Upload
alexandra-dean
View
212
Download
0
Embed Size (px)
Citation preview
1
8. IMPLEMENTING THE PLAN
Objective:
To understand the principles of successfully implementing a plan, by communicating the plan to key site personnel, monitoring the progress of work, and identifying problems.
Summary:8.1 Monitoring Progress of the Activities8.2 Monitoring Progress of the Project8.3 Site Implementation of Plan
2
• The plan generated from the activity network (following rescheduling) indicates:– planned start and finish activity times;– floats available (management by exception etc);– when to order equipment, materials, etc;– when information (plans, etc) are required
• Having established this plan, we need to implement it (a cyclical process):– communicate what is to be done to site personnel;– monitor the progress of work to see if it deviates from the plan;– plan remedial action to bring project back on target (control).
3
8.1 MONITORING PROGRESS OF
THE ACTIVITIES• Monitor the progress of work to see if it deviates from the
plan, and determine:– whether behind, ahead, or on schedule;– identify where the problem is:
• section of project (eg: ground work - weather) ?• a site manager is not performing well; etc...
– suggest possible solutions;– determine likely impact:
• project completion delays;• cash flow problems; etc..
• Use a template to monitor:
4Fig. 8-1: Monitoring the Progress of Work Using a Bar Chart
0 5 12 15 21 25 30 32TIME
1-2 (5 days)
2-3 (7 days)
3-5 (6 days)
2-4 (10 days)
5-7 (5 days)
4-6 (10 days)
6-7 (7 days)
PlannedStart & Finish
TIMENOW
RevisedStart & Finish
= ActualProgress
ActivityCompleted
Activity behindSchedule
Activity onSchedule
5
TIMENOW
3-5 (6 days)
– Activity 3-5 was planned to be 100% complete.
3-5
75%
– At its revised schedule, activity 3-5 should be 75% complete.
30%
– Activity 3-5 is actually just 30% complete• what is meant by % complete?
6
• The portion of an activity completed can be measured in many ways: – physical quantity of object built:
• volume,
• area,
• length, etc..
(problems ?)
– value of work built ($) (problems ?)– laborer hours (days etc) completed (problems ?)– activity hours (days etc) completed (problems ?)
7Fig. 8-2: Measuring Activity Days
0 5 12 15 21 25 30 32TIME
1-2 (5 days)
2-3 (7 days)
3-5 (6 days)
2-4 (10 days)
5-7 (5 days)
4-6 (10 days)
6-7 (7 days)TIMENOW
= ActualProgress
ActivityDays = planned
= actual
8
• A primary use of the shaded bar chart is to identify which activities could lead to delays to project completion or to milestones:– compare delay in the activity with its float, looking out
for:• critical activities, or activities with small total float;
• activities that are susceptible to delay (eg; weather dependent)
• accumulating delays along a sequence of activities;
• possibility that further delays will be incurred (eg: ground obstructions for piling operations).
9
8.2 MONITORING PROGRESS OF
THE PROJECT
• Shaded activity bar charts are good for monitoring work at the activity level.
• What about the overall progress of the project?– Compare the planned and actual cumulative progress
curves for the entire project (or section):• Typically, cumulative progress curves follow the classic
‘S’ form
– Can measure progress as for activities (ie: value of work completed, laborer hours completed, etc)
10Fig. 8-3: Measuring Cumulative Activity Days
0 5 12 15 21 25 30 32TIME
1-2 (5 days)
2-3 (7 days)
3-5 (6 days)
2-4 (10 days)
5-7 (5 days)
4-6 (10 days)
6-7 (7 days)TIMENOW
= ActualProgress
ActivityDays = planned
= actual50
25
0
11
Fig. 8-4: Monitoring the Cumulative Progress of Work
CUMULATIVEPROGRESS
TIME
= planned progress= actual progressTIME
NOW
extent to which workis behind schedule
trend is divergencetherefore
worsening
12
8.3 SITE IMPLEMENTATION OF
PLAN• There is a need to communicate the plan to
site personnel– Detailed, identifying resources required, on
which days– Only go a short distance into future (2-3 weeks)
as detail quickly becomes out-of-date.– May give a review of previous weeks activities.– Should be in a form understood by supervisors
(eg bar charts and simple data lists)– Information targeted at a specific operation (eg:
concreting; framing; etc)
13
Fig. 8-5: Example Short Interval Schedule
OPERATION:
Activity Mon
Tue
Wed
Thu
Fri
Sat
Sun
Mon
Tue
Wed
Thu
Fri
Sat
Sun
Mon
Tue
Wed
Thu
Fri
Sat
Sun
Last Week Week 1 Week 2
Foundation
ProfilesExcavateFormsRe-bars
Concretingsee sheet 2Strike form
delayed2 laborers; 2 carpenters; drawings #45-2122
2 laborers; 2 steel workers; schedules #31-2122
4 laborers; 1 mixer
see sheet 2
2 laborers