26
* The views in this paper are entirely the authors and do not necessarily reflect the views of BP America Production Company or its affiliates. MORE THAN MEETING SPEC: EXAMINATION OF RECENT PROCESS SAFETY INCIDENTS IN GAS CONDITIONING SYSTEMS SHOULD BE CAUSE FOR PAUSE Brian Pack, P.E. * BP America Production Company 501 Westlake Park Blvd [email protected] 281-366-1604 Aubry Shackelford, P.E. Inglenook Engineering, Inc. 15306 Amesbury Lane Sugar Land, TX 77478 [email protected] 713-805-8277 ABSTRACT Review of several Upstream natural gas liquids (NGL) processing facilities, onshore gas conditioning and dew point process facilities, booster compressor stations, and offshore production platforms and FPSOs can offer designers of gas conditioning systems, such as glycol dehydration systems and amine sweetening systems, lessons on process safety that should be fundamental to any design of these systems. In particular, this paper evaluates four industry process safety examples of possible inadequate overpressure protection design related to amine sweetening, glycol dehydration, and molecular sieve dehydration systems. The examples reflect systematic design issues in traditional gas sweetening overpressure protection analysis and reveal opportunities for improvement in future designs. Further, this paper provides an analysis of other design conditions that should be verified regarding overpressure protection within typical gas conditioning systems based on prior weaknesses identified in these designs by the Authors. It is the Authors’ goal to raise awareness that the design intent of gas conditioning systems must be more than just meeting process specification but must consider robust process safety features due to in-situ hazardous materials and often harsh process conditions such as high operating pressures and temperatures and corrosive environments. SYNOPSIS As illustrated by recent process safety related incidents and near-misses, designs of gas conditioning systems must consider robust process safety features, including overpressure protection. 323

2013: MORE THAN MEETING SPEC: EXAMINATION OF …...such as catastrophic failure or release of materials, due to abnormal pressures. In the U.S. Chemical Safety and Hazard Investigation

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 2013: MORE THAN MEETING SPEC: EXAMINATION OF …...such as catastrophic failure or release of materials, due to abnormal pressures. In the U.S. Chemical Safety and Hazard Investigation

*The views in this paper are entirely the authors and do not necessarily reflect the views of BP America

Production Company or its affiliates.

MORE THAN MEETING SPEC: EXAMINATION OF RECENT

PROCESS SAFETY INCIDENTS IN GAS CONDITIONING SYSTEMS

SHOULD BE CAUSE FOR PAUSE

Brian Pack, P.E.

*

BP America Production Company

501 Westlake Park Blvd

[email protected]

281-366-1604

Aubry Shackelford, P.E.

Inglenook Engineering, Inc.

15306 Amesbury Lane

Sugar Land, TX 77478

[email protected]

713-805-8277

ABSTRACT

Review of several Upstream natural gas liquids (NGL) processing facilities, onshore gas

conditioning and dew point process facilities, booster compressor stations, and offshore

production platforms and FPSOs can offer designers of gas conditioning systems, such as

glycol dehydration systems and amine sweetening systems, lessons on process safety that

should be fundamental to any design of these systems. In particular, this paper evaluates four

industry process safety examples of possible inadequate overpressure protection design

related to amine sweetening, glycol dehydration, and molecular sieve dehydration systems.

The examples reflect systematic design issues in traditional gas sweetening overpressure

protection analysis and reveal opportunities for improvement in future designs. Further, this

paper provides an analysis of other design conditions that should be verified regarding

overpressure protection within typical gas conditioning systems based on prior weaknesses

identified in these designs by the Authors. It is the Authors’ goal to raise awareness that the

design intent of gas conditioning systems must be more than just meeting process

specification but must consider robust process safety features due to in-situ hazardous

materials and often harsh process conditions such as high operating pressures and

temperatures and corrosive environments.

SYNOPSIS

As illustrated by recent process safety related incidents and near-misses, designs of gas

conditioning systems must consider robust process safety features, including overpressure

protection.

323

Page 2: 2013: MORE THAN MEETING SPEC: EXAMINATION OF …...such as catastrophic failure or release of materials, due to abnormal pressures. In the U.S. Chemical Safety and Hazard Investigation

MORE THAN MEETING SPEC: EXAMINATION OF RECENT

PROCESS SAFETY INCIDENTS IN GAS CONDITIONING SYSTEMS

SHOULD BE CAUSE FOR PAUSE

Brian Pack, P.E.; BP America Production Company; Houston, TX

Aubry Shackelford, P.E.; Inglenook Engineering, Inc.; Sugar Land, TX

Introduction

In 2006, the AIChE’s Center for Chemical Process Safety (CCPS) published the

second edition of an industry-wide study called “The Business Case for Process Safety” [1]

that identifies significant ways in which a business benefits from a vigorous process safety

program: as a means for enhancing the public’s perception of a company’s corporate

responsibility, as a useful element in ensuring a company’s business flexibility, as a direct

means to reducing risks to the company, and as a means for sustaining the value of a

company. These key items impress upon various industries the value of process safety, even

when a particular industry or operating facility is not specifically covered under the

Occupational Safety & Health Administration (OSHA) Process Safety Management (PSM)

standard 29 CFR 1910.119 Management of Highly Hazardous Chemicals, such as many gas

conditioning units. Despite some gas conditioning units not being covered under the PSM

standard, Owner/Operators in the United States are still accountable to act in accordance with

the “general duty” requirements of the Occupation Safety & Health Act of 1970.

One important element in a PSM program is the overpressure protection and effluent

handling systems that are designed to protect equipment and personnel from consequences

such as catastrophic failure or release of materials, due to abnormal pressures. In the U.S.

Chemical Safety and Hazard Investigation Board’s 1998 investigation into the explosion at

the Temple 22-1 Common Point Separation Facility in Pitkin, Louisiana [2], the final report

recommended that the oil and gas operator “institute a formal engineering design review

process for all oil and gas production facilities, following good engineering practices and

including analyses of process hazards; implement a program to ensure that all oil and gas

production equipment that is potentially subject to overpressurization is equipped with

adequate pressure-relief systems, and audit compliance with the program; and develop

written operating procedures for oil and gas production facilities and implement programs to

ensure that all workers, including contract employees, are trained in the use of the

procedures…” The findings of the investigation echo the importance the Owner/Operator

has in embedding the sound process safety design philosophy inherent in the PSM standard,

even if the processes in question are not specifically governed by the regulation.

Another important element in a PSM program, and for process safety in general, is

embedding the philosophy of inherently safer design (ISD), where a process is made safer as

part of the design itself, during the facility or process’s concept stage. In response to the U.S.

Chemical Safety and Hazard Investigation Board’s 2008 investigation into the explosion at

the Bayer CropScience facility in West Virginia [3], the United States Congress directed the

Chemical Safety Board (CSB) to commission the National Academy of Sciences to

investigate the application of ISD, and the CSB has subsequently called for Industry to apply

324

Page 3: 2013: MORE THAN MEETING SPEC: EXAMINATION OF …...such as catastrophic failure or release of materials, due to abnormal pressures. In the U.S. Chemical Safety and Hazard Investigation

the principles of ISD. According to CSB Chair Rafael Moure-Eraso, “the principles of

inherently safer processing can be an effective way for chemical companies to eliminate or

reduce hazards, prevent accidents, and protect nearby communities.”

