Upload
vodieu
View
221
Download
1
Embed Size (px)
Citation preview
Existing
Past actions
Other present actions
Reasonably foreseeable future action
Proposed action
Mitigation action
y1
y2
y3
y4
y5
y6
x1
©2008 O
wen L
. S
chm
idt
Existing
Past actions
Other present actions
Reasonably foreseeable future action
Proposed action
Mitigation action
y1
y2
y3
y4
y5
y6
x1
}40 CFR 1502.16(a) & (b); 1508.8
40 CFR 1508.7; 1508.25(c)(3)
40 CFR 1508.25(b)(3); 1502.16(h);
1505.2(c)
40 CFR 1508.23; 1508.25(a)(2) &(3)
40 CFR 1508.27(b)(10); 1502.16(c);
1506.2(d)
©2008 O
wen L
. S
chm
idt
1. Would you want to know about the action itself? 2. Would you want to know what Mother Nature has in store? 3. Would you want to know where the pipelines are? 4. Would you want to know what else is happening today? 5. Would you want to know what is planned for the future? 6. Would you want to know ahead of time about clean-up? Red bar: Would you want to know about sidebars?
1
You already were going to do this .....
2
The vocabulary of NEPA:
Relevance
Delano v. Roche, 391 F.Supp.2d 79, 89 (D.D.C. 2005) (not a NEPA case) (relevant evidence is defined in the Federal Rules of Evidence as “evidence having any tendency to make the existence of any fact that is of consequence to the determination of the action more probable or less probable than it would be without the evidence”)
©2008 O
wen L
. S
chm
idt
The vocabulary of NEPA:
Reasons
Not to prepare a CatEx, EA, or EIS
Not to prepare an EIS
Not to include an alleged alternative
Not to include an alleged connected action
Not to include an alleged consequence
©2007 O
wen L
. S
chm
idt
3
The giving of reasons is the rational connection between the facts found to the choice made. “The relevant inquiry is whether the agency considered the relevant factors and articulated a rational connection between the facts found and the choice made.” Pyramid Lake Paiute Tribe v. U.S. Dept. of Navy, 898 F.2d 1410, 1414 (9th Cir. 1990)
4
The vocabulary of NEPA:
Significance
x1 y6What How much Reasons
Ultimate conclusion
Basic conclusions
Evidence
Legal result
Legal
Context Intensity
©2008 O
wen L
. S
chm
idt
The vocabulary of NEPA:
Addition includes subtraction
1 + 2 = 3
12 + (-9) = 3
9 + (-12) = -3
©2008 O
wen L
. S
chm
idt
5
Multiplication is rapid addition. Division is rapid subtraction. Subtraction is addition of a negative number. And addition is addition. It’s all addition.
6
The vocabulary of NEPA:
Proximate cause, cause-in-fact, chain of causation
Cause-and-effect
Chain of
causation
Intervening cause• Dependent
• Independent
A reasonably close causal relationship
NOT coincidence, acausal relationship (synchronicity), magic ......
Direct
Indirect
3©
2008 O
wen L
. S
chm
idt
The vocabulary of NEPA:
Idea
Proposal
Recommendation or report
Decision
Action
Monitoring
Idea
Proposal for action
Decision
Action
Monitoring
Recommendation or report on proposal for
action
©2008 O
wen L
. S
chm
idt
CASE LIST: A close causal relationshipCause-and-effect is the only relationship known to science, practically overlooked in the vocabulary of NEPA, except in the Supreme Court and a few very recent decisions. Is there any other method for predicting the future, other than the method of applying cause-and-effect?
7
The vocabulary of decisionmaking, derived from the text of NEPA itself. The NEPA process is triggered by a proposal for action, and must be concluded in time to be included in any recommendation or report on such a proposal. Once the decision is made and action is taken, monitoring may indicate a need for further action, in which case a new proposal may be made.
