State of Washington
Office of Financial Management
8:28:38AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
150 - Department of General Administration
BLRB Architects
1250 Pacific Avenue, Suite 700
Tacoma, WA 98402-4308
Auditorium Renovations Predesign, Washington School for the Deaf
Competitive
JK - Architectural & Engineering Services
Start Date: 9/13/2010
End Date: 11/4/2010
Reporting Date: 9/14/2010
Federal:
State:
Other:
Total:
$61,649
$61,649
Current Contract Total: $61,649
Accepted
Hayre McElroy & Associates
2757 152nd Avenue NE
Redmond, WA 98052-
Project No. 2007-193, Testing services for AC flexible pavement and subgrade, HS Complex Replacement, GRCC. On-Call Testing Services.
Various Agencies, Western Washington
Competitive
JK - Architectural & Engineering Services
Start Date: 8/15/2010
End Date: 6/30/2011
Reporting Date: 9/14/2010
Federal:
State:
Other:
Total:
$16,262
$16,262
Current Contract Total: $16,262
Accepted
S M Stemper Architects PLLC
4000 Delridge Way SW, Suite 200
Seattle, WA 98106-
Design services for CA & project closeout, Parks Hall Addition & Replacement, Everett Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 8/19/2010
End Date: 1/30/2011
Reporting Date: 9/14/2010
Federal:
State:
Other:
Total:
$64,941
$64,941
Current Contract Total: $64,941
Accepted
Page 1 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Calvin Jordan Associates
15049 Bel-Red Road
Bellevue, WA 98007-4211
Issaquah Property Site Analysis, Bellevue College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/8/2010
End Date: 12/1/2010
Reporting Date: 9/14/2010
Federal:
State:
Other:
Total:
$13,200
$13,200
Current Contract Total: $13,200
Accepted
Hultz/BHU Consulting Engineers, Inc.
2407 N 31st Street
Suite 200
Tacoma, WA 98407-
Building 5 Improvements, Clover Park Technical College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/9/2010
End Date: 11/26/2010
Reporting Date: 9/10/2010
Federal:
State:
Other:
Total:
$54,086
$54,086
Current Contract Total: $54,086
Accepted
S M Stemper Architects PLLC
4000 Delridge Way SW, Suite 200
Seattle, WA 98106-
Design of pads for exterior mounted HVAC equipment, Building 9 Noise Remedy Remodel, Highline Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 8/17/2010
End Date: 2/10/2011
Reporting Date: 9/2/2010
Federal:
State:
Other:
Total:
$9,200
$9,200
Current Contract Total: $9,200
Accepted
Page 2 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
S M Stemper Architects PLLC
4000 Delridge Way SW, Suite 200
Seattle, WA 98106-
Civil engineering services, Buillding 9 Noise Remedy Remodel, Highline Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 8/17/2010
End Date: 2/10/2011
Reporting Date: 9/2/2010
Federal:
State:
Other:
Total:
$5,060
$5,060
Current Contract Total: $5,060
Accepted
S M Stemper Architects PLLC
4000 Delridge Way SW, Suite 200
Seattle, WA 98106-
Coordination of documents and cost estimate, Building 9 Noise Remedy, Highline Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 8/16/2010
End Date: 2/10/2011
Reporting Date: 9/2/2010
Federal:
State:
Other:
Total:
$12,560
$12,560
Current Contract Total: $12,560
Accepted
Bernardo Willis Architects
107 South Howard
Suite 420
Spokane, WA 99204
Credit for asbestos consultant, Building 1400 N Wing Renovation, ADA Restrooms, Big Bend Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 8/19/2010
End Date: 3/30/2011
Reporting Date: 9/14/2010
Federal:
State:
Other:
Total:
$3,135
$3,135
Current Contract Total: $3,135
Accepted
Page 3 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Bernardo Willis Architects
107 South Howard
Suite 420
Spokane, WA 99204
Add C/O Design budget, Auditorium Remodel, Big Bend Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 8/19/2010
End Date: 8/30/2010
Reporting Date: 9/14/2010
Federal:
State:
Other:
Total:
$612
$612
Current Contract Total: $612
Accepted
PSI
10025 South Tacoma Way #H-1
Tacoma, WA 98499-
Project No. 2009-033, N Parking Lot Improvements, Adjust to actual, Pierce College. On-Call Testing Services, Various Agencies, Western
Washington - North of Longview
Competitive
JK - Architectural & Engineering Services
Start Date: 8/19/2010
End Date: 6/30/2011
Reporting Date: 9/14/2010
Federal:
State:
Other:
Total:
$1,132
$1,132
Current Contract Total: $1,132
Accepted
James Guerrero Architects
7520 Bridgeport Way West
Lakewood, WA 98499-
Building 6 Tenant Improvement, Clover Park Technical College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/30/2010
End Date: 10/21/2010
Reporting Date: 9/14/2010
Federal:
State:
Other:
Total:
$21,920
$21,920
Current Contract Total: $21,920
Accepted
Page 4 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Olympic Associates Company
701 Dexter Avenue North
Suite 301
Seattle, WA 98109-
Project No. 2007-142, Value analysis for Hralth Careers Center, Tacoma Community College. On-Call Value Engineering/ Constructability Services,
Various Agencies, Statewide
Competitive
JK - Architectural & Engineering Services
Start Date: 8/27/2010
End Date: 6/30/2011
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$43,450
$43,450
Current Contract Total: $43,450
Accepted
Leavengood Architects
1920 Eastlake Avenue E., #100
Seattle, WA 98102-
Value engineering, Health & Science Building, Lower Columbia College
Competitive
JK - Architectural & Engineering Services
Start Date: 8/22/2010
End Date: 3/31/2013
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$10,438
$10,438
Current Contract Total: $10,438
Accepted
S M Stemper Architects PLLC
4000 Delridge Way SW, Suite 200
Seattle, WA 98106-
Services performed for tasks related to preparing bid documents, Reroof L&I Headquarters, Dept. of Labor & Industries
Competitive
JK - Architectural & Engineering Services
Start Date: 8/30/2010
End Date: 11/9/2010
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$1,719
$1,719
Current Contract Total: $1,719
Accepted
Page 5 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Zervas Group Architects
209 Prospect Street
Bellingham, WA 98225-
Construction Phase services, Foundation Building Exterior Upgrades, Whatcom Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 8/30/2010
End Date: 11/15/2010
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$3,000
$3,000
Current Contract Total: $3,000
Accepted
Calvin Jordan Associates
15049 Bel-Red Road
Bellevue, WA 98007-4211
Professional roofing inspections, A and B Buildings Roof Replacement, Bellevue College
Competitive
JK - Architectural & Engineering Services
Start Date: 8/31/2010
End Date: 10/15/2010
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$20,075
$20,075
Current Contract Total: $20,075
Accepted
S M Stemper Architects PLLC
4000 Delridge Way SW, Suite 200
Seattle, WA 98106-
Healt Dept/SEPA Coordination, Parks Hall Addition & Renovation, Everett Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 8/31/2010
End Date: 1/30/2011
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$22,842
$22,842
Current Contract Total: $22,842
Accepted
Page 6 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Hayre McElroy & Associates
2757 152nd Avenue NE
Redmond, WA 98052-
Project No. 2006-132, Testing & inspection, Integrated Resource Center, North Seattle Community College. On-Call Testing Services, Various
Agencies, Western Washington
Competitive
JK - Architectural & Engineering Services
Start Date: 8/23/2010
End Date: 6/30/2011
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$4,352
$4,352
Current Contract Total: $4,352
Accepted
Buffalo Design
1919 Second Avenue, Suite 200
Seattle, WA 98101-
Bid set printing, Replace the Floor Surface in Main Kitchen Building, Veterans Home, Department of Veterans Affairs.
Competitive
JK - Architectural & Engineering Services
Start Date: 8/23/2010
End Date: 9/26/2010
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$1,334
$1,334
Current Contract Total: $1,334
Accepted
PBS Environmental
130 Nickerson Street
Suite 107
Seattle, WA 98109-
Project No. 2007-072, Adjusting to actual amount invoiced, Seattle Central Community College. On-Call Hazardous Substance Consultant, Various
Agencies, Statewide
Competitive
JK - Architectural & Engineering Services
Start Date: 8/18/2010
End Date: 8/31/2010
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$5,053
$5,053
Current Contract Total: $5,053
Accepted
Page 7 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
MSGS Architects
510 S Capitol Way
Olympia, WA 98501
Programming & Design, Documentation, Bidding & Construction Administration, Communication Arts & Allied Health Building, Pierce College,
Puyallup
Competitive
JK - Architectural & Engineering Services
Start Date: 8/24/2010
End Date: 4/1/2011
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$11,000
$11,000
Current Contract Total: $11,000
Accepted
Building Envelope Technology & Research
4000 Delridge Way SW, First Floor
Seattle, WA 98106-
Review/respomd to an additional 30 RFI's, New Fitness Center, Building Envelope, Everett Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/1/2010
End Date: 12/14/2010
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$7,200
$7,200
Current Contract Total: $7,200
Accepted
Building Envelope Technology & Research
4000 Delridge Way SW, First Floor
Seattle, WA 98106-
Revisions to curtain wall isometric drawings, New Fitness Center, Building Envelope, Everett Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/1/2010
End Date: 12/14/2010
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$1,116
$1,116
Current Contract Total: $1,116
Accepted
Page 8 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
DLR Group
901 Fifth Avenue, Suite 700
Seattle, WA 98164-
Design-Completion & Closeout, Athletic Field Renovation, Phase II, Edmonds Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 8/24/2010
End Date: 10/10/2011
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$191,282
$191,282
Current Contract Total: $191,282
Accepted
James Guerrero Architects
7520 Bridgeport Way West
Lakewood, WA 98499-
Document design for COP's 1, 2 & 3, Tile Repairs and Drainage Improvement for WWII Memorial, Capitol Campus
Competitive
JK - Architectural & Engineering Services
Start Date: 8/25/2010
End Date: 10/31/2010
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$1,140
$1,140
Current Contract Total: $1,140
Accepted
MSGS Architects
510 S Capitol Way
Olympia, WA 98501
Geotechnical construction administration services, Communication Arts & Allied Health Building, Pierce College, Puyallup
Competitive
JK - Architectural & Engineering Services
Start Date: 8/25/2010
End Date: 4/1/2011
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$3,510
$3,510
Current Contract Total: $3,510
Accepted
Page 9 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
LSW Architects PC
2300 Main Street
Vancouver, WA 98660
Adjust to actual amount invoiced, Master Plan Update, Walla Walla Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 8/25/2010
End Date: 9/1/2010
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$18,320
$18,320
Current Contract Total: $18,320
Accepted
Buffalo Design
1919 Second Avenue, Suite 200
Seattle, WA 98101-
Investigate services for kitchen floor in Bldg, 10, Replace the Floor Surface in Main Kitchen Building, Veterans Home, Retsil, Dept. of Veterans
Affairs
Competitive
JK - Architectural & Engineering Services
Start Date: 8/25/2010
End Date: 9/26/2010
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$1,792
$1,792
Current Contract Total: $1,792
Accepted
MSGS Architects
510 S Capitol Way
Olympia, WA 98501
Record drawings for construction, Rainier Building, Pierce College, Fort Steilacoom
Competitive
JK - Architectural & Engineering Services
Start Date: 8/25/2010
End Date: 10/1/2010
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$48,021
$48,021
Current Contract Total: $48,021
Accepted
Page 10 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
MSGS Architects
510 S Capitol Way
Olympia, WA 98501
Programming & Design, Documentation, Bidding & Construction Administration, Rainier Building, Pierce College, Fort Steilacoom
Competitive
JK - Architectural & Engineering Services
Start Date: 8/25/2010
End Date: 10/1/2010
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$11,000
$11,000
Current Contract Total: $11,000
Accepted
Rushing
1725 Westlake Avenue N., Suite 300
Seattle, WA 98109-
Adjust to actual amount invoiced, Bellevue Electrical Upgrades, Washington State Patrol
Competitive
JK - Architectural & Engineering Services
Start Date: 8/26/2010
End Date: 8/31/2010
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$71
$71
Current Contract Total: $71
Accepted
HKP Architects
314 Pine Street
Mount Vernon, WA 98273
Reimbursement for printing, Padilla Bay Reserve Boat Storafe Pole Barn, Department of Ecology
Competitive
JK - Architectural & Engineering Services
Start Date: 8/26/2010
End Date: 10/31/2010
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$330
$330
Current Contract Total: $330
Accepted
Page 11 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Schacht Aslani Architects
506 Second Avenue, Suite 700
Seattle, WA 98104-
Extended Construction Administration, 2700 Chemistry Bldg. Student Vent Hood Replacement, Shoreline Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 8/30/2010
End Date: 9/1/2010
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$4,719
$4,719
Current Contract Total: $4,719
Accepted
Stock & Associates, Inc.
