1.RMJJ ProjectManagementNotes June2010 59

  • Upload
    pz

  • View
    220

  • Download
    0

Embed Size (px)

Citation preview

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    1/59

    Author: Remi MalahieudeBased on: Release PR-A2-engb 2/2008 (1006) John Rhoton 's PM Notes from 2010 Date: June 09, 2010

    Dear fellow students,

    This notes are based on John Rhotons notes from 2010. They are pretty much the same, in a slightly differentlayout and with some additions or some removals, based on my own taste.

    My final notes were much more complete that this document. The reason being is that I printed the whole file onone sided pages, bonded the whole, and completed them with either hand-written notes from Past Papers, or theblack book such as diagrams and figures (not hand-written, just printed them on big etiquette and pasted them inmy notes binder.

    Whatever you decide to do, my suggestion is to customize any notes to your own taste so that they becomeYOUR notes.

    I wish you all the best in your study.

    Remi Malahieude

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    2/59

    - 2/ -

    Module 1 Introduction1. What is a Project?2. What is Project Management?3. Characteristics of Project Management4. Potential Benefits and Challenges of Project Management5. The History of Project Management6. Project Management Today

    Module 2 Individual and Team Issues1. Introduction

    2. The Project Manager3. The Project Team4. Project Team Staffing Profile and Operation5. Project Team Evolution6. Project Team Motivation7. Project Team Communications8. Project Team Stress9. Conflict Identification and Resolution

    Module 3 Project Risk Management1. Introduction2. Background to Risk3. Risk Handling4. Types of Risk5. Risk Conditions and Decision making

    6. The Concept of Risk Management7. Risk, Contracts and Procurement

    Module 4 Project Management Organisational Structures and Standards1. Introduction2. Organisational Theory and Structures3. Examples of Organisational Structures4. Project Management Standards

    Module 5 Project Time Planning and Control1. The Concept of Project Time Planning and Control2. The Process of Project Time Planning3. Project Replanning4. Trade-off Analysis5. Resource Scheduling

    6. Project Planning Software

    Module 6 Project Cost Planning and Control1. Introduction2. Project Cost Planning and Control Systems3. The Project Cost Control System

    Module 7 Project Quality Management1. Introduction2. Quality Management as a Concept3. The Quality Gurus4. The Quality Management Six Pack5. Total Quality Management6. Configuration Management7. Concurrent Engineering and Time-Based Competition

    Module 8 Case Study1. Aims and Objectives of the Case Study2. Introduction (Module 1)3. Individual and Team Issues (Module 2)4. Risk Management (Module 3)5. Case Study First Supplement6. Organisational Structures (Module 4)7. Case Study Second Supplement8. Time Planning and Control (Module 5)9. Cost Planning and Control (Module 6)

    10. Quality Management (Module 7)

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    3/59

    - 3/ -

    Module 1 - Introduction

    1 What Is a Project?

    Projectone-off process with single definable end-result or product.

    Three key variables: Time, Cost, Quality.

    Production system takes resource inputs, passes through transformation, changes into desired outputs.

    Projects and Other Production Systems

    Mass productionlargenumber of repetitive items, maximum efficiency, capital intensive, mechanistic, little managementBatch productionnon-continuous demand, modifications at intervals, less mechanistic, more management, functional groupingsProject productionone-off, non-repetitive, no learning curve, complex management planning and control

    A programme is a set of identifiable projects aimed at achieving some goal or objective. Some no specified enddate until decision taken to stop or replace them.

    Characteristics of Projects

    Single definable purpose, product or result Defined constraints, targets

    Skills & talents from multiple professions/ organisations

    Unique, unfamiliar

    Temporary

    Interlinked process; directed at achieving goal

    Secondary importance to organisation

    Complex

    Project management

    Plans, coordinates, controls complex & diverse activities in projects

    Is in essence the General management of an organisation Requires skills

    - Financial awareness- Marketing appreciation- Technical knowledge- Planning skills- Strategic awareness- Quality management

    Project types

    External (revenue source)

    Internal (improve operations)&

    Hardware (tangible physical result)

    Software (end result is system or process)

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    4/59

    - 4/ -

    Definition of Project Management

    Achieving time, cost, quality targets

    Within context of overall strategic and tactical clientrequirements

    By using project resources

    Planning and controlling from inception to completion (life cycle)

    Decide on success criteria (time, cost, quality)

    Running the project as single entity

    Driving the team to success

    The Basic Project Management Structures

    Internal (non-executive) Project Management

    Project members also part of functional structure

    Single designated responsible (the project manager)

    Acts independently (outside functional structure)

    Equal authority to functional managers

    Single leader coordinates resources to achieve objectives

    Multidisciplinary group to integrate

    Negotiates with functional managers shared resources Two lines of authority for members

    Decision-making, accountability, rewards shared

    Temporary structure

    Can originate from any organisational level (pdt dev from Mkg, IT systems upgrade) Require assistance from support structures (FI, HR, IT)

    External Project Management

    Agent on behalf of client

    More flexible than internal system

    Instructions/communications cross organisational boundary

    Lower team allegiance

    PM has direct control Functional structure not relevant

    Requirement for risk transfer and contractual control

    No built-in knowledge of firm

    Characteristics of Project Management

    Differences to traditional management

    Uses both international standards and

    industry-specific benchmarks

    Advise on the full life-cycle

    Multiple Objectives

    Ensure project-success criteria are met within changing constraints of time-cost-quality continuum.

    International Co-operation and Standards

    IPMA International Project Management Association

    National agencies allow for cultural and economic differences:- APM Association for Project Management (UK)- PMI Project Management Institute (US)

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    5/59

    - 5/ -

    Multi-Industry/Multidisciplinary Practitioners

    Largest membership groups in APM:- Information Technology (IT)- Process engineering- Construction

    Generic BenchmarksBS6079current UK standard for PM practice

    ISO10006European code of practicePRINCE2controlled environment industries and UK governmentCny-specific responses: British Telecom and Construction Industry Council codes of practice

    Specific Provisions

    Professional project managerspecialist manager, trained in PM with relevant industry experience in PM

    Project Life Cycle

    Inceptionassemble basic proposalFeasibilityvalidate the proposal (financial, time-dependent, technological, political perspectives) PrototypeFull design development

    Tendering and contractual arrangementsManufacturingCommissioning (switching system on)Operation (may be longest part but not always, e.g. moon rockets)Decommissioning (switching system off)Removal and recycling (legislative and environmental concerns)

    Potential Benefits and Challenges of PM

    Potential Benefits of PM

    Focus on objectivesEfficient use of resourcesAccountability

    Competition with functional unitsReduced disruptionVisibilityLife-cycle costsRelease speedCommunicationsControl multiple objectivesSecurity of project informationTeam spirit/cohesionInnovationSkill development

    Potential Challenges to PM

    Impact on functional performanceDetrimental effect to compete for resourcesConflicting ordersFunctional manager deprives resourcesAdditional level of authorityContingency on flexible approach/attitudeReadjustment to functional working after project

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    6/59

    - 6/ -

    The History of Project Management

    Pyramids, Great Wall, Roman roads/aqueductsIndustrial Revolution: traditional management practicesworked well for batch/mass production1900s Gantt chart1940s Los Alamos/ Manhattan Projectfirst complex, high-tech project1950 Network diagrams for industrial processes1957 DuPontCPM Critical Path Method

    1958 US NavyPERT Program Evaluation and Review TechniqueLate 1960s Project Management Institute (PMI) & Association for Project Management (APM)

    1988 APM Body of Knowledge (BoK)1996 BS60791997 ISO10006

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    7/59

    - 7/ -

    Module 2 - Individual and Team Issues

    No urgent need for developing tools further. People make projects succeed or fail.

    The term project manager means different things to different peopleWide variation in roles and duties

    Selecting the Project Manager Charged with organising and managing a project team to meet objectives

    Sole responsibility for outcome

    Responsible to project sponsor

    Temporary role without traditional hierarchical power

    Authority to make decisions about priorities

    No authority to issue direct orders

    Sources of influence:Competency

    ProfessionalismProject Reputation FunctionalManager Skill Managers

    Interpersonal skills

    Alliances

    May manage across functional, departmental, organisational and geographic boundaries

    Central position High volume of communications

    Intellect to devise strategy and diligence to ensure execution

    Primary requirements

    - Planning

    - Organising team

    - Interfacing

    - Negotiating

    - Managing resources

    - Monitoring/controlling status

    - Identifying issues

    - Finding solutions

    - Resolving conflicts

    Interface managementwith a balance between managerial and technical functionsTo control project creep or creeping scope i.e. any changes. Only changes agreed are authorized orcontracted for.