8
The vocabulary of NEPA:
Impact
im!pact noun [ím pàkt ] (plural im!pacts)
1. action of hitting: the action of one object hitting another2. force of collision: the force with which one object hits another3. effect: the strong effect that something or somebody has
transitive and intransitive verb [im pákt ] (past im!pact!ed, past participle im!pact!ed, present participle im!pact!ing, 3rd person present singular im!pacts) 1. strike something: to strike something with force2. have an effect on something: to have an immediate and strong effect on something or somebody3. press together forcefully: to press together with great force
Word Key: Usage NoteImpact, noun and verb: The noun impact, in its figurative meaning, should normally convey some sense of powerful or dramatic consequence, and should not just be an alternative word for effect or impression. To use it in a context like he had an impact on everyone in the room - except in highly unusual circumstances - is to devalue the word. Many careful users of the language strongly dislike the verb impact in any figurative sense whatsoever, regardless of whether the verb is followed by on: both, for example, this impacts the company favorably and this impacts on the company are courting contempt. The verb is undeniably common in business communication, but anyone who hopes to achieve an effect that is even faintly literary should avoid it in favor of affect, change, or the like. Use of the verb is uncontroversial only in physical senses: The car impacted the railing.
Encarta® World English Dictionary [North American Edition] © & (P) 2001 Microsoft Corporation. All rights reserved. Developed for Microsoft by Bloomsbury Publishing Plc.
©2008 O
wen L
. S
chm
idt
The vocabulary of NEPA:
Direct, indirect, and cumulative
Can you describe an “impact” that occurs in a natural system that is anything other than the direct consequence of an immediately preceding event or events? In other words, aren’t all “impacts” in a natural system “direct” impacts, though they may exist in a chain of impacts?
Can you describe an “impact” that occurs in a natural system that is anything other than the addition (where “addition” includes “subtraction”) to something that has occurred, is occurring, or will occur? In other words, could there be an “impact” at all unless there were an addition to something that has occurred, is occurring, or will occur?
Go to your library. Dig through your inventory of EAs and EISs. Put your finger on each and every "impact" you find. Ask first whether this impact is the direct consequence of something else in the EA or EIS (such as the proposed action, an alternative action, a mitigation measure, something in the existing environment, a connected action, a consequence of one these, etc.). Is it a direct impact? Ask second whether this impact adds to or subtracts from something that has happened, is happening, or foreseeably will happen in the future. Is it a cumulative impact? You will answer yes to each question each time!
Delete the word when you encounter it, and see if it makes any difference to the meaning of the sentence or the paragraph. You may well discover that the word is extraneous, and that the phrase “cumulative impact” has no meaning other than the single word “impact.”
The word “cumulative” is an adjective. To prove that this is a valid construction, we would have to find an impact that is not also a “cumulative impact,” just as we would have to find a warbler that is not also a “yellow warbler.” As already shown, every impact is a cumulative impact by its very nature. Every impact is the addition of something to something that has happened, is happening, or foreseeably will happen. So this proof cannot be made. We can find warblers that are not yellow, but we cannot find impacts that are not the addition of something to something that has happened, is happening, or foreseeably will happen.
4-7©2008 O
wen L
. S
chm
idt
The word “impact” may be a noun or a verb. The phrase “impact statement” or “impact assessment” is ambiguous.
9
ESSAY: No such thing as a cumulative impact as a third, distinct type of impact.
10
40 CFR 1508.25 Scope. Scope consists of the range of actions, alternatives, and impacts to be considered in an environmental impact
statement. The scope of an individual statement may depend on its relationships to other statements (Section 1502.20 and Section 1508.28). To determine the scope of environmental impact statements, agencies shall consider 3 types of actions, 3 types of alternatives, and 3 types of impacts. They include:
(a) Actions (other than unconnected single actions) which may be: (1) Connected actions, which means that they are closely related and therefore should be discussed in the
same impact statement. Actions are connected if they: (i) Automatically trigger other actions which may require environmental impact statements. (ii) Cannot or will not proceed unless other actions are taken previously or simultaneously. (iii) Are interdependent parts of a larger action and depend on the larger action for their justification.
