10111ce601 - Construction Techniques Equipments and Practice (1)

Embed Size (px)

Citation preview

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    1/76

    10111CE601 CONSTRUCTION TECHNIQUES, EQUIPMENT AND PRACTICES

    OBJECTIVEThe main objective of this course is to make the student aware of the various construction

    techniques, practices and the equipment needed for different types of construction activities.

    At the end of this course the student shall have a reasonable knowledge about the variousconstruction procedures for sub to super structure and also the equipment needed forconstruction of various types of structures from foundation to super structure.

    UNIT I CONCRETE TECHNOLOGYCementsGrade of cements - manufacture of cementconcrete chemicals and Applications

    Mix design conceptmix design as per BIS & ACI methodsmanufacturing of concrete

    Batchingmixingtransportingplacingcompaction of concretecuring and finishing.

    Testing of fresh and hardened concretequality of concrete - Nondestructive testing.

    UNIT II CONSTRUCTION PRACTICES

    Specifications, details and sequence of activities and construction co-ordinationSite ClearanceMarkingEarthwork - masonrystone masonryBond in masonry - concrete hollow block

    masonryflooringdamp proof coursesconstruction jointsmovement and expansion joints

    pre cast pavementsBuilding foundationsbasementstemporary shedcentering and

    shutteringslip formsscaffoldingsde-shuttering formsFabrication and erection of steeltrussesframesbraced domeslaying brickweather and water proofroof finishes

    acoustic and fire protection.

    UNIT III SUB STRUCTURE CONSTRUCTIONTechniques of Box jackingPipe Jacking -under water construction of diaphragm walls and

    basement-Tunneling techniquesPiling techniques - well and caisson - sinking cofferdam

    cable anchoring and grouting-driving diaphragm walls, sheet piles - shoring for deep cuttingwell points -Dewatering and stand by Plant equipment for underground open excavation.

    UNIT IV SUPER STRUCTURE CONSTRUCTIONLaunching girders, bridge decks, off shore platformsspecial forms for shells - techniques for

    heavy decksin-situ pre-stressing in high rise structures, Material handling - erecting light

    weight components on tall structures - Support structure for heavy Equipment and conveyors

    Erection of articulated structures, braced domes and space decks.

    UNIT V CONSTRUCTION EQUIPMENT

    Selection of equipment for earth work - earth moving operations - types of earthwork equipment- tractors, motor graders, scrapers, front end waders, earth moversEquipment for foundation

    and pile driving. Equipment for compaction, batching and mixing and concreting - Equipment

    for material handling and erection of structures - Equipment for dredging, trenching, tunneling,

    TEXT BOOKS

    1. Peurifoy, R.L., Ledbetter, W.B. and Schexnayder, C., "Construction Planning, Equipmentand Methods", 5th Edition, McGraw Hill, Singapore, 1995.

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    2/76

    2. Arora S.P. and Bindra S.P., Building Construction, Planning Techniques and Method ofConstruction, Dhanpat Rai and Sons, 1997.

    3. Varghese , P.C. Building construction, Prentice Hall of India Pvt. Ltd, New Delhi, 2007.4. Sheety, M.S, Concrete Technology, Theory and Practice, S. Chand and Company Ltd, New

    Delhi, 2005.

    REFERENCES

    1. Jha J and Sinha S.K., Construction and Foundation Engineering, Khanna Publishers, 1993.2. Sharma S.C. Construction Equipment and Management, Khanna Publishers New Delhi,

    1988.

    3. Deodhar, S.V. Construction Equipment and Job Planning, Khanna Publishers, New Delhi,1988.

    4. Dr. Mahesh Varma, Construction Equipment and its Planning and Application,Metropolitan Book Company, New Delhi-, 1983.

    5. Gambhir, M.L, Concrete Technology, Tata McGrawHill Publishing Company Ltd, NewDelhi, 2004

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    3/76

    UNIT I

    CONCRETE TECHNOLOGY

    CementsGrade of cements - manufacture of cementconcrete chemicals and Applications

    Mix design conceptmix design as per BIS & ACI methodsmanufacturing of concreteBatchingmixingtransportingplacingcompaction of concretecuring and finishing.Testing of fresh and hardened concretequality of concrete - Nondestructive testing.

    TYPES OF CEMENT

    Ordinary Portland cementOPC33,OPC43 and OPC53 grade

    Rapid hardening cement

    Extra rapid hardening cement Sulphate resisting cement Portland slag cement Quick setting cement Low heat cement Portland pazzolona cement Air entraining cement Colored cement White cement Hydrophobic cement Masonry cement expansive cement Oil well cement Redi set cemnt

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    4/76

    Concrete sleeper grade cement High alumina cement Very high strength cement

    CHEMICAL ADMIXTURES OF CONCRETE

    Water-reducing admixture / Plasticizers:

    These admixtures are used for following purposes:

    1. To achieve a higher strength by decreasing the water cement ratio at the same workabilityas an admixture free mix.

    2. To achieve the same workability by decreasing the cement content so as to reduce theheat of hydration in mass concrete.

    3. To increase the workability so as to ease placing in accessible locations4.

    Water reduction more than 5% but less than 12%

    Actions involved:

    1. Dispersion:Surface active agents alter the physic chemical forces at the interface. They are adsorbed on the

    cement particles, giving them a negative charge which leads to repulsion between the particles.

    Electrostatic forces are developed causing disintegration and the free water become available forworkability.

    2.

    Lubrication:

    As these agents are organic by nature, thus they lubricate the mix reducing the friction andincreasing the workability.

    3. Retardation:A thin layer is formed over the cement particles protecting them from hydration and increasing

    the setting time. Most normal plasticizers give some retardation, 3090 minutes

    Super Plasticizers:

    These are more recent and more effective type of water reducing admixtures also knownas high range water reducer

    The commonly used Super Plasticizers are as follows:

    Sulphonatedmelamineformaldehydecondensates(SMF)

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    5/76

    Give 1625%+ water reduction. SMF gives little or no retardation, which makes them very

    effective at low temperatures or where early strength is most critical.

    However, at higher temperatures, they lose workability relatively quickly. SMF generally give a

    good finish and are colorless, giving no staining in white concrete.

    They are therefore often used where appearance is important.

    Sulphonated naphthalene formaldehyde condensates (SNF)

    Typically give 1625%+ water reduction. They tend to increase the entrapment of larger,unstable air bubbles. This can improve cohesion but may lead to more surface defects.

    Retardation is more than with SMF but will still not normally exceed 90 minutes. SNF is a verycost-effective.

    Polycarboxylate ether super plasticizers (PCE)

    Typically give 2035%+ water reduction. They are relatively expensive per liter but are verypowerful so a lower dose (or more dilute solution) is normally used.

    In general the dosage levels are usually higher than with conventional water reducers, and the

    possible undesirable side effects are reduced because they do not markedly lower the surfacetension of the water.

    Accelerators:

    An admixture which, when added to concrete, mortar, or grout, increases the rate of hydration ofhydraulic cement, shortens the time of set in concrete, or increases the rate of hardening or

    strength development.

    Accelerating admixtures can be divided into groups based on their performance and application:

    1. SetAcceleratingAdmixtures,Reduce the time for the mix to change from the plastic to the hardened state.

    Set accelerators have relatively limited use, mainly to produce an early set.

    2. HardeningAccelerators,Which increase the strength at 24 hours by at least 120% at 20C and at 5C by at least 130% at48 hours. Hardening accelerators find use where early stripping of shuttering or very early access

    to pavements is required.

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    6/76

    They are often used in combination with a high range water reducer, especially in cold

    conditions.

    .

    Set Retarders:

    The function of retarder is to delay or extend the setting time of cement paste in concrete. Theseare helpful for concrete that has to be transported to long distance, and helpful in placing the

    concrete at high temperatures.

    When water is first added to cement there is a rapid initial hydration reaction, after which there is

    little formation of further hydrates for typically 23 hours.

    The exact time depends mainly on the cement type and the temperature. This is called the

    dormant periodwhen the concrete is plastic and can be placed.

    At the end of the dormant period, the hydration rate increases and a lot of calcium silicate

    hydrate and calcium hydroxide is formed relatively quickly. This corresponds to the setting time

    of the concrete.

    Retarding admixtures delay the end of the dormant period and the start of setting and hardening.

    This is useful when used with plasticizers to give workability retention. Used on their own,retarders allow later vibration of the concrete to prevent the formation of cold joints between

    layers of concrete placed with a significant delay between them.