109 Bell Street
Seattle, WA 98121-
Contract Documents-Completion, Entry Reconfiguration, Dept, of Services for the Blind
Competitive
JK - Architectural & Engineering Services
Start Date: 9/1/2010
End Date: 12/15/2010
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$10,553
$10,553
Current Contract Total: $10,553
Accepted
SRG Partnership PC
621 SW Morrison Street
Portland, OR 97205
Testing & special inspection, Science Building, Spokane Falls Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 8/23/2010
End Date: 4/15/2011
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$5,617
$5,617
Current Contract Total: $5,617
Accepted
Page 12 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Stock & Associates, Inc.
109 Bell Street
Seattle, WA 98121-
Entry Reconfiguration, Dept. of Services for the Blind
Competitive
JK - Architectural & Engineering Services
Start Date: 7/14/2010
End Date: 12/15/2010
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$3,990
$3,990
Current Contract Total: $3,990
Accepted
Calvin Jordan Associates
15049 Bel-Red Road
Bellevue, WA 98007-4211
Cancel structural analysis, Continuing Education Instructional Building, Bellevue College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/2/2010
End Date: 5/30/2011
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$17,600
$17,600
Current Contract Total: $17,600
Accepted
AHBL, Inc.
2215 North 30th Street, Suite 300
Tacoma, WA 98403-
Base map for site plan and drawings, On-Call Campus Civil Engineer, Highline Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/2/2010
End Date: 6/30/2011
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$4,000
$4,000
Current Contract Total: $4,000
Accepted
Page 13 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Sargent Engineers
320 Ronlee Lane NW
Olympia, WA 98502
Adjust to actual invoiced amount, Isabella Bush Re-level Floor Surface, Capitol Campus
Competitive
JK - Architectural & Engineering Services
Start Date: 9/2/2010
End Date: 9/30/2010
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$535
$535
Current Contract Total: $535
Accepted
Building Envelope Technology & Research
4000 Delridge Way SW, First Floor
Seattle, WA 98106-
Additional monitoring of cladding and roofing installations, New Fitness Center, Building Envelope, Everett Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/1/2010
End Date: 12/14/2010
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$46,800
$46,800
Current Contract Total: $46,800
Accepted
Schreiber Starling & Lane Architects
185 University St
Seattle, WA 98101-
Tech support, Seattle Maritime Academy Replacement,Seattle Central Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/2/2010
End Date: 2/15/2012
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$2,051
$2,051
Current Contract Total: $2,051
Accepted
Page 14 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Wolfe Architectural Group
1015 N. Calispel, Suite B
Spokane, WA 99201-
Adjust to actual invoiced amount, 2010 Parking Lot Survey, Spokane Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/3/2010
End Date: 9/4/2010
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$1,397
$1,397
Current Contract Total: $1,397
Accepted
HKP Architects
314 Pine Street
Mount Vernon, WA 98273
North Cascades Gateway Center Emergency Roof Replacement, Sedro Woolley
Competitive
JK - Architectural & Engineering Services
Start Date: 9/8/2010
End Date: 10/1/2010
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$7,500
$7,500
Current Contract Total: $7,500
Accepted
Building Envelope Technology & Research
4000 Delridge Way SW, First Floor
Seattle, WA 98106-
Additional time for isometric drawings, New Fitness Center, Building Envelope, Everett Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/3/2010
End Date: 12/14/2010
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$5,800
$5,800
Current Contract Total: $5,800
Accepted
Page 15 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Schacht Aslani Architects
506 Second Avenue, Suite 700
Seattle, WA 98104-
Traffic signal design, Student Parking Lot, Olympic College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/3/2010
End Date: 10/31/2010
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$10,883
$10,883
Current Contract Total: $10,883
Accepted
Hatton Godat Pantier
1840 Barnes Blvd SW
Tumwater , WA 98512-
Project No. 2008-150, Topographic surveying and mapping, South Puget Sound Community College. On-Call Surveying Services, Various
Agencies, Statewide
Competitive
JK - Architectural & Engineering Services
Start Date: 9/2/2010
End Date: 6/30/2011
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$4,000
$4,000
Current Contract Total: $4,000
Accepted
GeoEngineers
2924 Colby Avenue
Everett, WA 98201-
Project No. 2010-087, Geotechnical Construction Monitoring, Everett Community College. On-Call Geotech Sercvies, Various Agencies, Statewide
Competitive
JK - Architectural & Engineering Services
Start Date: 9/8/2010
End Date: 6/30/2011
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$9,500
$9,500
Current Contract Total: $9,500
Accepted
Page 16 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Golder Associates
18300 NE Union Hill Road
Suite 200
Redmond, WA 98052
Design drawings and specs. Hillside Evaluation and Preliminary Design, Capitol Campus
Competitive
JK - Architectural & Engineering Services
Start Date: 8/24/2010
End Date: 8/31/2010
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$39,684
$39,684
Current Contract Total: $39,684
Accepted
Weatherholt and Associates INC
13104 mNortheast 85th Street
PO box 816
Kirkland, WA 98083-0816
Project No. 2010-919, Reroof the Conference Center Building. Edmonds Community College. On-Call Building Envelope & Roof Services, Various
Agencies, Statewide
Competitive
JK - Architectural & Engineering Services
Start Date: 8/30/2010
End Date: 6/30/2011
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$16,500
$16,500
Current Contract Total: $16,500
Accepted
Sazan Group, Inc.
600 Stewart Street
Suite 1400
Seattle, WA 98101-
Project No. 2010-134, 30 days monitoring of NRB & DOT panels effected by the new and relocated compressors. On-Call Mechanical Engineer
Services, Various Agencies, Statewide
Competitive
JK - Architectural & Engineering Services
Start Date: 8/31/2010
End Date: 6/30/2011
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$3,058
$3,058
Current Contract Total: $3,058
Accepted
Page 17 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Weatherholt and Associates INC
13104 mNortheast 85th Street
PO box 816
Kirkland, WA 98083-0816
Additional site visits, Roof Repairs and Replacement, Washington State School for the Blind, Vancouver
Competitive
JK - Architectural & Engineering Services
Start Date: 9/1/2010
End Date: 9/15/2010
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$1,700
$1,700
Current Contract Total: $1,700
Accepted
Reid Middleton
728 - 134th Street SW
Suite 200
Everett, WA 98204-
Project No. 2010-129, Investigation of Liberty Building, Bellevue College. On-Call Structural Engineering Servcies. Various Agencies, Statewide
Competitive
JK - Architectural & Engineering Services
Start Date: 9/2/2010
End Date: 6/30/2011
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$21,000
$21,000
Current Contract Total: $21,000
Accepted
Hayre McElroy & Associates
2757 152nd Avenue NE
Redmond, WA 98052-
Project No. 2009-244, Soil Sampling & Testing, Sewer Line Replacement, Highling Community College. On-Call Testing Services, Various
Agencies, Western Washington
Competitive
JK - Architectural & Engineering Services
Start Date: 9/23/2010
End Date: 6/30/2011
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$818
$818
Current Contract Total: $818
Accepted
Page 18 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Leavengood Architects
1920 Eastlake Avenue E., #100
Seattle, WA 98102-
Acoustical engineering services, Health & Science Building, Lower Columbia College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/23/2010
End Date: 3/31/2013
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$26,353
$26,353
Current Contract Total: $26,353
Accepted
Berger Partnership
1721 Eighth Avenue N
Seattle, WA 98109-
Printing costs, Perimeter Improvements Design, Tacoma Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/23/2010
End Date: 12/31/2010
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$1,542
$1,542
Current Contract Total: $1,542
Accepted
Berger Partnership
1721 Eighth Avenue N
Seattle, WA 98109-
Permit fees reimbursement, Perimeter Improvements Design, Tacoma Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/23/2010
End Date: 12/31/2010
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$2,011
$2,011
Current Contract Total: $2,011
Accepted
Page 19 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Schacht Aslani Architects
506 Second Avenue, Suite 700
Seattle, WA 98104-
Review fees, 5000 Building Improvements, Shoreline Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/24/2010
End Date: 4/17/2011
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$457
$457
Current Contract Total: $457
Accepted
SRG Partnership PC
101 Yesler Way Suite 200
Seattle, WA 98104-
Landscape design revisions, New Fitness Center, Everett Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/22/2010
End Date: 12/14/2010
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$1,100
$1,100
Current Contract Total: $1,100
Accepted
McGranahan Architects
2111 Pacific Ave Suite 100
Tacoma, WA 98402-
Provide anchorage calculations, Cascade Building Phase II, Pierce College, Fort Steilacoom
Competitive
JK - Architectural & Engineering Services
Start Date: 9/22/2010
End Date: 10/31/2010
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$1,100
$1,100
Current Contract Total: $1,100
Accepted
Page 20 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
SRG Partnership PC
110 Union Street, Suite 300
Seattle, WA 98101-
Design of wayfinding elements, New Fitness Center, Everett Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 8/25/2010
End Date: 9/15/2010
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$7,540
$7,540
Current Contract Total: $7,540
Accepted
Stock & Associates, Inc.
109 Bell Street
Seattle, WA 98121-
Last 2 phases, Entry Reconfiguration, Dept. of Services for the Blind
Competitive
JK - Architectural & Engineering Services
Start Date: 9/21/2010
End Date: 9/30/2010
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$2,925
$2,925
Current Contract Total: $2,925
Accepted
Sazan Group, Inc.
600 Stewart Street
Suite 1400
Seattle, WA 98101-
Science Facility Piping Repairs, Peninsula College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/22/2010
End Date: 10/15/2010
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$33,770
$33,770
Current Contract Total: $33,770
Accepted
Page 21 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Schacht Aslani Architects
506 Second Avenue, Suite 700
Seattle, WA 98104-
Pre-design for the Allied Health & Early Childhood Development Center, Peninsula College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/22/2010
End Date: 1/1/2011
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$15,000
$15,000
Current Contract Total: $15,000
Accepted
PLSA Engineering & Surveying
1120 West Lincoln Avenue
Yakima, WA 98902-
Grandview Library, Yakima Valley Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/27/2010
End Date: 8/31/2011
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$13,943
$13,943
Current Contract Total: $13,943
Accepted
KMB Design Groups, Inc., P.S.