(2) Cumulative actions, which when viewed with other proposed actions have cumulatively significant impacts and should therefore be discussed in the same impact statement.
(3) Similar actions, which when viewed with other reasonably foreseeable or proposed agency actions, have similarities that provide a basis for evaluating their environmental consequences together, such as common timing or geography. An agency may wish to analyze these actions in the same impact statement. It should do so when the best way to assess adequately the combined impacts of similar actions or reasonable alternatives to such actions is to treat them in a single impact statement.
(b) Alternatives, which include:(1) No action alternative. (2) Other reasonable courses of actions. (3) Mitigation measures (not in the proposed action).
(c) Impacts, which may be: (1) Direct; (2) indirect; (3) cumulative.
©2008 O
wen L
. S
chm
idt
The vocabulary of NEPA:
“Cumulative” is an adjective
Yellow
Warbler Impact
Cumulative
©2008 O
wen L
. S
chm
idt
There is no connector between (2) and (3). There is no requirement anywhere that impacts be properly labeled, or labeled at all.
11
The “cums.” NOT. If “cumulative” means to increase by successive additions (where addition includes subtraction), then all impacts are “cumulative.” If there is no addition (or subtraction), there simply is no impact. All impacts are thus cumulative. We see warblers that are not yellow. Can we find an impact that is not “cumulative”?
12
The vocabulary of NEPA:
Aggregative, Interactive, Diachronic, Phase transitional• Aggregative — Addition or subtraction. A proposal for action may add to or subtract from the
existing environment. By CEQ’s definition, such a proposed action is a cumulative action. In fact,
isn’t every action that is proposed, proposed for the very purpose of adding to or subtracting from
the existing environment?
• Interactive — Synergism. Everything is connected to everything else in natural systems.
Everything interacts with everything else, at some level through some number of connectors. By
definition, then, every action and every consequence is “cumulative” in the synergistic sense. It is
the central purpose of our analysis, though, to figure out how one event (such as a proposed action)
interacts with another event (such as an element of the existing environment).
• Diachronic — Change over time. Almost nothing in natural systems is static over time. Almost
everything in the environment is constantly changing. The “existing environment” changes over time,
and thus “doing nothing” (the no-action alternative) has its own consequences. Doing something (the
proposal or other action alternative) has its consequences, which may in turn be dynamic over time.
This is the “time” component of our analysis — perhaps the most-overlooked of all consequences.
“The only constant is change.”
• Phase transition emergent phenomenon — Change not predicted by prior action. Take water at
33 degrees and cool it one degree. It is just cooler water. Cool it still more to remove latent heat
and it changes to ice — a phase transition not predicted by the cooling events that preceded it.
Take water at 211 degrees and heat it one degree. It is warmer water. Add enough heat and it boils
— a phase transition not predicted by the heating events that preceded it. “The straw that broke
the camel’s back.”
7©
2008 O
wen L
. S
chm
idt
40 CFR 1508.7 Cumulative impact. ‘‘Cumulative impact’’ is the impact on the environment which results from the incremental impact of the action when added to other past, present, and reasonably foreseeable future actions regardless of what agency (Federal or non-Federal) or person undertakes such other actions. Cumulative impacts can result from individually minor but collectively significant actions taking place over a period of time.
40 CFR 1508.8 Effects. ‘‘Effects’’ include:
(a) Direct effects, which are caused by the action and occur at the same time and place.
(b) Indirect effects, which are caused by the action and are later in time or farther removed in distance, but are still reasonably foreseeable. Indirect effects may include growth inducing effects and other effects related to induced changes in the pattern of land use, population density or growth rate, and related effects on air and water and other natural systems, including ecosystems.
Effects and impacts as used in these regulations are synonymous. Effects includes ecological (such as the effects on natural resources and on the components, structures, and functioning of affected ecosystems), aesthetic, historic, cultural, economic, social, or health, whether direct, indirect, or cumulative. Effects may also include those resulting from actions which may have both beneficial and detrimental effects, even if on balance the agency believes that the effect will be beneficial.
