2009 SOUTHEAST ARIZONA TRANSMISSION SYSTEM STUDY REPORT
6th BTA WorkshopCarnegie Library, Phoenix, AZ
By TEP on behalf of SATS ParticipantsJune 3-4, 2010
Entities with Generation, Transmission and Distribution Facilities within SATS• Arizona Public Service (APS)• Central Arizona Water Conservation District / Central Arizona Project
(CAWCD/CAP)• Duncan Valley Electric Cooperative (DVEC)• Graham County Electric Cooperative (GCEC)• Southwest Transmission Cooperative (SWTC)• Sulphur Springs Valley Electric Cooperative (SSVEC)• Trico Electric Cooperative (Trico)• Tucson Electric Power Company (TEP)• UniSource Energy Services (UNSE)• Western Area Power Administration (Western)
Other SATS Participants• Acciona• Arizona Corporation Commission (ACC) Staff• Arizona Power Authority (APA)• Arizona Independent Scheduling Administrator (AzISA)• Black Forest Partners• El Paso Electric (EPE)• Environmental Planning Group (EPG)• Federal Energy Regulatory Commission (FERC) Staff• Freeport-McMoRan (FMI)• Fort Huachuca• Kleinfelder• New Mexico Renewable Energy Transmission Authority (NM RETA)• Public Service Company of New Mexico (PNM)• Salt River Project (SRP)• Southwestern Power Group• SunZia, LLC• Tessera Solar• United States Bureau of Reclamation (USBR)• WestConnect Planning Staff• Western States Energy Solutions (WSES)
33
29
30
08
34
41
31
04
35
53
31
83
36
76
32
77
37
96
33
55
39
19
34
38
40
40
35
16
41
68
35
96
43
03
36
75
44
43
37
54
45
88
38
39
0
500
1000
1500
2000
2500
3000
3500
4000
4500
5000L
oad
(M
W)
2009 2011 2013 2015 2017 2019
2008 Forecast 2009 Forecast
SATS Area Load Forecast
0
500
1000
1500
2000
2500
3000
3500
4000
2009 2011 2013 2015 2017 2019
TEP SWTC UNSE-Santa Cruz APS CAP
Combined SATS Entities Load Forecast
Tasks Completed InSATS 2009 Study Plan
2010 through 2014 and 2019 Planning horizon • Development of power flow cases• Revision of load forecasts– Addressed expected increases in mining load
• Evaluation of the planned system• Identification of planned and potential
projects
Conclusions
• The transmission system in the SATS footprint can reliably meet the needs of Southeastern Arizona with the projects proposed by the SATS participants.
• Overloads will be mitigated with planned projects, operating procedures, or automated actions.
2010 SATS Study Plan1. Present Plan and subsequent findings to SWAT, WestConnect, and local
stakeholders;2. Revise load forecasts;3. Develop base cases for 2010 study;4. Conduct study to determine impacts of deferring previously planned
projects;5. Investigate alternative configurations to mitigate high flows on the
Winchester 345/230 kV transformer, Apache – Bicknell 230 kV line, and Bicknell 345/230 kV transformer caused by EHV system contingencies;
6. Develop and evaluate alternatives to the two joint Tortolita – North Loop 345 kV proposals based on the SPPR three Terminal proposal;
7. Develop and evaluate alternatives for joint SWTC/TEP substation(s) to supply TEP/Trico loads south of Tucson;
8. Identify potential projects in the SATS footprint;9. VAR Margin Study – 230 kV and above buses.