828 7th Avenue SE
Olympia, WA 98501-1509
Parking Garage Deck Coating, Department of Ecology
Competitive
JK - Architectural & Engineering Services
Start Date: 9/28/2010
End Date: 9/15/2011
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$49,395
$49,395
Current Contract Total: $49,395
Accepted
Page 22 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Roen Associates
1526 1/2 W Riverside Avenue
Spokane, WA 99210-
Project No. 2010-051, Construction review for the New Music & Arts Building, Wenatchee Valley College. On-Call Value Engineering &
Constructability Services, Various Agencies, Statewide
Competitive
JK - Architectural & Engineering Services
Start Date: 9/28/2010
End Date: 6/30/2011
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$39,702
$39,702
Current Contract Total: $39,702
Accepted
EDAW
710 Second Avenue, Suite 1000
Seattle, WA 98104-
East Plaza Repairs, Phase 5, Capitol Campus, Department of General Administration
Competitive
JK - Architectural & Engineering Services
Start Date: 9/22/2010
End Date: 10/31/2010
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$3,652
$3,652
Current Contract Total: $3,652
Accepted
Schreiber Starling & Lane Architects
185 University St
Seattle, WA 98101-
Design through Closeout, Wood Construction Center Replacement, Seattle Central Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/14/2010
End Date: 6/15/2012
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$5,500
$5,500
Current Contract Total: $5,500
Accepted
Page 23 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Weatherholt and Associates INC
PO Box 816
Kirkland, WA 98083-0816
Project No. 2010-253, Phase I Evaluation, Facility & Site Repairs, Clark College. On-Call Building Envelope & Roof Services, Various Agencies,
Statewide
Competitive
JK - Architectural & Engineering Services
Start Date: 9/13/2010
End Date: 6/30/2011
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$10,750
$10,750
Current Contract Total: $10,750
Accepted
LSW Architects PC
2300 Main Street
Vancouver, WA 98660
Additional geotechnical servcies during demo & repair, Sewer Line Repair, Clark College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/13/2010
End Date: 10/1/2010
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$8,360
$8,360
Current Contract Total: $8,360
Accepted
S M Stemper Architects PLLC
4000 Delridge Way SW, Suite 200
Seattle, WA 98106-
Entry Modifications, Parks Hall Addition & Renovation, Everett Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/14/2010
End Date: 1/30/2011
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$22,626
$22,626
Current Contract Total: $22,626
Accepted
Page 24 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Olympic Associates Company
701 Dexter Avenue North
Suite 301
Seattle, WA 98109-
Project No. 2009-249, VE Review, SMT Renovation, Green River Community. On-Call Value Engineering/Constructability Services, Statewide
Competitive
JK - Architectural & Engineering Services
Start Date: 9/1/2010
End Date: 6/30/2011
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$22,400
$22,400
Current Contract Total: $22,400
Accepted
McGranahan Architects
2111 Pacific Ave Suite 100
Tacoma, WA 98402-
Add Bid Pac, Civil Engineering, Landscape Architecture & surveying Building Envelope, Cascade Building Envelope Repair, Pierce College.
Competitive
JK - Architectural & Engineering Services
Start Date: 9/14/2010
End Date: 3/1/2011
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$377,435
$377,435
Current Contract Total: $377,435
Accepted
Integrus Architecture
117 South Main Street, Suite 100
Seattle, WA 98104-
Add additional servcies, CI Furniture Factory, Stafford Creek Corrections Center, DOC
Competitive
JK - Architectural & Engineering Services
Start Date: 8/31/2010
End Date: 9/1/2010
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$35,583
$35,583
Current Contract Total: $35,583
Accepted
Page 25 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Integrus Architecture
117 South Main Street, Suite 100
Seattle, WA 98104-
Add additional services, CI Furniture Factory, Stafford Creek Corrections Center, DOC
Competitive
JK - Architectural & Engineering Services
Start Date: 8/31/2010
End Date: 9/1/2010
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$14,633
$14,633
Current Contract Total: $14,633
Accepted
S M Stemper Architects PLLC
4000 Delridge Way SW, Suite 200
Seattle, WA 98106-
Additional acoustical engineering, Trades & Industry Building, Green River Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/15/2010
End Date: 5/19/2013
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$6,435
$6,435
Current Contract Total: $6,435
Accepted
S M Stemper Architects PLLC
4000 Delridge Way SW, Suite 200
Seattle, WA 98106-
Lea Hill wetlands report, Trades & Industry Building, Green River Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/15/2010
End Date: 5/19/2013
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$4,145
$4,145
Current Contract Total: $4,145
Accepted
Page 26 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
S M Stemper Architects PLLC
4000 Delridge Way SW, Suite 200
Seattle, WA 98106-
Trades supplementary detention facility survey, Trades & Industry Building, Green River Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/15/2010
End Date: 5/19/2013
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$7,040
$7,040
Current Contract Total: $7,040
Accepted
S M Stemper Architects PLLC
4000 Delridge Way SW, Suite 200
Seattle, WA 98106-
Environmental consuting for supplementary storm water detention site, Trades & Industry Building, Green River Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/15/2010
End Date: 5/19/2013
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$7,920
$7,920
Current Contract Total: $7,920
Accepted
S M Stemper Architects PLLC
4000 Delridge Way SW, Suite 200
Seattle, WA 98106-
Additional reflagging of the supplemental detention site, Trades & Industry Building, Green River Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/15/2010
End Date: 5/19/2013
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$5,632
$5,632
Current Contract Total: $5,632
Accepted
Page 27 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
S M Stemper Architects PLLC
4000 Delridge Way SW, Suite 200
Seattle, WA 98106-
Add construction & completion phases for BP #1, Electric Room Cleaning, Miscellaneous HVAC and Electrical Modifications, Renton Technical
College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/27/2010
End Date: 10/1/2011
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$2,240
$2,240
Current Contract Total: $2,240
Accepted
HKP Architects
314 Pine Street
Mount Vernon, WA 98273
Construction & closeout phases, Padilla Bay Reserve Boat Storage Pole Barn, Department of Ecology
Competitive
JK - Architectural & Engineering Services
Start Date: 9/27/2010
End Date: 10/1/2010
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$3,701
$3,701
Current Contract Total: $3,701
Accepted
McGranahan Architects
2111 Pacific Ave Suite 100
Tacoma, WA 98402-
Additional reimbursables for printing, Buildings A and B Renovation, Bates Technical College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/24/2010
End Date: 9/30/2010
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$901
$901
Current Contract Total: $901
Accepted
Page 28 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
McGranahan Architects
2111 Pacific Ave Suite 100
Tacoma, WA 98402-
Civil surveying for "Request for Segregation on Construction", Communications and Technology Center, Bates Technical College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/24/2010
End Date: 12/31/2012
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$1,100
$1,100
Current Contract Total: $1,100
Accepted
McGranahan Architects
2111 Pacific Ave Suite 100
Tacoma, WA 98402-
Energy Life Cycle Cost Analysis, Communications and Technology Center, Bates Technical College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/27/2010
End Date: 12/31/2012
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$13,200
$13,200
Current Contract Total: $13,200
Accepted
DLR Group
901 Fifth Avenue, Suite 700
Seattle, WA 98164-
Additional on-site project representation, Plant Sciences Complex, Seattle Central Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/23/2010
End Date: 9/15/2011
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$3,120
$3,120
Current Contract Total: $3,120
Accepted
Page 29 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
ALSC Architects PS
203 N Washington
Suite 400
Spokane, WA 99201-0254
Allowance for travel, Center for Water and Environmental Studies, Walla Walla Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/23/2010
End Date: 9/30/2010
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$3,000
$3,000
Current Contract Total: $3,000
Accepted
ALSC Architects PS
203 N Washington
Suite 400
Spokane, WA 99201-0254
Testing required for Building Code, Center for Water and Environmental Studies, Walla Walla Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/23/2010
End Date: 9/30/2010
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$5,610
$5,610
Current Contract Total: $5,610
Accepted
S M Stemper Architects PLLC
4000 Delridge Way SW, Suite 200
Seattle, WA 98106-
Provide miscellaneous services, Building 9 Noise Remedy Remodel, Highline Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/28/2010
End Date: 2/10/2011
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$14,068
$14,068
Current Contract Total: $14,068
Accepted
Page 30 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Architects BCRA Tsang
2106 Pacific Avenue
Suite 300
Tacoma, WA 98402-
Additional Hall assessment services, Hawthorne (Cyprus) Dormitory, Criminal Justice Training Center
Competitive
JK - Architectural & Engineering Services
Start Date: 6/29/2010
End Date: 10/1/2010
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$3,208
$3,208
Current Contract Total: $3,208
Accepted
Keithly Barber Associates, Inc.
14237R Ambaum Blvd. SW
Burien, WA 98166-
TESC Arts Lab Renovation Commissioning. State Commissioning On-Call for Public Facilities' Commissioning projects.
Competitive
JK - Architectural & Engineering Services
Start Date: 9/9/2010
End Date: 6/30/2011
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$16,940
$16,940
Current Contract Total: $16,940
Accepted
McGranahan Architects
2111 Pacific Ave Suite 100
Tacoma, WA 98402-
Additional construction phase services, Emergency Repair Bldg. No. 14, Clover Park Technical College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/8/2010
End Date: 9/30/2010
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$5,500
$5,500
Current Contract Total: $5,500
Accepted
Page 31 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
PSI
10025 South Tacoma Way #H-1
Tacoma, WA 98499-
Project No. 2010-251, Materials Testing and Inspection, Parking Aisle & Parking Lot Improvements, Pierce College, Puyallup. On-Call Testing
Services, Various Agencies, Western Washington - North of Longview
Competitive
JK - Architectural & Engineering Services
Start Date: 9/10/2010
End Date: 6/30/2011
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$5,000
$5,000
Current Contract Total: $5,000
Accepted
McGranahan Architects
2111 Pacific Ave Suite 100
Tacoma, WA 98402-
1700 Building Improvemets, Shoreline Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/20/2010
End Date: 10/22/2010
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$24,580
$24,580
Current Contract Total: $24,580
Accepted
S M Stemper Architects PLLC
4000 Delridge Way SW, Suite 200
Seattle, WA 98106-
Greenhouse Renovation, Everett Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/20/2010
End Date: 11/1/2010
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$7,980
$7,980
Current Contract Total: $7,980
Accepted
Page 32 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Schacht Aslani Architects
506 Second Avenue, Suite 700
Seattle, WA 98104-
Additional landscape architectural services, Maier Hall and West Campus Improvements, Peninsula College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/22/2010
End Date: 12/17/2011
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$9,372
$9,372
Current Contract Total: $9,372
Accepted
Schacht Aslani Architects
506 Second Avenue, Suite 700
Seattle, WA 98104-
Additional geotechnical engineering services, Maier Hall and West Campus Improvements, Peninsula College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/22/2010
End Date: 12/17/2011
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$19,800
$19,800
Current Contract Total: $19,800
Accepted
Schacht Aslani Architects
506 Second Avenue, Suite 700
Seattle, WA 98104-
Additional civil enigneeirng services, Maier Hall and West Campus Improvements, Peninsula College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/22/2010
End Date: 12/17/2011
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$5,530
$5,530
Current Contract Total: $5,530
Accepted
Page 33 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
HKP Architects
314 Pine Street
Mount Vernon, WA 98273
Miscellaneous additional services, Campus Center: Construction Administration Services, Bellingham Technical College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/22/2010
End Date: 5/31/2012
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$149,922
$149,922
Current Contract Total: $149,922
Accepted
PSI
10025 South Tacoma Way #H-1
Tacoma, WA 98499-
Project No. 2009-060, Construction Material Testing, Emergency Repair Bldg. No. 14, Clover Park Technical College. On-Call Testing Services,
Various Agencies, Western Washington, North of Longview
Competitive
JK - Architectural & Engineering Services
Start Date: 9/8/2010
End Date: 6/30/2011
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$2,988
$2,988
Current Contract Total: $2,988
Accepted
Architects BCRA Tsang
2106 Pacific Avenue
Suite 300
Tacoma, WA 98402-
Reprographic costs, Hawthorne (Cypress) Hall Dormitory, Criminal Justice Training Center
Competitive
JK - Architectural & Engineering Services
Start Date: 9/9/2010
End Date: 10/1/2010
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$12,893
$12,893
Current Contract Total: $12,893
Accepted
Page 34 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Ambia Enduring Architecture
108 First Avenue South
Suite 200
Seattle, WA 98104
Interior design and furniture fixtures and equipment consulting, John L. O'Brien Building Renovation, Capitol Campus
Competitive
JK - Architectural & Engineering Services
Start Date: 5/7/2010
End Date: 12/1/2011
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$105,947
$105,947
Current Contract Total: $105,947
Accepted
Schreiber Starling & Lane Architects
185 University St
Seattle, WA 98101-
Construction Administration, Wood Construction Center Replacement, Seattle Central Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 6/2/2010
End Date: 3/15/2012
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$267,236
$267,236
Current Contract Total: $267,236
Accepted
Engineering Economics
1201 Western Avenue, Suite 325
Seattle, WA 98104-
Project No. 2010-063, Commissioning Services, South Seattle Community College. On-Call Commissioning Services for Public Facilities
Competitive
JK - Architectural & Engineering Services
Start Date: 9/21/2010
End Date: 6/30/2011
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$15,360
$15,360
Current Contract Total: $15,360
Accepted
Page 35 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
GeoEngineers
2924 Colby Avenue
Everett, WA 98201-
Project No. 2010-917, Geotechnical Construction monitoring, North Parking Lot & Concourse Repair, South Seattle Community College. On-Call
Geotech Services, Various Agencies, Statewide
Competitive
JK - Architectural & Engineering Services
Start Date: 9/21/2010
End Date: 6/30/2011
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$2,500
$2,500
Current Contract Total: $2,500
Accepted
McGranahan Architects
2111 Pacific Ave Suite 100
Tacoma, WA 98402-
Design services to prepare feasibility study. On-Call Campus Architect, Highline Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/21/2010
End Date: 6/30/2012
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$6,408
$6,408
Current Contract Total: $6,408
Accepted
S M Stemper Architects PLLC
4000 Delridge Way SW, Suite 200
Seattle, WA 98106-
Geotechnical investigation, Trades and Industry Building, Green River Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/15/2010
End Date: 5/19/2013
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$4,180
$4,180
Current Contract Total: $4,180
Accepted
Page 36 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
S M Stemper Architects PLLC
4000 Delridge Way SW, Suite 200
Seattle, WA 98106-
Traffic study, Trades & Industry Building, Green River Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/15/2010
End Date: 5/19/2013
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$3,850
$3,850
Current Contract Total: $3,850
Accepted
Ambia Enduring Architecture
108 First Avenue South
Suite 200
Seattle, WA 98104
Exterior masonry repairs and cleaning, John L. O'Brien Building Renovations, Capitol Campus
Competitive
JK - Architectural & Engineering Services
Start Date: 9/15/2010
End Date: 12/1/2011
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$50,180
$50,180
Current Contract Total: $50,180
Accepted
MSGS Architects
510 S Capitol Way
Olympia, WA 98501
Field Study & Site Analysis for the Archaeological Site Assessment, Kaiser Natural Outdoor Learning Lab (KNOLL), Centralia College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/17/2010
End Date: 10/29/2010
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$6,456
$6,456
Current Contract Total: $6,456
Accepted
Page 37 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Cortner Architectural Company
1903 West Third Avenue
Spokane, WA 99204
Adjust to actual construction cost, HVAC Improvements, Spokane Falls Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/17/2010
End Date: 10/1/2010
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$12,160
$12,160
Current Contract Total: $12,160
Accepted
Weatherholt and Associates INC
PO Box 816
Kirkland, WA 98083-0816
Adjust to actual amount invoiced, Roof Repairs and Replacement, Washington State School for the Blind
Competitive
JK - Architectural & Engineering Services
Start Date: 9/17/2010
End Date: 9/30/2010
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$8
$8
Current Contract Total: $8
Accepted
Stock & Associates, Inc.
