ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 1 of 84
IX STATIC EQUIPMENT – Procurement Stage
INSPECTION AND TEST PLAN (ITP) FOR LOW ALLOY AND CLAD PRESSURE VESSEL
(Tower, Vessel and Heat Exchanger)
Print Name
Signature Name of Company Doc No:
EPM‐ITP‐QP‐001 Prepared By: (1)
Approved By: (2) Revision 0
SABIC App: Stage Procurement Discipline: Static Equipment PROJECT: Date:
Location: (3) Item Name (3): Tag No (3): Page:
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
EPC
SABIC
Remarks
1 Raw Material Inspection
a) Mechanical Test (including. bond shear test for cladding and impact test if specified)
Tensile strength, impact, bend and bonding shear strength properties.
SESQ01-F35, SES Q01-S01 SES Q01-T02, ASME II
SES Q01- S01 clause 6 Conform to ASME II, SA-263, SA-264 and SA-265, and minimum bond shear test of 140 MPa.
Material Test Certificate I R R
b) Non
Destructive Examination (if specified)
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 2 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
EPC
SABIC
Remarks
i. Ultrasonic examination for plate and forging
Subsurface discontinuities.
SES Q01 S01 SESQ01-F35, Project Specification for NDT
SES Q01 S01 Clause 8.2.3 SES Q01 F35 Clause 6 Material Specification
NDT Report I R R
ii. Liquid Penetrant Examination for forging
Surface discontinuities
SES Q01 T01, Project Specification for NDT
SES Q01 T01 clause 6.3.4 NDT Report I R R
iii. Ultrasonic
examination for cladding
Lack of Bonding
SES Q01 S01 SESQ01-F35, SES Q01 T01 Project Specification for NDT
SES Q01 S01 Clause 8.2.3 SES Q01 F35 Clause 6 SES Q01 T01 clause 6.3.2
NDT Report I R R
2
Material Certification (pressure parts and stress members)
Material used to be identified and certified
SESQ01-F35, SESQ01-F08, SES Q01-S01’ SES Q02-F01
Material per the required specification
Material Certificate R R R
3
Material Identification for Alloy
Verification of Alloy Material SES Q01-T07
Percentages of alloying elements within tolerances
PMI Report I W2 R
4
Ultrasonic Examination for Claddings (after forming)
Lack of bonding
SES Q01 S01 SESQ01-F35, SES Q01 T01 Project Specification for NDT
SES Q01 S01 Clause 8.2.3 SES Q01 F35 Clause 6 SES Q01 T01 clause 6.3.2
NDT Report I W2 R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 3 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
EPC
SABIC
Remarks
5
Welding Procedure Specification Approval
Essential, nonessential, and supplementary essential variables in accordance to PQR
SES W11-F01 ASME IX
WPS approved As per SES W11-F01/ASME Section IX requirements
WPS /PQR Register I W1* R
6 Welder/ Welding Operator approval
Welder ability to deposit sound weld metal and welding operators ability to operate the welding equipment
ASME IX SES W11-F01
Welders and Operator Approved As per SES W11-F01/ ASME Section IX requirements
Welder and Welding Operator Qualification Test
I W1* R
NOTE: * Previous records may be reviewed.
7
Weld Joint Fit-up Edge Preparation (including clad stripping)
Root gap, land zone including angle, weld face cleanliness, material specification, alignment and fit-up dimensions. Copper sulfate test after clad stripping.
SES Q01- F01 SES Q01- F08 SES Q01-F35 Relevant WPS Vendor drawings
As per WPS, Drawings, Clad materials completely removed
Weld Map Report/ Reference Welding Inspection Checklist
I W2 R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 4 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
EPC
SABIC
Remarks
8
Magnetic Particle Examination or Liquid Penetrant Examination a) Edge to be welded (if specified) b) Attachment welds c) Deposited Welds for cladding d) knuckle area of formed heads.
Surface discontinuities
SES Q01 S01 SES Q01 T01 Project Specification for NDT
SES Q01 S01 Clause 8.2.4, 8.2.5 & 8.2.6 SES Q01 T01 clause 6.3.3 & 6.3.4
NDT Report I W2 R
9 Inspection During Welding
Interpass temperature, interpass cleaning and other essential non-essential parameters and weave width. Visual and LPT after back gouging prior to second side welding.
