Upload
md-shahabuddin
View
197
Download
4
Embed Size (px)
Citation preview
Page 1
Analysis of Two-Output Inverter For Induction Heating Application Analysis of Two-Output Inverter For Induction Heating Application
SOOTBLOWING OPTIMIZATION: FIELD EXPERIENCE
1YASHPAL SAHU,
2AMIT PANDEY,
3MD SHAHABUDDIN,
4POOJA AGRAWAL
Jindal Power Limited, Tamnar
Abstract—Furnace and convective pass slagging and fouling have a negative effect on boiler performance and emissions. The purpose of soot blowers is to keep the heat transfer surface clean so as to contribute towards optimal performance of the boiler. Excessive soot blowing can cause increased maintenance in fossil-fired boilers. Soot blowers perform on-line cleaning of localized areas consuming substantial amounts of costly high pressure Main Steam; this cost motivates the study of soot blowers and development of improved soot blowing strategies. Boiler
operators typically follow one continuous soot blowing sequence. Most rely on manufacturer’s recommendations, while some try to improve soot blower activation strategy by employing a trial-and-error approach. Considering the importance of soot blowing on plant operations and availability, soot blower operations need more attention. The Jindal Power Limited – different Dept. teamed up and has taken the initiative to perform a study on soot blower optimization by implementing pattern wise blowing. For this, different combination of tiers wise SB was done and the requirement and effectiveness of each tier was observed by studying different parameters and developed a pra ctical, knowledge-based approach to soot blowing optimization and has implemented it in Unit # 3 & Unit # 1 of 4 x 250 MW, OPJSTPP. This approach can deal with the reduction of soot blower activation frequency, and steam temperature
control. This paper describes the approach; implementation on a 250 MW tangentially fired boiler, operating experience, and benefits to the plants.
Keywords— Soot Blower, slagging
I. INTRODUCTION
All coals contain mineral matter in coal ash. Furnace
slagging occurs as molten or sticky fly ash particles
come in contact with the furnace walls or other
radiant surfaces and form deposits due to the
quenching effect of the tube wall. Slag deposits
reduce heat transfer to the furnace walls, and increase
the amount of heat available to the convection pass.
This results in a higher furnace exit gas temperature
(FEGT) and, for subcritical boilers, in a higher steam
temperature, desuperheating spray flows and NOx emissions. Deposition of ash on tubes or heat transfer
surfaces in the convective pass reduces heat transfer
in that part of the boiler. The convective pass fouling
results in less heat is transfer to the working fluid, a
decrease in steam temperature and desuperheating
spray flows, and in an increase in flue gas temperature
at the boiler exit.
The challenge in sootblowing optimization is to
determine which sections of the boiler to clean and on
what schedule, considering the factors such as tube
life, sootblower steam or steam consumption and
maintenance cost. For best boiler performance, it is important to maintain an optimal balance between
furnace and convective pass heat transfer.
A. BASICS OF SOOT BLOWING
Sootblowing controls the level of ash and slag
deposits on heat transfer sections. Sootblowers
perform on-line cleaning of localized areas using
high-pressure steam or air. Wall blowers and water
cannons remove slag from furnace water walls, while
retractable blowers clean the convective pass of the boiler (including the air preheater). Furnace cleaning
increases radiation heat transfer to water walls and
reduces the FEGT. This decreases the amount of heat that is available to the convective pass.
Therefore, over-cleaning of furnace walls can result
in low steam temperatures (below design level) with
resulting heat rate penalties and increased moisture
levels and erosion damage in last stages of the low-
pressure turbine. Reduced reheat steam temperature
also results in lower turbine and unit power output.
II. JPL APPROACH TO SOOT BLOWING
OPTIMIZATION
JPL has developed a sootblowing optimization
approach, described in References [1 to 47], for
balancing furnace and convection pass heat transfer to improve boiler performance, reduce NOx
emissions, and minimize disturbances caused by
sootblower activation.
The JPL sootblowing optimization approach
depends on a database describing the effects of
sootblower activation on parameters, such as
cleanliness of heat transfer surfaces, steam
temperatures, attemperating sprays, and other
parameters of interest. The sootblower
characterization database (SBCD), created from a
series of sootblower characterization tests, contains of the effect of one sootblower or sootblower group
at a time on parameters of interest.