The CCPS, in its comprehensive book on the topic states that, “Inherent safety is a

concept, an approach to safety that focuses on eliminating or reducing the hazards associated

with a set of conditions…if it reduces or eliminates the hazards associated with materials and

operations used in the process and this reduction or elimination is permanent and

inseparable” [4]. Trevor Kletz has outlined the concept of minimizing process hazards as

opposed to simply controlling them in his work to identify and reduce process safety

incidents [5], and the technology and implementation of ISD continues to evolve and to

receive greater exposure. The four oft-cited tenets of ISD consistent with Kletz’ original

work and subsequent elaboration on the topic by the CCPS are: substitution (replacing one

material with another that is less hazardous), minimization (reducing the amount of

hazardous material in the process), moderation (using less hazardous process conditions such

as lower pressures or temperatures), and simplification (designing processes to be less

complicated and less prone to failure as a result). Application of these principles has led to

significant improvements not only in reducing the potential for process safety incidents, but

also in the design and operation of these processes. It is important, however, to recognize

that these principles are better incorporated during design as adding inherent safety features

to an existing facility may not always be justified from a risk and economic investment

standpoint [4].

In this article, several recent examples are reviewed to highlight specific instances of

issues related to overpressure protection and effluent handling systems as well as

opportunities for embedding the ISD concept in engineering molecular sieve dehydration,

glycol dehydration, and amine sweetening units. In addition, a general overview of

frequently encountered issues in the design of the protective systems for these gas

conditioning units is provided. It should be noted that each conditioning unit installation

may have unique aspects that are not considered in the general overview, that commonly

required aspects are not touched upon in this analysis, and that formal engineering design

reviews and effective hazard analyses are required when designing the protective systems for

these units; nonetheless, the intent is to provide some additional considerations, based on

experience and review of varying configurations for the aforementioned gas conditioning

units, for those conducting engineering design reviews and hazard analyses on these units.

These examples related to overpressure protection and effluent handling re-emphasize the

need to raise awareness that designs of gas conditioning systems must be more than just

meeting process specification – the designs must consider robust process safety features due

to in-situ hazardous materials and process conditions.

Molecular Sieve Dehydration

Introduction

Molecular sieve technology is common in Upstream processing facilities throughout

the world. Molecular sieve units are used to separate water from natural gas, separate

contaminates, such as mercaptans, from natural gas liquids (NGLs), and can be used in

325

Page 4: 2013: MORE THAN MEETING SPEC: EXAMINATION OF …...such as catastrophic failure or release of materials, due to abnormal pressures. In the U.S. Chemical Safety and Hazard Investigation

cryogenic plants to separate small amounts of CO2 from N2-rich natural gas upstream of the

Cold Box. Molecular sieve technology is based on the fundamental separation principle of

adsorption. Adsorption requires design of a solid structure (sieve media) such that the

desired molecule (contaminant) to be adsorbed preferentially binds to the solid structure.

Unlike absorption where the molecule is dissolved into the solution of the absorbent,

adsorption does not physically alter the structure of the molecule but only serves as a

binding-agent while the other non-preferential material passes through. The adsorbed

molecule is then released (regenerated) by either increased heating (breaking the bond

established from the surface tension) or decreased pressure.

The molecular sieve process is carried out in a multi-bed packed-column arrangement

where one (or many) bed(s) operate(s) in adsorption while one (or many) bed(s)

simultaneously operate(s) in regeneration. Mole sieve separation is a batch process because

it takes time for the desired separation molecule to generate during the heating or

depressuring cycle. Typically, mole sieve cycle times are 8 to 12 hours. By using more than

one bed, the operation becomes continuous in principle since one bed is in adsorption and the

other bed is in regeneration. When the regeneration cycle is complete, either automatically

or manually, the cycles are reversed—the bed in adsorption goes into regeneration while the

newly regenerated bed receives the feed containing the molecule in need of adsorption.

Figure 1 below shows a typical mole sieve set-up, obtained from Figure 20-80 of GPSA

Engineering Data Book, 12th Edition [6], and will form the basis of the case study examined

in this section of the paper.

Figure 1 - General Representation of Molecular Sieve Process

In Figure 1, Bed 1 receives the wet feed gas from the feed gas separator, while Bed 2

is isolated from the feed. Bed 2 is receiving hot regenerated gas, usually feed gas that is

heated by a regeneration gas heater. The heat media for the regeneration gas heater may be

hot oil, glycol, or even direct fired-natural gas as depicted in the figure above. The

326

Page 5: 2013: MORE THAN MEETING SPEC: EXAMINATION OF …...such as catastrophic failure or release of materials, due to abnormal pressures. In the U.S. Chemical Safety and Hazard Investigation

regenerated gas flows upward through the bed and departs the top of the bed where it is

cooled via an overhead condenser and the desorbed water is collected and disposed.

While this operation seems simple and straight forward, there are a number of issues

to consider when operating mole sieve units as cited in the literature. One textbook lists the

following to be aware of when using mole sieve technology.

“Under normal operating conditions, the usable life of desiccant ranges from one to

four years…Abnormally fast degradation occurs through blockage of small pores and

capillary openings from lubricating oils, amines, glycols, corrosion inhibitors, and other

contaminants, which cannot be removed during the regeneration cycle. Hydrogen sulphide

can also damage the desiccant and reduce its capacity.

“Operating problems with the solid-desiccant dehydration include:

• Space adsorbents degenerate with use and require replacement.

• Dehydrating tower must be regenerated and cooled for operation before another

tower approaches exhaustion. The maximum allowable time on dehydration

gradually shortens because desiccant loses capacity with use.

“Although this type of dehydrator has high adaptability to sudden load changes,

sudden pressure surges should be avoided because they may upset the desiccant bed and

channel the gas stream resulting in poor dehydration” [7].

The author does not mention safety issues that may be created by design, which can

sometimes lead to unintended consequences as a result of the nature of the process. The

author points out, and discusses at some length, the precision involved in the mole sieve

dehydration process. The timing of the regeneration and cooling cycles is precise and

changes as the sieve media becomes spent with age. He speaks of pressure control and how

it is important in preventing bed channeling, and where control is poor, how it contributes to

“clumping” of media in the column, which can drive additional pressure drop. These two

areas are just a couple of instances where “operational” concerns can reveal themselves as

design flaws where adequate overpressure protection was not provided, possibly leading to

compromising the integrity of the equipment.

Incident Description – Switching Valve Failure

This portion of the paper will focus specifically on the first operational consideration

mentioned, the precise nature of the switching valve behavior. An example will be described

in which the switching valves failed, resulting in the overpressure (but not loss of

containment or equipment integrity) of the downstream regeneration system.

The nature of the batch operation and the switching between adsorption, regeneration

or cooling cycles requires a level of reliability in the control scheme that may be overlooked.

If the overhead valve on the bed in regeneration sticks open during a change from adsorption,

high pressure gas is suddenly introduced into the bed intended for low pressure hot

regeneration gas. The adsorption and regeneration systems should be designed to

accommodate the failure of the switching valves during changeover from drying to

327

Page 6: 2013: MORE THAN MEETING SPEC: EXAMINATION OF …...such as catastrophic failure or release of materials, due to abnormal pressures. In the U.S. Chemical Safety and Hazard Investigation

regeneration in order to alleviate this concern. The designs should consider the temperature,

volume, and pressure changes that may occur during this failure.

