ENVIRONMENTAL RESOURCES MANAGEMENT KEADBY DEVELOPMENTS LIMITED
2-1
2 THE PROPOSED DEVELOPMENT
2.1 OVERVIEW
The Proposed Development, known as ‘Keadby II’, will be located immediately
to the west of the existing Keadby CCGT power station (‘Keadby I’),
constructed in the 1990s. The red line application boundary of the Proposed
Development is the same as that for the Consented Development.
The Proposed Development site (the Site) is located in the borough of North
Lincolnshire (the unitary planning authority), approximately 500 m northwest
and west of the residential area of Keadby and southeast of the residential
area of Ealand. The closest residential receptors are more than 100 m from
the Site and a larger distance from the main operational structures. The Site
and its surroundings are shown on Figure 2.1.
The Proposed Development will comprise a natural gas fired CCGT
generating station with an output capacity of up to 910 MW. The station will
include an industrial gas turbine unit, a heat recovery steam generator, a
steam turbine unit and ancillary plant and equipment located in the main
power island in the eastern part of the Site. The western part of the Site will
include hybrid cooling towers. In accordance with the requirements of The
Carbon Capture Readiness (Electricity Generating Stations) Regulations 2013
for new generating infrastructure (of greater than 300 MW gross capacity and
of a type covered by the EU Large Combustion Plant Directive), an area of
land has been designated for possible future carbon capture equipment has
been designated on the western part of the Site. The site layout is presented
in Figure 2.2.
The Site also includes land provision for connections to gas transmission
infrastructure, connections to the National Grid and routes for pipelines to
water abstraction and discharge points. The connection to the national grid
has been consented separately under Section 37 of the Electricity Act (1989)
and granted pursuant to The Department for Business, Energy & lndustrial
Strategy reference numbers: 12.04.09.05-579U (Keadby 2 Overhead line) and
2.04.09.05-560U (Keadby 1 Replacement line).
Further details of the Proposed Development are set out in Section 2.3.
Comparison of Consented Development with Proposed Development:
Overview
The Proposed Development will have an output capacity of up to 910 MW
whereas the Consented Development has an output capacity of up to
820 MW. There will still be only one natural gas fired CCGT generating
station, although it will be larger and some component parts will be larger
which will result in an increase in the number of special loads transported
to the Site.
ENVIRONMENTAL RESOURCES MANAGEMENT KEADBY DEVELOPMENTS LIMITED
2-2
2.2 PROPOSED DEVELOPMENT APPLICATION BOUNDARY
The 2016 Consent was based on the application boundary for the Consented
Development, presented in Annex L of the ES (see Annex D).
The Consented Development is based on a number of fundamental aspects,
primarily development of a gas turbine generating station adjacent to
Keadby I, land designated for possible future carbon capture equipment and
associated infrastructure such as pipelines for cooling water intake and
discharge. The Proposed Development boundary is presented in Figure 2.1.
2.3 DESCRIPTION OF THE PROPOSED DEVELOPMENT
2.3.1 Flexibility in Design
Flexibility to respond to emerging economic circumstances and technological
advances and to accommodate variations between commercially available
turbines from different suppliers is essential if the Proposed Development is to
proceed and be successful. In line with the application relating to the
Consented Development, a degree of flexibility has therefore been built into
the Proposed Development that has been subject to the EIA.
Whilst this introduces some complexity to the EIA process; it is common to
many large scale developments that are dependent on market conditions for
their delivery.
The EIA Regulations require an EIA Report to provide a description of the
location, design and size of the scheme to enable the likely significant
environmental effects to be assessed and to enable the decision maker,
statutory consultees and the public to make a properly informed response. In
view of this, a balance has to be sought between defining the Proposed
Development in enough detail to predict its effects, whilst leaving enough
flexibility to enable the Proposed Development to be successfully delivered
under conditions that may be subject to change.
The project definition parameters presented in this EIA Report together with
the ES provide an ‘envelope’ for assessing the effects of the Proposed
Development. In order to ensure that likely significant effects of the Proposed
Development on the environment are described and assessed, parameters
have been set which are broad enough to encompass the potential variations
in turbine design and other aspects of the Proposed Development. The EIA
takes account of all the reasonable variations (or degrees of freedom) in the
form of the Proposed Development that would be permissible under the
parameters, and describes and assesses the likely significant effects on the
environment as appropriate.
Comparison of Consented Development with Proposed Development:
Application Boundary
There are no proposed changes to the application boundary.
National Grid Electricity Transmission System
Rive
r Tren
t
KeadbyVillage
Vazon Bridge Cottage
Existing Keadby IPower Station
Railway
Ealand
Hawthorn Cottage
Keadby and Stainforth Canal
A18
M180
DRAWN: OBCHECKED: LGAPPROVED: KM
PROJECT: 0280278
Figure 2.1Proposed Development Boundaryand Site Surroundings ±0 200 400 600 800 1,000
Metres
SCALE: See Scale Bar
Path: \\UKEDIDC01\Data\Edinburgh\Projects\0280278_KeadbyGIS_GB_KM\MAPS\EIA 2017\0280278_PropDevBoundary _A02.mxdSOURCE: Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS,USDA, USGS, AeroGRID, IGN, and the GIS User Community
PROJ
ECTIO
N: Br
itish N
ation
al Gr
id
Proposed DevelopmentBoundary
DATE: 06/07/2017
VERSION: A01SIZE: A4
Heat Recovery Steam Generator
Gas Turbine Building
Steam Turbine Building
Cooling Water Pipework (underground)
Cooling Tower
Stack
Land set aside for future carbon capture technology
installation
DRAWN: OBCHECKED: RMAPPROVED: KM
PROJECT: 0280278
Figure 2.2Site Layout
±
Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS User Community
SCALE: See Scale Bar
Path: P:\Projects\0280278_KeadbyGIS_GB_KM\MAPS\EIA 2017\0280278_SiteLayout_A02.mxd
PROJ
ECTIO
N: Br
itish N
ation
al Gr
id
VERSION: A02SIZE: A3
DATE: 24/07/2017
0 20 40 60 80 100Metres
Proposed Development BoundarySite Layout
ENVIRONMENTAL RESOURCES MANAGEMENT KEADBY DEVELOPMENTS LIMITED
2-5
Such an approach is considered good practice, as reflected in case law on the
‘Rochdale Envelope’ principle. Suitably applied in EIA it can help to avoid the
need for protracted re-submission procedures at a later stage, whilst ensuring
that there is a comprehensive assessment of the likely significant effects.
