22
Detailed Project Report for Rail Based Mass Transit System in Varanasi Final Report CHAPTER 10: MAINTENANCE DEPOT February, 2016 Page 101 1 1 0 0 . . M M A A I I N N T T E E N N A A N N C C E E D D E E P P O O T T 10.1 INTRODUCTION The Maintenance facilities for BHU to BHEL Corridor and Benia Bagh to Sarnath Corridor of Varanasi MRTS are proposed to be provided at Ganeshpur Depot near BHEL for about 56 rakes of 3 car. Since, track connectivity between the two corridors is proposed at Beniabagh, one major depot near BHEL i.e. Ganeshpur Depot is planned to cater to the maintenance requirements of the corridors of Varanasi MRTS. The depots will have infrastructure to maintain the rakes with necessary facilities viz stabling lines, scheduled inspection lines, workshop for overhaul, unscheduled maintenance including major repairs, wheel profiling, heavy interior/under frame/roof cleaning etc. for the rolling stock operational on the corridor as well as maintenance facilities for Civil – track, buildings, water supply; Electrical Traction, E&M; Signalling & Telecomm.; Automatic Fare Collection etc. In broad terms, based on the planned rolling stock requirements, this chapter covers the conceptual design of the following aspects of the Depots. Conceptual design and layout of servicing shed and workshop to provide maintenance facilities and stabling facilities for Rolling Stock. Operational and functional safety requirements. Ancillary buildings for other maintenance facilities. Electrical & mechanical services, power supply and distribution system. Water supplies, drainage & sewerage. The details of the depot are provided on conceptual design basis and will work as a guideline for detailed design later. 10.2 MAINTENANCE PHILOSOPHY The outline of the maintenance philosophy followed would be as below: Typical Maintenance schedules being followed by Bangalore Metro have been considered for determining the requirement of lines in depot. Unit replacement and to get essential repairs to major equipments done by the OEMs.

10. Maintenance Depot 12.02.2016 final · TABLE 10.1: RAKE REQUIREMENT FOR DIFFERENT HORIZON YEARS Corridor Year 2023 2031 2041 Design BHU to BHEL Corridor (19.4 km) Headway (seconds)

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

  • Detailed Project Report for Rail Based Mass Transit System in Varanasi 

    Final Report                                                CHAPTER 10: MAINTENANCE DEPOT 

                                                                                            February, 2016                                                                        Page 10‐1 

    1100.. MMAAIINNTTEENNAANNCCEE   DDEEPPOOTT   10.1   INTRODUCTION 

    The Maintenance facilities for BHU to BHEL Corridor and Benia Bagh to Sarnath 

    Corridor of Varanasi MRTS are proposed  to be provided at Ganeshpur Depot 

    near BHEL  for about 56  rakes of 3 car. Since,  track connectivity between  the 

    two  corridors  is  proposed  at  Beniabagh,  one  major  depot  near  BHEL  i.e. 

    Ganeshpur Depot is planned to cater to the maintenance requirements of the 

    corridors of Varanasi MRTS. The depots will have infrastructure to maintain the 

    rakes  with  necessary  facilities  viz  stabling  lines,  scheduled  inspection  lines, 

    workshop  for  overhaul,  unscheduled  maintenance  including  major  repairs, 

    wheel profiling, heavy  interior/under  frame/roof  cleaning etc.  for  the  rolling 

    stock operational on  the  corridor as well as maintenance  facilities  for Civil – 

    track,  buildings,  water  supply;  Electrical  –  Traction,  E&M;  Signalling  & 

    Telecomm.; Automatic Fare Collection etc.  

    In broad terms, based on the planned rolling stock requirements, this chapter 

    covers the conceptual design of the following aspects of the Depots. 

    Conceptual design and layout of servicing shed and workshop to provide maintenance facilities and stabling facilities for Rolling Stock. 

    Operational and functional safety requirements.  Ancillary buildings for other maintenance facilities.  Electrical & mechanical services, power supply and distribution system.  Water supplies, drainage & sewerage. 

    The details of the depot are provided on conceptual design basis and will work 

    as a guideline for detailed design later.   

    10.2 MAINTENANCE PHILOSOPHY The outline of the maintenance philosophy followed would be as below: 

    Typical Maintenance schedules being followed by Bangalore Metro have been considered for determining the requirement of lines in depot.  

    Unit replacement and to get essential repairs to major equipments done by the OEMs.  

  • Detailed Project Report for Rail Based Mass Transit System in Varanasi 

    Final Report                                                CHAPTER 10: MAINTENANCE DEPOT 

                                                                                            February, 2016                                                                        Page 10‐2 

    Automation  with  state‐of‐the‐art  machinery  to  ensure  quality  and reliability. Labour intensive procedures will be kept to the minimum. 