SES Q01- F01 SES Q01-T01 WPS
As per WPS SES Q01-T01 clause 6.3.4
Welding Inspection Checklist NDT Report
I R R
10 Visual Examination of Completed Welds
Surface defects, weld size and profile/appearance. Identification of weld and welders.
SES Q01-T01 SES Q01-S01 ASME Sec VIII Div. 1 & 2
SES Q01-T01 ASME Sec VIII div 1 clause UW 33 & 35 or Div 2 clause 7.5.2
Welding Inspection Checklist
I R R
11 PMI on Weld Overlay
Verification of Alloy Material
SES Q01-T07
Percentages of basic alloying elements within tolerances
PMI Report I W2 R
12 Reinforcing Pad Test Leaks around the pad SES Q01-S01 SES Q02-T02 No leaks around the pad Leak test
Report I W2 R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 5 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
EPC
SABIC
Remarks
13 Post Weld Heating, if required As per WPS SES Q01-F01
WPS Relevant WPS As per WPS I R R
14 Ultrasonic Examination of Welds before PWHT and / or Hydro test
Surface and subsurface discontinuities
SES Q01-S01 ASME Sec VIII Div. 1 & 2
ASME Sec VIII Div. 1 Appendix 12, ASME Sec VIII Div. 2 Article 9-3
NDT Report I R R
15
Radiographic Examination (checking of radiographic film)
Surface and internal discontinuities.
SES Q01-S01 ASME Sec VIII Div. 1 & 2
ASME div . 1 Clause UW 51/52 or div 2 Clause 7.5.3 as applicable
NDT report , I R R
16
Post Weld Heat Treatment
Heating temperature, soaking time and cooling rate
SES Q01-S01, ASME VIII Div. 1 and 2
Heating /cooling rate and soaking time as per the requirements
PWHT Chart I R R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 6 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
EPC
SABIC
Remarks
17
Ultrasonic Examination of Cladding after PWHT
Lack of bonding
SES Q01 S01 SES Q01-F35, SES Q01 T01 Project Specification for NDT
SES Q01 S01 Clause 8.2.3 SES Q01 F35 Clause 6 SES Q01 T01 clause 6.3.2
NDT Report I W2 R
18 Magnetic Particle Examination after PWHT
a) Pressure retaining welds
Surface and near surface discontinuities
SES Q01-T01 SES Q01-S01, ASME VIII Div.1 and 2 Project Specification for NDT ,
SES Q01 S01 Clause 8.2.4, 8.2.5 SES Q01 T01 clause 6.3.3
NDT Report
I
W2
R
b) Vessel to support welds
c) Non-pressure attachment welds
d) Removal of temporary attachment areas, thermocouple and arc strike ground areas
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 7 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
EPC
SABIC
Remarks
19
Liquid Penetrant Examination after PWHT (Deposit Welded for Cladding, pressure retaining and attachment welds, removal of temporary attachment areas and arc strike ground areas)
Surface discontinuities
SES Q01-T01 SES Q01-S01, ASME VIII Div.1 and 2 Project Specification for NDT ,
SES Q01 S01 Clause 8.2.6, SES Q01 T01 clause 6.3.4
NDT Report I W2 R
20 Tube Bending Inspection
Visible laminations, Scale, Scratches, flattening and crack
SES Q02-F01
Crack not permissible other defects within specification
Inspection Report I W2 R
21 PWHT of Tubes After Bending- if specified
Heating /cooling Rate and soaking time. Temp Range & Duration
SES Q02-F01, Project Specification for PWHT
Correctly performed and temperature readings conform to the requirements.
PWHT Chart and report I W2 R
22 Tube to Tube sheet Joint Inspection
Cleanliness, tube expansion, welding defects and tightness check
SES Q02-F01, SES Q02-E01, SES Q02-T01,
Clean, wall thinning within the range, free of welding defect and passed tube leak or tightness check
Inspection Report I W1 R
23 Hardness Test Hardness of the weld and heat affected zone
SES Q01-F01, SES Q02-T01, SES Q01-S01
Below the maximum allowable limit as specified in reference project specification
Hardness Test Report I W2 R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 8 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
EPC
SABIC
Remarks
24
Final Visual and Dimensional Inspection (incl. stacking of multiple shell arrangement and bundle inspection)
Visual defects, general surface condition / appearance, alignment and main dimensions
SES Q01-F28 Vendor Drawings
As per drawing and relevant project specification
Inspection Report I H H
25 Hydrostatic Test (and Chloride Check, if required)
Water quality, Equipment Calibration, Test Pressure and Duration
SES Q01-T01 SES Q01-T02 SES Q01-S01 ASMEVIII Div. 1 & 2.
