  • OptiX RTN 950 Radio Transmission SystemV100R003C03

    Commissioning Guide (U2000)

    Issue 01Date 2011-10-30

    HUAWEI TECHNOLOGIES CO., LTD.

  • Copyright Huawei Technologies Co., Ltd. 2011. All rights reserved.No part of this document may be reproduced or transmitted in any form or by any means without prior writtenconsent of Huawei Technologies Co., Ltd. Trademarks and Permissions

    and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd.All other trademarks and trade names mentioned in this document are the property of their respective holders. NoticeThe purchased products, services and features are stipulated by the contract made between Huawei and thecustomer. All or part of the products, services and features described in this document may not be within thepurchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information,and recommendations in this document are provided "AS IS" without warranties, guarantees or representationsof any kind, either express or implied.

    The information in this document is subject to change without notice. Every effort has been made in thepreparation of this document to ensure accuracy of the contents, but all statements, information, andrecommendations in this document do not constitute the warranty of any kind, express or implied. Huawei Technologies Co., Ltd.Address: Huawei Industrial Base

    Bantian, LonggangShenzhen 518129People's Republic of China

    Website: http://www.huawei.comEmail: [email protected]

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    i

  • About This Document

    Related VersionsThe following table lists the product versions related to this document.

    Product Name VersionOptiX RTN 950 V100R003C03iManager U2000 V100R006C00

    Intended AudienceThis document describes how to commission the OptiX RTN 950, including preparations beforecommissioning, site commissioning, and system commissioning.The intended audience of this document are:Installation and commissioning engineers

    Symbol ConventionsThe symbols that may be found in this document are defined as follows.

    Symbol Description

    Indicates a hazard with a high level of risk,which if not avoided, will result in death orserious injury.

    Indicates a hazard with a medium or low levelof risk, which if not avoided, could result inminor or moderate injury.

    Indicates a potentially hazardous situation,which if not avoided, could result inequipment damage, data loss, performancedegradation, or unexpected results.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) About This Document

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    ii

  • Symbol Description

    Indicates a tip that may help you solve aproblem or save time.

    Provides additional information to emphasizeor supplement important points of the maintext.

    General ConventionsThe general conventions that may be found in this document are defined as follows.

    Convention DescriptionTimes New Roman Normal paragraphs are in Times New Roman.Boldface Names of files, directories, folders, and users are in

    boldface. For example, log in as user root.Italic Book titles are in italics.Courier New Examples of information displayed on the screen are in

    Courier New.

    Command ConventionsThe command conventions that may be found in this document are defined as follows.

    Convention DescriptionBoldface The keywords of a command line are in boldface.Italic Command arguments are in italics.[ ] Items (keywords or arguments) in brackets [ ] are optional.{ x | y | ... } Optional items are grouped in braces and separated by

    vertical bars. One item is selected.[ x | y | ... ] Optional items are grouped in brackets and separated by

    vertical bars. One item is selected or no item is selected.{ x | y | ... }* Optional items are grouped in braces and separated by

    vertical bars. A minimum of one item or a maximum of allitems can be selected.

    [ x | y | ... ]* Optional items are grouped in brackets and separated byvertical bars. Several items or no item can be selected.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) About This Document

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    iii

  • GUI ConventionsThe GUI conventions that may be found in this document are defined as follows.

    Convention DescriptionBoldface Buttons, menus, parameters, tabs, window, and dialog titles

    are in boldface. For example, click OK.> Multi-level menus are in boldface and separated by the ">"

    signs. For example, choose File > Create > Folder.

    Change HistoryUpdates between document issues are cumulative. Therefore, the latest document issue containsall updates made in previous issues.

    Updates in Issue 01 (2011-10-30) Based on Product Version V100R003C03This document is the first release of the V100R003C03 version.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) About This Document

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    iv

  • Contents

    About This Document.....................................................................................................................ii1 Safety Precautions.........................................................................................................................1

    1.1 General Safety Precautions.................................................................................................................................21.2 Warning and Safety Symbols.............................................................................................................................31.3 Electrical Safety..................................................................................................................................................41.4 Environment of Flammable Gas.........................................................................................................................71.5 Storage Batteries.................................................................................................................................................71.6 Radiation.............................................................................................................................................................9

    1.6.1 Safe Usage of Optical Fibers.....................................................................................................................91.6.2 Electromagnetic Exposure.......................................................................................................................111.6.3 Forbidden Areas......................................................................................................................................111.6.4 Laser........................................................................................................................................................111.6.5 Microwave...............................................................................................................................................12

    1.7 Working at Heights...........................................................................................................................................131.7.1 Hoisting Heavy Objects...........................................................................................................................131.7.2 Using Ladders..........................................................................................................................................14

    1.8 Mechanical Safety............................................................................................................................................161.9 Other Precautions.............................................................................................................................................17

    2 Notices for High-Risk Operations...........................................................................................192.1 Operation Guide for the Toggle Lever Switch.................................................................................................202.2 Operation Guide for the IF Jumper...................................................................................................................222.3 Operation Guide for the IF Cable.....................................................................................................................232.4 Operation Guide for the IF Board.....................................................................................................................24

    3 Commissioning Preparations....................................................................................................263.1 Commissioning Process....................................................................................................................................27

    3.1.1 Site Commissioning Process...................................................................................................................273.1.2 System Commissioning Process..............................................................................................................29

    3.2 Determining the Commissioning Method........................................................................................................303.3 Preparing Documents and Tools.......................................................................................................................313.4 Checking Commissioning Conditions..............................................................................................................33

    3.4.1 Site Commissioning.................................................................................................................................333.4.2 System Commissioning...........................................................................................................................33

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) Contents

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    v

  • 4 Site Commissioning....................................................................................................................344.1 Powering On the Equipment.............................................................................................................................354.2 Configuring Site Commissioning Data by Using the Web LCT......................................................................37

    4.2.1 Connecting the Web LCT to the IDU......................................................................................................464.2.2 Creating NEs by Using the Search Method.............................................................................................484.2.3 Logging In to an NE................................................................................................................................514.2.4 Changing the NE ID................................................................................................................................524.2.5 Changing the NE Name...........................................................................................................................534.2.6 Setting NE Communication Parameters..................................................................................................544.2.7 Configuring Logical Boards....................................................................................................................554.2.8 Creating an IF 1+1 Protection Group......................................................................................................564.2.9 Configuring the IF/ODU Information of a Radio Link...........................................................................584.2.10 Creating an XPIC Workgroup...............................................................................................................594.2.11 Setting the Hybrid/AM Attributes of the XPIC Workgroup.................................................................604.2.12 Synchronizing NE Time........................................................................................................................614.2.13 Configuring the Orderwire....................................................................................................................624.2.14 Checking Alarms...................................................................................................................................63

    4.3 Configuring Site Commissioning Data by Using the Handheld Tool..............................................................644.3.1 Connecting the Handheld Tool to the IDU..............................................................................................644.3.2 Setting NE Attributes...............................................................................................................................664.3.3 Configuring a Radio Link........................................................................................................................684.3.4 Checking Alarms.....................................................................................................................................72

    4.4 Testing Connectivity of Cables........................................................................................................................734.4.1 Testing Connectivity of E1 Cables by Using the Web LCT...................................................................734.4.2 Testing Connectivity of E1 Cables by Using the Handheld Tool...........................................................744.4.3 Testing Connectivity of Network Cables................................................................................................764.4.4 Checking Fiber Jumper Connection........................................................................................................77

    4.5 Aligning the Antennas......................................................................................................................................794.5.1 Main Lobe and Side Lobes......................................................................................................................794.5.2 Aligning Single-Polarized Antennas.......................................................................................................824.5.3 Aligning Dual-Polarized Antennas..........................................................................................................85