    Soft management skills

    - Flexibility

    - Parallel focus

    - Initiative

    - Persuasiveness

    - Communications

    - Organization

    - Generalist rather than specialist

    - Planning & Implementing

    - Problem identification

    - Time management

    - Negotiation / influence / diplomacy

    Hard skills

    - Team set-up and management

    - Complex time/ cost plans

    - Contracts, procurement, purchasing,personnel

    - Training / Development

    - Technology

    - Business strategytranslate into objectives

    Selection

    - Internal (best) good functional manager with PM skillsshould not retain functional role!- External consultant is alternativeLearning curveDisparity of interest (no allegiance)

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    8/59

    - 8/ -

    Some Essential Project Manager Requirements

    Functions1. Project planning2. Authorizing3. Team organizing4. Controlling

    5. Directing6. Team building7. Leadership8. Life-cycle leadership

    Constraints/ success-failure criteria:TimeCostQualityRisk levelEnvironmental impactHealth and safety

    1. Project Planning

    Time, cost, quality

    Define authority linkages with Task Responsibility Matrix (TRM)

    - Milestones

    - Important activities

    - General & Specific responsibilities

    - responsibilities

    - Dates

    2. Authorising

    Accumulate sufficient authority to get the job done

    Delegate to others

    Authority is the ability to control and direct (Power is given)

    Approval Preparation Checking Making and input Authorising

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    9/59

    - 9/ -

    3. Team organising

    Classical/ traditional theory

    - People are merely components of a production process (e.g. automotive)

    - Emphasis on the produced goods or services

    Empirical theory

    - Essential similarities between systems and processes

    - Observation and interpretation

    - Correct process will materialise from sample and data set

    - e.g. trains

    Behavioural theory

    - Human relations school Interpersonal relationship between people and work/ organization (Intrinsic links) Profit sharing Expectancy theory

    - Social system school Social characteristics of organisations and individuals Evolution as people leave/join External influences e.g. smoking ban, health and safety regulations

    Decision theory

    - Mathematical: management science - operations research

    Systems management theory

    - Organisation characterised by throughput of resources

    - Inputprocessingoutput

    Functional managers favour Classical, Empirical, Behavioural theory.Project managers favour Decision and Systems management theory.

    Organising throughout the life-cycle but greatest organisational development at beginning.Clarify at first meeting:

    - Individual responsibilities

    - Organisational Breakdown Structure OBS

    - Task Responsibility Matrix TRM

    - Communication links

    - Authority links

    - Configuration Management System CMS

    - Project programme

    4. Controlling1. Targeting

    - Aligned with success and failure criteria

    - Cost, output, quality2. Measuring

    - Formal (objective eg EVA), informal (subjective)

    3. Evaluating

    - Identification/isolation of problem

    - Alternative options

    - Corrective action

    - Variance analysis in conjunction with forecasting4. Correcting

    - Identify source of problem

    - Correct it

    - Monitor actual and planned correction performance (2nd level variance analysis)

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    10/59

    - 10/ -

    5. Directing

    Setting up project team

    Training and development

    Supervision

    - Individual targets, evaluation, discipline, definition of objectives and responsibilities

    Motivation (team and individual)

    - Rewards, evaluation, feedback, reconciliation of individual/organisational goals

    Co-ordination

    - Prioritisation of work; monitoring resources

    6. Team buildingEarly stages most critical (initial culture often continues)1. Team/ Individual commitment

    - Common objectives, reward system, motivation drivers2. Team spirit (not same as commitment)3. Obtaining necessary resources

    - Number of people, mix of skills4. Clear team/individual goals and success criteria5. Formalisation of visible management support (attendance at key meetings)6. Effective programme leadership

    - Accuracy of planning, efficiency of monitoring/control. Ownership of large problems

    7. Open formal/informal communications8. Rewards and retribution systems (good performers rewarded, poor performers reprimanded)9. Identification /management of conflict

    - High pressure is common source

    - Sudden change in energy levels can be a sign10. Heterogeneity and cohesiveness

    7. Leadership

    Decision-making ability

    Problem-solving ability

    Integration of new members (flexibility, provision of sufficient learning time)

    Interpersonal skills (comradeship and trust) Identify and manage conflict (when objectives/limitations are changed)

    Communication skills(most important tool)

    Interface management (upward, downward, horizontal)

    Factor-balancing skills

    8. Life-cycle leadership

    - Project teams last relatively short period of time

    - Project team changes to meet needs/challenges

    Phase Characteristic Task People Effect1 Inception High Low Telling

    2 Development High High Persuading3 Stabilisation Low High Participating

    4 Maturity Low Low Delegating

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    11/59

    - 11/ -

    The Project Team

    Project Teams within Functional Organisations

    Allocated to most appropriate department

    Using resources from one function or across several

    Contrast with Pure project organisation for relatively large one-off projects (e.g. Millennium Dome)

    Advantages of projects within functional organisation

    - Flexibility and full use of employees

    - Employees gain new experience/skills

    - Cross-functional working attitude

    - Experts create new synergies outside rigid functional structure

    - Follow primary career path within function or new career path through project

    - Less costly than external consultants

    Disadvantages

    - Function is depleted of resources

    - Functional managers offload less efficient people

    - Difficulty in adapting to the demands of project environment

    - Prioritisation of simultaneous projects

    - Communication barriers (compared established channels of functional units)

    - Motivation (unless senior management support)

    Team Multi-disciplinary & Heterogeneity Issues

    Sentience: tendency to identify with own profession/background rather than with project and organisation

    Interdependency: tendency for teams to depend on input from more than one individual

    - Pooled interdependency (sections/divisions make contributions)

    - Sequential interdependency (input from multiple individuals required to move to next phase)

    - Reciprocal interdependency

    Integration: process of defining responsibilities and control, ensuring everyone adheres to same definition

    Differentiation (specialism) contributes to sentience

    Multidisciplinary nature tends to increase sentience and interdependencyGreater range of backgrounds reduces overall bias (but more discussion and conflict)

    Group and Team Processes

    Group: collection of individuals with common objective

    Team: group working under direction of team leader

    Organisation contains many formal and informal groups.Informal tend to form quickly and voluntarily for social reasons.

    Groups better at problem solving than individuals. Groups tend to:

    - Brainstorm

    - Consider wider range of factors

    - Enhanced logic flow

    - Generate more original ideas

    - More potential solutions

    - Solve problems more accurately and quickly

    Project Team Performance

    Most important factors contributing to performance:

    - Heterogeneityin qualifications, experience, outlook- Cohesivenessalignment of personal and team goals; commitment and morale of members

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    12/59

    - 12/ -

    Project Team Staffing Profile and Operation

    Project Team Staffing

    Balance of skills:

    - Technical

    - Management

    - Administrative

    - Interpersonal

    Other considerations:

    - Immediate and long-term availability

    - Ability

    - Continuity requirements

    - Teamworking skills

    - Special skills

    Trade-off between continuity and ability

    Mix of internal and external staff

    Guidelines:

    - Voluntary staffing

    - Staffed to add value to project

    - Operated less formally than functional teams

    - PMgr Lead by example

    - Flexible and responsive

    - Interface across organisational boundaries

    - Teams innovate and evolve

    - Functional managers receive recognition and credit for provided resources

    - Conflict should be promoted during staffing (the sooner the better)

    Project Team Profile

    Widest interpretation of project team:

    - Contractors personnel-

    Subcontractors- Clients

    - In-house staff

    - Other interested bodies (inspectors, government, lobby groups)

    In almost everyones interests to meet objectives in timely and cost -effective manner

    Project office: focal point, physical hub of project

    Three specials project-management positions:

    - Project manager (managing director)- Project planner (operations director)- Project controller (financial director)

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    13/59

    - 13/ -

    Project Team Operation

    1. Establish measurable objectives

    - Identify and acknowledge stakeholders

    - Establish dimensions of success

    - Agree on criteria for success

    2. Stakeholder management

    - Invisible team can provide great source of support

    - Protect image of team

    - Develop network of useful contacts

    - Exploit network for quality project resources

    3. Establish/plan measurable targets

    - Understandable and practicable

    - Multi-level

    - Plan for unknown (contingencies)

    - Realistic milestones

    4. Plan and establish processes

    - Firm ground rules

    - Create open environment to be creative and take responsibility

    - Develop relationships

    - Flexible environment when needed

    5. Leadership

    - Clear direction, stimulate high performance

    - Reward good performance

    6. Membership and identity

    - Members must trust PM

    - Active followership more valuable than passive

    - Temporary drafts must be seen in positive light

    - Clear understanding of roles

    - Members recognise their own value

    7. Communication systems

    - Formal/informal meetings to confirm identity, provide opportunities, reinforce rules, celebrate success

    - Accept and address conflict

    - Efficient communication with external bodies

    - Meetings result in actions, documented with time scales and responsibilities

    8. Team separation

    - Members can rely on fellow team members

    - Commitment and momentum maintained even when physically separated

    - Regular contact enables clear communications

    9. Information technology

    Advantages

    - Reduced need for specific facilities (video)-

    Reduced direct interactionfewer personality clashes- Record keeping, simplified accountability and audit- Less direct supervision

    - Less control bureaucracy

    Disadvantages

    - Expensive remote support

    -

    Loneliness- Loss of managerial control

    - Time differencecoordination- IT can go wrong

    - Cohesion severely restricted

    10. Teams in general (optimal when)

    - Regular face-to-face meetings

    - Performance measures and criteria are clear

    - Members have responsibility and accountability

    - Clear time commitments established

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    14/59

    - 14/ -

    Project Team Evolution

    Project Life CyclesConception and feasibilityOutline proposals and definitionTooling upOperation and productionDecommissioning

    Project Change Control and Management

    Historically little attempt to standardise life-cycle phasesBS6079 proposes Strategic Project Plan (SPP) defining standard planning & control system

    Project Team Evolution

    Forming

    - TRM Task Responsibility Matrix

    - OBS Organisational Breakdown Structure

    - Project staff register

    - Baseline set of team and project objectives

    Storming

    - Establish cohesiveness

    - Increasing tendency of conflict

    - Attempts to depose leader

    Norming

    - Formal/informal

    - Behaviour

    - Performance

    Performing

    - Team members satisfied that team is balanced

    - New conflicts dealt with by team

    Groupthink

    Groupthink is the tendency for teams to delude themselves over the quality and reliability of the product. Most oftenencountered in long-term teams where there has been initial success.

