10

 · 2020. 3. 17. · Photo 5: Temporary culvert crossing in new channel.Scheduled for removal on 10/23/2018. Recommend removal of as much soil as possible from crossing prior to removal

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1:  · 2020. 3. 17. · Photo 5: Temporary culvert crossing in new channel.Scheduled for removal on 10/23/2018. Recommend removal of as much soil as possible from crossing prior to removal
Page 2:  · 2020. 3. 17. · Photo 5: Temporary culvert crossing in new channel.Scheduled for removal on 10/23/2018. Recommend removal of as much soil as possible from crossing prior to removal
Page 3:  · 2020. 3. 17. · Photo 5: Temporary culvert crossing in new channel.Scheduled for removal on 10/23/2018. Recommend removal of as much soil as possible from crossing prior to removal
Page 4:  · 2020. 3. 17. · Photo 5: Temporary culvert crossing in new channel.Scheduled for removal on 10/23/2018. Recommend removal of as much soil as possible from crossing prior to removal
Page 5:  · 2020. 3. 17. · Photo 5: Temporary culvert crossing in new channel.Scheduled for removal on 10/23/2018. Recommend removal of as much soil as possible from crossing prior to removal
Page 6:  · 2020. 3. 17. · Photo 5: Temporary culvert crossing in new channel.Scheduled for removal on 10/23/2018. Recommend removal of as much soil as possible from crossing prior to removal
Page 7:  · 2020. 3. 17. · Photo 5: Temporary culvert crossing in new channel.Scheduled for removal on 10/23/2018. Recommend removal of as much soil as possible from crossing prior to removal

Good Housekeeping

Photo 1: Pan installed under portable toilet and spill kit on site.

Photo 2: Staged straw bales ready to be deployed prior to any qualifying rain event.

Page 8:  · 2020. 3. 17. · Photo 5: Temporary culvert crossing in new channel.Scheduled for removal on 10/23/2018. Recommend removal of as much soil as possible from crossing prior to removal

Photo 3: Planting and mulching along channel is ongoing.

Photo 4: Planting and native vegetation left in place. Mulch pile on hand for soil stabilization prior to anticipated rain events.

Page 9:  · 2020. 3. 17. · Photo 5: Temporary culvert crossing in new channel.Scheduled for removal on 10/23/2018. Recommend removal of as much soil as possible from crossing prior to removal

Photo 5: Temporary culvert crossing in new channel. Scheduled for removal on 10/23/2018. Recommend removal of as much soil as possible from crossing prior to removal of culverts and spreading of gravel into channel. Items of Concern

Photo 6: Fuel tank in containment and spill kit present. Contained tank should be covered during rain events to prevent pooling of water in container.

Page 10:  · 2020. 3. 17. · Photo 5: Temporary culvert crossing in new channel.Scheduled for removal on 10/23/2018. Recommend removal of as much soil as possible from crossing prior to removal

Site Deficiencies None