    4.6 Checking the Status of Radio Links.................................................................................................................884.7 Querying the DCN Status.................................................................................................................................89

    5 System Commissioning..............................................................................................................905.1 Configuring Networkwide Service Data..........................................................................................................92

    5.1.1 Creating NEs by Using the Search Method.............................................................................................925.1.2 Changing the NE ID................................................................................................................................945.1.3 Changing the NE Name...........................................................................................................................955.1.4 Setting NE Communication Parameters..................................................................................................955.1.5 Configuring the Logical Board................................................................................................................965.1.6 Creating an IF 1+1 Protection Group......................................................................................................975.1.7 Configuring the IF/ODU Information of a Radio Link...........................................................................99

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) Contents

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    vi

  • 5.1.8 Configuring ATPC Attributes...............................................................................................................1015.1.9 Synchronizing the NE Time..................................................................................................................1025.1.10 Creating the Cross-Connections of Point-to-Point Services................................................................1055.1.11 Configuring the Clock Sources............................................................................................................1065.1.12 Configuring Orderwire........................................................................................................................107

    5.2 Testing E1 Services........................................................................................................................................1085.2.1 Testing E1 Services by Using a BER Tester.........................................................................................1085.2.2 Testing E1 Services Using PRBS..........................................................................................................110

    5.3 Testing Ethernet Services...............................................................................................................................1115.4 Testing ATM Services....................................................................................................................................1155.5 Testing AM Switching....................................................................................................................................118

    5.5.1 Testing AM Switching by Using a BER Tester....................................................................................1185.5.2 Testing AM Switching Without a BER Tester......................................................................................120

    5.6 Testing Protection Switching..........................................................................................................................1225.6.1 Testing IF 1+1 Switching......................................................................................................................1225.6.2 Testing N+1 Protection Switching........................................................................................................1255.6.3 Testing SNCP Switching.......................................................................................................................1285.6.4 Testing ERPS Switching.......................................................................................................................1325.6.5 Testing MPLS APS Protection Switching.............................................................................................1335.6.6 Testing Linear MSP Switching..............................................................................................................136

    5.7 Checking the Clock Status..............................................................................................................................1405.8 Testing the FM over a Radio Link..................................................................................................................1405.9 Testing 24-Hour BER.....................................................................................................................................144

    6 Introduction to the Handheld Tool........................................................................................1476.1 Functions and Features...................................................................................................................................1486.2 Operation Interface.........................................................................................................................................148

    7 Configuration Example of Service Data................................................................................1507.1 Networking Diagram......................................................................................................................................1517.2 Board Configurations.....................................................................................................................................1517.3 Service Planning.............................................................................................................................................1527.4 Configuration Process.....................................................................................................................................154

    A Parameters Description...........................................................................................................158A.1 Parameter Description: NE Searching...........................................................................................................160A.2 Parameter Description: Login to an NE.........................................................................................................164A.3 Parameter Description: NE Attribute_NE ID Change...................................................................................164A.4 Parameter Description: Attribute_Changing NE IDs....................................................................................165A.5 Parameter Description: NE Communication Parameter Setting....................................................................166A.6 Parameter Description: Link Configuration_XPIC Workgroup_Creation....................................................168A.7 Parameter Description: Link Configuration_XPIC.......................................................................................173A.8 Parameter Description: Link Configuration_IF 1+1 Protection....................................................................180A.9 Parameter Description: IF 1+1 Protection_Create.........................................................................................183

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) Contents

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    vii

  • A.10 Parameter: Link Configuration_IF/ODU Configuration.............................................................................186A.11 Parameter Description: IF Interface_ATPC Attribute.................................................................................196A.12 Parameter Description: NE Time Synchronization.....................................................................................198A.13 Parameter Description: SDH Service Configuration_Creation...................................................................201A.14 Parameter Description: Clock Source Priority Table..................................................................................204A.15 Parameter Description: Orderwire_General................................................................................................205A.16 Parameter Description: Orderwire_Advanced.............................................................................................207

    B Glossary......................................................................................................................................209B.1 0-9..................................................................................................................................................................210B.2 A-E.................................................................................................................................................................210B.3 F-J..................................................................................................................................................................219B.4 K-O................................................................................................................................................................224B.5 P-T..................................................................................................................................................................230B.6 U-Z.................................................................................................................................................................239

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) Contents

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    viii

  • 1 Safety PrecautionsAbout This Chapter

    This topic describes the safety precautions that you must follow when installing, operating, andmaintaining Huawei devices.

    1.1 General Safety PrecautionsThis topic describes essential safety precautions that instruct you in the selection of measuringand testing instruments when you install, operate, and maintain Huawei devices.1.2 Warning and Safety SymbolsBefore using the equipment, note the following warning and safety symbols on the equipment.1.3 Electrical SafetyThis topic describes safety precautions for high voltage, lightning strikes, high leakage current,power cables, fuses, and ESD.1.4 Environment of Flammable GasThis topic describes safety precautions for the operating environment of a device.1.5 Storage BatteriesThis topic describes safety precautions for operations of storage batteries.1.6 RadiationThis topic describes safety precautions for electromagnetic exposure and lasers.1.7 Working at HeightsThis topic describes safety precautions for working at heights.1.8 Mechanical SafetyThis topic describes safety precautions for drilling holes, handling sharp objects, operating fans,and carrying heavy objects.1.9 Other PrecautionsThis topic describes safety precautions for removing and inserting boards, binding signal cables,and routing cables.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 1 Safety Precautions

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    1

  • 1.1 General Safety PrecautionsThis topic describes essential safety precautions that instruct you in the selection of measuringand testing instruments when you install, operate, and maintain Huawei devices.

    All Safety PrecautionsTo ensure the safety of humans and a device, follow the marks on the device and all the safetyprecautions in this document when installing, operating, and maintaining a device.The "CAUTION", "WARNING", and "DANGER" marks in this document do not cover all thesafety precautions that must be followed. They are supplements to the safety precautions.

    Local Laws and RegulationsWhen operating a device, always comply with the local laws and regulations. The safetyprecautions provided in the documents are in addition/supplementary to the local laws andregulations.

    Basic Installation RequirementsThe installation and maintenance personnel of Huawei devices must receive strict training andbe familiar with the proper operation methods and safety precautions before any operation.l Only trained and qualified personnel are permitted to install, operate, and maintain a device.l Only certified professionals are permitted to remove the safety facilities, and to troubleshoot

    and maintain the device.l Only the personnel authenticated or authorized by Huawei are permitted to replace or

    change the device or parts of the device (including software).l The operating personnel must immediately report the faults or errors that may cause safety

    problems to the person in charge.

    Grounding RequirementsThe grounding requirements are applicable to the device that needs to be grounded.l When installing the device, always connect the grounding facilities first. When removing

    the device, always disconnect the grounding facilities last.l Ensure that the grounding conductor is intact.l Do not operate the device in the absence of a suitably installed grounding conductor.l The device must be connected to the PGND permanently. Before operating the device,

    check the electrical connections of the device, and ensure that the device is properlygrounded.

    Human Safetyl When there is a risk of a lightning strike, do not operate the fixed terminal or touch the

    cables.l When there is risk of a lightning strike, unplug the AC power connector. Do not use the

    fixed terminal or touch the terminal or antenna connector.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 1 Safety Precautions

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    2

  • NOTEThe preceding requirements apply to wireless fixed station terminals.

    l To avoid electric shocks, do not connect safety extra-low voltage (SELV) circuits totelephone-network voltage (TNV) circuits.

    l Do not look into optical ports without eye protection. Otherwise, human eyes may be hurtby laser beams.

    l Before operating the device, wear an ESD protective coat, ESD gloves, and an ESD wriststrap. In addition, you need to get off the conductive objects, such as jewelry and watches,to prevent electric shock and burn.

    l In case of fire, escape from the building or site where the device is located and press thefire alarm bell or dial the telephone number for fire alarms. Do not enter the burning buildingagain in any situation.