    The mechanism of set retards is based on absorption. The large admixture anions and molecules

    are absorbed on the surface of cement particles, which hinders further reactions between cementand water i.e. retards setting.

    Air Entrained Admixtures:

    An addition for hydraulic cement or an admixture for concrete or mortar which causes air,usually in small quantity, to be incorporated in the form of minute bubbles in the concrete or

    mortar during mixing, usually to increase its workabilityand frost resistance.

    Air-entraining admixtures are surfactantsthat change the surface tension of the water.

    Traditionally, they were based on fatty acid salts or vinsol resin but these have largely been

    replaced by synthetic surfactants or blends of surfactants to give improved stability and voidcharacteristics to the entrained air.

    Air entrainment is used to produce a number of effects in both the plastic and the hardened

    concrete. These include:

    Resistance to freezethaw action in the hardened concrete.

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    7/76

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    8/76

    Water is added to make a thick paste which contains 14% of moisture

    The paste format are dried and off charged into a rotary kiln

    The product obtained often calcinations in rotary kiln

    The clinker I obtained as a result of incipient fusion and sintering at a temp about 1400c to1500 c

    The clinker is cooled to preserve the meta stable compounds and there solid solutions

    Dispersion of one solid with another solid which made the clinker again heated

    Clinker is again cooled and grounded in tube mills where 2-3% gypsum is added

    The purpose of adding gypsum is to coat the cement particle by interfering the process of

    hydration of cement particles

    The flow diagram of dry process

    Wet process

    The operations are

    Mixing Burning Grinding

    Process

    The crushed raw materials are fed in to a ball mill and a little water is added

    The steel balls in the ball mill pulverized the raw material which form a slurry with water

    The slurry is passed through storage tanks where the proportioning of compound is adjusted toensure desired chemical composition

    The corrected slurry having moisture about 40%,is then fed into rotary kiln

    Where it loses moisture and form on to lumps

    These are finally burned at 1500 to 1600 c

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    9/76

    It becomes clinker at this stage, the clinker is cooled and then grounded in tube mills

    While grinding the clinker 3% gypsum I added this is stored in silos and packed

    Concrete Mix Design concept

    Definition:

    Mix design can be defined as the process of selecting suitable ingredients of concrete and

    determining their relative proportions with the object of producing concrete of certain minimumstrength and durability as economically as possible.

    One of the ultimate aims of studying the various properties of the materials of concrete, plastic

    concrete and hardened concrete is to enable a concrete technologist to design a concrete mix fora particular strength and durability.

    The design of concrete mix is not a simple task on account of the widely varying properties of

    the constituent materials, the conditions that prevail at the site of work, in particular the exposurecondition, and the conditions that are demanded for a particular work for which the mix is

    designed.

    Design of concrete mixrequires complete knowledge of the various properties of these

    constituent materials, these make the task of mix design more complex and difficult.

    Design of concrete mix needs not only the knowledge of material properties and properties of

    concrete in plastic condition; it also needs wider knowledge and experience of concreting.

    Even then the proportion of the materials of concrete found out at the laboratory requires

    modification and re adjustments to suit the field conditions.

    With better understanding of the properties, the concrete is becoming more and more an exactmaterial than in the past.

    The structural designer specifies certain minimum strength; and the concrete technologistdesigns the concrete mix with the knowledge of the materials, site exposure conditions and

    standard of supervision available at the site of work to achieve this minimum strength and

    durability.

    Further, the site engineer is required to make the concrete at site, closely following the

    parameters suggested by the mix designer to achieve the minimum strength specified by thestructural engineer.

    In some cases the site engineer may be required to slightly modify the mix proportions given by

    the mix designer.

    He also makes cubes or cylinders sufficient in numbers and tests them to confirm theachievements with respect to the minimum specified strength. Mix designer, earlier, may have

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    10/76

    made trial cubes with representative materials to arrive at the value of standard deviation or

    coefficient of variation to be used in the mix design.

    American Concrete Institute Method of Mix Design 11.3 (ACI Concrete Mix Design)

    This method of proportioning was first published in 1944 by ACI committee 613. In 1954 themethod was revised to include, among other modifications, the use of entrained air. In 1970, the

    method of ACI mix design became the responsibility of ACI committee 211. We shall now deal

    with the latest ACI Committee 211.1 method.

    It has the advantages of simplicity in that it:

    1. Applies equally well2. With more or less identical procedure to rounded or angular aggregate3. To regular or light weight aggregates4. To air entrained or non-air-entrained concretes.

    Manufacturing of concrete

    IntroductionProduction of concrete requires meticulous care at every stage

    The ingredients of good and bad concrete are same but good rules are not

    Observed it may become bad

    Manufacturing of concrete includes the following stages

    1. Batching2.

    Mixing3. Transporting

    4. Placing5. Compacting6. Curing7. Finishing

    Batching

    The measurement of materials for making concrete is known as batching.

    Methods of batching Volume batching Weigh batching

    Volume batching

    The required ingredients of conc. Are measured by volume basis

    o Volume batching is done by various types of gauge boxes

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    11/76

    o The gauge boxes are made with comparatively deeper with narrow surfaceo Some times bottomless gauge boxes are used but it should be avoided

    Volume batching is not a good practice because of the difficulties it offers to granularmaterial.

    Some of the sand in loose condition weighs much less than the same volume of dry

    compacted soil.

    For un important concrete or any small job concrete may be batched by volume.

    Weigh batching

    It is the correct method of measuring materials for concrete.

    Use of weight system in batching ,facilitates accuracy flexibility and simplicity

    The different types of weigh batching are there, they are used based on the different situation.

    In small works the weighing arrangement consist of two weighing buckets connected to the

    levers of spring loaded dials which indicates the load,

    The weighing buckets are mounted on a central spindle about which they rotate

    On large works the weigh bucket type of weighing equipment used ,the materials are fedfrom the over head storage hopper and it discharges by gravity.

    Mixing

    Thorough mixing of materials is essential for the production of uniform concrete

    The mixing should ensure that the mass becomes homogeneous uniform in color and

    consistency.

    Types of mixingHand mixing

    Machine mixing

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    12/76

    Hand mixing

    It is practiced for small scale un important concrete works

    Hand mixing should be done over a impervious concrete or brick floor sufficiently large size

    take one bag of cement .

    Spread out and measure d out fine aggregates and course aggregate in alternative layers.

    Pour he cement on the top of it and mix them dry by showel, turning the mixture over andover again until the uniformity of color is achieved.

    The uniform mixture is spread out in the thickness of about 20 cm

    The water is taken and sprinkled over the mixture and simultaneously turned over

    The operation is continued till such time a good uniform homogeneous concrete is obtained

    Machine mixing

    Mixing of concrete almost invariably carried ot by machine ,for reinforced concrete work

    medium or large scale concrete works .

    Machine mixing is not only efficient it is also economical when quantity of concrete to be

    produced is large

    Type of mixer for mixing concrete

    Batch mixer Continuous mixer

    Batch mixer

    Batch mixer produce concrete batch by batch with time interval

    This is used in normal concrete work

    Batch mixers are two types

    Pan type Drum type

    Drum types are further classified into tilting ,non tilting and forced action type

    The capacity of batch mixer depends on the proportion of the mix

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    13/76

    For 1:2:4 ideal mixer 200 liters

    For 1:3:6 ideal mixer 280 liters

    Mixing time

    Concrete mixers are generally designed to run at a speed of 15 to 20 revolutions per minute

    For proper mixing it is seen that about 25to 30 revolutions are required in a well designed

    mixer

    It is important that a mixer should not stop in between concreting operations for this

    requirement concrete mixer must be kept maintained

    Transporting of concrete

    Concrete can be imported by variety of methods and equipments

    Methods adopted for transportation of concrete

    Mortar pan]

    Wheel barrow Crane, bucket and rope way Truck mixers and dumpers Belt conveyors Chute Skip and hoist Transit mixer Pump and pipe line Helicopter

    Mortar pan

    This case concrete is carried out in small quantities

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    14/76

    This method exposes greater surface area of concrete for drying conditions

    This results a geat loss of water particularly in hot weather

    Mortar pan must be wetted to start with and must be kept clean

    Wheel barrow

    Used for transporting concrete in ground level.

    This method is employed for hauling concrete in longer distance in case of concrete road

    construction.

    If the distance is long or ground is rough it is likely that the concrete get segregated due to

    vibrationTo avoid this, wheel barrows are provided with pneumatic wheel.