    Maintenance  staff  shall  be  given  special  training  to  develop  high‐level skills  in  their  trade  to  ensure  quality  and  productivity  in  their 

    performance. 

    Adequate facilities for the stabling have been provided at the depot.  To  maintain  high  degree  of  cleanliness,  Automatic  washing  plant  has 

    been proposed for cleaning of rakes. 

    10.3 PLANNING OF MAINTENANCE FACILITIES SETUP The  Rolling  Stock  requirements  in  different  horizon  years  for  the  proposed 

    corridors are indicated in Table 10.1: 

               TABLE 10.1: RAKE REQUIREMENT FOR DIFFERENT HORIZON YEARS 

    Corridor  Year  2023  2031  2041  Design

    BHU to BHEL 

    Corridor 

    (19.4 km) 

    Headway (seconds)  276  228  174  144 

    No. of Cars/Train  3  3  3  3 

    Rakes Required  21  24  32  38 

    Cars Required  63  72  96  114 

    Beniabagh 

    to Sarnath 

    (9.9 km) 

    Headway (seconds)  360  258  228  192 

    No. of Cars/Train  3  3  3  3 

    Rakes Required  10  13  15  18 

    Cars Required  30  39  45  54 

     

    All  the  systems  and  infrastructure  on  the  proposed  corridors  has  been 

    conceptualized considering 3 car trains operating at 144 seconds headway for 

    BHU  to  BHEL  Corridor  and  192  seconds  headway  for  Beniabagh  to  Sarnath 

    corridor. 

    10.4 ROLLING STOCK MAINTENANCE NEEDS 

    10.4.1 Maintenance schedule 

    Servicing  requirements  shall  be  determined  from  the  Rolling  Stock 

    manufacturer.  Depending  upon  manufacturer's  requirements,  servicing 

    facilities may  be  provided  to  include  the  ability  to  carry  out  the  inspection, 

    maintenance,  overhaul  and  repair  of  the  rolling  stock  fleet,  including  the 

    following components: 

  • Detailed Project Report for Rail Based Mass Transit System in Varanasi 

    Final Report                                                CHAPTER 10: MAINTENANCE DEPOT 

                                                                                            February, 2016                                                                        Page 10‐3 

    Body;  Bogies;  Wheels (Re‐discing / re‐axling is planned at workshop only);  Traction motors;  Electrical components;  Electronics; PA/ PIS  Mechanical components;  Batteries;  Rolling stock air conditioning;  Brake modules;   Vehicle doors, windows and internal fittings. The  modern,  fully  equipped  facilities  are  to  be  provided  that  meet  these 

    requirements efficiently and  in full.  In meeting these requirements,  it shall be 

    assumed that the average daily distance travelled by each rolling stock unit  is 

    approximately 300 km. The following maintenance schedule has been followed 

    for the conceptual design:  

    TABLE 10.2: PROPOSED MAINTENANCE SCHEDULE 

    Type of Schedule Interval Work content Locations

    Daily  Daily  Check  on  the  train  condition  and 

    function  at  every  daily  service 

    completion.  Internal  cleaning  / 

    mopping  of  floor  and  walls  with 

    vacuum cleaner. 

    Stabling 

    Lines 

    A Service 

    Check 

    5,000 Km 

    (approx. 

    15 days) 

    Detailed  inspection  and  testing  of 

    sub  ‐systems,  under  frame, 

    replacement/  topping  up  of  oils  & 

    lubricants. 

    Inspection 

    Bays 

    B Service 

    Check 

    15,000 Km 

    (approx. 

    45 days) 

    Detailed inspection of ‘A’ type tasks 

    plus items at multiples of 15,000 Km 

    (‘B’ type tasks) 

    Inspection 

    Bays 

    Intermediate 

    Overhaul 

    (IOH) 

    420,000 

    Km 

    (approx. 

    3.5 years) 

    Check  and  testing  of  all  sub‐

    assemblies (Electrical + Mechanical). 

    Overhaul  of  pneumatic  valves, 

    Compressor.  Condition  based 

    Workshop 

  • Detailed Project Report for Rail Based Mass Transit System in Varanasi 

    Final Report                                                CHAPTER 10: MAINTENANCE DEPOT 

                                                                                            February, 2016                                                                        Page 10‐4 

    Type of Schedule Interval Work content Locations

    maintenance  of  sub‐systems  to 

    bring  them  to  original  condition. 

    Replacement  of  parts  and 

    rectification, trial run. 

    Periodical 

    Overhaul 

    (POH) 

    840,000 

    Km 

    (approx.  

    7 years) 

    Dismantling  of  all  sub‐assemblies, 

    bogies  suspension  system,  traction 

    motor, gear, control equipment, air‐

    conditioning  units  etc.  Overhauling 

    to bring  them  to original condition. 

    Checking repair and replacement as 

    necessary. Inspection and trial. 