    Device Safetyl Before any operation, install the device firmly on the ground or other rigid objects, such as

    on a wall or in a rack.l When the system is working, ensure that the ventilation hole is not blocked.l When installing the front panel, use a tool to tighten the screws firmly, if required.l After installing the device, clean up the packing materials.

    1.2 Warning and Safety SymbolsBefore using the equipment, note the following warning and safety symbols on the equipment.Table 1-1 lists the warning and safety symbols of the OptiX RTN 950 and their meanings.

    Table 1-1 Warning and safety symbols of the OptiX RTN 950Symbol Indication

    This symbol is for ESD protection.A notice with this symbol indicates that you should wearan ES wrist strap or glove when you touch a board.Otherwise, you may cause damage to the board.

    CLASS 1LASER

    PRODUCT

    LASERRADIATION

    DO NOT VIEW DIRECTLYWITH OPTICALINSTRUMENTS

    CLASS 1M LASERPRODUCT

    This symbol is for the laser class.A notice with this symbol indicates the class of the laser.Avoid direct exposure to the laser beams. Otherwise, it maydamage you eyes or skin.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 1 Safety Precautions

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    3

  • Symbol IndicationA notice with this symbol indicates where the subrack isgrounded.

    ATTENTION CLEAN PERIODICALLY

    A notice with this symbol indicates that the air filter shouldbe cleaned periodically.

    DON'T TOUCH THEFAN LEAVES BEFORETHEY SLOW DOWN !

    This symbol is for fan safety.A notice with this symbol indicates that the fan leavesshould not be touched when the fan is rotating.

    1.3 Electrical SafetyThis topic describes safety precautions for high voltage, lightning strikes, high leakage current,power cables, fuses, and ESD.

    High Voltage

    DANGERl A high-voltage power supply provides power for device operations. Direct human contact

    with the high voltage power supply or human contact through damp objects can be fatal.l Unspecified or unauthorized high voltage operations could result in fire or electric shock, or

    both.

    ThunderstormThe requirements apply only to wireless base stations or devices with antennas and feeders.

    DANGERDo not perform operations on high voltage, AC power, towers, or backstays in stormy weatherconditions.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 1 Safety Precautions

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    4

  • High Leakage Current

    WARNINGBefore powering on a device, ground the device. Otherwise, the safety of humans and the devicecannot be ensured.

    If a high leakage current mark is labeled near the power connector of the device, you mustconnect the PGND terminal on the shell to the ground before connecting the device to an A/Cinput power supply. This is to prevent the electric shock caused by leakage current of the device.

    Power Cables

    DANGERDo not install or remove the power cable with a live line. Transient contact between the core ofthe power cable and the conductor may generate electric arc or spark, which may cause fire oreye injury.

    l Before installing or removing power cables, you must power off the device.l Before connecting a power cable, you must ensure that the label on the power cable is

    correct.

    Device with Power On

    DANGERInstalling or removing a device is prohibited if the device is on.

    DANGERDo not install or remove the power cables of the equipment when it is powered on.

    Short CircuitsWhen installing and maintaining devices, place and use the associated tools and instruments inaccordance with regulations to avoid short-circuits caused by metal objects.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 1 Safety Precautions

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    5

  • CAUTIONTo avoid short-circuits when using a tool (such as a screwdriver), do not place the tool on theventilation plate of the subrack.

    CAUTIONPrevent any screws from dropping into the subrack or chassis to avoid short-circuits.

    Fuse

    WARNINGIf the fuse on a device blows, replace the fuse with a fuse of the same type and specifications toensure safe operation of the device.

    Electrostatic Discharge

    CAUTIONThe static electricity generated by the human body may damage the electrostatic sensitivecomponents on the board, such as the large-scale integrated circuit (LSI).

    l The human body can generate static electromagnetic fields in the following situations:physical movement, clothing friction, friction between shoes and the ground, plastics inthe hand. Such static electromagnetic effects can remain for an appreciable time.

    l Before operating a device, circuit boards, or ASICs, wear an ESD wrist strap that is properlygrounded. The ESD wrist strap can prevent the electrostatic-sensitive components frombeing damaged by the static electricity in the human body.

    Figure 1-1 shows the method of wearing an ESD wrist strap.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 1 Safety Precautions

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    6

  • Figure 1-1 Wearing an ESD wrist strap

    1.4 Environment of Flammable GasThis topic describes safety precautions for the operating environment of a device.

    DANGERDo not place or operate devices in an environment of flammable or explosive air or gas.

    Operating an electronic device in an environment of flammable gas causes a severe hazard.

    1.5 Storage BatteriesThis topic describes safety precautions for operations of storage batteries.

    DANGERBefore operating a storage battery, you must read the safety precautions carefully and be familiarwith the method of connecting a storage battery.

    l Incorrect operations of storage batteries cause hazards. During operation, prevent any short-circuit, and prevent the electrolyte from overflowing or leakage.

    l If the electrolyte overflows, it causes potential hazards to the device. The electrolyte maycorrode metal parts and the circuit boards, and ultimately damage the circuit boards.

    l A storage battery contains a great deal of energy. Misoperations may cause a short-circuit,which leads to human injuries.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 1 Safety Precautions

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    7

  • Basic PrecautionsTo ensure safety, note the following points before installing or maintaining the storage battery:l Use special insulation tools.l Wear an eye protector and take effective protection measures.l Wear rubber gloves and a protection coat to prevent the hazard caused by the overflowing

    electrolyte.l When handling the storage battery, ensure that its electrodes are upward. Leaning or

    reversing the storage battery is prohibited.l Before installing or maintaining the storage battery, ensure that the storage battery is

    disconnected from the power supply that charges the storage battery.

    Short-Circuit

    DANGERA battery short-circuit may cause human injuries. Although the voltage of an ordinary batteryis low, the instantaneous high current caused by a short-circuit emits a great deal of energy.

    Avoid any short-circuit of batteries caused by metal objects. If possible, disconnect the workingbattery before performing other operations.

    Hazardous Gas

    CAUTIONDo not use any unsealed lead-acid storage battery. Lay a storage battery horizontally and fix itproperly to prevent the battery from emitting flammable gas, which may cause fire or deviceerosion.

    Working lead-acid storage batteries emit flammable gas. Therefore, ventilation and fireproofingmeasures must be taken at the sites where lead-acid storage batteries are placed.

    Battery Temperature

    CAUTIONIf a battery overheats, the battery may be deformed or damaged, and the electrolyte mayoverflow.

    When the temperature of the battery is higher than 60C, you need to check whether theelectrolyte overflows. If the electrolyte overflows, take appropriate measures immediately.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 1 Safety Precautions

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    8

  • Battery Leakage

    CAUTIONIn the event of acid overflow or spillage, neutralize the acid and clean it up appropriately.

    When handling a leaky battery, protect against the possible damage caused by the acid. Whenyou find the electrolyte leaks, you can use the following substances to counteract and absorb theleaking electrolyte:l Sodium bicarbonate (NaHCO3)l Sodium carbonate (Na2CO3)In the event of acid overflow or spillage, neutralize the acid and clean it up as recommended bythe battery manufacturer and any local regulations for acid disposal.If a person contacts battery electrolyte, clean the skin that contacts the battery electrolyteimmediately by using water. In case of a severe situation, the person must be sent to a hospitalimmediately.