Chloride content within the specified limit as per the specification. No Leaks. Test Pressure Maintained
Pressure Test Report I H W1
26
Ultrasonic and Magnetic Particle Examination after Hydro Test (if specified)
Internal and Surface discontinuities
SES Q01-T01 SES Q01-S01, ASME VIII Div.1 and 2 Project Specification for NDT
SES Q01 S01 Clause 8.2.3 SES Q01 F35 Clause 6 SES Q01 T01 clause 6.3.2 SES Q01 S01 Clause 8.2.4, SES Q01 T01 clause 6.3.3
NDT Report I W1 R
27 Internal Installation Check (if any)
Installation of all internal components/accessories and tightening of fasteners.
Vendor Drawings, SES Q01-T72, SES Q01-F72
Conform to vendor drawings and specified bolt torque
Inspection Report I W1 W2
28 Rust Prevention Check and Painting Inspection
Surface preparation, DFT, surface defect, rust prevention and equipment preservation
SES Z01-G07, SES T01-S01 Project Procedure for Equipment / Material Preservation
Surface profile/condition. DFT within the lower and upper limits and free from surface irregularities. Equipment properly dry and securely preserved
Painting and preservation reports
I W1 R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 9 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
EPC
SABIC
Remarks
29 Shipping Preparation Inspection
Certified records, release note, proper packaging, nameplate data, orientation/spare parts markings, preservation, loading and shipping instructions.
SES Q01-S01, SES Q02-F01, SES Z01-G07
Fulfilled all requirements
Equipment Dossier, Packing Lists, Packing Inspection Reports. Inspection Release Note.
I W1 W2
Legend
(1) ‘Prepared by’ should be the name, signature and Company’s name for the Vendor’s/Sub Contractor’s representative. (2) ‘Approved by’ should be the name, signature and Company’s name for the Contractor’s representative. (3) ‘Location’, ‘Item Name’ and ‘Tag Number’ shall be used if applicable. (4) ‘Characteristics Verified’ are the parameters checked during the inspection activity. (5) ‘Reference Document’ is the Project Specification / Code / Standard / Drawing, Procedure etc on the basis of which inspection shall be conducted. (6) ‘Acceptance Criteria’ is the tolerance, reading, value or an outcome derived from reference documents. (7) “Verifying Document’ is the record generated during inspection & Testing using approved forms / checklists. (8) “Inspection Responsibility’ is the role of Vendor / Sub Contractor , Contractor and SABIC for each inspection step. Inspection responsibility shall be ‘I’ for Inspection, ‘R’ for review, ‘S’ for Surveillance,
“W1’ for 100% Witness, ‘W2’ for random witness and ‘H’ for hold. For the explanation of these inspection responsibilities refer to the ‘definitions’ part of PEI section 4.7.1 (9) Rust prevention coating should protect the material from corrosion and shall be easily removed in the field. Austenitic stainless steel materials shall not be coated but shall be protected from ferritic
contamination, chloride attack and galvanic corrosion.
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 10 of 84
INSPECTION AND TEST PLAN (ITP) FOR HIGH ALLOY PRESSURE VESSEL
(Tower, Vessel and Heat Exchanger)
Print Name
Signature Name of Company Doc No:
EPM‐ITP‐QP‐002 Prepared By: (1)
Approved By: (2) Revision 0
SABIC App: Stage Procurement Discipline: Static Equipment PROJECT: Date:
Location: (3) Item Name (3): Tag No (3): Page:
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
1 Raw Material Inspection
1. Mechanical
Test (impact test if specified)
Tensile, compression, impact, weldability, fatigue and bend strength properties.
Purchase Specification
Material as per project specification and by approved vendors
Material Test Certificate R R R
2. Non Destructive
Examination (if specified)
a) Ultrasonic Examination of Plate and Forging
Lamination and other Internal discontinuities.