    Typical symptoms:Absolute commitment to the projectLack of respect for competitorsIntolerance of dissentersFear (of authority or majority)Self-delusion (invincibility)common in successful teams with high cohesion and commitmentSelective reporting

    Project Team Motivation

    McGregor

    Theory Xoperatives are basically lazy and unmotivated. Require threat and punishment.(Often espoused by autocratic functional managers.)

    Theory Yoperatives are willing to work and complete job without close supervision. Want to successbecause it generates greater self-respect. (Typically preferred by project managers.)

    Maslows hierarchy of needs

    Self-actualisation

    Esteem

    Belongingness

    Safety

    Physiology

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    15/59

    - 15/ -

    Implications:

    Relative importance of needs

    Time-based requirements (higher levels require more time)

    Unsatisfied needs (no guarantee) Complex needs (higher level needs more subjective)

    Anticipation (fulfilled needs become hygiene factors rather than motivators)

    Equity theoryperceived fairness compared to othersChoices during perceived inequity

    Seek promotion

    Seek increased reward level

    Reduce contribution

    Increase other inputs

    Expectancy theorymotivated in obtaining desired rewards

    Project Team Communications

    Inward and outwardFormal and informal

    Project Communication

    High-quality information sharing and exchange

    Quantity and Quality of face-to-face meetingAccess to meetings should be open to all team membersEncouraged to attend

    Communication methods:

    - Meetings

    - Telephone

    - Letters/memos

    - Email

    - Notice boards

    - Chats

    - Seminars

    - Project plans and reports

    - Newsletters

    Formal and Informal Communication

    Operational islands: sections defined by power and functional boundaries

    Formal lines of communication essential for collecting and disseminating project information

    Formal communication tools:

    - Frequent reports on all aspects with clearly defined distribution lists

    - Regular project meetings (debate encouraged)

    - Project memos

    -

    Newsletters- Notice-board

    - Away-days and events

    Informal communication revolves around the grapevineInfluence ita gauge of feeling- Identify and expose issues quickly

    - unhealthy grapevine harbours resentmentand disillusionment

    Lunch and dinner

    - Telephone

    - Coffee breaks

    - Evenings in the bar

    - Social events

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    16/59

    - 16/ -

    Internal and External Communications

    Typically internal are informalOpen communication encouraged

    External is formal, explicitrequire absolute control on dissemination of information

    Project Team Stress

    Origins and Symptoms of Team Member Stress Sources of project stress

    - Dual reportingproject manager & functional manager- Strict time, cost and quality limits

    - Short life span of teams

    - Project complexity

    - Frequently changing environment

    Main sources of stress

    - Personal

    - Work (project and functional)

    - Environment

    Symptoms- Psychological

    - Physiological

    - Behavioural

    Stress Management

    Individual stress management

    - Diet

    - Reduced alcohol, tobacco

    - Exercise

    - Physiological awareness

    - Communication (most important single element)

    - Realignment of goals and self-limits

    - Psychological self-examination

    - Breaks/holidays

    Project-team stress management

    - Deregulation (rigid to flexible working times)

    - Reasonableness

    - Fairness

    - Open-mindedness

    - Flexibility

    - Approachableness

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    17/59

    - 17/ -

    Conflict Identification and Resolution

    Constructive/ meaningful conflict

    Sources of Conflict

    Onerous resource constraints

    Pressure to increase speed/reduce costs

    Imposition of new aims/objectives

    Change and realignment Conflicting function and project demands

    Personality clashes

    Different interpretations of requirements

    Incorrect/ late information/ communication

    Perceived inequalities

    Underlying resentment

    Conflict Characteristics

    Potential for conflict increased by

    - Heterogeneity, multidisciplinary nature

    - Lower PM authority in functional organisation

    -

    Lower degree of specified/ quantifiable objectives- Lower communication and accountability

    - Greater degree of change

    - Lower perceived prestige of project

    Approaches to Conflict

    Areas of conflict

    - Onerous deadlines

    - Change occurs

    - Errors/ omissions discovered

    - Resources reduced or inadequate

    - Personality clash

    - Agreeing on areas for concentration

    - Agreeing on priorities

    - High uncertainty

    Questions to ask

    - What is source

    - Why?

    - Impact?

    - How to reduce or eliminate

    - How to foresee and avoid in future

    Project objectives should be SMART, and also:

    - Compatible with strategic plan

    - Agreed by senior management

    - Communicated to team

    - Communicated to stakeholders

    Conflict Management

    Conflict avoidance

    Conflict absorption

    Conflict resolution imposition

    Negotiated conflict resolution

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    18/59

    - 18/ -

    Module 3 - Project Risk Management

    Human beings naturally consider risk and reward as part of the decision-making process.Project manager inherent risk takerPrimary Function to identify and control risk

    Background to Risk

    The Concept of Risk

    Risk management evolved from design of nuclear reactors (1950s),Energy source is inherently dangerous, consequences catastrophic, no point in examining single events

    Riskmeasure of probability and consequence of not achieving specific goal.

    (event, uncertainty, consequence) = 1st level equation for risk

    Risksomethingor the lack of somethingcauses a risky situation.

    (event, hazard, safeguard) = 2nd level equation for riskHazardsource of dangerSafeguardmitigation against the hazard

    Exposure: vulnerability of parts of organisation to risk impacts

    Sensitivity to risk composed of 3 elements: significance(severity/impact), likelihood, ability to manage implications

    Effective Risk Exploitation (ERE) makes use of non-balance-sheet assets (SCM, IP, KM)

    Risk is the distribution of possible outcomes in performance over time due to changes in key variables (greater range = greater risk

    Considerations:World is uncertainRisk cannot always be eliminatedRisk is a function of opportunityRisk can be an advantage (intimidates competition)Risk management is set of analytical toolsOperates at all levelsRisks may be foreseeable, partially foreseeable and wholly unforeseeable.No risk management is infallible

    The Human Cognitive Process

    Cognitive process in risk assessment:

    Pattern recognition

    Attention

    Memory

    Bounded Rationality

    - Generally we opt for rational behaviour within constraints

    - Examine possible actions and possible outcomes

    - Risk forecasting

    Based on experience, present, extrapolation (aka Prediction Momentum) Combination of subjective and complex modelling (chaos theory)Success factors:

    Accurate data

    Time limits

    Cost (effort)

    VisionoIntuitioncombination of experience and extrapolationsoBiastendency to misinterpret data because of own perceptions/preferences

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    19/59

    - 19/ -

    Risk Handling

    Risk Assessment and Control

    Risk analysis determination of probability of risk events and establishing measure of consequencetogether with monitoring and control system

    Risk handling process of dealing with riskRisk feedback occurred risks are analysed and results fed back to system for future strategiesRisk control risk analysis, handling and feedback

    Typically risk management considered: risk assessment and risk control.