    1.6 RadiationThis topic describes safety precautions for electromagnetic exposure and lasers.

    1.6.1 Safe Usage of Optical FibersThe laser beam can cause damage to your eyes. Hence, you must exercise caution when usingoptical fibers.

    DANGERWhen installing or maintaining an optical interface board or optical fibers, avoid direct eyeexposure to the laser beams launched from the optical interface board or fiber connectors. Thelaser beam can cause damage to your eyes.

    Cleaning Fiber Connectors and Optical Interfaces

    CAUTIONIf fiber connectors or flanges are contaminated, optical power commissioning is seriouslyaffected. Therefore, the two endfaces and flange of every external fiber must be cleaned beforethe fiber is led into the equipment through the ODF for being inserted into an optical interfaceon the equipment.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 1 Safety Precautions

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    9

  • The fiber connectors and optical interfaces of the lasers must be cleaned with the followingspecial cleaning tools and materials:l Special cleaning solvent: It is preferred to use isoamylol. Propyl alcohol, however, can also

    be used. It is prohibited that you use alcohol and formalin.l Non-woven lens tissuel Special compressed gasl Cotton stick (medical cotton or long fiber cotton)l Special cleaning roll, used with the recommended cleaning solventl Special magnifier for fiber connectorsFor cleaning steps, see Task Collection "Cleaning Fiber Connectors and Adapters" in the OptiXRTN 950 Radio Transmission System Maintenance and Troubleshooting.

    Replacing Optical FibersWhen replacing an optical fiber, cover the fiber connector of the unused optical fiber with aprotective cap.

    Connecting Optical Fibersl Use an attenuator if the optical power is excessively high. A high received optical power

    damages the optical interface.l Directly connect an attenuator to a slanting optical interface. Install the attenuator on the

    IN port instead of the OUT port.l Do not directly connect an attenuator to the level optical interface. Use the optical

    distribution frame (ODF) to connect an attenuator to a level optical interface.Figure 1-2 shows a slanting optical interface, and Figure 1-3 shows a level optical interface.

    Figure 1-2 Slanting optical interface

    Slanting opticalinterface

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 1 Safety Precautions

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    10

  • Figure 1-3 Level optical interface

    Level opticalinterface

    1.6.2 Electromagnetic ExposureThis topic describes safety precautions for electromagnetic exposure.If multiple transmit antennas are installed on a tower or backstay, keep away from the transmitdirections of the antennas when you install or maintain an antenna locally.

    CAUTIONEnsure that all personnel are beyond the transmit direction of a working antenna.

    1.6.3 Forbidden AreasThe topic describes requirements for a forbidden area.l Before entering an area where the electromagnetic radiation is beyond the specified range,

    the associated personnel must shut down the electromagnetic radiator or stay at least 10meters away from the electromagnetic radiator, if in the transmit direction.

    l A physical barrier and an eye-catching warning flag should be available in each forbiddenarea.

    1.6.4 LaserThis topic describes safety precautions for lasers.

    WARNINGWhen handling optical fibers, do not stand close to, or look into the optical fiber outlet directlywithout eye protection.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 1 Safety Precautions

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    11

  • Laser transceivers are used in the optical transmission system and associated test tools. The lasertransmitted through the bare optical fiber produces a small beam of light, and therefore it hasvery high power density and is invisible to human eyes. When a beam of light enters eyes, theeyes may be damaged.In normal cases, viewing an un-terminated optical fiber or a damaged optical fiber without eyeprotection at a distance greater than 150 mm does not cause eye injury. Eye injury may occur,however, if an optical tool such as a microscope, magnifying glass, or eye loupe is used to viewan un-terminated optical fiber.

    Safety Instructions Regarding LasersTo avoid laser radiation, obey the following instructions:l All operations should be performed by authorized personnel who have completed the

    required training courses.l Wear a pair of eye-protective glasses when you are handling lasers or fibers.l Ensure that the optical source is switched off before disconnecting optical fiber connectors.l Do not look into the end of an exposed fiber or an open connector when you are not sure

    whether the optical source is switched off.l Use an optical power meter to measure the optical power and ensure that the optical source

    is switched off.l Before opening the front door of an optical transmission device, ensure that you are not

    exposed to laser radiation.l Do not use an optical tool such as a microscope, a magnifying glass, or an eye loupe to

    view the optical connector or fiber that is transmitting optical signals.

    Instructions Regarding Fiber HandlingRead and abide by the following instructions before handling fibers:l Only trained personnel are permitted to cut and splice fibers.l Before cutting or splicing a fiber, ensure that the fiber is disconnected from the optical

    source. After disconnecting the fiber, cap to the fiber connectors.

    1.6.5 MicrowaveWhen installing and maintaining the equipment of Huawei, follow the safety precautions ofmicrowave to ensure the safety of the human body and the equipment.

    WARNINGStrong radio frequency can harm the human body.

    When installing or maintaining an aerial on the tower or mast that is installed with multipleaerials, switch off the transmitter in advance.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 1 Safety Precautions

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    12

  • 1.7 Working at HeightsThis topic describes safety precautions for working at heights.

    WARNINGWhen working at heights, be cautious to prevent objects from falling down.

    The requirements for working at heights are as follows:l The personnel who work at heights must be trained.l Carry and handle the operating machines and tools with caution to prevent them from falling

    down.l Safety measures, such as wearing a helmet and a safety belt, must be taken.l Wear cold-proof clothes when working at heights in cold areas.l Check all lifting appliances thoroughly before starting the work, and ensure that they are

    intact.

    1.7.1 Hoisting Heavy ObjectsThis topic describes the safety precautions for hoisting heavy objects that you must follow wheninstalling, operating, and maintaining Huawei devices.

    WARNINGWhen heavy objects are being hoisted, do not walk below the cantilever or hoisted objects.

    l Only trained and qualified personnel can perform hoisting operations.l Before hoisting heavy objects, check that the hoisting tools are complete and in good

    condition.l Before hoisting heavy objects, ensure that the hoisting tools are fixed to a secure object or

    wall with good weight-bearing capacity.l Issue orders with short and explicit words to ensure correct operations.l Ensure that the angle between the two cables is less than or equal to 90 degrees during the

    lifting, as shown in Figure 1-4.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 1 Safety Precautions

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    13

  • Figure 1-4 Hoisting heavy objects

    1.7.2 Using LaddersThis topic describes safety precautions for using ladders.

    Checking Laddersl Before using a ladder, check whether the ladder is damaged. After checking that the ladder

    is in good condition, you can use the ladder.l Before using a ladder, you should know the maximum weight capacity of the ladder. Avoid

    overweighing the ladder.

    Placing LaddersThe proper slant angle of the ladder is 75 degrees. You can measure the slant angle of the ladderwith an angle square or your arms, as shown in Figure 1-5. When using a ladder, to prevent theladder from sliding, ensure that the wider feet of the ladder are downward, or take protectionmeasures for the ladder feet. Ensure that the ladder is placed securely.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 1 Safety Precautions

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    14

  • Figure 1-5 Slanting a ladder

    Climbing Up a LadderWhen climbing up a ladder, pay attention to the following points:l Ensure that the center of gravity of your body does not deviate from the edges of the two

    long sides.l Before operations, ensure that your body is stable to reduce risks.l Do not climb higher than the fourth rung of the ladder (counted from up to down).If you want to climb up a roof, ensure that the ladder top is at least one meter higher than theroof, as shown in Figure 1-6.