    Workshop 

    Heavy 

    Repairs 

    ‐  Changing  of  heavy  item  such  as 

    bogies,  traction  motor,  axles,  gear 

    cases & axle boxes etc. 

    Workshop 

     

    The  above  Schedule  may  need  slight  revision  based  on  the  actual  earned 

    kilometers  per  train  and  the  specific  maintenance  requirements  of  Rolling 

    Stock finally procured. 

    10.4.2 Washing needs of Rolling Stock 

    The Metro trains are maintained to a high degree of cleanliness and therefore 

    needs the maintenance schedule as mentioned in Table 10.3. 

    TABLE 10.3: SCHEDULE OF CLEANING 

    S.N.  Kind of Inspection  Maint. Cycle Time  Maintenance Place 

    1. Outside Cleaning  (wet washing on automatic washing plant) 

    3 Days 10 mins 

    Automatic washing plantof Depot Single Pass 

    2. 

    Outside  heavy  Cleaning  (wet washing on  automatic washing plant  and  Front  Face, Vestibule/Buffer  area,  Floor, walls  inside/outside  and  roof. Manually) 

    30 days  3 Hrs Automatic  washing Plant & washing line 

        

  • Detailed Project Report for Rail Based Mass Transit System in Varanasi 

    Final Report                                                CHAPTER 10: MAINTENANCE DEPOT 

                                                                                            February, 2016                                                                        Page 10‐5 

    10.5   DEPOT CUM WORKSHOP LAYOUT Different  options  of  Depot  cum  Workshop  Layout  has  been  explored  to 

    optimize the area required for planning the maintenance facilities considering 

    1in 7 turnouts, 1 in 5 turnouts in place of 1 in 7 turnouts and depot layout on 

    elevated infrastructure. The three options are discussed as below: 

    Option 1: At Grade Layout Plan with 1 in 7 turnouts 

    Option‐1 of depot    layout  is proposed with a curve and ramp down  to depot 

    entry at grade level as shown in Annexure‐10.1. This layout has been planned 

    with all the required facilities in an area of about 13.2 hectares considering 1 in 

    7 turnouts and a minimum radius of 120m.  

    Option 2: At Grade Layout Plan with 1 in 5 turnouts 

    Option‐2 of depot  layout  is proposed with  1  in  5  turnouts  instead of  1  in  7 

    turnouts  similar  to maintenance  depot  constructed  in Mumbai Metro.  The 

    layout plan in option‐2 is proposed in an area of about 12.5 hectares indicating 

    all  the  infrastructure  facilities as  shown  in Annexure‐10.2. This option offers 

    the advantage of reduction in the land requirement for the depot i.e. about 0.7 

    hectares in comparison to layout in option‐1. Since, the depot constructed for 

    Mumbai Metro has been approved with certain restrictions and has not been 

    tested for its efficient and proper functioning. Thus, depot layout in option‐ 2 is 

    not recommended for Varanasi Metro Corridor. 

    Option 3: Elevated Layout plan with 1 in 7 turnouts 

    Option‐3 of the depot Layout  is proposed with elevated  infrastructure  in two 

    levels  along  the  BHEL  station  as  shown  in  Annexure  10.3(a).  Some  of  the 

    facilities in the depot viz. stabling lines, automatic coach wash plant, pit wheel 

    lathe, ETU  shed have been proposed elevated at a height of 13m and other 

    maintenance and inspection facilities have been proposed at ground level. The 

    ground  level  plan  and  the  upper  level  plan  for  the  depot  are  shown  in 

    Annexure 10.3 (b) and (c). The properties/buildings along the corridor have to 

    be  acquired  for  this  option.  Land  Cost  including  solatium  is  21.85  Crore/ 

    hectare.  Also, the construction of elevated depot shall have an additional cost 

    implication of Rs 44 crore per hectare for the elevated portion.  

    In  view  of  above  and  considering  the  cost  implications  and  acquisition  of 

  • Detailed Project Report for Rail Based Mass Transit System in Varanasi 

    Final Report                                                CHAPTER 10: MAINTENANCE DEPOT 

                                                                                            February, 2016                                                                        Page 10‐6 

    properties/buildings along the corridor for option‐3, it recommended to adopt 

    depot layout in option‐1 for Varanasi Metro Corridor. 

    The rake induction and withdrawal from depot to the open line will have to be 

    so planned  that  the headway of open  line  is not  affected.  For  this purpose, 

    facilities  for  simultaneous  receipt and dispatch of  trains  from depot  to open 

    line should be created. The stabling area should be  interlocked with the open 

    line so that the induction of train from the stabling can be done without loss of 

    time.  The  rake  washing  can  be  done  at  automatic  coach  washing  plant 

    provided at the entry of depot i.e. before rake is placed on stabling lines. 