SOOTBLOWING OPTIMIZATION: FIELD EXPERIENCE
Page - 2 -
III. SOOT BLOWERS OPTIMIZATION IN
BOILERS
There are many methods used for optimization of wall
blower operation in boiler furnace, like the manual
method, heat flux measurement method, and the automated method. The manual method is discussed
as this will bring out the philosophy involved in
optimizing wall blower operation.
Wall blowers are provided in boilers to clean the
furnace wall deposits. They seldom find use in
oil and gas fired boilers. The deposition and
slagging in boiler furnace is required to be
removed from the furnace walls at regular
intervals. The interval period will depend on the
area of deposition and the severity of deposition.
Steam wall blowers are found to be very efficient
in removing the furnace wall deposits.
In JPL Stage-I boiler of around 825t/hr capacity,
the total number of soot blowers are 90. In this,
around 56 numbers are wall blowers. The
frequency of soot blowing depends upon the type
of coal being fired. However the operating group
must remember that the initial suggested
sequence and frequency is more general and has
to be adapted to each boiler. The purpose of these
soot blowers is to keep the heat transfer surface
clean so as to contribute towards optimal
performance of the boiler.
A. EFFECT OF THE SOOT BLOWER ON
BOILER PERFORMANCE
Removes the deposits on the furnace wall and
ensures good heat transfer in the furnace region
The furnace outlet temperature slowly ramps up
after wall blowing as time lapses
Superheater spray quantity is seen to increase
with time lapse after wall blowing
Increases the bottom ash quantity depending
upon the deposition on furnace walls
Increases furnace tube material loss if blowing
is done too frequently without any deposits.
This leads to boiler outage or increased
maintenance.
In the case of water lancers for removing molten
slag, while operating there will be a large dip in
generation for the same heat input. This is mainly
due to the increased boiler losses
B. MEASURES TO BE CONSIDERED
Before taking up wall blower optimization, the
following has to be ensured:
All wall blowers are set to the right steam
pressure recommended by the designer
Check the alignment of the wall blower with
respect to the furnace walls
Ensure at least 50 degree centigrade of super
heat in the steam being used. This is to prevent
damage of the furnace walls due to wet team
impingement.
All wall blowers are operational
It is of great help if the boiler furnace walls are
photographed just after a planned shutdown.
Before shutting down the boiler, do not wall
blow the furnace for one full sequence. This
ensures deposit collection on the walls between
the adopted frequencies. While shutting down
the boiler ensure minimal thermal shock, by
slowly lowering the load. This ensures deposits
stay on the walls. Take the photograph from a
convenient man hole. But take all safety
precautions as anytime the deposit can fall
down due to cooling or thermal gradient.
There are many methods used for optimization of
wall blower operation, like the manual method, heat
flux measurement method, and the automated
method. The manual method is discussed as this is
bringing out the philosophy involved in optimizing wall blower operation.
SOOTBLOWING OPTIMIZATION: FIELD EXPERIENCE
Page - 3 -
C. NEED FOR SOOT BLOWER
OPTIMIZATION
To improve consistency in efficient operation of
boiler
To reduce steam wastage by identifying those
areas of low or no deposits
To reduce damage on furnace wall tubes due to
excessive blowing
The change in SH spray & RH Spray without change in other parameters indicates that the furnace deposits
are increasing. If the superheater or reheater sprays
increases above a particular level (to be determined
for each boiler), operate all wall blowers. These are
two basic things to adhere to while optimizing wall
blowers.
IV. OPTIMISATION STRATEGY ADOPTED
A. EARLIER OPERATION OF WALL
BLOWER
In every 8-hr shift, wall blowing used to be done once. It takes around 1 hour 30 min for complete
blowing. All blowers (1 to 56) were operated at a
pressure of about 22 kgf/cm2 & temperature of about
240 deg. C.
B. TECHNIQUE ADOPTED
There are 56 wall blowers in a boiler furnace wall, the
steps for optimization is listed.