Three gas production facilities having a mole sieve arrangement similar to that shown

in Figure 1 were reviewed during a relief system design basis calculation revalidation

process. During the review, it was noted that two of the three facilities had regeneration

systems rated at pressures substantially lower than the mole sieve beds. The third facility’s

regeneration system was rated for the same pressure as the mole sieve beds, and so was less

likely to experience adverse pressures due to a failure of switching valves during the

adsorption/regeneration cycle. While it may be common to design the regeneration system at

a lower pressure than the drying section of the mole sieve unit, the overpressure protection

scheme should be designed to accommodate failures across this pressure boundary interface.

Design of the drying and regeneration sections to the same pressure is a result of putting ISD

concepts into practice.

At one of the facilities where the regeneration system was not rated to the same

pressure as the drying section a flaring event occurred. The downstream regeneration system

was protected by a single rupture disk located on the overhead piping of the regeneration gas

scrubber, and this rupture disk burst in response to the pressure spike produced as a result of

upstream switching valve failure. Pressure continued to rise in the flare header/knock-out

(KO) drum requiring Operations personnel to take action to cut the feed to the mole sieve

beds, stemming the overpressure event. While it is important that no physical or sustainable

adverse consequence resulted (outside of having to replace the burst disk), the event resulted

in mechanical equipment exceeding its specified operating design limits for a short duration.

One of the overhead switching valves spuriously tripped open, allowing 600 psig

inlet gas to flow into the regeneration system operating at 65 psig. The regeneration system

itself pressured up rapidly from 65 psig to the burst pressure of the rupture disk at 200 psig.

Figure 2 below shows a representation of the process.

Figure 2 - Representation of Mole Sieve Process for Switching Valve Failure Incident

328

Page 7: 2013: MORE THAN MEETING SPEC: EXAMINATION OF …...such as catastrophic failure or release of materials, due to abnormal pressures. In the U.S. Chemical Safety and Hazard Investigation

The relief basis indicated that the downstream rupture disk protecting the

regeneration system is sized for blocked flow from the inlet gas. Because the switching

valve misalignment does not appear to have been considered in design, the relief header was

not suited to handle the initial transient flow across the open valve at upstream operating

pressure. In the event a switching valve fails open at normal upstream operating conditions

the relief capacity is approximately four times the rate determined for the blocked flow case.

The flare header is rated (limited by the pressure rating of the KO drum) to a capacity less

than the rate produced by the switching valve failure. Figure 3 shows a more detailed

representation of this switching valve failure case.

Figure 3 - Regeneration Process at Incident Conditions

The design data obtained during the review did not consider the failure of the

switching valve during normal operations. Because the documentation for the justification

behind not considering this a valid case for overpressure was not found during the review,

any reason suggested here is conjecture. However, one of three reasons is likely possible:

1) The designers did not believe the failure of the switching valves was very likely.

2) Only a consideration was made for steady state rate during the failure as opposed

to the initial transient flow (more on this in a minute).

3) Transient flow was considered and it was decided that the design would not be

based on a condition that resulted in possible hazardous conditions for a short period

of time (more on this as well).

Whatever the actual reason, it does highlight the fact that overpressure protection is

not necessarily a black and white science, as there can be subjectivity and judgment that

informs the basis for the relief protection philosophy. If the reasons were either (2) or (3)

this would be a decision the original designers took from a risk position. Not considering the

higher transient flows resulting from switching valve failure involves an acceptance of the

notion a deviation from design can occur, but the likelihood and duration are sufficiently low

that it should not govern the basis for design of the flare. While this may be acceptable to a

given Owner/Operator, the lack of documentation does not help when a revalidation of

design may occur many years later.

329

Page 8: 2013: MORE THAN MEETING SPEC: EXAMINATION OF …...such as catastrophic failure or release of materials, due to abnormal pressures. In the U.S. Chemical Safety and Hazard Investigation

The main drivers resulting in the higher transient relief load from switching valve

failure are the volumetric imbalance and pressure imbalance (driving a difference in fluid

density). The volume upstream of the switching valve is approximately 1.3 times greater

than the gas expansion volume available in the regeneration section (including the flare

header). The depressuring of this volume at operating pressure to relief conditions across the

fixed flow area of the failed-open switching valve is a much larger rate than the steady state

flow rate into the plant. Once the upstream stored volume is exhausted from the higher

depressuring rate, the relief requirement becomes the steady state rate. These two factors

explain why the pressure continued to rise when the rupture disk burst in the example

discussed here.

So summarizing the relief scenario:

1) One dryer is in regeneration mode.

2) Gas flow from the inlet and through the regeneration system is at normal inlet

conditions.

3) Switching valve on the dryer in adsorption fails open.

4) High pressure inlet gas from the dryer in adsorption and the resident regeneration

gas flowing through the bed in regeneration begin to fill up the regeneration system

(cooler and scrubber).

5) The higher transient flow of approximately four times steady-state inlet rate flows

across the failed switching valve and into the regeneration system.

6) Pressure in the regeneration system increases causing the rupture disk to burst and

the pressure in the flare system to continue to rise.

7) Inlet flow is stopped, stemming the rising pressure in the flare system.

Modeling performed later supported the bottleneck existing in the relief system

during a switching valve failure. A HYSYS depressuring model was built to simulate the

transient conditions described above. The results of the model are summarized in Figure 4

below. When a switching valve fails open, there is a period of less than two minutes where

rates and pressures exceed the capacity of the flare system before steady state conditions are

returned. It is during this transient period the integrity of the relief system may be subject to

compromise. While each Owner/Operator needs to consider its philosophy for handling

transient conditions, it was deemed unacceptable for this facility not to provide overpressure

protection for this case, and a team was formed to resolve the issue. Though it likely would

not have altered the decision to modify or accept this original design, the inability to find

documentation supporting the decision to not consider switching valve failure a credible

overpressure case is important and stresses the need for the development and lifecycle

maintenance of thorough documentation for the basis of overpressure protection. Much care

was taken to maintain the basis for the operational design of the mole sieve (original

operations and maintenance manuals are existent and in continued use), and the relief design

basis must be treated in like manner such that it stays evergreen for the full facility lifecycle.

330

Page 9: 2013: MORE THAN MEETING SPEC: EXAMINATION OF …...such as catastrophic failure or release of materials, due to abnormal pressures. In the U.S. Chemical Safety and Hazard Investigation

Figure 4 - Simulated Flow Rate (lb/hr) Profile vs Time (sec) under Relief Conditions

A number of proposed solutions were considered and though much could be learned

from this process, this paper does not allow for the time to delve into these options. A few of

the more salient proposed solutions that were investigated are listed below with the last

option being that which was selected for design and installation:

1) Replacement or addition of smaller trim in the switching valves.

2) Installation of a high integrity pressure protection system (HIPPS) on the

regeneration overhead.

3) Replacement of existing switching valves with valves rated for the identified safety

integrity level (SIL) as determined by a layer of protection analysis (LOPA).

