13
©2001 Plan B Systems Inc. PBSi Quantitative Quantitative Cost/Schedule Cost/Schedule Risk Analysis Risk Analysis

©2001 Plan B Systems Inc. PBSi Quantitative Cost/Schedule Risk Analysis

Embed Size (px)

Citation preview

Page 1: ©2001 Plan B Systems Inc. PBSi Quantitative Cost/Schedule Risk Analysis

©2001 Plan B Systems Inc.

PBSi

Quantitative Cost/Schedule Quantitative Cost/Schedule Risk AnalysisRisk Analysis

Page 2: ©2001 Plan B Systems Inc. PBSi Quantitative Cost/Schedule Risk Analysis

©2001 Plan B Systems Inc.

PBSi

Quantitative AnalysisQuantitative Analysis• All risks have potential impacts on

– cost– schedule

• Impacts are rated in the RM process– dollars– months

• All risks are linked to– area (of program– WBS #

Page 3: ©2001 Plan B Systems Inc. PBSi Quantitative Cost/Schedule Risk Analysis

©2001 Plan B Systems Inc.

PBSi

Quantitative AnalysisQuantitative Analysis

• Your plan has– cost– schedule

• allocated to plan elements– cost accounts– tasks

Page 4: ©2001 Plan B Systems Inc. PBSi Quantitative Cost/Schedule Risk Analysis

©2001 Plan B Systems Inc.

PBSi

Quantitative AnalysisQuantitative Analysis

Risks WBS #

Cost Impacts

Budget

Time Impacts

Schedule

Map

Page 5: ©2001 Plan B Systems Inc. PBSi Quantitative Cost/Schedule Risk Analysis

©2001 Plan B Systems Inc.

PBSi

Impact TableImpact Table

WBS # CostBudget$M

ScheduleBudgetmonths

Costimpact$M

Scheduleimpactmonths

Risk #

2 3 03

0.5 4 23

001 10 7

1 2 47

1 1 09020 5 13

0.5 6 13

Page 6: ©2001 Plan B Systems Inc. PBSi Quantitative Cost/Schedule Risk Analysis

©2001 Plan B Systems Inc.

PBSi

Quantitative AnalysisQuantitative Analysis

• NOW, interview risk managers

• Work with the impact table

• Determine three point estimates.– Best case no risks impact– expected case some risks impact– worst case all risks impact

• Use lots of common sense

Page 7: ©2001 Plan B Systems Inc. PBSi Quantitative Cost/Schedule Risk Analysis

©2001 Plan B Systems Inc.

PBSi

Quantitative AnalysisQuantitative Analysis

Impacted Cost Estimates Impacted Schedule Estimates

WBS # Best Expected Worst Best Expected Worst

001 10 12 13.5 6 8 10

020 4 5 5.5 10 13 16

WBS # CostBudget$M

ScheduleBudgetmonths

Costimpact$M

Scheduleimpactmonths

Risk #

2 3 03

0.5 4 23

001 10 7

1 2 47

1 1 09020 5 13

0.5 6 13

Page 8: ©2001 Plan B Systems Inc. PBSi Quantitative Cost/Schedule Risk Analysis

©2001 Plan B Systems Inc.

PBSi

Quantitative AnalysisQuantitative Analysis

• Note that the manager may already have some reserve in his plan.

• This needs to be taken into account in establishing the impacted estimates

Page 9: ©2001 Plan B Systems Inc. PBSi Quantitative Cost/Schedule Risk Analysis

©2001 Plan B Systems Inc.

PBSi

Quantitative AnalysisQuantitative Analysis

• Run Monte Carlo Simulation• Randomly combine the distributions• Run many different times (>100)

Best Expected Worst

Cost or Schedule for WBS #

ProbabilityProbability Distribution for cost /schedule of WBS#

Page 10: ©2001 Plan B Systems Inc. PBSi Quantitative Cost/Schedule Risk Analysis

©2001 Plan B Systems Inc.

PBSi

Qualitative AnalysisQualitative Analysis

• Outputs are– Cost Probability Distributions for project– Schedule Probability Distributions for

milestones

Page 11: ©2001 Plan B Systems Inc. PBSi Quantitative Cost/Schedule Risk Analysis

©2001 Plan B Systems Inc.

PBSi

Option1: Quantitative Cost Option1: Quantitative Cost Risk AnalysisRisk Analysis

Per Cent

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

11.00 11.20 11.40 11.60 11.80 12.00 12.20 12.40 12.60 12.80 13.00

Project Budget ($M)

Cum

ulat

ive

Per

cent

age

Cha

nce

Prudent Management Reserve

Prerequisite: Project Cost Breakdown by WBS

Page 12: ©2001 Plan B Systems Inc. PBSi Quantitative Cost/Schedule Risk Analysis

©2001 Plan B Systems Inc.

PBSi

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

01-Apr-97 10-Jul-97 18-Oct-97 26-Jan-98 06-May-98 14-Aug-98 22-Nov-98 02-Mar-99 10-Jun-99 18-Sep-99 27-Dec-99Time

Cu

mu

lati

ve P

ercen

tag

e C

ha

nce

1 Apr 98Phase 1

5 Oct 99Phase 3

7 Sep 98Phase 2

Option 2: Schedule Risk AnalysisOption 2: Schedule Risk Analysis

CumulativeProbability of

Meeting Schedule%

Set Date

Prerequisite: Project Logic Network/PERT

80%

50%

10%

Phase 2 Phase 3Phase 1

Page 13: ©2001 Plan B Systems Inc. PBSi Quantitative Cost/Schedule Risk Analysis

©2001 Plan B Systems Inc.

PBSi

Qualitative AnalysisQualitative Analysis

Provides assessment of:

• Adequacy of management reserves

• Achievability of critical milestones

Integrates risk management into project planning, not just project management