Operate all 56 blowers
See the effect on superheater spray and note all
operating parameters of boiler
Wait for the superheater spray to ramp up to the
initial level and stay almost steady
Wall blow each row - study effect
Watch superheater spray drop and regain time
The interval between blowers is to be maintained
constant
Repeat if required each row independently,
waiting each time for the spray to reach the
original level with other parameters of boiler
remaining constant
Repeat the study for two adjacent rows
Repeat the study for two alternate rows
Repeat the study for blowers in front, rear, left
and right sides of furnace walls separately and
study the effect on superheater spray flow.
The blowing having the least effect on the
superheater spray indicates low or no deposit on
the walls.
A plot of superheater spray drop when each
blower is operated will give a good idea of
deposition in that area
Use the photograph of the furnace wall to
validate the effectiveness of blowers
Decide which blowers can be skipped during
blowing as well as the effectiveness of the row
The procedure for wall blower operation can be
evolved after the study and data analysis for the most effective way of wall blowing.
The use of heat flux meter by embedding
thermopiles at appropriate location in the furnace
walls to understand whether the tube in the region is
clean or with deposition the operation of the wall
blower requirement can be decided.
In the case of fully automated intelligent wall blower
system, the need to wall blow each blower is
understood from the effective heat flux falling on the
tubes. Designers use different methods to establish
this.
Day
Shift Remarks
A B C
1 Current operation for data capturing
2 1 to 14 All 56 All 56
3 1 to 14 All 56 All 56 For data
validation
3 15 to
28 All 56 All 56
4 15 to
28 All 56 All 56
For data
validation
5 29 to
42 All 56 All 56
6 29 to
42 All 56 All 56
For data
validation
5 43 to
56 All 56 All 56
6 43 to
56 All 56 All 56
For data
validation
SOOTBLOWING OPTIMIZATION: FIELD EXPERIENCE
Page - 4 -
C. OBSERVATION
Following are the observations taken under notice with the data collected:
D. PRESENT SCENARIO
A Shift B Shift C Shift
Tiers operated 1st
, 2nd
& 3rd.
2nd
and 3rd.
All four tiers
Soot Blowers to be
operated 1 to 42 15 to 42 1 to 56
Number blowers not
operated 14 28 0
So the number of blowers which will not operate in a day is 42 blowers
Parameter
1 to 56 Blower 1 to 14 Blower 15 to 28 Blower 29 to 42 Blower 43 to 56 Blower
Effect on
SH Spray
Spray just before
SB > 52 TPH > 50 TPH > 46 TPH > 48 TPH > 50 TPH
Reduced by 10 to 11 TPH 6 to 8 TPH 16 to 18 TPH ~ 15 TPH
No noticeable
change recorded Deteriorated to
same condition
after around
2 hr 1 and 1/2 hr 2 hr 2 hr
Effect on
RH Spray
Spray just before SB
5 TPH < 3 TPH < 2 TPH 2 TPH 5 TPH
Reduced by 5 3 2 2
No noticeable
change recorded Starts
deteriorating
slowly after
around
1 and 1/2 hr 2 hrs 2- 3 hrs 2- 3 hrs
Effect on
Burner Tilt
Deteriorated to
same condition
after around
1 and 1/2 hr No noticeable
change
No noticeable
change
No noticeable
change
Tilt position
remains same
SOOTBLOWING OPTIMIZATION: FIELD EXPERIENCE
Page 2
E. COMPILED DATA BEFORE & AFTER OPTIMIZATION
F. SH & RH TREND
Parameter May Jun Jul Aug Sep Oct Nov
Load 251.8 248.7 250.3 250.2 249.9 252.2 250.5
Avg MS Temp 534.0 534.6 534.2 534.3 534.6 534.7 534.6
Avg HRH Temp 535.7 535.5 535.8 535.8 536.0 536.0 535.7