©2008 O
wen L
. S
chm
idt
Science-based impact assessment.
13
14
Existing
Past actions
Other present actions
Reasonably foreseeable action
Proposed action
Mitigation action
The x-axis is the “what” — What is the consequence of concern? Land, air, water ….
x
y
Make a new column for each
consequence of concern.
The y-axis is the “how much” — How big is that consequence?
The y-value can be qualitative or quantitative.
Every!ing !at can be c"nted do# not nec#sa$ly c"nt; every!ing !at c"nts cannot nec#sa$ly be c"nted.
Albe% Ein&ein
©2008 O
wen L
. S
chm
idt
It is safe to omit x from detailed analysis; give reasons why further
investigation is not warranted
Show all 6 y-values (or use alternative method) for x, and compare to level of concern (and/or other alternatives)
Is it an “x”?
It is safe to omit x
Internal scoping
External scoping
No
Start
No
Yes
Yes
ZeroAgency must investigate whether the y1 value is zero or not zero.
Not Zero
Scoping“for an early identification of what are and what are not the real issues,” 40 CFR 1500.5(d); “for
determining the scope of issues to be addressed and for identifying the significant issues related to a
proposed action,” 40 CFR 1501.7
Agency must analyze sum total aggregate cumulative value of x
No
Yes
Is there a level of concern?
Is x a “significant” issue? Is there another reason to omit x?
Is it a consequence of concern?
Jump to administrative
estoppelJump to next
frame
8
©2008 O
wen L
. S
chm
idt
The model for a “perfect cumulative impacts analysis” is based on a typical column graph, where the horizontal x-axis represents “what” the impact of concern is, and the vertical y-axis represents “how big” the impact is. The “intensity” of impact “x” will be known in proper context when all 6 y-values are finally added up.
15
There are 3 possible outcomes: (1) The issue never comes up, so it is safe to omit it. (2) The issue comes up, but for reasons stated the issue is omitted. (3) The issue is included.
16
Reasons why it is safe to omit x from detailed analysis
• RELEVANCE — the agency has determined in the scoping process that x is “not relevant” to the decision to be made
• x has a value (y1) of zero
• tiering
• the agency can do nothing about x
• SIGNIFICANCE — the agency has determined in the scoping process that x is “not significant”
910
©2008 O
wen L
. S
chm
idt
x1
y1 Proposed action
Start with one of the consequences of concern. How big
is it?The value y1 is the size of
the consequence of concern.
The value at y1 is not a consequence of x1; it is the measure of the size of x1
©2008 O
wen L
. S
chm
idt
If the y1 value of x1 is zero, it has no bearing on the outcome and would not be relevant. If the agency is tiering the x-issue, it would not be relevant to the decision to be made. If the agency can do nothing about x, it is not the legally relevant cause.
17
x1 is one of the consequences of concern, and y1 is the size of x1. y1 is not a consequence of x; it is the size of x1.
18
y1
Existing/Natural“Mother Nature”y2
Proposed action
If this thing adds to something that is already present in the naturally-occurring environment,
add it.
y2 = y1 when there is nothing in the
backgroundor baseline
The value y2 is the incremental
impact of the proposed action added
to what is already naturally present.
x1
©2008 O
wen L
. S
chm
idt
x
y1
Existingy2
Past actions
Proposed action
y3
The value y3 is the incremental
impact of the proposed action added to
the impacts of past actions and what
was naturally occurring.
Lands Council v. Powell, 395 F.3d 1019, 1028 (9th Cir. 2005): For the public and agency personnel to adequately evaluate the cumulative effects of past timber harvests, the Final Environmental Impact Statement should have provided adequate data of the time, type, place, and scale of past timber harvests and should have explained in sufficient detail how different project plans and harvest methods affected the environment.
Add the consequences of past actions.
y3 = y1 when the
consequences of the proposed
action do not add to anything
11
©2008 O
wen L
. S
chm
idt
13
The next y-value, y2, is the increment that the proposed action adds to what naturally occurs in the existing environment. Synonyms are used to emphasize that this is not the increment added to human-caused impacts: “Mother Nature,” background, baseline, naturally-occurring, and existing environment.
