Democratic Socialist Republic of Sri Lanka

Ministry of Mahaweli Development and Environment

Mahaweli Water Security Investment Program

Program Management, Design and Supervision Consultant

INCEPTION REPORT – FINAL

March 2016

Page 2: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page i

© Joint Venture Lahmeyer International GmbH – GeoConsult ZT GmbH, 2016. The information contained inthis document is solely for the use of the Client identified on the cover sheet for the purpose for which ithas been prepared. The Joint Venture undertakes neither any duty to, nor accepts any responsibilitytowards, any third party who may rely upon this document. All rights reserved. No section or element ofthis document may be removed from this document, reproduced, electronically stored or transmitted inany form without written permission of the Joint Venture.

Page 3: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page ii

INCEPTION REPORT - FINAL

Prepared for:

Ministry of Mahaweli Development and EnvironmentProgram Management UnitNo. 493 T.B. Jayah MawathaColombo 10Sri Lanka

Prepared by:

Program Management, Design and Supervision ConsultantJoint Venture Lahmeyer International GmbH – GeoConsult ZT GmbHin Association with NIRAS (Denmark), Engineering Consultants Ltd. (Sri Lanka), andInfotechs IDEAS (Pvt.) (Ltd.) (Sri Lanka)No. 493 T.B. Jayah MawathaColombo 10Sri Lanka

Lahmeyer International Main OfficeFriedberger Str. 17361118 Bad VilbelGermany

Distribution Register:

Distribution List: Date of Issue Number of Copies

MMDE March 2016 4

ADB March 2016 2

LI March 2016 3

GC March 2016 1

InfoTechs March 2016 1

ECL March 2016 1

NIRAS March 2016 1

Revision History:

Revision Date Author Department Checked by Approved by Description

1 6 Mar 2016 MRC/BJF GW2 MRC BJF

Page 4: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page iii

ABBREVIATIONS

ADB Asian Development BankBoQCAPCCEA

Bill of QuantitiesCabinet Appointed Procurement CommitteeCentral Environmental Authority

DPC Department Procurement CommitteeEIAEOIFAMGBLGOSLIAICTADIDISEWPkmKMTC

Environmental Impact AssessmentExpression of InterestFacility Administration ManualGeotechnical Baseline ReportGovernment of Sri LankaImplementing AgencyInstitute for Construction Training and DevelopmentIrrigation DepartmentImproving system efficiencies and water productivityKilometreKalu Ganga-Moragahakanda Transfer Canal

m³/smaslMASL

Cubic metres per secondMetres above mean sea levelMahaweli Authority of Sri Lanka

MCB Mahaweli Consultancy BureauMCMMDPMIWRMMLBCR

Million m3

Mahaweli Development ProgramMinistry of Irrigation and Water Resources ManagementMinipe Left Bank Canal Rehabilitation

MFFMFPMMDEMPCMPPMRBNCPCPNPA

Multitranche financing facilityMinistry of Finance and PlanningMinistry of Mahaweli Development and EnvironmentMinistry Procurement CommitteeMaster Procurement PlanMahaweli River BasinNorth Central Province Canal ProjectNational Procurement Agency

NWPC North Western Province CanalPD-MWSIP Program Director Mahaweli Water Security Investment

ProgramPD-UEC Project Director –Upper Elahera CanalPMDSC Program Management, Design and Supervision ConsultantPPTAPSCRFRIPRPCSBDSIWRMToRUEC

Project Preparatory Technical AssistanceProgram Steering CommitteeResettlement FrameworkResettlement Implementation PlanRegional Procurement CommitteeStandard Bid DocumentsStrengthening Integrated water Resources ManagementTerms of ReferenceUpper Elahera Canal

Page 5: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page iv

Table of Contents

1 EXECUTIVE SUMMARY .........................................................................................................1

1.1 INTRODUCTION ..................................................................................................................................1

1.2 IMPLEMENTATION ARRANGEMENTS .......................................................................................................2

1.3 PROGRESS TO DATE ............................................................................................................................3

1.4 DETAILED WORKPLAN, ACTIVITIES, STAFFING AND TASKS ...........................................................................4

1.5 PROGRAM IMPLEMENTATION PLAN .......................................................................................................5

1.6 STRUCTURE OF THE REPORT..................................................................................................................7

2 INTRODUCTION....................................................................................................................8

2.1 MAHAWELI WATER SECURITY INVESTMENT PROGRAM ..............................................................................8

2.2 BACKGROUND TO WATER RESOURCES IN SRI LANKA ...............................................................................102.2.1 Mahaweli Ganga ...................................................................................................................102.2.2 Mahaweli Development Program prior to the MWSIP ..........................................................11

2.3 PREVIOUS STUDIES, SURVEYS AND INVESTIGATIONS ................................................................................12

3 IMPLEMENTATION ARRANGEMENTS .................................................................................16

3.1 INVESTMENT PROGRAM.....................................................................................................................163.1.1 Multi-Tranche Financing Facility............................................................................................163.1.2 Implementation Schedule ......................................................................................................163.1.3 Program Outputs ...................................................................................................................17

3.2 ORGANIZATIONAL SETUP ...................................................................................................................213.2.1 Implementation Agencies ......................................................................................................21

3.3 PROGRAM MANAGEMENT, DESIGN AND SUPERVISION CONSULTANT .........................................................223.3.1 Mobilization...........................................................................................................................223.3.2 Scope of Services....................................................................................................................22

3.4 SAFEGUARDS ...................................................................................................................................233.4.1 Environmental........................................................................................................................233.4.2 Resettlement..........................................................................................................................25

3.5 POVERTY AND SOCIAL........................................................................................................................25

4 PROGRESS TO DATE ...........................................................................................................26

4.1 PMDSC OFFICE AND LOGISTICS..........................................................................................................26

4.2 MEETINGS ......................................................................................................................................26

4.3 TASK 1 – PROGRAM MANAGEMENT ....................................................................................................264.3.1 Program Inception .................................................................................................................264.3.2 Reconnaissance......................................................................................................................274.3.3 Continuous GIS Update..........................................................................................................274.3.4 Terms of Reference for Improving System Efficiency and Water Productivity (ISEWP) .........274.3.5 Program Fund Disbursement Handbook................................................................................27

4.4 TASK 2 – DESIGN REVIEW, DETAILED DESIGNS AND PREPARING CONTRACT DOCUMENTS...............................274.4.1 Preparation of Tenders for Additional Surveys and Investigations........................................274.4.2 Designs...................................................................................................................................294.4.3 Tunnel Optimisation ..............................................................................................................294.4.4 Commencement of Tender Design Review ............................................................................31

4.5 TASK 3 – CONTRACT MANAGEMENT, CONSTRUCTION SUPERVISION, COMMISSIONING AND OPERATION ..........344.5.1 Tenders Floated .....................................................................................................................344.5.2 Imminent Tenders..................................................................................................................34

4.6 TASK 4 - CAPACITY DEVELOPMENT AND TRAINING IMPLEMENTATION.........................................................34

4.7 TASK 5 – COMMUNICATIONS..............................................................................................................34

Page 6: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page v

4.8 TASK 6 – PREPARING A STRATEGIC ENVIRONMENT ASSESSMENT (SEA) ......................................................34

4.9 TASK 7 - PREPARATION OF PHASE 2.....................................................................................................354.9.1 Route Selection ......................................................................................................................354.9.2 Modelling...............................................................................................................................36

5 DETAILED WORKPLAN, ACTIVITIES, STAFFING AND TASKS .................................................38

5.1 CURRENT STATUS .............................................................................................................................38

5.2 PPMES AND MIS ............................................................................................................................38

5.3 UEC TUNNEL 3 EARLIER CONSTRUCTION START (TASKS 2 AND 3) .............................................................395.3.1 Rationales ..............................................................................................................................395.3.2 Actions to be taken including Additional Investigations........................................................395.3.3 Potential for an Early Start to Construction...........................................................................40

5.4 UEC-ICB-3 (6+226 TO 17+900KM) IN TRANCHE 2..............................................................................405.4.1 Rationales ..............................................................................................................................405.4.2 Implications for Resource Allocations....................................................................................40

5.5 KMTC ADVANCEMENT (TASKS 2 AND 3) ..............................................................................................405.5.1 Rationales ..............................................................................................................................405.5.2 Actions to be taken including Additional Investigations........................................................415.5.3 Implications for Resource Allocation .....................................................................................41

5.6 NATIONAL VS. INTERNATIONAL DESIGN STANDARDS (TASKS 2 AND 3) ........................................................415.6.1 Dam Safety (ICOLD) ...............................................................................................................415.6.2 Possible Scope Changes Relating to Existing Structures (Tasks 2 and 3) ...............................435.6.3 Kongetiya Level Crossing .......................................................................................................445.6.4 Implications for Resource Allocation .....................................................................................45

5.7 CAPACITY DEVELOPMENT STRATEGY (TASK 4)........................................................................................465.7.1 Approach ...............................................................................................................................465.7.2 Training Needs Assessment and formulation of Training and Capacity Development Program

485.7.3 Implementing the Training Program .....................................................................................485.7.4 Preliminary Review of Water Resource Management on Sri Lanka ......................................495.7.5 Institutional and Staff long-term Development Plans for MMDE..........................................495.7.6 Finalizing ToR for the SIWRM Consultancy ............................................................................505.7.7 Anticipated Deliverables under Task 4...................................................................................50

5.8 COMMUNICATIONS STRATEGY (TASK 5)................................................................................................505.8.1 Approach to Stakeholder Communications ...........................................................................505.8.2 Priorities and Next Steps for Implementation of the Strategic Communications Plan ..........52

5.9 SEA STRATEGY (TASK 6)....................................................................................................................52

5.10 ACCELERATION OF ROUTE SELECTION FOR PHASE 2 (TASK 7)....................................................................535.10.1 Justification for Acceleration of the Route Selection .............................................................535.10.2 Strategy .................................................................................................................................545.10.3 Technical Issues .....................................................................................................................545.10.4 Actions to be Taken (Investigations, Surveys, Modelling, Stakeholder Consultations)..........55

5.11 MODELLING ....................................................................................................................................575.11.1 Baseline Assessment ..............................................................................................................605.11.2 Model Development ..............................................................................................................615.11.3 Model Extension ....................................................................................................................645.11.4 Substantiation of the Approach.............................................................................................645.11.5 Dam Break Modelling ............................................................................................................65

5.12 RESETTLEMENT ................................................................................................................................665.12.1 Priority Actions for Tranche 1 ................................................................................................665.12.2 MLBCRP..................................................................................................................................675.12.3 NWPCP...................................................................................................................................675.12.4 For Preparation of Tranche 2 and 3.......................................................................................68

Page 7: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page vi

6 PROGRAM IMPLEMENTATION PLAN ..................................................................................69

6.1 GOVERNMENT ACTIONS ....................................................................................................................696.1.1 PMU/PIU Staff Recruitment...................................................................................................696.1.2 Human-Elephant Conflict.......................................................................................................696.1.3 MMDE and ADB Approvals ....................................................................................................69

6.2 PROCUREMENT ISSUES ......................................................................................................................72

6.3 MODELLING ....................................................................................................................................72

6.4 REVISED STAFFING SCHEDULE .............................................................................................................726.4.1 Staff Replacements ................................................................................................................726.4.2 Staff Inputs from Home Office ...............................................................................................736.4.3 Re-scheduling of Supervision Staffing....................................................................................736.4.4 Proposed Additional Inputs....................................................................................................73

6.5 FINANCIAL ISSUES.............................................................................................................................756.5.1 Proposed Staging of Payments for LS Deliverables................................................................756.5.2 Provisional Sums ....................................................................................................................756.5.3 New Tax Rates .......................................................................................................................766.5.4 PMDSC Offices .......................................................................................................................76

ANNEX A IMPLEMENTATION SCHEDULE............................................................................................77

ANNEX B STAFF MOBILISATION.........................................................................................................80

ANNEX C MINUTES OF MEETINGS .....................................................................................................81

ANNEX D PMDSC DETAILED WORKPLAN............................................................................................96

ANNEX E DATA REQUIREMENTS FOR GEOTECHNICAL DESIGNS ......................................................102

ANNEX F DATA REQUIREMENTS FOR MODELLING ..........................................................................104

ANNEX G UPDATED STAFFING SCHEDULE ........................................................................................106

ANNEX H TERMS OF REFERENCE......................................................................................................109

ANNEX I LUMP SUM PAYMENT SCHEDULE .....................................................................................112

ANNEX J PROCUREMENT PLAN.......................................................................................................113

Page 8: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page vii

List of Figures

Figure 1: Layout Map of the Mahaweli Water Security Investment Program...............................................9

Figure 2: Mahaweli Declared Areas.............................................................................................................13

Figure 3: Kalu Ganga – Moragahakanda Transfer Canal and Upper Elahera Canal Project ........................18

Figure 4: North West Province Canal Project ..............................................................................................19

Figure 5: Minipe Left Bank Canal Rehabilitation Project .............................................................................20

Figure 6: Organizational Chart of the MWSIP..............................................................................................21

Figure 7: Typical Horseshoe Tunnel Profile .................................................................................................30

Figure 8: The Hierarchy of Capacity Needs..................................................................................................47

Figure 9: MCA Schedule...............................................................................................................................56

Figure 10: Proposed Approach to Model Development for the Mahaweli System ....................................59

List of Tables

Table 1: Feasibility Studies done for the NCPCP (2012-2013) .....................................................................14

Table 2: Status of Additional Geotechnical Investigations (12 February 2016)...........................................28

Table 3: Initial Meetings with Authorities ...................................................................................................36

Table 4: PPMES Arrangement for the MWSIP .............................................................................................39

Table 5: Preliminary Classification of Embankment Dams in MWSIP .........................................................43

Table 6: MCA Effects Table Structure..........................................................................................................55

Table 7: Canal Lengths in the Mahaweli System .........................................................................................58

Table 8: CEA and ADB Approval Status (12 February 2016) ..........................................................................70

Table 9: Status of Bid Document Preparation and Review by ADB and PMU .............................................71

Page 9: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 1

1 EXECUTIVE SUMMARY

1.1 Introduction

1. The Mahaweli Water Security Investment Program (MWSIP) is the final stage of the MahaweliDevelopment Plan (MDP), which has been pivotal in meeting national development goals. The NorthCentral Province Canal Project (NCPCP) is an outstanding investment component of MDP: Phase 1 ofNCPCP will transfer water from the Mahaweli River Basin to existing reservoirs in the Central, NorthCentral and North Western Provinces, and Phase 2 will extend the transfer of water from the NorthCentral Province reservoirs to the Northern Province.

2. The MWSIP will implement Phase 1 of the NCPCP to increase agricultural production and improvedrinking water supplies to households within the North West and North Central Provinces. Key elementsof the program of Phase 1 include the Upper Elahera Canal Project (UECP), the North West ProvinceCanal Project (NWPCP), and the Minipe Left Bank Canal Rehabilitation Project (MLBCRP), located in thedownstream reach of the Mahaweli Ganga (River). The MWSIP will also address other key sectorpriorities through improving irrigation system efficiencies and water productivity and throughstrengthening water management institutions.

3. Phase 2 will extend the transfer of water to the North Central and North Provinces, with theextension of the Phase 1 transfer canals and tunnels, construction of new reservoirs and hydropowerstations and the transfer of additional water to support drinking water supply and irrigated agriculture.On completion of the NCPCP, the total area fully or partially supplied from the Mahaweli Ganga will risefrom 146,000 ha to 233,000 ha, municipal and domestic water supplies in the north of the country willhave been enhanced by some 100 MCM per year, and the installed capacity within the MahaweliDevelopment area will have increased by 30 MW.

4. Sri Lanka’s water resources are not well distributed in time and space between the ‘wet zone’ ofthe central and south west districts (25% of the area and 70% of the water resource) and the ‘dry zone’of the north and east (30% of the water but more than 80% of the water demand). Annual per capitaendowment of water (ACE) in the north is predicted to decline to water scarcity levels (less than 1,000 m3)by 2025. With regard to energy production, 40% of the country’s installed capacity is in hydropower,mostly within the ‘wet zone’, and is used primarily for meeting peak daily demands.

5. The Mahaweli Ganga is the largest river basin (of 103) in Sri Lanka, with a catchment area ofapproximately 10,300 km2 and annual average flow volume of 5,474 MCM (more than 10% of nationalannual renewable water). The headwaters originate in the highlands of the wet zone, and the river flowsto the northeast. It represents a large and strategically important water resource, which is beingdeveloped to meet the countries energy, water and food needs. There are estimated to be more than30,000 tanks nationally and government has historically promoted water storage and water resourcesdevelopment programs. However, climate change is likely to cause increased demand and a decline inreliability of water sources, which could further exacerbate shortages and reliability of water sourceswithin the northern dry zone and increase vulnerability of communities to food shortages.

6. The MDP, initiated in the early 1960s with the objective of developing the water and landresources of Mahaweli Basin and the dry zone areas of the northern provinces, was ambitious andincluded multiple storage dams, hydropower stations, transfer canals and irrigation systems. To-datecompleted works include the construction of the cascade of storage dams and power-stations on theMahaweli Ganga, dams constructed on the Amban Ganga (tributary of the Mahaweli Ganga), andconstruction of two diversion tunnels. A further four reservoirs and power stations are under

Page 10: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 2

construction, two of which would also be on one of the possible routes for water transfers fromMahaweli Ganga.

7. Development so far has largely been focused within the Mahaweli Basin and the development ofthe land and water resources of the northern provinces remains to be completed, largely through watertransfers. This is the objective of the final stage of the MDP and aims to complete fulfilment of the plan’sgoals. Previous studies, surveys and investigations were undertaken to fulfil the aims of the NCPCP, butwork was suspended in the late 1970s due limitations in financial and other resources. Subsequently,several studies were conducted to update the planning for the project but these could not beimplemented due to financial constraints and civil disturbances. The NCPCP has now been prioritised toaddress urgent socio-economic needs in the country.

8. During April to December 2014, the Asian Development Bank (ADB) supported a ProjectPreparatory Technical Assistance (PPTA) to conduct due diligence of Phase 1 of the NCPCP and preparethe investment program documents, comprising assessment of technical, economic, financial,governance, poverty, social, and safeguards issues. The activities under this PPTA led to the preparation ofa program proposal in ADB’s format for financing an investment program. During the PPTA engineeringdesigns and draft bid documents were prepared for three advance contract packages, feasibility-leveldesigns were prepared for other civil works packages and a large program of geotechnical investigationswas completed. In 2015 the investment program was approved by ADB and the government.

1.2 Implementation Arrangements

9. The cost of the MWSIP is estimated at $675 million and will use the ADB’s multi-tranche financingfacility (MFF) modality, loaned to the government in three tranches. Tranche 1 was approved in 2015.Approval for the second tranche is scheduled for 2016 and approval for the third tranche is scheduledin 2018. Construction will be through a combination of international and national competitive bidding.Phase 2 of the Program is not financed under the current investment program; however, feasibility workfor the second phase forms part of the work to be carried out by the Program Management, Design andSupervision Consultant (PMDSC), who were contracted in 2015 and mobilised in December of last year.

10. Implementation of the MFF is tentatively scheduled from 2015 to 2024 and will include 20 majorworks packages and three main consultancy packages and various individual consultant assignments, aswell as training and capacity development of government officers and departments. Evaluation of thefirst tendered package is currently in progress. Program outputs include nearly 200 km of canals andtunnels, two large main earthfill dams and the heightening of an existing anicut together with therehabilitation of the 74km of canals the irrigated areas that it will serve.

11. The executing agency (EA) for the MWSIP is the Ministry of Mahaweli Development andEnvironment (MMDE) under which a Program Management Unit (PMU) and three Project ImplementationUnits (PIUs) have been established to implement the program. A Program Steering Committee (PSC) hasbeen established to provide overall coordination. An independent review panel (IRP) is being recruitedto review outputs from the PMDSC and other consultants, and provide advice to the PMU and ADB ontechnical and contractual matters. At the completion of the investment program, the investments willbe managed by either the ID or MASL.

Page 11: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 3

12. The Joint Venture of Lahmeyer International GmbH – GeoConsult ZT GmbH, in association withInfotech IDEAS (Sri Lanka), Engineering Consultants (Pvt) Ltd (Sri Lanka), and NIRAS (Denmark) wasappointed the PMDSC in November 2015. They commenced mobilising to Colombo on 1 December2015. The PMDSC will assist the PMU over a period of five years with designs, procurement of civilconstruction contracts and consulting services, supervision of construction works and preparation ofPhase 2 investments. The Terms of References (ToR) of PMDSC include 7 major tasks, which aredescribed in the following sections.

13. All three investment projects have been categorized for safeguards and assessments preparedprior to ADB Board approval and safeguard documents were prepared during the PPTA in respect ofenvironmental and assessments and resettlement issues. Environmental Impact Assessments (EIAs) andan Initial Environmental Examination (IEE) have been completed and some approvals have been given.Environmental Management Plans (EMPs) have been prepared for each EIA and IEE. An EnvironmentalAssessment Review Framework (EARF) was prepared by the PPTA to guide the formulation of safeguardsdocuments for future tranches according to the government’s and ADB’s policy requirements.

14. Involuntary resettlement will be required for parts of the program and resettlementimplementation plans (RIPs) were prepared for each project to ensure that there are adequate socialsafeguards for affected persons. The PMU/PIU will monitor the RIPs implementation to determinewhether resettlement goals have been achieved.

1.3 Progress to Date

15. During the ADB inception mission, the PMDSC presented the progress to date of the MWSIP tothe meeting of the Program Steering Committee (PSC) on 25 February 2016. The implementation of theprogram was reviewed with members of the committee along with a discussion of critical path itemsincluding (i) finalization of the Minipe Anicut design and whether to incorporate a mini-hydro powergeneration facility; (ii) approval of the PMDSC’s recommendation to raise the invert elevation of the UECat the outlet from the Moragahakanda Dam; and (iii) the final selection of the route for conveyance ofwater transfers in Phase 2.

16. The PMDSC carried out reconnaissance visits covering the majority of the Program area and heldinitial meetings with PMU, ADB as well as with the Central Environmental Authority (CEA) to provideclarifications for different parts of the Program. An organisational structure was set up for the office,using temporary facilities during December and early January, and moving into the offices provided byMMDE mid-January. The Terms of Reference for the consultancy package for irrigation system efficiencyimprovement were updated and are submitted with this Inception Report.

17. Bid documents for additional geotechnical investigations required for finalisation of the design ofthe dams and tunnels have been prepared following site visits to the corresponding areas, and two setsof documents were issued with invitations to submit bids. One set has already been returned andevaluated and clarifications are being sought.

18. Design review Tranche 1 packages commenced and optimisation has begun on a range ofconstruction contract designs. Some modifications have been recommended to both canal and tunneldesigns, such as adhering to international design standards and increasing the robustness of concretestructures. A Tender Design Review Report (TDRR) will be prepared for three packages that were at an‘advanced stage’ of completion at the commencement of services by the PMDSC. It has been determinedthat some packages indicated to be 100% complete during the PMDSC’s contract negotiations are in factnot construction-ready and will need further work on them before being issued. Adjustments to designpackages are described in detail in this Inception Report.

Page 12: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 4

19. One tender package was floated for national competitive bidding (NCB) during December 2015and a further NCB package, as well as one package for international competitive bidding (ICB), are to beissued during February. Other bid documents are under preparation. Preliminary work has begun on theCapacity Development and Communications tasks, and the national and international environmentalteam for preparation of the Strategic Environment Assessment (SEA) has been mobilised.

20. The updated ToR for the consulting services package that will prepare strategy for theimprovement of cascade irrigation system efficiency and water productivity (ISEWP) was reviewed withthe PMU and ADB during the inception mission. An integral part of the work is that it will bedemonstrated in selected areas as the first step in scaling-up the process of addressing neededimprovements in agricultural productivity, especially in light of the vulnerability to climate change thatwill exacerbate water shortages in the dry zone. Approval for the ToR and budget is sought from the PMUso that recruitment of the ISEWP may occur by mid-2016.

21. Work progressed on the preparation of a study of two possible alternative routes for conveyingwater from the Mahaweli Ganga to the Moragahakanda Reservoir. The selection of one of these is anessential pre-condition for progressing the Phase 2 investigations and feasibility study work. Literaturereview has been complemented by mathematical simulation of water transfers and power generationfor one of the options – the other having already been previously simulated. Further, a workshop wasarranged for carrying out multi-criteria analysis (MCA) of the two optional routes with the participationof a wide range of institutional stakeholders.

22. Progress was also made with planning a general approach to fulfilling the requirements of thePMDSC’s ToR in respect of general model(s) development, and key meetings were held with the WaterManagement Secretariat (WMS), the Ceylon Electricity Board (CEB), and others to determine planningstrategies and data availability for further model development and simulation use. Strategies wereformulated for the various model types to be developed under the PMDSC ToR.

1.4 Detailed Workplan, Activities, Staffing and Tasks

23. Initial focus has been on reviewing and completing bid documents for issue as early as reasonablypossible, consistent with the completion of essential modifications. The PMU and ADB have indicatedthat priority needs to be given to the issue of bid invitations and the construction of Tranche 2 worksand the PMDSC has started investigating the implications of such changes in sequence. Tranche 2comprises a long tunnel to be constructed by tunnel boring machine (TBM) and the connection of tworeservoirs by canal and tunnel sections. The long tunnel lies on the critical path for completion of theoverall Program. Additional investigations are being instructed: the associated package is currently beingtendered. At the present stage of investigations and subsequent design modification it is not currentlypossible to give assurances on an earlier start than previously envisaged.

24. The canal and tunnel connection of the two reservoirs, if moved forward to an earlier start underan accelerated program, would bring some water allocation and power benefits. However, constructionsupervision of these works is currently outside the scope of the PMDSC’s ToR and additional resourceswould be required if this work were to be included.

25. Concerns have arisen related to the adoption of international design standards for dams asrequired by the PMDSC’s ToR, in that these are more strict than the Sri Lankan standards adopted todate, and will be associated with higher costs than previously estimated when applied. This affects areassuch as spillway capacity, dam stability, and instrumentation. Several dams in the Program are classifiedas ‘high dams’ under internationally recognised guidelines and pose potentially severe risks to thoseliving downstream of them in the event of failure.

Page 13: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 5

26. A further concern is that some existing structures, including dams of significant dimensions, willbecome part of the NCPCP infrastructure and are not currently included in the scope of work of theMWSIP or PMDSC, though they may require stability checks and modifications to comply withinternational standards.1 Significant leaks and other defects were noted during reconnaissance visits atsome existing level crossings in the project areas. Additional resources will be required to manage thiswork. We have included in this report a proposal to conduct an inventory of the existing dams and levelcrossings to assess them and make recommendations to the PMU about any additional works required.

27. Work on the capacity development and communications tasks will commence during Februaryand an exchange of information as well as detailed discussion of methodologies and strategies will formpart of the inception mission’s activities. Outline methodologies are included in this Inception Report.

28. Work has also started on planning of the SEA strategy, including literature review of the MDP,other ongoing and planned development programs within the MDP’s area of influence, environmentaland socio-economic baseline data, previous SEAs, EIAs, ESIAs and IEEs, policies, laws and regulations,and the institutional framework that defines the responsibilities for MDP operations and the managementof natural resources in its scope.

29. Progress made so far on a study of two possible alternative routes for conveying water from theMahaweli Ganga to the Moragahakanda Reservoir has been reported in Section 1.3, where its importancefor proceeding with Phase 2 investigations and studies is also described. Work on the MCA evaluationof routing alternatives, now in progress, is expected to allow earlier completion of the associated routeselection report than previously planned. Simulation work for comparison of water allocations usingeach of the two routes is being carried out using the existing water allocation/balance model that is alsoused by WMS. A component of one of the route alternatives is the heightening of the Kotmale Dam byabout one third of its existing height, and there would be significant risks with such work, which wouldneed extensive study if it were to be implemented. It is unlikely that such a significant raising of this typeof dam has a precedent anywhere in the world.

30. Plans and recommendations have been formulated for the development of various model typesspecified in the PMDSC’s ToR. Proposals for the long-term development of a “Mahaweli SystemOperations Model” are outlined in this report, which would comprise several different numerical modelsserving specific purposes as part of an integrated decision support system (DSS). A suite of models willbe required, which may be linked to one another and run iteratively. A flow chart is presented, whichprovides an overview of the approach intended for development of an appropriate suite of models. Thenext stage of work will involve intensive data collection and plausibility checking followed by modelsetup, calibration and verification. Modelling is also required under the consultancy package to besupervised by PMDSC in respect of strengthening integrated water resources management (IWRM). Afurther simulation task will be that of dam break modelling, which will be carried out for dams designedunder the Program.

1.5 Program Implementation Plan

31. The early recruitment of staff to the PMU and three PIUs so all critical positions all filled in thenext several months, especially the safeguards specialists, will be essential for maintaining progress onthe Program. The PMU will add several young engineers recruited from MASL and ID in order to buildthe technical and management capacity of the next generation of Sri Lanka’s water resources engineers.

1 Some but not all of the dams and level crossings in the MWSIP were previously analysed as part of the World Bank DamSafety and Water Resources Planning Project.

Page 14: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 6

32. To comply with ADB and government environmental safeguard policies, a study related to HumanElephant Conflict (HEC) must be carried out in support of the recommendations in the EIA report;however, it has not yet been initiated. These EIAs prepared for the UECP and NWPCP have not yet beenapproved by the CEA, although the mobilisation of contractors cannot start until this occurs, along withthe sanctioning of the contractor’s EMPs. There is a risk of some delay to the commencement ofconstruction activities if the EIAs are not approved soon.

33. Conditional approval has already been given by ADB for some Tranche 1 packages; however, thePMDSC has identified some revisions are needed for the design and bid documents, in addition to thosecomments the PMU received from ADB. In some cases the MMDE’s Technical Evaluation Committee(TEC) have requested even further modifications to these packages. A detailed status of the approvalstatus of each Tranche 1 package is given in the report.

34. The procurement of vehicles for the PMDSC has been temporarily delayed by the inability toreceive price quotations from suppliers, due to uncertainty over new importation duties and taxes.Initial indications though are the Provisional Sum budget will be inadequate to purchase enough vehiclesfor effective supervision of the large number of civil works packages to be implemented concurrently.The PMDSC is presently obtaining quotations and will prepare an updated budget request for the PMU’sapproval. The available budget for office equipment is also being reviewed in light of the needs foreffectively supporting the Program.

35. The PMDSC’s staffing schedule has been revised to reflect the present status of planning, asoutlined in Section 1.4. No additional resources or staffing are being requested for finalizing the designsand bid documents (Task 2) or for preparing the Strategic Environmental Assessment (SEA) Task 6, sincethese are both part of the Lump Sum contract. Rationales for the additional staffing inputs or re-scheduling in the Time-based tasks (Tasks 1, 3, 4, 5 and 7) include (i) the acceleration of the constructionof the KMTC; (ii) the inclusion of the Kongetiya Level Crossing in the UEC-ICB-3 bid package; (iii) carryingout an assessment of the existing dams and level crossings that will become part of the Phase 1 constructedworks in the project areas; and (iv) the requirement for additional specialists’ inputs based on ourrecommendations for the best ways of meeting the government’s objectives of an acceleratedimplementation schedule, as discussed in this report. None of these activities was included in the originalscope of work in PMDSC’s Terms of Reference. It should be noted that the resources included for thesupervision of the civil works packages, including the construction of KMTC, assume the same constructionduration (simply moved forward) as in the contract agreement. Should this duration be longer, thesupervision resources required would increase accordingly. Due to the delayed commencement ofconstruction activities, the PMDSC has proposed re-scheduling some staffing resources to bettersupport the extensive planning and preparation of Phase 2, which an initial assessment of thepreparation of the preliminary designs has indicated will definitely be required.

36. Mobilisation to the site offices, and their being properly equipped and staffed by supportpersonnel, will be necessary soon in order to support the supervision tasks. Concerns have been raisedabout the adequacy of the available work space for the planned number of PMDSC staff, which will be20 to 25 people at peak times. Additional resources may be requested for extra running costs if thePMDSC staff are stationed at more offices than planned.

Page 15: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 7

1.6 Structure of the Report

37. This Inception Report presents the main findings of the PMDSC and includes a revised work planfor the updated implementation schedule. We report all on all the Tasks (1 to 7) in the MWSIP since thereare activities and progress that has been made on each one; however, we will also prepare separateinception reports specifically for Tasks 6 and 7 at a later date according to the schedule in the ToR.

38. The report begins with a brief description (Section 2) of the MWSIP and background of the MDP,and outlines in Section 3 the objectives of, activities by, and outputs expected from the PMDSC, theauthors of this report. The progress to date with activities required by the Consultant’s ToR is reportedin Section 4.

39. The initial intent of the ToR was that the Inception Report would restrict its reporting to Tasks 1(Program Management), 2 (Design Review and Preparation of Bidding Documents), 3 (ContractAdministration), 4 (Capacity Development), and 5 (Communications). For some aspects of the Program,circumstances are however now different and changes in emphasis have occurred since the time atwhich the ToR were prepared. For example, the ToR anticipated that at the time of mobilisation of theConsultant several construction packages would have been tendered, whereas in fact the first packagewas issued for bidding in late December 2015 after the PMDSC’s mobilisation, and at the time of writingmodifications to other sets of bid documents are being implemented prior to issue. It was alsoanticipated by the ToR that the PMU and PIU counter-part staff would be up to full strength at thecommencement of the Program. This is not yet the case and no substantial start has been made on theCapacity Development and Communication components to-date, though the corresponding specialistsare now mobilising. Further, work on Task 6 (Strategic Environment Assessment [SEA]) has begun andprogress has already been made on Task 7 (Preparation of Phase 2), in particular in respect of theselection of the best route for transferring water from Mahaweli Ganga to Moragahakanda Reservoir.The final decision on the route selection is a key pre-condition for proceeding with Phase 2 work, whichis intended to run in parallel with Phase 1 and to be completed within the first two years of the Program.Section 5 therefore describes progress with all Tasks and not only Tasks 1 to 5. It is considered importantto report on Tasks 6 and 7 at the inception stage in view of the activities already undertaken.Nevertheless, dedicated Inception Reports will be separately prepared for the SEA and for Phase 2 asforeseen in the ToR. During the ADB Inception Mission it was agreed that the Phase 2 Inception Reportand the Route Selection Report – due in Months 4 and 8, respectively – could be submitted simultaneouslyby Month 6. This is a rational change insofar as the Phase 2 work cannot be fully planned until the routeselection has been finalised.

40. Section 6 covers the Consultant’s proposals for proceeding, in particular where circumstanceshave changed from those foreseen when the ToR were issued. This section also describes changes topriorities that have been requested by the Client and the ADB, and the Consultant’s initial responses tothese requests. The report highlights implementation issues where action or decisions beyond the scopeof the Consultant’s ToR may be required to facilitate progress.

Page 16: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 8

2 INTRODUCTION

2.1 Mahaweli Water Security Investment Program

41. The Mahaweli Water Security Investment Program (MWSIP) is the final stage of the MahaweliDevelopment Plan (MDP), a multi-sector development of the water and land resources of the MahaweliGanga (River) Basin and North Central Province. This is the end point of an investment program that hasspanned more than six decades and been pivotal in meeting national development goals in foodsecurity, social development, energy production and environmental protection. The updated MDP willaddress the government’s sector priorities by constructing the North Central Province Canal Project(NCPCP), an outstanding investment component of MDP that is estimated to cost $1.64 billion. TheNCPCP will be implemented in two sequential phases: Phase 1 will transfer water from the MahaweliRiver Basin to existing reservoirs in the Central, North Central and North Western Provinces; and Phase2 will extend the transfer of water from the North Central Province reservoirs to existing reservoirs inthe Northern Province, and may eventually augment drinking water supplies to Jaffna and Kilinochchi.