Detailed explanations are provided in Chapters 4 and 5 of this EIA Report and
Chapters 6 to 13 of the ES on how a worst case assessment approach has
been applied to the extent it is relevant to the particular EIA topic being
addressed. Specific areas of flexibility in design are also noted in the following
subsections.
2.3.2 Key Components of the Proposed Development
The Proposed Development will include the following major components:
a gas turbine generator;
waste heat recovery boiler;
a condensing steam turbine;
hybrid cooling towers;
control room and instrumentation system;
water treatment plant;
cooling water abstraction and discharge pipe work; and
ancillary plant and equipment including (but not limited) to unloading
facilities, pumps, blowers, interconnecting pipelines and mixing apparatus,
together with options for addressing emission abatement measures
determined by the Environmental Permitting process, which could include
such matters as selective catalytic reduction and additional wastewater
treatment.
The Site includes two principle areas, as shown in Figure 2.2:
the main power island area to the east; and
hybrid cooling towers and area reserved for carbon capture readiness on
the western part of the Site.
The power island area will accommodate the power generating equipment
including the gas and steam turbines, boilers, auxiliary structures and
administration buildings.
2.3.3 Turbine Configuration and Technology
The gas and steam turbines are anticipated to be constructed in a multi-shaft
configuration, as shown in Figure 2.2.
The ES primarily used the single-shaft option as the basis of assessment, as
this has the larger building footprint for the main turbine buildings. Where the
Comparison of Consented Development with Proposed Development:
Key Components
The Proposed Development includes the same key components as the
Consented Development.
ENVIRONMENTAL RESOURCES MANAGEMENT KEADBY DEVELOPMENTS LIMITED
2-6
multi-shaft option could give rise to likely significant environmental effects that
could potentially be materially different from those assessed for the single-
shaft option then these effects were also independently addressed in the ES.
While there were differences in effects between single and multi-shaft
configurations these did not lead to likely significant effects that were
materially different, i.e. a change from an effect of minor significance for one
layout to an effect of moderate significant for the other in regard to the same
type of impact.
It is anticipated that the Proposed Development will proceed as a multi-shaft
configuration; however based on the findings of the ES, which considered both
a single shaft and a multi-shaft configuration, the conclusions of the
assessment of the likely significant environmental effects of the Proposed
Development multi-shaft configuration presented in this EIA Report would
apply to a single-shaft configuration.
The dimensions of the main components are listed in Table 2.1 and Table 2.2.
Table 2.1 Dimensions of Main Structures of the Proposed Development in
Comparison with the Consented Development (1)
Item Width, m Length, m Height, m
Consented Proposed Consented Proposed Consented Proposed
Steam
turbine
building
(large)
45 50 47 39 44 30
Steam
turbine
building
(small)
- 50 - 14 - 12
Heat
recovery
steam
generator
building
27 30 46 50 44 52
Gas Turbine
building
20 23 47 50 30 27
Stack 8 m diameter 75 to 85 75 to 85
(1) The corresponding Table 2.1 of the ES contained some minor errors corrected here. The nature of the
error was by omission and labelling and not in the dimensions used in the ES.
Table 2.2 Dimensions of Other Structures of the Proposed Development in
Comparison with the Consented Development
Item Width, m Length, m Height, m
Consented Proposed Consented Proposed Consented Proposed
Cooling
towers (for a
single bank of
12) (1)
17 25 177 192 28 28
(1) The landscape and visual impact assessment conducted in relation to the Consented
Development initially considered cooling tower heights of 25 m; however, the noise
assessment indicated the possible need to raise the height of the cooling towers to 28 m.
Photomontages of the Proposed Development are based on a 28 m height.
ENVIRONMENTAL RESOURCES MANAGEMENT KEADBY DEVELOPMENTS LIMITED
2-7
The stack height will be between 75 and 85 m. In order to carry out a
conservative assessment of effects from the Proposed Development, different
stack heights within this range are considered within certain assessment
topics, using the option that represents the worst case for the respective
discipline, such that the air quality assessment considers a height of 75 m and
the photomontages provided in Chapter 3 are based on a height of 85 m.
In recognising the evolution of turbine technology, there is potential for further
advances to be made prior to or during detailed design of the Proposed
Development. On this basis, the proposed variation seeks to retain flexibility
in the design to allow the project to adapt to future market conditions and
Company and policy requirements.
The Company has not determined which specific turbine technology will be
procured and therefore the EIA is based on elements drawn from a range of
turbine designs provided by technology suppliers.
From an operational and environmental perspective, disregarding layout and
building mass, the main areas of variation between turbine technologies will
be in emissions to air, noise and water demand. In developing the indicative
plant layouts a design envelope has been developed, drawing on details from
a range of turbine suppliers to ensure that the EIA is based on an
environmental worst-case scenario.
The gas turbine hall, heat recovery steam generator building and steam
turbine hall will be constructed of clad steel. The finish will be similar to that of
Keadby I, in keeping with the architectural vernacular of the site. An
illustrative view of the Proposed Development, showing the building finish and
appearance, is provided in Figure 2.3, with the Proposed Development on the
left and existing Keadby I central.
Figure 2.3 Illustrative View of Buildings
Note: This viewpoint (1b) is 0.25 km to the north of the Proposed Development site looking
south towards the Proposed Development.
ENVIRONMENTAL RESOURCES MANAGEMENT KEADBY DEVELOPMENTS LIMITED
2-8
2.3.4 Power Generation Process
The following activities will be carried out within the Proposed Development
process to generate electrical power:
combustion of natural gas in a gas turbine to directly generate electricity
which is exported to the National Grid;
use of waste heat from the gas turbine to raise steam in the boiler to
generate additional electricity in a steam turbine for export to the National
Grid;
condensing of residual steam;
release of combustion gases through a single stack; and
management and disposal of residues produced by the generation
process.
