Upload
winfred-lucas
View
216
Download
1
Embed Size (px)
Citation preview
1
Distribution System Expansion PlanningUsing a GA-Based Algorithm
Shiqiong Tong , Yiming Mao, Karen Miu
Center for Electric Power EngineerDrexel University
2
• Introduction
• Problem Formulation
• Solution Algorithm
• Simulations
• Conclusions
Outline
ControlVariables
DG ControlVariables
Feeder UpgradeControl Variables
GeneticAlgorithm
HeuristicAlgorithm
GA-BasedAlgorithm
3
• Careful DG placement is an option to - expand generation capacity - release transmission and distribution system capacity - delay equipment upgrade - enhance system reliability
• New strategies and methods for distribution system expansion planning need to be developed
Introduction
4
Introduction
Previous work about DG placement
• Grffin et. al. [6] provided a method based on loss sensitivity or load distribution to reduce losses. (2000)
• Nara et. al. [7] applied tabu search to minimize interruption cost. (2001)
• Kim et. al. [8] used fuzzy-GA method to minimize distribution loss cost. (2002)
• Teng et. al. [9] proposed a GA to maximize the benefit/cost ratio of DG placement. (2002)
5
• We proposed a cost-based problem formulation including:
- feeder upgrade costs
- DG installation costs
- DG operating costs
- wheeling costs
• A GA-based algorithm is designed to solve this problem
Introduction
6
Problem Formulation
,min ( , )
x uf x u
( , ) 0F x u
( , ) 0G x u
st.
aggregate objective function
where: x : continuous state variables u : discrete control variables
Constrained Optimization Problem:
voltage magnitude, current magnitude, feeder capacity , DG penetration constraints
3 power flow equations
7
Problem Formulation
[ ]loc type fDG DG Gu u u P u
1 1 2[ ] [ , , , ]DG DG
loc loc loc locDG n nu u u u
1 1 2[ ] [ , , , ]DG DG
type type type typeDG n nu u u u
1 1 2 21 1 1 1[ ] [ , , , , , ] 'l l
DG l DG DG DG
n nG n n G Gn G Gn G GnP P P P P P P
, , , , , ,2 1 1 1 2 2[ ] [ , , , , , , ] '
branch branch branch
f f R f X f R f X f R f Xn n nu u u u u u u
DG location:
DG type:
DG output:
Feeder upgrade:
8
Objective Function:
Problem Formulation
4
1
( , ) ( , )ii
f x u C x u
where:
C1(x,u) : total feeder upgrade cost
C2(x,u) : total DG installation cost
C3(x,u) : total DG operating cost
C4(x,u) : total wheeling cost
9
• DG model
- P|V| bus
- same type DG can be installed on one bus
• Balanced three-phase transformer and branch upgrades
• Keep original configuration of radial distribution power system
Modeling Issues
10
• GA-based algorithm Design
- Genetic Algorithm Determine DG control variables DG initial locations are bias using available feeder
capacities
- Heuristic Algorithm Determine feeder upgrade control variables
- using three-power flow studies with DG
information to decide upgrade options
Solution Algorithm
11
• GA-based Algorithm Design (Continued)– Coding
Solution Algorithm
location 1 location 2 location 3
type onlocation 1
type onlocation 2
type onlocation 3
output onlocation 1
output onlocation 2
output onlocation 3
output onlocation 1
output onlocation 2
output onlocation 3
Load Leval lnLoad Level 2Load Level 1
DG location substring
DG type substring
DG output substring
GA controlvariables
(Binary code)
options forbranch 1
options forbranch 2
options forbranch 3
Options forbranch nb
Feeder upgradesubstring
Dependent controlvariables
(Integer code)
output onlocation 1
output onlocation 2
output onlocation 3
12
• A 20-bus distribution system• Two 4MVA transformers• 17 line feeders ( total length about 7.18 miles)• 12 loads
Simulations
1 2 3
4 5 6 7 8 9 10 11
12 13 14
15 16 17 18
19 20Transformer
Closed Switch
Load
13
• Loads
- The total three-phase base load 5.8610 MW and 2.104 Mvar
- Three load levels Low: 0.7 times of the base load Medium: the base load High: 1.1 times of the base load
- Each load level lasts one year
Simulations
14
• Cost data
- Wheeling cost $0.065 per KWh
- Transformer upgrade cost $400,000 for each
- Line upgrade cost: $30,000 per 1000 feet
- DG cost: see Table 2 on the paper
Simulations
15
• Transformer between Bus 2 and Bus 4 is over-loaded
- Transformer capacity: 4 MVA
- Medium-load level:
= 4.1789 MVA > 4 MVA
- High-load level:
= 4.6519 MVA > 4 MVA
SimulationsCase 1. Original system
32 4S
32 4S
16
• Upgrade the transformer between Bus 2 and Bus 4• Total cost: $11,320,006
Total cost = Wheeling costs + Upgrade costs
= $10,920,006 + $ 400,000
= $11,320,006
Simulations
Case 2. Feeder upgrade without DG placement
17
• Use proposed GA-based algorithm• Solution: - No feeder upgrade - One DG on bus 8:
0.5 MW reciprocating operating outputs: 0,0.5 and 0.5 MW
- Total cost: $11,043,429
Total cost = Wheeling costs + DG installation costs + DG operating costs = $10,182,569 + $ 217,000 + $643,860 = $11,043,429
Simulations
Case 3. Feeder upgrade with DG placement
18
Simulations
0 50 100 150 200 250 300 3501.1
1.11
1.12
1.13
1.14
1.15
1.16
1.17
1.18
1.19
1.2x 10
7
To
tal
Co
st,
$
generation
Algorithm performance
Case 2: feeder upgrade without DG placement
Case 3: feeder upgrade with DG placement
C=$276,577
19
• The proposed GA-based algorithm successfully generate high quality solutions
• DG placement with feeder upgrade can provide more diverse expansion solutions
• DG placement can avoid or delay equipment upgrades
• Considering DGs’ impacts to outage cost may further decrease cost for utilities.
Simulations
20
• In this paper, a problem formulation of distribution expansion planning with DG placement was proposed.
• A cost-based objective function considering feeder upgrade costs, DG installation costs, DG operating costs, and wheeling costs were discussed.
• A GA-based algorithm was discussed
• The simulation results using different methods were compared
Conclusions