39
An Overview of the EPRI/BPIG Recommended EPRI/BPIG Recommended Program for Buried Piping Bo Clark EPRI, BOP Corrosion Program Manager Industry/NRC Meeting on Buried Pipe October 22, 2009 White Flint, MD

10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

An Overview of the EPRI/BPIG RecommendedEPRI/BPIG Recommended Program for Buried Piping

Bo ClarkEPRI, BOP Corrosion Program Manager

Industry/NRC Meeting on Buried PipeOctober 22, 2009 White Flint, MD

Page 2: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

Introduction

• The EPRI/BPIG recommended program

“Recommendations for an Effective Program to Control the Degradation of Buried Pipe”, Dec 2008 – Report # 1016456

Page 2

© 2009 Electric Power Research Institute, Inc. All rights reserved.

–Industry consensus document

–Periodic updates (update in progress)

• Guidance for concrete pipe

• Industry feedback from use

Document placed in Public Domain

Page 3: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

Objectives of Document

Recommend program elements supporting:

– Safe and reliable operation of buried piping

Page 3

© 2009 Electric Power Research Institute, Inc. All rights reserved.

operation of buried piping systems

– A best practices/ industry consensus approach

Page 4: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

Basis

• Body of knowledge from

– Oil and gas pipelines

– Waterworks

– Process plants

Power plants

Page 4

© 2009 Electric Power Research Institute, Inc. All rights reserved.

– Power plants

NACE – API – PRCI – ASTM – ASME – AWWA – EPRI

Page 5: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

Six-Step Program

Step 1 - Program Policy, Plan and Procedures

Step 2 - Risk Ranking

Step 3 Inspection

Page 5

© 2009 Electric Power Research Institute, Inc. All rights reserved.

Step 3 - Inspection

Step 4 - Fitness-for-Service

Step 5 - Repair

Step 6 – Prevention

Page 6: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

Step 1 – Program Policy, Plan & Procedures

Step 1 - Program Policy, Plan and Procedures

Step 2 - Risk Ranking

Step 3 Inspection

Page 6

© 2009 Electric Power Research Institute, Inc. All rights reserved.

Step 3 - Inspection

Step 4 - Fitness-for-Service

Step 5 - Repair

Step 6 - Prevention

Page 7: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

1. Procedures and Oversight

• Scope

– Both safety and non-safety

– Piping designed to B31.1, B31.7, AWWA, Section III, and NFPA Codes

M t lli (f d f )

Page 7

© 2009 Electric Power Research Institute, Inc. All rights reserved.

– Metallic (ferrous and non-ferrous)

• Intend to add concrete pipe in 2009

– Liquids, gases, and vapors

• Recommendations apply to both ID and OD initiated degradation

– Can exclude ID if covered in another program

Page 8: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

1. Procedures and Oversight (continued)

• Policies and Procedures. A Buried Pipe Integrity Program Plan and implementing procedures should be developed.

• Program Database. A database should be developed t t k k d t d f i di t

Page 8

© 2009 Electric Power Research Institute, Inc. All rights reserved.

to track key program data and performance indicators.

– Other related data such as CP and coating surveys to be documented

• Performance Indicators. System or program health reports and performance indicators should be developed for the Buried Pipe Integrity Program.

Page 9: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

Step 2 - Risk Ranking

Step 1 - Program Policy, Plan and Procedures

Step 2 - Risk Ranking

Step 3 Inspection

Page 9

© 2009 Electric Power Research Institute, Inc. All rights reserved.

Step 3 - Inspection

Step 4 - Fitness-for-Service

Step 5 - Repair

Step 6 - Prevention

Page 10: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

2. Risk Ranking (continued)

• Risk Ranking

– Prioritize the selection of inspection locations.

– Series of matrices that correlates

• the likelihood of failure against the consequences of failure.

Page 10

© 2009 Electric Power Research Institute, Inc. All rights reserved.

Page 11: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

2. Risk Ranking (continued)

The steps involved in Risk Ranking include:

• Developing Scope Drawings

• Route Confirmation

• Scope Exclusions• Data Collection

Page 11

© 2009 Electric Power Research Institute, Inc. All rights reserved.

• Definition of Segments

• Soil Analysis

• Cathodic Protection Check

• Over-the-Line Surveys

• The Likelihood of Leak.

• The Likelihood of Break

• Failure Modes

Page 12: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

2. Risk Ranking (continued)

• Segment risk is maximum of:

– Likelihood of ID or OD leak, break, or occlusion versus consequences of occurrence of the failure mode

• The risk ranking should be periodically reviewed and

Page 12

© 2009 Electric Power Research Institute, Inc. All rights reserved.