SES Q01 S01 Project Specification for NDT
SES Q01 S01 Clause 8.2.3
NDT Report I R R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 11 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
EPC
SABIC
Remarks
b) Liquid Penetrant Examination of Forging
Surface discontinuities
SES Q01 T01, Project Specification for NDT
SES Q01 T01 clause 6.3.4 NDT Report I R R
2 Material Certification (pressure parts and stress members)
Material used to be identified and certified
SES Q01-S01, SES Q02-F01
Material per the required specification Material Certificate R R R
3 Material Identification for Alloy
Verification of basic alloy element
SES Q01-T07
SES Q01-T07 Clause 8
PMI Report, I W2 R
4
Welding Procedure Specification Approval
Essential, nonessential, andsupplementary essential variables in accordance to PQR
SES W11-F01 ASME IX
WPS approved As per SES W11-F01/ASME Section IX requirements
WPS /PQR Register I W1* R
5 Welder/ Welding Operator approval
Welder ability to deposit sound weld metal and welding operators ability to operate the welding equipment
ASME IX SES W11-F01
Welders and Operator Approved As per SES W11-F01/ ASME Section IX requirements
Welder and Welding Operator Qualification Test
I W1* R
NOTE: * Previous records may be reviewed.
6 Weld Joint Fit-up and Edge Preparation
Root gap, land zone including angle, weld face cleanliness, alignment, material specification and fit-up dimensions.
SES Q01- F01 Relevant WPS Vendor drawings
As per WPS, Drawings,
Weld Map Report/ Reference Welding Inspection Checklist
I W2 R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 12 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
EPC
SABIC
Remarks
7
Liquid Penetrant Examination a) Edge to be welded (if specified) b) Attachment welds c) knuckle area of formed heads.
Surface discontinuities
SES Q01 S01 SES Q01 T01 Project Specification for NDT
SES Q01 S01 Clause 8.2.6 SES Q01 T01 clause 6.3.4
NDT Report I W2 R
8 Inspection During Welding
Interpass temperature, interpass, cleaning and other essential non-essential parameters and weave width. Visual, LPT after back gouging prior to second side welding.
SES Q01- F01 SES Q01-T01 WPS
As per WPS SES Q01-T01 clause 6.3.4
Welding Inspection Checklist NDT Report
I R R
9 Visual Examination of Completed Welds
Surface defects, weld size and profile/appearance. Identification of weld and welders,
SES Q01-T01 SES Q01-S01 ASME Sec VIII Div. 1 & 2
SES Q01-T01 ASME Sec VIII div 1 clause UW 33 & 35 or Div 2 clause 7.5.2
Welding Inspection Checklist I R R
10 PMI on Pressure Retaining Welds
Verification of Alloy Material
SES Q01-T07
Percentages of basic alloying elements within tolerances
PMI Report I W2 R
11 Ferrite Content Check (when required)
Ferrite number SES Q01-F01
Ferrite number within the minimum and maximum range of relevant specification
Inspection Report I R R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 13 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
EPC
SABIC
Remarks
12 Reinforcing Pad Test Leaks around the pad SES Q01-S01 SES Q02-T02
No leaks around the pad Leak test Report I W2 R
13
Radiographic Examination (checking of radiographic film)
Surface and internal discontinuities.
SES Q01-S01, ASME Sec VIII Div. 1 & 2
ASME div . 1 Clause UW 51/52 or div 2 Clause 7.5.3 as applicable
NDT report , I R R
14
Post Weld Heat Treatment - if Required
Heating temperature, soaking time and cooling rate
SES Q01-S01, ASME VIII Div. 1 and 2
Heating /cooling rate and soaking time as per the requirements
PWHT Chart and report I R R
15 Hardness Test Hardness of the weld and heat affected zone
SES Q01-F01, SES Q02-T01, SES Q01-S01
Below the maximum allowable limit as specified in reference project specification
Hardness Test Report I W2 R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 14 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
EPC
SABIC
Remarks
16
Liquid Penetrant Examination after PWHT (Pressure retaining and attachment welds, removal of temporary attachment areas and arc strike ground areas)
Surface discontinuities
SES Q01-T01 SES Q01-S01, ASME VIII Div.1 and 2 Project Specification for NDT
SES Q01 S01 Clause 8.2.6, SES Q01 T01 clause 6.3.4
NDT Report I W2 R
17 Tube Bending Inspection
Visible laminations, scale, scratches, flattening and crack
SES Q02-F01 Crack not permissible other defects within specification
Inspection Report I W2 R
18 PWHT of Tubes After Bending - if specified
Heating /cooling Rate and soaking time. Temp Range & Duration
SES Q02-F01, Project Specification for PWHT
Correctly performed and temperature readings conform to the requirements.