    The other movements in the depot, viz from the stabling to the inspection shed 

    or workshop and vice versa may be non‐interlocked. Two emergency re‐railing 

    lines  have  been  provided  from  which  emergency  rescue  vehicles  can  be 

    dispatched  to open  line  in  the event of any emergency. To cater  to  the peak 

    requirements, all trains would be in the service, only trains under maintenance 

    would  be  in  the  shed.  However  during  the  off‐peak  hour  in  daytime, 

    approximately  half  of  the  trains  will  be  withdrawn  from  the  service.  The 

    scheduled inspections are envisaged to be carried out during the day off‐peak 

    hours and night. Tower wagon shall be housed inside the ETU cum emergency 

    rerailing building along with the Accident Relief Train.  

    The  stabling  and  the  yard  layout  would  be  at  grade  level  for  least  power 

    requirements in shunting movements and to avoid accidental rolling of Rolling 

    Stock resulting into accidents and damages to the property 

    10.6 INFRASTRUCTURE FACILITIES PLANNED AT DEPOT  

    10.6.1. Inspection Lines and Workshop Lines in Depot As per the frequency of  inspections  indicated  in Table 10.2, the visits of rakes 

    to Depots are as shown below in Figure 10.1: 

    To  assess  the  number  of  lines  required  to  maintain  the  rakes,  following 

    assumptions are made: 

     

    i. For Washing of rakes, an automatic washing plant  is proposed. Hence, no separate washing line is needed exclusively for washing. However, one line 

  • De

    Fina

        

    etailed Project 

    al Report 

                               

    is

    in

     

     

     

     

     

     

     

     

     

     

     

    ii. Iniii. Iniv. Ba

    da

    As  a

    inspe

     

    TAB

    Sche

    InspA SeChec

    B SeChec

    AdjuInsp

    Report for Rai

       

                              

      provided

    nside/outsid

    FIGU

    n a day, two

    n a day, one

    ased on the

    ays are take

    No. of day

    No. of Sun

    No. of ava

    gainst  abo

    ection of the

    BLE 10.4: IN

    edule Totper7

    pection Sheervice ck 

    ervice ck 

    ustment linepection Line

    l Based Mass T

     

                              

      for  heav

    de and roof

    RE 10.1 RA

    o rakes are t

    e rake is tak

    e number o

    en as 300 fo

    ys of Public 

    ndays in a y

    ailable work

    ove  require

    e rakes for V

    SPECTION A

    tal visits r rake in  years 

    v/

    112 

    54 

    e for minor s Provided

    Transit System i

         

         February, 20

    vy  cleanin

    ).   

    AKE VISITS T

    taken for ‘A

    en for ‘B ch

    of holidays a

    or calculatin

    holidays in 

    year 

    king days in 

    ement,  the

    Varanasi Me

    AND WORK

    METRO C

    Avg. visits /year

    TotAris(forrak

    16  89

    7.71  43

    repair/test

    in Varanasi 

                          

    016                     

    g  (Manua

    TO DEPOTS 

    A check’ on a

    hecks’ on a p

    as given bel

    ng the requi

    a year

    a year

    e  infrastruc

    etro corrido

    KSHOP LINE

    CORRIDORS

    tal sing r 56 es) 

    LiOccu

    96  2 rada

    32  1 rada

    ting after PO

               CHAPTER

                              

    l  cleaning

    AND WORK

    a pit line. 

    pit line. 

    low, total n

    irement of 

     :   13 

     :   52 

     :  365 ‐ 6

    cture  provi

    ors is indica

    ES PROVIDE

    ne pancy 

    LRe(le

    kes/ ay 

    kes/ ay 

    OH 

    R 10: MAINTEN

                             P

    g  of  Floor

    KSHOPS 

    umbers of 

    lines. 

    65 = 300 day

    ided  for  S

    ted in Table

    ED FOR VAR

    Lines equired (3 car ength) 

    LiPr(6le

    1.49 

    1.44 

    ANCE DEPOT 

    Page 10‐7 

    r,  walls 

    working 

    ys. 

    Schedule 

    e 10.4. 

    RANASI 

    nes rovided 6 car ength) 

    1 3 

  • Detailed Project Report for Rail Based Mass Transit System in Varanasi 

    Final Report                                                CHAPTER 10: MAINTENANCE DEPOT 

                                                                                            February, 2016                                                                        Page 10‐8 

    Workshop Shed 

    IOH  1  0.14  7.84 1 rake 10 days  0.261 

    POH  1  0.14  7.84 1 rake 20 days  0.523 

    Unscheduled Repair / Lifting /Wheel/Bogie sections etc.  2 Workshop Lines Provided  4  

    Ganeshpur  Depot  will  have  maintenance  facilities  and  infrastructure  to 

    maintain 56 rakes of 3 car  length  for  the Varanasi Metro corridors. Based on 

    the calculations  indicated  in Table 10.4, the depot  is proposed to be planned 

    with 3 inspection lines and 4 workshop lines.  