109 Bell Street
Seattle, WA 98121-
Alaska Street Interior Painting Project, Dept. of General Administration
Competitive
JK - Architectural & Engineering Services
Start Date: 9/20/2010
End Date: 11/12/2010
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$3,950
$3,950
Current Contract Total: $3,950
Accepted
Page 38 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Krazan & Associates
922 Valley Avenue NW, Suite 101
Puyallup, WA 98371-
Project No. 2010-033, Noise Remedy Remodel, Highline Community College. On-Call Testing Services, Various Agencies, Statewide
Competitive
JK - Architectural & Engineering Services
Start Date: 8/12/2010
End Date: 6/30/2011
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$12,445
$12,445
Current Contract Total: $12,445
Accepted
ALSC Architects PS
203 N Washington
Suite 400
Spokane, WA 99201-0254
Revise eater service configuration, Center for Water and Environmental Studies, Walla Walla Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/29/2010
End Date: 10/1/2010
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$2,000
$2,000
Current Contract Total: $2,000
Accepted
Schacht Aslani Architects
506 Second Avenue, Suite 700
Seattle, WA 98104-
Print & distribution of documents, 1100 Building Renovation, Shoreline Community College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/29/2010
End Date: 8/31/2011
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$5,774
$5,774
Current Contract Total: $5,774
Accepted
Page 39 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Krazan & Associates
922 Valley Avenue NW, Suite 101
Puyallup, WA 98371-
Project No. 2011-010, Stout Hall Emergency Repairs - Testing, Clark College. On-Call Testing Services, Various Agencies, Statewide
Competitive
JK - Architectural & Engineering Services
Start Date: 9/28/2010
End Date: 6/30/2011
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$9,169
$9,169
Current Contract Total: $9,169
Accepted
Bruce Dees & Associates, LLC
222 East 26th Street, #202
Tacoma, WA 98421-
Delete electrical engineer services. Reimbursable expenses for printing and distribution of plans & specs. Athletic Field Renovations, Peninsula
College
Competitive
JK - Architectural & Engineering Services
Start Date: 9/22/2010
End Date: 9/30/2010
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$12,185
$12,185
Current Contract Total: $12,185
Accepted
Beaman Architecture Ltd.
PO Box 86038
Portland, OR 97286-
Specs for Bid Pac #4, Old Main Kitchen Renovation, WA State School for the Blind
Competitive
JK - Architectural & Engineering Services
Start Date: 9/13/2010
End Date: 11/30/2010
Reporting Date: 9/29/2010
Federal:
State:
Other:
Total:
$7,650
$7,650
Current Contract Total: $7,650
Accepted
Totals by Service Description:
JK - Architectural & Engineering Services $2,453,567 120
Page 40 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Totals by Filing Type:
New Contract $314,615 14
Amendment $2,138,952 106
$2,453,567 120Total for 150 - Department of General Administration
Page 41 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
300 - Department of Social and Health Services
NC Consulting, LLC
PO Box 141
East Olympia, WA 98540-
Amendment extends the services for agression replacement training to the tribes for an additional year through 6/30/11
Competitive
CZ - Other Services
Start Date: 7/1/2010
End Date: 6/30/2011
Reporting Date: 9/22/2010
Federal:
State:
Other:
Total:
$4,760
$4,760
Current Contract Total: $9,520
Accepted
Totals by Service Description:
CZ - Other Services $4,760 1
Totals by Filing Type:
Amendment $4,760 1
$4,760 1Total for 300 - Department of Social and Health Services
Page 42 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
350 - Superintendent of Public Instruction
Heather Dorsey
205 Country Estates Drive W
Rainier, WA 98576-
Contractor shall work as a National Board Certification Regional Coordinator with the District and School Improvement Team(s) and district
personnel, and the District and School Improvement and Accountability (DSIA) Program at the Office of Superintendent of Public Instruction (OSPI).
The Contractor shall deliver, through the National Board Office at OSPI, on-going and relevant communication within regional areas regarding
outreach for National Board Certification. The Contractor shall further provide technical expertise regarding National Board Certification in one of
specific on-going projects identified by the National Board for Professional Teaching Standards (NBPTS) program director at OSPI. Contractor shall
also support the ongoing efforts of the OSPI National Board Certification Facilitator Training and Conditional Loan programs.
Competitive
CE - Social Research Services
Start Date: 9/1/2010
End Date: 6/30/2011
Reporting Date: 9/1/2010
Federal:
State:
Other:
Total:
$6,000
$6,000
Current Contract Total: $6,000
Accepted
Applegate, Sarah
2415 Columbia Street S.W.
Olympia, WA 98501-
Contractor shall work as a National Board Certification Regional Coordinator with the District and School Improvement Team(s) and district
personnel, and the District and School Improvement and Accountability (DSIA) Program at the Office of Superintendent of Public Instruction (OSPI).
The Contractor shall deliver, through the National Board Office at OSPI, on-going and relevant communication within regional areas regarding
outreach for National Board Certification. The Contractor shall further provide technical expertise regarding National Board Certification in one of
specific on-going projects identified by the National Board for Professional Teaching Standards (NBPTS) program director at OSPI. Contractor shall
also support the ongoing efforts of the OSPI National Board Certification Facilitator Training and Conditional Loan programs.
Competitive
CE - Social Research Services
Start Date: 9/1/2010
End Date: 6/30/2011
Reporting Date: 9/1/2010
Federal:
State:
Other:
Total:
$6,000
$6,000
Current Contract Total: $6,000
Accepted
Page 43 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Kareen Borders
13600 Whispering Pines Dr NW
Gig Harbor, WA 98332-
Contractor shall work as a National Board Certification Regional Coordinator with the District and School Improvement Team(s) and district
personnel, and the District and School Improvement and Accountability (DSIA) Program at the Office of Superintendent of Public Instruction (OSPI).
The Contractor shall deliver, through the National Board Office at OSPI, on-going and relevant communication within regional areas regarding
outreach for National Board Certification. The Contractor shall further provide technical expertise regarding National Board Certification in one of
specific on-going projects identified by the National Board for Professional Teaching Standards (NBPTS) program director at OSPI. Contractor shall
also support the ongoing efforts of the OSPI National Board Certification Facilitator Training and Conditional Loan programs.
Competitive
CE - Social Research Services
Start Date: 9/1/2010
End Date: 6/30/2011
Reporting Date: 9/1/2010
Federal:
State:
Other:
Total:
$8,000
$8,000
Current Contract Total: $8,000
Accepted
Cindy P. Rockholt
2910 Shelton Avenue
Yakima, WA 98902-
Contractor shall work as a National Board Certification Regional Coordinator with the District and School Improvement Team(s) and district
personnel, and the District and School Improvement and Accountability (DSIA) Program at the Office of Superintendent of Public Instruction (OSPI).
The Contractor shall deliver, through the National Board Office at OSPI, on-going and relevant communication within regional areas regarding
outreach for National Board Certification. The Contractor shall further provide technical expertise regarding National Board Certification in one of
specific on-going projects identified by the National Board for Professional Teaching Standards (NBPTS) program director at OSPI. Contractor shall
also support the ongoing efforts of the OSPI National Board Certification Facilitator Training and Conditional Loan programs.
Competitive
CE - Social Research Services
Start Date: 9/1/2010
End Date: 6/30/2011
Reporting Date: 9/1/2010
Federal:
State:
Other:
Total:
$10,000
$10,000
Current Contract Total: $10,000
Accepted
Page 44 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Christina Carlson
115 Gilbert Drive
Yakima, WA 98902-
Contractor shall work as a National Board Certification Regional Coordinator with the District and School Improvement Team(s) and district
personnel, and the District and School Improvement and Accountability (DSIA) Program at the Office of Superintendent of Public Instruction (OSPI).
The Contractor shall deliver, through the National Board Office at OSPI, on-going and relevant communication within regional areas regarding
outreach for National Board Certification. The Contractor shall further provide technical expertise regarding National Board Certification in one of
specific on-going projects identified by the National Board for Professional Teaching Standards (NBPTS) program director at OSPI. Contractor shall
also support the ongoing efforts of the OSPI National Board Certification Facilitator Training and Conditional Loan programs.
Competitive
CE - Social Research Services
Start Date: 9/1/2010
End Date: 6/30/2011
Reporting Date: 9/1/2010
Federal:
State:
Other:
Total:
$10,000
$10,000
Current Contract Total: $10,000
Accepted
Totals by Service Description:
CE - Social Research Services $40,000 5
Totals by Filing Type:
New Contract $40,000 5
$40,000 5Total for 350 - Superintendent of Public Instruction
Page 45 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
360 - University of Washington
Lawson Software Inc
380 St Peter St
St Paul, MN 55102-
Provide Cloverleaf services. Funding provided by self support patient revenue.
Competitive
CA - Management/Organizational Services
Start Date: 8/1/2010
End Date: 8/30/2010
Reporting Date: 9/20/2010
Federal:
State:
Other:
Total:
$41,920
$41,920
Current Contract Total: $271,440
Accepted
KFORCE INC
3001 112TH AVE NE
BELLEVUE, WA 98004-
Provide Epic implementation, project management and support services to the CHARMS Project. Funding provided by self support patient revenue.