    Crane bucket and rope way

    This is one of the right way for transporting concrete above the ground level

    Crane can handle concrete in high rise construction project and are becoming familiar sites in bigcities

    Rope way buckets of various sizes are used

    Rope way method is adopted for

    Concrete works in valley

    Construction work of the pier in the river

    For dam construction

    Truck mixer and dumpers

    For large concrete works particularly for concrete to be placed at ground level

    These are ordinary open steel tipping lorries

    Dumpers having 2-3 cubic meter capacity

    Belt conveyors also can be used for

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    15/76

    Chutes

    Provided for transporting concrete from ground to lower level

    The surface should have same slope not flatter than 1 vertical to 2 and a1/2 horizontal

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    16/76

    Skip and hoist

    Adopted method for transporting concrete vertically for 3 to 4 floors

    Mortar pan with staging and human ladder is used for transporting concrete

    Transit mixer

    This is the equipment for transporting concrete over a big distance particularky ready mix

    concreteThey are truck mounted having a capacity of 4 to 7 m3

    The speed of rotation of truck mixer is 4to16 rev/min

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    17/76

    A small concrete pump is also mounted on the truck carrying transit mixer

    Pumps and pipe lines

    Universally accepted method

    Starts with the suction stroke for suck the concrete inside the pipe

    It has a piston which moves forward and backward to have suction and delivery of concrete

    Choosing a correct pump involves Length of horizontal pipe Length of vertical pipe Number of bends Diameter of pipe line Length of flexible hose Change in line diameter Slump of concrete

    Placing of concrete

    Concrete must be placed in a systematic manner to yield optimum results

    Some situation where we used provide concrete

    Placing concrete within earth mould

    Placing concrete with large earth mould or timber plank form work

    Placing concrete in layers with in timber or steel shutter

    Placing concrete with in usual form work

    Placing concrete under water

    Placing concrete within earth mould

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    18/76

    Concrete is invariably as foundation bed below the walls and columns

    Before placing concrete

    All loose earth must be removed

    Roots of trees must be cut

    If surface is dry must be made just damp

    If it is too wet or rain soaked the water slush must be removed

    Placing concrete with large earth mould or timber plank form work

    For construction of road slabs,air field slabs and ground floor slabs in building conc os placed inthis method

    The ground surface must be free from loose earth pool of water ,grass or roots or leaves

    The earth must be compacted well

    Poly ethylene film is used in between conc ground to avoid absorption of moisture

    Concrete is laid alternative layers to give enough scope for shrinkage

    Placing concrete in layers with in timber or steel shutter

    This can be used in the following cases

    Dam construction

    Construction of concrete abutments

    Raft for a high rise building

    The thickness of layers depend on

    Method of compactionSize of vibrator

    Frequency of vibrator used

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    19/76

    It is good for laying 15 to 30 cm thick layer of concrete ,for mass concrete it may varie from 35

    to 45 cm

    Its better to leave the top of the layer rough so that succeeding layer can have the good bond

    Placing concrete with in usual form work

    This can be adopt for Column ,beam and floors

    Rules that should be followed while placing the concrete

    Check the reinforcements are correctly tied and placed Check the reinforcement is having appropriate cover The joints between plywoods or sheets properly plugged Mould releasing agent should be applied

    The concrete must be placed very care fully a small quantity at a time so that they will not blockthe entry of subsequent concrete

    Placing concrete under water

    Concrete is often required to be placed under water or I a trench filled with slurry

    In such a cases use of bottom slurry buckets or termic pipes are used

    In the bottom bucket concrete is taken through water in a water tight box or bucket reaching finalplace of deposition

    The bottom is made to open by some mechanism and the whole concrete is dumped slowly.

    Compaction of concrete

    Compaction of concrete is the process adopted for expelling the entrapped air from the concrete

    Method for compacting concrete

    Hand compaction

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    20/76

    Compaction by vibrator

    Compaction by pressure and jolting

    Compaction by spinning

    Hand compaction

    Adopted in case of unimportant concrete

    This can be adopted when mechanical mean cannot be used

    It consist of Roding Ramming Tamping

    Roding

    Poking the concrete with about 2m long 16 mm dia rod to poke the concrete reinforcement

    Ramming

    Should be done with care

    Permitted in unreinforced foundation concrete in ground floor construction

    Tamping

    The thickness of conc should be comparatively less

    Consist of beating the op surface by wooden cross beam

    The section of wooden beam is about 10x10 cm

    Compaction by vibrators

    We can place the concrete economically when compared to hand compaction

    The use of vibrators may be essential for the production of good concrete

    Type of vibrators

    Internal vibrator

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    21/76

    Formwork vibrator

    Table vibrator

    Platform vibrator

    Surface vibrator

    Vibratory rollers

    Compaction by pressure and jolting

    This is one of the effective method of compacting dry concrete

    Often used for compacting hollow block ,cavity blocks concrete blocks

    The stiff concrete is vibrated pressed and also given jolts

    With the combined action of the three the stiff conc gets compacted to an dense form to give

    good strength and volume

    Compaction by spinning

    This is one of the recent method of the compacting concrete

    This is adopted for fabrication of concrete pipes

    The plastic concrete when at every high speed get well compacted by centrifugal force

    Potential products such as spun pipes are compacted by spinning process

    Vibratory rollers

    One of the recent methods of compacting very lean or dry concrete

    The concrete compacted by rollers can be called as roller concrete

    Tests on concrete

    Concrete Slump Test

    This test is performed to check the consistency of freshly made concrete.

    The slump test is done to make sure a concrete mix is workable.

    The measured slump must be within a set range, or tolerance, from the target slump.

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    22/76

    Workability of concrete is mainly affected by consistency i.e. wetter mixes will be more

    workable than drier mixes, but concrete of the same consistency may vary in workability.

    It can also be defined as the relative plasticity of freshly mixed concrete as indicative of its

    workability.

    Tools and apparatus used for slump test (equipment):

    1. Standard slump cone (100 mm top diameter x 200 mm bottom diameter x 300 mm high)2. Small scoop3. Bullet-nosed rod (600 mm long x 16 mm diameter)4. Rule5. Slump plate (500 mm x 500 mm)

    Procedure of slump test for concrete:

    Clean the cone. Dampen with water and place on the slump plate. The slump plate should beclean, firm, level and non-absorbent. Collect a sample of concrete to perform the slum test

    .

    Stand firmly on the footpieces and fill 1/3 the volume of the cone with the sample. Compactthe concrete by 'rodding' 25 times. Rodding means to push a steel rod in and out of theconcrete to compact it into the cylinder, or slump cone. Always rod in a definite pattern,

    working from outside into the middle. Now fill to 2/3 and again rod 25 times, just into the top of the first layer. Fill to overflowing, rodding again this time just into the top of the second layer. Top up the

    cone till it overflows. Level off the surface with the steel rod using a rolling action. Clean any concrete fromaround the base and top of the cone, push down on the handles and step off the footpieces.

    Carefully lift the cone straight up making sure not to move the sample.Turn the cone upside down and place the rod across the up-turned cone.

    Take several measurements and report the average distance to the top of the sample.If the sample

    fails by being outside the tolerance (ie the slump is too high or too low), another must be taken.If this also fails the remainder of the batch should be rejected.

    Compression Test

    The compression test shows the compressive strength of hardened concrete.

    The compression test shows the best possible strength concrete can reach in perfect conditions.

    The compression test measures concrete strength in the hardened state. Testing should always be

    done carefully. Wrong test results can be costly.

    http://www.aboutcivil.com/Properties-of-concrete-factors-affecting-them.htmlhttp://www.aboutcivil.com/Properties-of-concrete-factors-affecting-them.html
  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    23/76

    The testing is done in a laboratory off-site. The only work done on-site is to make a concrete

    cylinder for the compression test.

    The strength is measured in Megapascals (MPa) and is commonly specified as a characteristic

    strength of concrete measured at 28 days after mixing.

    The compressive strength is a measure of the concretes ability to resist loads which tend to

    crush it.

    Apparatus for compression test

    Cylinders (100 mm diameter x 200 mm high or 150 mm diameter x 300 mm high) (The small

    cylinders are normally used for most testing due to their lighter weight)

    1. Small scoop2. Bullet-nosed rod (600 mm x 16 mm)3.

    Steel float4. Steel plate

    Procedure for compression test of concrete

    Clean the cylinder mould and coat the inside lightly with form oil, then place on a clean,level and firm surface, ie the steel plate. Collect a sample.

    Fill 1/2 the volume of the mould with concrete then compact by rodding 25 times. Cylindersmay also be compacted by vibrating using a vibrating table.