42. The MWSIP will implement Phase 1 of the NCPCP. The principal objective of Phase 1 is to increaseagricultural production on approximately 33,000 ha of irrigated lands and to improve drinking watersupplies to households within the North West and North Central Provinces. This will be achieved throughinvestment in water infrastructure, transfer canals and reservoirs, and in capacity building ofstakeholders for improved water resource planning and management. The infrastructure will deliverapproximately 130 MCM per annum of water for irrigation of about 11,500 ha of systems in the NorthWest Province, and approximately 270 MCM per annum for irrigation of 12,400 ha of systems in NorthCentral Province, as well as supply of 100 MCM of drinking water. Productivity on about 7,500 ha ofirrigated lands in the Minipe System will also be improved. The storage capacity within the systems ofthe North West Province will be increased by about 26 MCM through the construction of two newstorage reservoirs.

43. Key elements of the program of Phase 1 include (refer to Figure 1):

• The Upper Elahera Canal Project (UECP), consisting of two elements: (i) the Kalu Ganga-Moragahakanda Transfer Canal (KMTC) for transfer of water from Kalu Ganga reservoir to theMoragahakanda Reservoir, and (ii) the Upper Elahera Canal (UEC) for transfer of water fromthe Moragahakanda Reservoir north to the existing Huruluwewa, Manankattiya, Eruwewaand Mahakanadarawa Reservoirs.

• The North West Province Canal Project (NWPCP), with 92 km of new and upgraded canals fortransfer of water from the Dambulu Oya River and existing Nalanda and WemedillaReservoirs, as well as two new earth dams at Mahakithula and Mahakirula.

• The Minipe Left Bank Canal Rehabilitation Project (MLBCRP), located in the downstream reachof the Mahaweli Ganga, with heightening of the existing concrete diversion weir (anicut) toadd upstream storage (needed to compensate for greater daily flow variations due to peakingoperation of the upstream power stations) and rehabilitation of regulating structures anddesilting of the main canal.

44. The MWSIP will also address other key sector priorities through two consulting packages: (i)improving system efficiencies and water productivity (ISEWP) with recommended investmentsconsidered for inclusion in the Program; and (ii) strengthening institutions with integrated waterresources management (SIWRM).

Page 17: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 9

Figure 1: Layout Map of the Mahaweli Water Security Investment Program

Page 18: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 10

45. The investment program will raise paddy production in 32,800 ha of existing command area byincreasing cropping intensities from 130% to 180% and yields from about 3 to 6 ton/ha. Additionalbenefits will arise from increased drainage return flows within the existing cascade systems thatdownstream communities will use. Once NCPCP Phase 2 is completed, the irrigated area commandedby the investment program will increase to 103,400 ha. Cropping intensities, yields and command areasmay be further increased through water use efficiency initiatives identified under the ISEWP package,which will also encourage diversification into less water consuming and higher value crops.

46. Phase 2 will extend the transfer of water to the North Central and North Provinces, with theextension of the transfer canals and transfer of an additional 700 MCM, to support drinking water supplyand irrigated agriculture. The key elements of Phase 2 comprise: (i) the Randenigala Kalu Ganga TransferCanal (RKTC) for transfer of water from the Randenigala Reservoir to the Kalu Ganga Reservoir (subjectto confirmed route selection); along with (ii) two new reservoirs and power stations (Upper Hasalakaand Heen Ganga); (iii) the Lower Uma Oya Reservoir and power station, for transfer of water to theRandenigala Reservoir; and (iv) the North Central Province Canal (NCPC) for transfer of water from theUEC to communities and command areas to the north. The investment in infrastructure will enabledelivery of approx. 700 MCM of water for domestic and irrigation use in the cascade systems of theNorth Central and North Provinces. It will on completion increase the total area full or partially suppliedfrom the Mahaweli Ganga from 146,000 ha to 233,000 ha. The storage capacity and installed capacitywithin the Mahaweli Development area will be increased by approximately 146 MCM and 30 MWrespectively, with the construction of three new reservoirs and hydropower stations.

2.2 Background to Water Resources in Sri Lanka

2.2.1 Mahaweli Ganga

47. The MWSIP is a large scale multi-faceted water resources program. As such it forms an integralpart of the MDP and an extension of existing investments in water infrastructure and irrigation systemsdevelopment. As outlined above the program is principally aimed at completion of the development ofinfrastructure for transfer of water to the northern dry zone. This section present a summary of thesignificance of water resources as part of sustainable development in Sri Lanka, and in particular the roleof the Mahaweli Ganga, progress to date on the MDP and preparation for the MWSIP.

48. While Sri Lanka has ample water resources with an annual per capita endowment (ACE) of 2,600cubic metres (m3), these resources are not well distributed in time and space due to topography andmonsoonal climate. The country is split between the ‘wet zone’ of the central and south west districts,which comprise about 25% of the area – but with 70% of the water resource – and the ‘dry zone’ of thenorth and east, with 30% of the water but more than 80% of the water demand2 (predominately forirrigated agriculture) as well as a significant and growing demand for drinking water.

49. In the northern dry zone districts3 ACE is 1,200 m3 and is predicted to decline to water scarcitylevels (less than 1,000 m3) by 2025 due to increasing demand for drinking water. There are also largeseasonal differences, with 80% of this resource being available in the Maha season4. The districts sufferfrom frequent droughts, especially in the Yala season, which severely impacts on irrigated agriculture

2 IWMI. 1999. Water Scarcity Variations within a Country: A Case Study of Sri Lanka. Research Report 32, Sri Lanka3 The districts include; Jaffna, Killinochchi, Trincomalle, Vuvaniya, Mullaitivu, Puttalam, Kurunegala, Anuradhapura4 In Sri Lanka there are two principal monsoonal periods, the South West Monsoon (Maha season) from December-February and the North East Monsoon (Yala season) from May-September.

Page 19: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 11

production (and therefore household food security and incomes) and drinking water supplies (impactingon public health).

50. In addition to water availability for consumptive uses, the geographical distribution of water is ofimportance for energy production. Some 40% of the country’s installed capacity is in hydropower, mostof which is in stations located within the ‘wet zone’. While the contribution to annual production hasdeclined in recent years due to increased production from thermal plants to meet rising demand, it isnevertheless a significant and strategic energy source, particularly during periods of peak demand. Theproportion of total energy provided by hydropower is less than the proportion of installed capacitybecause of the use of hydropower primarily for peaking.

51. Climate change is likely to increase the vulnerability of communities to water shortages due toincreased demand and decline in reliability of water sources. Rainfall in past years (1880 to 1970s) wascharacterised in addition to the seasonality (Maha and Yala monsoon seasons) by high annual variability,with alternate dry and wet periods as well as a general decline (MIWRM, 2010)5. Over the period 1931to 1990 the average annual rainfall is reported to have decreased from 2,005 mm to 1,861 mm, a declineof 7% (Jayatilake et al, 2005).6

52. While projections for annual rainfall trends differ between sources (with both increasing anddecreasing mean annual precipitation) there is general consensus that Maha (North East Monsoon)rainfall will decrease and Yala (South West Monsoon) rainfall will increase. This could further exacerbateshortages and reliability of water sources within the northern dry zone, and increase vulnerability ofcommunities to food shortages.

53. Historically (over several millennia) water availability for both drinking and irrigation wasimproved through development of surface water resources, construction of diversion structures, canalsand tanks (storage dams). There are estimated to be more than 30,000 tanks nationally. Over the pastfifty years the government has been proactive in promoting water storage and development programsfor multi-sector use for drinking water supply, power generation and irrigated agriculture.

2.2.2 Mahaweli Development Program prior to the MWSIP

54. The Mahaweli Ganga (River) is the largest river basin (of 103) in Sri Lanka, with a catchment areaof 10,300 km2 and annual average flow volume of 5,474 MCM (more than 10% of national annualrenewable water). The headwaters originate in the highlands of the wet zone, and the river flows to thenortheast. It represents a large and strategically important water resource, which is being developed tomeet the countries energy, water and food needs.

55. The MDP was initiated in the early 1960s with the objective of developing the water and landresources of Mahaweli River Basin and the dry zone areas of the northern provinces for irrigation andpower generation. The plan was ambitious and included multiple storage dams, hydropower stations,transfer canals and irrigation systems. The reliability of water availability from the Mahaweli River Basinfor the investment program is essential to assess under both current and future water demandconditions to determine supply reliability and impact of the projects on other existing and planned wateruses within the MDP. It is also potentially sensitive to climate change impacts, particularly in terms ofimpacts on water demand due to predicted temperature increases and changes to rainfall patterns.

5 Sri Lanka Water Development Report: 2010.6 Jayatillake, H.M., Chandrapala, L, Basnayake, B.R.S.B, Dharmaratne, G.H.P, (2005). Water Resources and Climate Change.Proceedings of the Workshop on Sri Lanka National Water Development Report, World Water Assessment Program, Paris.

Page 20: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 12

56. Figure 2 shows the principal features and declared areas of the MDP. To-date completed worksinclude the construction of the cascade of storage dams and power-stations on the Mahaweli Ganga,comprising Upper Kotmale, Kotmale, Victoria, Randenigala and Rantambe, with a combined storagevolume of about 1,800 MCM and combined installed capacity of 770 MW. The Nalanda and BowatennaDams have been constructed on the Amban Ganga (tributary of the Mahaweli Ganga), with a combinedstorage volume of 52 MCM and combined installed capacity of 40 MW. The works also includedconstruction of two diversion tunnels: Polgolla, diverting water from the Mahaweli to Amban Ganga,and Bowatenna diverting from the Amban Ganga to the Dambulu Oya. In addition, a further fourreservoirs and power stations are under construction: Upper Uma Oya (150 MW), Moragahakanda (25MW), and Morogalla (27 MW) for a combined installed capacity of 202 MW. The Kalu Ganga Dam, whichwill supplement water supplies to Moragahakanda, is also currently under construction. Kalu Ganga andMoragahakanda Reservoirs would also be on the route of water transfers from Mahaweli Ganga if thediversion following the Randenigala-Kalu Ganga Transfer Canal (RKTC) is selected during Phase 2 works(see also Sections 4.9.1 and 5.10).

57. The total irrigated area is currently about 161,000 ha in 14 systems, of which six are managed bythe Mahaweli Authority of Sri Lanka (MASL) with 62% of the irrigated area, and the other eight aremanaged by the Irrigation Department (ID).

58. Development to date has largely been focused within the Mahaweli Ganga Basin, both in termsof hydropower production and irrigated agriculture. What remains to be completed is the developmentof the land and water resources of the northern provinces, largely through water transfers. Some 1,000MCM of reliably renewable water resources can be transferred to the water-short north. This is theobjective of the final stage of the MDP and aims to complete fulfilment of the MDP goals.

2.3 Previous Studies, Surveys and Investigations

59. The NCPCP has been conceived by the government to serve the largest agricultural benefit areaunder the MDP. The original conception of the project encompassed the transfer of Mahaweli water tothe North Central and Northern Provinces through a canal taking off from the Moragahakanda Reservoirbuilt across Amban Ganga and augmented from the Bowatenna Reservoir. However, work wassuspended in the late 1970s due to limitations in financial and other resources. Subsequently, severalstudies were conducted to update the planning for the project and proposed alternative solutions,which could not be implemented due to financial constraints and the civil disturbances that prevailed inthe country from 1983 to 2009.

Construction of the Moragahakanda Reservoir and Kalu Ganga Reservoir commenced in 2012 and2014, respectively. Under the government’s policy framework of the “Mahinda Chinthana – Vision forthe Future”, the NCPCP was prioritized for implementation to address the urgent need for socio-eco-nomic development and increasing water demands in the dry zone. Subsequently, the Ministry ofIrrigation and Water Resources Management undertook a major Pre-feasibility study to assess theavailability of water resources in the Mahaweli and Amban River Basins and propose the optimumdiversion quantities and routes for the proposed development areas with minimum impacts on theexisting irrigation systems and environment. A number of other major studies and investigations werecarried during 2012 and 2013 (refer to Table 1).7

7 In addition, other major studies had been carried out in previous decades including the original UNDP Master Plan Study(1968), the NEDECO Implementation Strategy Study (1979), the Electrowatt Trans-basin Diversion Study (1980), and theJICA Trans-basin Study (1989).

Page 21: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 13

Figure 2: Mahaweli Declared Areas

Page 22: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 14

Table 1: Feasibility Studies done for the NCPCP (2012-2013)

No Contract Name Contract No. Submission

1Pre-feasibility Study for NCP Canal Project WaterResources Development Plan for NCP, NP andNWP (NCP Canal)

TS/NCP/P-FS/88 February 2012

2

Consultancy Services for Feasibility Studies andDetailed Design of Raising/Modifications toMinipe Anicut and Rehabilitation of Minipe LeftBank Canal

MIWRM/AGR/Consult/2011/23

March 2013

3

Consultancy Services on Modification toConfiguration of Moragahakanda – Kalu Ganga(M-K) Projects to Integrate NCP Canal ProjectLayout

MIWRM/AGR/Consult/2011/20

May 2013

4

Consultancy Services for Feasibility Studies forDiversion of Mahaweli Water to Upper Mi Oya &Hakwatuna Oya Basins in Kurunegala District viaExisting Bowatenna Tunnel

MIWRM/AGR/Consult/2011/24

October 2013

5

Consultancy Services for ComprehensiveHydrological / Water Balance Study andFinalization of Configuration of ProposedRandenigala – Kalu Ganga Transfer Canal Complexencompassing Hasalaka and Heen Ganga togetherwith Lower Uma Oya Complexes

MIWRM/AGR/Consult/2011/22

December 2013

60. The Pre-feasibility Study (2012) recommended seven sub-projects to revive the NCPCP of MDP asdetailed below. Each of these sub-projects has been the subject of further studies and investigations byrelevant government agencies.8

• Kalinganuwara Pumping Complex

• Randenigala – Kalu Ganga Transfer Canal

• Kalu Ganga - Moragahakanda Transfer Canal

• Upper Elahera Canal

• North Western Province Canal Project

• NCP Canal Development

• Lower Uma Oya Hydropower Project

• Hasalaka Oya and Heenganga Hydropower Projects

• System B Right Bank Development Project

• Minipe Anicut raising and rehabilitation of the Left Bank Main Canal

8 Feasibility studies and detailed designs for major projects go through a formal review process utilizing ad hoc TechnicalReview Committees (TRCs) comprising representatives from the MASL, ID and other relevant stakeholders or interestedparties. The TRCs will also be involved with the review and approval of all civil works packages in the MWSIP. Similarly,Technical Evaluation Committees (TECs) are responsible for review and approval of bid documents, and evaluate submittedbids to make recommendations for contract award.

Page 23: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 15

61. During April to December 2014, ADB supported a Project Preparatory Technical Assistance (PPTA)to conduct due diligence of Phase 1 of the NCPCP and prepare the investment program documents,comprising assessment of technical, economic, financial, governance, poverty, social, and safeguardsissues. The scope of the PPTA was to: (i) review the technical and economic viability and designs of thethree investment projects under the investment program; (ii) review and update safeguard measures;(iii) review civil works contract documents and advise government engineers to ensure they meetnecessary criteria; (iv) prepare the ISEWP consultancy package; (v) undertake financial and procurementassessments of the EA and IAs; and (vi) prepare all requirements to meet the processing criteria for theMFF and its first tranche. The activities under this PPTA led to the preparation of a program proposal inADB’s format for financing an investment program.9 In 2015 the investment program was approved byADB and the government.

62. During the PPTA detailed engineering designs and draft bid documents were prepared for threeadvanced contract packages.10 Feasibility-level designs were prepared for the other civil works packages.In addition, a large investigations program was carried out by the Geological Survey and Mines Bureau(GSMB), the GeoEngineering Consultancy, the Geology Department of the University of Peradeniya, andthe Central Engineering Consultancy Bureau (CECB). Investigations now being specified and tenderedare described in Section 4.4.1.

9 ADB. Water Resources Development Investment Program. Technical Assistance Consultant’s Report. December 2014.10 The three advance contract packages were the UEC-ICB-1, NWP-ICB-1 and MLBCR-ICB-1.

Page 24: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 16

3 IMPLEMENTATION ARRANGEMENTS

3.1 Investment Program

3.1.1 Multi-Tranche Financing Facility

63. The investment program will implement NCPCP Phase 1 using the Asian Development Bank’s(ADB’s) multi-tranche financing facility (MFF) modality, loaned to the government in three tranches.11

The MFF will comprise three tranches: (i) Tranche 1 will implement the MLBCR, NWPC Stage 1 andcertain non-tunnel segments of the UEC; (ii) Tranche 2 will implement the KMTC and the TBM tunnelsegment of the UEC; and (iii) Tranche 3 will implement NWPC Stage 2 and remaining tunnel and non-tunnel segments of the UEC. The number of tranches and projects, especially those after Tranche 1 areindicative and are subject to change. Procurement to be financed from the ADB loans under the MFFwill be strictly carried out in accordance with ADB’s Procurement Guidelines for goods, works, servicesand consultants (April 2015), as amended from time to time. To foster competition the ADB permitsbidders from all eligible countries to offer goods, works and service for all ADB-financed projects.12

64. The cost of the MWSIP is estimated at $675 million, including contingencies and financing charges.Tranche 1 was approved in 2015. Approval for the second tranche is scheduled for 2017 and approvalfor the third tranche is scheduled in 2018. 13

65. Bid documents will be prepared following ADB’s Standard Bid Documents (SBDs). Forprocurement of ICB contract packages the single stage two envelope bidding procedure with LargeWorks Conditions of Contract will be used. For procurement of NCB contract packages the single stagetwo envelope bidding procedure with Small Works Conditions of Contract will be used. Internationalcompetitive bidding (ICB) will be followed for civil work contracts costing $7.5 million or more in Tranche1. Civil works contracts costing less than $15 million will be procured through national competitivebidding (NCB) procedures acceptable to ADB. Numerous small service contracts or community works (tobe determined in consultation with project area community groups / civil society organizations andawarded as a community works contract) costing less than $20,000 each may be directly contracted.

66. Construction of Phase 2 of the NCPCP is not financed under this investment program, althoughthe PMDSC will be responsible for undertaking detailed feasibility and safeguards studies, and preparingthe necessary documents for ADB consideration for possible future financing.

3.1.2 Implementation Schedule

67. Implementation of the MFF is tentatively scheduled from 2015 to 2024. The MWSIP willimplement approximately 20 major works packages comprising civil works construction, in addition tothe ISEWP and SIWRM consultancy packages, in addition to training and capacity development ofgovernment officers and departments. These civil works packages will be constructed in stages undereach tranche of the investment program.

68. An updated Implementation Schedule is included in Annex A. An accelerated version of theschedule has also been prepared for discussion purposes wherein the construction of the KMTC is

11 Additional co-financers may be involved in Tranches 2 and 3.12 ADB. 2015. Procurement Guidelines. Manila.13 The government seeks to expedite completion of the NCPCP as soon as practical, particularly for the UECP and Phase 2investments. Throughout our services the PMDSC will recommend viable options for achieving these goals.

Page 25: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 17

moved forward to 2017-2019 from 2023-2024. The implementation schedule shows indicative timerequirements for each civil works packages as follows:

• Revision and finalization of tender documents 1 to 18 months

• Approval by the PMU and ADB 2-3 months

• Bidding and contract award 6-8 months

• Construction 24 to 60 months

• Defects liability period 12 months

69. Tendering for the first civil works package (MLCB-NCB-1) has been initiated in December 2015 andthe first construction is tentatively scheduled to begin by June 2016.

3.1.3 Program Outputs

70. The program outputs in Phase 1 are construction of new and improved water conveyance andstorage infrastructure, including:

• Upper Elahera Canal (UEC); construction of approximately 82 km of canal (including 28 km oftunnel) connecting the Moragahakanda Reservoir to the existing tanks of Huruluwewa,Manankattiya, Eruwewa and Mahakanadarawa. The Kalu Ganga – Moragahakanda TransferCanal (see below) is also a component of the UECP.

• Kalu Ganga – Moragahakanda Transfer Canal (KMTC); construction of approximately 9 kmtransfer of canal (including 8 km of tunnel) for the transfer of water between the Kalu Gangaand Moragahakanda reservoirs. Refer to Figure 3.

• North Western Province Canal (NWPC); construction of 96 km of new and upgraded canals(including 940 m of tunnel) for transfer of water from the Dambulu Oya River and the existingNalanda and Wemedilla reservoirs to the cascade irrigation systems and Mahakithula andMahakirula Reservoirs with a combined storage volume of approximately 26 MCM linked tothe NWPC. Refer to Figure 4.

• Minipe Anicut Heightening and Left Bank Canal Rehabilitation (MLBCR); the heightening ofthe Minipe diversion weir (downstream of the Rantambe dam) by approximately 3.5 m,construction of new intake gates to the Minipe Left Bank system, construction of emergencyside spillways on both the left and right bank system canals, and rehabilitation ofapproximately 74 km of the left bank system to improve conveyance and reliability of serviceto existing irrigated lands. Refer to Figure 5.

• Systems for improving water resources management and productivity developed.

• Multi-disciplinary investment program management operational.

Page 26: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 18

Figure 3: Kalu Ganga – Moragahakanda Transfer Canal and Upper Elahera Canal Project

Page 27: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 19Page

Figure 4: North West Province Canal Project

Page 28: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 20

Figure 5: Minipe Left Bank Canal Rehabilitation Project

Page 29: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 21Page

3.2 Organizational Setup

71. An organization chart of the program is shown in Figure 6.

Figure 6: Organizational Chart of the MWSIP

3.2.1 Implementation Agencies

72. The executing agency (EA) for the investment program is the Ministry of MahaweliDevelopment and Environment (MMDE) under which a Program Management Unit (PMU) has beenestablished to implement this investment program. The PMU is led by the Program Director (PD),Mr. Sisira Kumara, who is an Additional Secretary of MMDE. Under the Program Director are threeProject Implementation Units (PIUs), each led by a Project Director, one for each investment projectas follows: Mr. S.A.A. Dharmasiri, Project Director UECP (Madatugama); Mr. G.M.R.A. Perera, ProjectDirector NWPCP (Kurunegala); and Mr. S.D. Mediwaka, Project Director MLBCRP (Hasalaka). ThePMU will oversee the ISEWP and SIWRM consulting packages.

73. A Program Steering Committee (PSC) has been established to provide overall coordination ofthe investment program and facilitate inter-ministerial coordination. The PSC is chaired by theSecretary, MMDE, and the Program Director will be the PSC’s Secretary; all concerned ministries andagencies will be represented.

74. An independent review panel (IRP) is being recruited to review outputs from the PMDSC andother consultants, and provide advice to the PMU and ADB on technical and contractual matters.Experts will include tunnel, dam, and contract management specialists and a geologist.

75. At the completion of the investment program, the investments will be managed by the ID andthe MASL. It may be noted that PD UECP comes under MASL, while the other two PDs come underthe Irrigation Department.

Page 30: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 22Page

3.3 Program Management, Design and Supervision Consultant

3.3.1 Mobilization

76. The Joint Venture of Lahmeyer International GmbH – GeoConsult ZT GmbH, in associationwith Infotech IDEAS (Sri Lanka), Engineering Consultants (Pvt) Ltd (Sri Lanka), and NIRAS (Denmark)was appointed the Program Management Design and Supervision Consultant (PMDSC) in November2015. The contract documents were signed on 25 November 2015. The consultants commencedmobilising to Colombo on 1 December 2015.

3.3.2 Scope of Services

77. The PMDSC will be responsible for assisting the PMU to: (i) finalize designs for all packagesand the bid documents of the remaining contract packages to be awarded under Project 1, and allcontract packages of Project 2 and Project 3; (ii) procure, mobilize, and supervise all Contractors forall projects in Tranches) 1 to 3; (iii) recruit, mobilize, and manage the consultant for the ISEWPconsulting services package; (iv) finalise the ToR, and recruit and manage a consulting firm toundertake the SIWRM consulting services package; (v) manage and supervise all civil works contractsand act as the “Engineer”; (vi) prepare Phase 2 investments and necessary ADB financingdocuments; (vii) provide technical and management advice, as required; (viii) manage andadminister the investment program; and (ix) prepare draft periodic financing requests forsubsequent tranches, and routine reporting requirements of ADB. The PMDSC will also assist MMDEwith preparations, logistics and reporting for missions fielded by ADB and other co-financiers, asnecessary, throughout the investment program.

78. The PMDSC will initially support the PMU for a period of five years (60 months) and thecontract has signed for the same period. The Contract is a Time-based contract with a Lump Sumcomponent, having (i) a reimbursable Provisional Sums component, (ii) a reimbursable Contingencycomponent, and (iii) a reimbursable other expenses component for the Time-based component

3.3.2.1 Staffing

79. The PMDSC consists of over 100 international and national consultants comprising thefollowing staff:14

Lump Sum Part

International Key Experts 13International Non-key Experts 1

National Key Experts 12National Non-key Experts 8

Time-based Part15

International Key Experts 22International Non-key Experts 1

National Key Experts 28National Non-key Experts 46

14 Note some consultants are in positions in both the Lump Sum and Time-based part of the contract.15 Additional Key Experts are for the Time-based tasks as discussed in this Inception Report.

Page 31: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 23Page

3.3.2.2 PMDSC Deliverables

80. The PMDSC is responsible for providing project management and technical support to thePMU and PIUs for program implementation. The PMDSC deliverables comprise 7 major tasks andare summarised as follows:

• Task 1: Program Management including; project reports (inception, monthly, quarterly,mid-term and final), periodic reports, handbooks (procurement and financial), andspecific reports; MIS, PPMES, Environmental Monitoring, Resettlement, Monitoring andEvaluation, PCR and Special

• Task 2: Design Review, Detailed Designs and Preparing Contract Documents including;Hydraulic Structures Design Manual, and reports for Tender Design Review, SCADASystem, Detailed Design, MOM manuals and Tender Documents

• Task 3: Contract Management, Construction Supervision, Commissioning and Operationin addition to periodic reports (Shifts, Claims, Contract Completion, Weekly, Monthlyand Annual) contract reports and manuals for; Construction Supervision, Health andSafety and Technical Reviews

• Task 4: Capacity Development and Training Implementation including Training NeedsAssessment and Training Plan and Training Completion Report and assisting withimplementation of training programs

• Task 5: Communications including Communications Strategy and Plan, and knowledgeproducts including website, video presentations and publications and support forsafeguards

• Task 6: Preparing a Strategic Environmental Assessment (SEA) including reports forinception, interim and SEA

• Task 7: Preparation of Phase 2 including reports for Inception, Route Selection, Interim,and Feasibility Designs as well as PDA and ADB loan documents

3.4 Safeguards

81. All three investment projects have been categorized for safeguards and assessments preparedprior to ADB Board approval. The following safeguards documents were prepared during the PPTAfor the investment program as per ADB’s SPS and the government rules:

• Environmental Assessment and Review Framework (EARF)

• Initial Environmental Examination (IEE) for the MLBCRP

• Environmental Impact Assessment (EIA) for the UECP, NWPCP and MLBCRP

• EIA for the NWPC

• Resettlement Framework (RF)

• Resettlement Implementation Plan (RIP) for the UECP and NWPCP

3.4.1 Environmental

82. The NWPC and UEC are classified as Category A for environment and the MLBCR is classifiedas Category B in accordance with ADB’s Safeguards Policy Statement (2009). The necessarysafeguards requirements have been completed and submitted to the Central EnvironmentalAuthority (CEA) including the Environment Impact Assessments (EIAs) for the NWPC and UECP andan Initial Environmental Examination (IEE) for the MLBCR, all prepared during the PPTA. The MLBCRis unlikely to cause any significant environmental impacts. The current status of environmentalapprovals is shown in Table 8.

Page 32: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 24Page

83. The potential impacts, mitigation measures, and monitoring and reporting requirements arepresented in the environmental management plans (EMPs) prepared for each EIA/IEE. The EMPs setout specific environmental safeguards and mitigation measures to be incorporated into the biddocuments and define institutional responsibilities and associated cost estimates.

84. The EARF was prepared by the PPTA to guide the formulation of environmental safeguardsdocuments for future tranches according to the government and ADB’s policy requirements.

85. A safeguards cell is being established in the PMU. The safeguards cell will be responsible tooversee overall monitoring and verification of environment and resettlement activities of theinvestment program. Two counterpart personnel with relevant experience will be assigned to thesafeguards cell which will have responsibility for ensuring compliance of the safeguardsrequirements including (i) environment and (ii) resettlement including gender.

86. The Project Director of each PIU will assume primary responsibility for the environmentalassessment as well as implementation of EMPs for their respective components. An environmentalofficer will be assigned to the project teams under the Project Directors. The duties of theenvironmental officer will include: (i) oversight of construction contractors for monitoring andimplementing mitigation measures; (ii) preparing and implementing environment policy guidelinesand environmental good practices; (iii) liaising with the environmental agencies and seeking their helpto solve the environment-related issues of project implementation; (iv) providing awareness trainingon environmental and social issues related to the program and; (v) preparation of environmentalmonitoring reports every 6 months for EIAs and once a year for IEEs (as required by ADB).

87. In addition, the PIU environmental officer with assistance from the PMDSC’s EnvironmentalSpecialists will: (i) update the environmental assessments including the EMPs based on detaileddesigns; (ii) ensure EMPs are included in bid documents and civil works contracts; (iii) provideoversight on environmental management aspects of the project and ensure EMPs are implementedby the contractors; (iv) facilitate and ensure contractors comply with all government rules andregulations regarding permits as well as any other relevant approvals required for works; (v)supervise and provide guidance to the contractors to properly carry out implementation of theEMPs; (vi) review, monitor and evaluate the effectiveness with which the EMPs are implemented,and recommend necessary corrective actions to be taken as necessary; (vii) consolidate periodicenvironmental monitoring reports to ADB; (viii) ensure timely disclosure of final environmentalassessments in locations and forms accessible to the public; (ix) take corrective actions when necessaryto ensure no environmental impacts; (x) conduct ongoing consultation with the community duringimplementation of the project; and (xi) establish a grievance redress mechanism and ensure it isoperated satisfactorily.

88. The CEA requires that the detailed EMP prepared by the contractor, including proposedmitigatory actions for each of the identified project interventions, is submitted by the PMU forreview and approval by the Monitoring Committee. Prior to giving approval the CEA’s MonitoringCommittee will conduct a field visit(s) to the project area to confirm the identified mitigatorymeasures in the submitted EMP.

Page 33: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 25Page

3.4.2 Resettlement

89. The NWPC and UEC are both classified as Category B for involuntary resettlement.16

Resettlement implementation plans (RIPs) were prepared for each project to ensure that there areadequate social safeguards for person that shall be affected by permanent or temporary landacquisition including provisions for (i) replacement of assets or properties lost; (ii) rehabilitation ofaffected persons; and (iii) restoration of their incomes, or better, from pre-project level. The designand implementation of a robust and accessible grievance mechanism to be provided to the affectedpopulation is a key ADB requirement.

90. The PMU will have resettlement cell with a full time specialist who will assist the formulationof RIPs, resettlement due diligence reports and resettlement monitoring reports. The specialist(s)key activities include: (i) screening of proposed projects for potential resettlement impacts and risks;(ii) reviewing of project alternatives to avoid or minimize resettlement impacts; (iii) assessing socialimpacts of the project; (iii) formulating an appropriate strategy for public consultations andresettlement information disclosure; (iv) formulating RIPs with resettlement consultants; and (v)establishing GRM and monitoring of their effectiveness. While EA will be responsible for overallcoordination, planning, and financing of resettlement program, the implementation of RIPs is theresponsibility of PMU.

91. The PMU/PIU will monitor the RIPs implementation to determine whether resettlement goalshave been achieved and livelihood and living standards have been restored, and to recommend howto further improve implementation. For this, each Project will elaborate specific, relevant anddetailed monitoring indicators. The PMU/PIU will prepare half-yearly monitoring reports to submitto EA and ADB. The reports will focus on whether resettlement activities have complied with IRsafeguard principles and loan covenants of the project. The report will also document consultationsconducted with project affected persons (PAPs) and summaries of issues identified and actionstaken to resolve them. It will also provide a summary of grievances or complaints lodged by PAPsand actions taken to redress them and the specific activities conducted to restore and improveincome sources and livelihoods of PAPs.

92. A Resettlement Framework (RF) was prepared by the PPTA to serve to guide safeguardassessments and the preparation of relevant safeguards documents in all three projects.

3.5 Poverty and Social

93. The PPTA prepared a Poverty and Social Assessment (PSA) based on the findings of pre-feasibility socio-economic surveys, resettlement census, environmental field surveys, and academicstudies that have been conducted in the project areas in the recent past to examine opportunities,constraints, and potential social impacts of the proposed projects on affected communities. Thedesign and implementation of a robust and accessible grievance mechanism to be provided to theaffected population is a key ADB requirement.

94. ADB has identified some deficiencies in the existing PSA that will need to be addressed duringthe processing of the Periodic Financing Request (PFR) of Tranche 2.

16 UEC Tranche 1 is category “C” for resettlement as no land or persons will be affected by the 6.2 km length of canal tobe constructed during the first tranche. However, Tranche 1 investment costs will be sufficient for all resettlement activi-ties to be undertaken for the entire investment program.

Page 34: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 26Page

4 PROGRESS TO DATE

4.1 PMDSC Office and Logistics

95. On 1 December 2015 the PMDSC commenced operations from the temporary office facilitiesat MASL premises on Jawatte Road. Work commenced with gathering and reviewing available data,reports, and other information related to the MWSIP. Field visits to project sites were conducted inmid-December in conjunction with the PMU staff and Project Directors to assess prevailing siteconditions.

96. The consultants were relocated to the refurbished office at 493 T.B. Jayah Mawatha duringJanuary 2016 and continued with the review of designs and contract packages and preparation ofdeliverables for each Task. During the period from 1 December 2015 to 31 January 2016, the expertsdeployed comprised 22 personnel, including both national and international staff. Details are givenin Annex B.

4.2 Meetings

97. The PMDSC attended 13 meetings with the MMDE, ADB, CEA, Ceylon Electricity Board (CEB),line agencies and others, during the period from 1 December 2015 to 31 January 2016. Annex Cprovides the minutes of meetings.

98. Client: At the commencement of the assignment, an initial meeting was held with the Clienton the 2 December 2015 followed by 3 fortnightly progress review meetings, and a post-site visitmeeting. In these meetings the prevailing site status and measures to overcome constraints werediscussed.

99. ADB: Two discussions were held with the Sri Lanka Resident Mission (SLRM) with ADB staff.The first discussion was on ADB contractual procedures and guidelines, and environmentalassessment and clearances. The second meeting covered procurement procedures, includingqualification of bidders, evaluation period, work program, bonds and securities, evaluation criteriaand selection of bidders.

100. Others: The Consultants participated in two meetings with CEA for clarification of theproposals for NWPC and UEC. Clarifications included explanation of (i) measures to mitigate impactson flora and fauna along the canal reaches through forest and wildlife reserves and on thegroundwater table; (ii) encroachments into reserves; (iii) reforestation of denuded reserves; and (iv)the measures to minimise human-elephant conflicts.

101. Representatives of the PMDSC participated in the Pre-Bid Meeting for MLBCR–NCB-1 packagefrom 0+00 to 30+00 km and assisted the PMU with the clarification of bid documents and withtechnical clarifications during the site visits.

102. PMDSC specialists held a series of discussions with the officials of the Water ManagementSecretariat (WMS), ID, MASL, Meteorological Department and CEB aimed at understanding thestrategies of these institutions and collection of data needed for modelling aspects of the Program.

4.3 Task 1 – Program Management

4.3.1 Program Inception

103. Initial mobilisation at the beginning of December 2015 was followed by introductory meetingswith the PMU, MMDE and ADB, and setting up an organisational structure for the PMDSC. Planningof early staffing and setting up administrative systems was partially handicapped for the initial weeksby having to shift to a temporary office setting, as work on completion of the permanent PMDSC

Page 35: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 27Page

office had been constrained during and immediately following the recent change of government.The permanent office for the PMDSC was made available during January 2016.

4.3.2 Reconnaissance

104. During the initial weeks after mobilisation of the first staff, reconnaissance visits were madeto various parts of the Program area. During the first reconnaissance, areas under Projects 1 to 3 inMLBCR, UEC and NWP were visited. Subsequently, Kotmale and Upper Kotmale Dams, PolgollaDiversion, Polgolla Tunnel and the Sudu Ganga to Bowatenna were visited to assess conditions inconnection with the Route Selection Report to be prepared as part of the Phase 2 feasibility studyactivities under Task 7.