Competitive
CA - Management/Organizational Services
Start Date: 7/26/2010
End Date: 8/22/2010
Reporting Date: 9/20/2010
Federal:
State:
Other:
Total:
$10,710
$10,710
Current Contract Total: $174,310
Accepted
Richard Slaughter Associates
907 Harrison Blvd
Boise, ID 83702-
No $ increase extension to do case studies, simulations and analysis of the Upper Snake River Basin
Sole Source
CF - Technical Research Services
Start Date: 10/1/2010
End Date: 11/30/2010
Reporting Date: 9/22/2010
Federal:
State:
Other:
Total:
Current Contract Total: $96,856
Accepted
Page 46 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
HealthBPM
5814 Blackshire Path
Inver Grove Heights, MN 55076-
Provide application implementation, project management, and related services for UW Medicine's CHARMS Project. Funding provided by self
support patient revenue.
Competitive
CA - Management/Organizational Services
Start Date: 8/8/2010
End Date: 8/20/2010
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$15,097
$15,097
Current Contract Total: $107,662
Accepted
Daniela Golinelli
1530 Louella Ave
Venice, CA 90291-
To provide statistician and data analysis services for a federal grant regarding Depression Care for Rural Latinos
Sole Source
CE - Social Research Services
Start Date: 2/1/2010
End Date: 6/30/2010
Reporting Date: 9/23/2010
Federal:
State:
Other:
Total:
$5,700
$5,700
Current Contract Total: $5,700
Accepted
Sparkworks Media
325 W. Republican Street
Seattle, WA 98119-4008
Video production services for IMPACT conferences
Sole Source
CH - Communications Services
Start Date: 9/22/2010
End Date: 10/31/2010
Reporting Date: 9/23/2010
Federal:
State:
Other:
Total:
$21,406
$21,406
Current Contract Total: $21,406
Accepted
Page 47 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Senior Services of Seattle King County
2208 Second Avenue
Seattle, WA 98121-
Senior Services will create a web-based data entry platform. An on-going collaborative research effort between UW HPRC and Senior Services
since 1995. 100% Federal Funds.
Sole Source
CA - Management/Organizational Services
Start Date: 9/24/2010
End Date: 3/31/2011
Reporting Date: 9/24/2010
Federal:
State:
Other:
Total:
$20,000
$20,000
Current Contract Total: $20,000
Accepted
WTC Consulting Inc.
801 S Grand Ave suite 700
Los Angeles, CA 90017-
Extension and increase for the study to create a costing model for the services of the UW Tech Dept. This phase is to consult on the "Recharge Fee
Rate Review" process.
Competitive
CC - Financial Services
Start Date: 10/1/2010
End Date: 1/31/2011
Reporting Date: 9/24/2010
Federal:
State:
Other:
Total:
$25,000
$25,000
Current Contract Total: $648,420
Accepted
ProjectCorps
100 West Harrison
Seattle, WA 98119-
External IT quality assurance services. Funding provided by self support patient revenue.
Competitive
CA - Management/Organizational Services
Start Date: 9/14/2010
End Date: 12/31/2012
Reporting Date: 9/27/2010
Federal:
State:
Other:
Total:
$486,000
$486,000
Current Contract Total: $486,000
Accepted
Page 48 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
MatchPoint Solutions, Inc.
6690 Amador Plaza Road, Suite 225
Dublin, CA 94568-
Provide expert level consultative services to UW Medicine's CHARMS Project. Funding provided by self support patient revenue.
Competitive
CA - Management/Organizational Services
Start Date: 9/30/2010
End Date: 10/8/2010
Reporting Date: 9/27/2010
Federal:
State:
Other:
Total:
$5,600
$5,600
Current Contract Total: $117,600
Accepted
Seattle Northwest Securties Corp
1420 5th Ave
Suite 4300
Seattle, WA 98101-
To extend the contract (no $ increase) for providing debt consultant services for the UW Treasury Office and Board of Regents
Competitive
CC - Financial Services
Start Date: 8/31/2010
End Date: 6/30/2012
Reporting Date: 9/16/2010
Federal:
State:
Other:
Total:
Current Contract Total: $250,000
Accepted
HealthBPM
5814 Blackshire Path
Inver Grove Heights, MN 55076-
Provide Epic application implementation, project management and related services to CHARMS Project. Funding provided by self support patient
revenue.
Competitive
CA - Management/Organizational Services
Start Date: 8/22/2010
End Date: 9/3/2010
Reporting Date: 9/21/2010
Federal:
State:
Other:
Total:
$13,365
$13,365
Current Contract Total: $121,027
Accepted
Page 49 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Waypoint Consulting Group LLC
8937 51stt W
University Way, WA 98467-
Legislative outreach consultant services for Life Sciences Discovery Fund
Competitive
CZ - Other Services
Start Date: 8/27/2010
End Date: 5/31/2011
Reporting Date: 9/1/2010
Federal:
State:
Other:
Total:
$50,000
$50,000
Current Contract Total: $50,000
Accepted
Exclaim
2125 Western Ave Ste 302
Seattle, WA 98121-
Increase $ amount to contract for the provision of marketing materials, as needed, for UW Medicine
Competitive
CG - Marketing Services
Start Date: 6/1/2010
End Date: 12/31/2010
Reporting Date: 9/10/2010
Federal:
State:
Other:
Total:
$5,000
$5,000
Current Contract Total: $585,000
Accepted
Sierra Systems
111 Market Street NE
Suite 225
Olympia, WA 98501-
Provide external IT Quality Assurance services. Funding provided by self support patient revenue.
Competitive
CA - Management/Organizational Services
Start Date: 7/1/2010
End Date: 10/31/2010
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$60,000
$60,000
Current Contract Total: $60,000
Accepted
Page 50 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
GRE International
2801 Alaskan Way ste 310
Seattle, WA 98121-
Marketing of Global Executive MBA program in the Middle East
Sole Source
CG - Marketing Services
Start Date: 9/7/2010
End Date: 12/31/2010
Reporting Date: 9/9/2010
Federal:
State:
Other:
Total:
$7,000
$7,000
Current Contract Total: $7,000
Accepted
Flexource LLC
545 Andover Park W
Suite 215
Tukwila, WA 98188-
To add additonal effort on dashboards and metrics to the implementation phase of the contract for consolidation of the UW Medicine call centers.
Competitive
CF - Technical Research Services
Start Date: 9/7/2010
End Date: 9/30/2011
Reporting Date: 9/7/2010
Federal:
State:
Other:
Total:
$50,000
$50,000
Current Contract Total: $1,360,000
Accepted
Helen Epstein
424 W 144th St
New York, NY 10031-
To assist with the writing, editing and preparation of manuscripts, reviews, and reports related to research on concurrent partnerships and HIV
prevalence
Sole Source
CE - Social Research Services
Start Date: 2/1/2010
End Date: 7/31/2010
Reporting Date: 9/14/2010
Federal:
State:
Other:
Total:
$6,000
$6,000
Current Contract Total: $6,000
Accepted
Page 51 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Michael A Vina
301 N Roadrunner Pkwy Apt 1102
Las Cruces, NM 88011-
To assist with the international adoption of circle hooks and TEDS project
Sole Source
CF - Technical Research Services
Start Date: 10/1/2010
End Date: 6/30/2011
Reporting Date: 9/30/2010
Federal:
State:
Other:
Total:
$14,400
$14,400
Current Contract Total: $14,400
Accepted
Point B
1420 5th Avenue suite 2200
Seattle, WA 98101-
Provide project management and implementation support. Funding provided by self support patient revenue.
Competitive
CA - Management/Organizational Services
Start Date: 9/1/2010
End Date: 10/31/2010
Reporting Date: 9/27/2010
Federal:
State:
Other:
Total:
$70,000
$70,000
Current Contract Total: $388,820
Accepted
DATSTAT
1000 N. Northlake Way, Suite C
Seattle, WA 98103-0000
Extend contract for mixed mode longitudinal study for 1 year
Sole Source
CF - Technical Research Services
Start Date: 9/1/2010
End Date: 8/31/2011
Reporting Date: 9/23/2010
Federal:
State:
Other:
Total:
$67,540
$67,540
Current Contract Total: $439,738
Accepted
Page 52 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Totals by Service Description:
CA - Management/Organizational Services $722,692 9
CC - Financial Services $25,000 2
CE - Social Research Services $11,700 2
CF - Technical Research Services $131,940 4
CG - Marketing Services $12,000 2
CH - Communications Services $21,406 1
CZ - Other Services $50,000 1
Totals by Filing Type:
New Contract $670,506 9
Amendment $304,232 12
$974,738 21Total for 360 - University of Washington
Page 53 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
365 - Washington State University
Derrick Smith
12878 Quartz Circle
Madison, AL 35756-
Blind Programming Project - educational evaluator. Conduct literature review, develop workshop instruments, data review, and data analysis.
Sole Source
CA - Management/Organizational Services
Start Date: 6/21/2010
End Date: 9/7/2010
Reporting Date: 9/24/2010
Federal:
State:
Other:
Total:
$5,250
$5,250
Current Contract Total: $5,250
Accepted
DeMaio Consulting, LLC
8495 East Cactus Wren Circle
Scottsdale, AZ 85266-
Act as an independent consultant to the Student Information Systems Replacement Project.
Sole Source
CA - Management/Organizational Services
Start Date: 9/23/2010
End Date: 6/30/2012
Reporting Date: 9/24/2010
Federal:
State:
Other:
Total:
$639,500
$639,500
Current Contract Total: $639,500
Accepted
Ronda Callister
1633 Mountain Road
Logan, UT 84321-
External evaluator as required in preparation for the third year visit by the Advance Grant agency the National Science Foundation.
Sole Source
CA - Management/Organizational Services
Start Date: 8/19/2010
End Date: 8/31/2011
Reporting Date: 9/21/2010
Federal:
State:
Other:
Total:
$10,000
$10,000
Current Contract Total: $10,000
Accepted
Page 54 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Robert Drago
1803 Biltmore St. NW #702
Washington DC, DC 20009-
EXCELenCE Center benchmarking, assessment, external evaluation, and conducting focus groups in preparation for a third year visit by the
National Science Foundation.
Sole Source
CA - Management/Organizational Services
Start Date: 8/10/2010
End Date: 8/31/2011
Reporting Date: 9/9/2010
Federal:
State:
Other:
Total:
$10,000
$10,000
Current Contract Total: $10,000
Accepted
Totals by Service Description:
CA - Management/Organizational Services $664,750 4
Totals by Filing Type:
New Contract $664,750 4
$664,750 4Total for 365 - Washington State University
Page 55 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
370 - Eastern Washington University
Diana Serquina
3421 W Providence Ave
Spokane, WA 99205-
As part of Get Lit!'s Writer-in-Residence program, contractor will work three hours a week at Lidgerwood Elementary school with students and
teachers to help improve their creative writing program.
Sole Source
CE - Social Research Services
Start Date: 10/1/2010
End Date: 6/1/2011
Reporting Date: 9/28/2010
Federal:
State:
Other:
Total:
$5,500
$5,500
Current Contract Total: $5,500
Accepted
Valerie Sultan
2201 SW Holden Street Apt D-102
Seattle, WA 98106-
Interpreter for School of Psychology Post-Master Certification Program.
Sole Source
CZ - Other Services
Start Date: 9/20/2010
End Date: 12/31/2011
Reporting Date: 9/30/2010
Federal:
State:
Other:
Total:
$40,800
$40,800
Current Contract Total: $40,800
Accepted
Dd Communications
PO Box 277
Lovejoy, GA 30250-
Comedy Showcase for Students
Sole Source
CZ - Other Services
Start Date: 9/23/2010
End Date: 9/23/2010
Reporting Date: 9/27/2010
Federal:
State:
Other:
Total:
$5,700
$5,700
Current Contract Total: $5,700
Accepted
Page 56 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
JoJo Sullivan
4835 B Delridge Way SW Seattle
Seattle, WA 98106-
Interpreter services for student in the School of Psychology Post-Master Certification Program.
Sole Source
CZ - Other Services
Start Date: 9/20/2010
End Date: 12/31/2011
Reporting Date: 9/30/2010
Federal:
State:
Other:
Total:
$40,800
$40,800
Current Contract Total: $40,800
Accepted
Totals by Service Description:
CE - Social Research Services $5,500 1
CZ - Other Services $87,300 3
Totals by Filing Type:
New Contract $92,800 4
$92,800 4Total for 370 - Eastern Washington University
Page 57 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
375 - Central Washington University
Paramount Communications, Inc.