19
CASE LIST: Cataloguing cases, time - type - place - scaleCEQ guidance memo on past actionsThe value at y3 is the increment added to the effects of past actions, which implicates the Lands Council case and CEQ’s guidance memo on cumulative impacts: CEQ, June 24, 2005, Guidance on the Consideration of Past Actions in Cumulative Effects Analysis, <http://ceq.eh.doe.gov/nepa/regs/guidance.html>, as of November 2005
20
y1
Existingy2
Past actions
Other present actions
y3Consult the “reasons to lump/reasons to split” table for the kinds of actions that must be included as “other present actions.” Add those that must be added, leave those out you may leave out — if that is your choice.
Proposed action
y4
The value y4 is the incremental
impact of the proposed action added
to the impacts of past actions, other
present actions, and what was naturally
occurring.
y4 - y1 is
the “existing
environment” —
it
consists of what has
happened plus what is
happening
Add the consequences of other present actions.
y4 = y1 when the
consequences of the proposed
action do not add to anything
x1
©2008 O
wen L
. S
chm
idt
Jump to next frame
©2008 O
wen L
. S
chm
idt
CASE LISTS: Actions casesThe value y4 is the incremental impact added to other present actions. Which “other present actions” are relevant is to be determined by ordinary principles of scoping after consulting a list of all the known reasons to consider other actions as well as to not to. The values y2, y3, and y4 — added together — constitutes what is usually depicted as the “existing environment” or the “affected environment.”
21
CASE LIST: “Actions” module from NEPA models and case lists, Owen L. Schmidt.
22
y1
Existingy2
Past actions
Other present actions
y3
Reasonably foreseeable action
y4
Proposed action
y5
Add the consequences of reasonably foreseeable future
actions.
y5 = y1 when the
consequences of the proposed
action do not add to anything
The value y5 is the incremental
impact of the proposed action added
to the impacts of past actions, other
present actions, reasonably foreseeable
future actions, and what was naturally
occurring.
A reasonably foreseeable future action is one that has been proposed. It could be a similar action, a connected action, or a cumulative action.
y5 - y1 is
the “no-action
alternative” —
it consists
of everything that happens
without the proposed
action happening
x1
15
©2008 O
wen L
. S
chm
idt
y1
Existingy2
Past actions
Other present actions
y3
y4
y5
Mitigation actiony6
The value y6 is the incremental
impact of the proposed action if
mitigation were adopted at the time of
the decision.
Add (subtract) the consequences of mitigation that is not already included in
the proposed action.
Mitigation that is included in the proposed action is already accounted for in y1
Reasonably foreseeable action
Proposed action
x1
16
“Duty to investigate the possibility of mitigation.”
©2008 O
wen L
. S
chm
idt
17
The value y5 brings in reasonably foreseeable future actions. y2, y3, y4, plus y5 constitute what we usually designate the “no-action alternative.” It is the future without the proposed action (y1).
23
CASE LIST: Mitigation as an alternativey6 adds or subtracts mitigation. If the value at y5 is not acceptable for any reason, then the sum total aggregate cumulative y-value can be changed by adding or subtracting at y6.
24
Existing
Past actions
Other present actions
Reasonably foreseeable action
Proposed action
Mitigation action
If there is a level of concern, state what that is and how the values in the y-
axis compare: ConsistencyCompliance
CompatibilityConformity
y6 ! Lc when the value of the y-axis exceeds or falls short of
the level of concern
y1
y2
y3
y4
y5
y6
x1
©2008 O
wen L
. S
chm
idt
x3
y1
Existingy2
Past actions
Other present actions
y3
Reasonably foreseeable action
y4
Proposed action
y5
Mitigation actiony6
Consequence1
Existing
Past actions
Other present actions
Reasonably foreseeable action
Proposed action
Mitigation action
Consequence2
Existing
Past actions
Other present actions
Reasonably foreseeable action
Proposed action
Mitigation action
Consequence3
1. For each consequence of concern …
The perfect cumulative impacts analysis
2. Disclose all 6 y-values …
3. Disclose the level of concern, if any, and compare to y6.
x1 x2
©2008 O
wen L
. S
chm
idt
The last step in the analysis compares the value at the top of y6 to whatever “level of concern” (Lc) there may be for x, the “consequence of concern.” This step may be iterative with the step at y6. If for any reason the value at y6 is not acceptable, it can be changed by making alterations to y1 or to y6.