PWHT Chart and report I W2 R
19 Tube to Tube sheet Joint Inspection
Cleanliness, tube expansion, welding defects and tightness check
SES Q02-F01, SES Q02-E01, SES Q02-T01
Clean, wall thinning within the range, free of welding defect and passed tube leak or
Inspection Report I W1 R
20
Final Visual and Dimensional Inspection (incl. stacking of multiple shell arrangement and bundle inspection)
Visual defects, general surface condition / appearance, alignment and main dimensions
SES Q01-F28 Vendor Drawings
As per drawing and relevant project specification
Inspection Report
I H H
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 15 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
EPC
SABIC
Remarks
21
Hydrostatic Test (and Chloride Check)
Water quality, Equipment Calibration, Test Pressure and Duration
SES Q01-T01 SES Q01-T02 SES Q01-S01 ASMEVIII Div. 1 & 2.
Chloride content within the specified limit as per the specification. No Leaks. Test Pressure Maintained
Pressure Test Report
I H W1
22
Ultrasonic and Liquid Penetrant Examination after Hydro. Test (if specified)
Internal and surface discontinuities
SES Q01-T01 SES Q01-S01, ASME VIII Div.1 and 2 Project Specification for NDT
SES Q01-S01 clause 8.2.3 SES Q01-T01 clause 6.3.2 SES Q01-S01 clause 8.2.6, SES Q01-T01 clause 6.3.4
NDT Report
I W1 R
23
Visual Check after Pickling (when required)
Check for stains, inorganic contaminants, rust or scale.
Approved pickling and passivation procedure
Free of surface contaminants
Inspection Report
I W1 W2
24
Internal Installation Check (if any)
Installation of all internal components/accessories and tightening of fasteners.
Vendor Drawings, SES Q01-T72, SES Q01-F72
Conform to vendor drawings and specified bolt torque
Inspection Report
I W1 W2
25
Rust Prevention Check and Painting Inspection
Surface preparation, DFT, surface defect, rust prevention and equipment preservation
SES Z01-G07, SES T01-S01 Project Procedure for Equipment / Material Preservation
Surface profile / condition. DFT within the lower and upper limits and free from surface irregularities. Equipment properly dry and securely preserved
Painting and preservation reports
I W1 R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 16 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
EPC
SABIC
Remarks
26
Shipping Preparation Inspection
Certified records, release note, proper packaging, nameplate data, orientation/spare parts markings, preservation, loading and shipping instructions.
SES Q01-S01, SES Z01-G07
Fulfilled all requirements
Equipment Dossier, Packing Lists, Packing Inspection Reports. Inspection Release Note.
I W1 W2
Legend
1) ‘Prepared by’ should be the name, signature and Company’s name for the Vendor’s/Sub Contractor’s representative. (2) ‘Approved by’ should be the name, signature and Company’s name for the Contractor’s representative. (3) ‘Location’, ‘Item Name’ and ‘Tag Number’ shall be used if applicable. (4) ‘Characteristics Verified’ are the parameters checked during the inspection activity. (5) ‘Reference Document’ is the Project Specification / Code / Standard / Drawing, Procedure etc on the basis of which inspection shall be conducted. (6) ‘Acceptance Criteria’ is the tolerance, reading, value or an outcome derived from reference documents. (7) “Verifying Document’ is the record generated during inspection & Testing using approved forms / checklists. All forms and checklists shall be attached to the ITP and submitted to the Company during the
approval Stage. (8) “Inspection Responsibility’ is the role of Vendor / Sub Contractor , Contractor and Company for each inspection step. Inspection responsibility shall be ‘I’ for Inspection, ‘R’ for review, ‘S’ for Surveillance,
“W1’ for 100% Witness, ‘W2’ for random witness and ‘H’ for hold. For the explanation of these inspection responsibilities refer to the ‘definitions’ part of PEI section 4.7.1
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 17 of 84
INSPECTION AND TEST PLAN (ITP) FOR CARBON STEEL PRESSURE VESSEL (Tower, Vessel and Heat Exchanger)
Print Name
Signature Name of Company Doc No:
EPM‐ITP‐QP‐003 Prepared By: (1)
Approved By: (2) Revision 0
SABIC App: Stage Procurement Discipline: Static Equipment PROJECT: Date:
Location: (3) Item Name (3): Tag No (3): Page:
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
1 Material Certificates
Size, heat number Material specification mechanical properties and chemical composition etc
ASME Sec II Part A or B as applicable Purchase order specification
ASME Sec II Part A or B as applicable and certified by 3rd party
Certified mill test report
R R R
2 Welding Procedure Qualification Test
Essential, nonessential, andsupplementary essential variables
ASME IX, SES W11-F01
WPS and PQR Approved As per SES W11-F01
WPS /PQR Register I W1* R
3
Welder and Welding Operator Qualification Test
Welder ability to deposit sound weld metal and welding operators ability to operate the welding equipment
ASME IX, SES W11-F01
Welders and Operator Approved as per SES W11-F01/ASME Sec IX As per SES W11-F01
Approved Welder list
I W1* R
NOTE: * If WPS already exist, records may be reviewed.