P.O. Box 6880
Kennewick, WA 99336-
Cabling to support new residence hall construction, master contract T05-MST-005
Competitive
JK - Architectural & Engineering Services
Start Date: 9/23/2010
End Date: 11/15/2010
Reporting Date: 9/23/2010
Federal:
State:
Other:
Total:
$48,800
$48,800
Current Contract Total: $48,800
Accepted
Knutson Crane, Inc.
6402 Manastash Road
Ellensburg, WA 98926-
Crane service for Psychology Building (need to replace coil, Ellensburg, WA) change order is for Crane service for steam tunnel maintenance, light
pole erection and misc. lifting
Competitive
JK - Architectural & Engineering Services
Start Date: 9/17/2010
End Date: 2/21/2011
Reporting Date: 9/17/2010
Federal:
State:
Other:
Total:
$3,000
$3,000
Current Contract Total: $3,000
Accepted
Coughlin Porter Lundeen
413 Pine Street, Suite 300
Seattle, WA 98101-
Engineering services for the Parking Lot at H-15
Competitive
JK - Architectural & Engineering Services
Start Date: 9/17/2010
End Date: 5/17/2011
Reporting Date: 9/17/2010
Federal:
State:
Other:
Total:
$4,500
$4,500
Current Contract Total: $4,500
Accepted
Page 58 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Coughlin Porter Lundeen
413 Pine Street, Suite 300
Seattle, WA 98101-
Engineering services for Chestnut Street Improvements
Competitive
JK - Architectural & Engineering Services
Start Date: 9/17/2010
End Date: 5/17/2011
Reporting Date: 9/17/2010
Federal:
State:
Other:
Total:
$22,000
$22,000
Current Contract Total: $22,000
Accepted
P.A.S.S.
200 Grayson Trail
Hogansville, GA 30230-
Perform on site service to put the Cleaver Brooks boiler #2 controls back in service
Competitive
JK - Architectural & Engineering Services
Start Date: 9/17/2010
End Date: 12/31/2010
Reporting Date: 9/20/2010
Federal:
State:
Other:
Total:
$8,805
$8,805
Current Contract Total: $8,805
Accepted
Parallel Electric, Inc.
P.O. Box 1417
Ellensburg, WA 98926-
Distance Education upgrades centers for Lynnwood, Des Moines, lakewood, Wenatchee and Moses Lake Amendment #1 is for additional work
as required to supply and install of frames, amplifier emulator, sine space AAP
Competitive
JK - Architectural & Engineering Services
Start Date: 9/16/2010
End Date: 11/21/2010
Reporting Date: 9/16/2010
Federal:
State:
Other:
Total:
$14,704
$14,704
Current Contract Total: $14,704
Accepted
Page 59 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Parallel Electric, Inc.
P.O. Box 1417
Ellensburg, WA 98926-
For transformer maintenance - Barge Hall, student union recreation center & brooklane daycare Amendment is for Transformer maintenance in
Mitchell hall
Competitive
JK - Architectural & Engineering Services
Start Date: 9/16/2010
End Date: 11/1/2010
Reporting Date: 9/16/2010
Federal:
State:
Other:
Total:
$3,240
$3,240
Current Contract Total: $3,240
Accepted
W.M Smith & Associates Inc.
P.O. Box 398
Ellensburg, WA 98926-
remove existing pool liner & Replace with a new myrtha pool liner change order #1 is for FA 1-3 and float valve repairs
Competitive
JK - Architectural & Engineering Services
Start Date: 9/17/2010
End Date: 11/17/2010
Reporting Date: 9/17/2010
Federal:
State:
Other:
Total:
$22,655
$22,655
Current Contract Total: $22,655
Accepted
T.W. Clark Construction, LLC
1117 N. Evergreen Road #1
Spokane Valley, WA 99216-
Hogue Hall Addition Change order: PR 10, PR 15, PR 19, PR 21, PR 22, PR 23, PR 24, PR 26, PR 28, PR 29, PR 31, PR 32, PR 33, PR34, PR
35, PR 36
Competitive
JK - Architectural & Engineering Services
Start Date: 9/27/2010
End Date: 11/22/2011
Reporting Date: 9/27/2010
Federal:
State:
Other:
Total:
$112,427
$112,427
Current Contract Total: $112,427
Accepted
Page 60 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
ARC Electric & Lighting Corporation
5524 N Julia Street
Spokane, WA 99217-
Construction for Medium Voltage Feeder Upgrades, Phase 1, Base Bid and Alternates 1,3.3 and 4.3 were accepted.
Competitive
JK - Architectural & Engineering Services
Start Date: 9/27/2010
End Date: 7/2/2011
Reporting Date: 9/27/2010
Federal:
State:
Other:
Total:
$477,377
$477,377
Current Contract Total: $477,377
Accepted
RMSA Retail Solutions LLC
1450 Iowa Ave, Suite 250
Riverside, CA 92507-
Inventory merchandise planning and forecasting services for University Bookstore as per RFP #10-011
Competitive
CG - Marketing Services
Start Date: 9/27/2010
End Date: 9/27/2011
Reporting Date: 9/22/2010
Federal:
State:
Other:
Total:
$15,147
$15,147
Current Contract Total: $15,147
Accepted
Prater Electric, Inc.
100 E. 17th Avenue
Ellensburg, WA 98926-
Demo of existing pool area lighting, installation of new pool area lighting and modifications to existing pool lighting controls, --additional time and
material for hot dipped galvanized material
Competitive
JK - Architectural & Engineering Services
Start Date: 9/23/2010
End Date: 10/16/2010
Reporting Date: 9/23/2010
Federal:
State:
Other:
Total:
$5,385
$5,385
Current Contract Total: $5,385
Accepted
Page 61 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Keithly Barber Associates, Inc.
14237R Ambaum Blvd. SW
Burien, WA 98166-
Commissioning services for the Hogue Hall addition
Competitive
JK - Architectural & Engineering Services
Start Date: 9/13/2010
End Date: 12/31/2011
Reporting Date: 9/13/2010
Federal:
State:
Other:
Total:
$14,970
$14,970
Current Contract Total: $14,970
Accepted
Totals by Service Description:
CG - Marketing Services $15,147 1
JK - Architectural & Engineering Services $737,863 12
Totals by Filing Type:
New Contract $576,629 6
Amendment $176,381 7
$753,010 13Total for 375 - Central Washington University
Page 62 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
376 - The Evergreen State College
Noel-Levitz, Inc.
2350 Oakdale Blvd
Coralville, IA 52241-
The purpose of this contract is to identify the terms and conditions that will be used by Evergreen and Noel-Levitaz as they work together in
developing a plan of action to strategically use financial aid and scholarship resoureces. This contract fits the exemption in the ESHB 2921 of being
not funded by state funds or tuition.
Competitive
CG - Marketing Services
Start Date: 9/23/2010
End Date: 9/30/2011
Reporting Date: 9/23/2010
Federal:
State:
Other:
Total:
$48,000
$48,000
Current Contract Total: $48,000
Accepted
Totals by Service Description:
CG - Marketing Services $48,000 1
Totals by Filing Type:
New Contract $48,000 1
$48,000 1Total for 376 - The Evergreen State College
Page 63 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
380 - Western Washington University
Lyric, Inc.
2215 41st Avenue SW
Seattle, WA 98116-
Additional Brand Strategy and Logo Development Services, Exercise first of four options to extend for one year period.
Competitive
CG - Marketing Services
Start Date: 4/2/2010
End Date: 7/26/2011
Reporting Date: 9/21/2010
Federal:
State:
Other:
Total:
$70,000
$70,000
Current Contract Total: $165,075
Accepted
Ross & McClure Architects
1223 Commercial
Bellingham, WA 98225
Various Capital Projects - assistance with multi-use playfield proposal and extension of period of service from 10/30/10 to 12/31/10.
Competitive
JK - Architectural & Engineering Services
Start Date: 9/8/2010
End Date: 12/31/2010
Reporting Date: 9/16/2010
Federal:
State:
Other:
Total:
$10,500
$10,500
Current Contract Total: $10,500
Accepted
Arbour North Architecture & Interiors LLC
3647 Toad Lake Rd
Bellingham, WA 98226-
Professional Service Agreement for PW599 EH Floor Repairs.
Competitive
JK - Architectural & Engineering Services
Start Date: 8/26/2010
End Date: 12/30/2011
Reporting Date: 9/16/2010
Federal:
State:
Other:
Total:
$22,500
$22,500
Current Contract Total: $22,500
Accepted
Page 64 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Arai Jackson Architects
2300 7th Avenue
Seattle, WA 98121-1904
PW-607 ES Exterior Renewal, additional services for added time and complexity related to window installation process
Competitive
JK - Architectural & Engineering Services
Start Date: 9/7/2010
End Date: 12/31/2010
Reporting Date: 9/16/2010
Federal:
State:
Other:
Total:
$13,450
$13,450
Current Contract Total: $13,450
Accepted
Anvil Corporation
1675 W Bakerview Road
Bellingham, WA 98226
Contract #F166982 for consulting services (welding inspection) related to PW-598 Steam Vault TN-15 Upgrade.
Competitive
JK - Architectural & Engineering Services
Start Date: 6/26/2010
End Date: 9/1/2010
Reporting Date: 9/14/2010
Federal:
State:
Other:
Total:
$3,315
$3,315
Current Contract Total: $3,315
Accepted
Geo Test Services
741 Marine Drive
Bellingham, WA 98225
Contract #F166978 for consultant services related to PW-621 LEBMC Bike Lane Development II.
Competitive
JK - Architectural & Engineering Services
Start Date: 6/21/2010
End Date: 9/3/2010
Reporting Date: 9/14/2010
Federal:
State:
Other:
Total:
$3,013
$3,013
Current Contract Total: $3,013
Accepted
Page 65 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Materials Testing & Consulting
777 Chrysler Drive
Burlington, WA
Contract #F166974 for consulting services related to PW-600 Shannon Point Marine Center Seawater Pumping System Phase II.
Competitive
JK - Architectural & Engineering Services
Start Date: 5/17/2010
End Date: 10/31/2010
Reporting Date: 9/14/2010
Federal:
State:
Other:
Total:
$2,569
$2,569
Current Contract Total: $2,569
Accepted
Arbour North Architecture & Interiors LLC
3647 Toad Lake Rd
Bellingham, WA 98226-
Contract #F166977 for consulting services related to PW-634 LEBMC South Campus Pedistrian Path Improvement.
Competitive
JK - Architectural & Engineering Services
Start Date: 6/23/2010
End Date: 1/31/2011
Reporting Date: 9/14/2010
Federal:
State:
Other:
Total:
$16,800
$16,800
Current Contract Total: $16,800
Accepted
Church Nickerson Jansen Associates
2722 Colby Avenue
Suite 607
Everett, WA 98201
Contract #F166979. Consulting services related to PW-631 Ridgeway Beta Residence Hall Improvements. Change Order #1 is issed to add
consultant services for:
1. Mayes Testing for seismic analysis during DD for $6,030
2. K-Engineers for electric hardware per COB for $9,550
In total, the change order will increase F166979 $15,580 from $595,315 to $610,895.
Competitive
JK - Architectural & Engineering Services
Start Date: 6/23/2010
End Date: 12/31/2013
Reporting Date: 9/14/2010
Federal:
State:
Other:
Total:
$15,580
$15,580
Current Contract Total: $15,580
Accepted
Page 66 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Church Nickerson Jansen Associates
2722 Colby Avenue
Suite 607
Everett, WA 98201
Contract #F166979 for consulting services related to PW-631 Ridgeway Beta Residence Hall Improvements.
Competitive
JK - Architectural & Engineering Services
Start Date: 6/23/2010
End Date: 12/31/2013
Reporting Date: 9/14/2010
Federal:
State:
Other:
Total:
$595,315
$595,315
Current Contract Total: $595,315
Accepted
Rolluda Architects, Inc.