    Risk assessmentiterative process identifying and assessing all potential risksRiskcombination of uncertainty and constraint (e.g. legislative deadline)

    Risk controlinvestigation of entire project (project plans, scrutiny of critical path)

    Risk identificationsource and effects Individual perception of risks will vary according to:

    - Organisational position

    - Power level

    - Area of authority

    - Responsibilities

    Project and Strategic Risk

    Project risk limited to risk considered entirely within project (delays, errors, cost increases)Strategic risk long-term, complex, difficult to model (economy, competition)Variance envelope allows divergence to a certain limit

    Types of Risk

    Generic Risk Headings

    Strategic risk long-term performance of organisationOperational risk process itself, asset base, project members, legal controls (e.g. project risk)

    Financial risk market, credit, capital structure, reportingKnowledge risk IT hw/ sw, IM, KMCatastrophic risk cannot be predicted or quantified, usually covered with reserve/contingency sum

    Market Risk and Static RiskMarket risk (Dynamic risk)potential gains/lossesCannot be reduced or controlledonly diversified

    Market business risk (MBR) company trading with its assetsconcern to all stakeholders (shareholders, creditors, employees) Market financial riskgearing ratio, concern to equity holders

    Static risk (specific risk or insurable risk)losses only; potential losses and safeguards. Insurance policy Fire insurance, tortuous liability insurance (professional indemnity), personnel insurance

    External Risk and Internal Risk

    External risks

    Competitor risk

    Market demand risk

    Innovation risk

    Exposure risk (e.g. gearing ratio)

    Shareholder risk

    Political risk

    Statute risk

    Impact risk

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    20/59

    - 20/ -

    Internal risk

    Operational processes risk

    - Resource availability

    - Production capacity

    - Process failure

    - Time-based competition

    Financial risk

    - Borrowing

    - Cash flow

    - Exchange rate

    Management risk

    - Management error

    - Strategy implementation

    - Communications

    IT and Technology risk

    - System obsolescence

    - Breakdown and failure

    - Malicious virus

    - Capacity limit

    Predictable Risks (known unknowns)and Unpredictable Risks (unknown unknowns)

    Risk Conditions and Decision making

    Conditions of certainty gravity

    Conditions of risk weather/rain

    Conditions of uncertainty earthquake, hurricane

    Decision Making under Conditions of Certainty

    Example: when same strategy optimal for all possible states/conditions (pay-off matrix)

    Decision Making under Conditions of Risk

    Typically: higher profits implies higher potential risks/losses

    Payoff-matrix: Profit-matrix for strategy x state, whereby each state has assigned probabilityMultiply payoff by probabilitysum for each strategy

    Decision making under Conditions of Uncertainty

    Assigned probabilities are not known. Sources of uncertainty can be

    Externally drivenenvironment: inflation, interest rates, demographic changes

    Internally drivenprocess: motivation, loyalty, new products, innovation

    Decision-driveninformation: strategy planning, R&D, investmentMaximax / Hurwicz criterion always optimistic, maximise profits irrespective of lossMaximin / Wald criterion pessimistic, minimise losses (minimum profits in worst-case scenario)Minimax / Savage criterion minimise maximum regretLaplace criterionassign equal probabilities to all outcomes (assumes Bayesian theory)

    The Need for a Risk Management Strategy

    Total Strategic Risk Management (TSRM) must be holistic and pre-emptive (similar to TQM)

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    21/59

    - 21/ -

    The Concept of Risk Management

    Risk management system must be

    Practical

    Realistic

    Compliant (with internal & external standards)

    Cost-efficient

    Risk Management areas

    identification classification

    analysis

    attitude

    response

    control, policy and reporting

    Risk Identification

    Detailed and thorough, identify source of risk

    Internal risks use WBS to identify most obvious risk areas (3-4 level)

    External risks e.g. interest rates, economic activitydifficult to identify and evaluateProject risks project administration and control techniquese.g. OBS, team membership, leadership, communication

    Risk Objective sourcessum total of past experienceRisk Subjective sourcessum total of current knowledge (e.g. PERT analysis)

    Brainstorming (Delphi, Nominal group, SWOT M7)1. Creative phase2. Evaluation phase

    Risk Classification

    Portfolio theoryconsiders from a financial point of view (beta coefficient)Classify as market risk (business/ dynamic risk) or static risk (systemic risk)

    Three-level classification

    Risk type

    Risk extent

    Risk impact (consequence)

    - Maximum probably loss

    - Most likely cost of loss

    - Cost of covering loss

    - Cost of insuring against event

    - Reliability of predictions about event

    Risk Analysis

    1. Evaluate all options2. Consider risk attitude3. Consider characteristics of risks (internal/external, controllable)4. Establish measurement system5. Interpret results6. Make decision

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    22/59

    - 22/ -

    Alternative methodology1. Identify source2. SWOT analysisMap risk drivers3. Assess probably and impactActual risk map4. Consider all optionsDevelop target risk map5. Assess value added with recommended risk response6. Set up monitoring and reporting

    Risk mapping = Risk profiling (aka Risk footprinting)4 quadrants reflecting high/low probability and impactRisk migrationfrom actual to target risk mapselected risks = controllable & internalShape (e.g. ellipse) versus point reflects variation limits

    Risk gridtable Dimensions: multiple levels of probability and severity

    Cell: indicates action (e.g. Retain, Part insurance, Full insurance, Cease activity)

    Risk Attitude Risk seeking AGAP = all goes according to plan

    Risk averse WHIF = what happens if

    Individuals more risk averse than teamsInclination to risk increases with age of team (time since formed)Multidisciplinary teams seek more risk than unidisciplinary teams.

    Risk Response

    Considerations

    Company policy

    Missing information on cause/effect

    Time of exposure Individual/team interests

    Involuntary/voluntary risk

    Alternatives

    Risk distributionContracttool to allocate/share riskConsiderations

    Is the outcome worth the risk?

    Who controls most risk

    Who is most liable?

    Incentives?

    High impact

    Low probability(Quadrant 2)

    High impact

    High probability(Quadrant 1)

    Low impactLow probability(Quadrant 4)

    Low impactHigh probability

    (Quadrant 3)Impact

    Damage

    Probability

    Impact

    Damage

    Probability

    A B

    C

    D Impact

    Damage

    Probability

    C1C2

    C3

    NeutralSeeker

    ImpactIe. max. reward or opportunity available

    AverseEffort

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    23/59

    - 23/ -

    Response Options

    Retentionignore risk (low-probability, low-impact) Reduction

    Transfer (insurancecontract: General Terms and Condition)- Insurability of risk (not all are insurable)

    - Cost of insurance

    - Maximum probable loss

    - Likely loss

    - Likely cost of covering loss

    Avoidance

    - Pre-contract negotiations

    - Rescission

    - Exemption clauses

    - Scope redefinition

    Seeking further information

    Risk Control, Policy and Reporting

    Risk handbookit documents experience with risk and risk managementRisk reports should be regular and integral to strategy

    Risk policy:

    Overall aims and objectives

    Accountability for managers (TRM)

    Formalised reporting channels

    Risk tolerances (variance)

    Authorisation

    Risk, Contracts and Procurement

    Contract is tool for risk transfer and mitigation. It transfers liability.

    To insurance company for premium

    Between suppliers/subcontractors Tender price reflects risk absorption

    Reasons for conflict

    Defective documentation

    Inappropriate arrangements

    Incorrect estimating/pricing

    Unreasonable risk allocation

    Communications breakdown

    Insolvency

    Ambiguity

    Contract defines rights, dues, obligations, liabilities.

    Commensurate riskinability to fulfill obligation due to own inadequacy,incapacity, inadvertence or errorUberrimae fidei (utmost good faith) obligation to disclose all relevant information to contract

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    24/59

    - 24/ -

    Basic Contract Theory

    Contract items

    - Signature block & project title

    - Definition of terms and scope

    - Information/facilities provided by client

    - Project approvals

    - Payment systems

    - Working drawing

    - Specification

    - Schedules

    - General conditions (sector-generic)

    - Specific conditions

    - Provisions for change

    - Form of tender

    - Dispute resolution

    - Bonds and warranties

    Contract requisites

    - Offer and acceptance

    - Consideration (e.g. deposit)depending on legal system- Capacity

    - Legal relations

    - Communication (acceptance to offeror)

    Performanceall parties complete all duties and liabilities

    Alternatives to performance

    - Breachone party in contravention to terms- Frustrationcannot be fulfilled although both parties wish to- Rescissionerror or misunderstanding, rescinded by court if terms are not acceptable (contradictory term- Rectification

    - Void (e.g. if goods are illegal)

    - Termination/determinationin accordance with provisions of contract

    ProcurementMost large organisations have Legal Services for procurement of contractsStrategic vs. Project procurement

    Procurement phases

    Objective phase

    Exposure phase (advertisement, investigation into possible sources)

    Alternatives phase (sources analysis)

    Documentation (of requirements)

    Tendering

    Award

    Contract administration

    Characteristics of ContractsControllable (e.g. human error, decision making) vs. uncontrollable (adverse weather)

    Fundamental contractual risks

    Design defectslatent and patent Project cost

    Safety and indemnification

    3rd party insurance

    Fire, flood Completion deadlines: Damages may be punitive, liquidative (cash) or ascertained (actual)

    Express/implied terms (e.g. PII professional indemnity/ liability insurance)

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    25/59

    - 25/ -

    Transfer of Risk in Contracts

    Indemnity clause transfers riskCourts unsympathetic to excessive transfer

    Variation Orders(EU)& Change Notices(US)

    Variationsallow for changes to contract without invalidating itMust be possible to price to compensate affected party

    Claims Risk

    Client risks

    Failure to provide information

    Late instructions

    Errors/omissions in contract documents

    Delays by nominated subcontractors or client consultants

    Changes in statute

    Non-availability of labour

    Civil commotion, war, natural disasters Adverse weather

    Determination of contract by contractor

    Obligation of client to insure against:

    Fire

    Flood

    Lightning

    Impact of aerial devices

    Radiation

    Contractor insurance

    Employer liability for employees

    Liability for damage to 3rd party persons and property Escape of hazardous materials

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    26/59

    - 26/ -

    Module 4PM Organisational Structures and Standards

    Internal (operational, non-executive) project managementExternal (executive) project managementInternal with external specialist support

    Organisational Theory and Structures

    People make projects succeed or failPeople are more difficult to predict/control than schedule/cost

    1. The Project within an Existing Organisation

    Most common form of PM groupingFundamental consideration is relationship between organisation and project; dependent on:

    Size, status and importance of project

    Resources available

    Strategic fit

    Functional organisational structure

    Most common; preferred by inflexible organisations, examples:

    - Government

    - Police forces

    - Military

    - Most large private companies

    Power/status defined by vertical hierarchy

    Horizontal communications only at top levels

    Projects may be contained within function

    Benefits:

    - Clear reporting, rules, responsibilities, chain of command

    - Mirrors traditional authority structures

    - Simple; intuitive

    - Specialisation & focus (shared knowledge)

    Disadvantages:

    - Inflexible

    - Cross-functional activity discouraged

    - Boundaries, barriers

    - Greater need for central support

    - Development of organisational and operational islands

    Pure project structure

    Can exist within functional structure

    Often have complete freedom within limits of final accountability

    Set up to deliver very visible projects

    Benefits:

    - Flexible & responsive to change

    - Encourages innovation and evolution

    - Operational costs can be adjusted to workload variations

    - No need to negotiate with functional manager for resources

    - Shorter in/formal communication lines

    - Authority contained within project

    - Team members not distracted by functional loyalty

    - Easier to incorporate external consultants

    - Easier to execute related projects as programme

    - In summary, best structure for a project

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    27/59

    - 27/ -

    Disadvantages:

    - Concurrent projects may lead to duplication of effort

    - High initial operating costs (until any projects are completed)

    - Centralized direction

    - Increased early operating costs if PMs think ahead to resources needed- Team members concern about long-term- Competition between project teams

    - Deadlines may force to cut corners

    - Prolonged absence from function can dilute specialisation

    Matrix structure (internal, Non-executive)

    Blend of mechanistic/ repititive (pure functional) and research/ innovative (project)

    Very popular for organisations undertaking projects

    Generally restricted to large organisations with constant/ predictable workload

    Main characteristics

    - Functional (vertical) boundaries

    - Power/status (horizontal) boundaries

    - Organisational islands

    - Project sponsorAdjudicate disputesAllocate resources

    Make executive decisions- PM chair

    Four legs: PM, sponsor, functional manager, teamThree interfaces for PM Three levels of control (subordinate, peer, superior)

    - Interfaces

    - Bidding

    - Time-recording and cost-centre charging

    Most internal structures make at least some use of external resources

    2. The Project External to the Existing Organisation

    Project team may comprise

    All internal resources managed by external PM

    All external consultants managed by consultant PM

    Mixture of internal and external resources

    Surrogacyextent to which client wishes to delegate control/authorityRisk transfernormally cover non-performance/ negligence but not supplier breaches

    External (Executive) PMmeans PM has full authority (does not need to negotiate over resources)

    Distinctive characteristics

    Multidisciplinary nature / shared loyalty Open and competitive fee structures

    - Fee bid package

    - Paid in TranchesPre-contract worksPost-contract worksFinal account

    - Percentages based on measured works totals or final account total

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    28/59

    - 28/ -

    External contractual linkages

    - Primary typesCompletion contractsTerm contracts (long-term agreements)Service-level agreements

    - Competitive contracts (tender) versus negotiated contracts

    - Pricing forms Fixed-pricelowest clients risk

    Cost/cost-plusgreatest clients risk Reimbursement + a fee Target-price + a fee

    - Forms Standard form (clear terms and conditions)Professional services (implied terms) Supply contracts (supply of goods)Subcontract agreements

    o Domestic subcontractor (free choice by contractor)o Nominated subcontractor (stipulated by client)

    - Pro-forma contractsnear/ monopoly- Links

    Client to PM and design teamprofessional service contractsClient to main contractorClient to service authoritiesgas/ electricity/ water pro-forma contracts Client to nominated subcontractors and suppliersClient to local authority

    External non-contractual linkages

    - Authority linksclassic agency arrangement, contractual risk of consultants borne by client - Communication linkscreeping scope = uncontrolled changes,

    is the classic tendency for poorly controlled projects to gradually increase in size and content

    Advantages of external PM

    Flexible, responsive

    New ideas/approaches

    Outsource where no internal expertise

    Quick ramp-up / easy disbanding Internal risks (resources) avoided

    Disadvantages

    Expensive

    Lack of loyalty

    Difficult recourse over poor performance

    New administrative and control system

    More stringent communication and coordination systems

    Risk profile changes

    Arbitration and litigation possibility

    Complexity for PM

    3. Criteria for Selecting the Organisational Structure

    Authority (project has shorter accountability lines)

    Communication (matrix reduces barriers)

    Knowledge transfer (e.g. between function and project)

    Loyalty

    Technology/ Innovation

    Cost (pure project has lower running costs, function has large fixed costs)

    Coordination(function has formal reporting, therefore low coordination requirement)

    Support functions(pure project requires less)

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    29/59

    - 29/ -

    Function Matrix Pure project

    Workload Constant Variable Significant variance

    Project Frequency Infrequent Frequent Frequent / dominant

    Focus Functional objectives P secondary, though of significant importance Project focus

    Informal Communications Not required Acceptable

    R&D / Innovation Some High

    Centralised support Required Present Little or none

    Clear authority Required Split authority ok Devolved to PM

    Change propensity Unlikely Some HighSize Small Small to medium Large, resource intensive

    Response time Not fast Fast not generally required Fast

    Project Management Standards

    For any given industry/ profession there are three standards:

    IPMA guidelines for UK APM BoKUS PMI BoK: = standards and areas of responsibilities for PMgrs BS6079(UK)ISO10006(EU) - - - Working guidelines for PM practice, such as SPP Industry-specific (e.g. PRINCE2)- - - PRoject management IN a Controlled Environment (IT industry)

    APM and APM Body of Knowledge

    AMP Objectives:

    1st point of contact (national authority on PM)

    Lead professional development

    Champion interest representation

    Standardise qualifications

    Develop national branch network

    Establish practice and procedures for training

    APM BoK Profile4 primary areas (UK and US)

    1. Project Management Project life cycles, Project strategy, Project environments2. Organisation and people Leadership, communication and team building

    3. Techniques and procedures Planning, estimating, control, monitoring

    4. General management Finance, law

    BS6079

    Focus is standardizationE.g. different methods of planning and control measurement

    Most important section is standard strategic project plan (SPP)

    1. Preliminaries Title page, project description, contents list, introduction, names

    Control reference, Security levels for different team members

    2. Project aims and objectives Time, cost, qualityhealth and safety, environmental

    3. Subject-specific sections BS6079 proposes standard numbering Scheduling, cost control, project history, project policy, certification procedures

    Acts as both a document and benchmarkClients may use SPP (up to baseline stage) as basis for competitive bids

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    30/59

    - 30/ -

    PRINCE2

    PRoject management IN a Controlled Environment version 2Alternative to BS6079developed by Central Computer Telecommunications Agency (CCTA) in 1989 for IT PM in UK government

    Based on process model of a project

    Project breakdown into processes with key inputs/ outputs and aims/ objectives

    Driven by project business case

    Advantages

    Standard project structurestart, middle, end Regular detailed reviewsmeasured against business case and planned progress Flexible decision points

    Automatic control of deviations

    Optimises involvement of stakeholders

    Encourages communications

    For bureaucratique and IT-driven project

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    31/59

    - 31/ -

    Module 5 - Project Time Planning and Control

    5.1 The Concept of Project Time Planning and Control

    Time-planning intrinsically linked to life cycle (separate from implementation) Not staticreplanning in parallel with implementation Variancecomparison of actual with planned performancebasis of management reporting Also feedback for future projects Extrapolation allows prediction of future performancepredictive/ proactive analysis

    Aims and Objectives of the Planning Process

    Plot course from current position to end position

    Establish variance limits

    Allow contingencies and resources for divergences

    Ensure correction for divergences

    More specifically

    Consider strategic objectives

    Establish project objectives

    Compartmentalise work

    Determine interdependencies Determine resources

    Determine cost/duration/sequence of packages

    Establish communications system

    Define responsibilities, deadlines

    Set up organisational structure

    Identify critical activities

    Motivation

    Produce Strategic Project Plan

    Project Time Planning and Control and the Generic Project Plan

    SPP includes time, cost, quality and planning for:

    Organisational and authority Risk management

    Communications system

    Finance

    Conflict and stress management

    Authorisation and compliance

    Health and safety

    Change management

    Project Time Planning involves identifying, sequencing and scheduling activities and resources.