4
Edge Preparation and Fit-up inspection Weld Joint Fit-up
Root gap, land zone including angle, material, LPT/MPT of weld face Preheat, Dimensions,
Drawings SES Q01-F28
As per drawings and project specification,
Fit-up Report
I W2 R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 18 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
Inspection during welding
Interpass temperature, interpass cleaning and other essential non-essential parameters, weave width, Visual, LPT/MPT of back gauging
SES Q01- F01 Q01 T01 WPS
SES Q01- F01 Q01 T01 WPS
Welding Inspection Checklist
5
Visual Inspection of completed Welds
Weld profile and welding discontinuities, Identification of weld and welders
SES Q01-S01 SES Q01-T01 SES Q02-F01 ASME Sec VIII
SES Q01-T01 ASME Sec VIII div 1 clause UW 33 & 35 or Div 2 clause 7.5.2
Welding Inspection Checklist Visual Inspection Report
I S S
6
Magnetic Particle Examination or Liquid Penetrant Examination
a) Knuckle area of formed heads b) Back gouging and/or grinding (if any) c) Pressure retaining and attachment welds d) Tube to tubesheet weld joints e) temporary attachment removal areas and arc strike ground areas
Surface discontinuities
Manufacturer Approved PT/MT Procedure
Free from unacceptable discontinuities NDT Report I
W2
R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 19 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
7 Reinforcing Pad Leak Test
Leaks around the pad SES Q01-S01 SES Q02-T02
No leaks Leak test Report I W1 W2
8
Radiographic Examination ( Before and after PWHT)
Surface and internal discontinuities.
SES Q01-S01 SESQ01-T01 Manufacturer Approved RT Procedure
SES Q01-S01 clause 8.2.2 SESQ01-T01clause 6.3.1
RT report
I R R
9 Post Weld Heat Treatment (when required)
Heating /cooling Rate and soaking time. Temp Range & Duration
SESW12-F04 SES Q01-S01 Project Specification for PWHT
SESW12-F04
PWHT Chart and report
I R R
10
Ultrasonic Examination of pressure retaining welds (before and after PWHT or Hydro test)
Detecting surface and internal discontinuities
SES Q01-T01 Manufacturer Approved UT Procedure
SES Q01-T01 clause 6.3.2 UT Report
I R/W2 R
11
Hardness Test
Hardness of the weld and heat affected zone
SES Q01-F01/ S01, SES Q02-F01 Project Specification
Hardness result within the specification
.Hardness Test Report
I W1 R
12
Magnetic Particle / Liquid Penetrant Examination after PWHT
Surface and near surface discontinuities in pressure and non pressure retaining welds arc strike ground areas (including temporary attachment removal area)
SES Q01-T01 Manufacturer Approved MT/PT Procedure
SES Q01-T01 clause 6.3.3/6.3.4 Free from unacceptable discontinuities
NDT Report
I W2 R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 20 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
15
Tube bending inspection
Visible laminations, scale, scratches, flattening and crack
SES Q02-F01 SES Q02- T01
Crack not permissible other defects within specification, SES Q02- T01
Inspection Report I W2 R
14 PWHT of tubes after bending (if specified)
Heating /cooling Rate and soaking time. Temp Range & Duration
SES Q02-F01 Project Specification for PWHT
SES Q02-F01 clause 6.6
PWHT Chart and report
I W2 R
Legend
(1) ‘Prepared by’ should be the name, signature and Company’s name for the Vendor’s/Sub Contractor’s representative. (2) ‘Approved by’ should be the name, signature and Company’s name for the Contractor’s representative. (3) ‘Location’, ‘Item Name’ and ‘Tag Number’ shall be used if applicable. (4) ‘Characteristics Verified’ are the parameters checked during the inspection activity. (5) ‘Reference Document’ is the Project Specification / Code / Standard / Drawing, Procedure etc on the basis of which inspection shall be conducted. (6) ‘Acceptance Criteria’ is the tolerance, reading, value or an outcome derived from reference documents. (7) “Verifying Document’ is the record generated during inspection & Testing using approved forms / checklists. (8) “Inspection Responsibility’ is the role of Vendor / Sub Contractor , Contractor and SABIC for each inspection step. Inspection responsibility shall be ‘I’ for Inspection, ‘R’ for review, ‘S’ for Surveillance, “W1’ for 100% Witness, ‘W2’ for random witness and ‘H’ for hold. For the explanation of these inspection responsibilities refer to the ‘definitions’ part of PEI section 4.7.1 (9) Rust prevention coating should protect the material from corrosion and shall be easily removed in the field.