4.3.3 Continuous GIS Update

105. The Geographic Information System (GIS) put in place by the Mahaweli Consultancy Bureau(MCB) during the PPTA is being updated continuously based on information from reconnaissancevisits and updates from recent surveys and tender document preparation.

4.3.4 Terms of Reference for Improving System Efficiency and Water Productivity(ISEWP)

106. The PMDSC has updated the ToR for the consultancy package “Improving System Efficienciesand Water Productivity” (ISEWP), the aim of which is to increase water availability to serve anexpanded MDP by maximizing system efficiencies and water productivity. The scope of the ISEWPpackage includes measures to (i) improve water use efficiencies by reducing conveyance losses andimproving distribution system controls; (ii) improve cascade system water management andscheduling to reduce percolation and drainage losses; (iii) improve on-farm application efficienciesthrough changes to on-farm management practices including irrigation scheduling; and (iv) reducewater demands with changes to cropping regimes and adoption higher value crops.

107. The updated ToR will be submitted to the PMU in March-April 2016.

4.3.5 Program Fund Disbursement Handbook

108. At the request of ADB and the PMU during the inception mission, the Financial ManagementSpecialist will prepare a Program Fund Disbursement Handbook. This handbook will serve as a guidefor the staff of the PMU and PIUs in designing and operating an efficient disbursement mechanismto support implementation of the MWSIP. An amended ToR is included in Annex H to include thisadditional task.

4.4 Task 2 – Design Review, Detailed Designs and Preparing ContractDocuments

4.4.1 Preparation of Tenders for Additional Surveys and Investigations

109. The technical specifications and BoQs for additional investigations to support the final designsof the NWPC-ICB1, in particular the investigations regarding dam foundation and borrow areamaterial for the Mahakithula and Mahakirula Dams was finalised and the associated works weretendered on 21 January 2016. Invitations to bid for the additional investigations for the design ofthe KMTC-ICB-1 were issued on 28 January 2016. The investigations for UEC-ICB2 are currently underpreparation. Further details about the status of additional surveys and investigations are given inTable 2.

110. The data requirements for the geotechnical designs are outlined in Annex E.

Page 36: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 28Page

Table 2: Status of Additional Geotechnical Investigations (12 February 2016)

111. Investigations for the 3 existing dams that will function as level crossings along the UEC(Kongetiya, Bogahawewa, and Madthewa) and the requirements associated with raising ormodifying them are not yet defined. Additional investigations were recommended by the PPTA in

Project /

PackageLocation Type of Investigation Institute

Status of

Completion

[%]

Borehole (1)

Auger Holes (23)

Test Pits (9)

Field Tests & Sampling

Borehole (1)

Auger Holes (32)

Test Pits (20)

Field Tests & Sampling

Auger Holes (7)

Test Pits (2)

Field Tests & Sampling

Test Pit (1)

Sampling

Auger Holes (22)

Test Pits (8)

Sampling

Standard Soil Testing

Direct Shear Tests

Triaxial Tests

Permeability Tests

Dispersivity Tests

Mahadambe Dam not yet defined

Pothuwilla Dam not yet defined

NWPC-

ICB2

Canal/

Tunnel Tracenot yet defined

Aqueduct 1 Boreholes (3)

Boreholes (6)

Seismic Refraction Survey

Aqueduct 2 Boreholes (3)

Tunnel 2 Boreholes (2)

Laboratory Rock Mechanics Testing

UEC-

ICB1

Kongetiya Level

Crossingnot yet defined

Boreholes (4)

Auger Holes (3?)

Test Pits (4?)

Field Permeability

Seismic Refraction Survey

Tunnel 3 Trace Boreholes (?)

Soil Testing

Rock Mechanics Testing

UEC-

ICB3 - 5

Canal/

Level Crossingsnot yet defined

NWPC-

NCB2 - 6

(Stage 2)

Canal Alignment not yet defined

Mahakirula Dam &

Borrow Area

Mahadambe

Borrow Area

Nebada Pokuna

Tank

Tender for investigations

issued on 21.01.2016

Contractor's Quotation

received on 03.02.2016

Remarks

Laboratory

Hakawatuna Oya

Reservoir

Mahakithula Dam

& Borrow Area

NWPC-

ICB1

Investigations for Check of

Dam Stability

Investigations for an approx.

200m long tunnel (design

change)

Investigations for several

level crossings (heightening

of dams)

Investigations for canal

alignment

Investigations for Dam

Heightening, Leakage of Dam

KMTC-

ICB1

Tunnel 1Tender for investigations

issued on 28.01.2016

UEC-

ICB2

Tunnel 3 Outlet Under preparation

Will be finalised following

GeoConsult input

Laboratory

Investigations for dam

heightening

Page 37: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 29Page

October 2015 at the partially constructed Kongetiya Level Crossing.17 If these dams are to beincluded in the scope of work of PMDSC (see also Section 5.6), additional investigations will need tobe carried out with the aim of establishing the current stability as well as the design of anystabilisation measures to be included in the Program in addition to the foreseen heightening of theexisting dams where required.

4.4.2 Designs

112. Since Program commencement in December 2015, a series of internal meetings amongnational and international PMDSC staff has been held, which addressed topics on potential designoptimization related to the following packages:

• MLBCR-ICB-01

• NWPC-ICB-01

• NWPC-NCB-01

• NWPC-NCB-06

• UEC-ICB-01

• UEC-ICB-02

• KMTC-ICB-01

113. Separate meetings focussed on potential refinement of the hydraulic design of the UEC.Subsequent to these meetings, additional hydraulic calculations have been conducted by the PMDSCto verify the canal’s discharge capacity under conditions of increased roughness of the concretelining surface, for instance caused by aging, and more conservative local minor losses, for instanceat partially clogged trash racks. Although these calculations are not yet finalised concerning theextent of segmented lining in UEC Tunnel 3 (i.e., the TBM tunnel), which is still being investigated,they indicate that the invert of the UEC should be raised at Moragahakanda Dam by 1.5 m in orderto safeguard water supply at design discharge to Huruluwewa Reservoir, and towards to the NCPC.These calculations and recommendations have been included in the PMDSC’s Special Report No. 1,which was submitted to the PMU on 9 February 2016. The PMU is now requested to contact the PD(Moragahakanda), who should then coordinate with SinoHydro, the contractor constructingMoragahakanda Dam, the necessary modifications in the area of the spillway stilling basin. Noinformation has been received on the model testing recommended in October 2015.

4.4.3 Tunnel Optimisation

114. One of the technical meetings was dedicated to Mahakithula Inlet Tunnel (Package NWPC-ICB-01), where optimisation options were discussed in detail, with reference to BoQ Section 3.2.4on “Tunnelling by Drill & Blast Method” and related drawings.

115. It was seen on the drawings related to tunnel excavation and rock support that there is a largenumber of rock classes. Instead of the currently envisaged 8 classes, 5 classes are normally sufficientfor the rock conditions assumed to be encountered. Fewer rock classes will simplify procedures onsite and reduce the risk of mistakes when selecting rock support items for application inside thetunnel.

116. Another identified issue relates to the cast concrete lining in the area of the water passage ofthe tunnel, as currently designed. This lining is considered dispensable since the discharge ismoderate and the tunnel profile with 4.40 m width and height is rather small. Hence, slightly

17 Recommended field investigations include 3 boreholes on the centreline of the embankment spaced at the locationsstn. 0+360, 0+560, 1+170, with depths of 10 m, 6 m and 15 m, respectively, and standard penetration tests (SPT) andpercolation tests (on undisturbed samples) should be carried out in order to properly assess the geotechnical conditionsof the existing embankment. These investigations have not been carried out to date.

Page 38: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 30Page

enlarging the profile to compensate for the increased roughness of the unlined tunnel walls will notlead to significant additional costs, while a considerable saving is gained by omitting the lining andby shortening the construction period.

117. The increased profile will also improve conditions during construction of the tunnel, mainlywith respect to the operation of machinery and vehicles and installation of ventilation ducts in thetunnel roof. If the profile is designed for a flow velocity in the order of 1.5 m/s, erosion will not occurin good rock conditions. Weak rock would require a shotcrete lining in the area of the tunnel walls,which is easily implemented with the shotcrete equipment being available already. The tunnel invertwould still be designed with a cast concrete slab to reduce hydraulic losses and to facilitate tunnelmaintenance. However, in contrast to the current design the invert slab would remain unreinforced.

118. Following the design approach outlined above, the BoQ can be simplified by deleting the itemsrelated to formwork and reinforcement. It is intended that shotcrete would be reinforced with steelfibres, which is quicker and easier to use than the presently envisaged welded fabric mats.

119. Omission of the concrete lining should be considered for the tunnels on the KMTC, as a costsaving measure, where the design discharge is much higher than for the NWPC, but where sufficienthead is available. Under these conditions a slight increase of the tunnel gradient would be preferred,rather than an enlargement of the tunnel profile. Moreover, application of a so-called “horseshoe”excavation profile with inclined side walls (i.e., conical towards the invert – see Figure 7) instead ofthe “D-shaped” excavation with vertical walls as currently shown on the drawings is recommendedfor unlined drill and blast tunnels with a diameter of more than 5 m. The invert width should not beless than 4 m. Measurement facilities also need to be incorporated in KMTC.

Figure 7: Typical Horseshoe Tunnel Profile

Page 39: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 31Page

120. Horseshoe profiles are advantageous compared with D-shaped profiles because they reducestress concentrations in the rock around the lower corners and the entire profile, which potentiallyreduces rock support requirements (quantities) in poor rock conditions. This is of particular importancefor tunnels with high overburden, i.e., high in-situ rock stresses.

121. The ToR for the Rock Mechanics Engineer and Senior Mechanical Engineer (TBM) have beenrevised as proposed in Annex H to properly reflect the responsibility of the Consultant and theContractor(s), such as preparing method statements for the use of explosives.

4.4.4 Commencement of Tender Design Review

122. Design review has commenced for most of the civil works packages, including:

(i) MLBCR-ICB-01: Heightening of Minipe Anicut including Water Control & MeasurementFacilities for Left Bank & Right Bank Canals

(ii) MLBCR-NCB-01: Rehabilitation of Minipe LBC, Stage 1 from 0+000 km to 30+140 km

(iii) MLBCR-NCB-02: Rehabilitation of Minipe LBC, Stage 2 from 30+140 km to 49+820 km

(iv) MLBCR-NCB-03: Rehabilitation of Minipe LBC, Stage 3 from 49+820 km to 63+650 km

(v) MLBCR-NCB-04: Rehabilitation of Minipe LBC, Stage 4 from 63+650 km to 73+960 km

(vi) NWPC-ICB-01: Construction of Mahakithula Inlet Tunnel, Mahakithula & MahakirulaReservoirs, Feeder Canal of Length 3.66 km from Mahakithula to Mahakirula Reservoir

(vii) NWPC-NCB-01: Improvements to Wemedilla LB Main Canal up to Nebadagahawattafrom 0+000 km to 5+250 km

(viii) NWPC-NCB-06: Main Canal from Dambulu Oya to Wemedilla

(ix) UEC-ICB-01: Construction of Upper Elahera Canal from 0+000 km to 6+226 km

(x) KMTC-ICB-01: Kalu Ganga - Moragahakanda Transfer Canal

123. Packages (ii), (vi) and (ix) have already obtained conditional approval from ADB and will beincluded in the Tender Design Review Report (TDRR), which is currently under preparation. Allsubsequent packages will be reviewed and then completed, and will not form part of the TDRR. Themost important topics identified in the course of the tender design review are listed below.

124. It is noted that the ToR indicated the status of design preparation for three of the Project 1packages was “Advanced,”18 and further, that feasibility-level designs were prepared for the packagescomprising Projects 2 and 3. As explained in the technical proposal for Task 2, the PMDSC logicallyexpected that the advanced status of the Project 1 packages meant that the detailed designs that hadbeen prepared by MMDE would therefore be construction-ready, except for marginal improvementsand enhancements to be identified in the TDRR. The PMDSC prepared their work plan on the basisthat the available feasibility-level designs for Projects 2 and 3 would not have substantial criticalerrors or deficiencies that would preclude the preparation of the detailed engineering designs andcontract packages without extensive re-designing. It is noted that bidders were invited to inspectthe status of the bid packages during preparation of the PMDSC proposal, and our staff didparticipate in the pre-bid meeting and site inspections of project sites. Design work and finalizationof the Tranche 1 packages continued after the bidding period for the PMDSC. It was confirmed bythe PMU during contract negotiations that the Detailed Design Report, bid documents and tenderdrawings for the Tranche 1 packages were 100% completed. In fact, the status of preparation forthe designs and bid documents for some packages have not met these criteria. This has significantimplications for the level of additional resources that will be required by the PMDSC for Tasks1, 2and 3 compared to duration of activities planned for finalization of the bid documents.

18 According to Table 2 in the RfP “Advanced” means the detailed engineering designs are near completion, tenderdocuments have been prepared, and the tendering process is underway.

Page 40: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 32Page

4.4.4.1 Package MLBCR-ICB-01

125. At Minipe Anicut, a new silt ejector will be designed in the centre of the anicut. Access to theejector for operation (opening and closing of the gate) and maintenance was foreseen by boat fromthe upstream side. Since access by boat is considered unsafe for the operations personnel, an accesswalkway (“passerelle”) will be introduced, leading from the left bank retaining wall to the silt ejector.The walkway will be arranged as a cantilever on the vertical upstream face of the heightened weir,sufficiently deep to prevent undue hydraulic interference with weir overflow. The walkway will be80 cm wide and will be protected on the reservoir side by a 1 m high wall.

4.4.4.2 Package UEC-ICB-01

126. One important issue identified is modification of the design of the first reach of the UECdownstream of the Moragahakanda Dam. It will be necessary to eliminate the risk of overtopping ofthe river banks into the canal during floods, and to ease space constraints for access roads and powerlines. Subsequent to a site meeting held on 8 December with PD Moragahakanda, modificationswere proposed to the initial reach of UEC to resolve the site issues. This will be achieved by a newcut-and-cover section of the canal between chainages 0+100 km and 0+592 km. To control theinflow into this canal section, a head regulator (currently not foreseen) will be designed.

127. As noted in Section 4, Section 4.4.2, modifications will be needed to the stilling basindownstream of the Moragahakanda UEC outlet in order to assure maximum head availability forconveying UEC water to the NCPC. The stilling basin is not in the scope of the PMDSC and closecoordination will be needed with the PD Moragahakanda about interface issues.

4.4.4.3 Package UEC-ICB-02

128. The final position of the outlet portal of Tunnel 3 (i.e., the TBM tunnel) is presently underdiscussion. It would be desirable to prolong the tunnel and to shift the portal downstream, towardsthe north, to avoid paddy fields in the area of the deep construction pit for the TBM. However, theresults of geoelectric soundings conducted in August 2015 are rather unfavourable in the area of theextended tunnel and the construction pit. Currently, a small-scale geotechnical investigationprogram has been initiated to confirm the results of the geoelectric soundings. The final location ofthe portal will be fixed depending on the results of the new investigations.

129. As indicated in Section 4.4.2, the type and extent of tunnel lining is not yet confirmed forTunnel 3. Being a very long tunnel with rather low rock cover, a number of partly contradictoryfactors play a role in the definition of the tunnel lining, these are

• TBM design and construction aspects

• Geological, hydro-geological and geotechnical boundary conditions

• Material handling aspects

• Civil design and hydraulic issues

• Environmental impacts, mainly with regard to minimising adverse impacts for residentsliving above or close to the tunnel alignment

• Economic aspects

130. From an engineering point of view, a segmental lining installed by the TBM would in manyrespects represent the safest solution. The PMDSC’s tunnel engineers are scheduled to arrive in SriLanka shortly and dealing with this subject will be one of their main tasks.

Page 41: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 33Page

4.4.4.4 Package NWPC-ICB-01

131. Several modifications have been identified to optimise the layout of this package. Theseinclude adjustments to the alignment of the Mahakithula Dam and the irrigation outlets onMahakithula and Mahakirula Dams.

132. Alignment of the Dam Axis of Mahakithula Main Dam. The axis alignment of the long southeastsection of the main dam is considered unfavourable in the area of the left abutment, where itconnects to the topography at an acute angle, forming a small, almost isolated pond in the reservoir.Slightly rotating the dam axis with a centre at the right abutment (i.e., at the hill between both damsections) towards the north will shorten the dam axis and allow better connection of the dam to thetopography and also better approach flow conditions to the spillway, which is located in this area.This rearrangement of the dam axis requires a modification of the alignment of the Inlet Canal toMahakithula in the area between the tunnel outlet portal and the reservoir, in order to shift thecanal entrance away from the dam. Further optimisations of the dam axis are being investigatedcurrently, which may even avoid the intermediate hill.

133. Arrangement of irrigation outlet crossing Mahakithula Main Dam. Currently the irrigationoutlet is designed in the short northwest section of the main dam at chainage 1+800 km and at sillel. 188.00 masl. This layout of the irrigation outlet sluice requires:

• The downstream canal to have a number of drops to connect it to the natural streamleading to Pothuwila Reservoir

• An additional short canal section to connect it to the natural stream leading towardsHakwatuna Oya Reservoir

134. If the outlet is shifted by 400 m to chainage 1+400 km (i.e., into the long southeast section ofthe main dam, close to its right abutment) and the sill level lowered by 6 m to el. 182.00 masl, thedrops and the extra canal section could be omitted.

135. Arrangement of Irrigation Outlet crossing Mahakirula Dam. The right bank irrigation outlet(located at the right dam abutment) to Galgiriyawa is currently designed with a sill level of 170.00masl. It may be lowered by 8 m to el. 162.0 masl. With this arrangement, the sluice can be used alsofor river diversion during dam construction. Moreover, the currently designed bottom outletcrossing the dam would become redundant and could be omitted.

136. The alignment of the first metres of the canal (d/s of the RB irrigation outlet) will be shiftedsouth, i.e., closer to the river, to avoid a forested area in the wildlife reserve.

4.4.4.5 Package NWPC-ICB-02

137. Potentially beneficial modifications have been identified to optimise the canal alignmentbetween Wemedilla and Mahakithula Inlet Tunnel.

• Ch. 8+900 km to 9+300 km: Replace open canal by tunnel and cut and cover canal

• Ch. 14+000 km: Replace aqueduct by a short tunnel cutting through the rock ridge

• Ch. 17+500 km: Shift canal southwards to saddle to avoid high fill and to avoid GalapithaWewa

138. These refinements will be further investigated and implemented if benefits are confirmed andthe changes are practicable.

Page 42: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 34Page

4.4.4.6 NWPC-NCB-06

139. A comment was received from CEA regarding river diversion not being considered properly inthe design of Dambulu Oya Diversion Weir. In consequence of this justified comment, the weirstructure (currently located in the river bed) will be shifted laterally by about 25 m to be located onthe left bank of Dambulu Oya, where it can be constructed in dry conditions while river flow remainsundisturbed. After completion of the weir structure, upstream and downstream connecting canalswill be excavated and river flow will be taken through the structure. Subsequently, the Dambulu Oyawill be closed with a permanent dam. An additional drawing will be provided to demonstrate thedesign and sequence of the river diversion. The new position of the weir structure is alsoadvantageous in terms of straightening the river course and thereby improving approach flowconditions to the weir.

4.4.4.7 KMTC

140. A bench flume is currently foreseen just upstream of Aqueduct No. 1, at Chainage 0+800 km.It is located in a curved canal section, which is not favourable in terms of measuring accuracy. Thebench flume will be replaced by a broad crested weir, which will be shifted about 100 m upstream,where the canal is almost straight.

141. The feasibility design of the KMTC includes reinforced concrete walls and a slab floor. Thedesign will be reviewed to determine whether the wall thickness can be reduced or replaced withshotcrete, depending on rock support requirements.

4.5 Task 3 – Contract Management, Construction Supervision,Commissioning and Operation

4.5.1 Tenders Floated

142. At the time of writing the only package for which bids have been invited is MLBCR-NCB-1,which is for the rehabilitation of the first 30 km reach of the Minipe Left Bank Canal.

4.5.2 Imminent Tenders

143. The next packages for which bids will be invited are those for a section of the canal system inNWPCP, NWP-NCB-1, and for the first reach of the main UEC north of Moragahakanda, UEC-ICB-1.

4.6 Task 4 - Capacity Development and Training Implementation

144. The PMDSC formal inputs for this task had not yet commenced at time of writing, but thenational and international institutional strengthening specialists were brought into contact with oneanother remotely to map out an initial approach to their work. The proposed approach is presentedin Section 5.7.

4.7 Task 5 – Communications

145. Similarly to Task 4, formal inputs had not yet commenced at the time of writing butnational/international communications specialists were introduced to one another and haveexchanged views on an appropriate approach. The result is put forward in Section 5.8.

4.8 Task 6 – Preparing a Strategic Environment Assessment (SEA)

146. Work on this task has just commenced at time of writing. Early contact was arranged betweenthe environmental specialists responsible for the SEA and the Environmental Specialist in the

Page 43: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 35Page

Resident Mission of the ADB in Colombo. A preliminary note on the strategy to be adopted is shownin Section 5.9.

4.9 Task 7 - Preparation of Phase 2

4.9.1 Route Selection

147. The ToR require the PMDSC to review two route options before selecting the preferred routein consultation with the PMU, and then preparing the designs for the associated investments tofeasibility level. The two options are described in the ToR as follows:

• Option 1 will transfer water from the Randenigala Reservoir to the Kalu Ganga Reservoirvia the planned Randenigala – Kalu Ganga Transfer Canal (RKTC) that will comprise a 40km long series of open canals and tunnels. This includes two new reservoirs located alongthe RKTC route at the Hasalaka and Heenganga Rivers. The Hasalaka Reservoir will have a70 m tall RCC dam and 28-MW HPP, and the Heenganga Reservoir will have an 80-m talldam and 5.5-MW HPP. Other associated infrastructure is also included such as accessroads and power transmission lines, etc.

• Option 2 will transfer water from Polgolla Barrage to the Moragahakanda Reservoir via anew tunnel and enlarged tailrace canal to the Bowatenna Reservoir. This option alsoincludes the heightening of the Kothmale Reservoir by 25 m to increase system storage.The existing facilities at the Polgolla Barrage and Bowatenna Reservoir will also requireupgrading to manage the increase in flows.

148. Progress to date has included initiation of a review of literature of the options, as presentedin previous studies, most notably as part of the World Bank Dam Safety and Water Resources MasterPlan, which included a report19 on route options for water transfers to the north as part of anupdated of the Mahaweli Development Plan.

149. Prior to the preparation of the PPTA, the ARSP water balance model (see Section 5.11) wasused to determine transfer volumes, supply reliability and energy production. However, this workwas confined to the Option 1 route, therefore during the current inception phase work has beeninitiated on modelling of the Option 2 route within the context of the MWSIP objectives, i.e., to meetthe required levels and reliability of water transfers and sustained energy production.

150. This water balance simulation work is ongoing. To-date five scenario simulations have beenprepared, based on the same time series as used for the earlier modelling work. The scenarioscomprise different combinations of the two key infrastructure improvements, heightening ofKotmale Dam to increase storage volume and a second Polgolla Tunnel to increase transfer flowrate, which may have different outcomes in supply volume and reliability.

151. The simulations to be analysed are:

• Run 31A: existing Kotmale Dam and existing Polgolla Tunnel

• Run 32A: heightened Kotmale Dam and existing Polgolla Tunnel

• Run 33A: heightened Kotmale Dam and second Polgolla Tunnel

• Run 34A: existing Kotmale Dam and second Polgolla Tunnel

• Run 35A: heightened Kotmale Dam, second Polgolla Tunnel, and the proposedexpansion of the Victoria installed capacity by 210 MW (for peaking generation)

19 Updated Mahaweli Water Resources Master Plan, Dam Safety Water Resources Planning Project, Multi Sector Water Resources

Planning Component 3, prepared for Ministry of Irrigation and Water Resources Management by SMEC International, Nov 2013.

Page 44: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 36Page

152. The initial results show that Option 2 is unfavourable for the following reasons:

• Supply reliability is below critical threshold levels for all scenarios and in Yala season therewould be frequent ‘supply failures’.

• There would be low average annual water levels in the reservoirs on the Mahaweli Gangadownstream of Polgolla, Victoria and Randenigala, which would impact on energy production.

• Peaking operation of Kotmale Power station would be limited to three hours.

• Peaking operation of Victoria (with the expansion) would be limited to three hours.

• There would be a need for increased duty and annual volume of the Kalinga-Nuwara PumpStation to compensate for additional diversion from the Amban Ganga (to the UEC).

153. In summary, the preliminary results obtained to date indicate that the Option 2 route isunlikely to be meet the equivalent supply reliability (of the Option 1 route) for the transfer watervolumes for the program irrigated areas and drinking water supply. If this route were found for otherreasons (social, environmental or financial) to be strongly preferred by MMDE and other stakeholders,consideration would need to be given to a reduction of the command area and levels of drinking watersupply to ensure supply can reliably meet demand. However, this would comprise a significant changeto the MWSIP objectives and would require the PMU, ADB and government approvals. It is to be notedthat the results are preliminary and work is continuing on scenario modelling.

4.9.2 Modelling

154. Section 5.11 describes the proposed general approach to model development. This currentsection describes progress made to date. The first step in the baseline assessment was to meet witheach authority able to provide substantial data input. A template list was set up and sent to eachauthority after an initial meeting to facilitate collection of data availability. Related activities to dateare summarised in Table 2.

Table 3: Initial Meetings with Authorities

AuthorityInitial Meeting and

RequestReceipt of Data Availability

List

Water Management Secretariat(WMS), Mahaweli Authority

19 Jan 2016

Hydrology DivisionDepartment of Irrigation

21 Jan 2016 25 Jan 2016 (discharge)

Water Management DivisionDepartment of Irrigation

21 Jan 2016

Data Archives DivisionDepartment of Meteorology

21 Jan 2016 21 Jan 2016

Agrometeorological DivisionDepartment of Meteorology

21 Jan 2016

Mahaweli Hydropower ComplexCeylon Electricity Board

28 Jan 2016

155. In terms of current water management strategies, initial discussions revealed the following:

• WMS and CEB consider daily time-step as more appropriate for water balance and allocationmodelling, as short-term decisions or events should reflected in the model, to the extentpossible. For special purposes, i.e., flood management for WMS and hydropower peaking forCEB, an even shorter time step, i.e., hourly, may be introduced. However, both agree that thistime step is not required for mid-term (seasonal) and short-term (weekly) planning, which isthe main purpose of the water management and allocation model.

Page 45: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 37Page

• Present spatial resolution is deemed sufficient and adequate to understand and analysesystem behaviour.

• WMS reported that there is no added benefit in knowing precise water levels and flowvelocities at specific locations (e.g., river, channels, and secondary branches) within thesystem. Thus, a high-resolution hydraulic model does not seem required, in part due to theenormous amount of field data needed to set up and calibrate such model (see also Section5.10).

• The irrigation demand model needs the capability to consider different cultivation periods/pattern for individual crops, including staggering.

• WMS would like to have remote monitoring capability for displaying real-time systemconditions, but not necessarily for system operation.

• Forecasting capabilities would be useful.

156. A further meeting was arranged with WMS on 27 January 2016 to focus on the existing modelsand modelling needs. WMS has noted that the present Mike-Customised model is not in a conditionthat allows for application, and it is not clear whether there is additional efforts within the damsafety planning project to rectify these deficits, which include:

• The irrigation demands cannot adequately be determined.

• The rainfall-runoff model is encapsulated in the model without stand-alone capability, andtherefore does not allow for flexible application (e.g. forecasting) or verification ofperformance.

• The spatial extent of the model is fixed to the present extent of the applied Acres ARSPmodel and present known developments (e.g., Moragahakanda, Kalu Ganga, KMTC). Thus,any new structures cannot be integrated, and adjustments to the existing setup are alsolimited, if possible at all.

157. Further meetings with WMS may become necessary to ensure that formulated needs are metand development of the models is in line with WMS expectations (WMS being the responsible bodyfor water management and allocation planning), and also with the other major stakeholder, CEB.

Page 46: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 38Page

5 DETAILED WORKPLAN, ACTIVITIES, STAFFING AND TASKS

5.1 Current Status

158. The PMDSC’s approach, methodology and scope of services are presented in Form Tech-3 andTech-4 of the Consultant’s technical proposal. This Inception Report provides recommendationswhereby the workplan of the PMDSC is to be modified or updated to minimize potential diversionfrom targeted dates of key milestones, while meeting the government’s objectives. The PMDSC’sdetailed workplan is presented in Annex D.

159. As noted in Section 1, at the time the ToR were received by the Consultant in March 2014 ithad been assumed that several packages would have been tendered prior to the PMDSC servicesbeing commenced, and that construction would be in progress, so that there would be a higheremphasis at inception stage on the Task 3 activities. In fact no packages had been tendered by thestart of the PMDSC activities and the focus has rather been on reviewing and completing biddocuments for issue as early as reasonably possible, consistent with the completion of essentialmodifications.

160. The PMU and ADB have indicated that priority needs to be given to the issue of bid invitationsand the construction of Tranche 2 works, which comprise the TBM Tunnel 3 of the UEC and theKMTC link, currently both components of UEC-ICB-2. Although no formal Addendum or accelerationinstruction has been received to date, the PMDSC has started investigating the implications of suchchanges in sequence compared with the planning on which the current PMDSC Agreement is based.Further details are given in succeeding sections.

5.2 PPMES and MIS

161. The start of construction activities has not happened as fast the schedule envisioned in thePMDSC’s ToR. This has temporarily delayed the need to fully deploy the Management InformationSystem (MIS) and the Project Performance Management Evaluation System (PPMES). In closeconsultation with the PMU, the PMDSC will support development of an MIS that addresses amongother things, individual and overall contract implementation schedules and budgets (planned andactual), project operational performance, operation and maintenance, safeguards and humanresource development. The PPMES will include a participatory baseline survey to be conductedwithin the first year of the Program, with follow-up surveys to evaluate any changes. Surveys willtarget direct and indirect stakeholders and beneficiaries. The PMDSC will collect necessary data,monitor and routinely evaluate project implementation results and impacts as part of the MISMonitoring and evaluation of pro-poor effects of the project will also be integrated into the PPMES.Manuals for the MIS and PPMES will be prepared that shows users how to update and use thesystem.

162. Table 1 shows typical PPMES indicators and a framework that we will expect to discuss, agreeand support PMU to implement.

Page 47: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 39Page

Table 4: PPMES Arrangement for the MWSIP

PROJECT PERFORMANCE MANAGEMENT SYSTEM (PPMES)

Criteria Performance Indicators Unit/Event

Monitoring and Evaluation of Project Outcomes

Increase agricultural produc-tion, food security and con-tribution to economic growth

Output per unit serviced area $/ha

Output per unit irrigated area $/ha

Output per unit irrigation supplied $/m3

Output per unit water consumed $/m3

Infrastructure Development

Construct robust infrastruc-ture without cost overrunsby agreed deadlines

Detailed designs confirmed for advanced projects; prepared forTranches 2/3

Target dates

Bid documents prepared, tendered and contracts awarded Target dates

Construction of Tranche 1 works Annual staged or % completion

Construction of Tranches 2 and 3 works Annual staged or % completion

Service Delivery Performance

High performing Total annual volume of irrigation water delivery m3/year

Annual irrigation water delivery per unit command area m3/year

Annual irrigation water delivery per unit irrigated area m3/year

Annual main system water delivery efficiency: total monthlymeasured water delivery to water users/total monthly meas-ured water inflow to the irrigation system

Efficiency

PROJECT FINANCIAL/ACCOUNTING MANAGEMENT SYSTEM (PFMES)

Criteria Indicator Measure/Event

Accounting/Financial Statements

Accountability Annual financial statements and accountsprepared itemizing all procurement

Quarterly/Annual

Records of funding received from all sources Quarterly/Annual

Expenditures incurred by category Quarterly/Annual

5.3 UEC Tunnel 3 Earlier Construction Start (Tasks 2 and 3)

5.3.1 Rationales

163. The TBM tunnel to be constructed under UEC ICB-2 lies on the critical path for completion ofthe NCPCP. The planning for it currently foresees its continuation after the completion of othercomponents of the MWSIP, so that any action taken to reduce the time of completion of thiscomponent will also shorten the time to completion of the Program.

164. Although options, including the potential for and implications of using a second TBM, werepreliminarily investigated during the PPTA, these are now to be reviewed by the PMDSC withadditional specialist tunnel expertise, to see whether other feasible actions can be taken to reducethe overall time to completion. These reviews will re-visit assessments made during the earlierdesign phases of the potential for economic use of a second TBM to speed up tunnelling time, andof opening a second heading from the upstream end using conventional tunnelling technology,taking due account of environmental constraints, such as the disturbance of wildlife by theuncontrolled use of explosives.

5.3.2 Actions to be taken including Additional Investigations

165. The additional investigations for UEC-ICB-2 focus mainly on the outlet of Tunnel 3 of the UEC.The tunnel invert is located approximately 25 m below original ground level at that location, whichmeans that a comparatively large and deep construction pit has to be excavated to allow theerection of the TBM. Therefore, not only does the surface of fresh rock have to be investigated, butalso the characteristics of the overlaying soil layers have to be determined for the design of theconstruction pit (e.g., slope angle, support, dewatering, etc.). Soil and rock samples therefore haveto be taken and analysed to determine the corresponding properties.

166. Furthermore, the additional investigation campaign has to lay emphasis on critical areas alongthe tunnel alignment, which may need additional or a more detailed investigation. The areas areidentified according to the results of the geo-electrical sounding (areas of low resistivity), according

Page 48: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 40Page

to the surface mapping (areas of rock types which pose potential waterways, if striking out to thesurface, e.g. calcareous gneiss layers or quartzite) and according to topographic (low cover, crossingof streams and waterways) and infrastructural features (undercrossing of roads, railways,settlements). Data of existing boreholes will be used to confirm or already exclude areas. For theremaining critical areas, which are so far not covered with any investigation, the necessity for furtherinvestigations has yet to be evaluated.

5.3.3 Potential for an Early Start to Construction

167. In view of the requirement to review options for accelerating tunnelling progress, the scale ofinvestigations still to be undertaken, the time required for the resulting design modifications andtheir approval by the PMU and ADB, and a realistic allowance of time between issuing invitations tobid and commencement of construction, an earlier start to construction than envisaged at the timethe FAM cannot be confirmed at this time. It is expected that the final results from the additionalinvestigations may take 6 months.

5.4 UEC-ICB-3 (6+226 to 17+900km) in Tranche 2

5.4.1 Rationales

168. At the request of the PMU and ADB in order to expedite the construction of the UECP, asection of the canal up to chainage 17+900km will be moved into Tranche 2. The PMDSC willprioritize the preparation of the bid documents, but the actual timing for this deliverable dependson the PMU’s approval of the PMDSC’s Contract Addendum, since the Kongetiya Level Crossing issituated in this section of the canal.

5.4.2 Implications for Resource Allocations

169. This will require the splitting of the original UEC-ICB-3 bid package into two sets of tenderdocuments (with an additional UEC ICB package in Tranche 3), and consequentially will result inadditional work for the PMDSC under Task 2, as well as under Task 3 for support during tendering.However, no additional claim is being made at this time for the Lump sum component of the Contract.

5.5 KMTC Advancement (Tasks 2 and 3)

5.5.1 Rationales

170. Impounding of Kalu Ganga and Moragahakanda Reservoirs is currently scheduled to becommenced by the end 2018. The stand-alone storage of Kalu Ganga Reservoir is sufficient, afteraugmenting its own command area, for transferring water to Moragahakanda Reservoir. Advancingthe implementation of KMTC would have the following advantages: (i) construction work would befacilitated, as the sill level of KMTC at the downstream end is below the FSL of Moragahakandareservoir; (ii) the enhanced water availability at Moragahakanda Reservoir capacity would:

• Facilitate meeting water demands in Polonnaruwa irrigation system, including additionalwater supplies to Kantale Reservoir for enhancing the irrigation supplies to the proposedsugar plantation expansion

• Offer the opportunity to reduce discharges from Bowatenna Reservoir to Amban Gangaand Polonnaruwa Systems, thereby allowing diversion of the saved water throughLenadora Tunnel to (a) Kala Wewa and Nachachaduwa Systems, and (b) Kandalama andHuruluwewa Systems

• Enhance the power generation capacity at Moragahakanda Dam

171. The government has requested the PMDSC to accelerate the implementation of the KMTC, soit is proposed that the tunnel designs and bid documents will be finalized during 2016, so thattendering can proceed in Q1 2017.