These processes will occur within different buildings and structures within the
power island area.
The processes for generating power without and with supplementary firing are
illustrated in Figure 2.4.
Comparison of Consented Development with Proposed Development:
Turbine Configuration Technology
The ES considered a multi-shaft and single-shaft option for the gas and
steam turbines. Throughout the ES the worst case was assessed, which
was primarily the single-shaft option as this has the larger building footprint
for the main turbine buildings. Where the multi-shaft option could have
given rise to likely significant environmental effects that were materially
different from those assessed for the single-shaft option then these effects
were also addressed. The Proposed Development is anticipated to be a
multi-shaft configuration. There are some changes in the multi-shaft
building sizes and these have been considered in Chapters 3 to 5 where
appropriate.
The Consented Development gas turbine hall and steam turbine hall were
to be constructed of clad steel with brickwork to the lower level. However,
the Proposed Development gas turbine hall and steam turbine hall are to
be constructed of clad steel down to ground level.
ENVIRONMENTAL RESOURCES MANAGEMENT KEADBY DEVELOPMENTS LIMITED
2-9
Figure 2.4 Gas Turbine Power Generation
2.3.5 Emissions Control Technology and Best Available Technique
The Industrial Emissions Directive (IED) is the successor of seven existing
Directives, including the Integrated Pollution Prevention and Control (IPPC)
Directive and in essence is concerned with minimising pollution from industrial
sources throughout the European Union through the implementation of
established Best Available Techniques (BAT) for pollution control. The IED
entered into force on 6 January 2011 and was transposed into national
legislation by Member States by 7 January 2013. In the UK, IED is
implemented through the existing Environmental Permitting Regulations, but
requires a somewhat different approach to previous regimes, insomuch as the
achievement of BAT is the explicit priority.
The permit conditions including emission limit values (ELVs) must be based
on the Achievable Emission Levels published in BAT Reference (BREF)
notes. BAT conclusions (documents containing information on the emission
levels associated with the best available techniques, which act as a summary
of BREF notes) are the reference for setting permit conditions. To determine
BAT, the European Commission organises an exchange of information
between experts from the EU Member States, industry and environmental
organisations. This results in the adoption and publication by the Commission
of the BAT conclusions and BAT Reference Documents.
The IED contains certain elements of flexibility by allowing the licensing
authorities (i.e. the Environment Agency) to set less strict emission limit values
High, Intermediate and
Low Pressure Steam
Turbines
Water
Steam
Heat R
ecovery
Ste
am
Genera
tor
Comparison of Consented Development with Proposed Development:
Power Generation Process
The Proposed Development will not use ‘supplementary firing’ (see Section
2.5.1 of the ES, Annex D) as part of the power generation process.
The Proposed Development is expected to have a higher efficiency than
the Consented Development; this is discussed further in Chapter 4.
ENVIRONMENTAL RESOURCES MANAGEMENT KEADBY DEVELOPMENTS LIMITED
2-10
in specific cases. Such measures are only applicable where an assessment
shows that the achievement of emission levels associated with BAT as
described in the BAT conclusions would lead to disproportionately higher
costs compared to the environmental benefits due to:
a) geographical location or the local environmental conditions; or
b) the technical characteristics of the installation.
The competent authority must always document the reasons for the
application of the flexibility measures in the permit including the result of the
cost-benefit assessment.
Article 15(4) of the IED contains a process for derogation from the requirement
for regulators to set permit emission limit values such that, under normal
operating conditions, emissions do not exceed BAT AELs associated with BAT
conclusions. At the Permitting stage, consideration will need to be given to
whether the Proposed Development will need to comply with the BAT AELs or
whether the LCP falls outside the scope of the LCPBREF due to its higher
efficiency.
The plant design considered in this EIA Report will be developed with
cognisance of the Best Available Techniques (BAT) Reference Document for
Large Combustion Plants Final Draft (June 2016), as cited by Industrial
Emissions Directive 2010/75EU, and the associated UK Regulator
Interpretation Document (currently being drafted). The basis of assessment
for the Proposed Development is 50 mg Nm-3 (i.e. the prevailing limit and the
value used as the basis of assessment for the Consented Development).
Both the Consented Development and the Proposed Development would fall
under the provisions described above.
Options for meeting a future limit will be addressed in the context of BAT as
part of applying to the EA for an Environmental Permit to operate the
Proposed Development.
2.3.6 Cooling Water System
A system will be installed to provide water cooling for the exhaust steam from
the steam turbine, and as a coolant for the gas turbine oils, boiler pumps and
other parts of the generating plant. Since submission of the application for the
Consented Development, further work has been undertaken on the detailed
design. It is now most likely that an indirect cooling system will be used,
although in the event that Keadby I should permanently cease operation
before the Proposed Development takes place it is possible that Keadby I
cooling water infrastructure could be used in terms of the intake and outfall on
the River Trent, the pump house and the pipework to and from the station (see
Comparison of Consented Development with Proposed Development:
Emissions Control Technology
Both the Consented Development and the Proposed Development will
include the addition of suitable emissions control techniques in the context
of future emission limits and the need to demonstrate BAT.
ENVIRONMENTAL RESOURCES MANAGEMENT KEADBY DEVELOPMENTS LIMITED
2-11
Figure 2.1). This section provides an overview of the indirect cooling system.
For further details on the direct cooling system see Section 2.3.5 of the ES
(Annex D).
The cooling water system will mainly consist of a bank of hybrid cooling
towers. The Proposed Development, as presented in Figure 2.2, shows a
single bank of 12 cooling towers. Depending on the final layout of the
Proposed Development, there may be a single bank or two back-to-back
banks of cooling towers located in the western part of the Site. If back-to-back
banks are selected, this would increase the number of cooling towers required
to 16.
The Company has not determined which specific cooling tower configuration
will be utilised in the Proposed Development and therefore the EIA has been
undertaken adopting a worst case approach. The EIA has been carried out on
the basis of a single bank of 12 cooling towers as this option has the largest
number of exposed ‘faces’ from which noise is emitted, and has the longest
footprint span for the purposes of visual impact assessment.