4) Replacement of the flare KO drum and debottleneck a section of the flare header.

5) Addition of a restriction orifice to reduce the flow through the switching valve and

addition of a new rupture disk to protect the regeneration system.

As mentioned earlier, a second facility’s mole sieve unit had a similar arrangement to

the one discussed in this section of the paper. Further investigation of the relief design basis

for this unit revealed the same problem. Modeling further supported the hypothesis that

during full-open failure of the overhead switching valve at normal operating pressures, the

regeneration system would experience pressures in excess of its MAWP. The solution at this

facility was a little different because the flare capacity was not constrained by the

overpressure event, as was the case in the facility reviewed here. The resulting design

solution was simply replacing the existing relief valve protecting the regeneration system to

an appropriately sized relief valve for the switching valve failure case.

331

Page 10: 2013: MORE THAN MEETING SPEC: EXAMINATION OF …...such as catastrophic failure or release of materials, due to abnormal pressures. In the U.S. Chemical Safety and Hazard Investigation

This evaluation revealed an issue in the fundamental design of the mole sieve system

and regeneration system and serves as a good reminder that all credible overpressure

situations should be considered and documented during design of the process unit and that a

facility must consider due diligence in full lifecycle maintenance of these records. Where

possible, ISD features should be considered (i.e., providing the same pressure rating for

drying and regeneration sections) or, at a minimum, the design should allow for the provision

of appropriate overpressure protection systems.

General Awareness Considerations

Figure 5 below shows an example process flow diagram for a solid desiccant

dehydrator twin tower system adapted from Figure 20-80 of GPSA Engineering Data Book,

12th Edition [6]. The process flow diagram shows several areas of additional emphasis.

Figure 5 - Example Solid Desiccant Dehydrator Twin Tower System

Valve misalignment – As described in the case study above, valve misalignment can

cause flow from the adsorbing beds into the regenerating beds with a potentially high initial

transient flow. Depending on the design and state of the systems, overpressure of the

downstream regeneration system may occur. In addition, other effects may need to be

considered, including those associated with rapid pressure and/or temperature changes.

Equivalent design pressure for the regeneration system – When feasible, the design

pressure for the mole sieve towers is specified at or above the maximum inlet gas pressure

achievable. As suggested in the case study above, the equipment in the regeneration system

should also be specified at or above the maximum inlet gas pressure, despite its operation at

lower pressures. This ISD may prevent blocked outlets or inadvertent lineups of the

regeneration system from overpressuring the equipment by the inlet gas.

Regeneration compressor suction pressure – In the event of a blocked outlet on the

regeneration gas compressor, the flow to the compressor and the pressure drop in the

upstream mole sieve towers will decrease. This results in a potential increase in the suction

pressure on the compressor, which directly translates into a higher discharge pressure. If ISD

332

Page 11: 2013: MORE THAN MEETING SPEC: EXAMINATION OF …...such as catastrophic failure or release of materials, due to abnormal pressures. In the U.S. Chemical Safety and Hazard Investigation

tactics are employed, the equipment between the compressor and potential sources of

blockage need to be designed to handle this potentially higher shut-in pressure.

Proximity of fired heater – The proximity of the fired heater to discharges to

atmosphere that may contain flammable gas should be considered. The fired heater may act

as an ignition source, and the dispersion of the relief effluent should be sufficient to prevent a

flammable atmosphere from developing near the fired heater. This design consideration is

discussed in more detail below.

Hydrate formation – The potential for hydrate formation, especially at cooling

locations with high water content such as the regeneration gas cooler, should be considered

as a potential mechanism for blockage.

Low temperature discharge – The pressure relief or depressuring of product from the

mole sieves can result in low temperature discharges into the effluent handling system.

Glycol Dehydration

Introduction

Glycol dehydration is a separation technique used in Upstream and Downstream

operations. It is the most popular form of drying technique within Industry for removal of

water from natural gas and NGLs. Glycol dehydration is a form of drying carried out based

on the principle of absorption, unlike the mole sieve process already discussed. As opposed

to adsorption where impurities preferentially attach to a solid media, absorption is a chemical

process where impurities are chemically saturated into the transport medium (glycol in this

case). In glycol dehydration water is removed from natural gas by maximizing contact time

for mass transfer in packed or trayed columns. Typically triethylene glycol (TEG) is used for

dehydrating natural gases, though other glycols such as ethylene glycol or diethylene glycol

(DEG) have been used. It remains the most common form of drying technique in gas

conditioning processes within Upstream and Downstream operations because it is

economically more attractive than adsorption processes and usually capable of meeting the

required product specification (water dew point for pipeline transport) [7].

Figure 6 shows a typical representation of a glycol dehydration system. The

following process description is based on the equipment shown in Figure 6 as taken from the

Natural Gas Engineering Handbook [7]. Gas enters the dehydration contactor through a two-

phase (or three-phase) inlet gas scrubber, or additionally a coalescer may be provided, to

remove as much entrained liquid hydrocarbons as possible. The gas enters the contactor at

the bottom of the column and flows upward where it contacts the falling glycol on the trayed

or in the packed sections of the column. The gas flows down through the vertical cooler on

the side of the contactor where it is cross exchanged with the hot regenerated glycol before it

enters the contactor. The dry glycol (often described as the “lean glycol” stream because the

absorbed water has been liberated in the still or regenerator column) enters the top of the

contactor and flows down each tray where it contacts the feed gas. The wet glycol (often

described as the “rich glycol” stream because it contains the absorbed water from the feed

gas) exits the bottom of the column, passing through a particulate filter before being pumped

333

Page 12: 2013: MORE THAN MEETING SPEC: EXAMINATION OF …...such as catastrophic failure or release of materials, due to abnormal pressures. In the U.S. Chemical Safety and Hazard Investigation

into the low pressure flash separator where entrained feed gas is liberated. The rich glycol

continues through to the tube side of the heat exchanger surge tank and enters the top of the

stripping still of the glycol regenerator. As the rich glycol flows down the stripping still (also

known as a stall column) it contacts hot rising glycol and water vapors exiting the reboiler.

The glycol flows through the reboiler and is heated to approximately 350 °F to 400 °F to

remove the absorbed water vapor. The now lean glycol exits the reboiler into the shell side

of the heat exchanger surge tank and is pumped back to the bottom of the glycol cooler

before entering the top of the contactor to begin the drying process again.

Figure 6 - General Glycol Dehydration System

The aforementioned text book discusses a number of issues with the design and

operation of the glycol dehydration system shown in Figure 6; however, as was the case with

the mole sieve operations book discussed already, there is no discussion of safety related

concerns. Most of the discussion centers on how to prevent operational issues such as

particulate contamination through high temperature deposition from degraded glycol,

foaming from liquid hydrocarbon, glycol losses, or freezing. Two areas that can drive

process safety incidents discussed are overtemperature of the glycol in the reboiler and

corrosion due to deposition from degraded glycol. However, the author discusses these

issues based on how they drive operational concerns and not safety concerns [7].

Like the previous discussion on molecular sieves, there are safety related elements in

glycol design, especially in regard to overpressure protection and facility siting issues that

should be addressed in the design and operation of these systems. The following sections

discuss an example related to an offshore glycol plant and then general process safety related

problems, as observed from the review of a number of glycol plants.