    Fill the cone to overflowing and rod 25 times into the top of the first layer, then top up themould till overflowing.

    Level off the top with the steel float and clean any concrete from around the mould.

    Cap, clearly tag the cylinder and put it in a cool dry place to set for at least 24 hours.

    After the mould is removed the cylinder is sent to the laboratory where it is cured andcrushed to test compressive strength

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    24/76

    UNIT II

    CONSTRUCTION PRACTICES

    Specifications, details and sequence of activities and construction co-ordinationSite ClearanceMarkingEarthwork - masonrystone masonryBond in masonry - concrete hollow blockmasonryflooringdamp proof coursesconstruction jointsmovement and expansion joints

    pre cast pavementsBuilding foundationsbasementstemporary shedcentering and

    shutteringslip formsscaffoldingsde-shuttering formsFabrication and erection of steeltrussesframesbraced domeslaying brickweather and water proofroof finishes

    acoustic and fire protection.

    Sequence of activities and construction co-ordination

    Planning

    Planning is considered as a precondition measures before attending any development program

    Particularly planning is more important in the following area

    When the fund available are limited

    The total requirement is much higher

    Sequence of operation

    It is always desirable to divide large projects into several construction stages

    For prepare progress of construction each stage may be constructed under separate contraction

    It should be carried out in the proper method and arrangement

    Before starting to construct the structure we must go for the sequence of operation in the projectit is better way o arrange the labour material and equipment

    Following are the sequence of operation in a highway project

    Site clearance

    Earth work for laying embankment

    Construction of drainage works

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    25/76

    Construction of pavement structures

    Installation of light poles and road signals

    MARKING, SETTING OUT OF FOUNDATION

    Setting out is the process of laying down the excavation lines and centre lines on the ground

    before excavation is started after the foundation design is done

    For setting out the foundation of a small building the centre line of the longest outer wall of the

    building is first marked on the ground by stretching a string between wooden or mild steel pegs

    driven at the ends

    Two pegs one on either from the central peg are driven at the each end of the line

    Each peg is equidistant from the central peg and the distance between the outer pegs correspondsto the width of foundation trench to be excavated

    Each peg may be projected about 25 to 50 mm above ground level may be driven at a distance of

    2m from the edge of excavation

    When the string is stretched joining the corresponding pegs at the two extremities of the line the

    boundary of the trench to be excavated can be marked on the ground with dry lime powders

    A right angle can be set out b forming 3, 4 and 5 units long

    The centre line of the other wall which is perpendicular to the long wall can be marked by settingout right angles

    All the specifications are made by tape or prismatic compass may be used for setting out rightangles

    Similarly outer lines of the foundation trench of each cross wall can be set out

    For big project reference pillars of masonry is constructed first, these pillars may be about 20cm

    thick and 15cm wider than the width of the foundation

    EXCAVATION

    Excavation of foundation can be done by manually or with the help of special mechanical

    equipments

    Manually it can be done by the help of following equipments

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    26/76

    Spade Phawrah Pick axe Crowbar

    Rammer Wedge Boning rod Sledge hammer Basket Iron pan line and pinsMechanically the excavation can be done by the help of following machineries

    o Boom bucket dipper handleo

    Trencho Chain mounted bucketso Raking cuto Vertical cut

    FOUNDATION

    The foundation is he lower portion of the building, usually located below the ground level, which

    transmit the load of super structure to sub soil

    Functions of foundation

    Reduction of load intensity Even distribution of load

    Provision of level surface Lateral stability

    Safety against undermining Protection against soil movements

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    27/76

    Types of foundation

    Shallow foundation Deep foundation

    Shallow foundation

    If the depth of foundation is less than or equal to width of foundation it is called as shallow

    foundation

    Types of shallow foundation

    Spread footing Combined footing Strap footing Mat foundation

    Spread footing

    Spread footing is those which spread the super imposed load to of a wall or column over thelarge area

    Spread footing support either a column or a wall

    It has the following types

    Single footing Stepped footing Sloped footing Wall footing with out step Stepped footing for wall Grillage foundation

    Combined footing

    A spread footing which supports two are more columnsis termed as combined footing

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    28/76

    It has the following types

    Rectangular combined footing Trapezoidal combined footing Combined column wall footing

    Trapezoidal footing

    If the independent footings of two columns are connected by a beam it is called as strap footing

    A strap footing may be used where the distance between the columns is so great that a combined

    trapezoidal footing becomes quite narrow

    The strap beam does not remains in contact with soil and thus does not transfer any pressure to

    the soil

    Mat foundation

    A raft or mat is a combined footing that covers the entire beneath a structureAnd supports all walls and columns

    It is used when the allowable soil pressure is low are the building loads are heavy

    It is used to reduce the settlement above highly compressible soil

    Rafts may divided into three types

    o Solid slab systemo Beam slab systemo Cellular system

    Deep foundation

    If the depth of foundation is equal to or more than the width of the foundation is called deep

    foundation

    Types

    Deep strip rectangular or square footing Pile foundation Pier foundation or drilled caisson foundation

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    29/76

    Well foundation or caissonsDeep strip footing

    Whenever the depth of strip footing is more than the width it is called as deep strip footing

    Pile foundation

    it is a type of deep foundation in which the loads are taken to a low level by means of vertical

    members which may be timber or concrete or steel

    Types of pile foundation

    End bearing pile Friction pile Combined end bearing and friction pile Compaction pile

    End bearing piles

    End bearing piles are used to transfer load through water or soft soil to a suitable bearing stratum

    Such piles are used to carry heavy loads to hard strata

    Multi storied buildings are invariably founded on end bearing piles, so that the settlements are

    minimized

    Friction piles

    Friction piles are used to transfer loads to a depth of a friction load carrying material by means of

    skin friction along the length of the pile

    These piles mostly used in granular soil

    Combined end bearing and friction pile

    These are the piles which transfer the super imposed load both through side friction as well as

    end bearing

    Such piles are more common, especially the end bearing piles are passed through granular soil

    Compaction piles

    These piles are used o compact loose soil thus increasing there bearing capacity

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    30/76

    The pile tube driven to compact the soil is gradually taken out and sand is filled in its place thus

    forming the sand pile

    Pier foundation

    A pier foundation consist of a cylindrical column of large diameter to support transfer largesuper imposed loads to the firm strata below

    Generally pier foundation is shallower in depth than the pile foundation

    It has two types

    o Masonryo concrete pier

    Drilled caissons

    Well foundation or caissons are box like structurescircular or rectangular which are sunk from

    the surface of either land or water to the desired depth

    Caisson foundations are used for major foundation work such as

    Bridge pier and abutments in river

    Wharves and quay walls docks

    Large water front structures such as pump houses, subjected to heavy vertical and horizontalloads

    Well foundations are caissons are hollow from inside, which may filled withstand and areplugged at the bottom, the load is transferred to the perimeter wall called as steining

    Stone Masonry

    Definition:

    The art of building a structure in stone with any suitable masonry is called stone masonry.

    Types of Stone Masonry:

    Stone masonry may be broadly classified into the following two types:

    1. Rubble Masonry

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    31/76

    2. Ashlar Masonry1. Rubble Masonry:

    The stone masonry in which either undressed or roughly dressed stone are laid in a suitablemortar is called rubble masonry. In this masonry the joints are not of uniform thickness.

    Rubble masonry is further sub-divided into the following three types:

    Random rubble masonry Squared rubble masonry Dry rubble masonry

    1. Random rubble masonry: The rubble masonry in which either undressed or hammerdressed stones are used is called random rubble masonry. Further random rubble

    masonry is also divided into the following three types:

    a. Un coursed random rubble masonry:The random rubble masonry in whichstones are laid without forming courses is known as un coursed random rubble

    masonry. This is the roughest and cheapest type of masonry and is of varying

    appearance. The stones used in this masonry are of different sizes and shapes.before lying, all projecting corners of stones are slightly knocked off. Vertical

    joints are not plumbed, joints are filled and flushed. Large stones are used at

    corners and at jambs to increase their strength. Once "through stone" is used forevery square meter of the face area for joining faces and backing.

    Suitability:Used for construction of walls of low height in case of ordinary

    buildings.

    b. Coursed random rubble masonry: The random rubble masonry in which stonesare laid in layers of equal height is called random rubble masonry. In this

    masonry, the stones are laid in somewhat level courses. Headers of one coursed

    height are placed at certain intervals. The stones are hammer dressed.

    Suitability: Used for construction of residential buildings, go downs, boundary

    walls etc.