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 21 of 84
INSPECTION AND TEST PLAN (ITP) FOR TRAYS FOR COLUMNS
Print Name
Signature Name of Company Doc No:
EPM‐ITP‐QP‐004 Prepared By: (1)
Approved By: (2) Revision 0
SABIC App: Stage Procurement Discipline: Static Equipment PROJECT: Date:
Location: (3) Item Name (3): Tag No (3): Page:
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
1
Material Certificate
Quantity, size, heat number,material specification, mechanical properties and chemical composition etc
SES Q01-F72 Purchase order specification
Material as per project specification and by approve vendors. SES Q01-F72
Mill Test Certificates, Material Test Report
R R R
2
Material Identification
Percentage of basic alloying elements
SES Q01-T07 SES Q01-T07 clause 8 Material Certificate and detailed alloy verification map
I R R
3
Visual and Dimensional Inspection* (incl. trial assembly)
General surface condition, thickness, schedule for nozzle and fitting, markings, main dimensions, etc.
, SES Q01-T72
Clean, smooth and free from imperfections . Compliance with the applicable drawings and project specifications
Inspection Report
I W1 W1
4 Leak testing
Leak Testing criteria according to the type of tray.
SES Q01-F72, SES Q01-T72
Leakage rate as per the specification
Leak Test Report I W1 W1
NOTE: * One tray of each diameter and of each specific type shall be pre‐assembled on a solid flat level at shop.
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 22 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
7 Tray Marking Inspection
Each tray part shall be piece-marked, Tray deck sections marked with the tray number
SESQ01-F72, SES Q01-T72
Clear and traceable Inspection Report
I W1 R
Indelible non-lead paint or an approved dye shall be used for marking
8
Rust Prevention Check and Painting Inspection
Protection from rust and damage
SES Z01-G07, SESQ01-F72 Project Procedure for Equipment / Material Preservation
Protected with Rust inhibitor but shall be easily removable at site.
Painting and Preservation report
I W2 R
9 Shipping Preparation Inspection
Packaging, preservation, marking, loading and shipping instructions , Tray parts and tray hardware for different tray designs shall not be intermixed
SES Q01-F72 SES Z01-G07
Securely packed and preserved. Materials for different columns shall not be mixed
Packing Lists, Packing Inspection Reports. I W1 W2
Legend
(1) ‘Prepared by’ should be the name, signature and Company’s name for the Vendor’s/Sub Contractor’s representative. (2) ‘Approved by’ should be the name, signature and Company’s name for the Contractor’s representative. (3) ‘Location’, ‘Item Name’ and ‘Tag Number’ shall be used if applicable. (4) ‘Characteristics Verified’ are the parameters checked during the inspection activity. (5) ‘Reference Document’ is the Project Specification / Code / Standard / Drawing, Procedure etc on the basis of which inspection shall be conducted. (6) ‘Acceptance Criteria’ is the tolerance, reading, value or an outcome derived from reference documents. (7) “Verifying Document’ is the record generated during inspection & Testing using approved forms / checklists. (8) “Inspection Responsibility’ is the role of Vendor / Sub Contractor , Contractor and SABIC for each inspection step. Inspection responsibility shall be ‘I’ for Inspection, ‘R’ for review, ‘S’ for Surveillance, “W1’ for 100% Witness, ‘W2’ for random witness and ‘H’ for hold. For the explanation of these inspection responsibilities refer to the ‘definitions’ part of PEI section 4.7.1 (9) Rust prevention coating should protect the material from corrosion and shall be easily removed in the field. Austenitic stainless steel materials shall not be coated but shall be protected from ferritic contamination, chloride attack and galvanic corrosion
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 23 of 84
INSPECTION AND TEST PLAN (ITP) FOR
AIR COOLED HEAT EXCHANGERS
Print Name
Signature Name of Company Doc No:
EPM‐ITP‐QP‐005 Prepared By: (1)
Approved By: (2) Revision 0
SABIC App: Stage Procurement Discipline: Static Equipment PROJECT: Date:
Location: (3) Item Name (3): Tag No (3): Page:
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
1 Tube Bundle Assembly
1.1
Material Certificate (pressure parts)
Size, heat number material specification, nominal composition and grade, class, or type designation.