Incident Description – Proximity to Fired Heater

In a typical glycol dehydration unit, the water is separated from the glycol in a Still

that is open to the atmosphere, where the water vapor exits the system, and the heat supply to

the reboiler is commonly a direct fired gas heater, having an exhaust flue stack that may be in

334

Page 13: 2013: MORE THAN MEETING SPEC: EXAMINATION OF …...such as catastrophic failure or release of materials, due to abnormal pressures. In the U.S. Chemical Safety and Hazard Investigation

close proximity to the atmospheric discharge from the Still. During various process upsets,

the effluent leaving the Still may not be all water vapor, and instead may contain flammable

materials, and the flue stack can provide an ignition source for that flammable material. In

an example from 2006, a level alarm on a flash separator prompted a shutdown and

subsequent drainage of the flash separator. Unfortunately, this drainage was not complete as

condensate was present in the separator during restart of the unit, and this condensate was fed

into the glycol recovery Still. Upon contact with the heated glycol/water system, the

condensate started boiling and exited into the atmosphere via the normal vent on the Still.

The condensate discharge contacted the nearby uninsulated flue stack, which served as an

ignition source, and a fire occurred.

Figure 7 – Representation of Glycol Dehydration System for Fired Heater Ignition Incident

This example illustrates a common approach to design where the hazard analysis is

limited to considerations based solely on the normal mode of operation. In the typical design

for a glycol reconcentration system having a direct fired gas heater, having the exhaust flue

stack from the heater in close proximity to the atmospheric vent from the Still is not even

considered as a potential hazard in relation to the effluent from that vent because the normal

vented material is water vapor. As seen in this example, various process upsets can cause

flammable materials to exit from the vent, and the flue stack can then be an ignition source.

The example reinforces the need for the design to consider ISD elements. While

physical separation is not always achievable in an offshore environment, the proper modeling

must be considered up-front to determine safe design distance for equipment where

interaction (such as the release of the flammable vapor) of hazardous conditions between the

equipment is minimized. Where the hazard cannot be eliminated due to spacing constraints

offshore, for example, the design should move to the next path in the ISD model which is

minimization. For this example, the effects of the hazardous condition may have been

prevented by installation of a shielding wall. If such a wall was prohibitive due to its weight,

335

Page 14: 2013: MORE THAN MEETING SPEC: EXAMINATION OF …...such as catastrophic failure or release of materials, due to abnormal pressures. In the U.S. Chemical Safety and Hazard Investigation

often a siting issue for offshore platforms, then control elements may need to be considered

(such as more robust gas or fire detection).

No matter the situation following the ISD methodology early in project development

helps the design provide support through documented rationale for design features related to

safety that are invaluable to the lifecycle operation of the facility. This example further

emphasizes the importance of the initial design hazards identification review. As stated,

abnormal operations were not considered in the design. Whether it was considered and

rejected is not apparent from the review of the incident. The investigation notes at a

minimum do not mention such documentation. The right people—such as operations,

engineering, process safety, and/or maintenance staff—must be involved during the early

hazards reviews in projects, even in the installation of somewhat simple gas conditioning

units such as glycol dehydration.

General Awareness Considerations

Figure 8 below shows an example process flow diagram for a glycol dehydration

system adapted from Figure 20-67 of GPSA Engineering Data Book, 12th Edition [6]. The

process flow diagram shows several areas of additional emphasis.

Figure 8 - Example Process Flow Diagram for Typical Glycol Dehydration Unit

Proximity of fired heater – As illustrated by the figure above, the proximity of a

fired heater to atmospheric discharges that may contain flammable materials should be

considered. This is particularly pertinent to the product breakthrough case discussed below

where the normal water vapor discharge may instead be a flammable material.

336

Page 15: 2013: MORE THAN MEETING SPEC: EXAMINATION OF …...such as catastrophic failure or release of materials, due to abnormal pressures. In the U.S. Chemical Safety and Hazard Investigation

Ice/hydrate formation in effluent – The rich glycol can contain a significant amount

of water, which may be present in the flash gas. In the event the discharge from the separator

is opened to a collection system (e.g. flare system), the conditions for ice and/or hydrate

formation may be present with the flow of free water, low molecular weight hydrocarbons,

and low temperature brought about by means of the Joule-Thompson cooling or auto-

refrigeration of the discharged fluid from higher pressure within the separator to lower

pressure in the collection system. Ice and/or hydrate formation is a mechanism for blockage

of the collection system piping, which may compromise the integrity of the system and

associated equipment. In addition, the blockage is likely to be common with the pressure

relief devices on equipment nearby the separator, thus compromising the overpressure

protection for that equipment as well. With a common blocked outlet, multiple pieces of

process equipment can experience overpressure for which there may be no appropriate relief

path.

Product breakthrough – As described in more detail in an example below, there is

the potential for the level of rich glycol to be lost, either by insufficient supply of lean glycol

to the Contactor or, more commonly, excessive withdrawal of rich glycol (e.g., level control

valve failure open), with subsequent flow of the product (“breakthrough”) into the glycol

regeneration system. If there is a Flash Tank (as shown in Figure 8) then the description

above is a scenario that affects the Flash Tank, and an additional breakthrough scenario may

need to be considered from the Flash Tank to the Reconcentrator (Reboiler / Still system).

Liquid overfilling – As described in more detail in an example below, there is the

potential for the level of rich glycol to exceed the top of the Flash Tank, depending on the

total glycol inventory and available volume within the Flash Tank.

Direct discharge to atmosphere does not automatically equate to adequate

overpressure protection – The water vapor outlet on the Still is commonly routed directly to

atmosphere, and the common presumption is that there is no need to provide overpressure

protection; however, depending on situations in which additional gas is supplied to the Still,

it is conceivable for the pressure to accumulate within the Still. For example, in the event of

a gas breakthrough from the Flash Tank, there is excess non-condensable gas introduced to

the Still at the same time some condensation of reboiled vapors provided by the direct

injection of the rich glycol is lost. The combination of this material accumulation may be

more than the discharge line can pass, thus causing the pressure within the Still to climb

above its pressure rating.

Low temperature discharge – The pressure relief or depressuring of gas from the

Contactor can result in low temperature discharges into the effluent handling system.

Amine Sweetening

Introduction

Amine is a solvent commonly used in Upstream and Downstream operations in the

Oil & Gas Industry to absorb contaminants in natural gas or NGLs. It is commonly used in

the Upstream environment to preferentially absorb CO2 or H2S in order to meet pipeline

337

Page 16: 2013: MORE THAN MEETING SPEC: EXAMINATION OF …...such as catastrophic failure or release of materials, due to abnormal pressures. In the U.S. Chemical Safety and Hazard Investigation

specifications. There are many types of amines used in the industry. Some common amines

are monoethanolamine (MEA), diethanolamine (DEA), and methyldiethanolamine (MDEA).