    Figure 1-6 Ladder top being one meter higher than the roof

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 1 Safety Precautions

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    15

  • 1.8 Mechanical SafetyThis topic describes safety precautions for drilling holes, handling sharp objects, operating fans,and carrying heavy objects.

    Drilling Holes

    WARNINGDo not drill holes on the cabinet without prior permission. Drilling holes without complyingwith the requirements affects the electromagnetic shielding performance of the cabinet anddamages the cables inside the cabinet. In addition, if the scraps caused by drilling enter thecabinet, the printed circuit boards (PCBs) may be short-circuited.

    l Before drilling a hole on the cabinet, remove the cables inside the cabinet.l Wear an eye protector when drilling holes. This is to prevent eyes from being injured by

    the splashing metal scraps.l Wear protection gloves when drilling holes.l Take measures to prevent the metallic scraps from falling into the cabinet. After the drilling,

    clean up the metallic scraps.

    Sharp Objects

    WARNINGWear protection gloves when carrying the device. This is to prevent hands from being injuredby the sharp edges of the device.

    Fansl When replacing parts, place the objects such as the parts, screws, and tools properly. This

    is to prevent them from falling into the operating fans, which damages the fans or device.l When replacing the parts near fans, keep your fingers or boards from touching operating

    fans before the fans are powered off and stop running. Otherwise, the hands or the boardsare damaged.

    Carrying Heavy ObjectsWear protection gloves when carrying heavy objects. This is to prevent hands from being hurt.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 1 Safety Precautions

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    16

  • WARNINGl The carrier must be prepared for load bearing before carrying heavy objects. This is to prevent

    the carrier from being strained or pressed by the heavy objects.l When you pull a chassis out of the cabinet, pay attention to the unstable or heavy objects on

    the cabinet. This is to prevent the heavy objects on the cabinet top from falling down, whichmay hurt you.

    l Generally, two persons are needed to carry a chassis. It is prohibited that only one personcarries a heavy chassis. When carrying a chassis, the carriers should stretch their backs andmove stably to avoid being strained.

    l When moving or lifting a chassis, hold the handles or bottom of the chassis. Do not holdthe handles of the modules installed in the chassis, such as the power modules, fan modules,and boards.

    1.9 Other PrecautionsThis topic describes safety precautions for removing and inserting boards, binding signal cables,and routing cables.

    Removing and Inserting a Board

    CAUTIONWhen inserting a board, wear an ESD wrist strap or ESD gloves, and handle the board gently toavoid distorting pins on the backplane.

    l Slide the board along the guide rails.l Do not contact one board with another to avoid short-circuits or damage.l When holding a board in hand, do not touch the board circuits, components, connectors,

    or connection slots of the board to prevent damage caused by ESD of the human body tothe electrostatic-sensitive components.

    Binding Signal Cables

    CAUTIONBind the signal cables separately from the high-current or high-voltage cables.

    Routing CablesIn the case of extremely low temperature, heavy shock or vibration may damage the plastic skinof the cables. To ensure the construction safety, comply with the following requirements:

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 1 Safety Precautions

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    17

  • l When installing cables, ensure that the environment temperature is above 0C.l If the cables are stored in a place where the ambient temperature is below 0C, transfer

    them to a place at room temperature and store the cables for more than 24 hours beforeinstallation.

    l Handle the cables gently, especially in a low-temperature environment. Do not performany improper operations, for example, pushing the cables down directly from a truck.

    High Temperature

    WARNINGIf the ambient temperature exceeds 55C, the temperature of the front panel surface marked the

    flag may exceed 70C. When touching the front panel of the board in such an environment,you must wear the protection gloves.

    IF Cables

    WARNINGBefore installing or removing an IF cable, you must turn off the power switch of the IF board.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 1 Safety Precautions

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    18

  • 2 Notices for High-Risk OperationsAbout This Chapter

    This chapter provides notices for the operations that may cause bodily injury or equipmentdamage if they are not performed properly during the commissioning and maintenance ofmicrowave equipment.

    2.1 Operation Guide for the Toggle Lever SwitchThe ODU-PWR switch on the IF board is a toggle lever switch which must be turned on and offas per the following instructions to avoid damaging the IF board.2.2 Operation Guide for the IF JumperBefore removing or installing an IF jumper, turn off the ODU-PWR switch to avoid bodily injuryor damage to the IF board and ODU.2.3 Operation Guide for the IF CableBefore removing or installing an IF cable, turn off the ODU-PWR switch to avoid bodily injuryor damage to the IF board and ODU.2.4 Operation Guide for the IF BoardBefore removing or installing an IF board, turn off the ODU-PWR switch to avoid bodily injuryor damage to the IF board and ODU.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 2 Notices for High-Risk Operations

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    19

  • 2.1 Operation Guide for the Toggle Lever SwitchThe ODU-PWR switch on the IF board is a toggle lever switch which must be turned on and offas per the following instructions to avoid damaging the IF board.

    Position and Description of the Toggle Lever SwitchThe toggle lever switch is located on the IF board and controls the power that is fed to the ODU,as shown in Figure 2-1.

    Figure 2-1 Toggle lever switch

    I : ON

    O: OFF

    Turning On the Toggle Lever Switch1. Gently pull on the toggle lever switch out.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 2 Notices for High-Risk Operations

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    20

  • 2. Turn it to the left.

    3. Release the toggle lever switch.

    Turning Off the Toggle Lever Switch1. Gently pull on the toggle lever switch.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 2 Notices for High-Risk Operations

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    21

  • 2. Turn it to the right.

    3. Release the toggle lever switch.

    2.2 Operation Guide for the IF JumperBefore removing or installing an IF jumper, turn off the ODU-PWR switch to avoid bodily injuryor damage to the IF board and ODU.

    ProcedureStep 1 Turn off the ODU-PWR switch on the IF board. For details, see 2.1 Operation Guide for the

    Toggle Lever Switch.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 2 Notices for High-Risk Operations

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    22

  • 21

    DANGEREnsure that the ODU is completely powered off before removing or installing the IF jumper.

    Step 2 Remove or install the IF jumper.----End

    2.3 Operation Guide for the IF CableBefore removing or installing an IF cable, turn off the ODU-PWR switch to avoid bodily injuryor damage to the IF board and ODU.

    ProcedureStep 1 Turn off the ODU power switch on the IF board. For details, see 2.1 Operation Guide for the

    Toggle Lever Switch.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 2 Notices for High-Risk Operations

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    23

  • 21

    DANGEREnsure that the ODU is completely powered off before removing or installing the IF cable.

    Step 2 Install or remove the IF cable.----End

    2.4 Operation Guide for the IF BoardBefore removing or installing an IF board, turn off the ODU-PWR switch to avoid bodily injuryor damage to the IF board and ODU.

    ProcedureStep 1 Turn off the ODU-PWR switch on the IF board. For details, see 2.1 Operation Guide for the

    Toggle Lever Switch.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 2 Notices for High-Risk Operations

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    24

  • 321

    3

    DANGEREnsure that the ODU is completely powered off before removing or installing the IF board.

    Step 2 Disconnect the IF jumper or IF cable.Step 3 Remove or install the IF board.

    ----End

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 2 Notices for High-Risk Operations

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    25

  • 3 Commissioning PreparationsAbout This Chapter

    This chapter describes the preparations that need to be made prior to commissioning equipment.