Page 49: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 41Page

5.5.2 Actions to be taken including Additional Investigations

172. The additional investigations for both KMTC tunnels focus on the portal locations (inlet, outlet)and areas of low cover. Boreholes are envisaged at these locations, to be drilled down to the invertlevel of the tunnel. Furthermore, an area was identified in which layers, probably of calcareousgneiss, strike out to the surface will be assessed. A borehole is proposed to investigate this layer andthe associated risk of a potential waterway from the surface to the tunnel.

173. In addition to the portal locations of the tunnels, the foundation conditions of the aqueductsneed to be investigated, e.g., rock levels are to be determined. Further, laboratory tests on rocksamples will be performed to investigate the rock mechanical properties of the different rock types.Depending on the results, the design of the KMTC may have to be adapted. It is expected that thefinal results from the additional investigations may take 4 months after which designs can beadjusted accordingly. This is likely to involve the citing of the portals and the extent of cut-and-coversections as well as the support measures in the tunnel. The aqueduct designs also require input fromthe results of geotechnical investigations.

174. It was agreed during the ADB Inception Mission that the original civil works package UEC-ICB-2, which included UEC Tunnel 3 and the KMTC, would be split into two separate packages: UEC-ICB-2A (UEC Tunnel 3) and UEC-ICB-2B (KMTC). This will involve preparation of separate sets of biddingdocuments and foresees the completion of construction of the second package (previouslyprogrammed for the period after completion of Tunnel 3 and after the period covered by the currentPMDSC Consulting Services contract) to be commenced as soon as possible.

5.5.3 Implications for Resource Allocation

175. The construction supervision of KMTC is beyond the current scope of PMDSC’s work plan (seeparagraph 174) and, now that it should be included in PMDSC’s responsibilities, it will requirecorresponding staffing resources to be added to those already provided for in the consultancybudget. For example, the ToR require continuous presence of the Senior Design Engineer (Dams andTunnels) during tunnel construction. These provisions have been included in the revised staffingschedule in Annex G. It should be noted that the resource estimate is made on the assumption thatthe construction duration remains as previously planned: should this be extended the supervisionresource requirement will increase accordingly.

5.6 National vs. International Design Standards (Tasks 2 and 3)

5.6.1 Dam Safety (ICOLD)

176. One important issue regarding the use of international design standards is the designdischarge capacity of dam spillways. This refers both to existing dams on level crossings (see alsoSection 5.6.2), which are partly heightened and integrated into the canal system of the UEC, and tothe new dams to be constructed on the NWPC. It is noted that the spillways of all dams on the MLBC,NWPC and UEC incorporate (or have been designed with) an ungated, free-overflow weir, which isan intrinsically safe configuration because it eliminates potential mechanical and electrical failuresrelated to spillway gates.

177. However, these dams have been designed according to a Sri Lankan standards using designflood values with a modest return interval. In the understanding of the PMDSC spillways of smalldams in Sri Lanka are currently designed for a flood with a return period of 1:200 years, if they areup to 9.1 m (or 30 ft) high, while higher dams are designed for 1:500 years. This design approachwas originally based on the Sri Lankan design standard “Design of Irrigation Headworks for smallCatchments” by A.J.P. Ponrajah, published by the Irrigation Department Colombo in May 1984.However, the return periods stated in Section 5.2 “Design Flood of Reservoirs” of this standard (1:50years for dams smaller than 9.1 m and 1:100 years for dams higher than 9.1 m) have been increasedin recent years as noted above in order to provide additional safety.

Page 50: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 42Page

178. Following this approach, a flood with a recurrence interval of 1:500 years was previously alsoselected for the MCB detailed design of the spillways on the new high dams on the NWPC (i.e.,Mahakithula and Mahakirula Dams).

179. Of particular relevance to fulfilling a requirement to design to international standards is therequirement of the International Committee on Large Dams (ICOLD) in their Bulletin 82: “Selectionof Design Flood” (1992). Its Section 4.9 “Design Flood Standards and Regulations” refers toguidelines of the Australian National Committee on Large Dams (ANCOLD) and of the US Army Corpsof Engineers (USACE). Under both guidelines, one decisive criterion is the downstream flood hazardcategory, which is to be classified as “high” if loss of life is to be expected in case of dam failure. Thiscategory defines the return period of the spillway design flood, which then has to be selected usingbetween 1:10,000 years and PMF for ANCOLD guidelines, and using PMF under USACE guidelines.

180. ICOLD standards classify the dams on the NWPC and UEC as “large dams”, either because oftheir height of more than 15 m or, if they are between 10 and 15 m high, because of their reservoirvolume of more than 1.0 million m³ or their crest length of more than 500 m. For the dams pertainingto level crossings on the MLBC, these conditions are still being assessed.

181. We would propose categorizing the dams into “large” and “small”, because the large damswould receive more attention, mainly concerning any follow-on geotechnical investigations thatmay be required to fully assess their condition. A preliminary inventory of the dams identified in theMWSIP is shown in Table 5.

182. With regard to the selection of the spillway design discharge there are several importantboundary conditions that are specific for the dams on the NWPC, on the UEC and on the MLBC:

• All these dams are earthfill embankments, which may not be overtopped.

• Reservoir operation is generally not aiming for flood control, thus reservoirs have to beassumed to be at FSL when a flood wave enters.

• The dams’ main purpose is provision of irrigation water, which means that farmers usingtheir water are living immediately downstream.

183. These factors demand a safe design approach for the dams’ outlet devices, including thespillways. The spillway designs for Mahakithula and Mahakirula Dams would have to be modified tocater for a larger design flood according to ICOLD guidelines if international standards are to be met.Considering the fact that catchment areas of the reservoirs on the NWPC and UEC are generallysmall, no substantial increase of the spillway size is expected in order to accommodate a design floodthat would satisfy the ICOLD standards addressed above.

Page 51: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 43Page

Table 5: Preliminary Classification of Embankment Dams in MWSIP

Area Level Crossing / DamClassification

L / S Remarks

Minipe, 6 dams

Hasalaka Wewa Large Due to reservoir volume and28 km canal section

Berabun Oya Small

Ulpothagama Small

Okirikotuwa Wewa Small

Totillagasella SmallDunuweila Wewa Large Due to 22 km canal section

UEC, 3 dams plusHurulu Wewa

Kongetiya Large Ponding at d/s toe andsurface slips identified at sitevisit

Bogaha Wewa Small

Madeththa Wewa Large Ponding at d/s toe identifiedat site visit

(Hurulu Wewa? No levelcrossing as such)

Large Recent review done by Pöyry

NWPC, 14 damsplus Wemedilla

(Wemedilla- no level cross-ing as such)

Large Surface slips identified atsite visit

Nabadagahawatta Wewa Small

Nilagama Wewa SmallMahadambe Wewa Small Leak identified at site visit

Jayalathgama Wewa Small

Ihala Wewa Small

Ulpotha Wewa Small

Galketiyagama Wewa Small

Kaduru Wewa SmallPothuwila Wewa Large

Angarewa Wewa Small

Edadukotte Wewa Small

Wahukotuwa Small

Bogolla Wewa SmallDikkanna Wewa Small

Ihalawaththa Wewa Small

Atawarala Wewa Small

Ihala Wewa Small

Konarage Wewa Small

5.6.2 Possible Scope Changes Relating to Existing Structures (Tasks 2 and 3)

184. The implications of spillway extensions are different for dams that are still in the design stage,such as the new dams in the NWPC described in the previous section, and for dams that alreadyphysically exist. A number of existing dams will be integrated into the canal system of the MLBC, theNWPC and the UEC. Some of these dams will be heightened, for instance Mahadambe Wewa on theNWPC, while others remain unchanged, for instance Pothuwila Wewa, also on the NWPC. Sri Lankanstandards have been used for the selection of the spillway design flood of these dams. Thesestandards are less demanding than the guidelines of ICOLD, which are generally invoked whenmeeting international standards (as required by the PMDSC’s ToR).

185. In this context, reference is made to ICOLD Bulletin 142 “Safe Passage of Extreme Floods”(2012), Section 1.1 “Importance of the Subject.” The following text appears in this reference: “Amajor reason for the reported cases of severe problems is overtopping, notably in earth, rockfilldams (31% as primary cause, 18% as secondary cause), and masonry dams (43%). A majority of casesof overtopping was due to inadequate spillway capacity (71%).”

Page 52: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 44Page

186. For existing dams on level crossings or other dams that become part of the MWSIP, ICOLDBulletin 59B “Safety Improvements of Existing Dams” (1998), would be relevant. For these dams thevalidity of hydrological parameters would have to be reassessed (reconfirmation of the floodhydrograph). Reference is also made to ICOLD Bulletin 125 “Dams and Floods” (2003), Section 7.4“Hydrological Safety of Existing Dams”, which states on page 211: “Bulletin 59B indicates that “thecriteria for determination of the design flood for an existing dam are intimately linked to safetyphilosophy”, and, in general, the “Hydrologic deficiency of a dam requires re-analysis based oncurrent standards.” For existing dams, irrespective of whether they are being raised or remainunchanged and are just being integrated in the canal system of the MWSIP, an increase of thespillway size would automatically lead to higher costs, which are not included in current estimates.

187. Considering the apparent incompatibility of Sri Lankan standards with ICOLD guidelines interms of the spillway design flood, and the fact that some of the existing dams to be integrated inthe MWSIP are not in a good state of repair, it seems appropriate to review basic parameters usedin their design; however, this is outside the present scope of work of the PMDSC.

188. This also refers to the stability calculations, which, for older dams, have been prepared on thebasis of the Sri Lankan standard “Technical Guide Lines for Irrigation Works” by A.J.P. Ponrajah,published by Irrigation Department in October 1988. Only in recent years, USACE Standard EM 1110-2-1902 “Slope Stability” (2003) replaced the previous Sri Lankan standard. Stability analyses ofMahakithula and Mahakirula Dams have been based on the cited USACE standard, which isacceptable. Generally, dam stability should fulfil the requirements of either USACE EM 1110-2-1902or of Eurocode 7.

189. During PMDSC’s site visit in December 2015, the majority of dams on level crossings of theNWPC and UEC were inspected, at a time when their reservoirs were at FSL due to heavy rains inthe weeks before, and overflow on some spillways had started. Not all embankments were found tobe in perfect condition: some have relatively steep slopes and showed very dense vegetation on thedownstream side, preventing visibility and inspection. Wet spots were detected at the downstreamtoe of Madeththa Wewa (UEC), a localized leak of about 4 l/s was found at Mahadambe Wewa(NWPC) and a number of surface slips were observed on the downstream shoulder of the relativelynew Wemedilla Dam (NWPC).

190. The conclusion of the PMDSC is that additional effort needs to be invested in examining theexisting structures that will become part of the expanded Mahaweli System as described in thefollowing sections.

5.6.3 Kongetiya Level Crossing

191. The Kongetiya Level Crossing is the first level crossing on the UEC starting at chainage 3+850km. The embankment is designed as an earthen embankment with a length of 1,562 m and amaximum height of 12 m. The upstream side will have armouring to protect against wave erosionand a small toe drain is foreseen on the downstream side. A gated outlet on the right side of theembankment will provide irrigation supplies to downstream riparian users and an overflow spillwaywill be constructed on the left side of the embankment (capacity = 6.4 m3/s). The construction ofthe adjacent saddle dam, with a length of 581 m and a maximum height of 11 m, has not yet started.

192. Due to the prolonged period that the embankment has been under construction, severeerosion of the top layer and embankment slopes has occurred. In some places the erosion gulliesare over 1 m deep.

193. Recommended follow-up actions include:

• Field investigations = 3 boreholes on the centreline of the embankment spaced at thelocations stn. 0+360, 0+560, 1+170, with depths of 10 m, 6 m and 15 m, respectively.Standard penetration tests (SPT) and percolation tests (on undisturbed samples) should be

Page 53: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 45Page

carried out in order to properly assess the geotechnical conditions of the existingembankment.

• Once the results from these field investigations are available, including a representativegrain size distribution of the constructed material, they should be jointly reviewed by thePMDSC and PIU as the basis for finalizing the design.

• It is already apparent though that a significant amount of the existing embankment slopeswill have to be removed and reconstructed. Similarly, the top gravelly layer of theembankment will have to be removed in order to prevent a pervious layer being present atthe existing elevation after construction.

• The armouring needs to be extended downwards from the minimum operation level andinstead go all the way down to the invert elevation of the Upper Elahera Canal where it willdischarge into the level crossing.

5.6.4 Implications for Resource Allocation

194. It is proposed that the assessments recommended for dams include the following under Task 1:

Large Dams

Site visit with visual inspectionGeotechnical investigations (one drill hole, some in-situ and lab tests)Check of dam stability (using “Slide” software)Statement concerning spillway capacity

Small Dams

Site visit with visual inspectionStatement concerning dam stabilityStatement concerning spillway capacity

195. The estimated resources for this additional scope includes:

• Geotechnical Investigations Engineer, International (+2 MMs)

• Modelling Specialist, International (+2 MMs)

• Assistant Geologist, National (+ 8 MMs)

196. Re-running the stability calculations for older dams with steep slopes would require detailedinformation about the as-built dam geometry and about geotechnical parameters of the damfoundation and the dam embankment. If this information is not available or if there are doubtsregarding the correctness of data, new surveys and geotechnical investigations would have to beinitiated.

197. Since reliability of geotechnical investigation results conducted in earlier project phases isoften questionable, a new small-scale (and inexpensive) geotechnical investigation program shouldin any case be implemented on each existing dam, if not already envisaged. The investigationprogram would begin with a field survey to evaluate the general condition of the dam (leakages,small slides, vegetation, etc.) and to already identify, where possible, critical areas which may needa more detailed investigation. Otherwise the investigation would mainly consist of at least one drillhole in the area of the deepest dam cross section, with undisturbed sampling for assessing the shearstrength of the embankment material, accompanied by standard soil testing (particle sizedistribution, Atterberg limits, etc.). It is also advisable to conduct some Standard Penetration Tests(SPT) along the dam axis to evaluate the compaction along the dam axis. Furthermore, the SPT blowcounts could also be used to estimate the shear strength. An inventory of all existing damsintegrated in or affected by the MWSIP is currently under preparation (including the dams on theMLBC) to obtain an overview of the situation. If the condition of these dams is to be assessed and

Page 54: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 46Page

measures to upgrade them in terms of durability and spillway capacity are to be designed andimplemented, additional resources would be needed. Instrumentation for monitoring is also likelyto be required.

198. Additional resources would be required if all existing dams that will become part of the MWSIP(independently whether they are heightened or assumed to remain unchanged) are to bereassessed in terms of dam stability and spillway design flood under PMDSC’s responsibility.Assessment of the costs of these investigations could be made once the inventory of existing damsin the system is complete.

199. For the Kongetiya Level Crossing it is proposed that the PMDSC take over the responsibility forcarrying out the required investigations program and finalizing the design for the heightenedembankment. The additional staff resources for this have been included in the revised staffingschedule and comprise: Geotechnical Engineer, International (+1 MM), Senior Canal Designer,International (+2 MMs), and Senior Canal Designer (+1 MM).

5.7 Capacity Development Strategy (Task 4)

5.7.1 Approach

200. In order to address properly the specific needs for capacity development for programdevelopment – managerial and technical skills – the PMDSC will carry out an initial situationalanalysis of the institutions and stakeholders involved in the MWSIP and the approach by Potter andBrough (2004)20 using the term “system capacity” which recognises that capacity deficiencies areseldom limited to single technical, organisational, institutional or infrastructural weaknesses, butrather that in most cases a combination of several different elements contributes to a capacitylimitation. This will be the optimal approach to ensure that all gaps are captured in order to ensurewell founded decision making, efficient management and better productivity.

201. The systemic approach is specifically suited to explore interfaces of large broad projects,where several main stakeholders and external decision makers may influence central water resourcemanagement organisations, such as MMDE, MASL and ID in matters related to effectivemanagement and operation. The approach is also suited to the analysis of which tasks are bestsuited to be performed in-house and which tasks that should be out-sourced or contracted out. Thesituational analysis, with a subsequent detailed training needs assessment, will also provide thefoundation for capacity development activities, so that outputs, expected results, impact andoutcomes can be formulated, then implemented and finally monitored.

202. Potter and Brough (2004) recognise that “capacity development” or business improvement isthe objective of many programs and a component of most others, however satisfactory definitionsremain elusive and it is widely suspected of being too broad a concept to be useful, as they state:“Too often it becomes merely a euphemism referring to little more than training”. They argue thatit is more important to address systemic capacity development, based on a combination of nineseparate, but interdependent capacity components:

• Performance Capacity (tools): Are the tools, money, equipment, consumables available todo the job?

• Personal Capacity (skills): Are the staff sufficiently knowledgeable (any gaps), skilled andconfident to perform properly? It is probably also required to address the mind-set tooperate efficiently.

20 Systemic Capacity Building: a Hierarchy of Needs; Potter, Christopher and Brough, Richard, Oxford University Press(2004). http://heapol.oxfordjournals.org/cgi/content/abstract/19/5/336

Page 55: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 47Page

• Workload Capacity (staff): Are there enough human resources with broad enough skills tocope with the workload? How many position is presently vacant? Are job descriptionspracticable? Is the skill mix appropriate?

• Supervisory Capacity (staff): Are there reporting and monitoring systems in place? Are thereclear lines of accountability? Can supervisors physically monitor the staff under them? Arethere effective incentives and sanctions available to keep staff employed?

• Facility Capacity (infrastructure): Are offices large enough? Are equipment, vehicles,infrastructure drawings, maps, GIS databases and other needed facilities available andsufficient?

• Support Service Capacity (infrastructure): Are there supply organisations, contractors,laboratories and quality control experts available? These may be provided by internalsections or by the private sector but they are required.

• Structural Capacity: Are decision-making coordinated between the various institutions, arethere forums where discussion may occur?

• Systems Capacity: Do the flow of information, money and managerial decisions function ina timely and effective manner? Is information shared? Are proper filing and informationsystems in use?

• Role capacity: Has sufficient authority and responsibility been given to make decisionsessential for effective performance? Can purchases be made without lengthy delays forauthorisation?

203. A capacity building plan should be based on the analysis of the whole hierarchy of capacityneeds, following the four dimensions shown in Figure 8.

Figure 8: The Hierarchy of Capacity Needs

204. The effectiveness of one form of capacity depends and builds on the effectiveness of the otherelements of capacity. Emphasising systemic capacity building would improve the diagnosis ofshortcomings and lead to more effective use of scarce resources and will lead to the proposal fortraining on management, operation and maintenance routines for optimal program implementationand effective water resource management in according with principles of good sector governance.

205. The complete situational analysis will be conducted in close and obviously active participationof MMDE, MASL and ID and reported and presented in a wider forum to capture all comments andviews on preliminary conclusions before being finalised.

Page 56: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 48Page

5.7.2 Training Needs Assessment and formulation of Training and CapacityDevelopment Program

206. Based on the above situational analyses, a Training Needs Assessment (TNA) will be carriedout to identify knowledge gaps and thereby key training areas, leading to proposed training andcapacity development program, targeting staff of MMDE, MASL and ID. The emphasis will be onneeds, since training, in order to be targeted and cost-effective, must be needs-based and demand-driven, as opposed to the supply-driven approach to training. The aim of the TNA will be to compareexisting qualifications and experience of staff (both within project management and engineering andwater resource management provision) with the required qualifications necessary to perform theirduties in the MWSIP, and to help identifying the training interventions, developing or updating thecourse curriculum and identifying proper training institutions, which are needed to fill the gaps.

207. The required competencies will be derived from the overall objective of MWSIP and possibleavailable staff specifications. Interviews will be conducted with relevant staff to assess the individualcompetencies and responsibilities. The TNA exercise will lead to the formulation of a detailedTraining and Capacity Development Plan covering the whole range of managerial, administrativeand technical tasks and duties. This plan will however need to be a “living document” that will needto be frequently updated to capture emerging capacity needs.

208. The management training will focus on practical management tools rather than thetheoretical concepts of management and human behaviour often favoured by academics. To thisend, training programs will include institutions and specialists who have first-hand experience ofmanaging people, and – equally important – advocating and managing change.

209. Using the TNA and situational analysis, recommendations will be formulated for an ActionPlan to transfer relevant knowledge and technology to MMDE staff regarding construction,operation and maintenance and “modernised” performance compared with internationallybenchmarked practices. Recommendations will be proposed for all departments, not only thetechnical – also including a senior management leadership development program. Part of such anAction Plan will include Human Resources Development that must encompass: (i) organisationalstructure; (ii) development of a staffing plan; (iii) development of career paths; and (iv) staff training.The Action Plan assumes that the people in the organisation have reasonable powers to make thechanges that they see are both necessary and within the delegated powers of that organisation. TheAction Plan must provide a clear roadmap for “managers” so that they know what they have to doto meet the objectives set for their departments – and in particular introduce performance basedmanagement with visible targets (objectively verifiable performance indicators) and achievements.The action plan will highlight necessary key position to be filled, key training requirements to beconducted and priority hardware and software to be procured.

5.7.3 Implementing the Training Program

210. Upon approval of the training program, the PMDSC will assist MMDE with the implementingof the training program, including programming, budgeting, scheduling and managing logistics ofthe training, institutional development and awareness programs.

211. The project management training for the PMU will focus on practical management toolsrather than theoretical concepts of management and human behaviour. To this end, we will striveto include institutions and specialists who have first-hand experience of managing ADB projects, butalso equally important – advocating and managing change. There would be a need to dovetail theprogram with training initiatives that may materialize under the awareness programs. The overallaims of the project management will be to improve and develop the capability of PMU and PIU staffto execute project planning, design and management as per international state-of-the-art methodsand tools but also to secure the investment made under the MWSIP through well performed andcontinued management, operation and maintenance.

Page 57: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 49Page

212. The training will be a process of creating situations to encourage participants to learn,extending their skills and knowledge and modifying attitudes in response. These situations are notrestricted to formal courses but include on-the-job learning under supervision, study tours, and evenself-instruction. We will consider training of the staff from MMDE, MASL and DOI both on site andin the PMU/PIU offices as a most important aspect to be incorporated through all phases of theprogram.

213. Our approach for knowledge and technology transfer to MMDE staff will follow requirementsgiven in the ToR, on gaps emerging from the TNA and issues to be brought up by the PMU/PIUs "on-the-job" or arising during project implementation. The training program will be structured accordingto the following project implementation phases:

• Training during the review of the construction design

• Training on the construction site (civil works and equipment)

• Training during the approval period of equipment design

• Training during the manufacturing and testing of equipment

• Training during the trial operation of power generation equipment

• Technical assistance after commissioning

214. For the benefit of the training of MMDE personnel, the PMDSC will advise and coordinate thetraining to PMU/PIUs in preparation of tender documents prepared in Task 2 and will coordinate thetraining provided by Contractors. Over and above the training to be provided by the Contractors,PMDSC will provide additional training in engineering design and construction design, constructionsite supervision, operation and maintenance as “on-the-job training”.

5.7.4 Preliminary Review of Water Resource Management on Sri Lanka

215. In continuation of the situation analysis, the PMDSC will perform a preliminary review of theprevailing policies, laws, regulations, agreements, frameworks, mechanisms and institutionalarrangements within MMDE, MASL and DOI currently being used (or in place) to govern themanagement of water resources in Sri Lanka. The focus will be to assess strengths, weaknesses andopportunities to improve interagency coordination – and hence to improve overall management ofthe Mahaweli Development Program (the two phases of the NWPCP). This review will be reportedby the PMDSC in a working document and will be the basis for the development of the ToR for theSIWRM consultancy promoting better (integrated) water resource management in Sri Lanka.

5.7.5 Institutional and Staff long-term Development Plans for MMDE

216. Using the TNA and situational analysis, we will formulate recommendations for institutionaland staff long-term development Action Plan for MMDE that will support long-term managementof the entire MDP and NCPCP. This involves transfer of knowledge and technology to MMDE staffregarding management, supervising construction of large infrastructures, operation andmaintenance and “modernise” performance management as per internationally benchmarkedpractices. Recommendations will be proposed for all department/unit, not only the technical – butalso including a senior management leadership development programme, secondments andexposure study tours to other water resource authorities. Part of such an Action Plan will includeHuman Resources Development that must encompass: (i) organisational structure; (ii) developmentof a staffing plan; (iii) development of career paths; and (iv) staff training.

217. The Action Plan will assume that the people within MMDE have reasonable powers to makethe changes that they see are both necessary and within the delegated powers of MMDE. The ActionPlan shall provide a clear roadmap for MMDE “managers” so that they know what they have to doto meet the objectives set for their departments – and in particular introduce performance basedmanagement with visible targets (objectively verifiable performance indicators) and achievements.

Page 58: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 50Page

The Action Plan will highlight necessary key position to be filled, key training requirement to beconducted and priority hardware and software to be procured.

5.7.6 Finalizing ToR for the SIWRM Consultancy

218. The SIWRM consulting services package seeks to promote the strengthening of IWRMprinciples both within the investment program area and nationally by benchmarking key watersector institutions and formulation of recommendations and guidelines for IWRM. The consultancywill also include updating of water resources management master plans, crop diversification,assessment of the water demands, development and implementation of IWRM decision supportsystem and modernization of the Water Management Secretariat under the MASL.

219. Based upon the preliminary review – the PMDSC will update and finalize the TOR for theSIWRM consulting package and subsequent support the PMU with the recruitment, and providemonitoring and advising on the outputs of the SIWRM Consultant.

5.7.7 Anticipated Deliverables under Task 4.

220. To summarise –the following will be completed and delivered under Task 4:

• Initial Situation Analysis (Working Paper)

• Training Needs Assessment

• Training Program

• Preliminary Review of Water Resources Management in Sri Lanka (Working Paper)

• Institutional and staff long-term development Action Plan for MMDE

• Updating and finalising ToR for the SIWRM Consultancy

221. Upon completion of the PMDSC contract, by Month 58, a Training Completion Report will beprepared summarizing the individual and institutional achievements and results from the MWSIPtraining program, including lessons learned and recommendations for future training efforts to becarried out in Phase 2 or other future supporting activities.

5.8 Communications Strategy (Task 5)

222. The purpose of the MWSIP communications effort is to support the PMU in a variety of waysthat bring about efficient and effective engagement and two way communications with and amongstakeholders of the investment program so that their views and concerns are reflected in theprojects. Activities under Task 5 will be aimed at assuring public trust of institutional stakeholdersand the public, so that the MWSIP is understood through the use of simple language and non-complex visuals that describe plans, show the ongoing works, dispel myths, correct misunderstandingsand unrealistic perceptions, and stand ready to respond in a positive, non-threatening way in theevent of problems.

223. Initial communication activities will organize a work plan that sets out a proper ranking ofcommunication priorities based on some key challenges already identified in the StakeholderCommunication Strategy (SCS) prepared during the PPTA, with the understanding that more will beadded as the program moves forward.

5.8.1 Approach to Stakeholder Communications

224. Defining MWSIP for stakeholders as the continuation of a large ongoing program:Communication of the MWSIP will need a carefully prepared set of materials that explain theprogram and describe the timing for execution of construction works, in the context of the customs ofpeople who are living in the project areas. Our approach to stakeholder communications will considerstakeholders and activities at 5 levels, namely: (i) PAPs; (ii) direct beneficiaries, the wider public in

Page 59: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 51Page

project areas, (iii) civil society including NGOs and potential media partners; (iv) inter-agencystakeholders and donor partners; and (v) national audiences through mass media and social media.

225. Targeted communications for households/communities in impacted areas on how better tounderstand and participate in the program to avoid conflicts: Where land acquisition or resettlementis required, effective information-sharing and consultation with those affected is necessary to helpavoid potential conflicts through misunderstandings. Communities and individuals may also beimpacted by construction or downstream effects and will need clear information about theanticipated impacts, their entitlements, how to voice concerns, and how to access grievance redressmechanisms, so that issues can be identified and addressed early before they escalate.

226. Managing expectations on water delivery: Sri Lanka’s northern dry zone is marked by severewater stress, with the regional annual per capita endowment of 1,200 m3 being well below the1,700m3 threshold that defines water stress, and this has been compounded by regular droughts.The need for water in these areas is contributing to high expectations among beneficiaries aboutthe health and livelihood improvements expected to be associated with water transfer. However,the MWSIP has a very long time frame and benefits are unlikely to be felt in northern regions untillate in the program. In addition, the expectations in some beneficiary areas may not be realistic orcommensurate with likely project impacts. It will be necessary to be transparent and realistic, aboutboth benefits and constraints of the investment program.

227. Ensuring that environmental impacts and community health are properly addressed: Human-elephant conflict (HEC) is an ongoing environmental concern in Sri Lanka. The combined investmentswill impact 11,600 ha of natural habitat, some of it elephant habitat, although only 1,100 ha of thisfalls under the investment program. The projects have the potential to increase human elephantconflict due to additional cropping in the Yala season and if the planned mitigation measures are notproperly implemented. Timely and transparent information-sharing and dialogue will be importantto maintain and strengthen engagement with NGOs. Addressing the issue of chronic kidney disease(CKD) is one of the aims of fresh water transfer and links to the Ministry of Health and other relevantgovernment agencies will be necessary.

228. Dispelling misconceptions on water-sharing and use: Some communities may perceive thatthe diversion of water to the NCPCP will negatively impact the water rights of communities locateddownstream of the diversion points. This issue is complicated by the politicisation of water rights,especially in the light of inter-ethnic post-war conflicts. Misperceptions will need to be continuouslyclarified through reliable information dissemination and community dialogues.

229. Relevant collaboration with other donor agencies and programs in impacted areas: Properconnections with ongoing projects and the sharing of information and materials will help to achievepositive public support for the MWSIP. These groups will be identified as part of the work plandevelopment.

230. Identifying and working with reputable non-governmental organisations (NGOs) and civilsociety organisations (CSOs): Along with relevant collaborating partners, a number of NGO andCSOs, both international and national, can help expand outreach for MWSIP communications. Thesepotential partners will be identified and contacted early on to help strengthen the achievement ofthe aims of the SCS and input into the resulting work plan.

Page 60: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 52Page

5.8.2 Priorities and Next Steps for Implementation of the Strategic CommunicationsPlan

231. The following priorities have been identified:

• Organise a communication team to include the PMU and PIUs and PMDSC

• Review the SCS. Lay out broad 5 year work plan and timeline, since program needs will shift,this will be considered a living document to be updated as needed. Based on the 5 yearworkplan, prioritize needs and activities for inclusion in the 2016 work plan

• Review and revise proposed SCS budget to align with 5 year work plan and 2016 work plan

• Based on the SCS, develop a system of monitoring and evaluation (M&E) for communications.Identify a set of measurable goals/objectives for inclusion into the program M&E. Wherepossible, identify opportunities to streamline communications monitoring into the projectmonitoring systems established for the projects and/or overall investment program

• Develop a set of communication objectives addressing MWSIP goals, so that measurableimpacts can be reported appropriately

• Develop a detailed profile of institutional and impacted stakeholders for inclusion in plan-ning targeted communications across all levels (from community-level affected people upto national public audiences)

• Based on the set of anticipated “challenges,” identify a set of methodologies for addressingpotential problems with tools that are adaptable for mass media dissemination

• Draft a brief media plan identifying key media, ways to work with them, appropriate timingin relation to project activities; and crisis communication plan in case of negative press

• Oversee communication research on various targeted stakeholders and set up and conductfurther target group research (e.g., focus groups, rapid market place surveys, etc.) to assessongoing public opinion

• Continue to develop and operationalize the MWSIP’s digital marketing and outreachstrategy. Establish a reporting system and supporting staff. Plan the extent to which socialmedia will be utilized and identify which platforms are appropriate and how internet serviceproviders can assist

• Establish strong links with Colombo-based broadcasting entities, so that relevant officialsand personnel can be occasional guests on national TV and radio programs, and developappropriate tools for these officials to be effective presenters

• Identity key communicators in the PMU, PIUs, ID, MASL, and other relevant agencies.Establish relevant staff training in communications for key communicators and develop aidsand materials (e.g., talking points, brochures, factsheets, etc.) to support them

• Complete NGO mapping to identify civil society actors with interests (positive or negative)in the MWSIP, their areas of concern, degrees of influence, and best ways to engage them

5.9 SEA Strategy (Task 6)

232. Work on the Strategic Environmental Assessment (SEA) for the NCPCP has started in Februarywith a review of the existing information. Documents that are being collected and reviewed coverthe following:

• Documents describing the MDP and how it has been evolving:

− MDP’s originally envisaged scope

− The infrastructure and operations as implemented to-date

− The updated plans for its ultimate completion

Page 61: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 53Page

• Plans on other ongoing and planned development programs within the MDP’s area ofinfluence (e.g., sector development programs, major infrastructure projects, any otherplans that have the capacity to influence the status of natural resources and land use on alarger scale)

• Environmental and social-economic baseline data for the MDP’s area of influence. Ofparticular interest will be databases, including GIS shape files, monitoring data, socio-economic statistics, etc. compiled by the MASL for the MDP area, either during previousenvironmental and social assessments, or for routine monitoring.

• Reports on SEAs previously undertaken for the MDP or in Sri Lanka at large

• EIAs, ESIAs, IEEs and any other environmental and social studies or assessments previouslyundertaken for projects within the MDPs’ area of influence

• Policies, laws and regulations that contain information on:

− The objectives and principles according to which land, water and other naturalresources are to be managed

− Particular requirements for the management of land, water and other naturalresources in the area of the MDP

• The institutional framework defining the responsibilities for:

− Planning, implementation and operation of MDP systems;

− Any sectoral institutions concerned with the management of land, water and othernatural resources; their responsibilities for planning and implementation of planswithin the MDP area.

233. The PMDSC requests that the PMU coordinate the provision of all information related to theabove.

234. Based on the initial review of the above listed information, the immediate next steps for theSEA will aim at:

• Defining the details of the scope and content for the SEA to be prepared for the NCPCP

• Determine procedural steps such as stakeholder consultations, consent or approval tobe taken before implementing the scope of work

• Identify additional information collection needs, if any

• Prepare time line for carrying out the SEA for NCPCP

235. A broad outline of the proposed SEA approach is described in the Consultant’s proposal (Tech-4, Section 4.7.2). The SEA Inception Report will describe the details of the scope and content for theSEA. It is proposed that the SEA inception report will function as scoping report for the SEA, and thatthis document could be shared with institutional stakeholders and their feedback integrated intothe SEA study.

5.10 Acceleration of Route Selection for Phase 2 (Task 7)

5.10.1 Justification for Acceleration of the Route Selection

236. The two route options, between which selection has to be made, are described in Section 4.9.The selection of a route for Phase 2 needs to be initiated as early as possible because its conclusionis a pre-condition for commencing investigations and other work on the engineering designs andfeasibility studies required for Task 7. The alternative routes include different project componentsand investigations/designs must focus early on the components in the selected route if thechallenging timeframe for completion is to be maintained. A full feasibility study of both options isnot foreseen or required by the ToR of PMDSC.

Page 62: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 54Page

5.10.2 Strategy

237. The PMDSC is required to apply multi-criteria analysis (MCA) to assist the PMU in the selectionof the preferred conveyance route from the Mahaweli River to supply the Moragahakanda Reservoir.

238. MCA techniques have been applied for many years in sometimes controversial situationswhere there are alternatives that need to be prioritised – many criteria exist by which thesealternatives can be compared – and where there are stakeholders with competing interests andvalues. Examples of MCA application include road route and pipeline selection, siting of facilitiessuch as landfills or industries, and ranking of protected areas.