    Squared rubble masonry:The rubble masonry in which the face stones are squared on

    all joints and beds by hammer dressing or chisel dressing before their actual laying, is

    called squared rubble masonry.

    There are two types of squared rubble masonry.

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    32/76

    c. Coursed Square rubble masonry: The square rubble masonry in which chiseldressed stones laid in courses is called coarse square rubble masonry. This is a

    superior variety of rubble masonry. It consists of stones, which are squared on alljoints and laid in courses. The stones are to be laid in courses of equal layers. and

    the joints should also be uniform.

    Suitability: Used for construction of public buildings, hospitals, schools,markets, modern residential buildings etc and in hilly areas where good quality ofstone is easily available.

    d. Un coursed square rubble masonry: The squared rubble in masonry whichhammer dressed stones are laid without making courses is called un coursedsquare rubble masonry. It consists of stones which are squared on all joints and

    beds by hammer dressing. All the stones to be laid are of different sizes.

    Suitability: Used for construction of ordinary buildings in hilly areas where a

    good variety of stones are cheaply available.

    2. Dry rubble masonry: The rubble masonry in which stones are laid without using anymortar is called dry rubble masonry or sometimes shortly as "dry stones". It is anordinary masonry and is recommended for constructing walls of height not more than

    6m. In case the height is more, three adjacent courses are laid in squared rubble masonry

    mortar at 3m intervals.

    2. Ashlar masonry:

    The stone masonry in which finely dressed stones are laid in cement or lime mortar is known as

    ashlars masonry. In this masonry are the courses are of uniform height, all the joints are regular,

    thin and have uniform thickness. This type of masonry is much costly as it requires dressing ofstones.

    Suitability: This masonry is used for heavy structures, architectural buildings, high piers andabutments of bridges.

    Ashlars masonry is further sub divided into the following types:

    Ashlars fine or coarse ashlar masonry Random coarse ashlars masonry Rough tooled ashlar masonry

    Rock or quarry faced ashlars masonry Chamfered ashlars masonry Block in coarse masonry Ashlar facing

    Ashlar fine or coursed ashlar masonry: In this type of stone masonrystone blocks of same height in each course are used. Every stone is fine

    tooled on all sides. Thickness of mortar is uniform through out. It is an

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    33/76

    expensive type of stone masonry as it requires heavy labor and wastage of

    material while dressing. Satisfactory bond can be obtained in this type of

    stone masonry. Random coursed ashlar masonry: This type of ashlar masonry consists

    of fine or coursed ashlar but the courses are of varying thick nesses,

    depending upon the character of the building Rough tooled ashlar masonry: This type of ashlar masonry the sides ofthe stones are rough tooled and dressed with chisels. Thickness of joints is

    uniform, which does not exceed 6mm. Rock or quarry faced ashlar masonry:This type of ashlar masonry is

    similar to rough tooled type except that there is chisel-drafted margin left

    rough on the face which is known as quarry faced.

    Chamfered ashlar masonry: It is similar to quarry faced except that theedges are beveled or chamfered to 450 for depth of 2.5 cm or more.

    Block-in course masonry: It is the name given to a class of ashlar masonrywhich occupies an intermediate place between rubble and ashlars. The

    stones are all squared and properly dressed. It resembles to coursed rubblemasonry or rough tooled ashlar masonry.

    Ashlar facing:Ashlar facing is the best type of ashlars masonry. Since this is type ofmasonry is very expensive, it is not commonly used throughout the whole thicknessof the wall, except in works of great importance and strength. For economy the facing

    are built in ashlars and the rest in rubble.

    Brick masonry

    cher bricks on edges instead of bed

    This bond is weak in strength but it is economical Brick masonry is made up of brick units

    bonded together with mortar

    Components of brick masonry

    Brick Mortar

    Types of mortar

    Cement mortar Lime mortar Cement-lime mortar Lime surkhi mortar Mud mortar

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    34/76

    Types of bricks

    Traditional bricks Modular bricks

    Traditional bricks

    It has not been standardize in size

    Dimensions varies from place to place

    Thickness varies from varies from cm to 7.5cm,widthvaries from 10to13 cm and length varies

    from 20to25 cm

    Modular brick

    Any brick which is the same uniform size as laid down by bis

    The nominal size of the modular brick is 20cm x10cmx10cm

    Actual size is 19x9x9

    Classes of brick

    First class brick Second class brick Third class brick

    Bonds in brick work

    Stretcher bond Header bond English bond Flemish bond Facing bond English crossing bond Brick on edge bond Dutch bond Racking bond Zigzag bond Garden wall bondStretcher bond

    The length of the brick its along with the face of the wall\

    This pattern is used only for those wall which have thickness of half brick

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    35/76

    Header bond

    The width of the bricks are thus along the direction of the wall

    This pattern is used only when the thickness of the wall is equal to one brick

    English bond

    It is the most commonly used methodthis bond is considered to be the strongest

    This bond consist of alternate course of stretchers and headers

    Alternative courses will show either headers or stretchers in elevation

    There is nop vertical joint

    Every alternative header come centrally over the joint between two stretchers in corse in

    below

    Since the number of vertical joint in the header course twice the number of vertical joints instretcher course ,the joints in the header course are made thinner than the joints in the

    stretcher course

    Flemish bond

    Inthis type of course is comprised of alternative headers and stretchers

    Types of Flemish bond

    Double Flemish bond

    Single Flemish bond

    Double Flemish bond

    Every course consist of headers and stretchers placed alternatively

    The facing and backing of the wall in each course have the same appearance

    Single Flemish bond

    Single Flemish bond is comprised of double Flemish bond facing an English bond backing

    and hearting in each course

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    36/76

    Facing bond

    This bond is used where the bricks of different thickness are to be used in the facing andbacking of the wall

    The nominal thickness of facing brick is 10 cm and that of backing bricks is 9 cm the headercourse tis provided at a vertical interval of 90 cm

    English cross bond

    This is he modification of English bond to improve the appearance e of the wall

    Brick on edge bond

    This type of bond uses stretdutch bond

    DAMP PROOF COURSE

    Materials for Damp Proof Course (DPC):

    An effective damp proofing material should have the following properties;

    1. It should be impervious.2. It should be strong and durable, and should be capable of withstanding both dead as well

    as live loads without damage.

    3.

    It should be dimensionally stable.4. It should be free from deliquescent salts like sulphates, chlorides and nitrates.The materials commonly used to check dampness can be divided into the following three

    categories:

    1. Flexible Materials: Materials like bitumen felts (which may be hessian based orfibre/glass fibre based), plastic sheeting (polythene sheets) etc.

    2. Semi-rigid Materials: Materials like mastic, asphalt, or combination of materials orlayers.

    3. Rigid Materials: Materials like first class bricks, stones, slate, cement concrete etc.SELECTION OF MATERIALS FOR DAMP PROOF COURSE:

    The choice of material to function as an effective damp proof course requires a judicious

    selection. It depends upon the climate and atmospheric conditions, nature of structure and the

    situation where DPC is to be provided. The points to be kept in view while making selection ofDPC materials are briefly discussed below:

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    37/76

    1. DPC above ground level: For DPC above ground level with wall thickness generally notexceeding 40cm, any one of the type of materials mentioned above may be used. Cement

    concrete is however commonly adopted material for DPC at plinth level, 38 to 50mmthick layer of cement concrete M15 (1:2:4 mix) serves the purpose under normal

    conditions.

    In case of damp and humid atmosphere, richer mix of concrete should be used. The concrete is

    further made dense by adding water proofing materials like Pudlo, Impermo, Waterlock etc in its

    ingredients during the process of mixing. It is used to apply two coats of hot bitumen over thethird surface of the concrete DPC.

    1. DPC Material for floors, roofs etc: For greater wall thickness or where DPC is to belaid over large areas such as floors, roofs, etc, the choice is limited to flexible materialswhich provide lesser number of joints like mastic, asphalt, bitumen felts, plastic sheets

    etc.

    The felts when used should be properly bonded to the surface with bitumen and laid with jointsproperly lapped and sealed.

    1. DPC Material for situations where differential thermal movements occur: In parapetwalls and other such situations, materials like mastic, asphalt, bitumen felts and metal

    (copper or lead) are recommended. It is important to ensure that the DPC material isflexible so as to avoid any damage or puncture of the material due to differential thermal

    movement between the material of the roof and the parapet.

    2. DPC material for Cavity Walls: In cavity wall construction, like cavity over the door orwindow should be bridged by flexible material like bitumen felt, strips or lead etc.

