD-2002, RAI, V.K.
10
Policy runs Two sets of schedule related policies considered first set pertains to the base model it does not consider effect of schedule pressure second set pertains to the revised model it considers effect of schedule pressure schedule estimations considered are:SPCT= 40 weeks (optimistic estimation)SPCT= 50 weeks (normal estimation)SPCT = 60 weeks (pessimistic estimation)Fact = two experienced and two new development staff Assumption= no body leaves and joins the project in the middle
SD-2002, RAI, V.K.
11
Figure 5: Base Model Policy Runs with Constant Productivity and ErrorpronenessPerformance Variables of Base Model (SPCT = 50 weeks)
2:43 AM 5/19/01
0.00 25.00 50.00 75.00 100.00
Time
1:
1:
1:
2:
2:
2:
3:
3:
3:
4:
4:
4:
0.00
50.00
100.00
1: PWRD 2: PWPD 3: EOR 4: EOL
1
1
1
1
2
2
2
2
3
3
3 3
4 44
4
Performance (SPCT = 50 weeks)
SD-2002, RAI, V.K.
12
Figure 6: Comparison of Work to be done for the Base Model Policies
12:33 AM 5/19/01
0.00 25.00 50.00 75.00 100.00
Time
1:
1:
1:
0.00
200.00
400.00
1: Work to be done 2: Work to be done 3: Work to be done
1
1
1
1
2
2
2
2
3
3
3
3
work done (different SPCT)
SD-2002, RAI, V.K.
13
Schedule Policy Runs at Project Completion Time (PCT) Table 2: Some important results of the base model
WC: Total Work Content of the Project; WUF: Work with Undetected Faults, WI : Initial Work Content of the Project: 400 Tasks.
Schedule
Policy
PCT
(weeks)
PWRD
(%)
PWPD
(%)
WC
(tasks)
EOR
(%)
WUF
(tasks)
EOL
(%)
SPCT=40 68.00 97.48 99.86 498 24.41 12.25 3.06
SPCT=50 74.00 97.51 99.87 543 35.74 12.80 3.20
SPCT=60 81.00 97.80 99.88 591 47.80 12.28 3.07
SD-2002, RAI, V.K.
14
Revised Model Policy Runs with Varying Values of Productivity and Errorproneness
Effect of schedule pressure on productivity and Errorproneness considered
Schedule related policies remain the same as in base model
figure 7 shows the rise of schedule pressure for the revised model, SPCT = 50 weeks
Figure 8 performance variables PWRD, PWPD, EOR & EOL for the revised model, SPCT = 50 weeks
Figure 9 compares the three policies with respect to Work to be done (W)
SD-2002, RAI, V.K.
15
Figure 7: Changes in Schedule Pressure with the Time Ratio
2:17 AM 5/19/01
0.00 25.00 50.00 75.00 100.00
Time
1:
1:
1:
2:
2:
2:
0.00
0.50
1.00
1.00
2.00
3.00
1: TR 2: SP
1
1
1 12
2
2 2
Graph 1 (Schedule Pressure)
SD-2002, RAI, V.K.
16
Figure 8: Performance Variables of Revised Model (SPCT = 50 weeks)
2:40 AM 5/19/01
0.00 25.00 50.00 75.00 100.00
Time
1:
1:
1:
2:
2:
2:
3:
3:
3:
4:
4:
4:
0.00
50.00
100.00
1: PWRD 2: PWPD 3: EOR 4: EOL
1
1
1
1
2
2
2
2
3
33 3
4 44
4
Performance (SPCT = 50 weeks)
SD-2002, RAI, V.K.
17
2:43 AM 5/19/01
0.00 25.00 50.00 75.00 100.00
Time
1:
1:
1:
0.00
200.00
400.00
1: Work to be done 2: Work to be done 3: Work to be done
1
1
1
1
2
2
2
2
3
3
3
3
work done (different SPCT)
Figure9: Comparison of work to be done for the revised model policies
SD-2002, RAI, V.K.
18
Some of the important results of the revised model. Table 3
Schedule
Policy
PCT
(weeks)
PWRD
(%)
PWPD
(%)
WC
(tasks)
EOR
(%)
WUF
(tasks)
EOL
(%)
SPCT=40 74.00 97.82 99.89 489 22.29 10.09 2.52
SPCT=50 72.00 97.91 99.89 511 27.70 10.10 2.53
SPCT=60 73.00 98.05 99.89 544 35.98 10.01 2.50
SD-2002, RAI, V.K.
19
Conclusion Effect of schedule pressure on productivity and
errorproneness is non-linear The base model shows significant increase in (PCT)
with increase in SPCT Revised model shows little increase in PCT with
increase in SPCT Extent of rework increases from 22% to 36% as SPCT
increases from 40 weeks to 60 weeks Extent of latent error, another measure of software
quality, remains around 2.5% for all cases
SD-2002, RAI, V.K.
20
THANK YOU