239. MCA is particularly useful as a tool for natural resource decision-making, where a complex andinter-connected range of environmental, social and economic issues must be taken intoconsideration and where objectives are often competing, making trade-offs unavoidable. It providesa robust and transparent decision-making structure, making explicit the key considerations and thevalues attributed to them, and providing opportunities for stakeholder participation.

240. MCA techniques are sometimes known as “decision-aiding” tools. They have their origins in abranch of mathematics knows as operations research, and they were originally used for businessdecision-aiding in the 1960s as alternatives to cost-benefit analysis. They involve stakeholders indetermining alternatives, along with criteria by which to compare the options. The techniques thenallow stakeholders to “weight” comparison criteria according to their own individual values. The endresult is a ranking of alternatives. MCA techniques are not consensus-based. They do not result inagreement on a negotiated “best” outcome. However, if done properly, they result in a broadunderstanding that the ranking process is legitimate, and therefore so is the outcome.

241. In applying MCA to the selection of a preferred conveyance route, stakeholder workshops willbe organized to understand the two route options, specify comparison criteria, and apply values tothe criteria. The procedure will allow for sensitivity analysis to be undertaken, so that participantscan analyse how ranking outcomes might (or might not) change as different stakeholder values areapplied. The proposed MCA steps are outlined in the next section.

5.10.3 Technical Issues

242. The accelerated program for route selection is utilising the existing ARPS water balance modelapplied at the WMS. Decisions for route selection based on the existing model will not be subject tore-evaluation by any new models. This approach is considered fully legitimate since, although theexisting model will eventually need replacement in order to meet future operational challenges, itsresults are reliable and accepted by decision-makers based on their experience with its predictivecapabilities.

243. One component of the Option 2 route is the required heightening of Kotmale Dam by about25-30 m to increase its reservoir storage volume. This dam was constructed between 1979 and 1984as a “Concrete Face Rockfill Dam” (CFRD) with a height above foundation of 87 m. Although aneventual heightening of the dam was foreseen at that time, the lower-height dam’s precise locationappears to have been selected with the aim of achieving the most economic layout for then currentdesign. However, the Kotmale Valley opens up immediately downstream of the dam, so that anyheightening (which would have to be achieved by placing embankment material on the downstreamside only, in order to maintain and extend the upstream concrete slab) would require verysubstantial embankment volume and thus costs.

244. There is a further technical issue related to dam heightening. In principal, the CFRD is asuccessful dam type, with many applications in the last 35 years worldwide, and with a range of damheights. However, some dams have suffered damage caused by insufficient compaction of therockfill material in the central and downstream areas of the embankment, which led to excessivesettlement of the dam crest and cracking of the concrete slab. In the case of Kotmale Dam, the

Page 63: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 55Page

amount of the heightening would be more than a third of its present height, which wouldsubstantially increase loads on the existing embankment and could cause unexpected settlements.It will hardly be possible to predict the behaviour of a dam raised by the amount required here,which is unprecedented in global experience: to the PMDSC’s knowledge, there are no cases ofCFRDs that have been raised by a significant amount after such a long time of operation.

5.10.4 Actions to be Taken (Investigations, Surveys, Modelling, StakeholderConsultations)

5.10.4.1 Outline of the Multi-Criteria Analysis (MCA) Process

245. The Multi-Criteria Analysis (MCA) will be applied in six steps, as follows:

(i) Presentation and clarification of the conveyance route/technology alternatives

(ii) Development of criteria by which to compare the route/technology alternatives

(iii) “Scoring” of the route/technology alternatives against the comparison criteria

(iv) Valuing (“weighting”) the criteria

(v) Undertaking the ranking computation

(vi) Analysing the ranking outcome through use of sensitivity analysis

246. “Scoring” in this context should not be confused with assigning ranking scores: rather it is theallocation of calculated values (e.g., absolute cost of construction, numbers of households affected,severity of environmental impact etc.).

247. Table 6 outlines the generic structure of the proposed MCA “effects table”. Note that this isonly example’s sake. There could be more possible route/technology variations, and there willcertainly be a longer list of comparison criteria.

Table 6: MCA Effects Table Structure

Comparison criterion(some quantitative,

some qualitative:units vary)

Weightassigned to

criterion

Randenigala-Kalu Ganga

route

Polgolla toMoragahakanda

route

a Number from1 to 10

Value (in originalunits)

Value (inoriginal units)

b

c

248. A strength of MCA, when done properly, is that it takes all offerings from stakeholders intoaccount. In fact, it is a stakeholder-driven process, and they are involved in all but one of the sixsteps. In the first step (“presentation and clarification of the conveyance route/technologyalternatives”) to be undertaken in a first workshop, the PMDSC will refine and clarify theroute/technology alternatives, based on previous work that has been undertaken to refine theRandenigala-Kalu Ganga route (Option 1), and the Polgolla to Moragahakanda route (Option 2). Thislist will be offered as a discussion starter, and stakeholders will have the opportunity to commenton its accuracy and completeness.

5.10.4.2 MCA Work Schedule

249. The proposed MCA work schedule is shown in Figure 9. The first workshop was held on 12February 2016. In this first workshop, stakeholders were asked to do two other things. First, theywere presented a complete list of comparison criteria. As long as these are not duplicative, any andall criteria were considered to be legitimate. Second, the stakeholders were asked to apply their

Page 64: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 56Page

values (also known in MCA jargon as “weights”) to each of the comparison criteria. This is becausestakeholders will have different understandings of how important each comparison criterion is inrelation to the others. Stakeholders were asked to “self-identify” according to their different maininterests, such as “environmentalist”, “power generator”, “government regulator,” etc. This willfacilitate sensitivity analysis at a later stage.

250. Through these criteria-listing and weighting processes, stakeholders perceive that theirinterests are being fully accounted for. The outcome of the first workshop was therefore acompleted “effects table”, with route/technology alternatives presented along the X axis of a matrix,and comparison criteria listed below on the Y axis, as shown in Table 6.

251. After the first workshop, the PMDSC has worked to fill out the effects table with “scores”(which are not to be confused with weights or ranking, as explained above). Depending on thenature and extent of both the route/technology alternatives and comparison criteria lists, thescoring procedure make take a full month. Scoring will be undertaken using as much quantitativedata as is available, although the MCA software program works equally well with mixed quantitativeand qualitative data. After scoring is completed, and the effects table is filled out, it will be possibleto undertake sensitivity analysis to show how the ranking outcomes might vary depending on whichweight sets are applied.

252. After the completion of scoring, the same set of stakeholders will be invited back for a secondworkshop, where they will be shown the computation of the route/technology rankings and theundertaking of sensitivity analysis, where interest group weight sets can be varied to see whetherthis has an impact on ranking.

5.10.4.3 Reporting

253. During the ADB Inception Mission it was agreed that the Phase 2 Inception Report and theRoute Selection Report – due in months 4 and 8 respectively – should be submitted simultaneouslyby month 6. This is a rational change insofar as the Phase 2 work cannot be fully planned until theroute selection has been finalised.

Figure 9: MCA Schedule

Page 65: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 57Page

5.11 Modelling

254. The accelerated program for route selection (see Section 5.10) necessitates the application ofthe existing ARPS (Acres Reservoir Simulation Package) water balance model used by WMS.Decisions for route selection can be sufficiently based on the existing model and would not besubject to re-evaluation by any new models. This current section describes the separatedevelopment of new modelling tools.

255. The ToR requires in Clause 59(i) “Developing a detailed and calibrated hydraulic model of themain conveyance systems of the fully developed Mahaweli System that will support planning,design, and management of the entire system. It should include accurate representation of allfeatures including gates, weirs, reservoirs, and main outlets to the cascade systems. The modelshould extend down to the head regulators of secondary canals within each system” and Clause59(iii) “Operating the above models for various time-steps ranging from hourly to monthly time-series. The results of these models will be used to finalize the designs of Phase 1 investments andfor selecting and finalizing the Phase 2 investments. The models will also be used by MMDE andother stakeholders for routine water management.”

256. Due to the acceleration of route selection (Section 5.10), application of the new models tofinalize Phase 1 and partially to confirm Phase 2 designs is no longer possible in view of the earlyneed of modelling at the initial stage of design work. Nonetheless, we consider model developmentas a separate sub-task under Task 7.

257. Furthermore, the description and intended purpose for modelling appears not fully in line withthe definition of a hydraulic model nor with the actual needs for water management of theMahaweli System or its components. Rather we think what is appropriate is a tool that could bedescribed as a “Mahaweli System Operations Model”, which would comprise several differentnumerical models serving specific purposes as part of an integrated decision support system (DSS).

258. Technically, a hydraulic simulation model could provide the user with the water level and flowrate at any location at any time throughout the underlying system. However, this would require verydetailed knowledge of the precise locations and dimensions of all hydraulic structures, includingreservoirs, rivers and primary and secondary conveyance canals. Main input would be cross-sectionsof all these structures at intervals between 200 m and 1000 m, which would have to be measured orderived first. A rough estimate of total length of the existing main conveyance canal networks isclose to 900 km (see Table 7). This level of field data collection and verification would beunrealistically time-consuming for MMDE and ID. Besides survey of cross-sections, detailedmeasurements of water levels and discharges would be required at multiple locations of eachstructure at different times in order to calibrate the model. River sections may further be influencedby natural or artificial (e.g., sand mining) morphological changes, so annual calibration at selectedsites would be required. The associated costs and overall timeline (minimum 12-18 months) tocollect the required data are excessive compared to the added value, which is considered minimalin general and not appropriate for seasonal and weekly water allocation and system operationdecisions.

Page 66: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 58Page

Table 7: Canal Lengths in the Mahaweli System

SystemCanals (km)

Main Branch

System B 53.0 72.0

System C 29.0 125.0

System G 5.0

System H 152.0 100.0

EMYE 33.0 146.0

System E 74.0 10.0

Minneriya 24.0

MKYE 32.0

Allai 30.0

Total 427.0 458.0

259. Nonetheless, the need to enhance present and future modelling capabilities for the MahaweliSystem operations is clear. Technically, we would classify such system operation models ashydrological or allocation models that can sufficiently and efficiently reproduce system behaviour atan appropriate time step.

260. The Mahaweli System can be characterised as a trans-basin diversion system that conveyswater from Mahaweli Ganga to the dry zone in the northern parts. Such large-scale and complexsystems can only be modelled with a suite of models covering different temporal and spatial scales,sharing a common database. The models may be linked to each other and iteratively executed.Building up of the models is a stepwise approach, starting from large spatial low temporal resolutionscale (regional/ macro models) to spatially constrained shorter time interval models (catchment/micro models), depending on the relevant questions and decisions to be taken for water allocation.

261. Future modelling capabilities tentatively identified in discussions with MMDE include peakoperation of hydropower plants, flood management and simulation of water allocation at microsystem level, i.e., downstream of main head regulators at anicuts or irrigation reservoirs. The PMDSCconsiders these as specialised applications of the system models that require refinements withrespect to shorter time steps and/or model extent and runtime.

262. As mentioned previously, the accelerated program for route selection necessitates theapplication of the existing ARSP water balance model applied at WMS. The ARSP is the principalmodel for water balance and allocation simulations developed in the 1980s. It represents the majorreservoir and water conveyance routes of the Mahaweli System. Water allocation decisions arebased on monthly evaluation of least system costs and is applied for seasonal planning and mid-term adjustments to system operation. However, the model is essentially a planning tool and cannotsatisfy future needs in terms of system operations.

Page 67: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 59Page

263. The following flow chart provides an overview to our principal approach to model suitedevelopment for the Mahaweli System.

Figure 10: Proposed Approach to Model Development for the Mahaweli System

264. Excluded in the above model development process is the setup of dam break models. Wepropose to consider this task as a work package applicable to each dam subject to detailed designscarried out in Tasks 2 and 3. A description of the dam break modelling approach is presented inSection 5.11.5.

Page 68: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 60Page

5.11.1 Baseline Assessment

265. The baseline assessment includes three tasks that can be processed simultaneously:

• Assess data availability for model input data and system characteristics database

• Evaluate existing models applied within WMS

• Identify and support the formulation of needs with respect to modelling and utilisation

of model output

266. The PMDSC is already working on these tasks (see Section 4.9.2 for present progress). A fulllist of data requirements is provided in Annex F.

5.11.1.1 Data Availability

267. The first task in the baseline assessment is to ascertain the availability of the data required forthe setup and operation of Mahaweli System Operations Model and supporting models. Dataconcerned include:

• Reservoir characteristics (e.g., volume and surface area curves, outlet rating curves)

• River and Channel characteristics (e.g., length, cross-sections, slope, roughness)

• Data on Irrigation Scheme (e.g., crop pattern, demand)

• Data on Hydropower Plants (e.g., head range and losses, efficiencies, operation)

• Hydro-meteorological data (e.g., rainfall, discharge, evaporation, temperature)

268. Due to different spatial and administrative responsibilities, data are scattered among thefollowing governmental authorities:

• Mahaweli Authority of Sri Lanka, Water Management Secretariat

• Ministry of Irrigation and Water Resources, Department of Irrigation, Hydrology Division

• Ministry of Irrigation and Water Resources, Department of Irrigation, Water

Management division

• Ministry of Disaster Management, Department of Meteorology, Data Archives Division

• Ministry of Disaster Management, Department of Meteorology, Agro-meteorology

Division

• Ministry of Power and Renewable Energy, Ceylon Electricity Board, Mahaweli Hydro-

power Complex

269. Due to the data being collected and archived among different authorities, we understand thatthe PMU would be in the best position to facilitate data collection and procurement. The PMDSCthrough PMU has already initiated the identification of data availability.

5.11.1.2 Assessment of Existing Models

270. Three models are available within the WMS:

• Acres Reservoir Simulation Package (ARSP)

• Acres Irrigation Demand Model (AIDM)

• DHI - Mike Customised (Mike)

271. The ARSP is the principal model currently being used for water balance and allocationsimulations. International Consultant Acres International Limited developed the model in the courseof the Mahaweli Water Resources Development Project in the 1980s. It represents the major

Page 69: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 61Page

reservoir and water conveyance routes of the Mahaweli System. Water allocation decisions arebased on monthly evaluation of least system costs. The model produces reliable results and is thecore for seasonal planning for and mid-term adjustments to the system operation.

272. AIDM is applied to generate irrigation demand, which is the key driver for water allocation.

Additionally, further tools are in use for the preparation of input data, e.g. HEC-4 to transfer gauge

rainfall data to inflow series at model nodes.

273. In the course of the Dam Safety Water Resources Planning Project within MASL, SMEC inassociation with Danish Hydraulic Institute (DHI) has developed the Mike Customised model. This isa tailor-made suite of software provided by DHI. The model is supposed to incorporate in a numericalsimulation platform (Mike) all capabilities of the models and tools presently used at WMS, i.e.,rainfall-runoff generation (HEC-4), irrigation demand determination (AIDM), water balance andallocation simulation (ARPS). However, WMS reports poor performance of the model and continuesto apply its old models.

274. The strengths and weaknesses of the individual models and tools will be assessed in closecollaboration with the PMU and WMS. Meetings held on 19 January 2016 and 27 January 2016 havealready initiated this process, and will be an important input to the subsequent step of model selection.

5.11.1.3 Identification of Modelling Needs

275. The identification of modelling needs runs simultaneously with the assessment of the existingmodels. Modelling needs are not restricted to the application, i.e., handling of the models. They alsoinclude the spatial and temporal resolution of the models in order to be able to reflect processesessential to system management and water allocation. This includes for example the shift frombaseload to peaking operation of the hydropower plants or temporary failures of gates. Pre-processing (e.g. generation of inflow data, determination of irrigation demand) and post-processing(e.g., system operation adjustment, reporting) are also key features.

276. We propose to update and finalize a HECRAS model of the UEC and have included additionaltime for the international Hydraulic Modelling Specialist (+2 MMs) and the national Senior DesignEngineer (Canals) (+1 MMs) to carry out this task.

5.11.2 Model Development

277. Two development paths are depicted in the flow chart. The primary development path relatesto the definition, selection, setup, and result analysis of the Mahaweli System Operations Model.The secondary development path covers supporting tools for the operations model as well asadditional data requirements.

5.11.2.1 Database Setup

278. Based on the available data and identification of data relevant for model setup, we will initiatedata collection through the PMU. For each authority in possession of relevant data, we will prepareand provide a list of data required. We expect that data will be provided free of charge to the PMUfrom WMS and the ID, and other agencies as appropriate. Data from some authorities may involvea small processing cost, depending on the type of data and period covered. Costs occurred will bepaid for and invoiced under the Provisional Sum for surveys and studies.

279. It is assumed that all data has been subject to extensive quality control by the responsible

authorities. Nonetheless, we will perform basic checks for consistency and completeness. All data

will be transferred to appropriate standard temporary formats for time series, tabulated data and

scalar information. Final formats can only be established after model selection. Section 6.3

addresses potential issues on data quantity and data quality.

Page 70: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 62Page

5.11.2.2 Model Selection

280. Based on the requirements of WMS, the shortfalls and proven features of existing models,and the data availability, the PMDSC will identify potential software candidates for the MahaweliSystem Operations Model for further evaluation. We will develop an evaluation procedure for themodel selection in consultation with WMS and other relevant stakeholder identified by PMU duringa workshop, considering at least the following criteria:

• Data pre-processing requirements, model preparation

• (Intuitive) formulation of operation rules for water balancing and allocation

• Ease of data exchange with other external model components, if applicable

• Provision of (statistical) methods and (graphical) tools to analyse system performance

• Automation of reporting, providing template tables and graphs

• Training

• Technical Support

• Costs

281. An upgrade of the present ARSP water balance and allocation model is not possible. The modelhas already reached its limit of allowable nodes and elements, and without the full source codeavailable this limitation cannot be lifted. Furthermore, Acres International - or Hatch, which hasacquired Acres in 2005 – confirmed that they no longer maintain the model.

282. The resources required for model setup greatly depends on the specific models selected. ThePMDSC will prepare a budget for the MMDE of the initial and running costs of the system operationmodel as part of the selection procedure subject to approval by PMU.

283. For the secondary development path for supporting models, i.e., the rainfall-runoff model andthe irrigation demand model, we will largely follow the selection procedure presented above.However, the supporting models are specialised models providing input to the system operationsmodel. Therefore, the number of candidates will be rather limited depending on the selected systemoperations model. We will address various aspects of the potential candidate software for thesupporting models during the workshop, while final decision will be made by the MMDE to ensurethe most efficient combination of tools while meeting Client’s requirements to the maximumfeasible level.

5.11.2.3 Additional Data Collection

284. Spatial and temporal availability of both rainfall and streamflow data indicate a considerabledeficit in particular in the northern region to cover the full range of catchment characteristics, whichis to be confirmed after complete feedback from the local authorities.

285. After seeking agreement from the PMU, we will discuss together with the WMS means tocompensate this data deficit. Any persisting deficit will directly affect model uncertainty due to lackof information for calibration and verification of model performance.

286. One option is the implementation of a measurement program. The WMS has equipment andstaff to execute this task. The measurement campaign would at least partially cover a wet and a dryseason. The PMDSC will identify respective impacts on time and cost schedules, and discuss furtheractions with PMU.

Page 71: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 63Page

5.11.2.4 Model Setup

287. Once the appropriate software has been selected, the planning and development of the

Mahaweli System Operations Model may commence, and subsequently the identification of the

supporting models depending on actual needs and data adequacy. As far as data availability allows,

the models will be calibrated and verified against observed measurement data.

288. The Mahaweli System Operations Model is envisioned to be based on the concept of a least

cost optimisation applicable at each monthly time step drives the water allocation in the present

water balance and allocation model. Each release decision is associated with a penalty (cost), e.g.,

minimum flow requirement, maximum channel capacity, or change in storage zone, reflecting

prioritisation of the allocation.

289. Another option to decide on allocation is to formulate more intuitively understandable rulesthat would be triggered at each (applicable) time step. The decision and requirement for theformulation of the system operation is fundamental to the selection of the model.

290. Present seasonal and short-term operation decisions rely on the output of the existing model,which has proven its applicability to capture system behaviour (although due to the operationalsetup, system behaviour, i.e. releases, are driven by the model output). Thus, the output of thepresent model will serve as a benchmark to test any new model.

291. The general modelling time step will be one day. Special attention is required for hydropoweroperation, which is mainly peak power generation during a few hours per day. Most models canadequately reflect such operation on a daily time step. However, at e.g. Polgolla diversion, the intra-daily hydrograph fluctuations along with limited storage capacity to absorb these fluctuations maylead to spilling and/or non-fulfilment of full diversion requirements at shorter-than-daily timeintervals. It needs to be studied to which degree and probability such conditions occur and how toreflect this at daily time step. An hourly time step for the full water balance and allocation model iscomputationally expensive and will hardly provide any additional benefits for the seasonal to weeklyplanning for systems operation.

292. The spatial extent and degree of detail with respect to structures will initially be the same asfor the present ARSP water balance and allocation model.

293. Irrigation Demand Model: The irrigation demand model considers assumed rainfall, irrigated

area, different crops and related specific demands, and to some degree also crop pattern. Any new

model will as a minimum provide the same capabilities. However, it is understood that in particular

staggering, i.e., a marginal shift of cultivation steps to enable maximum use of available resources,

as well as more flexibility in the type of crops considered is desired. In general, the applied model

needs to be transparent also in terms of communicating and reflecting the constraints and demands

of local farmer communities in order to facilitate support and acceptance of the water management

decisions, which could impact on the type of crop and extent of cultivated area for the next season.

294. Rainfall-Runoff Model: The rainfall-runoff model converts rainfall data to inflow at nodes of

the water balance model. Rainfall data may be spatially disaggregated from observed gauge

measurements, short- to mid-term forecasts or estimates reflecting climatic change. Depending on

the needs, we will establish interfaces to the respective data sources.

295. The most critical aspect in model setup is the calibration and verification of model behaviour.For large basins, model behaviour is derived at selected representative sub-catchments forinterpolation to the full area.

Page 72: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 64Page

5.11.2.5 Data Analysis

296. Essential for any system operations decision is a good understanding and interpretation of themodel result data. Together with the WMS and other relevant stakeholders identified by the PMUwe will elaborate key parameter and system information and associated presentation in tables andgraphs during a workshop.

297. Efficient automation of the generation of such output will shift resources from output

preparation to output interpretation. Thus, different and/or more detailed operation decisions may

be discussed to facilitate a more efficient and accepted water allocation amongst various stakeholders.

5.11.3 Model Extension

298. Based on the basic models development, we see further potential in the application of themodels respectively in additions to enhance model capabilities.

5.11.3.1 Special Applications

299. The main water balance model may be adjusted to facilitate flood management and to studylocal effects of hydropower peaking. To do so, the temporal resolution (hourly), the spatial extent(e.g. hill region to Minipe) and the operation rules need to be adjusted to meet the respectiverequirements.

5.11.3.2 Forecasting

300. During initial meetings, several additional features have been discussed that can provideadded value to the system analysis and operation. In particular forecasting capability along withstochastic modelling and analysis has been identified as key improvement. In particular the rainfall-runoff model respectively its link to input databases need to adjusted. This would also enable tostudy effects of potential climatic change.

5.11.3.3 Micro Models

301. Micro models are detailed models of specific irrigation areas, e.g., existing systems, NCP orNWP. These models can be implemented with the same software as the main water balance andallocation model. They will cover the main distribution channels and related tanks.

302. Integration into the main model will be an iterative process. First, the micro models willoperate stand-alone with no upstream limitation in order to determine the system demand. Thissystem demand will then be introduced at the respective downstream node of the main model tocheck system supply. In case of a deficit, the micro models and respective local demands will haveto be adjusted. It needs to be mentioned that performance of the micro models can only beconfirmed when sufficient measurement data at critical locations are available.

303. The micro models are considered an ideal point to hand-over model development to the Clientbut will require capacity building to ensure the long-term success of the effort. Hands-on applicationand implementation of the gained knowledge is the most efficient means of consolidating theexperience gathered and transferred during workshops, training and discussions along the modeldevelopment process.

5.11.4 Substantiation of the Approach

304. Our suggested approach for model development presented above develops further theoriginal brief description in the PMDSC’s ToR and encompasses many details and decisions that havebeen arrived at collaboratively in discussions with multiple agencies. Our proposal is based on the

Page 73: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 65Page

actual needs identified so far, and we are of the strong opinion that the project will benefit from theplanning steps outlined here that underlie such a complex and large-scale modelling effort.

305. Together with the PMU the next step is to define which components of the modelling will beimplemented under both of the following packages that will be supervised by the PMDSC:

• Strengthening Integrated Water Resources Management (SIWRM)

• Mahaweli Water Management Software and Control Centre (MWMSCC)21

306. Subject to Tranche 3 proceeding (ToR Clause 11), the SIWRM is proposed as follows: “Thisconsulting services package seeks to promote the strengthening of IWRM principles both within theinvestment program area and nationally, including recommending and supporting strengthening ofwater resources management and irrigation sector policies, legislation and institutions. This will beachieved through the review of current policy and legal frameworks, benchmarking of key watersector institutions, and formulation of recommendations and guidelines for improvements toinstitutionalize IWRM. This activity will also support: (i) updating of current water resourcesmanagement master plans to include the completed MDP incorporating analysis of climate changeimpacts and water management practices for dry periods; (ii) possible crop diversification andimpacts to scheme designs and management; (iii) assessment of the water demands of, andmanagement of, other major water users including the environment; (iv) design, development andimplementation of an IWRM decision support system; and (v) updating and modernizing the WaterManagement Secretariat under the Mahaweli Authority of Sri Lanka (MASL).”

307. We understand that the present task for the PMDSC is to define modelling needs, develop asuitable approach and prepare specifications for bid documents rather than to write software toimplement new models. A revised ToR for the Modelling Specialist is proposed in Annex H reflectingthe recommended approach. However, if the PMU has identified increased requirements for earlyimplementation of new modelling tools and will provide the substantial amount of field-verifiedcalibration data, the PMDSC is prepared and qualified to promote and undertake this development.The resource requirements of the PMDSC may need to be adjusted to accommodate the challengingprogram depending on the final structure of the model development and of the models selected.Due to the complexity of the task, such estimates could only be made reliably after main modelsetup, as it builds and relies upon work achieved.

5.11.5 Dam Break Modelling

308. Simulation of dam breach events and their resulting floods are crucial to characterizing andidentifying threats due to potential dam failures, in particular for dams close to downstreamsettlements where there is potential for loss of life. On the other hand, following standard designguidelines and construction methods will minimize the risk of dam failure to the extent possible.

309. The dam break analysis can be split into the following tasks:

• Identification of the breach mechanism of the dam

• Analysis for prediction of the flood wave initiating at the dam and travelling indownstream direction

• Estimation of inundation levels and damage to downstream structures

310. There is a variety of methods and numerical models available for routing the dam break floodthrough the downstream valley. Normally, the dam-break flood analysis is performed by means ofan appropriate hydrodynamic flood routing analysis. Standard software packages (e.g. MIKE11, HEC-RAS) are available with the Consultant to setup a respective hydrodynamic model. Usually, an

21 Comprises the UEC-ICB-6 package.

Page 74: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 66Page

implicit, finite difference scheme for the computation of unsteady flows in rivers is applied todescribe subcritical as well as supercritical flow conditions, able to adapt to the local flow conditions(in time and space).

311. The numerical model will be calibrated with the roughness coefficient. For calibration, a waterlevel vs. discharge curve would be required, or otherwise the roughness coefficient must beestimated by visual observations and engineering experience, which should be satisfactory for a dambreak analysis with its large over-bank flows. A sensitivity analysis will be conducted to address howalternative parameters for outflow discharge, time of failure, initial reservoir conditions, downstreamchannel and over bank roughness, calculation time-step, the cross sectional distance, etc. affect thecomputed flow depths in the downstream area.

312. Of particular interest for a dam break analysis is the flood routing along the downstreamreach, i.e. the reduction of the peak discharge (attenuation) as it moves downstream, the travel timeof the flood peak between points of interest; the maximum water stage at points of interest (bridges,temple sites), and the change in shape of the flood hydrograph as it moves downstream.

313. The output of the numerical model will be a view along the downstream river of the variationof water levels and/or water depth with time. At selected locations, the passing dam break flood willbe plotted as water level versus time.

314. The inundation map will provide a description of the spatial extent of flooding that would beproduced by the dam break flood. The inundation map will delineate the areas that would beflooded as a result of dam failure.

5.12 Resettlement

5.12.1 Priority Actions for Tranche 1

315. The resettlement specialists will carry out the following general tasks for Tranche 1:

• In close coordination with design team, identify changes on detailed design of all sub-projects under Tranche 1 to ensure whether the change in design will change the preparedRP, or will cause the need to prepare a new RIP.

• Review whether the detailed design or/and change design on sub-projects and also theneed of access road for construction works, will lead to the need to update the existing RIP;if update is needed provide detail plan on when to be done and when to be completed(bearing in mind its link between the approval and implementation plan of RIP andprocurement process)

• Oversee the sub-project activities under Tranche 1, to ensure its compliance with ADB’sInvoluntary Resettlement (under SPS 2009)’s requirements. If it is not certain whether anRIP is needed, a due diligence report will be prepared. Based on due diligence report,prepare RIP if it is needed (e.g., for Minipe).

• Oversee the implementation of the RIP and link it with procurement process to ensure whencontract will be awarded an adequate clear area is available for civil work to systematicallyimplemented by providing advices and assist PMU to expedite a process in obtaining seriesof approval from the government

• Guide contractors to comply with RIP, in the case they will need a land for establishing aconstruction camp, storage for construction materials or machineries, and other needs tohave temporary land to support their works

• Assist the PMU in implementing the RIPs, especially in keeping record on its implementation,and preparing a progress report in implementing RP for submission to ADB

• Assist PMU in implementing GRM by keeping records and reporting

Page 75: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 67Page

5.12.2 MLBCRP

316. The following issues related to involuntary resettlement under the MLBCRP were identifiedduring the ADB mission:

• The reservation areas (government owned riparian areas along both sides of the canal)along this 74-km long canal have been encroached by farmers who mostly have land titlesadjacent to the reservation areas.

• The Farmer Organization Leaders have given an assurance that all encroached farmers willvoluntary give up their agricultural activities during the construction period, if they arerequired to allow the Contractor’s access to the canal and works sites. However, the FarmerOrganization Leaders believe it is not their responsibility to request or enforce theencroached farmers to stop their activities in related reservation areas.

• The PIU has not directly approached and consulted these farmers, and has no record of theencroached farmers.

317. ADB has advised the following actions are required:

• A due diligence report should be prepared to determine whether a RIP will be needed. Thedue diligence report, or RIP if needed, should be submitted to ADB for approval prior toawarding civil works.

• Since the first civil works package to be awarded (MLBCR-NCB-01) will be awarded in April2016, the due diligence report for MLBCRP will be prepared as two reports: (i) the first duediligence report will cover 0 to 30+140km; and (ii) the second due diligence report will cover30+140 to 74+000km.

• The inventory of encroached farmers will be carried out with support from the FarmerOrganization Leaders.

• The agreed preparation schedule for the first due diligence report will be as follows: (i) aninventory data encroached farmers will be undertaken between 25 February to 15 March2016; (ii) the PIU will hold a consultation meeting with encroached farmers by 20 March2016; (iii) the PIU will submit a draft due diligence report to ADB by 25 March 2016; and (iv)the PIU will officially submit the final due diligence Report by 4 April 2016. The PMDSCresettlement specialists will support the PIU with completing these tasks.

• The second due diligence report will be prepared and submitted to ADB in time to ensurethe report is approved by ADB prior to awarding associated civil work contracts.

5.12.3 NWPCP

318. The RIP for the NWPCP will have to be updated and contracted for the first civil works package.The ADB mission has noted that in-depth consultations PAPs on the RIP should have been carriedout to raise their awareness of the program. It is important the PIU now supports this consultation.The following issues are related to involuntary resettlement under the NWPCP:

• The needs of requiring access roads that involve temporary land acquisition should be takeninto account with the RIP.

• A cost to rehabilitate existing roads that will be used for transporting construction materialsand equipment should be included under total project costs.

• Detailed design is being revised and changed, for example: (i) 8+900 to 9+300km; (ii) 14+000km replace aqueduct, and (iii) between 17+000 and 17+500 km. The RIP needs to beupdated to account for these changes.

• The possibility of moving the planned canal alignment should be explored between 9+300to 17+000 km to account for a local resident who does not wish to be resettled orcompensated.

Page 76: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 68Page

5.12.4 For Preparation of Tranche 2 and 3

319. The resettlement specialists will carry out the following tasks for Tranches 2 and 3:

• Ιn close coordination with engineering group, identify potential involuntary resettlementincluding land acquisition for both permanent and also temporary, and update the RIP inaccordance to the government’s requirements and to comply with ADB Safeguard PolicyStatement (SPS), 2009

• The RIP has to be prepared by systematically done with clear methodology for inventory oflosses, socio-economic survey of project affected people to be used as basis to identifyvulnerable group, livelihood improvement program, relocation or the need of resettlementsite if any. The RIPs have to be updated with adequate consultations with project affectedpeople, and consultation meeting has to be recorded, in terms of attended and subjectdiscussed and solved

• Ensure that RF for the MFF will continually cater for the issues related with resettlementdue to sub-projects in Tranches 2 and 3, and revise RF if necessary to be part of submissionPFR for Tranche 2

Page 77: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 69Page

6 PROGRAM IMPLEMENTATION PLAN

6.1 Government Actions

6.1.1 PMU/PIU Staff Recruitment

320. It will be important for the foreseen staffing build-up of the PMU and PIUs to be completedearly, so that there are no negative impacts on progress resulting from staff being unavailable forfulfilling particular responsibilities. One example is the recruitment of safeguards staff, whoseinterventions will be essential in processing of applications for environmental approval of variouscomponents of the Program. They have a leading role to play in implementing the EMPs and theresettlement activities. For Phase 2, they also have a role to play in meeting the expectations/requirements of CEA, because more EIAs will be submitted for the Phase 2 feasibility studies.

6.1.2 Human-Elephant Conflict

321. In the EIA reports prepared for UEC and NWP, it was recommended that the “IUCN MasterPlan for Integrating Wildlife Management into the Water Resources Development: AddressingHuman Elephant conflict” related to the Program should be implemented as part of theEnvironmental Safeguard Implementation procedure for Tranches 1 and 2. It is noted thatcompletion of the safeguard procedures for Tranche 1 is likely to be a condition of approval ofTranche 2. However, the study has not yet been initiated and it is unlikely that the study can becompleted prior to commencing Tranche 1 implementation, since implementation has in effectalready started with the tendering of MLBCR-NCB-1 and the imminent tendering of more packages.Failure to implement the study could handicap MMDE’s ability to satisfy the ADB requirement onintegration of Wild Life Management into the Water Resources Development under MWSIP. HECmanagement options have to be addressed in the implementation of the EMPs to comply with bothADB and government environmental safeguard policies.

6.1.3 MMDE and ADB Approvals

322. The environmental approval from the TEC of the CEA on the IEE for the proposed raising ofthe Minipe Anicut and MLBCR was given with some conditions, and the approval for the EIAs on UECand NWP is in progress followed by the public consultation. The ADB clearances for the respectiveIEE and EIA reports were already given and ADB has advised that revisions be submitted as anaddendum, with revised EMPs, where necessary. Appropriate design changes are required tocomply with the conditions given by the DWLC for MLBCR project in relation to the position of“Environmental Flow Tube” at the existing LB canal silt excluder.

323. Table 8 shows the current status of EIA approvals. The final approval from CEA for the EIAs forthe UECP and NWCP are still pending.

324. Table 9 shows the status of Tranche 1 bid documents review and approval by the PMU and ADB.For some Tranche 1 construction packages, the MMDE’s TEC reports were received after ADBapproval, which led to the requirement to carry out additional review and modification work by thePMDSC to resolve differences between the recommendations and requirements of the two entities.22

It will be advantageous if all future TEC reviews can be completed prior to receiving ADB’s conditionalapproval so that the finalisation of tender documents can be carried out efficiently and effectively.

