Upload
shan4600
View
2
Download
0
Tags:
Embed Size (px)
DESCRIPTION
wind
Citation preview
Wind Energy Basics & Project Cycle
1.800.580.3765 ▪ WWW.TTECI.COM
Wind Energy Basics & Project Cycle
Pramod Jain, Ph.D.Presented to:
DFCC Bank and RERED Consortia MembersJanuary 26– 27, 2011 | Colombo, Sri Lanka
Agenda
Basics of Wind Energy• Energy … Blowing in the wind• Renewable• Advantages• Growth
What is life cycle of a wind project?• Steps• Timeframe• Cost• Funding requirements
Wind energy versus other methods of generating electricity
2/4/2011 3
Module Objectives
Learning Objectives• Understand basics of wind energy. What factors influence amount of
energy produced?• Understand basics of wind turbine generator (WTG). What are the major
components of WTG? What are the new developments?• What are the steps in a wind project lifecycle?• What are the timelines, activities and deliverables?
2/4/2011 4
Basics of Wind Energy: Energy is blowing in the wind
Wind is a form of solar energy
Uneven heating of earth
Heating of ground versus water
Source: http://www.physicalgeography.net/fundamentals/7o.html2/4/2011 5
Basics of Wind Energy
Power in wind = ½ A v3
= ½ r2 v3
Units of Power: kilo-Watts, mega-Watts, giga-Watts
Energy = Power * Time Units of energy: kilo-Watt
Hours (kWh), MWh, GWh
0
1000
2000
3000
4000
5000
6000
7000
0 2 4 6 8 10 12 14 16
Power in
Watts
Wind Speed, m/s
0
50
100
150
200
250
300
350
400
450
0 5 10 15 20
Power in
KW
Radius of a HAWT in meters
Turbine of rotor radius = 1 m
Wind speed = 8 m/s
Source: P. Jain, Wind Energy Engineering, 20102/4/2011 6
Basics of Wind Energy Wind speed vs. elevation above
ground level Density vs. height above sea level
• 2% at 200m• 17.8% at 2000m
Density as a function of humidity• 0.6% at 100% relative humidity
Power Production Curve of Turbine
Source: P. Jain, Wind Energy Engineering, 2010
• The power of the wind is converted according to the power curve (red curve)
• The Ce curve (green curve) gives the conversion ratio. How much the wind energy is converted to electricity
2/4/2011 7
Basics of Wind Turbines
1. Pitch drives. 2. Rotor that connects blades to main shaft. 3. Main shaft. 4. Main bearing. 5. Gearbox. 6. Yaw drive. 7. Disk brakes. 8. Brake hydraulic system. 9. Generator. 10. Main hydraulic system. 11. Nacelle frame. 12. Yaw brakes.
Source: P. Jain, Wind Energy Engineering, 20102/4/2011 8
Three types of generators Double Fed Induction Generator
• Gearbox to increase speed of generator rotor
• Generator is smaller in size but high speed
• Optimal energy capture in a narrow wind speed range
Direct Drive Synchronous Generator
• No gearbox• Generator size is large in size,
but lower speed• Optimal energy capture in a
bigger wind speed range
Basics of Generators and Electrical Grid
Direct Drive Permanent Magnet• No gearbox• Generator size is large in size but lower
speed• Optimal energy capture in a bigger wind
speed range• Full power conversion
Source: P. Jain, Wind Energy Engineering, 2010 & http://greenpoweroregon.com/Images/WindDiagram_Lg.gif2/4/2011 9
Advantages of Wind Energy
No fuel costs No variability in cost of
energy production, other than O&M costs
Revenue to local land owners with out substantially altering land use
Boost to the local economy during construction and through out life of project
Boost to infrastructure
Zero emissions Zero water use Zero mining of fuels Zero transportation of
fuels Clean energy 90 to 95% of land can
be used for the original purpose
Wind-hydro hybrid can provide a powerful combination for year-round energy production
Wind-diesel hybrid can provide reliable power to remote areas
2/4/2011 10
Disadvantages of Wind Power
Intermittent energy production: Electricity is produced only when wind is blowing
There is still need for traditional power plants (hydro or fossil fuel-based) to provide base-load
Wind energy replaces “peaking” units or “spinning reserves”
High capital investment Incentives are required for
investors, but not much different compared to other sources
New transmission lines may be needed from remote areas to cities
Large foot print of wind farms. • In interior areas, 30 to 60 acres per
MW• In coastal areas with single row of
turbines, 2 to 5 acres per MW• Note most of land can be used for
other purposes Birds/bat fatalities Visual impact Noise, and others High levels of wind energy (>30%) in
grid may require variety of upgrades to the entire electricity network
2/4/2011 11
QUESTIONS?Questions?