25
The “perfect” cumulative impacts analysis: (1) for each consequence of concern the agency would (2) disclose all 6 y-values and then (3) disclose the comparison between y6 and the level of concern, if one exists.
26
y1
Existingy2
Past actions
Other present actions
y3
Reasonably foreseeable action
y4
Proposed action
y5
Mitigation actiony6
x1
Discussion point: is anything left out?
Nothing is left out. Or, what is left out?
©2008 O
wen L
. S
chm
idt
Existing
Past actions
Other present actions
Reasonably foreseeable action
Proposed action
Mitigation action
y1
y2
y3
y4
y5
y6
x1
7• Aggregative — Addition or
subtraction • Interactive — Synergism • Diachronic — Change over
time • Phase transition emergent
phenomenon — Change not predicted by prior change
Discussion point: it might not be simple addition …
.... and addition includes subtraction
©2008 O
wen L
. S
chm
idt
Disclosing all 6 y-values will capture all reasonably foreseeable consequences of action x. Or, to put it the other way around, what is left out?
27
28
Method 1 Method 2 Method 3 Method 4 Method 5
Existing
Past actions
Other present actions
Reasonably foreseeable action
Proposed action
Mitigation action
y1
y2
y3
y4
y5
y6
Lump the components of the “affected environment”
Reasonably foreseeable action
Proposed action
Mitigation action
Lump the impacts of all actions that
may be “cumulative”
(except mitigation — which must be
kept separate)
Proposed action
Mitigation action
Existing
Lump the impacts of past,
other present, and reasonably
foreseeable future actions
Proposed action
Mitigation action
Individual action
Individual action
Individual action
Individual action
Individual action
Individual action
Individual action
Individual action
Individual action
Discussion point: choice of method for assessing cumulative impacts
©2008 O
wen L
. S
chm
idt
18
CASE LIST: Choice of methodsMethod 4 is the one that has been modeled. Method 5, which splits each category of action into its component parts, is the default method derived from case law such as Lands Council v. Powell. Method 2 is the method preferred by some agencies. Agencies choosing any method (perhaps other than Method 5) will have to disclose the reasons for their choice of method. 40 CFR 1502.24 (“identify any methodologies used”).
29
30
Discussion point: CEQ’s June 24, 2005, guidance memorandum
http://www.nepa.gov/nepa/regs/guidance.html
33
34
Details about individual past and
other present actions may safely
be omitted
Details about individual past and
other present actions must be
provided
Can the agency conduct an adequate cumulative effects
analysis by observing the current aggregate effects of past actions without delving into the historical details of individual past actions?
Would detailed information on past actions be useful when predicting the effects of a proposed action?
SCOPING: Can the agency determine in the scoping process and/or subsequent analysis that the “affected environment” is adequately described without details of individual past and other present actions?
With respect to past actions, during the scoping process
and subsequent preparation of the analysis, the agency
must determine what information regarding past actions
is useful and relevant to the required analysis of
cumulative effects. Cataloging past actions and specific
information about the direct and indirect effects of their
design and implementation could in some contexts be
useful to predict the cumulative effects of the proposal.
The CEQ regulations, however, do not require agencies
to catalogue or exhaustively list and analyze all
individual past actions.
Yes
Step 1
Yes
No
No
… review of past actions is
required to the extent that this
review informs agency
decisionmaking regarding the
proposed action.
