8
1 © 2011 Profile Recorder for ProtoFlow S Installation Instruction

1 © 2011 Profile Recorder for ProtoFlow S Installation Instruction

Embed Size (px)

Citation preview

Page 1: 1 © 2011 Profile Recorder for ProtoFlow S Installation Instruction

1 © 2011

Profile Recorder for ProtoFlow SInstallation Instruction

Page 2: 1 © 2011 Profile Recorder for ProtoFlow S Installation Instruction

2 © 2011

Profile recorder – Installation

• Switch the oven ON

• Open the drawer (select function „OPEN/CLOSE“ in „SETTING“ menu)

• Switch the oven OFF, leaving the drawer opened

• Unplug a power cord from the mains!

Disconnect the system from the mains during all maintenance work on the system.

Disconnect the system from the mains during all maintenance work on the system.

Page 3: 1 © 2011 Profile Recorder for ProtoFlow S Installation Instruction

3 © 2011

Profile recorder – Installation

Position of the “blank” cover or the “Profile recorder” connection box:

•The “blank” cover which covers the profile recorder installation or the “Profile recorder” connection box is mounted in a front part of the drawer

Exchanging or removing the “blank” cover :

•Unscrew all three screws from the bottom side of the drawer

•Use Allen key no.:2.5

Page 4: 1 © 2011 Profile Recorder for ProtoFlow S Installation Instruction

4 © 2011

Profile recorder – Installation

Remove the screws:

• Remove all three screws completely

• Gently lift up the “blank” cover

Lifting up:

• Lift up the cover or the box

• Remove cable from a clip

• Pull out a rubber grommet

Be careful to not scratch the glass.

Page 5: 1 © 2011 Profile Recorder for ProtoFlow S Installation Instruction

5 © 2011

Profile recorder – Installation

Inserting the “profile recorder” connection box

•Take a “profile recorder” connection box and put it into drawer with the electronic side up.

Electrical connections:

•Plug in the connector

Page 6: 1 © 2011 Profile Recorder for ProtoFlow S Installation Instruction

6 © 2011

Profile recorder – Installation

Fixing the cable

• Fix the cable with pushing the rubber grommet into the slot

Fix the connection box

• Flip the connection box and place it in its place

• Fix the connection box with screws from the bottom side of the drawer

Page 7: 1 © 2011 Profile Recorder for ProtoFlow S Installation Instruction

7 © 2011

Profile recorder – Installation

The installation procedure is finished.

To check:

• Plug the power cord into mains

• Press the power switch to turn ON the oven

After turn ON the oven, it recognize the profile recorder automatically.

• Choose the number of sensors to be displayed on the LCD:

o SETTINGS LCD VIEW

LCD 5CH

LCD 7CH

Page 8: 1 © 2011 Profile Recorder for ProtoFlow S Installation Instruction

8 © 2011

Thank you for your attention!LPKF Laser & Elektronika d.o.o. · Polica 33 · 4202 Naklo · www.lpkf.si

+386 592 08 800, [email protected]