2/4/2011 12
Wind Power: Incredible Growth
2/4/2011 13
Wind Power: Incredible Growth
2/4/2011 14
Wind Power: By Country
2/4/2011 15
Wind Power Penetration: By Country
2/4/2011 16
Wind Project Life Cycle
Prospecting Wind Resource Assessment
Siting: Permits, EIA,
Interconnection
PPAFinancing
EngineeringProcurementContracting
Construction Installation
Commissioning
Operations & Maintenance
17 Pramod Jain; Sept. 22, 2010
3 months to evaluate multiple sites
5 Criteria: Wind, env.grid, cost, rev
At least 15 months. 2 to 3 yrs for large wind farms
Locale specific: 6 to 12 months
Locale specific: 3 mos
Locale specific: 3 to 24 mosTurbine Cost=$1000-1400 /kW
Faster than1 turbine/moCost=$300-400/kW, includes BOP
Ongoing$40/KW per year
Development: 4 steps. 18 to 36 mos. Cost= $10 to $20 per kW*
*For large projects of size > 20MW. Does not include financing costs (range: $50- $100/kW)
2/4/2011
Prospecting
Goal: Identify a handful of areas that have a good wind resource Compute wind speed and wind energy estimates based on publicly
available wind data: Airport, NCAR, Weather stations Tools: RetScreen Energy estimate: +/- 50% Other factors in site selection: Grid connection, buyer, construction
cost, environmental factors 3 months … $5 to 10K After site(s) have been selected, Obtain site control through leases
2/4/2011 18
Wind Resource Assessment
Goal: Quantify wind resources Measure wind speed. Compute wind energy estimates based on at
least one year of measurement and long-term reference data Tools: WindPRO, Wind Farmer Energy estimate: +/- 15% 15 to 36 months Cost: $10 to 15K per MW
2/4/2011 19
Siting: Permitting, EIA, Interconnection
Environmental Impact Assessment• Wildlife: Migratory birds &
bats, local birds & bats and terrestrial wildlife
• Water resources and wetlands• Neighboring communities:
Noise, shadow flicker, viewshed
Permits• Power producer• Construction & Transportation• Zoning• Environmental
Others:• Long-range radar interference• Telecommunications
interference• Obstruction to aviation
Interconnection• Agreement to connect to the
grid• Agreement on the quality of
power
2/4/2011 20
PPA, Financing
PPA• Agreement with buyer of energy about price of energy and conditions for
purchase• In most cases, this is a standard Power purchase agreement
Preliminary Project Design & Engineering• Prepare maps and survey• Design layout of turbines, access roads, storage areas, substation, local
office and transmission lines. Financing
• Create a project financing package for presentation to investors• Negotiate terms with tax-equity investors, other equity investors and lenders
212/4/2011
Engineering, Procurement and Contracting
EPC or turnkey contracts are the most common contract; components are:• Prespecified delivery timeframe and cost• Prespecified level of production and quality
Project Engineering• Layout, civil engineering of infrastructure• Foundation design• Electrical design• Logistics planning and design
Procurement of turbines• Wind condition and locale specific
222/4/2011
Construction, Installation and Commissioning
Transportation• May be a significant challenge,
depends on location: Bridges, roads, ports, hauling equipment
Construction & Installation• Infrastructure• Site preparation• Foundation construction• Turbine Erection• Collection system and substation
construction
Commissioning• Objective: Ensure wind plant is
safe to operate, produces energy in a reliable manner and acceptable quality
• List of outstanding issues• 95% availability during 250
hours of continuous operation• End result: Handover of project
from contractor to owner
2/4/2011 23
Video of installation of wind turbine
http://www.youtube.com/watch?v=ODTl3ST-_WI&feature=player_embedded#!