When operating, approximately 19.6 Ml per day of water will be supplied from
the Stainforth and Keadby Canal by a new pumping station and pipework
connecting the canal to the Proposed Development. The Company has
liaised with the Canal and River Trust (CRT), which has operational
responsibility for the Stainforth and Keadby Canal, to discuss water provision
for the Consented Development. Correspondence with the Environment
Agency and CRT with regard to a sustainable supply of water to the Proposed
Development is included in Annex D to the ES. As agreed with the CRT
abstraction will not exceed 19.6 Ml per day but may vary in rate over the day
with periods of higher abstraction compensated by periods of lower extraction
over the 24 hour cycle.
Filtering and treatment of the abstracted water prior to use will be undertaken
on Site as required.
The water that evaporates during the cooling cycle will not contain the
dissolved solids that were originally in the water, so their concentration in the
remaining water will increase. If this process was allowed to continue,
eventually the solids would be too high a concentration to stay in solution and
would cause scaling or fouling. To avoid this, chemicals may be added and
some of the recirculating cooling water is purged from the system and
ultimately discharged.
As water concentrates in the cooling tower the ratio between the
concentrations of a chemical in the water in the tower, to the chemical in the
make-up water indicate the number of times the water has been concentrated.
For a concentration factor (CF) of 1 there is no concentration of the water (i.e.
a ‘once-through’ system. This is costly and inefficient in terms of chemical
dosing. The volume of purge water drops exponentially with increasing CF.
At CF2, the purge equals the evaporation rate and make-up water equals
twice the evaporation. At CF3 the make-up water equals one and half times
the evaporation. At CF 5, the make-up water equals one and a quarter times
the evaporation. Essentially the higher the CF, the less water is required and
the less chemicals are used all else being equal. The Proposed Development
ENVIRONMENTAL RESOURCES MANAGEMENT KEADBY DEVELOPMENTS LIMITED
2-12
will likely operate with CFs between 3 and 5. As a result water demand and
discharge rates will be variable. Following treatment, cooling water will be
discharged to the River Trent, through a new pipeline to be installed in the
existing pipeline from Keadby I or the same pipeline by mixing the blowdown
of Keadby II with the outfall water of Keadby I. If a new pipeline is built, the
new Keadby II pipeline may either be installed in its own trench or inserted into
the existing Keadby I pipeline.
There is also a possible design scenario whereby the Proposed Development
could be part cooled using hybrid cooling towers and part cooled using the
existing Keadby I cooling system. In as much as this intermediate scenario
would not result in any increase in water abstraction and discharge rates or
thermal load above and beyond that existing for Keadby I, its environmental
effects are addressed by considering the Proposed Development operating
with hybrid cooling towers while Keadby I operates in normal mode in
accordance with its Environmental Permit. As such it is not necessary to
address this possible scenario in its own right since its potential environmental
effects will be within the envelope of effects assessed for the Proposed
Development.
2.3.7 Connection to Gas Transmission System
Keadby II will be fuelled by a supply of natural gas. The supply will be taken
from the existing National Gas Transmission System which has a connection
point at Keadby I via a purpose built gas compound. A new pipeline within the
boundary of the Site will connect the Proposed Development to the existing
gas compound. National Grid Gas has confirmed that there is sufficient
supply in this transmission network to meet the fuel demands of Keadby II and
Keadby I together.
2.3.8 Connection to National Grid Electricity Transmission System
The electricity generated by the Proposed Development will be exported to the
National Grid Electricity Transmission System. The grid connection will be
made immediately to the north of Keadby I and the Site to the existing
National Grid 400 kV Electricity Transmission System. The Proposed
Development will connect to the system via a new overhead line connection to
an existing transmission tower (pylon), which currently facilitates a connection
from Keadby I. As such, a new tower is needed to realign and reconnect
Keadby I to the system.
Comparison of Consented Development with Proposed Development:
Cooling Water System
There are no material proposed changes to the cooling water system, since
indirect cooling was the basis of assessment in the ES.
Comparison of Consented Development with Proposed Development:
Connection to Gas Transmission System
There are no proposed changes to the connection to the gas transmission
system.
ENVIRONMENTAL RESOURCES MANAGEMENT KEADBY DEVELOPMENTS LIMITED
2-13
Consent has been granted for both the new connection and realignment of the
Keadby I connection under separate consents to this section 36 variation
application. As it is necessary for the grid connection for the Proposed
Development to be in place prior to commencement of operation, it is likely
that the programme for constructing the new tower and realignment will
overlap with the Proposed Development construction programme. Therefore,
these works have been considered, as described in Chapter 5 of the ES, as
schemes with potential for indirect and cumulative effects.
2.3.9 Landscaping
The completed Proposed Development will include perimeter planting and
nature conservation enhancement provisions. A Landscape Masterplan will
be prepared in consultation with North Lincolnshire Council and Lincolnshire
Wildlife Trust which will contain the details for these provisions.
2.3.10 Project Programme
The current overall programme is in part driven by a grid connection date
since commissioning tests cannot be undertaken in advance of a connection.
Unless the grid connection date is modified the earliest grid connection date is
2020. Construction and commissioning are anticipated to last 43 months, of
which the latter 12 months would be for testing and commissioning of the
Proposed Development. On the basis of this current programme and the
earliest date of commissioning, construction activities could begin in 2018 and
the Proposed Development could begin commercial operations in 2021.
Year 1 2 3 4
Months
1-3
4-6
7-9
10-1
2
13-1
5
16-1
8
19-2
1
22-2
4
25-2
7
28-3
0
31-3
3
33-3
6
37-3
9
40-4
3
Design and
procurement
Site
preparation
Construction
phase
Commissioning
The Proposed Development is designed to have an operational life of at least
25 years. The main pre-construction, construction and commissioning
activities proposed to be undertaken through this application and the
Comparison of Consented Development with Proposed Development:
Connection to National Grid Electricity Transmission System
There are no proposed changes to the connection to National Grid
Electricity Transmission System.
Comparison of Consented Development with Proposed Development:
Landscaping
There are no proposed changes to the site landscaping.