    10.6.2. Stabling Facility for Rakes 

    The  rake  requirement  for  the  corridors  of Varanasi Metro  viz.  BHU  to  BHEL 

    corridor and Beniabagh to Sarnath corridor  is 38 rakes of 3 car  length and 18 

    rakes of 3 car length respectively (Total 56 rakes of 3 cars i.e. 168 coaches) for 

    ultimate design. Ganeshpur depot near BHEL is planned with stabling facility of 

    12 lines of 9 car length each (to stable three rakes of 3 car on each line). Hence, 

    the depot will have stabling facility for 108 coaches. 

    In  addition  to  the  above  stabling  facility,  the  terminal  stations  viz.  BHU, 

    Beniabagh  and  Sarnath  have  been  also  planned   with  stabling  facility  for  4 

    rakes,  4  rakes  and  2  rakes  respectively.  At  a  given  time,  three  rakes would 

    remain  under  inspection  and  the  remaining  rakes  will  be  stabled  at  the 

    platforms of the terminal stations for the start of early morning services. 

    Hence,  there will be  sufficient  stabling  facility  for 56  rakes of 3  cars  i.e. 168 

    coaches and the depot will have sufficient facilities to cater to the maintenance 

    requirements of the rolling stock operational on the Varanasi MRTS corridors 

    for the ultimate design.  

    10.7 DEPOT CUM WORKSHOP PLANNING As per  the dimensions of  the Rolling  Stock,  the  approximate  length of 3‐car 

    trains would be 65 m (approx). However  in the design of the Inspection shed, 

    workshop  lines  and  stabling  lines  at  depot,  length  of  6‐car  train  is  taken  in 

    consideration.  

     

  • Detailed Project Report for Rail Based Mass Transit System in Varanasi 

    Final Report                                                CHAPTER 10: MAINTENANCE DEPOT 

                                                                                            February, 2016                                                                        Page 10‐9 

     

    I) Stabling Lines in Depot For the design of the stabling lines in the depot, following approximate lengths 

    have been taken in consideration: 

    (i) Length of one 3‐car rake= 65 m (ii) Gap between two 3 car trains= 10m (iii) Free  length  at  outer  ends  of  the  rake  (  for  cross  pathway,  Signal  and 

    Friction buffers)= 10m each side 

    (iv) Total  length  of  Stabling  line  =  (iii)+(i)+(ii)+(i)+(ii)+(i)+(iii)=  10+ 65+10+65+10+65+10= 235 m (say 240m)  

    Looking  to  the  car  width  of  2900  on  Standard  Gauge,  5m  Track  Centre  is 

    proposed  for  all  the  stabling  lines.  Thus,  space  between  stabling  shall  be 

    sufficient  to  include a pathway  to be  constructed between  tracks  to provide 

    access for internal train cleaning and undercarriage inspection.  

    50% of stabling lines shall be covered with a roof in order to facilitate testing of 

    air  conditioning of  trains and  their pre‐cooling under  controlled  condition of 

    temperature. 

    II)  Inspection Lines in Depot For the design of the Inspection Bay Lines in the depot, following approximate 

    lengths  have  been  taken  in 

    consideration: 

    (i) Length of one 3‐car rake= 65 m (approx) 

    (ii) Gap between two 3 car trains= 10m 

    (iii) Cross path at each end = 10 m  (iv) Total length of Inspection line 

    = (iii)+(i)+(ii)+(i)+(iii)= 10+ 

    65+10+65+10 = 160m 

    The inspection bay in Ganeshpur Depot shall be of 160 X 23.5m² size with three 

    inspection  lines having sunken  floor. The  track spacing between  the adjacent 

    inspection Bay Lines shall be 6.25 m. 

    There  would  be  lighting  below  the  rail  level  to  facilitate  the  under  frame 

  • Detailed Project Report for Rail Based Mass Transit System in Varanasi 

    Final Report                                                CHAPTER 10: MAINTENANCE DEPOT 

                                                                                            February, 2016                                                                        Page 10‐10 

    inspection. Ramps of 1:8 slopes, 3 meter wide should be provided with sunken 

    floor  system  for  movement  of  material  for  the  cars.  Further,  3.5  m  cross 

    pathways are left at each end for movement of material by fork lifter/ Leister/ 

    Hand  trolley.  Stinger  system  shall  be  provided  for  750V  DC  traction  power 

    supply to the rolling stock. 415V 3 phase 50 Hz, 230V 1 phase 50 Hz AC supply 

    and  Pneumatic  supply  shall  also  be made  available  on  each  inspection  shed 

    columns. Air‐circulators shall be provided on each column.  

    Roof  and walls  shall  be  of  such  design  that  optimum  natural  air  ventilation 

    occurs all the time and sufficient natural light is also available. Each Inspection 

    bay will also have arrangement close by for cleaning of HVAC filter under high 

    pressure water jet. 