The risk ranking should be periodically reviewed and updated as necessary.

Page 13: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

Step 3 - Inspection

Step 1 - Program Policy, Plan and Procedures

Step 2 - Risk Ranking

Step 3 Inspection

Page 13

© 2009 Electric Power Research Institute, Inc. All rights reserved.

Step 3 - Inspection

Step 4 - Fitness-for-Service

Step 5 - Repair

Step 6 - Prevention

Page 14: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

3. Inspections (continued)

• Inspections

– Should be performed at the piping locations that have the highest risk

– Access and cost may be considered when rankings equal

Page 14

© 2009 Electric Power Research Institute, Inc. All rights reserved.

equal

• 4 means of direct pipe inspection:

– Entry or excavation

– In-line inspection

– Corrosion monitoring

– Hydrotest

• Selection of the appropriate inspection method is left to the Owner

Page 15: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

3. Inspections (continued)

Entry or Excavation

• High risk segments can be uncovered to survey the condition of the pipe and coating

Page 15

© 2009 Electric Power Research Institute, Inc. All rights reserved.

Page 16: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

3. Inspections (continued)

Surface visual examinations can be performed to characterize pitting or cracking

Page 16

© 2009 Electric Power Research Institute, Inc. All rights reserved.

Pitt Measurements

Page 17: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

3. Inspections (continued)

• Volumetric examinations can provide wall thickness for FFS assessment

– Classic UT scan

– On-line UT

Page 17

© 2009 Electric Power Research Institute, Inc. All rights reserved.

Page 18: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

3. Inspections (continued)

In-line inspections of ID

• Borescope

• Robotics (source: RS Technical Services)

• Direct access

Page 18

© 2009 Electric Power Research Institute, Inc. All rights reserved.

Page 19: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

3. Inspections (continued)

• Intelligent pigs can be used to inspect high-risk segments

– MFL pig

– UT pig

– Caliper pig

Tethered pig

Page 19

© 2009 Electric Power Research Institute, Inc. All rights reserved.

– Tethered pig

• Challenges

– Access openings

– Pipe size changes

– Bends

– Valves

– Cleanliness

Page 20: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

3. Inspections (continued)

• Corrosion monitoring using corrosion coupons or probes can be considered for high-risk (ID corrosion) segments

– Corrosion coupon

– ER probe

Page 20

© 2009 Electric Power Research Institute, Inc. All rights reserved.

Page 21: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

3. Inspections (continued)

• For high-risk (rupture likelihood segments) hydrotest is an option when the line is out-of-service. The test should be at anticipated pressure-transient pressure

C b k l l t i

Page 21

© 2009 Electric Power Research Institute, Inc. All rights reserved.

− Can back-calculate maximum flaw/pit geometries upon successful hydro

− ASME B31G

Page 22: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

Step 4 – Fitness-for-Service

Step 1 - Program Policy, Plan and Procedures

Step 2 - Risk Ranking

Step 3 Inspection

Page 22

© 2009 Electric Power Research Institute, Inc. All rights reserved.

Step 3 - Inspection

Step 4 - Fitness-for-Service

Step 5 - Repair

Step 6 - Prevention

Page 23: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

4. Fitness-for-Service (continued)

• Design Analysis: The integrity assessment should be based on the design analysis of the buried piping system.

– The analysis should be regenerated if it cannot be retrieved. Loads to consider include:

• Minimum Code Requirement

Page 23

© 2009 Electric Power Research Institute, Inc. All rights reserved.

• Inspection Data

• Run/Repair decision

• Feedback to Risk Ranking

Page 24: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

Step 4 – Fitness-for-Service (continued)

4FFS

4.1Design Margins

4.2Inspection Results

Page 24

© 2009 Electric Power Research Institute, Inc. All rights reserved.

4.3Integrity Analysis

4.2.1Wall Thinning

4.2.2Cracking

4.2.3Mechanical Damage

4.2.4Flow Constriction

API 579 / ASME FFS-1CC N-513CC N-597

ASME B31GNUREG/CR-6876 Caution

API 579 / ASME FFS-1ASME XI

API 579 / ASME FFS-149 CFR

Pressure DropFouling

Page 25: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

Six-Step Program

Step 1 - Program Policy, Plan and Procedures

Step 2 - Risk Ranking

Step 3 Inspection

Page 25

© 2009 Electric Power Research Institute, Inc. All rights reserved.