    General principles to be observed while laying DPC are:

    1. The DPC should cover full thickness of walls excluding rendering.2. The mortar bed upon which the DPC is to be laid should be made level, even and free

    from projections. Uneven base is likely to cause damage to DPC.

    3. When a horizontal DPC is to be continued up a vertical face a cement concrete fillet75mm in radius should be provided at the junction prior to the treatment.

    4. Each DPC should be placed in correct relation to other DPC so as to ensure complete andcontinuous barrier to the passage of water from floors, walls or roof.

    Figures 1 to 7 explain provision of DPC under different conditions

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    38/76

    Figure 1: Air Drain

    Figure 2: DPC Treatment for basement on undrained soils.

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    39/76

    Figure 3: Plan of building showing DPC

    Figure 5: Asphalt tanking for basement

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    40/76

    Figure 6: DPC for flooring

    FLOORS

    The purpose of floor is to provide a level surface capable of supporting the occupants of the

    building, furniture, equipment and some time interior wall

    The floor must satisfy the following requirements

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    41/76

    Adequate strength and stability Adequate fire resistance Sound proof Damp resistance Thermal insulations

    Components of a floor

    Sub floor, basecourse or floor base

    Floor covering or flooring

    Selection of flooring materials

    Factor that affect the choice of flooring

    Initial cost Appearance Cleanliness Durability Damp resistance Sound insulation Thermal insulation Fire resistance Smoothness Hardness Maintenance

    Types of flooring

    Mud flooring and muram flooring Brick flooring Flag stone flooring cement concrete flooring Terrazzo flooring Mosaic flooring Tiled flooring Marble flooring timber flooring Asphalt flooring Rubber flooring Linoleum flooring Cork flooring

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    42/76

    Glass flooring Plastic or pvc flooring

    Mud flooring and muram flooring

    This type of flooring is cheap, hard highly impervious

    It is easy to construct and easy to maintain

    It has good thermal insulation property due to which it remains cool in summer and warm in

    winter

    Over a well prepared ground 25 cm thick selected moist earth is spread and it rammed well to

    compacted thickness of 15cm

    In order to prevent cracks small quantity of chopped straw is mixed

    Muram flooring

    Muram is a form of disintegrated rock with binding material

    To construct such a floor a 15 cm thick layer muram is laid over prepared sub grade over it 2.5cm thick powder layer of muram is spread and rammed

    Brick flooring

    The sub grade is compacted properly, to the desired leveland 7.5 cm thick layer is spread

    Over this a course of brick is laid flat in mortar is built

    Such flooring is used in cheap construction, especially where good bricks are available

    Flag stone flooring

    Flag stone is laminated sand stone available in 2cm to 4cm thickness in the form of stone slab of30X30 cm or 45X45cm and 60X60 cm

    This type of works also called paving.

    The stones are laid on concrete base the subsoil is properly compacted over which 10 to of limeconcrete or lean cement concrete is laid

    Cement concrete flooring

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    43/76

    This is commonly used for residential, commercial even industrial building..

    It is moderately cheap quite durable and easy to construct

    The floor consist of two components

    Base concrete

    Topping or wearing surface

    The base course ma be 7.5 to 10 cm thick

    The topping consist of 1:2:4 cement concrete

    Terrazzo flooring

    Terrazzo flooring is another type of floor finish that is laid in thin layer over concrete topping

    It is very decorative and good wearing properties

    Terrazzo is a specially prepare concrete surface containing cement and marble chips in the

    proportion to 1:1 1/4 to 1:2

    When the surface has set the chips are exposed by grinding operation

    Mosaic flooring

    Mosaic flooring Is made of small pieces of broken tiles of china glazed or of cement or of marblearranged in different pattern

    These pieces are cut to desired shape and sizes

    a concrete base is prepare as in the case of concrete flooring over that 5to8 thick lime surkhi

    mortar is spread over an area, over this 3mm thick cementing paste is layered and is left to dry

    about 4 hours,

    ,there after small pieces of broken tiles or marble pieces of different colors arranged definite

    pattern and hammered in different layers

    Tiled flooring

    Tiledflooring is constructed from square ,hexagonal or other shapes made up of clay cementconcrete and terrazzo

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    44/76

    These are available In various thickness

    Thes are commonly used in residential houses ,schools,hospitals and other public buildings

    Over the concrete base a 25 to 30 mm thick layr of lime mortar 1:3 to serve as a bedding

    The bedding mortar is allowed to harden for 12 to 24 hours

    Neat cement slurry is spread over it and the tiles are laid flat over it

    Marble flooring

    It is the superior type of flooring used in bathrooms and kitchens of residential building and

    hospitals ,sanitorium ,temples etc

    After the preparation of base concrete 20 mm thick bed layer of 1:4 cement mix spread under the

    area of each individual slabs.

    The marble layer is then laid over it and pressed with wooden mallet and leveled

    Timber flooring

    Timber flooring is used for carpentry halls ,dancing halls auditorium

    Etc

    These are not commonly usedin India because its costlier

    But hilly area where wood is available and temperature drops very low timber flooring is quite

    common

    The suspended type of wooden floor is supported above the ground

    The solid type of wooden floor is fully supported on the ground

    SCAFFOLDING

    When te higt of wall or column or othet structural member of a building exceeding1.5 m

    temporary structures needed to support trhe platforms over which the work man sit and carry o

    the work

    These temporary structures constructed very close to the wall is in the form of imber o steel

    frame work commonly called as scaffoldings

    Components of scaffoldings

    Ledgers Braces Put logs

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    45/76

    Transoms Boarding Guard rail Toe board

    Single scaffolding or brick layer scaffolding Double scaffoldings or masons scaffoldings Cantilever or needle scaffoldings Suspended scaffoldings Trestle scaffolding Steel scaffolding Patented scaffoldings

    Single scaffoldings

    This consists of a single frame work of standards, legers, put logs etcConstructed parallel to the wall at a distance of about 1.2 meters

    The standards are placed at a distance of 2to2.5m interval

    Ledger connected with the standards, and are provided at a vertical distance of 1.2to 1.5 m

    Put logs or connected with one end on the ledgers and other end at the holes of the wall at aninterval of1.2 to 1.5 m interval

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    46/76

    Double are masons

    scaffoldings It is very difficult to put holes in walls to m support putlogs in stone masonry

    In the case a strong scaffolding is used consisting of two rows of scaffolding

    The first row placed 20 to 30 cm away from the wall the other frame will 1m distance from the

    first one

    Put logs are the supported on both the supports, rakers and cross braces are provided to make the

    scaffolding more strong

    It also called as independent scaffoldings

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    47/76

    Cantilever or needle scaffolding

    Cantilever supports can be used under following circumctances

    Ground is week to support standardsConstruction of the upper part of the wall is to be carried out

    It is required to keep the ground near wall free for traffic etc i

    It ha s two types

    Single Frame

    Te standards are supported on series of needle taken out through opening or through holes

    Double frame

    The needles are projecting beams are strutted inside the floors

    Suspended scaffolding

    It is the light weight scaffolding used for repair works such as pointing, painting etc

    The working platforms are suspended from roofs by means of wire ropes or chains etc

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    48/76

    Trestle scaffolding

    Such type of scaffoldings are used for painting and repairing work inside the room up to a height

    of 5m

    The working platform is supported over the top of movable contrivances such as tripods laddersetc

    Steel scaffolding

    Steel scaffolding is practically similar to the timber scaffolding, here wooden members are

    replaced by steel couplets are fittings

    Such scaffolding can be erected and dismantled rapidly

    It has a greater strength and greater durability

    Patented scaffolding

    Many patented scaffolding made of steel are available in the market

    Thos scaffoldings are equipped with special couplings frames etc

    TRUSSES

    Trusses are the frame formed by number of straight members connected in the form of triangles

    The embers are made by steel angles and they are joined by rivet or welding, these joints arecalled nodes

    It is assumed that the external loads act at the nodes only and the members are subjected to onlytension or compression

    The compression members are called as struts and the tension members are called as ties

    Steel roof trusses are used under the following condition

    Large spans are to be covered

    Intermediate columns are to be avoided to have an unobstructed working area inside

    There is a heavy rain or snow fall

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    49/76

    Types of roof trusses

    King post truss

    Here t hecommon rafters are supported by wooden frame work called truss under required interval

    The frame work consist of a king post, two struts two principal rafters and tie beam

    The truss rest on stone bed blocks at either end

    The common rafters rest on wooden purlins which in turn are fixed to the principal rafters of thetruss

    The king post connect the ridge post and the middle of the tie beam

    The struts are connected to the king post at the bottom and the principal rafters at the top