    III)  Workshop in depot The  size  of  the  workshop  shed  in 

    Depot shall be 160 x 44.5 m² each and 

    an  additional  covered  space  of  160  x 

    7.5 m² shall be provided in the depots 

    to  cater  for  offices  cum maintenance 

    sections,  costly  item  store,  locker 

    room,  toilet etc. Following equipment 

    repair/overhaul  facilities  are  planned 

    in the workshop. 

    Body furnishing.    Bogie.      Wheels.      Traction Motor  Axle box and axle bearing    Pentograph.      Electrical  equipment  like  transformer,  converter/inverter,  circuit 

    breaker, relays.   

    Battery.        Air compressor.            Air conditioning equipments.           Brake equipment.          Door actuators.           

  • Detailed Project Report for Rail Based Mass Transit System in Varanasi 

    Final Report                                                CHAPTER 10: MAINTENANCE DEPOT 

                                                                                            February, 2016                                                                        Page 10‐11 

    Control and measuring equipments.      Pneumatic equipments  Dampers and Springs  Couplers/ Gangways   

    Cross track equipped with bogie turntables have been provided for movement 

    between bays.   

    IV) Pit Wheel Lathe  A  separate  building  is  planned  for 

    housing  pit  wheel  lathe  (PWL)  for  

    Ganeshpur  Depot  which  is 

    approachable  from  workshop,  ins 

    pection bay and stabling  lines through 

    rail and road for placement of cars for 

    re‐ profiling of wheels within the depot 

    along with space for depot of scrap. 

     

    V) Engineering Train Unit Workshop Since  the  workshop  cum  depot  is 

    designed optimally, it would not be wise 

    to waste  its capacity  in maintaining the 

    other  than  passenger  Rolling  Stock 

    vehicles. Carrying  these  vehicles  to  the 

    inspection shed affects the Rolling Stock 

    maintenance  as  shunting  is  also 

    involved.  Therefore,  other  vehicles  like 

    rail  cum  road  vehicle,  tower  wagons, 

    etc. may be housed and given required inspection attention in a separate shed 

    called  ETU workshop,  for which  2  lines  have  been  provided  in  the  depots. 

    However  for  the  heavy  lifting  needs,  these  vehicles may  be  taken  to main 

    workshop for required attention. 

    VI) Car Delivery Area The newly procured  coaches, which are  transported by  road,  shall  reach  the 

    Depot‐cum Workshop by the road on trailers. To unload the coaches and bring 

    them to the track, provision of space, along the side of shunting neck, has to be 

  • Detailed Project Report for Rail Based Mass Transit System in Varanasi 

    Final Report                                                CHAPTER 10: MAINTENANCE DEPOT 

                                                                                            February, 2016                                                                        Page 10‐12 

    made for unloading of cars and other heavy materials. There should be enough 

    space  available  for  movement  of  heavy  cranes  for  lifting  of  coaches.  The 

    unloading area should be easily accessible for heavy duty hydraulic trailers. 

    VII)  Automatic Coach Washing Plant (AWP)  Provision to be made for Rolling Stock exterior surfaces to be washed using a 

    fully  automated  Train  Washing  System  with  a  throughput  capacity  of 

    approximately  six  trains  per  hour.  The  AWP  shall  be  situated  at  such  a 

    convenient point on the incoming route so that incoming trains can be washed 

    before  entry  to  the  depot  and  undesirable movement/shunting  over  ingress 

    and egress routes within the depot is avoided.  

    VIII) Test Track A test track of 630 mts. length will be provided beside workshop in Ganeshpur 

    Depot.  It  shall be equipped with  signaling equipments  (ATP/ATO).  It  shall be 

    used  for  the  commissioning of  the new  trains,  their  trials  and  testing of  the 

    trains after the IOH and POH. In compliance to safety norms, the boundary of 

    the  track  shall  be  completely  fenced  to  prevent  unauthorized  trespassing 

    across or along the track. 

    IX) Internal Cleaning Shed Monthly  heavy  cleaning  of  interior walls,  floors,  seats, windows  glasses  etc, 

    outside heavy cleaning, Front/rear Face, Vestibule/ Buffer area, outside walls 

    and  roof  shall  be  done manually  in  the  interior  cleaning  plant  designed  for 

    cleaning  of  one  at  a  time.  A  line  adjacent  to  inspection  shed  should  be  so 

    provided that placement of rakes is possible from workshop or inspection lines 

    & vice – versa conveniently and with ease. 

    X) Train Operators Booking Office Suitable office  facility adjacent  to  the  stabling  lines at each depot  should be 

    provided  so  that  train  operators  reporting  ‘On’  duty  or  going  ‘Off’  duty  can 

    obtain  updates  regarding  ‘Special  Notices’,  ‘Safety  Circulars’  and  other 

    technical updates/information in vogue. These offices should have an attached 

    cycle/scooter/car stand facility for convenience of the train operating staff. 