Step 3 - Inspection

Step 4 - Fitness-for-Service

Step 5 - Repair

Step 6 - Prevention

Page 26: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

5. Repairs (continued)

• Pre-Approved Repair Options should be in place for prompt implementation in case a buried pipe fails. The detailed design of the selected repair should accommodate the specifics of the failure.

• Leak Detection and Isolation techniques and options h ld b l d f i l i h ld

Page 26

© 2009 Electric Power Research Institute, Inc. All rights reserved.

should be pre-selected for prompt implementation should a leak occur.

Page 27: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

5. Repair Techniques (continued)

Step 5Repairs

5.1 Non-Welded 5.2 Welded

5 1 1 Leak Strap 5 2 1 Replace

Page 27

© 2009 Electric Power Research Institute, Inc. All rights reserved.

5.1.1 Leak Strap

5.1.2 Mechanical Clamp

5.1.3 Wrap

5.1.4 Insertion Liner

5.2.1 Replace

5.2.2 Fillet Welded Patch

5.2.3 Leak Box

5.2.4 Overlay

Page 28: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

5. Non-Welded Repairs - Clamps

Page 28

© 2009 Electric Power Research Institute, Inc. All rights reserved.

Page 29: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

5. Non-Welded Repairs - Wraps

Page 29

© 2009 Electric Power Research Institute, Inc. All rights reserved.

Page 30: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

5. Non-Welded Repairs - Liners

Page 30

© 2009 Electric Power Research Institute, Inc. All rights reserved.

Page 31: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

5. Welded Repairs

Page 31

© 2009 Electric Power Research Institute, Inc. All rights reserved.

Fillet-Welded Patch Welded Leak Box

Page 32: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

Step 6 – Prevention and Mitigation

Step 1 - Program Policy, Plan and Procedures

Step 2 - Risk Ranking

Step 3 Inspection

Page 32

© 2009 Electric Power Research Institute, Inc. All rights reserved.

Step 3 - Inspection

Step 4 - Fitness-for-Service

Step 5 - Repair

Step 6 – Prevention and Mitigation

Page 33: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

Prevention and Mitigation

Unacceptable Risk?

YES NO

Page 33

© 2009 Electric Power Research Institute, Inc. All rights reserved.

-YES-

Preventive Measures

-NO-

Mitigative Measures

Reduce Likelihood

of Failure

Leak Detection

Repair

Page 34: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

6. Prevention and Mitigation (continued)

Preventive Measures

Water Treatment & Cleaning

Coatings

Page 34

© 2009 Electric Power Research Institute, Inc. All rights reserved.

Linings

Cathodic Protection

Pipe Material Selection

Trench Fill Material

Leak Detection

Page 35: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

6. Prevention and Mitigation (continued)

• Resistant materials can virtually eliminate susceptibility

Page 35

© 2009 Electric Power Research Institute, Inc. All rights reserved.

Use of High Density Polyethylene

Page 36: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

EPRI’s Survey on Buried Pipe Programs

• July 2009 Informational Survey

– Roughly gauge industry’s implementation of BP programs

• Survey asked questions such as:

– Number of operating units that have begun

Page 36

© 2009 Electric Power Research Institute, Inc. All rights reserved.

u be o ope at g u ts t at a e beguimplementing a Buried Pipe Integrity Program (BPIP)

– Has Corporate document governing BPIP been issued?

– Have Site-Specific document(s) governing BPIP been issued?

– Number of operating units that have BPIP program basis document and database.

Page 37: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

EPRI’s Survey on Buried Pipe Programs

• Survey questions (continued)

– Has Guided Wave (GW) been performed on high risk areas, as determined by BPIP database?

– What actions have been employed as a result of information gained from your BPIP (such as cathodic

Page 37

© 2009 Electric Power Research Institute, Inc. All rights reserved.

protection, alternative material used for replacement, permanent monitoring techniques, etc.)?

– Have you excavated buried piping for the sole purpose of performing inspections?

Page 38: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

EPRI’s Survey on Buried Pipe Programs

• Survey Results

– Over 90% of units have begun implementing a Buried Pipe Integrity Program (BPIP)

– 24 of 27 responding utilities have issued BPIP procedures

Page 38

© 2009 Electric Power Research Institute, Inc. All rights reserved.

procedures

– 14 of 27 utilities have performed GW on high risk piping

– 8 of 27 utilities have excavated solely for pipe inspection

Page 39: 10/22/2009 Meeting Presentation 'An Overview of the EPRI ... › docs › ML0930 › ML093010474.pdf · “Recommendations for an Effective Program to Control the Degradation of Buried

Together…Shaping the Future of Electricity

Page 39

© 2009 Electric Power Research Institute, Inc. All rights reserved.