22 The following 5 bid packages were submitted by MMDE to ADB during 2015 for final approval: MLBCR-ICB-1, MLBC-NCB-1, NWPC-ICB-1, NWPC-NCB-1, and UEC-ICB-1. Of these only the MLBCR-NCB-1, NWPC-NCB-1 and UEC-ICB-1 werereviewed by the relevant TEC.

Page 78: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 70Page

Table 8: CEA and ADB Approval Status (12 February 2016)

Project CEA ADB Other Approvals Further Actions

MLBCR 16.10.2015 - conditionalapproval given for the IEEE.The conditions laid by theDWLC as a part of CEAapproval to be incorporatedinto the designs.Addendum to be sent to theCEA addressing all the designchanges.

Approval granted andpublished IEE on theADB website.The updated EMP to besubmitted along withthe revised technicaldetails/ design changesas an addendum to thesubmitted IEE.

Approvals for thefelling of treesobtained from thedivisional secretariat(DS) Minipe on23/04/2015.NBRO approvalobtained forlandslide hazardverification in Oct2014.Both approvals areannexed to theapproved IEE.

CEA to be informed with thedates of commencement of theproject activities, including thephase implementation schedule(Clause 1.6 of CEA approval).Measures to be taken todemarcate the 100 mreservations from the FSL of theMinipe pool, left bank canal withthe irrigation department.Reforestation boundarydemarcation to be carried out inconsultation with the irrigationdepartment and DWLC.Reforestation /enrichment areasto be clearly marked on a mapand submitted to CEA and forestdepartment along with theplanting schedule (clause 2.4 ofCEA approval letter).Preparation of a detailed EMPand monitoring planincorporating the mitigatoryactions precisely according to thework plan and any designchanges, and submit to CEA forthe approval of the monitoringcommittee appointed by the CEAprior to the commencement ofconstruction.

UEC EIA was opened for publiccomments.Addendum on the queriessubmitted on 12/01/16.CEA approval pending.

Approval granted, andpublished EIAR on theADB website.The updated EMP to besubmitted along withthe revised technicaldetails/ design changes(if any) as an addendumto the submitted EIAreport after receivingthe CEA approval.

NBRO approvalobtained forlandslide hazardverification andsubmitted to CEA asan addendum inJanuary 2016.Archaeologicaldepartmentclearances attachedto the draft EIA.

A survey to identify the numberof trees to be cut down and theappropriate approvals to beprocessed.Reforestation boundarydemarcation to be carried out inconsultation with the irrigationdepartment Forest Dept. andDWLC.

NWPC EIA was opened for publiccomments.Addendum on the queriessubmitted on 29/01/16CEA approval pending.

Approval granted, andpublished EIA on theADB website.The updated EMP to besubmitted along withthe revised technicaldetails/ design changes(if any) as an addendumto the submitted EIAreport after receivingthe CEA approval.

NBRO approvalobtained forlandslide hazardverification andsubmitted to CEA asan addendum inJanuary 2016.Archaeologicaldepartmentclearances attachedwith the draft EIA.

A survey to identify the numberof trees to be cut down and theappropriate approvals to beprocessed.Reforestation boundarydemarcation to be carried out inconsultation with the irrigationdepartment Forest Dept andDWLC.

RKTCPhase II

BIQ submitted to CEA on21.11.2012. Request lettermade to Archaeological Dept.for necessary Assessments;CEA responded on 06.12.16stating to get the DWLCconsent prior to issues the ToR.

Not yet submitted.

Page 79: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 71Page

Table 9: Status of Bid Document Preparation and Review by ADB and PMU

No Package Description Submitted to PMU*Comments from

TRC/PPTAComments from ADB Comments from PMU/TEC Remarks

1 MLBCR-ICB-1 28 May 2015 19 December 2014 -TRC5 December 2014 - PPTA

9 February 201513 July 2015

5 November 2015, PMUinstructed to carry out adesign change (Ogee Weir)

2 MLBCR-NCB-1 28 May 2015 16 July 2015 30 December 2015 Bid evaluation in progress

3 MLBCR-NCB-2 28 May 2015 Not reviewed by TRC/TEC - - Design review by PDMSC

4 MLBCR-NCB-3 28 May 2015 Not reviewed by TRC/TEC Design review by PDMSC

5 MLBCR-NCB-4 28 May 2015 Not reviewed by TRC/TEC Design review by PDMSC

6 MLBCR-NCB-5 Not submitted

7 UEC-ICB-1 28 May 2015 29 October 2014 - TRC6 December 2014

27 October 2014 - PPTA11 February 2015 - PPTA

4 May 2015 - PPTA

13 July 2015 6 August 2015 - PMU5 November 2015 - PMU

1 January 2016 - TEC

Final submission by 10th

February 2016

8 NWPC-NCB-1 28 May 2015 22 October 2014 - PPTA 12 November 201424 July 2015

5 November 2015 - PMU24 December 2015 - TEC

Final submission by 12February 2016

9 NWPC-ICB-1 28 May 2015 17 February 2015 - PPTA 27 July 2015 5 November 2015 Bids called for additionalGeotechnical investigation

10 NWPC-ICB-2 28 May 2015 Not reviewed by TRC/TEC

* By the Mahaweli Consultancy Bureau (MCB)

Page 80: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 72

6.2 Procurement Issues

325. The number of vehicles to be provided under the PMDSC’s indicative Provisional Sum budget(12 vehicles and 16 motorcycles) is inadequate for the effective supervision of the number of civilworks packages that will be implemented concurrently. It has therefore been proposed to the PMUthat additional vehicles for the Engineer’s use be included in bid documents. In addition, the firstquotations received for vehicle purchase indicate that the actual budget has to be increased toapproximately double for the planned number of vehicles. The PMU has initially indicated thatgovernment restrictions on the purchase of new vehicles mean that additional vehicles will have to beprovided by renting/leasing. The impact of this decision and the calculation of associated vehiclenumbers has not been fully assessed.

6.3 Modelling

326. The PMDSC will continuously follow-up with the PMU and relevant authorities for theassessment of data availability and subsequent collection of relevant data. We will require supportfrom the PMU to enable and accelerate this process at inter-governmental level, in case weanticipate substantial impediments or delays for the progress of Task 7. We may also seek supportin the procurement and negotiation of costs for data acquisition from authorities.

327. Depending on data availability for the setup of the proposed rainfall-runoff model, additionalfield measurements may be required. If deemed necessary, the PMDSC will elaborate a program fora measurement campaign subject to discussion and approval be PMU, including utilisation ofequipment and staff available with MASL.

328. The resources required for model setup greatly depends on the specific models selected. ThePMDSC will prepare an update on the time and cost budget for model development as part of themodel selection procedure and after the setup period, subject to approval by PMU.

6.4 Revised Staffing Schedule

329. A revised staffing schedule for the Time-based part of the Program (i.e., Tasks 1, 3, 4, 5 and 7)is included in Annex G. An addendum to the PMDSC’s contract includes the new staffing plan. Therevisions to the staffing work plan are justified on the basis of the government’s objective ofaccelerating the construction of the KMTC and UEC, and are a critical requirement to reduce therisks of delays in implementation. In addition the scope of the PMDSC’s services have increased asdetailed in this report. These additional inputs are necessary to support the PMDSC’s assistanceduring tendering, supervision and management of the KMTC, plus the other tasks that have beenadded to the scope of the PMDSC.

6.4.1 Staff Replacements

330. Two replacements for International Key Experts have already been approved by the PMU dueto medical reasons:

• Communication Specialist – Mr. Darryl Kuhnle

• Environment – Dr. David Annandale

331. In addition, on 18 December 2015 the PMDSC submitted to the PMU the CVs for highlyqualified replacement candidates for the following national Non-key Experts who are no longer

Page 81: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 73

available for their assignment due to the delay in mobilisation of the PMDSC and further delays inthe planned commencement of construction activities:23

Senior Surveyor - 1 (MLBCR)Senior Surveyor - 2 (NWPC)Senior Surveyor - 3 (UEC)Assistant Design Engineer - 7Engineer Assistant (Construction Supervision) - 8Engineer Assistant (Construction Supervision) - 9Engineer Assistant (Construction Supervision) - 12Assistant Mechanical and Electrical Engineer - 1Survey Assistant - 4Draftsperson – 3 and 4

6.4.2 Staff Inputs from Home Office

332. It has become apparent that the input of some specialists will be required on an intermittent“as required” advisory or short-term basis that does not justify travelling to Sri Lanka on each andevery occasion where input is required. Examples are some parts of the international inputs of theProcurement and Contracts Specialist, the Modelling Specialist and some of the Design specialists.The new staffing schedule included in Annex G shows the proposed Home Office time allocationsfor selected International Key Experts. Corresponding reductions for the associated reimbursablecosts are reflected in the contract addendum.

6.4.3 Re-scheduling of Supervision Staffing

333. As discussed previously, the number of construction contracts ready for award or already inprogress was less than expected at the start of the Program, therefore, in the updated staffingschedule corresponding re-scheduling has been made to the site staff. In addition, the timing formobilisation of some international and national Key Experts has been adjusted to reflect the plannedstart of construction for the civil works packages as shown in the updated Implementation Schedule.The re-scheduling also considers it more beneficial to employ site supervision staff on a full-timebasis, when practical.

6.4.4 Proposed Additional Inputs

334. During the inception phase, the PMDSC has identified some additional requirements forinternational Non-Key Experts for the Time-based tasks in the increased PMDSC budget to befinanced using the Contingency Provisional Sum. This will permit the PMDSC to optimise the workplan in accordance with the actual needs of the Program, which centres on ways to finish theconstruction of civil works on an accelerated implementation schedule at the request of thegovernment (refer to Annex A). Reasons for the additional staffing inputs include (i) the accelerationof the construction of the KMTC; (ii) the inclusion of the Kongetiya Level Crossing in the UEC bidpackage; (iii) carrying out the assessment of the existing dams and level crossing that will be part ofthe constructed works in the project areas; (iv) preparation of a Program Fund DisbursementHandbook; and (v) the recommended new specialists as explained below.

335. Preparation of the Phase 2 feasibility-level NCPCP designs comprises major civil and electro-mechanical works, including three large dams and associated hydro-power stations. The proposedstaffing requirements for the PMDSC were based on the perception of the likely scope of the MWSIPwhen the PMDSC proposal was prepared. Based on our findings during the inception phase, we havea better understanding of the government’s requirements and priorities.

23 In the ToR the original commencement date for the services of the PMDSC was June 2015.

Page 82: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 74

336. In addition to re-programming the timing and duration of some specialist’s inputs to optimisethe work plan we have identified additional inputs that are required. The ToRs for additionalproposed international Non-key staff include:

• Hydropower Engineer (Civil Designer): The preliminary review of the pre-feasibility leveldesigns for the hydropower stations in Phase 2 including Lower Uma Oya (10 MW), Hasalaka(9.3 MW) and Heen Ganga (2.25 MW), indicates the need for detailed review and updatingfocused on their civil construction designs. This particular focus on the infrastructuredesigns of these power stations is not well-covered in the PMDSC’s current ToR. Theproposed specialist’s ToR includes: to review the feasibility studies from the viewpoint ofoverall engineering aspects, design and cost; plan hydropower design works; preparegeneral and technical parts of the civil works in the updated feasibility-level designs.

• Geotechnical Engineer (Investigations): to assess the adequacy of geotechnicalinvestigations carried out by contractors; determine whether dam instrumentation andmonitoring is consistent with bid document requirements; and prepare technical notes, asnecessary, advising on the completeness and accuracy of interpretation of fieldinvestigations in the design of below ground engineering works. This is particular importantfor the KMTC because our close supervision of the investigation program carried out duringconstruction will help reduce the risk of delays and cost overruns.

• Mechanical Engineer (Turbine Designer): The PMDSC’s initial review of the pre-feasibilitylevel information prepared for Phase 2 indicates that the turbine designs for thehydropower stations at Lower Uma Oya (10 MW, Francis type), Hasalaka (9.3 MW, Peltontype) and Heen Ganga (2.25 MW, Kaplan type) Reservoirs need to be reviewed andconfirmed with the final design criteria, which requires a turbine engineer. This criticaldesign task is not adequately resourced in the current ToR. The specialist’s proposed ToRincludes: to review and finalize the designs for the electro-mechanical equipment as part ofa detailed engineering study of turbine design and performance; examine methods ofmechanical (turbine) equipment procurement, installation and testing; finalize feasibility-level cost estimates of mechanical (turbine) equipment based on the implementationschedule for detailed design, transportation and installation work of mechanical equipment;and support the Hydropower Engineer prepare technical designs for the mechanicalequipment.

• Senior Design Engineer (Canals): to review and finalize the designs for the UEC levelcrossings and update the bid packages according to the final embankment heights andmodified spillway designs. The PMDSC’s current ToR does not include an internationalspecialist for this position, but as mentioned elsewhere in this report the Consultant hasdetermined that the national specialists need intensive support to ensure the final designsfor the level crossings are robust.

• Hydraulic Modelling Specialist: to analyse and update the HECRAS simulation modelpreviously prepared for the UEC. In addition, it is proposed that this specialist carry out thedam break study for the Phase 2 dams instead of the Modelling Specialist, which includethree major tasks: (a) development of dam break model; (b) defining alternative dam breakschemes; and (c) risk assessment of a flood. The modelling specialist is also required for thedam assessment.

• Senior Geotechnical Engineer (Dam Expert): A short input is proposed to provide specializedexpertise in order to assess and investigate design alternatives for dam designs in terms ofconstructability and potential risks; assess the adequacy of investigations program andprovide quality assurance/quality control practices for NWPCP dam construction andmodification, and a determination with respect to whether designs and completedconstruction are completed in conformance to requirements.

Page 83: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 75

337. The input for the Social and Resettlement Safeguards Specialists is proposed to be increasedby 1 MM in order to address the deficiencies in the existing PSA that were identified by ADB duringthe inception mission (refer to revised ToR in Annex H).

338. The input for the Communications Specialist is proposed to be increased by 2 MM. Thejustification for this is based on the existing capacity in the PMU for managing such a largecommunications program budget, along with the urgent need to support professional engagementwith a multi-level assortment of stakeholders, particularly the PAP and beneficiaries. ADB has notedin their Aide Memoire that the alternative is to increase the number of communications personnelin the PMU. This increased staffing will allow the PMDSC to provide the additional support tocommunicate the important lessons from the ISEWP consultancy package, which is critical to theMWSIP’s objectives of increasing agricultural productivity throughout all Mahaweli systems.

6.5 Financial Issues

6.5.1 Proposed Staging of Payments for LS Deliverables

339. A tentative payment schedule has been worked out for the Lump Sum deliverables as shownin Annex I. This payment schedule is consistent with the percentages for each Lump Sum deliverablein the PMDSC’s ToR and the proposed implementation schedule.

6.5.2 Provisional Sums

340. The PMDSC budget includes Provisional Sum budgets for (i) vehicles and motorcycles; (ii) surveysand studies; (iii) office equipment; (iv) meetings, workshops and training; and (v) communicationsmaterials (refer to Table 7 of the Consultant’s ToR).

341. Vehicles and motorcycles: As mentioned in Section 6.2, the available budget is inadequate forthe number of vehicles needed to properly supervise the works, and to support the deployment ofstaff doing field work, attending meetings and holding workshops in project areas. The Consultant’sprojection is that the available budget will be sufficient for procurement of 6-7 vehicles during 2016.Therefore, the budget for procurement of vehicles must be increased or the construction contractsbe amended to include vehicles for the use of the PMDSC.

342. Surveys and studies: Tenders have been floated for geotechnical investigations and bidevaluations are ongoing (refer to Table 2). The Consultant will use the shopping procurementmethod and obtained three quotes for each tendered package. We anticipate that the investigationsnecessary for finalizing the civil works packages will all be tendered during 2016. When theconveyance route for Phase 2 is confirmed, the PMDSC will prepare a proposal for the additionalinvestigations required for the Phase 2 designs. We expect there to be some savings in this budgetthat may be available for re-allocation to other provisional sums to meet further requirements suchas vehicles or office equipment.

343. Office equipment: This budget is for the procurement (shopping method) of office equipment(printers, servers, copy machines, computers for support staff, etc.) for the PMDSC’s offices. TheConsultant has developed detailed specifications and is obtaining quotations for the supply,installation and servicing for a computer server and accessories for the Colombo office. The ITsystem for the Colombo office, which will be occupied by up to 50 staff at peak periods, will be amajor expense and use the available budget of $50,000. Providing similarly equipped IT systems forthe site offices will exceed the available budget, so the Consultant proposes to use re-allocated fundsin the amount of $100,000 from the surveys and studies provisional sum.

344. Meetings, workshops and training: The PMDSC has already held the first workshop for theMCA process in February. Workshops and training sessions are a core part of Task 4 (Capacitybuilding) and Task 5 (Communications), but they also will be a regular feature of the entire program’s

Page 84: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 76

activities. It was mentioned in the PMDSC’s proposal that the available provisional sum may not besufficient for the full five years of the contract period, but for the medium-term period no requestfor an increase is anticipated.

345. Communications: The PMDSC’s Communications specialists are preparing a work plan,including identification of appropriate media and channels of dissemination that will convey prioritymessages to key stakeholders. One priority is assisting the PMU to develop and hosting a programweb site. The SCS Implementation Note will provide an updated budget to reflect the revisedactivities and workplan.

6.5.3 New Tax Rates

346. The rates for the Value Added Tax (VAT) and Nation Building Tax (NBT) have been revised bythe Department of Inland Revenue with effect from 1 January 2016.24 All local indirect taxes arereimbursable to the PMDSC by the government, which are in addition to the ceiling amounts of thecontract for consultancy services. The effect of the NBT increase (present and future) on the PMDSCand our sub-consultants represents an incalculable cost to the Program. The MMDE is advised toapply for general tax exemption of the MWSIP.

347. The MMDE has instructed that the new VAT rate (12.5%) be incorporated into the biddocuments.

6.5.4 PMDSC Offices

348. The PMU initially selected locations for the Project Offices at Madatugama, Kurunegala, andHasalaka for the UECP, NWPCP, and MLBCRP, respectively. Alternate locations at Elahera andPolpithigama have also been proposed by the PMU for the UECP and NWPCP, respectively. Theoffices for PMDSC staff need to consider the available accommodations in the nearby vicinity, aswell as travel time to the construction works.

349. The PMDSC has informed the PMU that the Project offices for the Resident Engineers andtheir staff (e.g., Concrete Engineer, Surveyor, Quantity Surveyor, Assistant Design Engineers, etc.)need to accommodate 20-25 people during peak periods, taking into account regular use by thedesign and safeguards teams who will also be in the project areas supporting the preparation ofPhase 2. As per the requirements in the ToR, the PMDSC has included provisions for running costsfor four offices in their financial proposal (1 main office in Colombo and 3 site offices); however, ifthe PMDSC staff need to occupy additional offices due to space limitations, the amount of runningcosts would need to be commensurately increased.

350. A separate Project Office for the PMDSC will be have to be established for managing theconstruction supervision of the KMTC. We have included the establishment and running cost intothe contract addendum.

24 At this time the proposed amendments to the government’s 2016 budget covering VAT and NBT have not been fullyenacted.

Page 85: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 77

ANNEX A IMPLEMENTATION SCHEDULE

Page 86: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Revise Tender Designs Approval by PMU and ADB Bidding and Contract Award Construction Defects Liability Period

2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60

MLBCR

1 MLBCR-ICB-1 Raising of Crest of Minipe Anicut and Water Control and Measurement Facilities

2 MLBCR-NCB-1 Rehabilitation of Minipe LB Canal (0+000km to 30+140km) - Stage 1

3 MLBCR-NCB-2 Rehabilitation of Minipe LB Canal (30+140km to 49+820km) - Stage 2

4 MLBCR-NCB-3 Rehabilitation of Minipe LB Canal (49+820km to 63+650km) - Stage 3

5 MLBCR-NCB-4 Rehabilitation of Minipe LB Canal (63+650km to 73+960km) - Stage 4

6 MLBCR-G-1 Rehabilitation and Improvements to Gated Control Structures

NWPC

7 NWPC-NCB-1 Wemedilla Sluice and LBMC from Reservoir to Nabadagahawatta (0+000 to 5+250km)

8 NWPC-ICB-1 Mahakithula Inlet Tunnel, Mahakithula and Mahakirula Reservoirs, Feeder Canal 3.66km

9 NWPC-ICB-2 Main Canal from Nebadagahawatta to Mahakithula Reservoir (5+250 to 22+500km)

UEC

10 UEC-ICB-1 Upper Elahera Canal (0+100 to 6+226km)

UEC Manufacturing, shipping, establishment and testing of TBM

11 UEC-ICB-2 Tunneling of UEC Tunnel 3 (TBM) (27+509 to 54+249km)

12 UEC-ICB-2B KMTC Tunnels 1 and 2 (0+000 to 9+120km)

13 UEC-ICB-3 Upper Elahera Canal (6+226 to 17+900km)

UEC

14 UEC-ICB-4 Upper Elahera Canal (17+900 to 27+509km)

15 UEC-ICB-5 Upper Elahera Canal (54+249 to 65+500km)

16 UEC-ICB-6 Feeder Canal to Manankattiya, Eruwewa and Mahakanadarawa Reservoirs (0+000 to 19+000km)

17 UEC-ICB-7 NCPCP Water Management Software and Control Center

NWPC

18 NWPC-NCB-2 Mi Oya RB 1 Canal, Mahakirula Reservoir to Galgiriyawa (0+000km to 13+731km)

19 NWPC-NCB-3 Mi Oya RB 2 Main Canal From Galgiriyawa to Kaduruwewa (13+731km to 21+231km)

20 NWPC-NCB-4 Mahakithula Reservoir to Potuwila (0+000 to 1+491km) and Upper Mediyawa (0+000 to 19+980km)

21 NWPC-NCB-5 Yapahuwa Canal from Mediyawa Canal (0+000 to 11+200km)

22 NWPC-NCB-6 Dambulu Oya to Wemedilla LBMC and Diversion Structure (0+000 to 8+590km)

PMDSC - 1

TRANCHE 3 (2018 - 2024)

2018 2019 2020

ACCELERATED IMPLEMENTATION SCHEDULE

Mahaweli Water Security Investment Program - Phase 1

Program Management, Design and Supervision Consultant

No. Package Milestones and Construction Activities2016 2017

Upper Elahera Canal - Stage 3 (17+900km to 27+509km) and (54+249km to 65+500km)

North Western Province Canal - Stage 2

TRANCHE 1 (2016 - 2021)

Minipe Left Bank Canal Rehabilitation

North Western Province Canal - Stage 1

Upper Elahera Canal - Stage 1 (0+100 to 6+226km)

TRANCHE 2 (2017 - 2024)

Upper Elahera Canal - Stage 2 (6+226 to 17+900km) and (27+509 to 54+249km) and KMTC (0+000 to 9+120km)

Mahaweli Water Security Investment Program Accelerated Schedule

Page 87: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

MLBCR

1 MLBCR-ICB-1 Raising of Crest of Minipe Anicut and Water Control and Measurement Facilities

2 MLBCR-NCB-1 Rehabilitation of Minipe LB Canal (0+000km to 30+140km) - Stage 1

3 MLBCR-NCB-2 Rehabilitation of Minipe LB Canal (30+140km to 49+820km) - Stage 2

4 MLBCR-NCB-3 Rehabilitation of Minipe LB Canal (49+820km to 63+650km) - Stage 3

5 MLBCR-NCB-4 Rehabilitation of Minipe LB Canal (63+650km to 73+960km) - Stage 4

6 MLBCR-G-1 Rehabilitation and Improvements to Gated Control Structures

NWPC

7 NWPC-NCB-1 Wemedilla Sluice and LBMC from Reservoir to Nabadagahawatta (0+000 to 5+250km)

8 NWPC-ICB-1 Mahakithula Inlet Tunnel, Mahakithula and Mahakirula Reservoirs, Feeder Canal 3.66km

9 NWPC-ICB-2 Main Canal from Nebadagahawatta to Mahakithula Reservoir (5+250 to 22+500km)

UEC

10 UEC-ICB-1 Upper Elahera Canal (0+100 to 6+226km)

UEC

11 UEC-ICB-2 Tunneling of UEC Tunnel 3 (TBM) (27+509 to 54+249km)

12 UEC-ICB-2B KMTC Tunnels 1 and 2 (0+000 to 9+120km)

13 UEC-ICB-3 Upper Elahera Canal (6+226 to 17+900km)

UEC

14 UEC-ICB-4 Upper Elahera Canal (17+900 to 27+509km)

15 UEC-ICB-5 Upper Elahera Canal (54+249 to 65+500km)

16 UEC-ICB-6 Feeder Canal to Manankattiya, Eruwewa and Mahakanadarawa Reservoirs (0+000 to 19+000km)

17 UEC-ICB-7 NCPCP Water Management Software and Control Center

NWPC

18 NWPC-NCB-2 Mi Oya RB 1 Canal, Mahakirula Reservoir to Galgiriyawa (0+000km to 13+731km)

19 NWPC-NCB-3 Mi Oya RB 2 Main Canal From Galgiriyawa to Kaduruwewa (13+731km to 21+231km)

20 NWPC-NCB-4 Mahakithula Reservoir to Potuwila (0+000 to 1+491km) and Upper Mediyawa (0+000 to 19+980km)

21 NWPC-NCB-5 Yapahuwa Canal from Mediyawa Canal (0+000 to 11+200km)

22 NWPC-NCB-6 Dambulu Oya to Wemedilla LBMC and Diversion Structure (0+000 to 8+590km)

TRANCHE 3 (2018 - 2024)

No. Package Milestones and Construction Activities

Upper Elahera Canal - Stage 3 (17+900km to 27+509km) and (54+249km to 65+500km)

North Western Province Canal - Stage 2

TRANCHE 1 (2016 - 2021)

Minipe Left Bank Canal Rehabilitation

North Western Province Canal - Stage 1

Upper Elahera Canal - Stage 1 (0+100 to 6+226km)

TRANCHE 2 (2017 - 2024)

Upper Elahera Canal - Stage 2 (6+226 to 17+900km) and (27+509 to 54+249km) and KMTC (0+000 to 9+120km)

61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109

ACCELERATED IMPLEMENTATION SCHEDULE

Mahaweli Water Security Investment Program - Phase 1

Program Management, Design and Supervision Consultant

PMDSC - 2

2021 2022 2023 2024

Mahaweli Water Security Investment Program Accelerated Schedule

Page 88: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 80

ANNEX B STAFF MOBILISATION

Professional experts deployed from 1 December 2015 to 31 January 2016.

Name Int/Nat Position Arrival

Key Staff

Mr. M.R. Chegwin I Team Leader 2 December 2015

Mr. S. Schmitt I Chief Design Engineer 2 December 2015

Mr. K. Thermann I Senior Geotechnical Engineer 7 December 2015

Mr. U.N.S. Wickramaratchi N Deputy Team Leader 2 December 2015

Mr. P.W.C. Dayaratne N Procurement Specialist 2 December 2015

Mr. J. Jochimthasan N Design Engineer 7 December 2015

Mr. S.K. Hewadewa N Civil Engineer 7 December 2015

Mr. N.P.K.G. Jayatilake N Assistant Geologist 7 December 2015

Mr. S.S. Ranatunga N Water Resources / Irrigation Planning Engineer 9 December 2015

Mr. B.S. Liyanagama N Modelling Specialist 9 December 2015

Mr. Y.Y.V. Costa N Survey Assistant 7 December 2015

Mrs. P.I.L. Imbulana N Senior Construction Engineer 1 January 2016

Mr. I. Wijesekera N Senior Drafts Person 1 January 2016

Mr. N.N.K. Dias N Drafts person 2 2 January 2016

Mr. A.L. Buruharudeen N Hydraulic Structures Engineer 11 January 2016

Dr. Jens Moedinger I Modelling Specialist 9 January 2016

Mr. Martin Brown I Procurement Specialist 18 January 2016

Dr. Anusha P. Kasige N Environmental Specialist 18 January 2016

Mr. G. Kudaliyanage N Institutional Strengthening Specialist 21 January 2016

Mr. Herath N Communications Specialist 22 January 2016

Dr David Annandale I Environmental Specialist 23 January 2016

Mr. Joerg Weber I Hydraulic Structures Engineer 25 January 2016

Page 89: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 81

ANNEX C MINUTES OF MEETINGS

Page 90: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 82

Mahaweli Water Security Investment Program

Program Management, Design, and Supervision Consultants

Minutes of the Meeting (01)

Venue : Program Management Unit, Colombo

Date : 2 December 2015

Subject : Inaugural Meeting of the Employer and the Consultants

Present :

Mr. Sisira Kumara - Additional Secretary (Technical) MMDE / ProgramDirector (MWSIP) PMU

Mr. Ariyaratne - Civil Engineer PMU

Mr. Mangalagama - Procurement Engineer PMU

Mr. M.R. Chegwin - Team Leader PMDSC

Mr. Stefan Schmitt - Chief Design Engineer PMDSC

Mr. P.W.C. Dayaratne - Procurement Specialist PMDSC

Mr. U.N.S. Wickramaratchi - Deputy Team Leader PMDSC

1. Introduction

After initial introductions of the MWSIP staff and PMDSC team, the Additional SecretaryMMDE /Program Director MWSIP welcomed the PMDSC consultants and informed them thatthe government has given high priority and expect to complete the Program on schedule forearly realisation of the benefits to the people. All efforts must be taken to ensure quality ofwork and timely completion.

The TL-PMDSC informed that all endeavours would be made on the part of the consultantsto ensure quality of work and timely completion.

2. Assignment and Tasks

The tasks of PMDSC were briefly discussed and the TL-PMDSC clarified that after gatheringthe project documents and initial familiarisation site visits, the consultants will review theproject documents and deploy the experts in phases to ensure the maximum benefits.

3. Office Space and Facilities for PMDSC

Availability of office space and equipment were discussed and the consultants were informedthat the office for PMDSC is being refurbished and will be available within 3 weeks. ThePMDSC proposed using office space immediately in Mahaweli Consultancy Bureau office atJawatta road, as a temporary measure.

Page 91: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 83

Mahaweli Water Security Investment Program

Program Management, Design, and Supervision Consultants

Minutes of the Meeting (02)

Venue : Program Management Unit, Colombo

Date : 4 December 2015

Subject : PMDSC Working Arrangements

Present :

1. Mr. Sisira Kumara - Additional Secretary (Technical) MMDE / ProgramDirector (MWSIP) PMU

2. Mr. Vijith Kodituwakku - Procurement Specialist PMU

3. Mr. Ariyaratne - Civil Engineer PMU

4. Mr. M.D.G. Mangalagama - Office Engineer PMU

5. Mr. M.R. Chegwin - Team Leader PMDSC

6. Mr. Stefan Schmitt - Chief Design Engineer PMDSC

7. Mr. P.W.C. Dayaratne - Procurement Specialist PMDSC

8. Mr. U.N.S. Wickramaratchi - Deputy Team Leader PMDSC

1. Program Implementation

PD-MWSIP informed that in view of the scheduled completion of Kalu Ganga andMoragahakanda reservoirs by end 2018, the government has changed the priorities in theimplementation program to complete Kalu Ganga Moragahakanda Transfer Canal by end2018. The PMDSC was requested modify the implementation program accordingly.

The TL –PMDSC agreed to examine necessary modifications to the work program and givefeedback on the implications for required activities and resources.

2. Procurement of Office Equipment and Vehicles

PMDSC will arrange for the procurement of vehicles, computers, printers and the serverunder local shopping procedures.

3. Office Space and Facilities for PMDSC

PMDSC have commenced operations from Mahaweli Consultancy Bureau office at Jawatteroad, pending completion of refurbishing of the designated office. TL explained the need foradditional office space by mid-February 2016 to accommodate the scheduled staff.

4. Contract Packages

The invitation for bids for Minipe Left Bank Canal Rehabilitation Project (MLBCRP), NCB-1package, has been advertised and review of the bid documents for UEC ICB-1 and NWPC ICB-1 are in progress.

Page 92: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 84

Mahaweli Water Security Investment Program

Program Management, Design, and Supervision Consultants

Minutes of the Meeting (03)

Venue : Central Environmental Authority, Battaramulla

Date : 4 December 2015

Subject : NWPC – EIA report

The PD - MWSIP and the staff of the PMU and PMDSC clarified for CEA staff the technical issuesrelated to North Western Province Canal (NWPC) system, including the steps taken for theminimising the adverse impacts on, and conservation of, wild life and forest reserves.

Page 93: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 85

Mahaweli Water Security Investment Program

Program Management, Design, and Supervision Consultants

Minutes of the Meeting (04)

Venue : Program Management Unit, Colombo

Date : 17 December 2015

Subject : Meeting of the Client and the Consultants for Review of Field Visits

Present :

1. Mr. Sisira Kumara - Additional Secretary (Technical) MMDE / ProgramDirector (MWSIP)

2. Mr. Ariyaratne - Civil Engineer –MWSIP

3. Mr. M.D.G. Mangalagama - Office Engineer – MWSIP

4. Mr. M.R. Chegwin - Team Leader PMDSC

5. Mr. Stefan Schmitt - Chief Design Engineer PMDSC

6. Mr. P.W.C. Dayaratne - Procurement Specialist PMDSC

7. Mr. U.N.S. Wickramaratchi - Deputy Team Leader PMDSC

Observations from the Field Visits

1. Minipe Left Bank CanalRepairs to office building for PIU office Minipe, at Hasalake were in progress andexpected to be completed by early January. The office available for PMDSC field staffwas not adequate and request was made to repair the old circuit bungalow to providesupplementary office space.

2. Upper Elahera CanalRepairs to the building for UEC PIU office at Elahera was in progress and expected to

be complete by mid-January 2016. The office available for PMDSC field staff was not

adequate and a request was made to relocate farmer organisation office to the

adjoining building and include the space for PMDSC. PD agreed to provide alternative

arrangement at Madatugama office complex from 1 January 2016 if required.

3. North Western Province CanalConstruction of the new building for PIU office for NWPC, at Polpithigama is in progress

and is expected to be complete by end January 2016. The office space provided was

adequate for all PMDSC field staff.

Page 94: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 86

Mahaweli Water Security Investment Program

Program Management, Design, and Supervision Consultants

Minutes of the Meeting (05)

Venue : Program Management Unit, Colombo

Date : 4 December 2015

Subject : Pre bid Meeting – MLBCR – NCB-1 Package

Present :

Mr. Sisira Kumara - Additional Secretary (Technical) MMDE / ProgramDirector (MWSIP) PMU

Mr. Vijith Kodituwakku - Procurement Specialist MMDE

Mr. Ariyaratne - Civil Engineer PMU

Mr. M.D.G. Mangalagama - Office Engineer PMU

Mr. M.R. Chegwin - Team Leader PMDSC

Mr. Stefan Schmitt - Chief Design Engineer PMDSC

Mr. P.W.C. Dayaratne - Procurement Specialist PMDSC

Mr. U.N.S. Wickramaratchi - Deputy Team Leader PMDSC

Representatives from 10 Bidders

Program Director (PD): MWSIP chaired the meeting and welcomed the bidders. He emphasisedthe need for maintaining high quality work and timely completions of work as scheduled, asMLBCRP has been recognized by Asian Development Bank (ADB) as a pilot irrigation systemrehabilitation project to be presented to executing agencies in future assignments. PD introducedthe Program Management, Design and Supervision Consultant (PDMSC), who will function as the"Engineer" for Contracts of MWSIP and informed establishment of the Project ImplementationUnit (PIU) office at Hasalaka, headed by Project Director MLBCRP for program implementationon behalf of the Employer

PD stated that water flow in the canal will not be stopped for construction work implementationor any other acute reason during cultivation periods. Hence he requested all bidders to carefullystudy the item of dealing with water included in the Bill of Quantities (BOQ) as a lump sum item2.1.2.1, and assess sufficiently the actual dewatering requirement to complete the job withouttime extensions.

The Procurement and Contracts Specialist of PMDSC presented the scope of work and anoverview of the work components. He emphasised the need for carrying out the constructionwork during water issues in the canal for completing work components within the scheduledperiod. Attention was drawn to the establishment of material testing laboratory, andEnvironmental Management and Monitoring Plan (EMMP) as described in Section 6: Employer'sRequirements of the bidding document.

