    Lanco Babandh Power Private Ltd.

    APPENDIX X

    DOCUMENTATION

    1.1 Drawing Document for Approval/Information:

    a) Complete Control and Instrumentation Material Take Off(MTO)/ Bill of Quantity (BOQ)

    b) Control System Configuration Drawing showingconnectivity among all control systems

    c) Filled out Technical Schedule for C&I

    d) Data sheets of all major C&I items

    e) Measurement Points with type of measurements for SWAS

    f) List of List of Measurement Points with type of measurements for CEMS

    g) UPS power and non UPS supply requirement for C&I

    h) Heat Load requirement for Central Control Room.

    i) Technical deviations listed as per list of deviations for C&I.

    j) List of Mandatory Spares C&I

    k) List of Recommended Spare for C&I

    l) List of sub Vendors for C&I Refer QA documents

    m) Conceptual Control Room Layout drawing

    n) Conceptual Power Supply Distribution Scheme

    o) Availability calculation of DDCMIS and other controlsystems.

    p) Conceptual scheme of Machine monitoring system

    q) Drawing showing interface of DDCMIS/PLC with Drives

    r) Brief write up on plant control philosophy including thefunctional distribution of control to various control system andwithin DDCMIS

    s) Catalogues of C&I items offered.

    2x660 MW, Unit 1 & 2 Vol-V, C&I, Sec - 15 1 of 3

  • 7/29/2019 15. Section - 15, Documentation_1320

    2/3

    Lanco Babandh Power Private Ltd.

    APPENDIX X

    1.2 Drawing Document during contract execution:

    S.No.

    Drawing/Document

    Categorizatio

    n for LBPPLapproval(A -

    Approval,R - Review,

    I Information)

    1 Drawing Document Schedule A2 Control System Configuration Drawing showing

    connectivity among all control systemsA

    3 Purchase Specification of All C&I items R4 Complete Instrument List for entire Plant I5 Control Room/ Control Equipment Room Layout A6 SWAS Scheme R7 Power Supply Distribution Scheme R8 DDCMIS I/O List I9 SOE List R10 Alarm List R11 List of Soft I/O points between DDCMIS and other control

    systemsI

    12 Control Valve Sizing Calculation R13 Flow Element sizing calculation R14 Thermowell Wake Frequency and Stress Calculation R

    15 SWAS room and CEMS shelter arrangement drawing R16 Instrument Installation Drawing R17 Instrument Source Connection Drawing R18 Control Philosophy Document A19 Electrical Drive Interface Drawing with DDCMIS/PLC/Local

    Control Panel20 Control Loop Drawing A21 Control Logic Drawing A22 Local control Panel, Unit Control Desk, Unit Control Board,

    Unit Control Panel GA Drawing, wiring diagram, terminaldrawing, and foundation details

    A

    23 Dynamic Graphics Drawing I24 Performance Monitoring Calculation Details R25 CMIMS configuration and specification details R26 Instrument Location Plan I27 Instrument Junction Box Schedule I28 Instrument Cable Schedule I29 Instrument Cable Interconnection Drawing I30 O&M Manual for all C&I items I31 Erection/Installation and Commissioning Manual of all C&I

    ItemsI

    32 FAT,SAT procedure of all C&I items R

    33 Software and Hardware Design Manual of all the controlsystems I

    2x660 MW, Unit 1 & 2 Vol-V, C&I, Sec - 15 2 of 3

  • 7/29/2019 15. Section - 15, Documentation_1320

    3/3

    Lanco Babandh Power Private Ltd.

    APPENDIX X

    S.

    No.

    Drawing/Document

    Categorization for LBPPLapproval

    (A -

    Approval,R - Review,I

    Information)34 As Built Drawing I35 All other documents specifically called for in various sections of

    specification36 All other documents not specifically mentioned here but required for

    completion of engineering work and proper coordination shall be unit wise

    1.3 OPERATION & MAINTENANCE INSTRUCTION MANUAL:

    The Contractor shall furnish operation & maintenance instructionmanual for all the instruments/equipment supplied by them.

    These shall be sent along with the instruments/equipment.Instruction regarding installation, testing, calibration, repair,maintenance and commissioning of the instruments/equipment sixmonths in advance.

    In addition the Contractor shall furnish instruction manual onoperation & maintenance of their overall C&I system. This shall befurnished to the Customer/Consultants Six (6) months before the

    commissioning date of the unit.

    2x660 MW, Unit 1 & 2 Vol-V, C&I, Sec - 15 3 of 3