ENVIRONMENTAL RESOURCES MANAGEMENT KEADBY DEVELOPMENTS LIMITED
2-14
approximate duration of the works are indicatively outlined below. The actual
programme for the Proposed Development will however be subject to
contractor requirements.
2.4 CONSTRUCTION PHASE ACTIVITIES
2.4.1 Overview
The construction programme is expected to last approximately 43 months.
The construction works associated with the Proposed Development, including
construction laydown compounds, will occur within the footprint of the Site.
Construction staff will peak at 500 during the construction programme, with a
peak of 10 two-way HGV movements per hour. A number of abnormal
indivisible load (AIL) deliveries to the Site will be required. The AILs vary in
size and a maximum of 10 AIL deliveries may still need to be routed through
the village of Ealand over the construction phase as assessed in the ES. The
remainder can be accommodated using the access from the A18 and the
bridge that was constructed to facilitate development of the Keadby Windfarm.
2.4.2 Site Preparation
Site preparation works within the Proposed Development area will largely
comprise site levelling of material within the site area to create suitable
development platforms for the main power island and the cooling towers.
As part of the site preparation, further geotechnical investigations and
chemical analysis will be undertaken to confirm the ground conditions,
undertaken by a suitably qualified specialist. Any contaminated materials
identified will be treated and replaced or removed from Site for appropriate
disposal. The selected management option will be based on an assessment
of the potential for migration of contaminants to sensitive receptors.
It is anticipated that remnant foundations and piles from the former coal fired
power station may be encountered in places. In some instances
Comparison of Consented Development with Proposed Development:
Project Programme
The estimated start date for construction of the Proposed Development
remains the same although the overall construction time has increased
from 36 to 43 months.
Comparison of Consented Development with Proposed Development:
Construction Phase Activities Overview
Although a higher number of AIL deliveries will be required for the
Proposed Development when compared to the Consented Development,
the maximum of 10 AIL deliveries that may need to be routed through the
village of Ealand over the construction phase will remain the same. All
additional AIL deliveries will take an alternative route.
ENVIRONMENTAL RESOURCES MANAGEMENT KEADBY DEVELOPMENTS LIMITED
2-15
demolition/removal may be required together with offsite disposal at a suitable
licensed facility.
As part of the site preparation works, trial trenching may be carried out in
areas where there will be intrusive works, such as piling, to establish presence
of archaeological interest or buried heritage. The works will be carried out
under Written Schemes of Investigation, to be submitted to and approved by
the local planning authority in advance of works commencing.
It is not anticipated that significant volumes of fill material will be imported to
the Site to create the development platforms. The development platform for
the Proposed Development will be at a height of 2.2 m above ordnance data
(AOD) plus 400 mm freeboard (or buffer) above this level, as agreed with the
Environment Agency. This will raise the Site above flood levels predicted for a
1 in 200 year tidal flood event, or a 1 in 100 year fluvial flood event, taking into
account 50 years of anticipated sea level rise. This will provide a built-in
safety factor for the Proposed Development from flood risk of over 130%.
2.4.3 Construction Laydown Areas
Temporary construction laydown areas will be required during the construction
phase. These will be located within the Proposed Development boundary,
with the main construction compound area located in the west of the Site,
occupying in the order of 5 ha of land.
This area will be used for storage, fabrication and temporary site facilities,
including the main contractor’s temporary site office and construction
workforce car parking. This area will be on hardstanding which will be either
reinstated or retained after construction as necessary or required. The area
will be cleared to allow access and safe working conditions.
2.4.4 Main Construction Works
The first stage of construction will require foundations, piling and concrete
base formation, as well as various other civil ground works. Piling for
foundations will be undertaken during day time only.
The main construction works will follow a logical sequence (albeit with some
activities overlapping), beginning with initial stages for the excavation for
structural foundations, services and drainage. The final stages will be for the
installation of the main power island equipment followed by commissioning
activities and the handover period.
Comparison of Consented Development with Proposed Development:
Site Preparation
There are no proposed changes to site preparation.
Comparison of Consented Development with Proposed Development:
Construction Laydown Areas
There are no proposed changes to the construction laydown areas.
ENVIRONMENTAL RESOURCES MANAGEMENT KEADBY DEVELOPMENTS LIMITED
2-16
The Proposed Development power plant buildings and structures will be
installed on reinforced concrete foundations. Driven pile foundations are likely
to be required for larger heavier equipment such as the gas turbine, steam
turbine and generator. Foundation types will be finalised as part of the
detailed design phase.
Once foundations are completed, super-structure construction will commence
with the provision of steel and/or concrete frames, cladding and other general
building works. Many of the plant items, such as boilers and turbines, will be
constructed offsite, requiring only final connection following delivery.
All materials will be delivered to Site by road and prefabricated plant items will
be delivered by abnormal load vehicles. All construction waste materials will
be regularly removed from the Site to an approved waste management site.
All hazardous wastes and waste containers will be appropriately stored on Site
prior to removal by a licensed contractor.
There will be a significant period of electrical and instrument connection,
testing, commissioning and re-testing prior to operation.
A landscaping strategy, to be agreed with the local planning authority and
relevant stakeholders, will be implemented.
2.4.5 Construction Plant
Consideration has been given to the types of mobile plant that are likely to be
used on Site during the site preparation and construction phase of the
Proposed Development. The typical suite of plant used is set out below:
excavators;
dump trucks;
cranes;
cherry pickers;
hoists;
fork lift trucks;
concrete delivery trucks;
concrete pumps;
piling rigs;
generators;
pumps; and
compressors.
Comparison of Consented Development with Proposed Development:
Main Construction Works
There are no proposed changes to the main construction works.
ENVIRONMENTAL RESOURCES MANAGEMENT KEADBY DEVELOPMENTS LIMITED
2-17
2.4.6 Site Access and Road Layout
Figure 2.5 illustrates the proposed access routes during construction and
operation.
Construction traffic is required to use the new access road that by-passes
Ealand and goes via Hatfield drain and North Pilfrey bridges, except in the
case of an emergency or for some abnormal indivisible loads (AIL), for which
the Company will require a special order from the Secretary of State for
Transport. The most appropriate route for AILs will be agreed on a case-by-
case basis, as required, in consultation with the local highways authority(ies).