These are described as Primary, Secondary, and Tertiary amines, respectively. The nature of

this description is based on these amines’ atomic structure. Amines are derivatives of

Ammonia (NH3) and a primary amine, for example, only has one of the hydrogen atoms

replaced by another compound (like an alcohol (OH), for instance). The secondary amine

has two of the hydrogen atoms substituted by another compound and a tertiary amine has all

three hydrogen atoms substituted. The substitution of the positive hydrogen atoms with

another group makes the amine progressively less reactive; hence, a primary amine has more

favorable kinetics for reaction with contaminants such as CO2 or H2S than a tertiary amine.

The structures for these three types, and a common amine representing that type, are shown

below.

MEA DEA MDEA

There are many great papers (and Laurance Reid Gas Conditioning Conference

Fundamentals topics) presented on the subject of amine sweetening processes and

technology. The reader is referred to the following references for further guidance: [8] & [9].

As a result, no attempt is made here to provide the theoretical basis behind the process, but

only a short summary of the intended purpose of the process is described.

Figure 9 - Typical Amine Unit

338

Page 17: 2013: MORE THAN MEETING SPEC: EXAMINATION OF …...such as catastrophic failure or release of materials, due to abnormal pressures. In the U.S. Chemical Safety and Hazard Investigation

Amines remove contaminants based on the chemical absorption process. The rate of

absorption of the contaminant is dependent on the “reactivity” of the amine with the

contaminant. The amine reacts with the contaminant to form a salt. Figure 9 shows a typical

Amine Sweetening process adapted from Figure 21-4 of GPSA Engineering Data Book, 12th

Edition [6]. The raw feed gas (containing the contaminant) enters the contactor (absorber)

where it is flows toward the overhead and mixes in the column with amine fed from the top

of the column. The contactor may be either a trayed or packed column depending on the type

of processing required. The amine exiting the bottom of the column is known as “rich

amine” because it contains the chemically absorbed contaminant in solution. The gas

overhead, now free of the contaminant, goes to sales or to other parts of the plant for further

processing (such as NGL extraction). The rich amine enters a flash tank where pressure is

reduced to release any entrained natural gas or other hydrocarbons from the solution. The

contaminants will not flash in this case because the pressure is not sufficiently low and

additional heating is required to release the chemical bonding that occurs as a result of the

absorption. The rich amine enters a charcoal filter(s) where solid deposits (such as entrained

salts) are removed. From the charcoal filter(s) the rich amine is pre-heated by cross-

exchange as it enters the regeneration (still) column. The regeneration column is operated at

very low pressure (15-25 psig typically) and high temperatures (usually in excess of 250°F

depending on the type of amine used). The amine exiting the bottom of the column is known

as lean amine because it is now free of the contaminant, which exits the overhead in vapor

form where it is either incinerated, vented (if CO2 only) or sent on to a sulfur treating facility

for further processing. The lean amine is cross-exchanged with the rich amine entering the

regenerator and is pressured up so that it can be recirculated to the overhead of the contactor

where the absorption cycle continues.

With a basic understanding of the intent of amine sweetening and a representative

drawing a brief discussion of some of the major troubleshooting problems associated with

amine plants ensues. What one quickly discovers from a list of references, such as those

provided here, is that there is little discussion on problems with amine design, outside of

those that are operational related (i.e., issues that inhibit treating). One article acknowledges

that troubleshooting “usually falls into four categories for amine plants: 1) Failure to meet

spec; 2) Foaming; 3) Amine losses; and, 4) Corrosion” [8]. Though one could argue there

are seeds of “safety related” issues that could sprout from each of these, the one evident

where safety is concerned is corrosion, due to the possible loss of containment from the

weakness in metallurgy due to thinning or through-wall pin holes resulting in leakage or

rupture of the piping/vessels. Corrosion tends to be addressed either through ISD principles

by the use of corrosion resistant materials or operationally treated via corrosion inhibition

from chemical injection with monitoring.

While the above areas of concern (or minor variations/additions) are described in the

literature on amine plants, there are other ISD principles that should be considered critical

design elements for amine plants. It may be the literature takes for granted these principles

are already incorporated or part of the stock design, but while evaluating the overpressure

protection scheme for amine plants some opportunities for change may be noticed and should

be highlighted. A purpose of this paper is to heighten awareness on practical design and

operational considerations for overpressure protection among designers and operators of

amine plants. A couple of examples involving inadequate or lower reliability design are

339

Page 18: 2013: MORE THAN MEETING SPEC: EXAMINATION OF …...such as catastrophic failure or release of materials, due to abnormal pressures. In the U.S. Chemical Safety and Hazard Investigation

discussed followed by a discussion of some other common overpressure protection issues

that can occur.

Incident Description – Overfilling

The first example reviewed resulted in carryover of amine to the flare. The cause,

design problem, and corrective actions are discussed here. Figure 10 below is a sketch of the

pertinent equipment of the amine plant in question. A sequence of the events leading up to

the carryover to the flare can be summarized as follows:

1) It is night and the facility is unmanned.

2) Contactor pressure raises ~ 0.8 psi.

3) A high level alarm on the Flare KO drum occurs.

4) A high CO2 alarm in NGL product stream results in an operator callout.

5) Operator #1 arrives on-site.

6) Operator #1 turns off one fan in discharge cooler and waits to verify if NGL spec

improves.

7) Operator #1 acknowledges both alarms in the controls system.

8) Operator #2 arrives onsite in the morning to start his shift.

9) Operator #1 debriefs Operator #2 and they decide to check the amine system

because NGL continues out-of-spec.

10) The Flash Tank pressure is observed at 85 psig (normal ~ 70 psig) and the

Charcoal Filter bypass valve is opened to drop level and pressure in flash tank.

11) Liquids in the flare are noticed and the fluid is identified as Water/Amine (97 gal

H2O / 53 gal DEA).

340

Page 19: 2013: MORE THAN MEETING SPEC: EXAMINATION OF …...such as catastrophic failure or release of materials, due to abnormal pressures. In the U.S. Chemical Safety and Hazard Investigation

Figure 10 - Amine Plant Schematic from Liquid Carryover Incident

While a detailed analysis of the root cause of the occurrence and detailed corrective

actions were developed, there is not space in this paper to address these. However, a brief

summary of the cause and corrective actions taken is here discussed. What is discussed in

more detail is the impact of this example on the integrity of the overpressure protection

system, the decisions taken by the facility that affected the overpressure protection design

basis, and some fundamental design considerations to better improve the overpressure

protection design.

The above chronology spanned a period of around 6 hours. During this time amine

mixture continued to build in the flare system until the bypass valve around the charcoal

filter was opened. There was a plug in the filter element resulting from “dirty” amine. Field

deposits, heat stable salts, and corrosion particulates had built-up over a period of time to the

point where the outlet of the charcoal filter was restricted. With the inflow to the flash tank

greater than the outflow from the charcoal filter, the flash tank began overfilling with rich

amine and the pressure rose. There were no high level or high pressure alarms on the flash

tank, only local gauge indication. The rich amine overfilled the flash tank and began spilling

into the flare header where the problem was transferred to the flare KO drum. Though the

flare KO drum was fitted with a high level alarm, it did not initiate an operator call-out but

only alarmed locally within the control room. The flooded flash tank caused poor gas

treatment triggering a high CO2 alarm from off-spec NGL in the pipeline, resulting in an

operator call-out. Though the flare header filled with amine the operator was able to stem its

flow prior to overfilling the flare stack, averting the potential loss of primary containment.

