Upload
vin
View
19
Download
0
Tags:
Embed Size (px)
DESCRIPTION
15 h ROAD PAVEMENTS FORUM East London May 2008 HMA Task Group. Resolution #2 From last November. - PowerPoint PPT Presentation
Citation preview
15h ROAD PAVEMENTS FORUM
East LondonMay 2008
HMA Task Group
Resolution #2 From last November
• That an RPF task group be established under the leadership of Arthur Taute to coordinate activities relating to HMA design, quality assurance, performance and specifications in line with the recommendations of CAPSA’07
HMA Progress
Issue Groups
• Mix Design– Many activities on research and
development• Gautrans forensic study
• APT
• Rut Challenge
– Implementation Lacking
Mix Design Issues
• Aggregate Packing– Bailey– DASR– (Dominant Aggregate Size Range) – Denneman
SATC 2007• Binder Stiffness– Problems with current specification that it can span
across several performance grades – Bahia/ Marais/ AsAc
• Binder Durability– Johan Muller
Mix Design Implementation
• Performance – need criteria– Rutting• Rut testing devices
– Cracking• Lots of cracking – water sensitive bases• Variability
– Permeability• Water sensitive bases• Variability
Performance Investigations
• Premature Cracking and Rutting as well as Inconsistency between design and actual asphalt laid– Gauteng Forensic Study
• Inappropriate use (tender mixes at intersections)• Gauteng Forensic Study
• Permeability– Rossmann et al CAPSA07
• Rutting– Verhaeghe et al CAPSA07– APT - Rut Challenge - Gautrans/Sabita - CSIR/Industry
Variability and Risk
Pavement Design
• Implementation– Pavement designs need to be improved and
to take available materials into account– Specifications need revision
Variability and Risk
Issue Groups
• Quality Management– Components
• Problems with binder consistency• Problems with aggregate consistency
– Implementation• Quality problems in practice• Entire process that can influence quality needs
improvement – from design and specification through procurement, mix design and approval, manufacture and construction
Construction Issues
• Variability within lots
• Consistency throughout project
• Uniformity across length and breadth of lanes
• Diversity of aggregate supply
• Regularity of supply and surface
• Homogeneity of materials
Problem Statement
• We can be as smart as we like on HMA design etc but then we have to be able to implement the design.
• With new mix paradigm (AC and very heavy loads), variability issues are over-riding any design processes and decisions in respect of the performance of the product.
HMA Task Group
Core
• A Taute
• D Rossmann
• H Marais
• PA Myburgh
• B Verhaeghe
Corresponding
• JA Grobler, D Pretorius
• JC vd Walt, E Sadzik, S Oloo
• J Wise AN Other
• T Distin, L Sampson
• E Denneman
How do we improve implementation in the light of the following
• Design – lack of resources• Specification - no new criteria - old• Procurement – cheapest price• Mix design approval – cumbersome - discourages
changes during works• Manufacture – commercial interests• Construction – focus on doing whatever one needs to,
to get acceptance• Acceptance testing – statistical methods which
assume reasonable uniformity and do often not reject substandard materials
Can Pay Factors Help?
• USA – common• RSA do have some penalties and partial payment
but no bonus for good quality work.• Clients feel they deserve quality but are not
always getting it unless the CE and contractor are “special”
• May allow for some discounts by those who know they can rely on PF>1
• PF should not be considered as a bonus but rather payment for better quality.
Proposed Pay Factors in Sabita Manual and at CAPSA
• Bonus/penalty for riding quality – some benefits but limited general acceptance
• Sabita Manual 5 – proposed but not retained – specification issue
• CAPSA proposals for PF based on consistency and average of – Binder Content– Density
– Now Aggregate Gradation
Binder Content Pay Factors – CAPSA07
Density Pay Factors – CAPSA07
Aggregate Gradation
• Substantial variation between individual samples. Many points on the road that are out of specification.
• Lot averages generally OK
• What do to about lots that do not meet specification ?
• How to encourage conformance?