    Project Time Planning and the Project Life Cycle

    Continuous planning/ replanning throughout the life cycle but intensity varies

    Most intense in early stages

    Critical changes increase replanning

    Replanning process critical in large projects

    Becomes more complex as project progresses

    Examples of replanning reasons:

    Internal (optional) changeclient-initiated External (imposed) changee.g. supplier/subcontractor fails Sequential disruptionresource reallocation (within project) Miscalculation

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    32/59

    - 32/ -

    5.2 The Process of Project Time Planning

    Factors Affecting the Time Planning Process

    Sources of time planning data

    Knowledge, experience, environmental conditions, form of contract

    Project uniqueness

    Extent of knowledge transfer Geographical location

    Objectives

    Availability of contractors, suppliers

    Contractual conditions

    Client characteristics

    Time of year

    Local conditions, government regulations, environment

    People issues

    Stakeholder buy-in

    View as fair, reasonable and achievable

    ComplexityAnalyze components for Position in sequence

    Importance of package

    Criticality of package

    Acceptable time/cost overrun

    Resources required

    Uncertainty & Change

    Not possible to eliminate risks completely

    Not cost-effective to eliminate some risks

    Eliminating some risks may give rise to others

    Difficult to assess some risks

    Relative importance may change over time

    Accuracy & Reliability

    Unfamiliarity with software

    Misguided assumptions

    Insufficient data

    Incomplete understanding of implications and linkages

    Communication

    Software promotes tendency to issue too much information

    The Planning Process

    1. Statement of Work (SOW)2. Work breakdown structure (WBS)3. Project Logic Evaluation (PLE)4. Separate time, cost, quality planning5. Network analysis (CPM, PERT)to generate DMS6. Trade-off analysis to replan7. Project Master Schedule (PMS)

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    33/59

    - 33/ -

    Statement of Workdefines overall content and limits of work; all required information for tender/bid Signature block, project title

    Terms and scope

    Information/ facilities provided by client

    Approval requirements

    Payment terms

    Working drawings

    Specification, schedules

    General and specific conditions Variations procedures

    Dispute resolution

    Bonds/ insurance

    Work Breakdown Structure

    Purpose

    - Improve accuracy of estimates

    - Define baseline for performance measurement and control

    - Identify tasks and responsibilities

    Levels of definition (typically six)

    Logical numbering system

    - Align with Cost Accounting Codes (CAC) in use

    - Typically generated by Computerised Database Estimating System (CDES)

    Dividing the WBS

    - Work type

    - Responsibility

    - Location

    Project Logic Evaluation (PLE)

    Define sequence of individual packages

    - Resource driven

    - Logic driven Sequential, parallel

    - Precedence diagrams with resource sheet

    Draft Master Schedule (DMS)

    Purposes & uses

    - Project completion date

    - Supply order/delivery dates

    - Subcontractor notification dates

    - Milestones for progress planning

    - Risk management system

    - Logic incompatibilities

    - Contractual compatibilities

    - Basis for Replanning & trade-off analysis, Resource levelling , Earned value analysis

    Critical Path Method (CPM)deterministic Program Evaluation and Review Technique (PERT)probabilistic Gantt Charts Network Diagrams (precedence diagram with activity durations)

    - Activity on arc (AOA)Activities shown as arcs Events shown as nodes (circles) with duration Dummy activities required represent dependencies (shown as broken line)

    - Activity on node (AON)Activities as nodes (boxes) Temporal relationship dependent on placement of arrow end-points

    Finish to start (most common, simplest)

    Finish to finish

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    34/59

    - 34/ -

    Start to start

    Start to finish

    Critical Path Method (CPM)DuPont 1960- Assign durations for each activity

    Modular technique (decompose activities) Benchmark technique (recorded time for similar works) Modelling technique (generate formula/model from previous activities) Computerised Database Estimating System (CDES) technique Parametric technique (dependent/independent variables e.g. time& length of digging tunn

    - Identify start & finish window for each activity Forward pass: Identify Earliest Event Times (EET)

    Earliest Start time (EST)

    Earliest Finish time (EFT) Backward pass: Identify Latest Event time (LET)

    - Critical path (no float window i.e. EET=LET)

    - Replan/ Rationalise resources Import new activities Decrease work (cut corners) Reshuffle resources Re-evaluate sequence Increase workload Overlap phases Speed up approvals Smooth resource utilisation Prioritise activities (allocate resources to critical path)

    - Form Draft Master Schedule (DMS)

    - Refine into Project Master Schedule (PMS)

    Program Evaluation and Review Technique (PERT)

    - Assign three durations to each activityoptimistic, most likely, pessimistic

    - Calculate mean duration and standard deviation for each activity (Beta distribution)

    Activity Duration (Beta Average): T = (a + 4m + b) a = optimistic time

    6 m = most likely time

    Activity Standard Deviation: s = (b a) b = pessimistic time

    6

    - Forward/ Backward pass, CP

    - Calculate project mean duration and standard deviation

    Project Mean Duration: TCPProject Standard Deviation: (SCP)2

    - Identify target completion date and calculate variance about target (Normal distribution)

    Nb. of standard deviations between Project Mean Duration and Target Duration (client-reques

    Project Mean Difference = PMDTarget Project Duration

    Standardised Mean Difference = PMDiffPSD

    Event within 1 standard deviation of the Mean ~ 68% of meeting deadlineEvent within 1 standard deviation above Average mean ~ 84% (50%+68% of 50%)

    Event within 1 standard deviation bellow Average mean ~ 16% (50% 68% of 50%)

    Event within 2 standard deviation ~ 95%Event within 3 standard deviation ~ 99%

    - Replan/ Rationalise resources

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    35/59

    - 35/ -

    - DMS

    - PMS

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    36/59

    - 36/ -

    5.3 Project Replanning

    Quality = performance in following sections. Elsewhere it may refer to specific measurable aspect of quality

    Crash analysishow much can project be accelerated and at what cost?

    Crash Analysis

    Trade-off between time and cost. Assumes Quality is fixed.

    Process:1. Define project logic2. Add duration to each activity3. Establish critical path4. Calculate crash cost per activity5. Calculate crash cost per unit time6. Determine most cost-effective crash sequence7. Check critical path8. Crash network to limit

    - Optimum cost point (starting point) --- additional time beyond this will accrue fixed overhead

    - First crash point (using cheapest critical path component to crash)

    - Maximum crash point

    5.4 Trade-off Analysis

    Methodology for Trade-off Analysis

    1. Identify the reason for the problem2. Reevaluate the project objectives3. Allow for any other relevant factors4. Assemble a shortlist of solutions scenarios5. Select and test the best (or approved) alternative6. Implement the best alternative

    1. Identify reason for problem Pre-execution trade-offs (during DMS)

    - Change in client requirements; strategic objectives

    - Design incompatibilities

    - Subcontractors/ suppliers/ external consultants changes

    - Misunderstandings/ miscommunications

    Execution trade-offs

    - Client requirements

    - Human error

    - Execution problems

    - Emerging risk

    - Project-specific

    2. Re-evaluate project objectives Competitor behaviour, customer demand, economy, technology, legislation

    3. Allow for other relevant factors

    Strategic and/or operational

    4. Shortlist solutions

    5. Select and test the best alternative

    6. Implement

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    37/59

    - 37/ -

    Trade-off Classification

    Type 1: Time is fixedType 2: Cost is fixedType 3: Performance is fixed

    Type 4: Time & Cost are fixed

    Type 5: Time & Performance are fixedType 6: Cost & Performance are fixed

    Type 7: Everything is fixed

    - Unusual; typically in small, simple projects

    - Unlikely change

    Type 8: Nothing is fixed

    - Also unusual

    - Emergency works

    - Stop-lossing (fulfill contractual obligations as soon as possible)

    -

    5.5 Resource Scheduling

    Seven types of resources:1. People

    2. Materials3. Equipment4. Funds5. Information6. Technology7. Space

    Considerations:

    Resource productivityProject productivity not a simple sum of individual productivity Resource availability

    Resource Aggregationis a way of estimating the total resource requirements on an ongoing basis throughout the life cycle of the project

    Large variations may lead to periodic idle time if resources cannot be easily redeployed

    Resource Utilisation (Efficiency)

    Resource Utilisation = # of person days worked on project t# of person days available for project

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    38/59

    - 38/ -

    Resource Levelling (or Resource Smoothing)

    Levelling out peaks and troughs in resource demand so that utilisation approaches an average

    Depends on:

    Flexibility of completion date

    Availability of resources

    Benefits:

    Reduced peaks in demand means fewer people on project at any one time reduces coordination and control Individuals work for longer period of timeBenefits in team dvpt & learning curve Reduced float times lead to greater continuity

    Reduce overall time subcontractors are required

    5.6 Project Planning Software

    Advantages of Computer-based Project Planning and Control

    Speed

    Cost

    Capacity

    Reliability

    Combined analysis (e.g. simultaneous planning for time and cost)