http://www.youtube.com/watch?v=iJ89Aw3Y86Q&feature=related http://www.youtube.com/watch?v=PyehD1j0kUU&feature=related
242/4/2011
Operations and Maintenance
Maximize energy production Minimize operations and maintenance costs Manage day-to-day tasks
Three models: Owner managed O&M Third-party managed O&M Turbine manufacturer managed O&M
252/4/2011
QUESTIONS?Questions?
2/4/2011 26
What is different about wind energy?
Transport raw material
Proximity to load
Capacity factor
Scale Variability of resource
Coal, Nuclear, Gas, Diesel
Yes Yes 90+% C/N: Large500MW+
G/D: Med/Low
Significant cost variability
Hydro No No Variable Variable Depends on rain
Wind No No 30 to 50% Variable High diurnaland seasonal
Solar No/Don’t have to
Yes 15 to 22% Small to medium Medium diurnal and seasonal
Geo‐thermal No No 90+% Large to medium Little
2/4/2011
Energy Generation Cost Comparison, 2008
0
20
40
60
80
100
120
6.00
6.25
6.50
6.75
7.00
7.25
7.50
7.75
8.00
8.25
8.50
8.75
9.00
9.25
9.50
9.75
10.00
Gen
eration cost Euros/M
Wh
Wind Speed m/s
Onshore installed cost 1300€/KW
Onshore installed cost 1700€/KW
0
20
40
60
80
100
120
Coal Nuclear Gas
Lowest price CO2 cost RangeSource: Wind Power Monthly, January 2009
2/4/2011 28
Energy Generation Installed Cost, 2008
Source: Wind Power Monthly, January 2009
Technology Installed Cost €/kW
Fuel Price €/MWh
O&M Cost €/kW
Gas‐fired 635‐875 US: 16 19‐30EU: 27
Coal‐fired 1,300‐2,325 US: 12 30‐60EU: 18
Nuclear 1,950‐3,400 3.6‐5.5 80‐96
Onshore wind 1,300‐1,500 N/A 33‐50Offshore wind 3,000 N/A 70
Global onshore wind total installed costs: $1,600 to $2,210, based on 3,600MW projects in 2008.Caveat: These prices are for large projects (possibly > 20MW)
2/4/2011 29
Levelized Cost of Energy
Excludes cost of transmission and integration. Excludes PTC.USA has 8,000 GW of power at $0.085/KWh or less. Source: NREL 20% Wind by 2030.
2/4/2011 30
Cost of New Generation
2/4/2011 31
Utility Scale versus Small Scale
Installed costs: $2/W
Taller structures, capture higher wind speed
Lesser turbulence In wind farms the scale of
energy production justifies dedicated O&M team resulting in higher production
Installed costs: $5 to $10 per Watt
Shorter structures, wind speed is lower
Higher turbulence due to surface roughness
No dedicated O&M team, higher chances of long downtime
Roof-top and other types of small turbines are usually not financially viable
2/4/2011 32
Conclusions
In most countries wind energy is the fastest growing new source of electrical energy
Wind projects cost about $1500 to $2000 per kW Timeframe for wind projects is 24 to 36 months Wind project lifecycle has a large number of steps Attention to details and rigorous due diligence during development
phase can mitigate risk of delays and cost overruns
2/4/2011 33