Total SH Spray 44.6 45.6 52.1 51.3 53.8 43.9 46.1
Total RH Spray 4.3 2.9 9.2 9.1 10.2 5.7 4.9
O2 at APH-A I/L 3.2 3.2 3.0 2.5 2.6 2.9 3.1
O2 at APH-B I/L 3.0 3.3 3.6 3.0 3.0 3.0 3.1
Avg O2 3.1 3.3 3.3 2.7 2.8 3.0 3.1
FGT after PSH (L) 822.9 818.9 843.5 840.3 834.5 817.7 817.5
FGT after PSH (R) 774.7 776.4 786.4 757.4 802.4 782.7 764.7
SH & RH trends before & after Wall Blowing Optimization
SOOTBLOWING OPTIMIZATION: FIELD EXPERIENCE
Page - 2 -
V. FINANCIAL ASPECT OF CASE
A. Quantity of DM Water Saved
Total quantity of steam consumed during wall blowing
(1 to 56):- 5 tones i.e. 5000 Kg of steam
=> The steam consumed per blower is = 5000/ 56 =
89.2 kg of steam
By adopting above mentioned combination amount of
steam consumption reduction
= (89 X 14) + (89 X 28) = 3738 kg of steam per day
Steam consumption reduction in a year (taking 97%
PLF) = 3738 x 0.97 x 365 = 13, 23,439 kg = 1323
tonnes in a year
DM water cost = 100 Rs per m3 = 100 Rs per tonne
Total cost of DM water lost = 1323 x 100= 132300 Rs = 1.32 Lacs
B. Amount of Heat Energy Saved in terms
of Coal by throttling of steam
Steam condition at Super heater header a throttling for supplying steam to wall blowers: - Pr. -165 Kg/cm2 &
Temp. – 420 degree C
Enthalpy of steam = 724 Kcal/kg
Quantity of steam saved = 1323 tonnes
Total savings = 1323 X 724 = 975852000 kcal
Taking coal GCV 3500 kcal/kg, Quantity of coal saved
= 975852000/3500 = 273672 kg = 273.6 tonnes
Amount saved = 273672 (assuming cost of coal 1000 Rs
per tonne)
= 2.73 lacs
Total amount saved = 1.32 +2.73 = 4.05 lacs in a year.
VI. CONCLUSION
A series of upgraded steps at the JPL have been coupled
with optimization systems to gain performance benefits
in the form of fuel savings, reduced emissions,
increased net power generation and improved dispatch
capability along with financial saving. The combination
of a flexible and capable toolset, application expertise
and the power of continuous improvement are now
Providing continuous and significant performance benefits to the station.
VII. REFERENCE
1. Sarunac, N., Romero, C.E., Clements, B., Pomalis,
R., Henrikson, J., Cylwa, W. and Luk, J.,
“Sootblowing Optimization: Part 1 - Methodology, Instrumentation and Determination of Section
Cleanliness,” Presented at Combustion Canada
2003 Conference, September 21-24, 2003,
Vancouver, BC, Canada.
2. Sarunac, N., Romero, C.E., Shan, J., Bian, X.,
Clements, B., Pomalis, R., Henrikson, J., Cylwa,
W. and Luk, J., “Sootblowing Optimization: Part
2– Sootblower Characterization and
Implementation of an Intelligent Sootblowing
Advisor,” Presented at Combustion Canada 2003
Conference, September 21-24, 2003, Vancouver, BC, Canada.
3. Sarunac, N. and Romero, C., “Sootblowing
Optimization and Intelligent
Sootblowing,” Presented at 4th Intelligent
Sootblowing Workshop, Houston,
Texas, March 2002.
4. Sarunac, N., Romero, C. E. and Bilirgen, H.,
“Optimization of Sootblowing in Utility Boilers,”
EPRI Heat Rate Conference, Birmingham,
Alabama, January 28- 30, 2003.
5. Sarunac, N., Romero, C.E. and Levy, E. K.,
“Combined Optimization for NOx Emissions, Unit Heat Rate and Slagging Control with Coal-Fired
Boilers,” 28th International technical Conference
on Coal Utilization and Fuel Systems, March 9-14
2003, Clearwater, Florida.
6. Pomalis, R., Clements, B. R. and Abdallah, I. “Ash
Monitoring System for Lambton Generation
Station Unit 3,” CETC Division Report CETC-O-
ACT-03-14 (CF), Natural Resources Canada,
2003.