Problem Statement
Improved siewe ,stockpile method at plant
9092949698
100
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63 65 67 STD ST 1 ST 1 ST 1 ST 2 ST 2 ST 3 ST 3 ST 4 ST 4 ST 5 ST 5 ST 5 ST 5
6.7 % passing
Lower Limit
80
85
90
95
100
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63 65 67 STD ST 1 ST 1 ST 1 ST 2 ST 2 ST 3 ST 3 ST 4 ST 4 ST 5 ST 5 ST 5 ST 5
4.75 % passing
Upper Limit
Lower Limit
60
65
70
75
80
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63 65 67 STD ST 1 ST 1 ST 1 ST 2 ST 2 ST 3 ST 3 ST 4 ST 4 ST 5 ST 5 ST 5 ST 5
2.36 mm
Upper Limit
Lower Limit
30354045505560
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63 65 67 STD ST 1 ST 1 ST 1 ST 2 ST 2 ST 3 ST 3 ST 4 ST 4 ST 5 ST 5 ST 5 ST 5
1.18 mm
1.18 mm
20
25
30
35
40
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63 65 67 STD ST 1 ST 1 ST 1 ST 2 ST 2 ST 3 ST 3 ST 4 ST 4 ST 5 ST 5 ST 5 ST 5
0.600 mm
Upper Limit
1015202530
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63 65 67 STD ST 1 ST 1 ST 1 ST 2 ST 2 ST 3 ST 3 ST 4 ST 4 ST 5 ST 5 ST 5 ST 5
0.300 mm
0.300 mm
510152025
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63 65 67 STD ST 1 ST 1 ST 1 ST 2 ST 2 ST 3 ST 3 ST 4 ST 4 ST 5 ST 5 ST 5 ST 5
0.150 mm
0.150 mm
0.05.0
10.015.020.0
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63 65 67 STD ST 1 ST 1 ST 1 ST 2 ST 2 ST 3 ST 3 ST 4 ST 4 ST 5 ST 5 ST 5 ST 5
0.075 mm
0.075 mm
Problem Statement
• Variation occurs through all sieve sizes of source material
• It is possible to reduce variation by premixing before loading into bins
• Propose a Pay Factor to accommodate the additional costs
Crusher Dust Variability - Individual Sieves
Crusher Dust Variation
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
9.5 6.7 4.75 2.36 1.18 0.600 0.300 0.150 0.075
Sieve Size
Valu
e_ Stdev
Spec Max
Control Stdev
Crusher Dust Variation
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
9.5 6.7 4.75 2.36 1.18 0.600 0.300 0.150 0.075
Sieve Size
Valu
e_ Stdev
Spec Max
Control Stdev
Crusher Dust Variation
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
9.5 6.7 4.75 2.36 1.18 0.600 0.300 0.150 0.075
Sieve Size
Valu
e_ Stdev
Spec Max
Control Stdev
Grading Pay Factor
• Need a Pay Factor that provides an indication of the deviation of the average grading of a lot from the target.
• Consider the sum of the absolute values of the difference between the percentage passing each sieve in a lot and the target grading
• Problem is that there can be substantial variation within a lot but the average can be OK
• Therefore need a parameter provides and indication of this variability
•
Grading Pay Factor Contd.
• Certain sieves are more critical than others– Eg current spec allows +- 5, +-4, +-3 and +-2 for
various sieves with the 0.150 and 0.075 being the most critical (+-2)
• The 2.36 mm sieve is also critical in continuously graded mixes.
• Therefore the absolute value of the differences needs to be weighted differently for various sieves
Grading Pay Factor Contd.
• Must try to ensure consistency when applying the Pay Factor across different mixes and gradations
• Therefore need to standardize on number of sieves being considered and weighting that is applied.
Consider weighted sum of differences
• Sum the weighted absolute value of differences between actual grading and target grading on selected sieves.
• Use weightings to correspond to current allowable variation
• Add extra weight for other important sieves.
Illustrative Weighted Sum of DifferencesSingle source – crusher run
Consider weighted sum of standard deviations
• Sum the weighted value of standard deviations on selected sieves.
• Use same weightings as on differences
Example of Sum of weighted std dev per sieve
Proposed Criteria
• Use weighting of 1 on all sieves and 2 on 2.36mm, 0.150mm and 0.075mm for medium graded asphalt
• Use a total weighting of 12• Vary the weighting and critical sieves depending
on mix design and critical issues.• Use values for Sum Weighted Std Dev as follows:• <12 – low variability• 12- 17 medium variability• >17 high variability
Proposed Pay Factor for Grading Consistency
Pay Factor
• Pay Factor Grading
– SStd>17 = 1.06 – 2 x WD (max 1.0 min 0.85)– SSTd>12 <17 = 1.12 - 2 x WD (max 1.05 min 0.85)– SStd<12 = 1.20 – 2 * WD (max 1.10 min 0.85)– WD = Weighted sum of absolute values of
differences between actual % passing and target % passing on sieves from 6.37mm to 0.075mm (9 sieves) where weight is 1 for all sieves except 2.36mm, 0.150mm and 0.075mm where it is 2.