105 S Main St. Suite 323
Seattle, WA 98104-
Amendment to F166936, agreement for consulting services for PW-595 Buchanan Towers Alarm and Sprinkler Upgrade. Amendment will increase
F166936 $21,806.75 from $401,532.00 to $423,338.75.
Competitive
JK - Architectural & Engineering Services
Start Date: 6/1/2009
End Date: 10/31/2011
Reporting Date: 9/2/2010
Federal:
State:
Other:
Total:
$21,807
$21,807
Current Contract Total: $21,807
Accepted
Geo Test Services
741 Marine Drive
Bellingham, WA 98225
New contract in the amount of $4,876.00 for consulting services: Special Inspection for PW 627 ET Lab Removal.
Competitive
JK - Architectural & Engineering Services
Start Date: 8/1/2010
End Date: 9/22/2010
Reporting Date: 9/2/2010
Federal:
State:
Other:
Total:
$4,876
$4,876
Current Contract Total: $4,876
Accepted
Page 67 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Mahlum Architects
71 Columbia, Suite 400
Seattle, WA 98104
Consulting services related to PW-465 Miller Hall Renovations. Change Order #17 is issued to increase F166861 $246,780.00 from $4, 528,871.00
to $4,775,651.00 for additional services. All other terms and conditions remain the same.
Competitive
JK - Architectural & Engineering Services
Start Date: 10/27/2007
End Date: 5/1/2013
Reporting Date: 9/2/2010
Federal:
State:
Other:
Total:
$246,780
$246,780
Current Contract Total: $246,780
Accepted
Sparling, Inc.
720 Olive Way, Suite 1400
Seattle, WA 98101-
Change Order #2 to F166951 for services related to PW-602 Mainstage and Concert Hall.
Competitive
JK - Architectural & Engineering Services
Start Date: 11/1/2009
End Date: 10/30/2010
Reporting Date: 9/23/2010
Federal:
State:
Other:
Total:
$350
$350
Current Contract Total: $350
Accepted
Geo Test Services
741 Marine Drive
Bellingham, WA 98225
PW-626 Physical Plant Remodel, Special Inspection and Materials Testing
Competitive
JK - Architectural & Engineering Services
Start Date: 10/15/2010
End Date: 3/22/2011
Reporting Date: 9/27/2010
Federal:
State:
Other:
Total:
$10,670
$10,670
Current Contract Total: $10,670
Accepted
Page 68 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Totals by Service Description:
CG - Marketing Services $70,000 1
JK - Architectural & Engineering Services $967,525 14
Totals by Filing Type:
New Contract $659,058 8
Amendment $378,467 7
$1,037,525 15Total for 380 - Western Washington University
Page 69 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
390 - Washington State Historical Society
Cultural Images
8890 NW Ash Street
Portland, OR 97229-
To process special collections items for the Women's History Consortium.
Competitive
CZ - Other Services
Start Date: 9/1/2010
End Date: 5/31/2011
Reporting Date: 9/2/2010
Federal:
State:
Other:
Total:
$15,785
$15,785
Current Contract Total: $15,785
Accepted
Totals by Service Description:
CZ - Other Services $15,785 1
Totals by Filing Type:
New Contract $15,785 1
$15,785 1Total for 390 - Washington State Historical Society
Page 70 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
405 - Department of Transportation
PBS&J
482 S Keller Road
Orlando, FL 32810-
Master Agreement for On-Call Engineering Specialty Services - Tolling, Amendment No. 4 provides for an increase of $130,000.00 and closure of
the agreement.
Competitive
JK - Architectural & Engineering Services
Start Date: 6/30/2010
End Date: 6/30/2010
Reporting Date: 9/3/2010
Federal:
State:
Other:
Total:
$130,000
$130,000
Current Contract Total: $130,000
Accepted
Shea, Carr & Jewell
2102 Carriage Street SW, Bldg. H
Olympia, WA 98502-
MASTER AGREEMENT for On-Call Transportation Design PS&E Above $500K
Competitive
JK - Architectural & Engineering Services
Start Date: 9/2/2010
End Date: 6/30/2014
Reporting Date: 9/8/2010
Federal:
State:
Other:
Total:
$7,500,000
$7,500,000
Current Contract Total: $7,500,000
Accepted
Shea, Carr & Jewell
2102 Carriage Street SW, Bldg. H
Olympia, WA 98502-
MASTER AGREEMENT for On-Call Transportation Studies Above $500K
Competitive
JK - Architectural & Engineering Services
Start Date: 9/2/2010
End Date: 6/30/2014
Reporting Date: 9/8/2010
Federal:
State:
Other:
Total:
$7,500,000
$7,500,000
Current Contract Total: $7,500,000
Accepted
Page 71 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Shea, Carr & Jewell
2102 Carriage Street SW, Bldg. H
Olympia, WA 98502-
MASTER AGREEMENT for On-Call Civil Engineering Services for Facilities
Competitive
JK - Architectural & Engineering Services
Start Date: 9/2/2010
End Date: 5/31/2014
Reporting Date: 9/8/2010
Federal:
State:
Other:
Total:
$350,000
$350,000
Current Contract Total: $350,000
Accepted
Exeltech Consulting, Inc.
8729 Commerce Place Drive NE
Suite A
Lacey, WA 98510-
2010, Statewide On-Call Transportation Design PS&E $500K and Below
Competitive
JK - Architectural & Engineering Services
Start Date: 9/17/2010
End Date: 6/30/2014
Reporting Date: 9/30/2010
Federal:
State:
Other:
Total:
$500,000
$500,000
Current Contract Total: $500,000
Accepted
Icicle Creek Engineers
29335 NE 20th Street
Carnation, WA 98014-9632
Shallow Well Investgation for NWR, Supplement No. 4 reduces the agreement by $16,137.00 from the total of $24,848.00 with a new total of
$8,711.00. The end date of the agreement is changed from December 31, 2010 to August 31, 2010. This supplement will close out the agreement.
Sole Source
JK - Architectural & Engineering Services
Start Date: 8/31/2010
End Date: 8/31/2010
Reporting Date: 9/30/2010
Federal:
State:
Other:
Total:
$(16,137)
$(16,137)
Current Contract Total: -$16,137
Accepted
Page 72 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
CTS Engineers of Washington PLLC
1412 - 112th Avenue NE
Suite 102
Bellevue, WA 98058-
2010, Statewide On-Call Land Surveying $500K and Below
Competitive
JK - Architectural & Engineering Services
Start Date: 9/22/2010
End Date: 6/30/2014
Reporting Date: 9/30/2010
Federal:
State:
Other:
Total:
$500,000
$500,000
Current Contract Total: $500,000
Accepted
CTS Engineers of Washington PLLC
1412 - 112th Avenue NE
Suite 102
Bellevue, WA 98058-
2010, Statewide On-Call Transportation Studies $500K and Below
Competitive
JK - Architectural & Engineering Services
Start Date: 9/22/2010
End Date: 6/30/2014
Reporting Date: 9/30/2010
Federal:
State:
Other:
Total:
$500,000
$500,000
Current Contract Total: $500,000
Accepted
Post Buckley Schuh & Jernigan, Inc.
901 - 5th Avenue
Suite 3100
Seattle, WA 98164-
2010, Statewide On-Call Transportation Studies above $500K
Competitive
JK - Architectural & Engineering Services
Start Date: 9/17/2010
End Date: 6/30/2014
Reporting Date: 9/30/2010
Federal:
State:
Other:
Total:
$7,500,000
$7,500,000
Current Contract Total: $7,500,000
Accepted
Page 73 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Jacobs Engineering Group, Inc.
600 108th Anvenue N.E.
Suite 700
Bellevue, WA 98004-
2010, Statewide On-Call Computer Aided Design & Drafting (CADD) Services
Competitive
JK - Architectural & Engineering Services
Start Date: 9/21/2010
End Date: 8/31/2013
Reporting Date: 9/30/2010
Federal:
State:
Other:
Total:
$1,500,000
$1,500,000
Current Contract Total: $1,500,000
Accepted
Global Geophysics
16651 White Mountain Road SE
Monroe, WA 98272-
2010, Satewide On-Call Geophysical Services
Competitive
JK - Architectural & Engineering Services
Start Date: 9/17/2010
End Date: 9/30/2013
Reporting Date: 9/30/2010
Federal:
State:
Other:
Total:
$350,000
$350,000
Current Contract Total: $350,000
Accepted
CTS Engineers of Washington PLLC
1412 - 112th Avenue NE
Suite 102
Bellevue, WA 98058-
2010, Statewide On-Call Transportation Design/PS&E $500K and Below
Competitive
JK - Architectural & Engineering Services
Start Date: 9/22/2010
End Date: 6/30/2014
Reporting Date: 9/30/2010
Federal:
State:
Other:
Total:
$500,000
$500,000
Current Contract Total: $500,000
Accepted
Totals by Service Description:
JK - Architectural & Engineering Services $26,813,863 12
Page 74 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Totals by Filing Type:
New Contract $26,700,000 10
Amendment $113,863 2
$26,813,863 12Total for 405 - Department of Transportation
Page 75 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
461 - Department of Ecology
CH2M Hill
777 108th Avenue NE
Bellevue, WA 98004
Add funds for operation and maintenance of remedial system at the Lilyblad site.
Competitive
JK - Architectural & Engineering Services
Start Date: 9/20/2010
End Date: 6/30/2016
Reporting Date: 9/20/2010
Federal:
State:
Other:
Total:
$36,112,214
$36,112,214
Current Contract Total: $36,112,214
Accepted
Totals by Service Description:
JK - Architectural & Engineering Services $36,112,214 1
Totals by Filing Type:
Amendment $36,112,214 1
$36,112,214 1Total for 461 - Department of Ecology
Page 76 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
465 - State Parks and Recreation Commission
Herrera Environmental Consultants
2200 Sixth Avenue
Suite 1000
Seattle, WA 98121-
Conceptual design for Low Impact Development Improvements at Twanoh State Park.
Competitive
JK - Architectural & Engineering Services
Start Date: 9/17/2010
End Date: 6/30/2011
Reporting Date: 9/17/2010
Federal:
State:
Other:
Total:
$52,850
$52,850
Current Contract Total: $52,850
Accepted
Wilson Engineering, LLC
805 Dupont Street, Suite 7
Bellingham, WA 98225-3128
Add back in package contract bid documents an construction administration for up to 5 deluxe cabins that were removed from the original contract.
Competitive
JK - Architectural & Engineering Services
Start Date: 9/17/2010
End Date: 6/30/2011
Reporting Date: 9/17/2010
Federal:
State:
Other:
Total:
$37,940
$37,940
Current Contract Total: $37,940
Accepted
GeoEngineers
8410 - 154th Avenue NE
Redmond, WA 98052-
Construction Engineering Services for the Tunnel 50 Roof Safety Improvements at Iron Horse State Park.
Competitive
JK - Architectural & Engineering Services
Start Date: 9/21/2010
End Date: 6/30/2011
Reporting Date: 9/21/2010
Federal:
State:
Other:
Total:
$102,330
$102,330
Current Contract Total: $102,330
Accepted
Page 77 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Peratrovich Nottingham & Drage
811 First Avenue
Seattle, WA 98104
Additional geotech analysis due to unforseen subsurface conditions for the relocation of stairs at South Whidbey State Park.
Competitive
JK - Architectural & Engineering Services
Start Date: 9/8/2010
End Date: 6/30/2011
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$9,000
$9,000
Current Contract Total: $9,000
Accepted
Associated Earth Sciences
911 Fifth Avenue
Suite 100
Kirkland, WA 98033
On Call geotech services via individual task orders on this convenience contract. Not to exceed 100.000.
Competitive
JK - Architectural & Engineering Services
Start Date: 9/15/2010
End Date: 6/30/2011
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$100,000
$100,000
Current Contract Total: $100,000
Accepted
Reid Middleton
728 - 134th Street SW
Suite 200
Everett, WA 98204-
Perform additional sitte visits to observe pile and float installations for the ADA Moorage at Jones Island State Park.