    3.1 Commissioning ProcessBased on the objects to be commissioned, the process can be divided into two stages: sitecommissioning and system commissioning.3.2 Determining the Commissioning MethodBy using the U2000 for commissioning, engineers can adopt the network commissioningmethod.3.3 Preparing Documents and ToolsThis section lists the document and tools that should be prepared prior to commissioning theequipment.3.4 Checking Commissioning ConditionsEnsure that the equipment meets the commissioning requirements for the site or system prior toperforming such tasks. The following sections provide a non-exhaustive checklist for bothscenarios.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 3 Commissioning Preparations

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    26

  • 3.1 Commissioning ProcessBased on the objects to be commissioned, the process can be divided into two stages: sitecommissioning and system commissioning.

    3.1.1 Site Commissioning ProcessSite commissioning refers to commissioning that is performed on a hop and sites at both endsof a radio link. Site commissioning ensures that the sites and the radio link between the siteswork properly, and is also performed in preparation of system commissioning.You can use the following methods to configure site commissioning data for the OptiX RTN950 on site:l Web LCTl Handheld tool

    NOTE

    You can commission only basic items by using the handheld tool.

    Site Commissioning Items (Configuring Site Commissioning Data by Using theWeb LCT)

    Commissioning engineers can configure site commissioning data by using the Web LCT on sitewhen they are:l Familiar with how to configure radio link data on the OptiX RTN 950.l Aware of the radio link data plan for the site.l Equipped with a laptop on which the Web LCT is installed.

    Table 3-1 Configuring site commissioning data by using the Web LCTCommissioning Item RemarksPowering On the Equipment RequiredConfiguring SiteCommissioning Data byUsing the Web LCT

    Connecting the Web LCT RequiredCreating NEs by Using theSearch Method

    Required

    Log in to an NE RequiredChanging the NE ID RequiredChanging the Name of anNE

    Optional

    Setting the CommunicationParameters of an NE

    Required

    Configuring LogicalBoards

    Required

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 3 Commissioning Preparations

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    27

  • Commissioning Item RemarksConfiguring IF 1+1protection

    Optional

    Configuring IF/ODUInformation for a RadioLink

    Required

    Synchronizing NE Time RequiredConfiguring Orderwire OptionalChecking Alarms Required

    Testing Connectivity ofCables

    Testing Connectivity of E1Cables (by Using the WebLCT)

    Required when E1 cables areused on the site

    Testing Connectivity ofNetwork Cables

    Required when networkcables are used on the site

    Testing Connectivity ofOptical Fibers

    Required when optical fibersare used on the site

    Aligning Antennasa Aligning Single-PolarizedAntennas

    Required when microwaveservices are transmitted bysingle-polarized antennas

    Aligning Dual-PolarizedAntennas

    Required when microwaveservices are transmitted bydual-polarized antennas

    Querying the Status of Radio Links RequiredQuerying the DCN Status Required

    NOTE

    a: Before aligning antennas, power on the equipment and configure site commissioning data on both ends of theradio link.

    Site Commissioning Items (Configuring Site Commissioning Data by Using theHandheld Tool)

    Commissioning engineers can configure site commissioning data by using the handheld tool onsite when they are:l Familiar with how to configure radio link data on the OptiX RTN 950.l Aware of the radio link data plan for the site.l Equipped with the handheld tool.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 3 Commissioning Preparations

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    28

  • Table 3-2 Configuring site commissioning data by using the handheld toolCommissioning Item RemarksPowering On the Equipment RequiredConfiguring SiteCommissioning Data byUsing the Handheld Tool

    Connecting the HandheldTool to the IDU

    Required

    Setting NE Attributes RequiredConfiguring a Radio Link RequiredChecking Alarms Required

    Testing Connectivity ofCables

    Testing Connectivity of E1Cables by Using theHandheld Tool

    Required when E1 cables areused on the site

    Testing Connectivity ofNetwork Cables

    Required when networkcables are used on the site

    Testing Connectivity ofOptical Fibers

    Required when optical fibersare used on the site

    Aligning the Antennasa Aligning Single-PolarizedAntennas

    Required when microwaveservices are transmitted bysingle-polarized antennas

    Aligning Dual-PolarizedAntennas

    Required when microwaveservices are transmitted bydual-polarized antennas

    NOTE

    a: Before aligning antennas, power on the equipment and configure site commissioning data on both ends of theradio link.

    3.1.2 System Commissioning ProcessSystem commissioning refers to commissioning for the entire microwave transmission network.System commissioning ensures that various services are transmitted properly and protectionfunctions are implemented over the microwave transmission network.

    Table 3-3 System commissioning processCommissioning Item RemarksConfiguring Network-wide Service Data RequiredTesting E1 Services Testing E1 Services

    by Using a BERTester

    Required when E1 service are available anda BER tester is available on site

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 3 Commissioning Preparations

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    29

  • Commissioning Item RemarksTesting E1 ServicesThrough PRBS

    Required when E1 services are available andno BER tester is available on site

    Testing Ethernet Services Required when Ethernet services areavailable

    Testing ATM Services Required when ATM services are availableTesting AMSwitching

    Testing AMSwitching by Usinga BER Tester

    Required when the AM function is enabledand a BER tester is available on site

    Testing AMSwitching Withouta BER Tester

    Required when the AM function is enabledand no BER tester is available on site

    Testing ProtectionSwitching

    Testing IF 1+1Switching

    Required when the radio links are configuredwith the 1+1 HSB/FD/SD

    Testing N+1ProtectionSwitching

    Required when the N+1 protection isconfigured

    Testing SNCPSwitching

    Required when the SNCP is configured

    Testing ERPSSwitching

    Required when ERPS is configured

    Testing MPLS APSProtectionSwitching

    Required when MPLS APS protection isconfigured

    Testing Linear MSPSwitching

    Required when 1+1/1:N linear MSP isconfigured

    Checking the Clock Status RequiredTesting 24-Hour BER Required when E1 services are available

    3.2 Determining the Commissioning MethodBy using the U2000 for commissioning, engineers can adopt the network commissioningmethod.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 3 Commissioning Preparations

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    30

  • NOTE

    In the following instructions for both types of commissioning methods, site commissioning and systemcommissioning are defined as follows:l Site commissioning refers to commissioning that is performed on a hop and sites at both ends of the

    radio link by connecting the commissioning tool to the NE at a single site.l System commissioning refers to commissioning that is performed on all the NEs in the network by

    connecting the commissioning tool to a gateway NE where it configures the commissioning data foreach site.

    Single-hop CommissioningThe single-hop commissioning method is preferred for small-scale microwave transmissionnetworks (for example, a network with only one or two radio link hops). By performing single-hop commissioning, you can complete all site and system commissioning items at a time. Themajor commissioning steps are as follows:1. On both ends of a radio link, power on the NEs.2. Use the Web LCT to configure all service data on the NEs.3. Use the Web LCT to complete the site commissioning items.4. Use the Web LCT to complete the system commissioning items.

    NOTE

    The Web LCT is used for single-hop commissioning, and therefore this document does not detail how to usethe Web LCT. For details about how to use the Web LCT, see the commissioning guide in the documentationpackage of the Web LCT version.

    Network CommissioningThe network commissioning method is usually used for large-scale microwave transmissionnetworks. The major commissioning steps are as follows:1. On both ends of a radio link, power on the NEs.2. Configure site commissioning data by using the Web LCT or configure site

    commissioning data by using the handheld tool.3. Use the U2000 to complete the site commissioning items at sites where services converge.4. Use the U2000 to complete the system commissioning items at sites where services

    converge.

    3.3 Preparing Documents and ToolsThis section lists the document and tools that should be prepared prior to commissioning theequipment.

    DocumentsThe following document should be available before commissioning the equipment:l Engineering design documents, including:

    Network plan Engineering design

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 3 Commissioning Preparations

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    31

  • l Commissioning guides, including: OptiX RTN 950 Radio Transmission System Commissioning Guide OptiX RTN 950 Radio Transmission System Configuration Guide

    ToolsTable 3-4 lists the tools required for the commissioning task.