7. Sarunac, N. and Romero, C.E. “Sootblowing
Operation: The Last Optimization Frontier,” Presented at the 29th International Technical
Conference on Coal Utilization & Fuel Systems,
Clearwater, Florida, April 18-22, 2004.
8. Sarunac, N. and Romero, C.E. “Sootblowing
Operation: The Last Optimization Frontier,”
Presented at the 29th International Technical
Conference on Coal Utilization & Fuel Systems,
Clearwater, Florida, April 18-22, 2004.
9. Sarunac, N., Romero, C.E., Bilirgen, H., Bokowski,
J. And Cilinski, M., “Comprehensive Approach to
Performance Improvement and Emissions Reduction on a 400 MW Tangentially-Fired
Boiler: Part 2 – ESP Performance Improvement
and Sootblowing Optimization,” Presented at the
30th International Technical Conference on Coal
Utilization and Fuel Systems, April 2005,
Clearwater, Florida.
10. Congdon, P., “Control Alternatives for Industrial
Boilers,” InTech, December 1981.
11. Walsh, T. J., “Controlling Boiler Efficiency,”
Instruments and Control Systems, January 1981.
SOOTBLOWING OPTIMIZATION: FIELD EXPERIENCE
Page - 3 -
12. ANSI/ASME, “PTC 4.1, Steam Generating Units
Power Test Codes,” American Society of
Mechanical Engineers (ASME), 1965. 13. Culp, A. W., Jr., Principles of Energy Conversion,
New York: McGraw-Hill, 1979, p. 102, pp. 204–
207.
14. MacDonald, J. A., “Optimizing Power Boiler
Efficiency Calls for Heat Loss Cuts, System
Insulation, and Modifications,” Energy-Tech, April
2004.
15. Shinskey, F. G., Energy Conservation through
Control, Academic Press, 1978.
16. Babcock and Wilcox, Steam: Its Generation and
Use, 40th ed., New York: Babcock and Wilcox, 1992.
17. NFPA, NFPA-85 — Boiler Combustion Safety,
National Fire Protection Association, 2004.
18. Garton, D., “Water Cannon for Water Wall Cleaning
Applications,” EPRI Intelligent Soot Blowing
Conference, December 6–7, 1999.
19. McMahon, J. F., president, Cleveland Controls,
verbal communications.
20. Dickey, P. S., “A Study of Damper Characteristics,”
Bailey Meter Co., Reprint No. A8.
21. Jorgensen, R., “Fans,” in Marks Standard Handbook
for Mechanical Engineers, 8th Ed., McGraw-Hill, New York, 1978, p. 14.53.
22. Dukelow, S. G., The Control of Boilers, 2nd ed.,
Research Triangle Park, NC: Instrumentation,
Systems, and Automation Society, 1991.
23. Hurlbert, A. W., “Air Flow Characterization
Improves Boiler Effi- ciency,” InTech, March 1978.
24. DeLorenzi, O., Combustion Engineering, Inc., 1967.
25. ANSI/ISA-77.42.01, “Fossil Fuel Power Plant
Feedwater Control System: Drum Type,”
Instrumentation, Systems, and Automation Society,
1999. 26. Shinskey, F. G., “Taming the Shrink–Swell
Dragon,” Control, March 2004.
27. Fisher Controls International, Control Valve
Sourcebook: Power and Severe Service,
Marshalltown, IA: Fisher Controls International,
1990.
28. Miller, H. L. and Stratton, L. R., “Fluid Kinetic
Energy as a Selection Criteria for Control Valves,”
American Society of Mechanical Engineers, Fluids
Engineering Division, summer meeting, June 22–26,
1997.
29. Shinskey, F. G., Process Control Systems, New York: McGraw-Hill, 1979.
30. Latta, C. A., “Methods for Reducing NOx
Emissions,” Plant Engineering, September 1998.
31. McDonald, J. A., “Controlling the NOx after the
Burn,” Energy-Tech, December 2002.
32. Schwartz, J. R., “Carbon Monoxide Monitoring,”
InTech, June 1983.