    The roofing material is fixed to the common rafters king post truss is used for spans of 5m to 9m

    Queen post truss

    The frame work consist of two principal rafters ,two queen post one straining sill two struts onetie beam and one straining beam

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    50/76

    The common matters rest on wooden purlins

    The staining beam resist the horizontal thrust developed

    The struts are connected to the queen post at the bottom and the principal rafters at the top

    North light roof truss

    North light or saw tooth roof truss is special type of roof trusses suitable for factories engaging inmanufacturing work

    North light truss is sawtooth

    Actual lighting is taken an advantage during day time by using the north light roof trussesIn this type of trusses vertical drops are provided this drops are covered with glasses so as to

    permit light in to the interior

    Centering and shuttering

    Shuttering is the temporary ancillary construction used as a mould for the structures

    In which the concrete is placed and allowed to hardened

    These are classified as steel wooden plywood combined woods steel, reinforced concrete andplain concrete

    Requirements of shutteringThe material should be cheap and should be suitable for re use several times

    It should be practically water proof so that it should not observe water from concrete

    It should be strong enough to with stand all loads coming on it

    It should be stiff enough so that deflection is minimum

    The surface of the formwork should smooth and it should afford easy stripping

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    51/76

    Loads on form work

    Live load due to labour etcDead weight of wet concrete

    Hydrostatic pressure of the fluid concrete

    Impact due t pouring concrete

    Shuttering for column

    Components

    Sheeting or column shutter all around the column

    Yokes

    Wedges

    bolt

    Shuttering for beam and slab floor

    The slab is continous over the beam

    The slab is supported on 2.5 cm thick sheeting laid parallel to the main beam

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    52/76

    form work for stairs

    Shuttering of walls

    The boarding may be 4 to 5 cm thick for walls up to 3to 4m high

    The boards are fixed to 5cmX10cm posts known as struts are soldiers

    ROOF FINISHING

    Roof finishing accessories include all types of accessory materials that are used to finish a roof.

    Flashing, drip edge, and roof drains are all examples of roofing accessories.

    Roof finishing accessories are widely available for a range of applications and may be chosen

    for functional, aesthetic, or budgetary reasons.

    Roofing accessories are largely made from aluminum, steel, copper, or PVC vinyl. They include

    a range of products including

    Rain gutters and Drains and guards

    Flashing or weatherproofing materials

    Roof caps Drip edges Ridges and shingles Chimney caps Leader boxes Finials and turrets Weathervanes.

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    53/76

    Rain gutters and Drains and guards

    Rain gutters, drains and guards are roof finishing accessories that collect and divert rainwater

    away from the roof and building foundation.

    These types of roof finishing accessories may also reduce erosion, prevent leaks in the

    foundation or basement, reduce water exposure on painted surfaces, and collect water foradditional use.

    Rain gutter, drain and guard roof finishing accessories may be available with screens, louvers, or

    hoods for additional protection.

    Flashing or weatherproofing materials

    Roof finishing accessories also include flashing, also known as weatherproofing.

    Flashing refers to installing a thin, continuous piece of sheet material to prevent the passage of

    water into the structure from a joint or angle.

    Flashing roof finishing accessories are commonly used around protruding objects in the roof,

    such as chimneys or pipes, to prevent water from reaching seams or joints.

    Roof caps, drip edges, ridges and shingles, and chimney caps

    Roof caps, drip edges, ridges and shingles, and chimney caps are also common, functional roof

    finishing accessories

    . Roof caps provide ventilation via the rooftop. They are commonly made from copper or

    galvanized steel, and often include an insect screen.

    Drip edge roof finishing accessories are useful in stopping water from seeping under a roof

    deck, which can prevent frame rot.

    Roof ridge caps and shingles are also used as finishing accessories. Roof shingles are individual,overlapping elements used for water-resistance.

    At the roof ridge, there is typically a copper, lead, or plastic cap to ensure water protection.

    Ridge vents are also commonly used as roof finishing accessories to provide ventilation to attic

    or upper crawlspaces.

    Leader boxes, Finials and turrets and Weathervanes.

    Finishing accessories can also be decorative.

    These accessories include leader boxes, finials and turrets, and weathervanes. Leader box

    accessories are used with gutter systems to hide or diminish the sight of leader elbows, and areavailable in a range of decorative styles, shapes, and designs.

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    54/76

    Roof finials and turrets are caps or towers affixed to the highest point of the roof, largely for

    decoration. Turrets are often designed to hold clocks or bells.

    Similarly, weathervanes are another type of roof finishing accessory often used for decoration atthe highest point of the roof. Weathervanes are not solely used for decoration, however, as they

    also point to the direction of the wind. Other, unlisted types of roof finishing accessories may

    also be available.

    ACOUSTICS

    Acoustics is the science of sound ,which deals with origin ,propagation and auditory sensation ofsound and also with design and construction of different building units to set optimum condition

    for producing and listenig speech musi etc

    FIRE PROTECION

    No building material is perfectly fire proof

    A wider interpretation of the fire safety may be deemed to cover the following aspects

    Fire prevention and reduction of number of out breaks of fire

    Spread of fire both internally and externally

    Safe existence of any and all occupants in the event of an out breaks of fire

    Fire load

    Fire load is the amount of heat in kilocalories which is liberated per square meter of floor area ofany combustible parts of the building itself

    The fire load is determined by multiplying the weight of all combustible materials by their

    calorific value and dividing the floor area under consideration

    Grading of building according to fire resistanceThe national building code of India (sp:7-1970) divides building in to the following four types

    according to the fire load the building is designed to resist

    Type 1 construction all structural components have 4 hours fire resistance

    Type 2 construction all structural components have 3 fire resistance

    Type 3construction all structural components have 2 hours fire resistance

    Type 4 construction all structural components have 1 hour fire resistance

    General fire safety requirements for buildings

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    55/76

    All building and particularly building having more than one storey shall be provided withliberally designed and safe fire proof existence

    The exist shall be so placed that they are always immediately accessible and each is capable oftaking all the persons on that floor a s alternative escape route

    Escape route shall be well ventilated as persons using the escapes are likely to over come from

    smoke

    Fire proof door shall conform rigidly to the fire safety requirements

    Electrical and mechanical lifts while reliable undr normal condition may not always be relied onescape purpose

    Lift shafts and stairways invariably serve as flues are tunnels thus increasing the fire byincreased draught

    Floors are required to withstand the effect of fire for full period stated for the particular grading

    Roofs of the various fire grades of the building shall be designed and constructed to withstand

    the effect of fire for the maximum period

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    56/76

    UNIT III

    SUB STRUCTURE CONSTRUCTION

    Techniques of Box jackingPipe Jacking -under water construction of diaphragm walls and

    basement-Tunneling techniquesPiling techniques - well and caisson - sinking cofferdamcable anchoring and grouting-driving diaphragm walls, sheet piles - shoring for deep cuttingwell points -Dewatering and stand by Plant equipment for underground open excavation.

    TECHNIQUES OF BOX JACKING

    Necessity of this technique

    When the increasing demands for various forms of transport infra structure to be constructed in

    congested locations or below existing facilities the need to be able to install large structures

    without destruction is a growing need.

    The jacking of large boxes to create an underpass below a railway track or road without

    destruction

    For around 30 years this box jacking techniques has found wide use Europe and India

    Types of structures under jacking

    Box jacking

    Arch jacking

    Pipe jacking

    OPERATONSThe box shaped tunnel structures are pre fabricated units which are pushed into soil by hydraulic

    jack

    Soil is excavated at the advancing face by manual means or by excavators

    To avoid settlements of over laying roads or rail track soil is excavated after it enters the cutting

    heads

    Excavation ahead of the cutting is avoided the cutting head is moved forward in small

    increments to avoid any having of the road or rail track

    In addition to that, without stabilizing the soil, the box technique would cause the super structure

    to settle the threatening structure failure so the ground ahead of tunnel boxes needed to be frozen

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    57/76

    PIPE JACKING

    In tunnels of damages above 2m men and machines worked the tunnel phase exacting andproviding soil support to the excavator soil by erecting the lining. The tunnel diameter becomes

    small it becomes difficult for workers to carry out soil excavation of in erect the tunnel lining

    system with in the tunnel shield

    For diameter in the range of 0.5m to 1.5m it is more efficient to excavate the soil by drilling

    systems controlled from a shaft or a pit to push the tunnel lining segment from the shaft or pit

    these techniques are often referred to us pipe jacking or micro tunneling techniques andequipments

    Pipe jacking refers to a technique in which a man in a sitting or crouch position, users epic and

    shovels to excavate tunnel face and the pipe is jacked forward from a shaft using hydraulicjacking system

    Horizontal auguring refers to a similar technique in which the man is replaced by a horizontalcontinuous flight helical auger

    INSTALATION

    The pipe sections are moved forward by hydraulic jacking and the miniature TBM derive itsreaction from these section

    Pipe segments of length 1 to 3 diameters 0.5 to 2m can be jacked into the soil using reaction

    from the concrete wall erected at the rior of jacking pit.