YesNo
Agencies are not required to list or analyze the
effects of individual past actions unless such
information is necessary to describe the
cumulative effect of all past actions combined. The Supreme Court
has also emphasized that
agencies may properly
limit the scope of their
cumulative effects
analysis based on
practical considerations.
Kleppe, 427 U.S at 414.
In some cases, based on scoping, information
about the effects of past actions that were similar
to the proposed action may be useful in describing
the possible effects of the proposed action. In
these circumstances, agencies should consider
using available information about the effects of
individual past actions that help illuminate or
predict the direct or indirect effects of the
proposed action and its alternatives.
“I have determined in the scoping process and/or subsequent preparation that detailed information on past and other present actions would not be useful and relevant to the required analysis of cumulative impacts.”
Step 2
Step 3
“I find that the historical details of individual past actions and other present actions would not be useful for predicting the effects of the proposed action, or there are practical considerations that limit the scope of analysis to the current aggregate of effects.”
©2008 O
wen L
. S
chm
idt
20
y1
Existingy2
Past actions
Other present actions
y3
Reasonably foreseeable action
y4
Proposed action
y5
Mitigation actiony6
x1
ReasonsIntensity
Context
Discussion point: we were going to do this anyway?
©2008 O
wen L
. S
chm
idt
Details about past actions may be omitted unless they may be … useful … relevant … necessary … informative.
35
Where “cumulative impacts” are relevant to the achievement of any standard (red bar), then x is the “what” and y is the “how much” to support any finding.
36
y1
Existingy2
Past actions
Other present actions
y3
Reasonably foreseeable action
y4
Proposed action
y5
Mitigation actiony6
x1
Discussion point: for an EA/FONSI, x is the left column, the top of y6 is the middle column, and scale is expressed in y2 through y6 or with the red bar (??) ........
x1 y6What How much Reasons
©2008 O
wen L
. S
chm
idt
y1
Existingy2
Past actions
Other present actions
y3
Reasonably foreseeable action
y4
Proposed action
y5
y6
x1
Discussion point: for an EA/FONSI, if mitigation is necessary to reach a “mitigated FONSI,” the mitigation must be incorporated into y1, not y6.
Mitigation action
For a “mitigated FONSI” only mitigation that is
incorporated into the proposal can be counted on to avoid adverse
consequences
16
©2008 O
wen L
. S
chm
idt
An EA/FONSI, properly prepared, would allow a reader to fill in a 3-column table where the left column reveals “what” the impacts are, the middle column reveals “how much” or the size of that impact, and the right column would give the reasons those impacts of that size are “not significant.”
37
38
Existing
Past actions
Other present actions
Reasonably foreseeable action
• No-action alternative
y1
Existingy2
Past actions
Other present actions
y3
y4
y5
y6
How much work is this?
• Existing condition• Affected environment
Proposed action
Mitigation action
• Proposed action alternative
Reasonably foreseeable action
Alternative action
Mitigation action
• Alternative action
Reasonably foreseeable action
Discussion point: we were going to do this anyway?
©2008 O
wen L
. S
chm
idt
y1
Existingy2
Past actions
Other present actions
y3
Reasonably foreseeable action
y4
y5
Mitigation actiony6
x1
Discussion point: when y1 = 0
If y1 = 0, there is no column because the proposed action could
not have an incremental impact
©2008 O
wen L
. S
chm
idt
The “affected environment” must be described, anyway. 40 CFR 1502.15. The “no-action alternative” must be described, anyway. 40 CFR 1508.25(b)(1). And the consequences of the proposed action and alternative action must be disclosed in a comparative form, anyway. 40 CFR 1502.14. Whether the consequences meet or exceed standards imposed for the protection of the environment must be disclosed, anyway. 40 CFR 1502.16.
39
When y1 = 0, the “consequence of concern” has turned out to be non-existent. If there is no consequence of concern, there can be no incremental impact caused by the proposed action and thus there can be no so-called “cumulative impact.” Nor is there a direct or indirect impact. If y1 is ! 0, than any “impact” it causes will necessarily be “cumulative” with whatever other y-value is implicated.
