CONSTRUCTION OF A NEW KESC SUB-STATION AND RELOCATION OF FOUR
GENERATORS AT THE CITY CAMPUS
MINUTES OF MEETING
PROGRESS REVIEW MEETING NO: 13
Progress Review meeting was held to discuss the Progress of Works & other Contractual
matter at the NESPAKs Site Office, IBA City Campus on January 19 , 2012 at 10:00 a.m.
with the following participants.
Participants:-
IBA (Client)
1. Mr. Shakil Anwer Project Engineer
2. Mr. Jawad khan Electrical Engineer
3. Mr. Nazir Ali Naeem Supervisor (Civil)
NESPAK (Project Manager)
1. Mr. Syed Mehdi Hassan Resident Engineer (RE)
2. Mr. Ch. M.Arif Inspector (Civil)
3. Mr. Muhmmad Irfan Inspector (Electrical)
M/s SIEMENS (Contractor)
1.2.
Mr. Muhammad YasirMr. Jahangir Khan
Project ManagerSite Engineer
2. Mr. Syed Furqan Executive Engineer
3. Mr. Akber Ismail P.M (KF Corp.)
Following points were discussed:
DESCRIPTIONACTION BY
1. Work Schedule:
- RE-NESPAK asked the PM-Siemens regarding
the submission of weekly work Program.
8/2/2019 17-Kesc-prm _ 13 Minutes
2/5
2
- PM-Siemens Confirmed that the weekly work
program for last & current weeks are submitted
to NESPAK site office for monitoring the
progress.
- RE-NESPAK showed his dissatisfaction over thecurrent weekly work program indicating only 30%
progress of Columns up to roof beam and also
other activities of next week. He advised to PM-
Siemens to enhance the man power & material &
complete the mentioned activities in max. one
week time. Otherwise work will be delayed.
- PM-Siemens agreed on it & committed to
achieve the target.
Contractor-Siemens
2. Material / Manufacturer:
- RE-NESPAK asked the PM-Siemens about the
Siemens reply on NESPAK comments on the
submittal of HV Switchgear for further necessary
action & also to avoid any further delay in
manufacturing.
- Executive Engineer-Siemens stated that he
replied on HV Switchgear, yesterday January
18, 2012 through e-mail.
- RE-NESPAK advised to SIEMENS to submits all
necessary documents through hard copies
instead of e-mail.
- Executive Engineer-Siemens agree on it.Contractor-Siemens
8/2/2019 17-Kesc-prm _ 13 Minutes
3/5
3
3. Generator Yard:
Approval of route for Rerouting of Cables:
- PM-Siemens requested to Project Engineer-IBA
regarding the formal approval for rerouting work.
- Project Engineer-IBA re conformed that verbal
approval has already been given by the Director
Projects (HEC)-IBA in last meeting & which is
recorded in minutes of meeting & should be
consider as Clients approval.
- RE-NESPAK reminded the PM-Siemens to
submit the composite rate analysis of all
additional items complete in all respect and again
instructed to start the work immediately to avoid
any further delay.
- Executive Engineer-Siemens Conformed that he
will submit rate analysis of all additional works
after this meeting & immediate will start the work
on rerouting of cables.
Contractor-Siemens
4. KESC Sub Station:
Slow Progress of Civil Works:
- PM-Siemens informed that concreting of Plinth
Beams have completed on January 18, 2012 as
committed in last meeting.
- RE-Nespak & Project Engineer-IBA suggested
the PM-Siemens that further efforts are required
to recoup the time lost.
- PM-Siemens accepted the Shortcomings and
committed to accelerate the progress of work asContractor-Siemens
8/2/2019 17-Kesc-prm _ 13 Minutes
4/5
4
maximum as possible.
5. Clients Additional requirements:
- Project Engineer-IBA again discuss the following
requirements:
1. Provide access doors for transformer & LT room
to access the LT System as & when required.
2. A Sleeve for the supply of medium voltage feeder
to AMAN Tower from the new Substation is
required.
3. An ACB of 400 A is required in the LT Room of
the new substation for supplying load to the new
Data centre at City campus.
4. LT Panels may be placed some 2 feet away from
trench on angle iron frame. During the transition
period load cables may be connected one by one
& these panels may be shifted.
Following point wise decision were also taken:
1. EA issued the Construction drawing as per client
requirement through e-mail.
However both Electrical Engineer and Project
Engineer-IBA reviewed the drawing and directed
to use the MS louvered door instead of MS
Corrugated Sheet.
2. Sleeves will be provided in the plinth beam of size
2 x 6.
3. EA-Electrical Engineer confirmed in his email that
the use of 400A ACB in LT panel is not advisable.
4. Siemens has submitted the shop drawing related
8/2/2019 17-Kesc-prm _ 13 Minutes
5/5
5
to the said requirement for review and approval
from Consultant-EA.
6. Absence of Consultant M/s EA in Progress Review
Meetings:
- PM-Siemens complained that due to the
continuous absence of EAs representative, most
of design issues & Drawings quarries remains
unattended.
- RE-Nespak also emphasized upon the presence
of EAs representative & suggested to Project
Engineer-IBA to make sure the presence of
Consultants representatives so that necessary
decision pertaining to design can be taken timely
to avoid unnecessary delay in the completion of
Project.
The meeting was adjourned with thanks to all participants.
SYED MEHDI HASSANResident Engineer
NESPAK
Muhammad YasirProject Manager
Siemens