Project Director-MLBCRP informed the normal annual closed cultivation periods with no water

Page 95: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 87

issues in the canal are from February to March and from August to November; the proposedtentative closed season for next year: 26 February to 10 March and first week of August to firstweek of November. The bidders were advised to make maximum use of the closed cultivationperiods to expedite the work.

Project Director-MLBCRP informed about the site visit which is to be arranged on 22 December2015 at 09:30 hours from Hasalaka Project Office. PD announced that the deadline forsubmission of bids is extended up to 28 January 2016, on or before 15:00 hours.

Clarifications raised by the Bidders and the Responses by the PMDSC Consultants:

No Bidder(Company / Firm/ Contractor)

Query and Response

1 Access Engineering PLC Gabion mattresses are included in BOQ (Item No. 2.2.5.8)but not mentioned in the Drawings

• Response: Location and thickness will be indicated inan addendum to Bidding documents

Geo-textile item not in the BOQ

• Response: This will be clarified later in the addendum

2 CML-MTD Construction Ltd Demolition of damaged structures are not separated forconcrete and rubble masonry structures in BOQ Item No.2.1.1.4 and difficult to quote the rate

• Response: This will be clarified later by an addendum

3 Edward and Christie CivilEngineering & RoadDevelopment Contractors

How to measure the de-silting quantity in the canal inBOQ Item No.2.1.3.2• Response: Using Cross Sectional Surveys of before and

after the construction4 Hovel Construction (Pvt) Ltd Applying the rate of 5% for provisional sum not enough

• Response: (i) If works executed by the Contractor –overhead & profit shall be included in the work item: (ii)if plant, materials or services purchased by thecontractor – 5% shall be included as handling fee in theclaim.

• 1500mm long dowels are mentioned in the BOQ item No.2.2.8.2, but in the drawings it is shown 1000mm dowels.

• In BOQ item 2.2.8.1 dowel size is mentioned as 25 mmbut in BOQ item 2.2.8.2 the dowel size is 20mm

• Response: this will be corrected in the addendum

5 Tudawe Brothers (Pvt) Ltd. BOQ items under 2.2.6: Hydro-mechanical items to bedesigned by the contractor

• Response Yes as per specifications and Engineer’sinstructions.

Page 96: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 88

Mahaweli Water Security Investment Program

Program Management, Design, and Supervision Consultants

Minutes of the Meeting (06)

Venue : Central Environmental Authority, Battaramulla

Date : 21 December 2015

Subject : NWPC – EIA report

The meeting was chaired by Mr. G. Jayasingha, Director General, Central Environmental Authorityin attendance with his staff, present were PD-MWSIP, representatives from Irrigation Department,Mahaweli Authority of Sri Lanka, Forest Department, Wild Life Department, Agrarian ServicesDepartment, Divisional Secretaries, and PMDSC.

The PD -MWSIP and the staff of PMU and PMDSC provided further clarifications on the proposedmeasures for protection of flora and fauna along the canal trace, and including the following:

• Presentation on water balance and water availability for NWP – Mr Liyanagama

• Wildlife corridor to Hakwatuna reservoir bed including relocation of unauthorisedsettlers.

• Dambulu Oya regulator design modifications.

• Water allocation priority for current Mahaweli benefit areas over the proposed new areas.

Summary of the outcome of the discussions is as follows:

• Technical Committee Members to inform early CEA any further clarification if necessary.

• CEA will forward the written comments of the TEC members to the Project Proponent.

• The Project Proponent should submit his responses to the public and TEC comments.

• Subject to above the CEA will consider project proposals favourably.

Page 97: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 89

Mahaweli Water Security Investment Program

Program Management, Design, and Supervision Consultants

Minutes of the Meeting (07)

Venue : Central Environmental Authority, Battaramulla

Date : 21 December 2015

Subject : Technical Evaluation Committee – Upper Elahera Canal

Present : Members of the TEC, PD-MWSIP, PMDSC representatives

The discussions encompassed the following:

1. Clarifications on the ADB requirements for Single Stage two-envelope bidding procedure.

2. Modification to UEC reach km 0+100 to 0+660 - replacing rectangular open canal with closedtwin barrel conduit.

3. Clarifications to ITB 25.1, 19.2, 18.1

4. Bid validity period: 183 days.

5. VAT increase the amount to 12.5%

6. Name board - include specifications for size and lettering.

Page 98: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 90

Mahaweli Water Security Investment Program

Program Management, Design, and Supervision Consultants

Minutes of the Meeting (08)

Venue : MWSIP Office

Date : 4 January 2016

Subject : PMDSC

Present :

Mr. Sisira Kumara - Additional Secretary (Technical) MMDE /Program Director (MWSIP) PMU

Mr. Ariyaratne - Civil Engineer PMU

Mr. M.D.G. Mangalagama - Office Engineer PMU

Mr. M.R. Chegwin - Team Leader PMDSC

Mr. P.W.C. Dayaratne - Procurement Specialist PMDSC

Mr. U.N.S. Wickramaratchi - Deputy Team Leader PMDSC

1. Office facilities - residual refurbishing work will be completed and furnished office will beavailable by 15 January 2016 for use.

2. Office space requirement: PMDSC expects to deploy about 55 persons in the design office inColombo by late April or early May 2016 and addition office space and facilities werediscussed.

3. Data - water allocation and system management data for studies could be obtained fromWater Management Secretariat. PD was requested to facilitate corresponding meetings.

4. Software procurement – Sole agent for supplying GIS – Seek ADB concurrence.

5. Vehicle procurement – adopt local shopping procedure for goods; quotations to include CIF,and taxes separately.

6. Surveys and investigations – adopt local shopping procedure for services.

7. Tranche 1 contracts – MLBCR: submission extended to 28 January 2016.

NWPC: needs modifications

UEC: attending to TEC comments

8. Draft inception report: 12 February 2016.

9. Tranche 2: include KMTC

10. Kalu Ganga Outlet & interface: need to be coordinated with supervision consultants andfinalised early.

11. UEC bed slope adjustments: PMDSC to review the design with due consideration to the designparameters and the available head between Moragahakanda and Huruluwewa.

Page 99: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 91

Mahaweli Water Security Investment Program

Program Management, Design, and Supervision Consultants

Minutes of the Meeting (09)

Venue : ADB Resident Mission, Colombo

Date : 12 January 2016

Subject : Procurement Procedures and Environmental Issues

Present :

Ms. Manjula Amarasingha - Project Management Specialist ADB -Colombo

Ms. Taisuke Miyao - Senior Portfolio Management Specialist ADB Colombo

Mr. Sisira Kumara - Additional Secretary (Technical) MMDE / PD-MWSIP

Mr. M.R. Chegwin - Team Leader PMDSC

Mr. P.W.C. Dayaratne - Procurement Specialist PMDSC

Mr. U.N.S. Wickramaratchi - Deputy Team Leader PMDSC

1. Environmental studies – EIA studies were conducted for MLBC, UEC and NWP; compatibilityof the reports with ADB requirements to be checked and updated.

References could be made to –“Environmental Resource Book – Vietnam” and “StrategicEnvironmental Planning – GOSL.”

Phase 2 – requires SEA, IEE and EIA: SEA should include review of all project information,environmental development potentials, additional investigations, mitigation measures.

Tranche 2 – Human-elephant conflict – ADB will require action to have been taken on thisTranche 1 issue before approving Tranche 2.

2. Procurement – Inclusion of copies of FIDIC in bid documents is not required: bid documentsshould give reference only.

Meeting with ADB review mission planned for 20/2/2016

All procurement matters are dealt by ADB head office in ManilaAll environmental matters are dealt by the ADB office in Colombo

Page 100: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 92

Mahaweli Water Security Investment Program

Program Management, Design, and Supervision Consultants

Minutes of the Meeting (10)

Venue : Water Management Secretariat, Colombo

Date : 19 January 2016

Subject : Hydrological data and information on models currently adopted for systemoperations

Present :

Eng. Ms. G.K.T. Samaratunga - Director (Water Management Secretariat)

Eng. Mrs. M.L. Nimanthi Manjula - Assistant Director (Water Management Secretariat)

Eng. Mr. S.D. Galappaththi - Civil Engineer - Daily Operation and Monitoring and HMIS

Eng. Mr. K.L.I.C. Kariyawasam - Civil Engineer - Data base Management and HMIS

Mr. D.H.M.S.M Piyathilaka - IT works in WMS and HMIS

Dr. Jens Moedinger - Modelling Specialist (I) PMDSC

Mr. B.S. Liyanagama - Modelling Specialist (N) PMDSC

Mr. U.N.S. Wickaramaratchi - Deputy Team Leader PMDSC

1. Data: available rainfall – runoff data from some stations; the data available with the IrrigationDepartment and Ceylon Electricity Board need to be collected from the respective sources.

2. Models adopted – Water distribution: Acres Model; Mike Basin Model adopted for planningpurposes only; the models need to be calibrated and updated to cater for the currentdemands.

3. WMS monitor reservoir water levels and main diversion nodes, and rainfall at some stations.

4. Irrigation Department, Mahaweli Authority and Ceylon Electricity Board have their ownrainfall-runoff data bases.

5. Meteorological Department has climatic data and rainfall monitored at selected locationsspread across the country.

6. WMS staff suggested improvements to make the model user-friendly and improve itsflexibility for further improvements to cater for future needs.

Page 101: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 93

Mahaweli Water Security Investment Program

Program Management, Design, and Supervision Consultants

Minutes of the Meeting (11)

Venue : ADB Resident Mission, Colombo

Date : 21 January 2016

Subject : Presentation on Procurement procedures

Present : Procurements Specialist –ADB and PMDSC staff

Mr. Jagath Peththawadu Procurement Specialist–ADB, presented and outlined ADB procurementprocedures and clarified the following:

• Financial and progress monitoring – adopt ADB formats and models

• Bid evaluations –Stage 1 - verify completeness and responsiveness,Stage 2 – verify substantial responsivenessStage 3 – Detailed evaluation of bids – sections 2 & 6.Stage 4 – Lowest bid

• CECB - Semi government institution, not registered under company act and cannot beaccepted as a bidder.

Page 102: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 94

Mahaweli Water Security Investment Program

Program Management, Design, and Supervision Consultants

Minutes of the Meeting (12)

Venue : Program Management Unit, Colombo

Date : 26 January 2016

Subject : Technical Evaluation Committee Meeting – UEC and NWPC Tranche 1

1. Present:

Mr. Sisira Kumara - Additional Secretary (Technical) MMDE / PD

Mr. Vijith Kodituwakku - Procurement Specialist MMDE

Mr. Ariyaratne - Civil Engineer PMU

Mr. M.D.G. Mangalagama - Office Engineer PMU

Mr. M.R. Chegwin - Team Leader PMDSC

Mr. Stefan Schmitt - Chief Design Engineer PMDSC

Mr. P.W.C. Dayaratne - Procurement Specialist PMDSC

Mr. U.N.S. Wickramaratchi - Deputy Team Leader PMDSC

1. Contract Packages

• NWPC-NCB-1

• UEC-ICB-1

Pending observations from Cabinet Appointed Tender Board (CATB) attend all

observations from the Ministry Tender Board (MTB)

2. The Bids will be on single stage two envelope system. The technical and financial proposals

should be separate and any bids where the financial proposals are included in the technical

proposal are to be rejected.

3. Bid document should clearly stipulate the above and be explained to the bidders at the Pre-

Bid meeting.

Page 103: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 95

Mahaweli Water Security Investment Program

Program Management, Design, and Supervision Consultants

Minutes of the Meeting (13)

Venue : Program Management Unit, Colombo

Date : 27 January 2016

Subject : General Progress and Issues

Present :

Mr. Sisira Kumara - Additional Secretary (Technical) MMDE / ProgramDirector (MWSIP) PMU

Mr Ariyaratne - Civil Engineer PMU

Mr. M.D.G. Mangalagama - Office Engineer PMU

Mr. M.R. Chegwin - Team Leader PMDSC

Mr. P.W.C. Dayaratne - Procurement Specialist PMDSC

Mr. U.N.S. Wickramaratchi - Deputy Team Leader PMDSC

Current status of program implementation was discussed and the outcome is given below:

1. CEB meeting to gather information – fixed at 9.30 am on 28 January 2016.

2. Kotmale as-built drawings – available at head office and the PMDSC will collect

3. SMEC Report - available and the PMDSC will collect

4. Vehicle for site staff – include in contract for hire and provide specifications

5. Monthly payments to PMDSC – PMU need clarifications of some of the field claims and

requested to conform to government regulations on auditing procedures, daily attendance

will be reflected in the timesheets of the consultants.

6. Route selection Phase 2 – Establish early dialogue with the stakeholders; in this regard the

PD-MWSIP will make arrangements with the stakeholders.

7. Survey maps – PD-MWSIP will approve the purchase of maps from the Survey Department.

8. Web site – Single web domain was concurred.

9. Procurement of goods & services – adopt ADB guidelines and procedures, PD-MWSIP will

evaluate and submit the recommendations to ADB for concurrence.

Page 104: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 96

ANNEX D PMDSC DETAILED WORKPLAN

Page 105: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

WORK SCHEDULE AND PLANNING FOR DELIVERABLES

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60

1.1 Mobilization

1.1.1 Mobilize, establish project offices in Colombo and sub-project offices

1.1.2 Procure equipment and office staff

1.1.3 Identify the project management needs, planning, strategies and schedules for execution

1.1.4 Start-up meetings with PMU, PIUs and key organizations and stakeholders

1.1.5 Collect design reports, feasibility designs, data and planning information

1.1.6 Identify and scope monitoring, evaluation and reporting requirements

1.1.7 Assess the completion status of available designs, reports, drawings and bid documents

1.1.8 Conduct reconnaissance site visits to Phase 1 project areas and PIU offices

1.1.9 Review and update the implementation schedule

1.1.10 Review and update the work program and staffing schedule

1.1.11 Preparation of Inception Report

1.1.12 Confirm project implementation strategy with MMDE and ADB

1.2 Program Management

1.2.1 Assist MMDE with the establishment of the Project Steering Committee

1.2.2 Update the ToR for ISEWP Consultancy Package

1.2.3 Prepare Quality Assurance Plan (QAP)

1.2.4 Prepare the Risk Management Plan (RMP)

1.2.5 Prepare the Procurement Handbook

1.2.6 Prepare the Financial Management Handbook

1.2.7 Design the Project Performance Management Evaluation System (PPMES)

1.2.8 Scope and initiate baseline and follow-up/monitoring surveys for PPMES

1.2.9 Update and finalize the SIWRM consultancy package

1.2.10 Assist the PMU and PIUs to tender, evaluate and award contracts

1.2.11 Assist MMDE with preparation and updating of project documents for Tranche 2

1.2.12 Assist MMDE with preparation and updating of project documents for Tranche 3

1.2.13 Prepare Project Completion Report

Task 1 - Deliverables/Reports Submission

1.1 Inception Report

1.2 Updated ToR and RFP for ISEWP Consultancy Package

1.3 Monitoring and Evaluation Manual (MEM)

1.3 Quality Assurance Plan (QAP)

1.3 Risk Management Plan (RMP)

1.4 Procurement Handbook

1.5 Financial Management Handbook

1.6 Management Information System (MIS)

1.7 Project Performance Management Evaluation System (PPMES)

1.8 Mid-term Reports

1.9 Final Report

1.1 Monthly Reports

1.11 Quarterly Reports

1.12 Briefing Reports

1.13 Draft Periodic Financing Requests

1.14 Environmental Monitoring Reports (semi-annual)

1.15 Resettlement Monitoring and Evaluation Reports

1.16 Project Completion Report

1.17 Special Reports

1.18 Updated ToR and RFP for SIWRM Consultancy Package

TASK 1 - PROGRAM MANAGEMENT

Mahaweli Water Security Investment Program

Program Management, Design and Supervision Consultant

No. PMDSC Deliverables2016 2017 2018 2019 2020

Mahaweli Water Security Investment Program PMDSC WORK SCHEDULE

Page 106: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

WORK SCHEDULE AND PLANNING FOR DELIVERABLES

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60

Mahaweli Water Security Investment Program

Program Management, Design and Supervision Consultant

No. PMDSC Deliverables2016 2017 2018 2019 2020

2.1 Design Review, Planning and Assessment

2.1.1 Review design concepts, proposed implementation schedule and packaging

2.1.2 Update design criteria and standards

2.1.3 Update implementation schedule

2.1.4 Prepare Hydraulic Structures Design Manual

2.1.5 Prepare SCADA System ToR and specifications

2.2 Advanced Contract Packages

2.2.1 Assess the completion status of tendered bid packages

2.2.2 Review design reports, detailed design drawings, specifications and contract documents

2.2.3 Scope additional surveys and investigations

2.2.4 Prepare and submit Tender Design Review Report

2.2.5 Undertake any necessary additional surveys and laboratory tests, if required

2.2.6 Advise on contract packaging, procurement modality, equipment

2.2.7 Update designs, drawings, BoQs, cost estimates, and specifications, if required

2.2.8 Issue addendas as required with approvals from Client and ADB

2.3 Project 1 (Tranche 1) Contract Packages

2.3.1 Assess the completion status of Project 1 bid packages

2.3.2 Review design reports, tender documents and propose improvements

2.3.3 Scope additional surveys and investigations

2.3.4 Undertake necessary additional surveys, investigations and laboratory tests, if required

2.3.5 Advise on contract packaging, procurement modality, equipment

2.3.6 Update designs, drawings, BoQs, cost estimates, and specifications, if required

2.3.7 Provide criteria for evaluation and selection criteria

2.3.8 Finalize and submit updated tender documents

2.3.9 Prepare Detailed Design Report for Project 1

2.3.10 Prepare Draft MOM Manual for Project 1

2.4 Project 2 (Tranche 2) Contract Packages

2.4.1 Review feasibility designs and design reports

2.4.2 Scope additional surveys and investigations

2.4.3 Undertake necessary additional surveys, investigations and laboratory tests, if required

2.4.4 Update designs, drawings, BoQs, cost estimates, and specifications, if required

2.4.5 Advise MMDE on contract modalities; finalize procurement method for tunneling contract(s)

2.4.6 Finalize the design for a TBM and prepare the technical specifications

2.4.7 Assess access facilities, power requirements and contractors camp(s) requirements

2.4.8 Prepared detailed procurement plans; updated annually as required

2.4.9 Prepare draft tender documents

2.4.10 Finalize tender documents with comments from Client and ADB

2.4.11 Prepare Detailed Design Report for Project 2

2.4.12 Prepare Draft MOM Manual for Project 1

2.5 Project 3 (Tranche 3) Contract Packages

2.5.1 Review feasibility designs and design reports

2.5.2 Scope additional surveys and investigations

2.5.3 Undertake necessary additional surveys, investigations and laboratory tests, if required

2.5.4 Update designs, drawings, BoQs, cost estimates, and specifications, if required

2.5.5 Prepared detailed procurement plans; updated annually as required

2.5.6 Prepare draft tender documents

2.5.7 Finalize tender documents with comments from Client and ADB

2.5.8 Prepare Detailed Design Report for Project 3

2.5.9 Prepare Draft MOM Manual for Project 3

Task 2 - Deliverables/Reports Submission

2.1 Hydraulic Structures Design Manual

2.2 Tender Design Review Report

2.3 SCADA System Report (Terms of Reference and Specifications)

2.4 Detailed Design Report for Project 1 - Interim/Final

2.5 Detailed Design Report for Project 2 - Interim/Final

2.6 Detailed Design Report for Project 3 - Interim/Final

2.7 Draft Management, Operation and Maintenance (MOM) Manuals

2.8 Tender Documents (Projects 1-3)

TASK 2 - DESIGN REVIEW, DETAILED DESIGN AND CONTRACT DOCUMENTS

Mahaweli Water Security Investment Program PMDSC WORK SCHEDULE

Page 107: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

WORK SCHEDULE AND PLANNING FOR DELIVERABLES

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60

Mahaweli Water Security Investment Program

Program Management, Design and Supervision Consultant

No. PMDSC Deliverables2016 2017 2018 2019 2020

TASK 3 - CONTRACT MANAGEMENT, CONSTRUCTION SUPERVISION, COMMISSIONING AND OPERATION

3.1 Pre-Construction Phase

3.1.1 Review and updating of construction schedules

3.1.2 Prepare standard criteria and checklists for tender evaluation

3.1.3 Prepare Construction Supervision Manual

3.1.4 Prepare Health and Safety Manual

3.1.5 Prepare pre-qualification documents, prequalify contractors

3.2 Assistance during Tendering and Contracting

3.2.1 Pre-tender meetings and site visits

3.2.2 Assist during tender period

3.2.3 Assist during tender evaluation

3.2.4 Prepare bid evaluation report

3.2.5 Assist during contract negotiations

3.3 Construction Contract Management

3.3.1 Set-up construction documentation, data transfer system for all contracts

3.3.2 Check and approve the contractors' submissions

3.3.3 Check and approve the contractors' programs

3.3.4 Review and approve the contractors' method statements

3.3.5 Check and approve the contractors' interim payment statements

3.3.6 Progress meetings, measurement and cost control

3.3.7 Manage variation orders

3.3.8 Manage disputes and claims

3.3.9 Issue daywork orders

3.3.10 Prepare partial, substantial and final completion certificates

3.3.11 Assist PMU with contract management and finance related issues - defects liability period

3.3.12 Check and approve as-constructed drawings

3.4 Quality Control of Construction Materials

3.4.1 Supervise contractors' laboratories

3.4.2 Supervise borrow and spoil areas and quarry operations

3.4.3 Assist with the design of concrete mixes and technical specifications

3.4.4 Review and approve the mix designs of concrete and grout mixes

3.4.5 Monitor concrete and grout batching operations

3.5 Construction Supervision

3.5.1 Check and approve contractors' surveys and setting-outs

3.5.2 Supervise civil works

3.5.3 Design services for works during construction

3.5.4 Maintain photographic and written records of all construction activities

3.5.5 Monitor compliance with EMPs

3.5.6 Follow-up and monitoring of the progress of works

3.5.7 Health and safety monitoring

3.6 Testing and Commissioning

3.6.1 Inspect works during defects liability period; assess structural and functional performance

3.6.2 Supervise trial runs of civil works and mechanical and electrical equipment

3.6.3 Prepare an inventory of the defects/damages rectification/repair works

3.6.4 Assist the PMU with evaluation of the proposed rectification/repair works; supervise works

3.6.5 Prepare detailed MOM manuals for all works

Task 3 - Deliverables/Reports Submission

3.1 Construction Supervision Manual

3.2 Health and Safety Manual

3.3 Shift Reports

3.4 Weekly Reports

3.5 Monthly Progress Reports

3.6 Annual Progress Reports

3.7 Health and Safety Reports

3.8 Claim Reports

3.9 Contract Completion Reports

3.1 Certificates

3.11 Final Reports

3.12 Technical Review Reports

3.13 Special Reports

3.14 Updated (Final) Management, Operation and Maintenance (MOM) Manuals

Mahaweli Water Security Investment Program PMDSC WORK SCHEDULE

Page 108: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

WORK SCHEDULE AND PLANNING FOR DELIVERABLES

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60

Mahaweli Water Security Investment Program

Program Management, Design and Supervision Consultant

No. PMDSC Deliverables2016 2017 2018 2019 2020

4.1 Institutional Development

4.1.1 Identify stakeholders for the investment program

4.1.2 Conduct training needs assessment of MMDE, MASL and DOI

4.1.3 Review of policy and governance environment related to water resources management

4.1.4 Develop training plans and programs and with the PMU formulate training courses

4.1.5 Prepare Training Needs Assessment and Training Plan

4.1.6 Assist PMU to implement training programs, study tours and demonstrations

4.1.7 Update and finalize the SIWRM consultancy package

4.1.8 Advise PMU, PIUs and relevant agencies on improving institutional capacities

4.1.9 Train MMDE and other stakeholders on Mahaweli System hydraulic and hydrological models

Task 4 - Deliverables/Reports Submission

4.1 Training Needs Assessment and Training Plan

4.2 Training Completion Report

5.1 Strategic Communications Program

5.1.1 Consult with MMDE, relevant government agencies and program beneficiaries/stakeholders

5.1.2 Update Strategic Communications Plan (SCP)

5.1.3 Prepare media publications and video presentations

5.1.4 Assist and advise MMDE to develop and manage an effective public relations plan

5.1.5 Assist MMDE in establishing a proactive informative campaign and stakeholder dialogue

5.1.6 Organize public relations events

5.1.7 Assist PMU with developing and maintaining an investment program website

5.1.8 Assist PMU to maintain and update the website

5.1.9 Prepare a photographic and video diary of the construction works

Task 5 - Deliverables/Reports Submission

5.1 Updated Communications Strategy and Plan

5.2 Media publications

5.3 Investment Program Website

5.4 Video Presentation

6.1 Preparation of the SEA

6.1.1 Review the SEA related reports and project EIAs

6.1.2 Conduct kick-off meetings with PMU, CEA and other concerned agencies and stakeholders

6.1.3 Prepare and finalize ToR for SEA and approval by MMDE and ADB

6.1.4 Identify and scope additional socio-environmental surveys

6.1.5 Prepare and submit Inception Report

6.1.6 Reconnaissance site visits and stakeholder meetings

6.1.7 Prepare and submit Interim Report

6.1.8 Prepare and submit Final SEA Report

Task 6 - Deliverables/Reports Submission

6.1 Inception Report

6.2 Interim Report

6.3 SEA Final Report

TASK 6 - STRATEGIC ENVIRONMENTAL ASSESSMENT

TASK 4 - CAPACITY DEVELOPMENT

TASK 5 - COMMUNICATIONS

Mahaweli Water Security Investment Program PMDSC WORK SCHEDULE

Page 109: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

WORK SCHEDULE AND PLANNING FOR DELIVERABLES

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60

Mahaweli Water Security Investment Program

Program Management, Design and Supervision Consultant

No. PMDSC Deliverables2016 2017 2018 2019 2020

7.1 Data Collection, Design Review and Sector/System Assessments

7.1.1 Review status of available designs, reports and assess scope of Phase 2 projects

7.1.2 Compile and review available water balance data, climate change analyses and software models

7.1.3 Liaise with MASL Water Management Secretariat to obtain updated water balance data

7.1.4 Conduct reconnaissance site visits to Phase 2 project areas

7.1.5 Review current and planned monitoring and control systems

7.1.6 Identify and scope additional surveys and investigations

7.1.7 Establish Phase 2 route selection criteria with MMDE

7.1.8 Prepare Inception Report

7.2 Water Balance and Climate Change Assessments

7.2.1 Identify and scope data and information needs for hydraulic and hydrological models

7.2.2 Establish design criteria and scope for modeling MMDE and ADB

7.2.3 Review and establish operational rules and framework for modeling; select software package(s)

7.2.4 Develop, calibrate and test software

7.2.5 Hydro-agricultural modeling and computation of irrigation and DMI water demands

7.2.6 Model simulations and reporting

7.2.7 Confirm scope for Phase 2 projects with MMDE

7.3 Feasibility Designs and Planning

7.3.1 Technical assessment of proposed designs; incorporate results from models

7.3.2 Assess and undertake additional surveys and investigations

7.3.3 Establish design concepts and update design criteria

7.3.4 Undertake additional water balance and multi-criteria analysis for Phase 2 route selection

7.3.5 Prepare feasibility-level designs, cost estimates and drawings

7.4 Safeguards Assessments

7.4.1 Identify, scope and undertake additional socioeconomic surveys and collect field data

7.4.2 Undertake environmental assessments, surveys, and prepare, EARF, EIAs and EMPs

7.4.3 Undertake social and poverty analyses; prepare SPRSS

7.4.4 Prepare resettlement framework, resettlement plans and GRM

7.4.5 Prepare and update consultations and communications plans

7.5 Economic and Financial Assessment

7.5.1 Undertake financial management assessment

7.5.2 Prepare procurement assessment and procurement plan

7.5.3 Agricultural economics analyses and project planning

7.5.4 Detailed economic and financial analyses and modeling

7.6 Project Preparation Documents

7.6.1 Refine technical designs, cost estimates, safeguards/economic/financial assessments

7.6.2 Prepare ToR for detailed engineering designs of Phase 2 projects

7.6.3 Conduct stakeholder consultations and workshops

7.6.4 Prepare feasibility study report

7.6.5 Prepare ADB loan documents; including PDA

Task 7 - Deliverables/Reports Submission

7.1 Inception Report

7.2 Route Selection Report

7.3 Interim Report

7.4 Feasibility Design Report for Phase 2

7.5 Project Design Advance (PDA) Documents

7.6 ADB Loan Documents

TASK 7 - PREPARING NCPCP PHASE 2

Mahaweli Water Security Investment Program PMDSC WORK SCHEDULE

Page 110: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 102

ANNEX E DATA REQUIREMENTS FOR GEOTECHNICAL DESIGNS

UECFor Tunnels:

- Soil and rock conditions at portal locations- Thickness of overburden, properties of overburden/soil material (shear resistance,

permeability)- Rock level at low cover sections,- Occurrence of layers which pose potential waterways (groundwater, surface),

permeability of such layers (Lugeon-values)- Rock mechanical parameters for each rock type that will probably be encountered

during tunnel excavation (e.g. Unit Weight, UCS, Young’s Modulus, Poisson’s Ratio,estimated GSI, RMR and/or Q-values)

- Orientation and shear resistance of discontinuities

NWPFor tunnels:

- Soil and rock conditions at portal locations- Rock level at low cover sections- Occurrence of layers which pose potential waterways (groundwater, surface),

permeability of such layers (Lugeon-values)- Rock mechanical parameters for each rock type that will probably be encountered

during tunnel excavation (e.g. Unit Weight, UCS, Young’s Modulus, Poisson’s Ratio,estimated GSI, RMR and/or Q-values)

- Orientation and shear resistance of discontinuities

For existing dams to be heightened:- Soil and rock conditions at portal locations- Rock level at low cover sections- Occurrence of layers which pose potential waterways (groundwater, surface),

permeability of such layers (Lugeon-values)

MLBCRPRehabilitation of the existing canal. No design changes envisaged which would requiregeotechnical data of embankment material and foundation conditions.

KMTCFor tunnels:

- Soil and rock conditions at portal locations- Rock level at low cover sections- Occurrence of layers which pose potential waterways (groundwater, surface),

permeability of such layers (Lugeon-values)- Rock mechanical parameters for each rock type that will probably be encountered

during tunnel excavation (e.g. Unit Weight, UCS, Young’s Modulus, Poisson’s Ratio,estimated GSI, RMR and/or Q-values)

- Orientation and shear resistance of discontinuities

For Aqueducts:- Foundation conditions (thickness of overburden, rock level, properties of rock and soil)

Page 111: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 103

Phase 2 (tentative)

Investigations for canals, tunnels, dams including:

Tunnels:- Geological surface mapping- Boreholes at portal locations- Boreholes at specific locations along tunnel trace (low cover areas, undercrossing of

streams, roads, railways, settlements, etc.)- Geo-electric Sounding / Seismic Refraction Survey at specific locations along the tunnel

trace

Dams:- Geological mapping of dam area- Foundation conditions along proposed dam axes, abutments (boreholes, test pits)- Investigation of construction materials (aggregates, borrow areas, etc.)

Canals:- Investigations of ground conditions of canal trace for quantity estimates (soil-rock)

Page 112: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 104

ANNEX F DATA REQUIREMENTS FOR MODELLING

Hydrological and meteorological data is required from all (including abandoned) stations in andsurrounding the Mahaweli Development Project for the full time period available since start ofoperation. Stations coordinates are mandatory.

This includes (in order of priority):- River levels and discharges. Rating curves. (daily, hourly if available e.g., for storm

events)- Rainfall (minimum daily, hourly if available, and gauges with only monthly data should

also be provided)- Temperature (daily min/max/mean)- Evaporation (probably only monthly data available)- Evapotranspiration (daily)- Humidity (daily)- Sunshine hours (daily)- Solar radiation (daily)

Spatial data is required for the rainfall-runoff model:- Digital Elevation Model- Land use- Land cover- Soil

Updated physical data and mapping of the Mahaweli system is required, in GIS format (e.g.,shapefiles). Other physical parameters required include:

For all reservoirs:- Elevation-area-volume curve- Tailwater rating curve- Discharge rating curve of individual outlets/weirs/spillways- Turbine characteristics- Operational requirements, constraints, etc.- Reservoir zones and respective penalties (driver for ACRES model)

For all rivers and channels:- Representative cross-section(s)- Length- Slope- Roughness (main, floodplain)- Losses (in-/exfiltration, small offtakes)

For all headwork structures:- Capacity (discharge rating curve)- Operational requirements, constraints, etc.