It may be necessary to undertake works to strengthen the Hatfield drain bridge
to enable heavy loads to deliver to the Site (see also Section 2.4.1). In this
event, the Company will commit to undertaking these works, subject to
necessary permissions from the local planning authority.
Access roads will be constructed of stone / asphalt and all services, such as
water, electricity and telecommunications, will be routed within pipeline
corridors or under the access roads and or verges.
2.4.7 Site Drainage
Sustainable drainage systems will be incorporated within the design to
manage surface water on Site, mimicking pre-project surface run-off
characteristics. A drainage strategy will be produced to manage flood
volumes and water quality and will be included as part of the detailed design
process. The Proposed Development will adopt the principles of sustainable
drainage strategies (SuDS) as part of detailed design.
Comparison of Consented Development with Proposed Development:
Construction Plant
There are no proposed changes to the construction plant used.
Comparison of Consented Development with Proposed Development:
Site Access and Road Layout
There are no proposed changes to site access or road layout. As noted
above a higher number of AIL deliveries will be required, however, the
maximum of 10 AIL deliveries routed through the village of Ealand over the
construction phase will remain the same. All additional AIL deliveries will
take an alternative route.
Comparison of Consented Development with Proposed Development:
Site Drainage
There are no proposed changes to the site drainage.
A18B1450
B1216
M181
M180
Construction Access Road
B1392
DRAWN: OBCHECKED: RMAPPROVED: KM
PROJECT: 0280278
Figure 2.5Site Access ±0 200 400 600 800 1,000
Metres
SCALE: See Scale Bar
Path: \\UKEDIDC01\Data\Edinburgh\Projects\0280278_KeadbyGIS_GB_KM\MAPS\EIA 2017\0280278_SiteAccess_A02.mxdSOURCE: Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS,AeroGRID, IGN, and the GIS User Community
PROJ
ECTIO
N: Br
itish N
ation
al Gr
id
Proposed DevelopmentBoundaryConstruction Access Road(dedicated access road fromA18)MotorwayA RoadB RoadMinor Road / Local Street
DATE: 06/07/2017
VERSION: A01SIZE: A4
ENVIRONMENTAL RESOURCES MANAGEMENT KEADBY DEVELOPMENTS LIMITED
2-19
2.4.8 Lighting
Task lighting during the construction phase will be required during the winter
months. The majority of construction activities will be undertaken during the
day time only, but safety requirements will lead to the need for some lighting
during late afternoon / early evening. Depending on the nature of the
construction task, it will not always be required to use high level task lighting.
Where it is not necessary to use high level lighting for safety purposes, low
level task lighting will be used.
2.4.9 Commissioning
The Proposed Development will be commissioned over a period of
approximately 12 months. The commissioning phase will prove the technical
acceptance of the Proposed Development.
Reliability tests will demonstrate the fitness for purpose of the Proposed
Development prior to commercial operation, and test compliance with plant
performance guarantees, including emission limits.
2.4.10 Construction Workforce
A construction workforce of approximately 300 personnel, with a peak of 500,
is expected. Details of the workforce will be confirmed as part of the
Contractor’s Requirements. The peak workforce will be employed on Site
during the busiest construction period which is expected to be between month
6 and month 30 of the construction programme. This will coincide with the
civils and installation of the turbine halls and mechanical and electrical plant.
The Company will encourage local contractors to tender for appropriate
elements of the works. SSE promotes local employment and procurement
where possible. In the context of the Proposed Development, this is
considered to be within an approximate 45 minute drive time from the Site.
Prior to commencement of construction, a ‘Meet the Buyer’ day will be held
locally, providing an opportunity for links to be made between the principal
contractor and the local supply chain. Specialist construction staff will be
required for installation of the generating plant, including turbines and boiler.
Comparison of Consented Development with Proposed Development:
Lighting
There are no proposed changes to the construction lighting.
Comparison of Consented Development with Proposed Development:
Commissioning
The commissioning phased has increased in time from approximately 26
weeks to 12 months.
ENVIRONMENTAL RESOURCES MANAGEMENT KEADBY DEVELOPMENTS LIMITED
2-20
2.4.11 Construction Hours
Construction hours will be agreed with the local planning authority. It is
proposed that working hours will be in line with those for the Consented
Development, as follows:
Monday to Friday: 24 hours per day; and
Saturday: 08:00 to 14:00.
Typical Monday to Friday working hours will be two-shift with the majority of
construction activities carried out between 07:00 to 19:00. 24 hour working is
likely to be limited to periods when the construction activity is at its most
intensive (typically fit out and internal installation activities) and the
commissioning phase.
Pile driving for foundations and other potentially noisy activities identified in
the ES will be limited to the following times:
Monday to Friday: 08:00 to 18:00; and
Saturday: 08:00 to 14:00.
2.4.12 Environmental Management
In advance of construction, a Construction Environmental Management Plan
(CEMP) (or similar) will be finalised, in consultation with the local planning
authority, the Environment Agency and other relevant stakeholders. The main
purposes of the CEMP will be:
to provide a mechanism for ensuring that measures to mitigate potentially
adverse environmental and socio-economic impacts are implemented;
to ensure that standards of good construction practice are adopted
throughout the construction of the Proposed Development;
to provide a framework for mitigating impacts that may be unforeseen or
unidentified until construction is underway;
to provide assurance to third parties that their requirements and the
commitments made in the ES with respect to environmental performance
will be met; and
Comparison of Consented Development with Proposed Development:
Construction Workforce
There are no proposed changes to the nature or numbers of the
construction workforce.
Comparison of Consented Development with Proposed Development:
Construction Hours
There are no proposed changes to the construction hours for normal or
noisy activities.
ENVIRONMENTAL RESOURCES MANAGEMENT KEADBY DEVELOPMENTS LIMITED
2-21
to provide a framework for compliance auditing and inspection to enable
the Company to be assured that its aims with respect to environmental
performance are being met.
The CEMP will be developed as the Proposed Development proceeds through
the detailed design and pre-construction phases, in conjunction with the
appointed construction contractors, and in consultation with relevant bodies
such as the local planning authority, Environment Agency, Historic England
and Natural England. The CEMP will reflect any conditions and obligations
contained in the varied consent.