    Disadvantages of Computer-Based Project Planning and Control

    Relianceprotected and backup Over-emphasis on time-consuming detail

    Information dump

    Potential misdirectionExcessive trust in well-presented material if based on erroneous data

    General Factors for Consideration

    Lead-in timeimplementation time of the software Transition

    Training Software Updates

    Networking CMS, security and access implications Wider compatibilityin linking the configuration management system to external consultants/ contractors/ suppliers

    Critical success factors

    Usableuser-friendly Familiar displays

    CMS compatibility

    Extendable

    General Features of Project Planning and Control Software Systems

    Project planningAutomaticGantt charts, network diagrams, critical path analysis Resource managementresource loading, conflicts, costs, budgets, forecasts Tracking and monitoringcompared to baseline Report generationstatus, budget, cash flow, resources, schedules Analysis and decision aidingwhat-if analysis, at least straightforward analysis

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    39/59

    - 39/ -

    Common Commercial Project Planning and Control Software

    High-end

    Power Project Professional

    Primavera Project Planner

    Artemis Views

    Open Plan

    Cobra

    Enterprise PM Micro Planner X-Pert

    Mid-range(up to 2000 tasks)

    Microsoft Project

    Micro-Planner Manager

    Primavera Suretrak

    Low-end (less than 100)

    Milestone Simplicity

    Project Vision

    Quick Gantt

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    40/59

    - 40/ -

    Module 6 - Project Cost Planning and Control

    6.2 Project Cost Planning and Control Systems

    Cost planning Breaking down project into elements WBS, assigning realistic estimate of cost and rolling up costsStrategic, establishes aims & objectives before

    Cost control Ensuring adherence to cost limits set by cost planningTactical, reactive

    Monitoring expenditures Identifying variances Determining reasons for variance Corrective action Monitoring to ensure resolution Taking further corrective action if necessary

    Cost Planning and Control as a Concept

    Target costs identified by account code systemNo direct time measurement but time does affect costCost variances from internal sources easier to control than from external sources

    General requirements

    Project schedule must be accurate

    Estimating system must be reliableTypically electronic estimating system, some still use price books

    Clear project scopeunambiguous, non-overlapping tasks

    Realistic budgetfair and reasonable

    Clear authorisation systemmulti-layer approvals filter

    Flexible and responsive system variation orders (EU) = change notices (US)

    Reliable approach to tracking varianceCDES

    Time-dependent variance sensitivitydiminishes over time

    Flexible use of reserves and contingencies

    Types of Control System: 1. Cybernetic 2. Analogue 3. Feedback

    Cybernetic

    Most common approach Automatic response mechanism= its key feature

    Used by animals and some plants to make decisions

    Set of inputs establish context

    Outputs subject to monitoring system

    Bounded rationality(see page 17)approach to information processing i.e. analysis

    Multi-level cybernetic control

    - Low-level: e.g. shower control with temperature sensor, instrument controls, animals Most cost-control systems Detecting time and cost variances Adjusting likely final time/cost estimates Re-programming schedule change

    - Mid-level: greater flexibility, complexity; automobile engine management Adjusting estimates for individual cost rates Establishing cost of change notices Releasing contingency sums

    - High-level: introduces intelligence, memory, experience, original thought Tactical solutions to programming problems Updating risk profile Developing negotiation strategy For controlling overall project performance

    - Human mind operates at all three levels

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    41/59

    - 41/ -

    Analogue

    Appropriate for smaller elements/packages

    Series of yes/no questions elimination process

    - Basis of human reasoning process

    - Eliminate unfeasible solutions and break feasible solutions into subsections

    Every aspectdetermine if preconditions met For rigid time, cost, performance limits

    Feedback control Post-project evaluation and feedback to future projects

    Cybernetic are automatic and therefore continuous; Analogue are invoked as neededCybernetic and analogue for ongoing use. Feedback applied after project completion

    Costs and Allowances

    Classification:

    Fixed and variable costsdepends on the level of project activity

    Direct and indirect costs

    Factory coststotal fixed/variable costs without any mark-up for profit Measured worksindividual and unit prices

    Contingencies and reserveempirically calculated, 10% or more

    Fluctuationsinflation

    Prime cost(pass-through)and provisional sums(foreseen but undefined work)

    Direct payments(local authorities or utilities)

    Bonds and warranties

    Exchange rates and currency fluctuations

    Insurance

    Life Cycle Costs

    Life-cycle costing (LCC)

    Considers long-term implications of early design decisions

    Typical Life-Cycle Phases

    - Inception

    - Feasibility

    - Detailed development

    - Production

    - Project termination, system operation, maintenance

    - System divestment

    Additional (optional) phases and costs

    - Research and development

    - Prototype

    - Design

    - Production

    - Commissioning

    - Operation

    - Maintenance

    - Decommissioningrunning the project down prior to recycling

    - Product retirement, phase-outdemolition, dismantling, decontamination, recycling

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    42/59

    - 42/ -

    LCC Process

    - Establish life-cycle characteristics

    - Build process cost model

    - Calibrate model (benchmark with standard)accurately measuring what is supposed to be measured

    - Input relevant data

    - Generate LCC and define strategybalance between long-term and project ramp-up

    LCC Advantages

    - Long-range considerations

    - Life-cycle viability

    - Strategic decision making

    - Future awareness

    - Market position

    - Compliance/ regulation

    LCC Disadvantages

    - Prediction accuracyinvalid assumptions

    - CostFull LCC is expensive

    - Sensitivityto change may produce inaccuracy

    - Competitionin case of unbalanced analysis

    - Riskimplications of inaccuracy

    6.3 The Project Cost Control System

    Two cycles1. Cost planning cycle - Phase 12. Cost control cycle

    - Phase 2: Work initiation

    - Phase 3: Cost data collection

    - Phase 4: Variance generation

    - Phase 5: Cost reporting

    The PCCS Planning Cycle

    Estimating procedure Professional estimator

    - Trained, experienced, unbiased, no loyalty

    Project team

    - Estimators are responsible

    - on the ground, best knowledge of resources and requirements - Aware of system limitations

    - Can confer, negotiate on resources

    - May cost low to win or high to succeed

    - Greater risk making mistake or over-optimistic estimates

    Other considerations

    - Project success criteria consistent with estimating assumptions

    - Project linkagessynergies

    - Standardised approachleverage central data and systems

    - Feedback

    Estimating elements

    Labour

    Materials

    Plant

    Also many others, e.g.

    Fuel

    Maintenance

    waste

    = Operating Cycle

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    43/59

    - 43/ -

    Additional considerations for materials and equipment

    Packaging and shipping costs (also insurance, duties) Availability (may need to pre-order or find alternate source)

    Detailed specifications may not be available on first issue of estimate

    Data gathering

    Standard tables

    Company-specific tables

    Previous project data Estimator skill and knowledge; estimator categories (increasingly dangerous):

    - Accurate

    - Pessimistic

    - Optimistic

    - Inconsistent

    Presenting the Estimate

    The order-of-magnitude estimate feasibility assessment

    Indicative estimate based on known information and published data

    Definitive estimate

    Project Estimating

    Top-down- Strategic alignment

    - More stable/static

    - Less local influence and bias

    - Executive commitmentBut:

    - Senior management disconnect from operational costs

    - Team may feel budget is unrealistic => reduced motivation

    - Politics

    Bottom-up

    - More team commitment if people own decisionBut:

    - Less status

    - Difficult to adapt to strategic changes

    - Easily overridden by senior management

    - Tendency to over-estimate

    Iterative [based on negotiation](interactive between task managers [operational]and senior managers [strategic])

    - Prepared by operational manager

    - Aligned to strategic objectives

    - Maintains market influenceBut:

    - Timely and costly negotiation

    - Requires control procedures

    - Dependency on negotiation skill of operational manager (more important than estimating skill)

    Bidding strategy and Estimate reporting1. Formulate estimating strategy2. ROM estimates3. Carry out preliminary refinement4. Indicative estimate5. Add for profit and risk6. Compare to cost limit7. Subjective evaluation of bid success probability8. Final/definitive estimatefinal or baseline budget plan

    Consider difference between type x acquisitions (one-off with no follow-on) and type y acquisitions (follow-on likely)

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    44/59

    - 44/ -

    Computerised Database Estimating System (CDES)

    Scan or digitise quantity information directly from drawings

    Description librarycollection of standard descriptions (arranged in same format as WBS) Price codes and unit rates

    Other database elements

    - Digitised drawings

    - Bill preparation systems Bill with tender, bill with estimated prices budget plan

    Project Budget Plan

    Perceived as the most important performance indicator

    Standard Method of Measurement (SMM)standard form to measure and quantify costs- How to measure work

    - What descriptions to use

    - What to include/exclude

    - Units of measurement

    - Assembly into bill of quantities for tenderer

    Role of project budget

    Forecast costs to particular project tasks

    Budget baseline

    Projected cost curves (for each element) Reference for variance analysis

    Moderation of spending

    Data for trade-off analysis

    Estimate effects of change notices

    Psychological effects (motivation, demotivation)