For all irrigation schemes:- Total lengths of main and secondary canals- Representative cross-section(s) of main and secondary canals- Deliveries, down to secondary canal headworks- Demand (gross, net i.e., diversion and depletion, estimated efficiencies)- Command area, both design and actual (i.e., service area) (gross, net)

Page 113: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 105

- Return flow fraction (e.g., spills, direct discharges to drains)- Seepage rates- Cropping patterns- Crop yields

Page 114: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 106

ANNEX G UPDATED STAFFING SCHEDULE

Page 115: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

No. Nationality Position Home Field Total 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60

KEY EXPERTS - INTERNATIONAL

K-1 UK Team Leader and Chief Design Engineer 0 46 46 1.0 1.0 1.0 1.0 0.5 1.0 1.0 1.0 1.0 1.0 1.0 0.5 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 0.5 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 0.5

K-2 UK Procurement and Contracts Specialist 5 13 18 0.5 0.5 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

K-3 UK Environment Specialist 1 8 9 0.5 1.0 1.0 1.0 1.0 1.0 0.5 1.0 1.0 0.25 0.25 0.25 0.25

K-4 Australia Social and Resettlement Safeguards Specialist 0 7 7 1.0 1.0 1.0 1.0 1.0 1.0 1.0

K-5 USA Communications Specialist 1 7 8 0.5 0.5 0.5 1.0 1.0 1.0 0.5 1.0 0.5 1.0 0.5

K-6 Denmark Institutional Strengthening Specialist 0 6 6 0.5 0.5 1.0 0.5 1.0 0.5 0.5 0.5 0.5 0.5

K-7 Vietnam Financial Management Specialist 0 4.5 4.5 0.5 1.0 0.5 0.5 1.0 1.0

K-8 Austria Chief Design Engineer (Tunnels) 0 4 4 0.5 0.5 1.0 1.0 1.0

K-9 Germany Senior Design Engineer (Dams and Tunnels) 2 11 13 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

K-10 Austria Rock Mechanics Engineer 1 9 10 0.5 0.5 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

K-11 Germany Senior Structural Engineer 2 4 6 1.0 1.0 1.0 1.0 1.0 1.0

K-12 Germany Senior Engineering Geologist 2 8 10 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

K-13 UK Senior Mechanical Engineer (TBM) 1 11 12 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

K-14 Germany Mechanical Engineer (Gates/Hydropower) 0 1 1 1.0

K-15 Germany Senior Electrical Engineer (TBM) 0 2 2 0.5 0.5 0.5 0.5

K-16 Germany Senior Electrical Engineer (Gates/Hydropower) 1 3 4 1.0 1.0 1.0 1.0

K-17 Germany Hydraulic Structures Engineer 1 1 2 1.0 1.0

K-18 New Zealand Water Resources/Irrigation Planning Specialist 1 5 6 1.0 1.0 1.0 1.0 1.0 1.0

K-19 Germany Modeling Specialist 4 5 9 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

K-20 India Economist 0 4 4 1.0 1.0 1.0 1.0

K-21 Switzerland Chief Resident Engineer 0 50 50 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

K-22 UK Tunnel Construction Engineer 2 19 21 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

24.0 228.5 252.5

KEY EXPERTS - NATIONAL

K-23 Sri Lanka Deputy Team Leader / Prog. Management 55 0 55 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

K-24 Sri Lanka Monitoring and Evaluation Specialist 10 0 10 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

K-25 Sri Lanka Procurement and Contracts Specialist 54 0 54 0.5 1.0 1.0 1.0 1.0 0.5 0.5 0.5 0.5 0.5 0.5 0.5 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

K-26 Sri Lanka Environment Specialist 30 0 30 1.0 1.0 0.5 0.5 0.5 0.5 0.5 0.5 0.5 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 0.5 1.0 1.0 0.5 0.5 0.5 1.0 1.0 0.5 0.5 0.5 1.0 1.0 1.0

K-27 Sri Lanka Social and Resettlement Safeguards Specialist 14 0 14 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 0.5 0.5 0.5 1.0 0.5 0.5 0.5 0.5 0.5

K-28 Sri Lanka Sociologist 6 0 6 1.0 1.0 1.0 1.0 0.5 0.5 0.5 0.5

K-29 Sri Lanka Communications Specialist 33 0 33 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 0.3 0.2 0.1 0.1 0.1 0.1 0.1 0.1 1.0 1.0 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 1.0 1.0 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 1.0 1.0 1.0

K-30 Sri Lanka Institutional Strengthening Specialist 12 0 12 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

K-31 Sri Lanka Financial Management Specialist 8 0 8 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

K-32 Sri Lanka Senior Design Engineer (Dams and Tunnels) 56 0 56 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

K-33 Sri Lanka Senior Design Engineer (Canals) 32 0 32 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5

K-34 Sri Lanka Rock Mechanics Engineer 44 0 44 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 0.5 0.5 0.5 0.5 1.0 1.0 1.0 0.5 0.5 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

K-35 Sri Lanka Senior Structural Engineer 22 0 22 1.0 1.0 1.0 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5

K-36 Sri Lanka Senior Engineering Geologist 27.5 0 27.5 1.0 1.0 1.0 1.0 1.0 1.0 0.5 0.5 0.5 0.5 0.5 1.0 1.0 1.0 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5

K-37 Sri Lanka Mechanical Engineer (Gates/Hydropower) 2 0 2 1.0 1.0

K-38 Sri Lanka Senior Electrical Engineer (TBM) 6 0 6 1.0 1.0 1.0 1.0 1.0 1.0

K-39 Sri Lanka Senior Electrical Engineer (Gates/Hydropower) 2 0 2 1.0 1.0

K-40 Sri Lanka Hydraulic Structures Engineer 4 0 4 1.0 1.0 1.0 1.0

K-41 Sri Lanka Water Resources/Irrigation Planning Specialist 11 0 11 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

K-42 Sri Lanka Modeling Specialist 20 0 20 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

K-43 Sri Lanka Agriculture Specialist 6 0 6 1.0 1.0 1.0 1.0 1.0 1.0

K-44 Sri Lanka Economist 10 0 10 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

K-45 Sri Lanka Senior Construction Engineer 55 0 55 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

K-46 Sri Lanka Resident Engineer - 1 (MLBCR) 40 0 40 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

K-47 Sri Lanka Resident Engineer - 2 (NWPC) 50 0 50 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

K-48 Sri Lanka Resident Engineer - 3 (UEC) 46 0 46 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

K-49 Sri Lanka Resident Engineer - 4 (KMTC) 29 0 29 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

K-50 Sri Lanka Tunnel Construction Engineer 47 0 47 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

K-51 Sri Lanka Dam Engineer 9 0 9 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

740.5 0.0 740.5Sub-total

TBN

M.M. Wijeratne

W.L.H.M.T. Bandara

A.M.P.K. Bandara

H.M.G. Herath

V.H.S. Samaratunga

Dr. S. Somaratne

P. D. Leelaratne

P.I.L. Imbulana

A.L. Buruhanudeen

S.S. Ranathunga

B.S. Liyanagama

D.E.N. Rajapakse

H.J. WARNAKULASURIYA

S.K. Weerasena

A.K.D.N. Atukorala

D.F.M. Perera

Dr. A. Gunasekera

S.H.A. Senaratne

R.M.P.W.K. Ratnayake

J. Joachimthasan

K. Jinapala

H.M.A.K. Herath

G. Kudaliyanage

P.W.C. Dayaratne

Dr. A. Kasige

Y.G. Wijeratne

Sub-total

U.N.S. Wickramaratchi

K.A.U.S. Imbulana

Dr. A. Rajagopal

Werner Buerkler

David Denman

Joerg Weber

Dr. Robert Rout

Dr. Jens Moedinger

Palitha Peiris

Ralf Bucher

Ralf Bucher

Dr. Mikhail Rosenberg

Dr. Eckhard Schnaecker

Colin Lawrenson

Bernhard Stacherl

Winfried Guth

Dr. Adrian Kattinger

Darryl Kuhnle

Claes Clifford

Dr. Tien Hai Truong

Martin Brown

David Annandale

Roger McIntyre

Name

Michael Chegwin

RFP No. CS-1 Project No. 47381-002-SRI (SF)

Mahaweli Water Security Investment Program

Program Management, Design and Supervision Consultant

TIME-BASED TEAM COMPOSITION, ASSIGNMENT AND KEY EXPERTS' INPUTS

TEAM COMPOSITION 2016 2017 2018 2019 2020

Mahaweli Water Security Investment Program STAFF SCHEDULE TIME BASED ACC

Page 116: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

No. Nationality Position Home Field Total 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60Name

RFP No. CS-1 Project No. 47381-002-SRI (SF)

Mahaweli Water Security Investment Program

Program Management, Design and Supervision Consultant

TIME-BASED TEAM COMPOSITION, ASSIGNMENT AND KEY EXPERTS' INPUTS

TEAM COMPOSITION 2016 2017 2018 2019 2020

NON-KEY EXPERTS - NATIONAL

N-1 Sri Lanka Concrete Engineer - 1 (MLBCR) 26 0 26 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-2 Sri Lanka Concrete Engineer - 2 (NWPC) 32 0 32 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-3 Sri Lanka Concrete Engineer - 3 (UEC) 31 0 31 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-4 Sri Lanka Concrete Engineer - 4 (KMTC) 29 0 29 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-5 Sri Lanka Senior Surveyor - 1 (MLBCR) 30 0 30 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-6 Sri Lanka Senior Surveyor - 2 (NWPC) 30 0 30 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-7 Sri Lanka Senior Surveyor - 3 (UEC) 16 0 16 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-8 Sri Lanka Senior Surveyor - 4 (KMTC) 24 0 24 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-9 Sri Lanka Quantity Surveyor - 1 (MLBCR) 30 0 30 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-10 Sri Lanka Quantity Surveyor - 2 (NWPC) 30 0 30 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-11 Sri Lanka Quantity Surveyor - 3 (UEC) 16 0 16 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-12 Sri Lanka Quantity Surveyor - 4 (KMTC) 24 0 24 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-13 Sri Lanka Health and Safety Officer 50 0 50 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-14 Sri Lanka Senior Draftsperson 54 0 54 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-15 Sri Lanka Assistant Design Engineer - 1 54 0 54 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-16 Sri Lanka Assistant Design Engineer - 2 12 0 12 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-17 Sri Lanka Assistant Design Engineer - 3 18 0 18 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5

N-18 Sri Lanka Assistant Design Engineer - 4 18 0 18 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5

N-19 Sri Lanka Assistant Design Engineer - 5 21 0 21 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-20 Sri Lanka Assistant Design Engineer - 6 21 0 21 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-21 Sri Lanka Assistant Design Engineer - 7 21 0 21 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-22 Sri Lanka Assistant Design Engineer - 8 21 0 21 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-23 Sri Lanka Assistant Design Engineer - 9 11 0 11 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-24 Sri Lanka Engineer Assistant (Construction Supervision) - 1 49 0 49 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-25 Sri Lanka Engineer Assistant (Construction Supervision) - 2 49 0 49 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-26 Sri Lanka Engineer Assistant (Construction Supervision) - 3 49 0 49 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-27 Sri Lanka Engineer Assistant (Construction Supervision) - 4 50 0 50 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-28 Sri Lanka Engineer Assistant (Construction Supervision) - 5 50 0 50 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-29 Sri Lanka Engineer Assistant (Construction Supervision) - 6 47 0 47 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-30 Sri Lanka Engineer Assistant (Construction Supervision) - 7 47 0 47 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-31 Sri Lanka Engineer Assistant (Construction Supervision) - 8 42 0 42 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-32 Sri Lanka Engineer Assistant (Construction Supervision) - 9 42 0 42 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-33 Sri Lanka Engineer Assistant (Construction Supervision) - 10 42 0 42 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-34 Sri Lanka Engineer Assistant (Construction Supervision) - 11 24 0 24 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-35 Sri Lanka Engineer Assistant (Construction Supervision) - 12 12 0 12 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-36 Sri Lanka Engineer Assistant (Construction Supervision) - 13 24 0 24 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-37 Sri Lanka Engineer Assistant (Construction Supervision) - 14 6 0 6 1.0 1.0 1.0 1.0 1.0 1.0

N-38 Sri Lanka Assistant Mechanical/Electrical Engineer - 1 22 0 22 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5

N-39 Sri Lanka Assistant Mechanical/Electrical Engineer - 2 26 0 26 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5

N-40 Sri Lanka Assistant Mechanical/Electrical Engineer - 3 23 0 23 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5

N-41 Sri Lanka Assistant Mechanical/Electrical Engineer - 4 22 0 22 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-42 Sri Lanka Assistant Mechanical/Electrical Engineer - 5 2 0 2 1.0 1.0

N-43 Sri Lanka Survey Assistant - 1 53 0 53 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-44 Sri Lanka Survey Assistant - 2 49 0 49 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-45 Sri Lanka Survey Assistant - 3 47 0 47 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-46 Sri Lanka Survey Assistant - 4 47 0 47 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-47 Sri Lanka Survey Assistant - 5 22 0 22 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-48 Sri Lanka Survey Assistant - 6 22 0 22 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-49 Sri Lanka Survey Assistant - 7 24 0 24 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-50 Sri Lanka Draftsperson - 1 49 0 49 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-51 Sri Lanka Draftsperson - 2 40 0 40 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5

N-52 Sri Lanka Draftsperson - 3 22 0 22 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-53 Sri Lanka Draftsperson - 4 22 0 22 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-54 Sri Lanka Draftsperson - 5 7 0 7 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-55 Sri Lanka Assistant Geologist 8 0 8 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 1.0 1.0

N-56 Sri Lanka GIS Specialist 30 0 30 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5

1689.0 0.0 1689.0

NON-KEY EXPERTS - INTERNATIONAL

N-57 Germany Chief Design Engineer 0 8 8 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-58 Germany Hydropower Engineer (Civil) 2 2 4 1.0 1.0 1.0 1.0

N-59 Germany Geotechnical Engineer (Investigations) 2 6 8 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

N-60 Germany Mechanical Engineer (Turbine) 1 2 3 1.0 1.0 1.0

N-61 Germany Senior Design Engineer (Canals) 1 1 2 1.0 1.0

N-62 Germany Hydraulic Modelling Specialist 2 2 4 1.0 1.0 1.0 1.0

N-63 China Senior Dam Engineer (RCC Dam Expert) 1 2 3 1.0 1.0 1.0

N-64 Germany Senior Geotechnical Engineer (Dam Expert) 1 1 2 1.0 1.0

10.0 24.0 34.0

2463.5 252.5 2716.0Total

Hannes Blindenhoefer

Bernd Hein

Sub-total

Stefan Schmitt

Frank Negrassus

Karsten Thermann

Jens Rieg

Andreas Tietze

Chongjiang Du

M. P. K. G. Jayathilaka

H.E. Weerawanni

Sub-total

D.M.N.N. Dissanayake

T.M.P.M. Bandara

H.G.L. Jayathunga

TBN

T.D.P. Peiris

TBN

A.K.M.N. Abeywickrama

W.A. U. Sandakelum

M.A.C. Priyadarshana

A.D.A. Wijesundara

TBN

Y.K.V. Costha

P.G.J.V. Chandrakumara

A.J.S. Jayawardane

B.A.A.I. Karunasena

S.U. Madushanka

TBN

TBN

S.C. Herath

M.M.L.J. Kalawana

R.M.A. Ratnayake

U.L.S. Silva

K.R.H.J. Punyasiri

M.H.A. Amarakoon

S.M.A. Senarathna

E.M.R. Ekanayake

J.A.S. Jayakody

R.M. Ranasinghe

W.A. Leelaratne

J.L. Hewawitharana

W.M. Karunaratne

A.I. Ahmed

S.A.M.A.N.I. Senarathne

TBN

B.M.D.N. Abeyratne

A.G.T.N. Jayaweera

M.I.M. Sabri

V.K. Pulasthi

H.K.R. Madushanka

C.D. Kothalawala

TBN

K.D. Amarasiri

I. Wijesekara

A.P. Karunaratne

W.S. Senanayake

K.M.H. Dias

A.H. Rupasinghe

B.J.S. Dhas

TBN

W.M.G.S. Wickramasinghe

TBN

B.A. Tilakaratne

A.M.A.K. Seneviratne

A.D.M.S. Bandara

Mahaweli Water Security Investment Program STAFF SCHEDULE TIME BASED ACC

Page 117: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 109

ANNEX H TERMS OF REFERENCE

Social and Resettlement Safeguards Specialist

(i) Updating the approved RF of the investment program, as necessary;

(ii) Updating resettlement plans for Tranches 2 and 3, as necessary;

(iii) Designing, commissioning, and supervising the implementation of appropriate socio-economicsurveys for Tranches 2 and 3 and Phase 2 investments; and provide all necessary inputs for thepreparing the associated social and resettlement activities including the social impactassessments, safeguard planning documents such as RIPs, SPRSS, and gender action plans;

(iv) Proposing practical and implementable options for improving resettlement implementation. Drawlessons to be learned from comparable projects and propose practical and implementable optionsfor improvement in resettlement implementation;

(v) Preparing MMDE's capacity assessment and involuntary resettlement training programs if gapsare identified;

(vi) Assisting PMU in: (a) identifying affected persons and the impact of the project on them; (b)making a detailed inventory of assets; (c) making swift payments of compensation and theprovision of other resettlement assistance, along with other relevant agencies; and (d) keepingdetailed records of progress on resettlement implementation;

(vii) Providing or organising training programs or other forms of support for income restoration andimprovement; and

(viii) Planning and implementing consultations with affected persons in accordance with theconsultation plan.

(ix) Updating the existing PSA to adhere to the government’s and ADB requirements.

Modelling Specialist

(i) Developing the outline design, framework, application analysis and recommendations for asystem operations model of the main conveyance systems of the fully developed MahaweliSystem that will support planning, design, and management of the entire system;

(ii) Developing a detailed and calibrated rainfall-runoff model and crop water demand model of thecomplete Mahaweli System that can accurately model spatially and temporally variable rainfalland crop water requirements. The model should provide upstream and downstream boundaryconditions to the system operations model. Ideally the two models would be linked, however theyshould also operate as standalone models;

(iii) Operating the model(s) for various time-steps ranging from daily to monthly time-series. Thissupporting model will also be used by MMDE and other stakeholders for routine watermanagement.

(iv) Assisting MMDE and other stakeholders to use the models developed for water management forat least 1 year to ensure effective handover of the tools.

(v) Use the developed models to support other PMDSC specialists undertake their work, as necessary;and,

(vi) Prepare user manuals for the developed models and provide training to MMDE, MASL, and PMUstaff in operating and updating the models.

Environmental Specialist (Time-based contract)

(i) Updating the EIAs and IEE, and the respective EMPs based on final detailed designs;

Page 118: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 110

(ii) Training and building capacity of PMU and PIU staff on environmental management,supervision, reporting, and monitoring of implementation of EMPs;

(iii) Orienting contractors on implementation of the EMPs;

(iv) Reviewing the environmental method statements provided by contractors and guide them onany revisions required;

(v) Monitoring implementation of the EMP and recommending any corrective actions on anyunforeseen environmental impacts;

(vi) Taking the lead in preparing environmental monitoring reports for PMU, ADB and CentralEnvironmental Authority (CEA);

(vii) Assisting with the selection of Phase 2 conveyance options through the application of multi-criteria analysis; and,

(viii) Once the Phase 2 route has been chosen, preparing separate EIAs for: (i) the North CentralProvince Canal Project; and (ii) the chosen southern route option (Polgolla or RKTC).

Rock Mechanics Engineers (Time-based contract)

(i) Examining the tunnelling methods (TBM, drill and blast) and recommend appropriate tunnellingmethod to fit the program time and cost constraints;

(ii) Identifying requirements for supplementary field investigations (if necessary) in closecooperation with the Senior Engineering Geologist, design, tender drawings, BOQ and costestimates for the tunnel components;

(iii) Analysing the issue of compatibility of drilling and shotcrete equipment with the tunnel crosssection and suggest the most optimal solutions for drilling and shotcrete;

(iv) Developing the optimal requirement of important equipment for critical activities of TBM, drilland blast; permanent support works (e.g., shotcrete); headworks; etc.;

(v) Reviewing the alignment and design of the tunnels in relation to the type of rock and thethickness of the burden; comment on the geological documentation; and recommend designand construction methods as necessary;

(vi) Reviewing the available investigation results on their reliability, completeness andrepresentativeness, and recommend and oversee additional laboratory and/or in-situ tests, ifdeemed necessary, in close cooperation with the Senior Engineering Geologist;

(vii) Reviewing the hazards for all tunnels with regard to low or insufficient rock cover, deep-seatedtropical weathering, and karstification; comment on countermeasures and recommend andoversee additional investigations, if necessary; elaborate cost estimates, supervise and evaluatethe findings;

(viii) Assessing the relevance of elevated primary stress in tunnels with high rock cover of 100m to370m (RKTC, KMTC, UEC); if positive, recommend in-situ tests for execution; supervise the testsand evaluate the recorded results. If the primary stress exceeds a tolerable limit, inform thePIU, PMU and the Contractor;

(ix) Recommending sections for convergence measurements in all tunnels and evaluate thedeformations on a graph and comment;

(x) Providing continuous representation during the construction of the tunnels and dams.

(xi) Checking the Contractor's equipment, all machines and respective personnel and recommend

additional resources;

Senior Mechanical Engineer (TBM)

(i) Reviewing the geological conditions along the tunnel alignments and the tunnelling concept for

TBM drive of KMTC and UEC tunnels;

Page 119: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 111

(ii) Advising the PMU and PIU on the preferred type of TBMs, their procurement and mobilization,

the costs of machines and backup/support systems, as well as possible modalities of financing;

(iii) Performing acceptance tests in the course of design and manufacture of the TBMs, in the

assembly as well as commissioning phase;

(iv) Commenting on the staffing and equipment of the Contractor’s TBMs; and

(v) Assisting the Contractor to overcome technical problems with the TBM and/or backup system.

Financial Management Specialists

(i) Support the PMU in establishing and using proper project financial management and accountingsystems to support financial management of the investment program and adopting the financialmanagement improvement proposed in the FAM;

(ii) Support preparation of the Phase 2 investments by: (a) updating the Financial ManagementAssessment of MMDE, MASL and DOI; (b) preparing the financial evaluation and analysis of thePhase 2 investments which will include both non-income generating components (irrigation andbulk water supply) and income generating components (hydropower). The formats of these as-sessments will follow ADB requirements.

(iii) Prepare and revise the project cost estimates, financial monitoring and financial analysis;

(iv) Prepare a Financial Management Handbook for the investment program and provide trainingto the PMU and PIUs as necessary on the handbook, project accounting and ADB proceduresfor disbursements;

(v) Assist the PMU in setting up the overall financial management, i.e., disbursement of funds, re-view of withdrawal applications, monitoring of project and counterpart funds, etc.;

(vi) Assist the PMU in implementing improvement measures recommended by the PPTA financialmanagement assessment, and update the FAM accordingly;

(vii) Assist PMU staff in the preparation of project accounts in a format suitable for both ADB andnational requirements;

(viii) Assist PMU staff in developing a system of internal control to ensure accurate and reliable fi-nancial information;

(ix) Assist the Team Leader and Deputy Team Leader in timely preparation of reports; and

(x) Prepare the Program Fund Disbursement Handbook.

Senior Electrical Engineers (TBM)

(i) Reviewing the existing plans and designs, recommending improvements, and assessing or up-dating the cost estimates;

(ii) Assisting the PMU and PIU with the supply of required power to the TBM sites;

(iii) Advising on the existing capacities of transmission lines and substations, and where necessaryrecommending improvements and extensions along with preparing pre-feasibility designs andcost estimates;

(iv) Carrying out acceptance tests with the manufacturer;

(v) Advising on the construction and power distribution on the various sites in cooperation withthe health and safety engineer;

(vi) Advising on all matters relating to the tunnel and site lighting, air handling, ventilation, de-watering, etc. Reviewing submittals and processing accordingly;

(vii) Providing support to preparing Phase 2 investments, as necessary; and

(viii) The national specialist will support the international specialist.

Page 120: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 112

ANNEX I LUMP SUM PAYMENT SCHEDULE

Deliverable Task % *

EstimatedMonth

Hydraulic Structures Design Manual 2 2.5 5

Tender Design Review Report 2 5 5

SCADA System Report 2 5 12

Detailed Design Report for Project 1 - Interim/Final 2 4/2.7 8/10

Detailed Design Report for Project 2 - Interim/Final 2 4/2.7 11/13

Detailed Design Report for Project 3 - Interim/Final 2 4/2.7 20/22

Draft Management, Operation and Maintenance Manuals 2 5/5/5 10/13/22

Tender Documents

MLBCR - 6 packages - 12.5% / 6 = 2.08% per package 2 2.08 3/4/7

NWPC - 8 packages - 12.5% / 8 = 1.56% per package 2 1.56 3/10/19

UEC - 7 packages - 12.5% / 7 = 1.79% per package 2 1.79 3/6/10/13/19

Inception Report 6 2.5 4

Interim Report 6 2.5 8

SEA Final Report 6 10 10

* Refer to Table 8 of the ToR.

Month % of Lump Sum Contract*

1 0.0%

2 0.0%

3 5.4%

4 8.7%

5 7.5%

6 1.8%

7 4.2%

8 6.5%

9 0.0%

10 24.4%

11 4.0%

12 5.0%

13 9.5%

14 0.0%

15 0.0%

16 0.0%

17 0.0%

18 0.0%

19 11.4%

20 4.0%

21 0.0%

22 7.7%

100%

* to be based on actual approval dateof Task 2 deliverables

Page 121: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Ministry of Mahaweli Development and Environment Mahaweli Water Security Investment ProgramINCEPTION REPORT

Program Management, Design and Supervision Consultant Page 113

ANNEX J PROCUREMENT PLAN

Page 122: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

PROCUREMENT PLAN

Basic Data

Project Name: Mahaweli Water Security Investment Program - Tranche 1

Project Number: 47381-002 Approval Number: 3267/3268

Country: Sri Lanka Executing Agency: Ministry of Mahaweli Development & Environment

Project Procurement Classification: Category A Implementing Agency: N/A

Project Procurement Risk: Substantial

Project Financing Amount: US$ 190,000,000 ADB Financing: US$ 150,000,000 Cofinancing (ADB Administered): Non-ADB Financing: US$ 40,000,000

Project Closing Date: 31 December 2019

Date of First Procurement Plan: 26 June 2015 Date of this Procurement Plan: 1 March 2016

A. Methods, Thresholds, Review and 18-Month Procurement Plan

1. Procurement and Consulting Methods and Thresholds

Except as the Asian Development Bank (ADB) may otherwise agree, the following process thresholds shall apply to procurement of goods and works.

Procurement of Goods and Works Method Threshold Comments

International Competitive Bidding for Goods US$ 2,000,000 and Above Threshold applies to all unless propriety items are required from overseas (e.g. MLBCR Goods ICB-01).

National Competitive Bidding for Goods Between US$ 100,001 and US$ 1,999,999 Shopping for Goods Up to US$ 100,000 International Competitive Bidding for Works US$ 7,500,000 and Above Except MLBCR-ICB-01

National Competitive Bidding for Works Between US$ 100,001 and US$ 7,499,999 Except MLBCR-ICB-01

Shopping for Works Up to US$ 100,000 Community Participation in Procurement for Works

Up to US$ 20,000 Simple civil works contracts costing less than $20,000 each may be directly awarded to project area community groups / civil society organizations as a community works contract using existing government rates. ADB PAI 5.10 for community participation is followed.

Force Account for Works Up to US$ 650,000 Includes works and goods. Total amount for entire tranche 1 is $650,000 (this amount includes all contract packages under tranche 1). Existing government rates shall be used. Utility shifting, field office works, and other works by government-owned entities (for activities which cannot be done by competitive contracting such as shifting power and telephone poles, realigning water/drainage pipes, road

Page 123: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

restoration, cables, cutting trees etc.)

Consulting Services

Method Comments Consultant's Qualification Selection for Consulting Firm Least-Cost Selection for Consulting Firm Quality- and Cost-Based Selection for Consulting Firm Quality-Based Selection for Consulting Firm Individual Consultants Selection for Individual Consultant

2. Goods and Works Contracts Estimated to Cost $1 Million or More

The following table lists goods and works contracts for which the procurement activity is either ongoing or expected to commence within the next 18 months.

Package Number General Description Estimated

Value Procurement

Method Review (Prior/ Post)

Bidding Procedure

Advertisement Date

(quarter/year) Comments

MLBCR-ICB-01

Heightening of Minipe Anicut including water control facilities for LB and RB canals

6,910,000.00

ICB Prior 1S2E Q4 / 2016 Prequalification of Bidders: N Domestic Preference Applicable: N Advance Contracting: Y Bidding Document: Large Works

MLBCR-NCB-01

Rehabilitation of Minipe LB Canal from 0+000 km to 30+140 km - stage 1

2,670,000.00

NCB Prior 1S2E Q4 / 2015 Prequalification of Bidders: N Domestic Preference Applicable: Y Advance Contracting: Y Bidding Document: Small Works

Page 124: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

MLBCR-NCB-02

Rehabilitation of Minipe LB Canal from 30+140 km to 49+820 km - stage 2

1,320,000.00

NCB Prior 1S2E Q3 / 2016 Prequalification of Bidders: N Domestic Preference Applicable: Y Advance Contracting: Y Bidding Document: Small Works

MLBCR-NCB-03

Rehabilitation of Minipe LB Canal from 49=820 km to 63=650 km - stage 3

5,230,000.00

NCB Prior 1S1E Q3 / 2016 Prequalification of Bidders: N Domestic Preference Applicable: N Advance Contracting: N Bidding Document: Small Works

MLBCR-NCB-04

Rehabilitation of Minipe LB Canal from 63=650 to 73+960 km - stage 4

2,440,000.00

NCB Prior 1S1E Q3 / 2016 Prequalification of Bidders: N Domestic Preference Applicable: N Advance Contracting: N Bidding Document: Small Works

NWPC-ICB-01

Construction of Mahakithula & Mahakirula tanks, feeder canal of 3.66 km from Mahakitula to Mahakirula and inlet tunnel to Mahakitula tank from

47,970,000.00

ICB Prior 1S2E Q1 / 2017 Prequalification of Bidders: N Domestic Preference Applicable: N

Page 125: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Nebadagahawatta diversion canal

Advance Contracting: Y Bidding Document: Large Works

NWPC-ICB-02

Construction of Main Canal from Nebadagahawatta Wewa to Mahakitula Wewa inlet tunnel (From 5+250 Km to 22+460 Km)

21,350,000.00

ICB Prior 1S2E Q1 / 2017 Prequalification of Bidders: N Domestic Preference Applicable: N Advance Contracting: N Bidding Document: Large Works

NWPC-NCB-01

Wemedilla LBMC from 0+000 Km to 5+250 Km & new Sluice and tail canal

5,550,000.00

NCB Prior 1S2E Q1 / 2016 Prequalification of Bidders: N Domestic Preference Applicable: Y Advance Contracting: N Bidding Document: Small Works

UEC-ICB-01

Construction of Upper Elahera Canal From 0+100 Km to 6+226 Km

24,740,000.00

ICB Prior 1S2E Q1 / 2016 Prequalification of Bidders: N Domestic Preference Applicable: N Advance Contracting: Y Bidding Document: Large Works

Page 126: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Various lots-1

Office furniture, IT equipment and software

1,360,000.00

SHOPPING Prior Q2 / 2014 Advance Contracting: N

3. Consulting Services Contracts Estimated to Cost $100,000 or More

The following table lists consulting services contracts for which the recruitment activity is either ongoing or expected to commence within the next 18 months.

Package Number General Description Estimated

Value Recruitment

Method Review (Prior/ Post)

Advertisement Date

(quarter/year) Type of

Proposal Comments

CS-2 “Improving System Efficiencies and Water Productivity” Consultants

1,350,000.00 QCBS Prior Q2 / 2016 STP

Assignment: International Quality-Cost Ratio: 90:10 Advance Contracting: N Comments: As per FAM.

CS-3 Expert panel and other specialist assistance as required

450,000.00 ICS Prior Q3 / 2015

Assignment: International Expertise: TBD Advance Contracting: N Comments: As per FAM.

Page 127: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

4. Goods and Works Contracts Estimated to Cost Less than $1 Million and Consulting Services Contracts Less than $100,000 (Smaller Value Contracts)

The following table lists smaller-value goods, works and consulting services contracts for which the activity is either ongoing or expected to commence within the next 18 months.

Goods and Works

Package Number

General Description

Estimated Value

Number of Contracts

Procurement Method

Review (Prior/ Post)

Bidding Procedure

Advertisement Date (quarter/year) Comments

MLBCR Goods-01

Supplying of operation and maintenance materials

660,000.00 1 NCB Prior 1S1E Q4 / 2016 Prequalification of Bidders: N Domestic Preference Applicable: N Advanced Contracting: N Bidding Document: Goods

Various lots-2

Utility shifting and deposit works by government-owned entities

450,000.00 1 FA Post Q4 / 2016 Advanced Contracting: N

Various lots-3

Community works contracts

180,000.00 1 CPP Prior Q2 / 2016 Advanced Contracting: N Comments: Many contracts, each contract not

Page 128: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

exceeding $20,000. Prior review for first contract. Direct contracting.

Various lots-4

Field office works 300,000.00 5 SHOPPING Post Q4 / 2014 Advanced Contracting: Y

Various lots-5

Vehicles 680,000.00 1 NCB Prior 1S1E Q1 / 2016 Prequalification of Bidders: N Domestic Preference Applicable: N Advanced Contracting: N Bidding Document: Goods

Consulting Services

Package Number

General Description

Estimated Value

Number of Contracts

Recruitment Method

Review (Prior/ Post)

Advertisement Date

(quarter/year) Type of

Proposal Comments

None

B. Indicative List of Packages Required Under the Project

The following table provides an indicative list of goods, works and consulting services contracts over the life of the project, other than those mentioned in previous sections (i.e., those expected beyond the current period).

Page 129: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

Goods and Works

Package Number General Description

Estimated Value

(cumulative)

Estimated Number of Contracts

Procurement Method

Review (Prior/Post)

Bidding Procedure Comments

None

Consulting Services

Package Number General Description

Estimated Value

(cumulative)

Estimated Number of Contracts

Recruitment Method

Review (Prior/Post)

Type of Proposal Comments

None

C. List of Awarded and On-going, and Completed Contracts

The following tables list the awarded and on-going contracts, and completed contracts.

1. Awarded and Ongoing Contracts Goods and Works

Package Number

General Description

Estimated Value

Awarded Contract

Value Procurement

Method Advertisement

Date (quarter/year)

Date of ADB Approval of

Contract Award

Comments

None Consulting Services

Package Number

General Description

Estimated Value

Awarded Contract

Value Recruitment

Method Advertisement

Date (quarter/year)

Date of ADB Approval of

Contract Award

Comments

CS-1 Program Design, Management and Supervision Consultants

22,630,000.00 20,783,510.88 QCBS Q4 / 2014 27-OCT-15

D. National Competitive Bidding

A. Regulation and Reference Documents 1. The procedures to be followed for national competitive bidding shall conform to the provisions prescribed in the Procurement Guidelines 2006 for Goods and Works issued in January 2006 by the National Procurement Agency, and the specific procedures prescribed by the Procurement Manual issued in March 2006, with the clarifications and modifications described in the following paragraphs required for compliance with the provisions of the ADB Procurement Guidelines. B. Procurement Procedures

Page 130: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

1. Eligibility 2. The eligibility of bidders shall be as defined under Section I of ADB’s Procurement Guidelines (2015, as amended from time to time) (the “Guidelines); accordingly, no bidder or potential bidder should be declared ineligible for reasons other than those provided in Section I of the Guidelines.

2. Registration and Sanctioning 3. Registration is acceptable under the following conditions:

(i) Bidding shall not be restricted to pre-registered firms under the national registration system of the Institute for Construction, Training and Development (ICTAD), and such registration shall not be a condition for the submission of bids in the bidding process.

(ii) Where registration is required prior to award of contract, bidders: (i) shall be allowed a reasonable time to

complete the ICTAD registration process; and (ii) shall not be denied registration for reasons unrelated to their capability and resources to successfully perform the contract, which shall be verified through post-qualification.

(iii) National sanction lists or blacklists may be applied only with prior approval of ADB.

3. Prequalification

4. Prequalification is discouraged for NCB. When used, particularly for works contracts, an individual prequalification exercise is acceptable for each contract as is the use of a registration system (or approved standing list) of contractors based on criteria such as experience, financial capacity, and technical capacity. Foreign bidders from eligible countries must, however, be allowed to register and to bid without unreasonable cost or additional requirements.

4. Advertising 5. The posting of NCB specific notices for contracts valued at less than $1 million on ADB’s website is not required but is highly recommended.

5. Preferences 6. The following shall be observed:

(i) No preference of any kind shall be given to domestic bidders or for domestically

manufactured goods.

(ii) Foreign suppliers and contractors from ADB member countries shall be allowed to bid, without registration, licensing, and other government authorizations, leaving compliance with these requirements for after award and before signing of contract.

6. Participation by Government-Owned Enterprises

7. Government-owned enterprises in the Democratic Socialist Republic of Sri Lanka shall be eligible to participate only if they can establish that they are legally and financially autonomous, operate under commercial law, and are not a dependent agency of the procuring entity, or the Project Executing Agency or Implementing Agency.

7. Rejection of Bids and Rebidding 8. Bids shall not be subjected to a test for unrealistic rates. No lowest evaluated and substantially responsive bid shall be rejected on the basis of comparison to rates, including but not limited to market, historical, or agency established rates, without prior approval of ADB.

Page 131: 20160305 MWSIP Final Inception Report Mahaweli Consultancy Bureau MCM MDP MIWRM ... Organizational Chart of the MWSIP ... The Hierarchy of Capacity Needs

9. Bids shall not be rejected and new bids solicited without the ADB’s prior concurrence.

8. Price Negotiations 10. Price negotiation shall be allowed only where the price offered by the lowest evaluated and substantially responsive bidder substantially exceeds costs estimates. Approval of ADB is required prior to any negotiation of prices.

C. Bidding Documents

9. Acceptable Bidding Documents 11. Procuring entities shall use standard bidding documents acceptable to ADB for the Procurement of Goods, Works and Consulting Services, based ideally on the standard bidding documents issued by ADB.

10. Bid Security 12. Where required, bid security shall be in the form of a certified check, a letter of credit or a bank guarantee from a reputable bank.

11. ADB Policy Clauses 13. A provision shall be included in all NCB works and goods contracts financed by ADB requiring suppliers and contractors to permit ADB to inspect their accounts and records and other documents relating to the bid submission and the performance of the contract, and to have them audited by auditors appointed by ADB.

14. A provision shall be included in all bidding documents for NCB works and goods contracts financed by ADB stating that the Borrower shall reject a proposal for award if it determines that the bidder recommended for award has, directly or through an agent, engaged in corrupt, fraudulent, collusive, coercive or obstructive practices in competing for the contract in question.

15. A provision shall be included in all bidding documents for NCB works and goods contracts financed by ADB stating that ADB will declare a firm or individual ineligible, either indefinitely or for a stated period, to be awarded a contract financed by ADB, if it at any time determines that the firm or individual has, directly or through an agent, engaged in corrupt, fraudulent, collusive, coercive or obstructive practices or any integrity violation in competing for, or in executing, ADB-financed contract.