As previously stated a number of causes led to the event with the immediate cause

determined as plugging in the charcoal filter from the dirty amine. First, for weeks the amine

was dirty based on the increased frequency in cycle time for filter element change-outs.

Almost three months prior, the filters completely plugged during the day shift. Operations

took corrective actions at the time and no adverse consequences resulted. At the time of this

incident, the filter elements were being replaced on a daily basis. Second, while the plant

341

Page 20: 2013: MORE THAN MEETING SPEC: EXAMINATION OF …...such as catastrophic failure or release of materials, due to abnormal pressures. In the U.S. Chemical Safety and Hazard Investigation

was originally designed as a fully manned facility, in recent years due to declining rates and

reduced facility complexity, it was manned for a single 12-hour shift during the day. While

moving to a non-continuous manned operation is a characteristic of the ISD philosophy, the

necessary changes were not made to the design or control scheme to support this operational

mode—where increased remote monitoring or active automated control may be required.

Third, a similar liquid carryover event to the flare (from a different process system) occurred

just 2 years prior from lack of automated controls. While active mechanical protection or

active instrumented protection are preferred protection layers to operator’s response to an

alarm, it is important to recognize that changes to operating philosophy may impact the

effectiveness of safeguards. Though reduction of workforce at the facility promoted the ISD

philosophies of minimization and separation, consideration must be given for how such a

change impacts the effectiveness of mechanical and instrumented safeguards at the facility.

A key takeaway for existing operations is that operating philosophy informs the

interdependencies of ISD features and any change to that philosophy not only affects

operations of the equipment, but also may adversely impact the effectiveness of safety

barriers, thereby reducing the overall process safety of the equipment.

While there were no adverse safety concerns as a result of this example (or the one

other prior liquid carryover situation), a few major concerns from carrying excessive liquids

into a flare system to consider are:

1) Quenching the flame.

2) Possible mixing of incompatible fluids.

3) Insufficient structural support of piping and effluent handling equipment.

Where excessive liquids can carryover from the KO drum and extinguish the flame,

environmental or safety hazards may result. During carryover, burning efficiency is likely

reduced and possible hazardous (flammable, toxic, or corrosive) fluid may be left uninhibited

to spray from the stack. The former can result in exceeding environmental permitting

constraints while the latter can result in fire, flammable or toxic vapor cloud, or other adverse

safety consequences such as personnel burns from hot liquid or acidic solution or damage to

the environment. Further, this situation could be compounded by a release from another part

of the facility involving a flammable or heavier than air vapor that could result in a major

explosion. In gas plants, amine systems may carry some of the largest liquid inventories in

the facility. If the flare KO drum is not sized to accommodate the overfilling that could

occur from this system, the overpressure protection of the facility may be compromised. It is

worthy to note at this point, that on more than one occasion the authors have come across

flare designs that speak of “THE design basis”; however, the facility designer must

understand how each piece of engineered equipment fits into the overall design scheme.

Amine systems carry the largest potential liquid inventories that may enter the flare system at

some facilities, and while the design of the flare may be said to be based on blocked outlet of

the inlet gas stream, this overpressure case may only be the design basis for the flare tip

itself. In reality, little liquids may result from blocked outlet of the inlet gas stream, and

therefore, it should not inform the basis of design of the flare KO drum liquid retention

capacity. As a result, each individual piece of equipment in the flare system must be

designed for the largest design overpressure load (or overfilling) case. For this plant, the

342

Page 21: 2013: MORE THAN MEETING SPEC: EXAMINATION OF …...such as catastrophic failure or release of materials, due to abnormal pressures. In the U.S. Chemical Safety and Hazard Investigation

amine flash tank carryover was the design case for the flare KO drum retention time, and it is

clear the installed equipment did not reflect that.

Where liquids can be released into a flare, the design of the header must be able to

accommodate the hazards of the liquids it receives. For this facility, there was not a “wet”

and “dry” flare system. Overpressure (and overfilling) cases from both vapor and liquid

sources were handled in a single flare system. In situations such as this, the designer must

understand the impact of possible simultaneous mixing of both wet and dry streams to

determine whether a negative outcome could occur. In some cases, the review of several

facilities using a common header system for wet and dry releases demonstrated the potential

of mixing “water-wet” streams (such as amine) and very cold gas (such as flashed NGLs).

This situation could result in freezing during the release. The releases do not have to be

simultaneous, however. A number of cases were noticed where pocketing existed in flare

headers. In these low points, the wet sources may build-up over time and the resident liquid

may freeze from a release from a cold source into the header. While the ISD principle of

segregation drives many facility designers today to build devoted flare headers for wet and

dry processes, it is recognized many designs in Upstream gas processing are not currently

configured in this manner. It is therefore incumbent on the engineering and operations staff

for these facilities to first understand whether the risk of freezing-off the header exists and

whether adequate measures are in place to eliminate or mitigate the potential consequences.

Before leaving this topic one should also note that “water-wet” solutions are not the only

source subject to freeze, creating a blockage in the header. Liquid hydrocarbon releases can

in fact be an even greater concern because of potential hydrate formation. Many hydrates

form at higher temperatures and therefore do not require cryogenic-type conditions to be

present for freezing and possible plugging to occur. Other possible hazards exist for mixing

of incompatible fluids but to a lesser extent in Upstream processing. These could include

situations such as mixing of volatiles or reactive fluids. It is important the designer and

operator understand the elements that inform all aspects of the flare header design.

It is uncommon that the piping supports and equipment supports (such as that for the

flare stack) in the flare header are designed for the weight imposed by a liquid filled system.

As a result, mechanical fatigue could compromise the integrity of the piping, equipment, and

supports. The result could be a loss of primary containment from failure of the support

system within the flare header. While it is not suggested here that the flare header be

designed based on a liquid filled system, it is important to understand that, if the liquid

handling part of the flare system has not been adequately addressed, it is a credible adverse

process condition that may arise.

As a result of the event, the site cleaned the amine solution and implemented better

monitoring of the health of the amine system. The design called for installation of high

pressure and level alarms and the addition to the safety logic of a plant shutdown on pressure

high-high and level high-high at both the flash tank and KO drum. These measures should

go a long way toward improving the overpressure protection system at the facility, but are

subject to issues as already discussed.

It is important to recognize that ISD is a philosophy. A balance of risk, design

feasibility, and business drivers ultimately inform the decisions on ISD features in the design

and evolution of safety barriers at a facility over time, and will vary from Owner/Operator to

343

Page 22: 2013: MORE THAN MEETING SPEC: EXAMINATION OF …...such as catastrophic failure or release of materials, due to abnormal pressures. In the U.S. Chemical Safety and Hazard Investigation

Owner/Operator. Further, and more importantly for existing facilities, it is crucial to

understand where interdependencies exist between safeguards within the ISD framework.

The decisions on how and when to incorporate the ISD principles must be made considering

the full lifecycle of the ISD tenets in practice at the facility. Without recognizing these

interdependencies, decisions that are made to promote continuous risk reduction by use of

ISD may in fact result in compromising other safeguards within the ISD lifecycle, diluting or

eliminating the desired risk reduction achieved at the facility.