    Budget Development and Layout

    Objectives and activities measurable outputs

    Financial resources allocated

    Start/finish points of each activity

    Facility to compare actual and planned performance

    Preliminary items general project overheads

    Prime cost sumswork is sublet to nominated subcontractor

    Provisional sumsexact extend of works in not known (e.g. excavation)

    Direct Paymentspayments made through project but not to project team

    Dayworksunforeseen and unmeasurable works (e.g. specialist to debug software)

    Measured worksphysically measured from specifications

    Contingencies, fees and taxes

    Budget changes

    Transparency importantvisibility of original budget, all changes, current budget

    Change control system (CCS)monitors all changes and predicts implications before authorising

    Cost account variation notice (CAVN) formalised process using CMS (for large projects)

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    45/59

    - 45/ -

    The PCCS Operating Cycle= cost & control system

    Phase 2: Work initiationPhase 3: Cost data collectionPhase 4: Variance generationPhase 5: Cost reporting

    Phase 2: Work initiation

    Controlled release of work: Project works order (PWO)

    Variation Order (VO)

    Describe work, standards, cost-centre to charge

    Phase 3: Cost data collection

    Earned Value analysis (EVA) required by APM, PMI, ISO10006, BS6079

    End result is generation of cost variance and schedule variance

    - Basis for evaluating performance and, if necessary, corrective action

    Milestone monitoring

    - Milestonedefinitive stage in the project, appropriate point to measure performance

    - Most suitable when plans not very detailed

    - Disadvantages Reaction time lagintervals too great Residual accumulated overspendin case of late detection Replanning issuesmilestones rescheduled easily Time scale issues do not allow for work in progress

    - Earned Value Analysis (EVA) Dynamic Combined time/performance assessment Frequent reporting Demonstrates value as well as cost Accurate assessment of cost implications of delays Easier trade-off analysis

    Earned Value Analysis

    Earned Value = cost of work originally estimated

    Cost variance = difference between budgeted cost and actual cost of works

    - Measurable effortseparate elements within defined schedule with tangible results- Support effortproject actions difficult to quantify (Project support, administrative services)

    Variance analysis

    - Identify / validate variance

    - Quantify variance

    - Determine source

    - Determine impact on project

    - Determine impact on other elements

    - Determine extent of ongoing tactical response

    - Determine range of possible outcomes of corrective actions

    = Operating Cycle

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    46/59

    - 46/ -

    Earned Value Analysis variables

    - Actual Cost of Works Performed (ACWP)

    - Budgeted Cost of Works Performed (BCWP) = Actual earned value

    - Budgeted Cost of Works Scheduled (BCWS) = Planned earned value

    - Scheduled Time for Work Performed (STWP)

    - Actual Time for Work Performed (ATWP)

    - Cost Variance (CV) CV = BCWPACWP

    - Schedule Variance (SV) SV = BCWPBCWS

    - Time Variance (TV) TV = STWPATWP

    - Budget At Completion (BAC) BAC = BCWS = project baseline

    - Estimate To Complete (ETC)

    - Estimate At Completion (EAC) EAC = ACWP + ETC = planned estimate approach

    EAC =BACCV

    EAC = x BAC = current estimate approach

    - Variance At Completion (VAC) VAC = BACEAC

    - Cost Variance Index CVI =

    - Schedule Variance Index SVI =

    - Time Variance Index TVI =

    Multi-level Earned Value Analysis

    - Allows roll-up analysis

    - Diagnostic analysis

    Phase 4: Generation of Variances

    Variance and Variance envelope

    Earned Value AnalysisEarned Valuecost of work originally estimated

    Alarm system:

    Critical Ratio = x = x

    Zone A: take no action eg. 0.901.00

    Zone B: record and monitor eg. 0.750.90

    Zone C: Act immediately eg. 0.600.75

    Zone D: Emergency response required eg. 0.500.60

    Zone A1: Observe and note eg. 1.001.25

    Zone A2: Investigate and correct(excessively pessimistic estimating or other errors)

    BCWP

    ACWP

    BCWP

    BCWS

    STWP

    ATWP

    ACWP

    BCWP

    actual progress

    scheduled progress

    budget cost

    actual cost

    AP

    SP

    BC

    AC

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    47/59

    - 47/ -

    Phase 5: Cost reporting

    Report guidelines

    - Punctual reporting

    - Include only relevant information

    - Highlight important information

    - Allow interrelationships

    - Honest and accurate

    - Issued to everybody involved

    - Where appropriate Propose solutions Clarify responsibilities & time scales

    Basic report types

    - Routine reports Cost, schedule, quality, risk

    - Development review reports Common for R&D Assessment of progress in relation to success criteria

    - Exception reports

    Issued to highlight anomalies Initial report highlights exception Subsequent reports describe progress of corrective actions (audit trail)

    - Subject-specific reports Monitor and control areas of concernhigh impact high probability risks (M3)

    - Project variance and analysis reports (PVAR)

    Project Variance Analysis Reporting (PVAR)

    - Common reporting tool for EVA

    - Shows variance (and all EVA metrics) for whole project and all 6 levels of WBS

    - For each cost centre WBS identifiers CAC identifiers and budget limits Current metricsACWP, BCWP, BCWS, CV, SV, BAC, EAC, ETC and VAC figures Previous (Month) metrics YTD metrics Differences between current and previous metrics Summary of significant differences Current EAC, ETC, ECTC, ETTC May show graphic curves in appendix Can calculate

    Earned value

    Earned value hours

    Anticipated final hours

    Project efficiency

    Project progress

    Level 1: The programme2: The project3: The element4: The sub-elemen

    5: The work packag6: The wp. compon

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    48/59

    - 48/ -

    Module 7 - Project Quality Management

    Projects non-repetitive therefore standard sampling techniques for batch production are insufficient

    7.2 Quality Management as a Concept

    Through 1960s low-cost was the primary priority in protected economies1970s the Japanese entered market at higher-quality and equal or better costQuality control standards (BS5750, ISO9000, BS6079, ISO10006) give equal importance to quality as to time and cos

    The Traditional Japanese View

    Overall value of quality

    - Curvilinear relationship to cost linear at some range but asymptotic at ultra-high-quality

    - Must be balanced with cost of defects which can be also addressed through warranties Not always an option (high-speed tyre blow-out)

    - Apparent value of quality what people will pay for a good-quality product- True value of quality also includes premium based on prestige/goodwill or reputation for reliability/quality

    - Overall value = apparent value + true value

    Overall cost of defects

    - True cost of a defect greater than apparent cost of fixing it

    - Loss of customers (churn)

    - Bad reputation

    - Overall cost = apparent cost + true cost

    Quality dividends

    - Employee motivation, company status and image

    - Better productivity

    - Industry respect/relations

    - Prospects in M&A, partnerships and alliances

    - Share price, risk profile- True payback = overall benefitimplementation costs

    Involving people

    - Japanese culture linked employee interest with company

    - Motivated employees to proactively ensure quality without expensive quality control systems

    Proactive planning

    - Preventive rather than responsive action

    - Cheaper and more effective quality systemsmove upstream/ more attention to pdt dvpt

    - Difficult / expensive for Western companies to emulate

    Involving whole organisation- Extended to non-production activities (sales, marketing, R&D)TQM

    Educating customer to expect quality

    - Differentiation in a competitive market

    Quality Standards

    2000 BCEgyptian quality control for funeral goods; imprint from government inspector1963: US Military standard MIL-Q-9858A

    1974: UK standard BS5179BS5750 first major UK Quality Management standardNow superseded by ISO 9000**

    ISO9000: Quality Management and Quality Assurance StandardsGuidelines for Selection and UseISO9001: Quality SystemsModel for Quality Assurance in Design, Development, Production, Installation and ServicingISO9002: Quality SystemsModel for Quality Assurance in Production and InstallationISO9003: Quality SystemsModel for Quality Assurance in Final Inspection and TestISO9004: Quality Management and Quality System ElementsGuidelines

    Main drawbacks:

    Bureaucratic

    Measures performance at one point in time

    Attempts generic measure across countries with different standards, process and cultures

    *** Superseded by ISO 9001:2008

  • 7/26/2019 1.RMJJ ProjectManagementNotes June2010 59

    49/59

    - 49/ -

    ISO9000 Twenty main parts:1. Management responsibility and quality policy2. Quality system3. Contract review4. Design control5. Document control6. Purchasing7. Purchaser-supplied product

    8. Product identification and traceability9. Process control10. Inspection and testing11. Inspection measuring and test equipment12. Inspection and test status13. Control of non-conforming products14. Corrective action15. Handling, storage, packing and delivery16. Quality records17. Internal quality audits18. Training19. Servicing20. Statistical techniques

    7.3 The Quality Gurus

    Common agreement:1. Quality pro