    XI) Administrative Building An  administrative  building  close  to  the main  entrance  is  planned.  It  can  be 

    suitably sized and architecturally designed at the detailed design stage. A time 

    and security office is also provided close to main entrance. It shall be equipped 

  • Detailed Project Report for Rail Based Mass Transit System in Varanasi 

    Final Report                                                CHAPTER 10: MAINTENANCE DEPOT 

                                                                                            February, 2016                                                                        Page 10‐13 

    with suitable Access control system for all the staff working in the complex. 

    XII) Operation Control Centre and Depot Control Centre Control  of  train  operation  will  be  done  centrally  from  Operations  Control 

    Center  (OCC),  which  will  house  Traffic  Control  Centre,  SCADA  System  for 

    Traction Power Control & Monitoring, SCADA System for Auxiliary Power, VAC 

    Control  & Monitoring,  Telecommunication,  CCTV  Control  & Monitoring  etc. 

    Movement of trains inside depot shall be controlled from Depot Control Centre 

    (DCC) located inside the depot. 

    XIII) Parking Facilities a)  Ample  parking  space  shall  be  provided  for  the  two  wheelers  and  four 

    wheelers at the   following points. 

    i)   Close to the depot entry. 

    ii)  Close to the stabling lines. 

    iii) Close to the Workshop/ IBL. 

    b) Space for parking of road and re‐railing equipments 

    Enough  space  for parking of  road  vehicle/  trailers/  trucks etc.  Enough  space 

    will also have  to be earmarked adjacent  to workshops. Similarly, provision of 

    space  for parking of  re‐railing equipments will have  to be made close  to  the 

    main exit gate of the Depot. 

    XIV) Watch Towers There shall be provision of adequate number of watch towers for the vigilance 

    of depot boundary. 

    XV) Power Supply An auxiliary substation of 2500 KVA capacity has been planned for catering to 

    the power supply requirement of the depot. Details of connected load, feeder 

    may be worked out during detailed designing stage. 

    XVI)   Standby Power Supply The  standby  power  supply  is  proposed  through  silent DG  set  of  2X320  KVA 

    adequate capacity to supply all essential loads without over loading.  

    XVII) Compressed Air Supply Silent  type  compressor  units  shall  be  suitably  installed  inside  the  depots  at 

    convenient  location  for  the  supply  of  compressed  air  to  workshop  and 

    Inspection sheds. Thus, the pneumatic pipeline shall run within the workshop 

  • Detailed Project Report for Rail Based Mass Transit System in Varanasi 

    Final Report                                                CHAPTER 10: MAINTENANCE DEPOT 

                                                                                            February, 2016                                                                        Page 10‐14 

    and  inspection  bays  as  to  have  compressed  air  supply  line  at  all  convenient 

    points. 

    XVIII)  Water Supply, Sewerage and Drainage Works In  house  facilities  shall  be  developed  for  the  water  supply  of  each  depot. 

    Sewerage,  storm water drainage  shall be given due  care while designing  the 

    depots for efficient system functioning. Past records of Municipal Corporation 

    shall be used  to design  the drainage  system. Rainwater harvesting would be 

    given due emphases to charge the underground reserves. 

    10.8 PLANT AND MACHINERY Plant  and machinery  proposed  for  the maintenance  facilities  at  Ganeshpur 

    depot have been listed in Annexure 10.4 

     

     

  • Detailed Project Report for Rail Based Mass Transit System in Varanasi 

    Final Report                                                CHAPTER 10: MAINTENANCE DEPOT 

                                                                                            February, 2016                                                                        Page 10‐15 

    Annexure 10.1 

    LAYOUT PLAN FOR GANESHPUR DEPOT‐ OPTION 1 

     

  • Detailed Project Report for Rail Based Mass Transit System in Varanasi 

    Final Report                                                CHAPTER 10: MAINTENANCE DEPOT 

                                                                                            February, 2016                                                                        Page 10‐16 

    Annexure 10.2 

    LAYOUT PLAN FOR GANESHPUR DEPOT‐ OPTION 2 

     

     

  • Detailed Project Report for Rail Based Mass Transit System in Varanasi 

    Final Report                                                CHAPTER 10: MAINTENANCE DEPOT 

                                                                                            February, 2016                                                                        Page 10‐17 

    Annexure 10.3(a) 

    LAYOUT PLAN FOR GANESHPUR DEPOT‐ OPTION 3

  • Detailed Project Report for Rail Based Mass Transit System in Varanasi 

    Final Report                                                CHAPTER 10: MAINTENANCE DEPOT 

                                                                                            February, 2016                                                                        Page 10‐18 

    Annexure 10.3(b) 