Incident Description – Product Breakthrough (Gas Blowby)

In a typical amine unit operation, the rich amine from a contactor column is sent, via

a level control valve, to a flash tank operating at much lower pressures, allowing some of the

dissolved gases to flash off. As described in API Standard 521, 5th Edition §5.10.3 [10], a

credible cause of overpressure for the flash tank is failure of the level control valve or loss of

liquid upstream, with subsequent flow of the high pressure gas (known as “breakthrough” or

“blowby”) into the flash tank. In a recent incident in the Red River Parish in Louisiana that

occurred during the start-up of a facility, an amine flash tank overpressured when an operator

manually set the level control valve fully open and left it unattended. The flash tank did have

a pressure relief device; however, the isolation block valves downstream of the pressure

relief device were closed and not opened prior to the start-up. Without a means to relieve the

pressure, the amine flash tank subsequently ruptured.

Figure 11 – Representation of Amine Flash Tank System for Product Breakthrough Incident

While the initial reaction may be to point to the isolated pressure relief device as the

ultimate problem in this example, a closer look reveals several areas for improvement. The

lack of sufficient isolation/bypass controls was apparent not only with the pressure relief

device remaining isolated during start-up but also with the operation of the level control

valve. In addition, the pressure relief device was likely inappropriately sized to limit the

pressure during the event to the maximum allowable accumulation pressure—the flow rate of

a gas through a level control valve that is normally passing liquid is substantially greater than

344

Page 23: 2013: MORE THAN MEETING SPEC: EXAMINATION OF …...such as catastrophic failure or release of materials, due to abnormal pressures. In the U.S. Chemical Safety and Hazard Investigation

the normal liquid flow, and should be considered fully in the design basis for the

overpressure protection. This is yet another example of where the hazard analysis may be

limited to considerations based solely on the normal mode of operation, and the potential for

high pressure gas to flow through the control valve may not have been considered.

General Awareness Considerations

Figure 12 below shows an example process flow diagram for a typical chemical

reaction gas sweetening system adapted from Figure 21-4 of GPSA Engineering Data Book,

12th Edition [6]. The process flow diagram shows several areas of additional emphasis.

Figure 12 - Typical Gas Sweetening by Chemical Reaction

Liquid overfilling – As described above, some of the equipment in the amine system

can be subject to overfilling depending on relative volumes and supply pressures, and the

liquid amine volume may very well dictate the design of the KO drum in the effluent

handling system. ISD approaches to prevent overfilling can include limiting liquid volumes,

maximizing available processing volumes, and minimizing the difference between supply

pressures and design pressures of the regeneration equipment.

Product breakthrough – As described above, the potential exists for a breakthrough

of the product from the contactor into downstream equipment that is normally processing the

amine. It is very common for the product pressures to exceed the design pressures of the

downstream equipment, thus creating the potential for overpressure to occur. The product

breakthrough may not have been considered in the design because of the commonly

overlooked aspects related to process upsets involving fluids that are not normally being

handled.

Approach temperature at stripper reboiler – Ideally, the temperature of the heating

medium in the stripper reboiler will be less than the bubblepoint temperature of the stripper

345

Page 24: 2013: MORE THAN MEETING SPEC: EXAMINATION OF …...such as catastrophic failure or release of materials, due to abnormal pressures. In the U.S. Chemical Safety and Hazard Investigation

bottoms at the MAWP of the system. This may result in a large difference between the

operating pressure and the design pressure, yet is an inherently safer solution.

Stripper rated for full vacuum – Ideally, the stripper system (including trays if

provided) would also be rated for full vacuum. Condensable fluid collapse in the event of a

significant rain storm can pull some vacuum within the tower.

Low temperature discharge – The pressure relief or depressuring of gas in the

contactor can result in low temperature discharges into the effluent handling system.

Conclusions

It is the authors’ purpose that the reader gains a deeper understanding of how the

design and operation intent of gas conditioning systems should be more than meeting product

specifications. Though often viewed as simple processes that aid in a facility producing a

quality product, these gas conditioning units also play an important role in the overall process

safety of the facility. By applying the principles of ISD early in concept design, gas

conditioning systems can operate safer and more reliably for the lifecycle of the facility,

ultimately achieving greater plant availability. In summary, the key takeaways from the

examples discussed in this paper and some elements to consider for ensuring an inherently

safer overpressure protection scheme in gas conditioning plants are the following:

• Consider ISD principles even in the most simple of gas conditioning applications.

• Incorporate ISD features in the overpressure protection scheme in DESIGN and do not

shift the burden to OPERATIONS.

• Consider the full suite of possible overpressure causes.

• Understand the importance of repeated signals that there may be problems (e.g.,

increased filter change frequency, as discussed).

• Follow-through on actions from prior incidents.

• Recognize the facility operating philosophy’s impact (and certainly changes to that

philosophy) on the overpressure protection scheme.

• Recognize that a process upset from even the simplest gas conditioning systems can

result in the overpressure (or overfilling) design case for equipment within the relief and

flare system.

• Understand the basis of the overpressure protection design, and understand how changes

to operating philosophy may impact that basis, and maintain the documented basis for the

facility lifecycle.

• When problems in the design, control, or operations of the facility are identified, take

action to mitigate them.

346

Page 25: 2013: MORE THAN MEETING SPEC: EXAMINATION OF …...such as catastrophic failure or release of materials, due to abnormal pressures. In the U.S. Chemical Safety and Hazard Investigation

• For existing operations it is critically important to recognize the interdependencies that

exist between ISD tenets and balance implementation of these tenets against operational

flexibility, process safety risk, and economic constraints.

Gas conditioning processes are key systems in the delivery of reliable energy

products to the world. Recognizing the design and operating issues that can result in

negative consequences from inadequate process safety assessments and accounting for these

deviations in the overpressure protection design should minimize facility downtime resulting

from of a reduction in frequency of incidents. The reduced downtime should drive higher

facility availability, providing for the delivery of consistent, on-spec product safely and

reliably to the market.

References

1. http://www.aiche.org/ccps/about/business-case-process-safety-pdf

2. http://www.csb.gov/investigations/detail.aspx?SID=73&Type=2&pg=1&F_All=y

3. http://www.csb.gov/investigations/detail.aspx?SID=3&Type=2&pg=1&F_All=y

4. Center for Chemical Process Safety (2009) Inherently Safer Chemical Processes (2nd

Edition) - A Lifecycle Approach. New York, New York: John Wiley & Sons, pp., 11, 19,

27, 28.

5. Kletz, T.A. (1998) Process Plants: A Handbook for Inherently Safer Design.

Philadelphia, PA: Taylor & Francis.

6. GPSA Engineering Data Book, 12th Edition.

7. Natural Gas Engineering Handbook, Ch. 8 Dehydration, 2005.

8. Amine Plant Troubleshooting and Optimization, Hydrocarbon Processing, April 1995,

pp. 41-50.

9. Fundamentals - Gas Sweetening. Fundamentals Proceedings Presented on February 26,

2006 at the Laurance Reid Gas Conditioning Conference, Norman, OK.

10. API Standard 521:2010.

347

Page 26: 2013: MORE THAN MEETING SPEC: EXAMINATION OF …...such as catastrophic failure or release of materials, due to abnormal pressures. In the U.S. Chemical Safety and Hazard Investigation

348