– SWStd = Sum of Weighted Stdev for the lot on same 9 sieves using the same weighting
Example 1 – Lot with medium variability and low difference
SampleDate
Source/ MixTonnage
Lane
Lot No Target SPEC 78 79 80 81 82 83 84 Avg Std Dev Weight (Sum 12)
Position 15.82 15.7 15.6 15.5 15.4 15.27 15.18
Weight (Sum 12)
Binder Content 5.1 4.8 - 5.4 5.57 5.29 4.85 5.37 5.41 5.54 5.43 5.35 0.24 0.92
SIEVE SIZE
26.5 100 100 100 100 100 100 100 100 100 100.00 0.00 0.0 0 0.019.0 100 100 100 100 100 100 100 100 100 100.00 0.00 0.0 0 0.013.2 100 100 100 100 100 100 100 100 100 100.00 0.00 0.0 0 0.09.5 98 94 - 100 99 99 99 98 99 98 100 98.86 0.69 0.9 1 0.96.7 85 80 - 90 87 83 81 84 84 85 90 84.86 2.91 0.1 1 0.14.75 69 65 - 73 72 66 60 67 65 69 73 67.43 4.43 1.6 1 1.62.36 43 39 - 47 47 43 38 43 43 46 47 43.86 6.37 0.9 2 1.71.18 29 25 - 33 31 29 26 29 29 30 31 29.29 1.70 0.3 1 0.3
0.600 21 17 - 25 22 21 20 21 21 22 22 21.29 0.76 0.3 1 0.30.300 15 12 - 18 15 14 14 15 14 15 15 14.57 0.53 0.4 1 0.40.150 10 8 - 12 11 11 10 11 11 11 11 10.86 0.76 0.9 2 1.70.075 7 6 - 8 8.3 7.7 7.3 7.7 7.5 7.9 8 7.77 0.66 0.8 2 1.5
18.81 6.1 12 8.5 89
Abs (Target -
Avg)
Weighted Diff
Pay Factor
Percentage Passing
LOT A6 Km 15.839 to Km 15.10022/11/2007A/C MED
357.08West Bound Fast Lane
Example 2: Lot with low variability but higher difference
SampleDate
Source/ MixTonnage
Lane
Lot No Target SPEC 60 61 62 63 64 29./11 30./11 AVG STD.
Position 17.28 17.14 16.98 16.84 16.72 Plant Plant DEV.Binder Content 5.1 4.8 - 5.4 4.81 4.75 4.86 4.94 4.71 5.15 4.97 4.88 0.15 1.01
SIEVE SIZE
26.5 100 100 100 100 100 100 100 100 100 100.00 0.00 0.0 0 0.019.0 100 100 100 100 100 100 100 100 100 100.00 0.00 0.0 0 0.013.2 100 100 100 100 100 100 100 100 100 100.00 0.00 0.0 0 0.09.5 98 94 - 100 99 98 99 99 99 99 99 98.86 0.38 0.9 1 0.96.7 85 80 - 90 83 82 82 84 81 86 84 83.14 1.68 1.9 1 1.94.75 69 65 - 73 68 66 67 67 67 72 67 67.71 1.98 1.3 1 1.32.36 43 39 - 47 43 44 42 43 43 47 45 43.86 3.35 0.9 2 1.71.18 29 25 - 33 27 28 27 28 28 29 30 28.14 1.07 0.9 1 0.9
0.600 21 17 - 25 20 20 19 20 20 19 20 19.71 0.49 1.3 1 1.30.300 15 12 - 18 14 13 13 14 13 13 14 13.43 0.53 1.6 1 1.60.150 10 8 - 12 10 10 10 10 10 10 10 10.00 0.00 0.0 2 0.00.075 7 6 - 8 7.7 7.4 7.5 7.6 7 6.5 7.4 7.30 0.83 0.3 2 0.6
10.31 8.9 12 10.0 100
Percentage Passing
Pay Factor
Abs (Target -
Avg)
Weighted Diff
Weight (Sum 12)
LOT 11 Km 17.3 to Km 16.614/11/2007A/C MED
280West Bound Fast Lane
Resulting Pay Factors for 10 lots
11 12 13 14 15 16 17 18 19 20Spec Weights
98 1 0.8 0.6 1.2 1.1 1.3 0.8 1.0 0.8 1.2 1.085 1 1.7 2.9 2.0 0.9 0.8 0.2 1.8 0.7 2.3 0.869 1 1.7 2.8 2.2 1.9 0.3 2.3 0.3 3.3 4.4 2.443 1 2.0 1.2 0.8 1.6 2.0 0.8 2.8 0.7 0.1 0.229 2 1.0 0.6 1.2 0.6 0.0 1.2 3.0 0.3 0.2 2.021 1 1.1 0.1 1.4 0.3 0.3 0.3 1.0 0.3 0.2 0.815 1 1.4 0.5 1.0 0.6 0.5 0.3 0.5 0.2 0.1 1.010 2 0.2 1.3 0.4 0.9 1.5 1.5 2.5 1.3 1.8 0.87 2 0.7 1.3 0.8 1.4 1.7 1.6 2.4 1.7 2.0 1.0
Sum WAbs 12 9.8 10.7 9.8 8.0 6.9 8.4 14.1 8.5 11.2 9.0100.4 90.5 92.5 96.0 98.2 89.2 83.8 94.9 89.5 94.1 92.9
11.0 12.6 13.8 14.0 12.5 20.5 14.8 13.4 16.0 15.6
Absolute Value of Weighted Deviation of Lot from target
Lot Number
Pay Factor
Sum of Weighted Stdev for lot (SWStd)
Action Plan
• Mix Design– Need criteria for various rut testing devices – ongoing
research rut challenge etc– Need criteria for permeability – problem is mix
variability resulting in variable results– Need to start implementing Pay Factors
• Require trial specification and feedback throughout industry.• Have used riding quality Pay Factors with success in the past
– therefore should be able to use others.• Need to assess how to combine Pay Factors – consider
multiplication• Need to start the debate and start moving away from what we
were doing.