The CEMP will address a range of matters including:
site access, boundary fencing, security and public safety;
control of surface run-off and drainage;
construction waste management;
construction traffic routing and access;
control of dust;
control of noise;
storage and handling of fuels, lubricant oil and other hazardous materials;
protection of sensitive habitats and species;
archaeological watching brief;
lighting protocol; and
public communication and complaints handling procedures.
A framework CEMP is provided in Annex K of the ES.
2.5 OPERATION
2.5.1 Overview
The operational phase of the Proposed Development is defined as the period
during which electricity is generated.
During operation, and so as to meet the expected electricity demand profile, it
is expected that the Proposed Development will operate in one of two
operating modes:
two-shift mode; or
base load.
Operating at two-shift mode, the Proposed Development will run at its full
design capacity to meet the hours of peak demand, typically morning
(between 07:00 and 10:00) and evening (between 16:00 and 20:00) times.
Comparison of Consented Development with Proposed Development:
Environmental Management
There are no proposed changes to the nature or content of the construction
environmental management system.
ENVIRONMENTAL RESOURCES MANAGEMENT KEADBY DEVELOPMENTS LIMITED
2-22
Operating at base load, the Proposed Development would generate
continuously to meet system demand.
The Proposed Development will be operated in accordance with an
Environmental Permit issued by the Environment Agency under the
Environmental Permitting (England and Wales) Regulations 2010.
2.5.2 Operational Staff
The Proposed Development will employ approximately 18 personnel (1). This
will include a range of roles, including:
electrical engineers;
mechanical and electrical operatives;
control and instrumentation engineers;
security personnel, and
administrative staff.
Plant operative staff will work on a two 12-hour shift pattern, with the first shift
between 07:00 - 19:00 and the second between 19:00 - 07:00.
Administrative staff will typically work an office-hour pattern of 08:30 – 18:00.
2.5.3 Safety, Health and Environmental Management
The Company’s approach to safety health and environmental (SHE)
management is accredited to ISO14001 and OHSAS18001. The Company’s
SHE policy including the Major Accident Prevention Policy addresses such
matters needed to properly address SHE management, including:
management organisation;
workforce (and contractor) competence, training and support;
systematic identification of hazards and risk assessment;
plant integrity and maintenance;
safe systems of work;
controls for the safe operation of processes;
emergency planning; and
SHE performance indicators and continuous improvement.
(1) This number of staff assumes that Keadby II and Keadby I will both be operating. If Keadby I permanently ceased
operations the number of staff needed to operate Keadby II would increase.
Comparison of Consented Development with Proposed Development:
Operational Staff
There are no proposed changes to the nature or numbers of the
operational staff.
ENVIRONMENTAL RESOURCES MANAGEMENT KEADBY DEVELOPMENTS LIMITED
2-23
2.5.4 Hazardous Substances Management
All industrial facilities that need to hold stocks of certain hazardous substances
above a threshold require Hazardous Substances consent under The Planning
(Hazardous Substances) Regulations 2015. Materials such as process
chemicals and lubricant oils that do pose a risk to human health and the
environment will be stored on secure areas (e.g. with secondary containment,
impervious bases) and handled in accordance with operational management
systems.
2.5.5 Security Management
The Proposed Development will incorporate the necessary security
infrastructure and systems that are required for nationally important power
generation infrastructure. It is likely that this will be broadly similar to and/or
integrated with that for Keadby I in terms of boundary security fencing,
external car parking and a 24 hour manned security gate and gatehouse.
2.6 DECOMMISSIONING
The Proposed Development is expected to operate for at least 25 years. If at
the end of this period, the Company wishes to take the plant out of permanent
operation, it will be decommissioned, dismantled and removed from the Site.
The site would be restored to its pre-project condition.
2.1.1 Comparison of Consented Development with Proposed Development:
Safety, Health and Environmental Management
There are no proposed changes to safety, health and environmental
management.
Comparison of Consented Development with Proposed Development:
Hazardous Substances Management
There are no proposed changes in regard to storage and use of hazardous
substances.
Comparison of Consented Development with Proposed Development:
Security Management
There are no proposed changes to the security management
arrangements.
Comparison of Consented Development with Proposed Development:
Decommissioning
There are no proposed changes to the decommissioning plans.
ENVIRONMENTAL RESOURCES MANAGEMENT KEADBY DEVELOPMENTS LIMITED
2-24
2.7 ALTERNATIVES
2.7.1 Overview
As this application relates to a variation of an existing section 36 consent, the
Company has not assessed alternative sites in the given instance. However it
is worth noting that the 1992 EA for construction and operation of a combined
cycle gas turbine generating station of about 710 MW at this site reported the
main advantages of the Keadby site as including the availability of a gas
supply without the need for a new pipeline and a nearby connection to the
National Grid that can be achieved via short lengths of cable and a single
pylon. The Proposed Development will also be located on land previously
used for power generation. Therefore it avoids many of the environmental
effects associated with a similar development located on a ‘green field’ site or
located on ‘brown field’ site that does not have the requisite gas and grid
connections.
The Company has given consideration to certain alternatives, including
alternative technologies, within the context of CCGT development. In addition,
as described in Section 2.3.1, the proposals allow for flexibility in the design
process, and in particular for single or multi-shaft gas and steam turbine
configurations.
2.7.2 Cooling Options
General Considerations
Potential cooling options include:
water cooling through direct abstraction from and discharge to the River
Trent as is currently done for Keadby I;
indirect water cooling using water from the Stainforth and Keadby Canal
cooling system as proposed for the Consented Development;
indirect cooling using water from the River Trent;
air cooling.
For each of these options there are associated environmental and
sustainability factors to be considered.
Direct Cooling
The water volumes used and discharged in direct cooling are considerable
and it is thought unlikely that a system for the Proposed Development running
alongside that for Keadby I would be sustainable in terms of effects on the
Trent ecosystem unless they were separated by a large distance. A large
separation distance would introduce additional needs in terms of pipework,
land access and costs as well as technical considerations in terms of pumping
capacity and pump house location. For these reasons a second direct cooling
system to serve Keadby II was rejected.