33. O’Meara, J. E., “Oxygen Trim for Combustion
Control,” InTech, March 1979.
34. McFadden, R. W., “Multiparameter Trim in
Combustion Control,” InTech, May 1984. 35. American Technical Services, “Boiler Audits,” June
1982.
36. McMahon, J. F., President, Cleveland Controls,
verbal communications.
37. Westinghouse Electric Corp., “Oxygen Trim Control,” AD-106-125, Westinghouse Electric
Corp., June 1979, January 1985.
38. Moelback, T., “Advanced Control Superheater
Steam Temperatures: An Evaluation Based on
Practical Applications,” Control Engineering
Practice, Vol. 7, 1999, pp. 1–10.
39. Dukelow, S. G., The Control of Boilers, 2nd ed.,
Research Triangle Park, NC: ISA, 1991.
40. Schieber, J. R., “The Case for Automated Boiler
Blowdown,” Universal Interlock, 1969.
41. Cho, C. H., “Optimum Boiler Allocation,” InTech, October 1978.
42. Wood, A. J., and Wollenberg, B. F., Power
Generation, Operation, and Control, 2nd ed., New
York: Wiley Interscience, 1996.
43. Romero, C., Sarunac, N., and Levy, E., “Soot
Blowing Optimization in Coal-Fired Boilers,”
Lehigh University Energy Research Center Energy
Liaison Program Annual Meeting, 2001.
44. Cheng, X., Kephart, R. W., and Williams, J. J.,
“Intelligent Soot Blower Scheduling for Improved
Boiler Operation,” Proceedings of ISA
POWID/EPRI Instrumentation and Control Conference, St. Petersburg, FL, June 1999.
45. Booth, R. C., and Roland, W. B., “Neural
Network-Based Combustion Optimization
Reduces NOx Emissions while Improving
Performance,” Proceedings of 1998 ASME
International Joint Power Generation Conference,
Baltimore, MD, 1998.
46. Lefebvre, C., Lynch, M., and Roland, R.,
“Application of ProcessLink Real-Time
Optimization System to Cajun Electric Power
Cooperative’s Big Cajun II Generating Station,” Proceedings, 1999 International Power-Gen
Conference, New Orleans, LA, 1999.
47. Lipták, B. G., “Save Energy by Optimizing Your
Boilers,” InTech, March 1981.
SOOTBLOWING OPTIMIZATION: FIELD EXPERIENCE
Page - 4 -
About Author:
Yashpal Sahu
Education qualifications: ME- Mechanical, BIT, Mesra Ranchi
BE-Mechanical, GRKIST, Jabalpur
Certified Energy Auditor
Certfied BOE
Work Exp: 10 yrs 8 months with Jindal Power Limited,
- Project Monitoring of 250 MW
- Commissioning & Operation of 250MW
- Efficiency and CEEPI department
- Commissioning of 600 MW unit
Cell no: +91 9329445005
Email: [email protected]
Md Shahabuddin
Education: B.Tech in Electrical & Electronics
Engineering (EEE)
From Bengal College of Engineering & Technology ,
Durgapur
PGDC in Thermal Power Plant from NPTI, Guwahati
Work Exp: 1. Since Aug 2009 to Jul 2012 as a Desk Operation Engineering (Asst Manager) in Vedanta
Aluminium Ltd. , Jharsuguda.
2. Currently working as a CEEPI TEAM
(Asst Manager) in Jindal Power Ltd. , Tamnar.
Cell no: +91 7898905434
Email: [email protected]
Amit Kumar Pandey
Education qualification:
B.E. Mechanical (Honours)
PGD in Thermal Power Plant Engg. NPTI Nagpur (M.S.)
Work Exp: Associated with Jindal Power Ltd. since
Aug 2007,
Currently working as Manager (Operation).
M- + 91 7898905225
Email: [email protected]
Pooja Agrawal
Education: B.Tech in Electrical Engineering (EE)
From Indian School of Mines, Dhanbad
Work: Currently working as a CEEPI TEAM (Asst
Manager) in Jindal Power Ltd. , Tamnar.
Cell no: +91 7898902697
Email: [email protected]