    Table 3-4 Tools and metersTool and Meter Application Scenariol Adjustable wrenchl Screwdriverl Telescopel Interphonel Hex keyl Multimeter that has a test cable with a

    BNC connector at one endl North-stabilized indicator

    Aligning antennas

    Laptop on which the Web LCT is installed l Configuring site commissioning data byusing the Web LCT

    l Testing connectivity of E1 cablesl Querying the DCN status

    Handheld tool l Configuring site commissioning datal Testing connectivity of E1 cables

    BER tester l Testing connectivity of E1 cablesl Testing E1 servicesl Testing AM switchingl Testing IF 1+1 switchingl Testing N+1 protection switchingl Testing SNCP switchingl Testing linear MSP switchingl Testing 24-hour BER

    Network cable tester Testing connectivity of network cablesl Optical power meterl Short fiber jumper

    Checking connectivity of optical fibers

    PC on which the U2000 is installed Commissioning system itemsE1 jumper Testing 24-hour BER

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 3 Commissioning Preparations

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    32

  • NOTEFor details about the requirements and methods for installing the Web LCT, see the iManager U2000 WebLCT User Guide.

    3.4 Checking Commissioning ConditionsEnsure that the equipment meets the commissioning requirements for the site or system prior toperforming such tasks. The following sections provide a non-exhaustive checklist for bothscenarios.

    3.4.1 Site CommissioningEnsure that the equipment and weather meet the requirements for site commissioning.Details about these requirements are as follows:l Hardware installation has been completed and has passed the installation check.l Power is available to the equipment.l The service signal cables that are connected to other equipment have been properly routed.l The appropriate risk control measures to arrest falling objects and ensure personnel safety

    are in place. Engineers are certified to commission the antennas.l There is no adverse weather (such as wind, rain, snow, or fog) that could hinder or impact

    the commissioning.

    3.4.2 System CommissioningEnsure that the equipment and weather meet the requirements for system commissioning.Details about these requirements are as follows:l Site commissioning at both ends of a radio link has been completed.l There is no adverse weather (such as wind, rain, snow, or fog) that could hinder or impact

    the commissioning.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 3 Commissioning Preparations

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    33

  • 4 Site CommissioningAbout This Chapter

    Site commissioning includes the specific commissioning processes for all site commissioningitems.

    4.1 Powering On the EquipmentBy checking the power-on process of equipment, you can verify whether the hardware systemof the equipment and the power system are functioning properly.4.2 Configuring Site Commissioning Data by Using the Web LCTThis topic describes how to configure site commissioning data when using the Web LCT toperform site commissioning.4.3 Configuring Site Commissioning Data by Using the Handheld ToolThis section describes how to configure site commissioning data by using the handheld tool.4.4 Testing Connectivity of CablesDuring the installation of the OptiX RTN 900, the cables may be connected to service interfacesincorrectly, or the hardware may malfunction. To ensure that the services run properly, testconnectivity of the cables.4.5 Aligning the AntennasAligning the antennas is the most important activity in HOP commissioning. The alignment hasa direct effect on the performance of the radio links.4.6 Checking the Status of Radio LinksAfter aligning the antennas, query the status of radio links and determine whether the radio linksare in the normal state.4.7 Querying the DCN StatusThe NMS manages NEs through DCN channels. By querying the radio links using the SearchFor Opposite NE, you can determine whether the DCN of the radio links runs properly.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 4 Site Commissioning

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    34

  • 4.1 Powering On the EquipmentBy checking the power-on process of equipment, you can verify whether the hardware systemof the equipment and the power system are functioning properly.

    Prerequisitel Hardware installation has been completed and has passed the installation check.l The power system is available. The voltage, pole connection, and fuse current of the power

    system have been checked in the process of connecting power cables.l The power supply (for example, the power box of the cabinet) has been turned off.

    Tools, Equipment, and MaterialsNone.

    Contextl For the OptiX RTN 950, the recommended fuse currents are listed in Table 4-1.

    Table 4-1 Fuse currentsChassis Fuse CurrentOptiX RTN 950 20 A

    l The OptiX RTN 950 supports the following system control, switching, and timing board:

    Chassis Board TypeOptiX RTN 950 CSH/CST

    Precautions

    CAUTIONl If the equipment is configured with two PIU boards, the nominal voltage for the input power

    of each PIU board must be the same.l The ODU-PWR switch on the front panel of the IF board is designed with a locking device.

    Hence, you must pull out the switches lightly before you turn it. If the switch points to "O",the switch is turned off. If the switch points to "I", the switch is turned on.

    l If the output voltage of the power supply does not meet test requirements, do not power onthe cabinet. First, reconstruct the power supply and then test the output voltage again.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 4 Site Commissioning

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    35

  • ProcedureStep 1 Verify that the power cables of the chassis are correctly connected. Then, power on the equipment

    and check the status of the indicators. In normal conditions, the PIU and FAN indicators aresteady green, as shown in Figure 4-1. Table 4-2 provides the descriptions for the different statesof the indicators.

    Table 4-2 Status of indicatorsIndicator State DescriptionPWR Steady green Indicates that the power supply is in

    the normal state.Off Indicates a power failure.

    FAN Steady green Indicates that the fan is runningproperly.

    Steady red Indicates that the fan is faulty.Off Indicates that the fan is powered off.

    Figure 4-1 Normal statePIU indicator FAN indicator

    Step 2 Check the status of the indicators on the system control, switching, and timing board and ensure

    that the equipment is powered on. The board indicators should conform to the following statesand sequences.1. The PROG indicator should be green, off, blinking green, and off. The process lasts about

    1 minute if service data is not configured.NOTE

    This process lasts longer if service data is configured.2. The STAT and SYNC indicators should be green.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 4 Site Commissioning

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    36

  • Figure 4-2 Normal state

    STAT PROG SYNC ACTX ACTC

    NOTE

    l For detailed meanings of the indicators, see the IDU hardware description.l For a board other than the system control, switching, and timing board on the IDU, the STAT indicator is

    on only after the corresponding logical board is added.

    Step 3 Turn the ODU-PWR switch on the IF board to "I".NOTE

    l The ODU indicator on an IF board is green only after the logical board of the IF board connected tothe ODU and the logical board of the ODU are created.

    l In the event of indicator abnormalities, contact Huawei technical support.

    ----End

    4.2 Configuring Site Commissioning Data by Using theWeb LCT

    This topic describes how to configure site commissioning data when using the Web LCT toperform site commissioning.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 4 Site Commissioning

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    37

  • Configuration ProcessFigure 4-3 describes the process of configuring site commissioning data.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 4 Site Commissioning

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    38

  • Figure 4-3 Configuration flowchart

    Procedure for configuring an radio link (XPIC disabled)

    End

    Mandatory

    Optional

    Start

    Connecting the Web LCT to the IDU

    Synchronizing NE time

    Creating an IF 1+1 protection group

    Procedure for configuring an radio link (XPIC enabled)

    Creating an XPIC group

    Configuring the IF/ODU information of a radio link

    Creating an IF 1+1 protection group

    Setting the AM attributes of the XPIC hybrid radio link

    EndConfiguring the IF/ODU

    information of a radio link

    Checking alarms

    Checking alarms

    Creating NEs

    Logging in to NEs

    Changing NE IDs

    Configuring logical boards

    Setting NE communication parameters

    Changing NE names

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 4 Site Commissioning

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    39

  • NOTE

    In TDM microwave mode, the AM attributes do not need to be configured for the links where the XPIC functionis enabled.