Competitive
JK - Architectural & Engineering Services
Start Date: 9/20/2010
End Date: 12/31/2010
Reporting Date: 9/21/2010
Federal:
State:
Other:
Total:
$5,000
$5,000
Current Contract Total: $5,000
Accepted
Page 78 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Reid Middleton
728 - 134th Street SW
Suite 200
Everett, WA 98204-
Perform additional site visits to observe the pile and float installations at Sucia Island State Park.
Competitive
JK - Architectural & Engineering Services
Start Date: 9/20/2010
End Date: 12/31/2010
Reporting Date: 9/21/2010
Federal:
State:
Other:
Total:
$5,000
$5,000
Current Contract Total: $5,000
Accepted
MacLeod Reckord
Colman Building, 91 Marion Street
Seattle, WA 98104-1441
Project was put on hold due to litigation and other State Park and WSDOT priorities for the Rocky Reach Trail.
Competitive
JK - Architectural & Engineering Services
Start Date: 9/23/2010
End Date: 6/30/2011
Reporting Date: 9/23/2010
Federal:
State:
Other:
Total:
Current Contract Total: $0
Accepted
Coast & Harbor Engineering
110 Main Streeet
Edmonds, WA 98020-
Engineering analysis of shoreline restoration alternatives, with ultimate design of preferred alternates for the Shoreline Stabilization at Bay View
State Park.
Competitive
JK - Architectural & Engineering Services
Start Date: 9/13/2010
End Date: 6/30/2011
Reporting Date: 9/14/2010
Federal:
State:
Other:
Total:
$124,000
$124,000
Current Contract Total: $124,000
Accepted
Page 79 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Susan L Licht
2030 Landau Street Southeast
Salem, OR 97306-6906
Produce Historic Structures Report for North Head Lighthouse at Cape Disappointment State Park.
Competitive
JK - Architectural & Engineering Services
Start Date: 9/13/2010
End Date: 3/31/2011
Reporting Date: 9/14/2010
Federal:
State:
Other:
Total:
$23,950
$23,950
Current Contract Total: $23,950
Accepted
Peninsula Engineering LLC
PO Box 1160
Olalla, WA 98359-
Award tasks two and three and reimbursable expenses as defined in the original contract for the sewer improvements at Fort Worden State Park.
Competitive
JK - Architectural & Engineering Services
Start Date: 9/8/2010
End Date: 1/31/2011
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$36,000
$36,000
Current Contract Total: $36,000
Accepted
Totals by Service Description:
JK - Architectural & Engineering Services $496,070 11
Totals by Filing Type:
New Contract $300,800 4
Amendment $195,270 7
$496,070 11Total for 465 - State Parks and Recreation Commission
Page 80 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
477 - Department of Fish and Wildlife
Northwest Hydraulic Consultants
16300 Christensen Road
Suite 350
Tukwila, WA 98188
Skagit Moorage Bank Protection - added funds for a redesign per Tribal comments to allow for more habitat features.
Competitive
JK - Architectural & Engineering Services
Start Date: 9/20/2010
End Date: 11/30/2011
Reporting Date: 9/27/2010
Federal:
State:
Other:
Total:
$14,842
$14,842
Current Contract Total: $14,842
Accepted
AMEC Earth & Environmental
11810 North Creek Parkway North
Bothell, WA 98011-
Skamania Hatchery Intake Replacement Geotechnical Report - Amendment is to add another site visit to other side of river.
Competitive
JK - Architectural & Engineering Services
Start Date: 9/16/2010
End Date: 6/30/2011
Reporting Date: 9/24/2010
Federal:
State:
Other:
Total:
$2,500
$2,500
Current Contract Total: $2,500
Accepted
Totals by Service Description:
JK - Architectural & Engineering Services $17,342 2
Totals by Filing Type:
Amendment $17,342 2
$17,342 2Total for 477 - Department of Fish and Wildlife
Page 81 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
515 - Fruit Commission
Duo Public Relations, Inc.
3609 1st Ave. NW
Seattle, WA 98107-
Duo PR collaborated with the Washington State Fruit Commission (WSFC) from April through September to plan and execute a multi-level publicity
and awareness campaign focused on preserving fruit. As a result of this campaign, the website www.sweetpreservation.com was established,
garnering more than 60,000 impressions and numerous media mentions. Given the success of the initial launch, WSFC is requesting Duo to
prepare a PR analysis of the season’s programs in order for the WSFC to align and further develop complimentary programming for the 2011
season.
Competitive
CG - Marketing Services
Start Date: 9/22/2010
End Date: 9/30/2010
Reporting Date: 9/22/2010
Federal:
State:
Other:
Total:
$1,890
$1,890
Current Contract Total: $18,715
Accepted
Totals by Service Description:
CG - Marketing Services $1,890 1
Totals by Filing Type:
Amendment $1,890 1
$1,890 1Total for 515 - Fruit Commission
Page 82 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
652 - Highline Community College
Indelible Media LLC
328 1/2 W Meeker St #3
Kent, WA 98032-
To continue and expand the college’s community engagement and outreach initiatives in local immigrant and refugee communities. This contract
fits the exemption in ESHB 2921 because Highline Community College is Higher Education and funding is not state funds or tuition.
Competitive
CE - Social Research Services
Start Date: 9/20/2010
End Date: 6/30/2011
Reporting Date: 9/17/2010
Federal:
State:
Other:
Total:
$35,000
$35,000
Current Contract Total: $35,000
Accepted
Totals by Service Description:
CE - Social Research Services $35,000 1
Totals by Filing Type:
New Contract $35,000 1
$35,000 1Total for 652 - Highline Community College
Page 83 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
670 - Seattle Community Colleges - District 6
Alford Group, The
2033 6th Ave #700
Seattle, WA 98121-
Conduct a campaign feasibility study for a $40 million health education facility on the Seattle Central Community College campus.
Competitive
CA - Management/Organizational Services
Start Date: 8/17/2010
End Date: 12/31/2010
Reporting Date: 9/10/2010
Federal:
State:
Other:
Total:
$42,000
$42,000
Current Contract Total: $42,000
Accepted
Totals by Service Description:
CA - Management/Organizational Services $42,000 1
Totals by Filing Type:
New Contract $42,000 1
$42,000 1Total for 670 - Seattle Community Colleges - District 6
Page 84 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
676 - Spokane Community Colleges - District 17
Asbell Professional Group
140 South Arthur
Suite 690
Spokane, WA 99202-2260
improved working relationships between employees of SFCC
Sole Source
CA - Management/Organizational Services
Start Date: 7/20/2009
End Date: 6/30/2010
Reporting Date: 9/14/2010
Federal:
State:
Other:
Total:
$6,219
$2,783
$9,002
Current Contract Total: $9,002
Accepted
The Gurian Institute
PO Box 60160
Colorado Springs, CO 80960-0160
full day professional development training at SFCC for Spokane County Head Start/ECEAP/EHS on May 3, 2010 for approximately 150 staff
Sole Source
CA - Management/Organizational Services
Start Date: 5/3/2010
End Date: 5/3/2010
Reporting Date: 9/14/2010
Federal:
State:
Other:
Total:
$5,500
$5,500
Current Contract Total: $5,500
Accepted
Koch, Lisa
1415 S KAHUNA DR
SPOKANE VALLEY, WA 99212-
Behavior Intervention Consultation Services
Competitive
CJ - Employee Training Services
Start Date: 12/10/2009
End Date: 9/30/2010
Reporting Date: 9/14/2010
Federal:
State:
Other:
Total:
$13,500
$13,500
Current Contract Total: $13,500
Accepted
Page 85 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Knuth Research Inc.
717 E BLACKHAWK DR
SPOKANE, WA 99208-
provide NSF grant evaluation for the period 7/1/2009 - 6/30/2010.
This activity is funded by NSF Grant #ATE0603496 from the National Science Foundation. The selection of this contractor was part of the grant
approval process, and the scope of work, deliverables and reporting requirements are specified in the grant.
Sole Source
CZ - Other Services
Start Date: 7/1/2009
End Date: 6/30/2010
Reporting Date: 9/14/2010
Federal:
State:
Other:
Total:
$5,000
$5,000
Current Contract Total: $5,000
Accepted
Dowden Associates
15828 Manion Way NE
Duvall, WA 98019
preparation of Title III Strengthening Institutions grant application.
Sole Source
CA - Management/Organizational Services
Start Date: 7/1/2009
End Date: 6/30/2010
Reporting Date: 9/14/2010
Federal:
State:
Other:
Total:
$27,845
$27,845
Current Contract Total: $27,845
Accepted
Dickson consulting Services LLC
2513 E Nicklaus Ave
Spokane, WA 99223-
curriculum development relating to various LEAN topics
Sole Source
CZ - Other Services
Start Date: 6/4/2010
End Date: 6/30/2010
Reporting Date: 9/14/2010
Federal:
State:
Other:
Total:
$6,500
$6,500
Current Contract Total: $6,500
Accepted
Page 86 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
CSV
237 PENTONVILLE RD
London, England -
interview and select prospective students for international internship
Sole Source
CZ - Other Services
Start Date: 11/2/2009
End Date: 12/31/2009
Reporting Date: 9/14/2010
Federal:
State:
Other:
Total:
$12,229
$12,229
Current Contract Total: $12,229
Accepted
JA Study Abroad Center
Shinjuku-1 - Land Tower 4F #1578, 6-5-1 Nishi-Shinjuku
Shinjuku-ku, Tokyo 163-1304, Japan -
recruit international college students
Sole Source
CK - Recruiting Services
Start Date: 7/1/2009
End Date: 6/30/2010
Reporting Date: 9/16/2010
Federal:
State:
Other:
Total:
$2,600
$3,552
$6,152
Current Contract Total: $6,152
Accepted
Totals by Service Description:
CA - Management/Organizational Services $42,347 3
CJ - Employee Training Services $13,500 1
CK - Recruiting Services $6,152 1
CZ - Other Services $23,729 3
Totals by Filing Type:
New Contract $85,728 8
$85,728 8Total for 676 - Spokane Community Colleges - District 17
Page 87 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
695 - Bates Technical College
Johnson Stone Pagano
1501 Regents Blvd., Suite 100
Fircrest, WA 98466-6060
Perform a comprehensive, independent audit of KBTC-TV for fiscal year 2009-2010.
Competitive
CZ - Other Services
Start Date: 10/4/2010
End Date: 11/30/2010
Reporting Date: 9/20/2010
Federal:
State:
Other:
Total:
$14,000
$14,000
Current Contract Total: $14,000
Accepted
Sunrise Media
9417 31st Ave NW
Seattle, WA 98117-
Provide marketing/media services; Assist in developing program marketing objectives and strategies. Develop communication plans based on
KBTC program marketing objectives and strategies. Provide continuous account service and consultation to ensure prompt completion of projects
as needed. Provide support analysis in specialized areas of multi-channel program strategy and marketing as needed.
Competitive
CG - Marketing Services
Start Date: 8/1/2010
End Date: 7/31/2011
Reporting Date: 9/15/2010
Federal:
State:
Other:
Total:
$5,400
$5,400
Current Contract Total: $5,400
Accepted
Totals by Service Description:
CG - Marketing Services $5,400 1
CZ - Other Services $14,000 1
Totals by Filing Type:
New Contract $19,400 2
$19,400 2Total for 695 - Bates Technical College
Page 88 of 89
State of Washington
Office of Financial Management
8:28:47AM
10/8/2010
AllAgency:
9/1/2010 to 9/30/2010Reporting Period
Reported Personal Service Contracts Summarized by
Agency
Grand Total by Service Description:
CA - Management/Organizational Services $1,471,789 17
CC - Financial Services $25,000 2
CE - Social Research Services $92,200 9
CF - Technical Research Services $131,940 4
CG - Marketing Services $152,437 7
CH - Communications Services $21,406 1
CJ - Employee Training Services $13,500 1
CK - Recruiting Services $6,152 1
CZ - Other Services $195,574 10
JK - Architectural & Engineering Services $67,598,444 172
Total$69,708,442 224
Grand Total by Filing Type:
Amendment $39,443,371 146
New Contract $30,265,071 78
$69,708,442 224 Total
Grand Total by Filing Category:
$30,555,056 93
Competitive, 50% Change, $5,000+, Approve $39,153,386 131
$69,708,442 224Total
Page 89 of 89