    LAYOUT PLAN FOR GANESHPUR DEPOT‐ OPTION 3 (Upper Level‐Elevated) 

     

     

  • Detailed Project Report for Rail Based Mass Transit System in Varanasi 

    Final Report                                                CHAPTER 10: MAINTENANCE DEPOT 

                                                                                            February, 2016                                                                        Page 10‐19 

    Annexure 10.3(c) 

    LAYOUT PLAN FOR GANESHPUR DEPOT –OPTION 3 (Lower Level‐ Ground)

  • Detailed Project Report for Rail Based Mass Transit System in Varanasi 

    Final Report                                                CHAPTER 10: MAINTENANCE DEPOT 

                                                                                            February, 2016                                                                        Page 10‐20 

    Annexure 10.4 

    LIST OF MAJOR PLANT AND MACHINERY FOR BHEL DEPOT 

    Sno.  PLANT & MACHINERY  Quantity 

    A.  MATERIAL HANDLING   

      Travelling over head EOT cranes for workshop 15/2T  2 

      Travelling over head EOT cranes for workshop 3.2T (Future)  2 

      Travelling over head EOT cranes for inspection bay 1.5T  2 

      Travelling over head EOT cranes for ETU shed 5T  1 

      Jib crane for workshop 3 T  2 

      Synchronized pit jacks system for car lifting  2 

      Car body stands for keeping 6 car shells  36 

      Dummy bogies  6 

      Mobile lifting jacks‐15T (Nos)  12 

      Mobile lifting jacks 10T (Nos) (Future)  24 

      Battery powered locomotive  1 

      Road mobile Crane 5T cap  1 

      Fork lift truck 3T cap  2 

      Fork lift trucks 2T cap  2 

      Pallet  trucks  4 

      TATA Truck  1 

      Scissors type lifting trolley  ‐ 2T capacity  2 

      Hydraulic trolleys ‐ 2T capacity  2 

    B.  Wheel shop   

      500T wheel press  1 

      Vertical boring m/c (Turret Lathe)  1 

      Multipurpose Wheel  Lathe  1 

      Axle turning lathe  1 

      Axle UST inspection machine  2 

      Radial drill m/c  1 

      Induction Heater  2 

      Bearing/Coupling Extractor  4 

  • Detailed Project Report for Rail Based Mass Transit System in Varanasi 

    Final Report                                                CHAPTER 10: MAINTENANCE DEPOT 

                                                                                            February, 2016                                                                        Page 10‐21 

    Sno.  PLANT & MACHINERY  Quantity 

    C.  Bogie shop   

      Bosch Tank : Bogie wash/cleaning plant  1 

      Bogie static load testing m/c  1 

      Shock absorber testing m/c  1 

      Spring scragging &testing m/c  1 

      Magnaflex crack detector  1 

      Glowcheck crack detector  1 

    D.  Rotating m/cs   

      Baking Oven  1 

      Dynamic balancing  1 

      Traction  motor test console  1 

      Motor compressor test bench  1 

      Tan Delta testing instrument  1 

    E.  Other m/cs   

      Re‐railing equipment  1 

      Mobile Wheel Turning Lathe  1 

      Chip crusher and conveyor for pit wheel lathe  1 

      Automatic Washing plant for Metro cars.  1 

      High‐pressure washing pump for front and rear end cleaning  1 

      Turn table for one car  1 

      Turntable for bogies  4 

      Driving Cab Simulator  1 

      Water de‐mineralizing plant (Distillation plant)  2 

      Painting booth for separate parts  1 

      Floor cleaning machine  4 

      Welding equipments  5 

      Compressor 500Cfm  2 

      DG set  320 KVA  3 

      Battery charger  2 

    F.  Machine shop   

      Guillotine  Shearing  m/c  1 

  • Detailed Project Report for Rail Based Mass Transit System in Varanasi 

    Final Report                                                CHAPTER 10: MAINTENANCE DEPOT 

                                                                                            February, 2016                                                                        Page 10‐22 

    Sno.  PLANT & MACHINERY  Quantity 

      Shearing, punching & cropping  1 

      Universal tool cutter & grinder  1 

      Vertical surface grinder  1 

      Centre lathe 2m bed  1 

      Centre lathe 1m bed  1 

      Radial drill m/c  1 

    G.  Test Benches/Instruments   

      Pneumatic test bench  1 

      Brake test bench  2 

      SPM test bench  2 

      Door test bench  2 

      Inverter test bench  1 

      Other test benches (MCB, RMPU etc.)  1 

      Oscilloscope  1 

    H.  Furniture/material storage/Small tools   

      Vertical storage system for DCOS store  1 

      Computer MMIS with LAN connectivity  1 

      Storage racks  LS 

      Industrial furniture  LS 

      Electric and pneumatic tools  LS 

      Measuring and testing equipments  LS 

      Tool kits  LS 

      Mobile safety steps  10