ENVIRONMENTAL RESOURCES MANAGEMENT KEADBY DEVELOPMENTS LIMITED
2-25
Air Cooling
Air cooling has no water demand of any note. However, the structures
involved in air cooling demand a large land take, are visually large in mass
(e.g. compared to the hybrid cooling towers used in indirect cooling) and give
rise to higher noise emissions than water cooling systems. Cost and
generation efficiency are also considerations as air cooling places the highest
parasitic load on a station of all cooling options.
Indirect Cooling
Indirect cooling has a water demand, but much less so than direct cooling, and
also requires hybrid cooling towers, albeit of modest dimensions when
compared with air cooling equipment. While the River Trent offers a ready
source of water, indirect cooling requires water of a certain minimum quality.
River Trent water at this location would require considerable treatment,
possibly involving settlement lagoons with a large land take. For this reason
the Company explored the feasibility of abstraction of water from the Stainforth
and Keadby Canal, with a return to the River Trent via the Keadby I outfall.
Through consultation with the Canal and River Trust (CRT) it is confirmed that
there are unconstrained water volumes available for the required cooling duty.
Correspondence between SSE and CRT is included in Annex D of the
Consented Development ES.
The Proposed Development will therefore use indirect water cooling,
abstracting water from the Stainforth and Keadby Canal. Other than avoiding
some of the environmental effects entailed by their alternatives, the main
reasons for the choice of indirect water cooling, taking into account the
environmental effects, were as follows.
1. Indirect cooling using hybrid cooling towers has a low volume requirement
for water that can be met sustainably from a nearby source.
2. The water quality of the source is sufficiently good to meet operational
needs without extensive pre-treatment such as the use of space
consuming settlement ponds.
3. Modern hybrid cooling towers have a relatively low profile and plume
abatement thus reducing their visual prominence.
Potential use of Keadby I Cooling Water Infrastructure
It should be noted that in the event that Keadby I permanently ceased
operation then the Proposed Development would consider the direct cooling
option using the Keadby I cooling water infrastructure. This would be an
attractive option from cost and environmental effect perspectives, since it
would use existing infrastructure, have a smaller land take, be less visually
prominent and be less noisy at receptors close to the proposed hybrid cooling
tower location.
2.7.3 Site Access
The site will be accessed from the public road network via a dedicated access
road and this will be used by all HGVs and other heavy commercial vehicle
traffic.
ENVIRONMENTAL RESOURCES MANAGEMENT KEADBY DEVELOPMENTS LIMITED
2-26
Since the site is adjacent to a canal consideration was given to delivery of
materials and equipment via water transport. However, there are several
constraints in terms of such matters as the size of the lock from the River
Trent into the canal, lack of canal-side unloading facilities and impedance of
safe crane operations by the presence of overhead lines. While some of
these could be overcome it would have extended the footprint and added to
the environmental effects of construction activity.
For abnormal loads there are two feasible alternatives (see also Chapter 11 of
the Consented Development ES):
via the A18 entrance, making use of the skewed access and bridge that
was constructed to facilitate development of the Keadby Windfarm; or
along the route via the A161 and along New Trent Street and Bonnyhale
Road through Ealand as used in the past for abnormal loads.
The route ultimately used will be determined on the basis of the actual sizes
and weights of the equipment to be transported to the site and applications
made to the Highways Agency.
2.8 POSSIBLE FUTURE DEVELOPMENT
2.8.1 Combined Heat and Power
Combined Heat and Power (CHP) is the simultaneous generation of usable
heat and electrical power in a single process and is more efficient than
generating heat and power separately. This can provide a more efficient and
less carbon-intensive generating process.
In line with the requirements of National Policy Statement (NPS) EN-2, an
assessment for combined heat and power (CHP) offtake potential was
undertaken for the Consented Development and has been updated for this
EIA Report (see Annex F).
The CHP report has identified potential offtakes, including Lincolnshire Lakes,
which will be considered further at the appropriate time when the Proposed
Development is operational. The Company will continue to review CHP
opportunities as the Proposed Development progresses.
2.8.2 Carbon Capture Readiness
The Carbon Capture Readiness (Electricity Generating Stations) Regulations
2013 have introduced the need for new generating stations to consider carbon
capture. Whilst there is no requirement at present for plants to install carbon
capture technology from the outset, it is necessary to demonstrate that there is
Comparison of Consented Development with Proposed Development:
Alternatives
There are no changes to the alternatives considered in the Consented
Development ES.
ENVIRONMENTAL RESOURCES MANAGEMENT KEADBY DEVELOPMENTS LIMITED
2-27
suitable provision for carbon capture technology in the future: referred to as
‘carbon capture readiness’ (CCR).
The Proposed Development will have a generating capacity of up to 910 MW,
thereby exceeding the threshold set out in NPS EN-2, requiring all generating
stations above 300 MW capacity to make provision for carbon capture
storage.
As shown on Figure 2.2, an area of land in the west of the Site has been set
aside for future carbon capture technology to be installed. The land
requirement for future carbon capture equipment has been assessed based
on the scale of the Proposed Development, and details are provided in the
separate ‘Carbon Capture Readiness Report for Keadby 2 CCGT’ in Annex G.
Imperial College guidance on the minimum land requirement for CCS retrofit
to a CCGT is 48 m2 per MW. A 910MW plant therefore requires 43,680 m2 of
land. The Carbon Capture Readiness Report for Keadby 2 CCGT states that
the area of land available for a CCS plant is 45,000 m2. On this basis the land
set aside for CCS for the Consented Development is adequate to cover the
slightly increased land requirement for the Proposed Development. In
addition, specific technology for carbon capture has not been selected. By
safeguarding this land for future carbon capture, there will be flexibility within
the varied consent for installation of equipment to enable carbon capture.
The likely nature of any future carbon capture equipment cannot be foreseen
at this stage so the only element of it that is assessed in the context of effects
on the environment is the land take. At such time when it is appropriate for
carbon capture equipment to be installed, this would require additional
consent which would be subject to assessment.
Comparison of Consented Development with Proposed Development:
Possible Future Development
There are no proposed changes that are material to the possible future
development scenarios considered in the Consented Development ES.