40
y1
Existingy2
Past actions
Other present actions
y3
Reasonably foreseeable action
y4
Proposed action
y5
Mitigation actiony6
x1
Discussion point: when there is no “level of concern”
… and there is no “level of concern,” what is the meaning of y6?
When y1 ! 0…
©2008 O
wen L
. S
chm
idt
y1
Existingy2
Past actions
Other present actions
y3
Reasonably foreseeable action
y4
Proposed action
y5
Mitigation actiony6
x1
Discussion point: what if x1 adds to x2?
Existing
Past actions
Other present actions
Reasonably foreseeable action
Proposed action
Mitigation action
x2
Then you haven’t yet gotten the right “x.” Make a new x3, if that is also a consequence of concern. Make a new x for every consequence of concern.
x3
©2008 O
wen L
. S
chm
idt
When y1 ! 0, and there is no level of concern, the only remaining reason to build a column graph would be to compare y6 for each alternative ….
41
42
y1
Existingy2
Past actions
Other present actions
y3
Reasonably foreseeable action
y4
Proposed action
y5
Mitigation actiony6
x1
Discussion point: when y6 is adverse
When y6 ! 0, and effects are adverse, these are “any adverse environmental effects which cannot be avoided should the proposal be implemented.” 42 U.S.C. 4332(2)(C)(ii)
©2008 O
wen L
. S
chm
idt
y1
Existingy2
Past actions
Other present actions
y3
Reasonably foreseeable action
y4
Proposed action
y5
Mitigation actiony6
x1
Discussion point: what if the agency has no statutory authority to act on y5?
When y5 ! 0, and effects are adverse, and the agency has no power to mitigate, then the agency has no decision to make and thus is not the legal cause of the consequence and thus need not account for the consequence
>0
>0
>0
0
11
©2008 O
wen L
. S
chm
idt
When y1 ! 0, but y6 = 0, something obviously happened between y1 and y6 to cancel the impact. Most likely this is the mitigation at y6. When y6 ! 0 and is adverse, after mitigation, these are “adverse effects which cannot be avoided.” 40 CFR 1502.16.
43
CASE LIST: Where an agency has no ability to prevent a certain effect due to its limited statutory authority over the relevant actions, the agency cannot be considered a legally relevant cause of the effectThis is why “Mitigation action” is placed at y6: we don’t know whether there is anything to “mitigate” until we know what all of the consequences are. What is the point of an agency assessing a consequence if the agency can do nothing about the consequence? But we have to assess it in order to know whether it is there at all. And it may be relevant, anyway, to the choice between alternatives. The purpose of NEPA is to inform agency decisionmaking ......
44
y1
y2
y3
y4
y5
y6
x1
Discussion point: adding temporal scale
Temporal scale can be added to show the effects over time when
temporal scale is relevantTime
©2008 O
wen L
. S
chm
idt
+
Discussion point: comparing positive values and negative values would invite use of a bar chart or histogram ........
+
+
+
+
-
-
-
©2008 O
wen L
. S
chm
idt
45
46
Existing
Past actions
Other present actions
Reasonably foreseeable action
Proposed action
Mitigation action Colors are arbitrarily assigned from the longest
wavelength at the bottom to the shortest wavelength at the top ...... blue, green, yellow,
orange, red, violet.
y1
y2
y3
y4
y5
y6
x1
Discussion point: Graphical options: color coding and double-sided graph
Continued ...
©2008 O
wen L
. S
chm
idt
Existing
Past actions
Other present actions
Alternative A
- -
-
+
++
+++
++++
Existing
Past actions
Other present actions
Reasonably foreseeable action
Proposed action
Mitigation action
- – -
+++
- – -
-- – – -
0
Reasonably foreseeable action
- – -
-
Proposed action
Mitigation action
+++
+
Alternative B
Sum total aggregate cumulative effect is -
Sum total aggregate cumulative effect is 0
©2008 O
wen L
. S
chm
idt
47
48