    Procedure for Configuring NE DataTable 4-3 Procedure for configuring NE data

    Step Action Description1 Connecting the Web LCT to

    the IDUMandatory.

    2 Creating NEs by Using theSearch Method

    Mandatory. It is recommended that youcreate an NE in IP Auto Discovery mode.

    3 Logging In to an NE Mandatory.Enter correct values in User Name andPassword. The default User Name is lct,and the default Password is password.

    4 Changing the NE ID Mandatory. Set parameters as follows:l Set ID according to the guideline

    specified in the DCN plan.l If a specific extended NE ID is required,

    change Extended ID.5 Changing the NE Name Optional.6 Setting NE Communication

    ParametersMandatory if special requirements areimposed on the IP address of the NE. SetIP and Subnet Mask as required.NOTE

    If the IP address of an NE is not changedmanually, the IP address changes to0x81000000 + NE ID.

    7 Configuring Logical Boards Mandatory.8 Synchronizing NE Time Mandatory. This operation synchronizes

    NE time with the time on the computer thatruns the Web LCT.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 4 Site Commissioning

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    40

  • Procedure for Configuring an Radio Link (XPIC Disabled)Table 4-4 Procedure for configuring an Radio link (XPIC disabled)

    Step Action Description1 4.2.8

    Creating anIF 1+1ProtectionGroupa

    Mandatory when radio links are configured with 1+1protection.Set the parameters according to the network plan.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 4 Site Commissioning

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    41

  • Step Action Description2 4.2.9

    Configuringthe IF/ODUInformationof a RadioLink

    Mandatory.l In the case of the TDM microwave, set main parameters

    as follows: Set Work Mode and Link ID according to the network

    plan. Set TX Frequency(MHz), T/R Spacing(MHz), and

    TX Power(dBm) according to the network plan. Set TX Status to Unmute. Set Power to Be Received(dBm) to the received signal

    level specified in the network plan. The antennamisalignment indication function is enabled only afterthis parameter is set. When the antenna misalignmentindication function is enabled, if the actual receivepower of the ODU is 3 dB lower than the powerexpected to be received, the ODU indicator on the IFboard connected to the ODU blinks yellow (300 ms on,300 ms off), indicating that the antennas are notaligned. After the antennas are aligned for 30consecutive minutes, the NE automatically disablesthe antenna misalignment indication function.

    NOTEl After the site commissioning, however, you need to reset

    ATPC Enable Status according to site requirements.l For radio links configured with 1+1 HSB/SD, you need to

    configure the IF and ODU information on the main radio linkonly. For radio links configured with 1+1 FD, you need toconfigure the IF and ODU information on the main radio linkand the ODU information on the standby radio link.

    l For TDM radio links configured with N+1 protection, youneed to configure the IF and ODU information on each link.Work Mode must be configured as 7, STM-1, 28MHz,128QAM.

    l For the Integrated IP radio, set main parameters as follows: Set AM Enable Status and IF Channel Bandwidth

    according to the network plan. Set AM Enable Status to Disabled. In addition, set

    Manually Specified Modulation Mode toModulation Mode of the Guarantee AM Capacityaccording to the network plan.

    Set Guarantee E1 Capacity and Link ID accordingto the network plan.

    Set TX Frequency(MHz), T/R Spacing(MHz), andTX Power(dBm) according to the network plan.

    Set TX Status to Unmute. Set Power to Be Received(dBm) to the received signal

    level specified in the network plan. The antenna

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 4 Site Commissioning

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    42

  • Step Action Descriptionmisalignment indication function is enabled only afterthis parameter is set. When the antenna misalignmentindication function is enabled, if the actual receivepower of the ODU is 3 dB lower than the powerexpected to be received, the ODU indicator on the IFboard connected to the ODU blinks yellow (300 ms on,300 ms off), indicating that the antennas are notaligned. After the antennas are aligned for 30consecutive minutes, the NE automatically disablesthe antenna misalignment indication function.

    NOTEl After the site commissioning, however, you need to reset AM

    Enable Status and ATPC Enable Status according to siterequirements.

    l For radio links configured with 1+1 HSB/SD, you need toconfigure the IF and ODU information on the main radio linkonly. For radio links configured with 1+1 FD, you need toconfigure the IF and ODU information on the main radio linkand the ODU information on the standby radio link.

    l To configure Integrated IP radio links with N+1 protection,you need to configure the IF and ODU information on eachlink.

    3 CheckingAlarms

    Mandatory.

    Procedure for Configuring an Radio Link (XPIC Enabled)Table 4-5 Procedure for configuring an Radio link (XPIC enabled)

    Step Action Description1 4.2.10

    Creating anXPICWorkgroup

    Mandatory.Set the parameters according to the network plan.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 4 Site Commissioning

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    43

  • Step Action Description2 4.2.11

    Setting theHybrid/AMAttributesof the XPICWorkgroup

    Mandatory. Set parameters as follows:l If the AM function is enabled for the XPIC link, set AM

    Enable Status to Disabled. In addition, set ManuallySpecified Modulation Mode to Modulation Mode ofthe Guarantee AM Capacity according to the networkplan.

    l If the AM function is disabled, set AM Enable Status toDisabled. Set Manually Specified Modulation Mode tothe modulation mode according to the network plan.

    l AM parameters must be the same in the horizontal andvertical polarization directions of the XPIC link.

    NOTEIn TDM microwave mode, the AM attributes do not need to beconfigured for the links where the XPIC function is enabled.

    3 4.2.8Creating anIF 1+1ProtectionGroup

    Mandatory when two XPIC workgroups need to form two 1+1 protection groups.Set the parameters according to the network plan.NOTE

    One XPIC workgroup cannot form a 1+1 protection group. The radiolink in the horizontal/vertical polarization direction of the XPICworkgroup can form a 1+1 protection group with the radio link in thehorizontal/vertical polarization direction of the other XPICworkgroup.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide (U2000) 4 Site Commissioning

    Issue 01 (2011-10-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    44

  • Step Action Description4 4.2.9

    Configuringthe IF/ODUInformationof a RadioLink

    Mandatory. Configure the IF and ODU information in bothhorizontal and vertical polarization directions. Set parametersas follows:l In the case of the TDM microwave, set main parameters

    as follows: Set Power to Be Received(dBm) to the received

    signal level specified in the network plan. The antennamisalignment indication function is enabled only afterthis parameter is set. When the antenna misalignmentindication function is enabled, if the actual receivepower of the ODU is 3 dB lower than the powerexpected to be received, the ODU indicator on the IFboard connected to the ODU blinks yellow (300 mson, 300 ms off), indicating that the antennas are notaligned. After the antennas are aligned for 30consecutive minutes, the NE automatically disablesthe antenna misalignment indication function.

    Power to Be Received(dBm) must be the same in thehorizontal and vertical polarization directions.

    NOTEl After the site commissioning, however, you need to reset

    ATPC Enable Status according to site requirements.l For radio links configured with 1+1 HSB/SD, you need

    to configure the IF and ODU information on the mainradio link only. For radio links configured with 1+1 FD,you need to configure the IF and ODU information onthe main radio link and the ODU information on thestandby radio link.

    l For TDM radio links configured with N+1 protection,you need to configure the IF and ODU information oneach link. Work Mode must be configured as 7, STM-1,28MHz, 128QAM.

    l For the Integrated IP radio, set main parameters asfollows: Set Guarantee E1 Capacity according to the network

    plan. Set Power to Be Received(dBm) to the received

    signal level specified in the network plan. The antennamisalignment indication function is enabled only afterthis parameter is set. When the antenna misalignmentindication function is enabled, if the actu