    DIAPHRAGM WALL

    In structural engineering, a diaphragmis a structural system used to transfer lateral loads toshear walls or frames primarily through in-plane shear stress

    . These lateral loads are usually wind and earthquake loads, but other lateral loads such as lateral

    earth pressure or hydrostatic pressure can also be resisted by diaphragm action.

    The diaphragm of a structure often does double duty as the floor system or roof system in a

    building or the deck of abridge, which simultaneously supports gravity loads.

    Diaphragms are usually constructed of plywood or oriented stand board in timber construction;

    Metal deck or composite metal deck in steel construction; or concrete slab in concrete

    construction.

    The two primary types of diaphragm are flexible and rigid. Flexible diaphragms resist lateral

    forces depending on the tributary area, irrespective of the flexibility of the members that they are

    transferring force to

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    58/76

    . On the other hand, rigid diaphragms transfer load to frames or shear walls depending on their

    flexibility and their location in the structure.

    Parts of a diaphragm include:

    the membrane, used as a shear panel to carry in-plane shear

    the drag strut member, used to transfer the load to the shear walls or frames The chord, used to resist the tension and compression forces that develop in the

    diaphragm, since the membrane is usually incapable of handling these loads alone.

    TUNNELING

    Process of making tunnels in order to reduce distance of travel or traffic congestion for highway

    and railway is called tunneling

    Tunneling is important for the following purpose

    o Time saving and reduction in fuelo Avoid unwanted traffic congestiono Maintain a proper speedo Avoid tiredness of travelo Avoid unwanted accidentso To avoid deforestation and death of animal while crossingo To avoid land slide in hilly regiono To avoid the long route around the mountaino

    To reduce the length of highway and railway and it may be economicalo To have flatter gradient that is essential to maintain the speed of the vehicle

    Tunneling types depending upon the shapes

    Poly centric

    Horse shoe

    Size of the tunnel

    It depends upon the number of track and the width and length of the mountain

    Alignment of tunneling

    o Identify the shortest routeo Height of mountain should be lesso Mark the points on the mountaino Transfer the tunnel inside the mountain by making of required depth

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    59/76

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    60/76

    The hammer is connected to the rope by a hook

    When it is lifted up after reaching a particular height it is dropped down

    Single acting hammer

    Hammer is lifted by stream and dropped then it will fell down in the top of the pile by

    gravitational force

    Double acting hammer

    It is the same as that of single acting but here both the lifting and dropping is done by steam

    engine

    Diesel hammer

    The process of lifting and dropping is done by diesel engine

    Vibrators

    If the soil condition is loose ,then using some vibrators the pile is inserted

    SHEET PILES

    It is the type of pile that is made of concrete, steel or wood

    The thickness of the pile is very less when compared to the length and width of the pile

    To prevent the entry water in construction the sheet piles are used, this is also used to separate

    the vertical member of the building

    The piles are inserted by some machine the depth of the piles can be increased by proper joints in

    successive installment

    Functions

    To enclose the site or part to prevent escape of loose soil

    To retain the sides of trenches or excavation

    To construct retaining wall in the marine structures

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    61/76

    To prevent seepage below the dams or hydraulic structures to construct coastal defense work

    To protect the foundation from scouring action of nearby river

    Concrete sheet piles

    Reinforced precast unit having the width of 50 to 60 cm and thickness 2to 6cm and the depth can

    be increased by further installment

    Timber sheet piles

    it is used only for temporary works ,the width of the pile varies from 225to 280 cm the thickness

    shall not be less than 50mm

    DEWATERING

    DEFINITION

    When water table exists at a shallow depth below ground surface, it is essential to lower the

    water so as to carry out construction of foundation, basement, and metro tunnels etc.This is

    achieved by pumping out water from multiple wells installed at the site. The process is called asdewatering.

    Types of dewatering method

    Dewatering can be done by adopting one of the following four strategiesDewatering of soil by temporary lowering of water table using wells and pumps prior excavation

    as depleted in figure

    Allowing water to reap into excavation area, collecting it in sumps and pumping it out. Before

    that adequate steps have to be taken to support the soil on sides of the excavated area, to prevent

    washing away of fines and have sufficient space for the work area.

    Making the soil around excavated zone impermeable by technique such as grouting are freezing

    so that inflow of water is stop are minimized.

    INSTALATION TECHNIQUE

    Sufficient size and capacity of dewatering system is necessary to lower and maintain groundwater table and to allow material to be excavated in a reasonable dry condition.

    Excavation slopes to be stabilized where sheeting is not required

    Dewatering system is to be operated continuously until backfill work has been completed.

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    62/76

    Then, the structure to be constructed at the excavated area has to be finished

    The complete stand by have to be available for immediate operation as may be required, toadequately maintain dewatering on continuous basis and in the event that all or any other part of

    the system may become inadequate or fail

    The water removed from the excavation to be disposed in such a manner as will not endangerportions of work under construction or completed.

    For dewatering purpose, well points deep well, caissons and tunnels are used.

    WELL POINTSDEWATERING

    When construction operation have to be excited below the ground water table level. Dewatering

    of soil can be done by the following methods

    Collecting water in sumps and pumping it out.

    Installing well points small or deep wells and pumping out ground water

    Using special technique in fine grained soils such as vaccum dewatering and electro-osmosis

    WELL POINTSTo pump out the ground water small sized wells called well points are used for a more dry

    working area the two methods used most often for lowering water table below the excavation

    level are the well point method and the deep well method.

    WELL POINT METHOD

    :This is economical and useful for lowering the water table by 15m or less.

    Incase of well point method or deep well method it is based on the fact that removal of water by

    continuous pumping from a well causes the water table level to become depressed and result in

    the formation of draw down.

    When a series of wells are placed close to each other, the overall effect is lowering of the water

    table level.

    Well points, being smaller, are easy to install.

    Well points, can lower the water table by only 6.7m because the pump, is located at the groundsurface and connected to group of well points through a pipe, cannot lift water from greater

    depth.

    Beyond 7m, multistage well points are used.

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    63/76

    DEEP WELL METHOD

    This method is useful for lowering the water table by more than 15m.

    Deep wells have larger diameter more depth and greater spacing.

    The pump is located at the bottom of well and hence can pump out water from greater depth.

    Deep wells become more economical if more points are required.

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    64/76

    UNIT IV

    SUPER STRUCTURE CONSTRUCTION

    Launching girders, bridge decks, off shore platformsspecial forms for shells - techniques for

    heavy decksin-situ pre-stressing in high rise structures, Material handling - erecting lightweight components on tall structures - Support structure for heavy Equipment and conveyorsErection of articulated structures, braced domes and space decks.

    BRIDGE DECKS

    The principal function of a bridge deck is to provide support to local vertical loads (from

    highway traffic, railway or pedestrians) and transmit these loads to the primary superstructure ofthe bridge, Figure 1(1). As a result of its function, the deck will be continuous along the bridge

    span and (apart from some railway bridges) continuous across the span. As a result of this

    continuity, it will act as a plate (isotropic or orthotropic depending on construction) to support

    cal patch

  • 8/13/2019 10111ce601 - Construction Techniques Equipments and Practice (1)

    65/76

    Continuity ensures that whether or not it has been designed to do so, it will participate in the

    overall structural action of the superstructure.

    The overall structural actions may include:

    Contributing to the top flange of the longitudinal girders, Figure 1(2).

    Contributing to the top flange of cross girders at supports and, where present in twingirder and cross girder structures, throughout the span, Figure 1(3).

    Stabilising longitudinal and cross girders, Figure 1(4).

    Acting as a diaphragm to transmit horizontal loads to supports, Figure 1(5).

    Providing a means of distribution of vertical load between longitudinal girders, Figure 1(6).

    It may be necessary to take account of these combined actions when verifying the design of the

    deck. This is most likely to be the case when there are significant stresses from the overall

    structural actions in the same direction as the maximum bending moments from local deckactions, e.g. in structures with cross girders where the direction of maximum momen