SESQ02-F02, ASME II’ Purchase order specification
Material as per specification and by approve vendors
Mill Test Certificates, Manufacturer's Test Reports
R R R
1.2
Material identification for alloy
Verification of basic alloying elements
SESQ01-T07,
SESQ01-T07 clause 8 Material as per the acceptance criteria defined in applicable specification
PMI Report
I W2 R
1.3 Welding Procedure Qualification Test (WPS/PQR)
Essential, nonessential, andsupplementary essential variables
SES W11-F01 ASME IX
WPS/PQR approved as per SES W11-F01/ASME Sec IX
WPS /PQR Register I W1* R
1.4
Welder and Welding Operator Qualification Test
Welder ability to deposit sound weld metal and welding operators ability to operate the welding equipment
ASME IX SES W11-F01
Welders and Operator Approved as per SES W11-F01/ASME Sec IX
WQT, Welder Register, Welder ID Card
I W1* R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 24 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
NOTE: * Previous records may be reviewed.
1.5
Edge preparation and Fit-up Inspection
Root gap, land zone including angle, material specification, fit up Dimension, alignment
Relevant WPS, Drawings, API 661
As per WPS, drawing and project specification
Welding Inspection Checklist
I W1 R
1.6 Inspection during welding
Interpass temperature, interpass cleaning and other essential non-essential parameters, weave width, Visual, LPT/MPT of back gauging
SES Q01- F01 Q01 T01 WPS
SES Q01- F01 Q01 T01 WPS
Welding Inspection Checklist
I W1 R
1.7 Visual Inspection of Completed Welds
Weld profile and surface discontinuities Surface defects, weld profile. Identification of weld and welders,
SES Q02-F02, Drawings
Clean and Free from weld surface discontinuities and sharp edges. SES Q01-T01 ASME Sec VIII div 1 clause UW 33 & 35 or Div
Welding Inspection Checklist
I S S
1.8
Magnetic Particle Examination or Liquid Penetrant Examination a. Edge for corner joint as per UG-93 (d) (3) b. Edge to be welded (if specified c. Back gouging and/or grinding (if any) d. Pressure Retaining welds including tube
Surface discontinuities Manufacturer approved MT / PT procedure
ASME Sec VIII div 1 mandatory Appendix 6/ ASME Sec VIII Div 2 clause 7.5.3 as applicable
NDT Report I W2 R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 25 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
to tube sheet weld joints.
1.9
Radiographic examination (Before & after PWHT)
Detect surface and internal discontinuities
ASME Sec V & VIII div 1 or 2 Manufacturer approved RT procedure
ASME Sec VIII div 1 clause UW 51 or 52 as applicable/ ASME Sec VIII Div 2 clause 7.5.3
Radiographic Test Report I R R
1.10
Post weld heat treatment (when required)
Heating /cooling Rate and soaking time. Temp Range & Duration
SES Q02-F02 Project Specification for PWHT
Heating /cooling, Soaking time as per requirements..
PWHT Chart and report I R R
1.11 Hardness Test
Brinell hardness of the weld and heat affected zone SES Q02-F02 Hardness within the
specification .Hardness Test Report I W1 R
1.12 Tube to Tube sheet Joint Inspection
Fixation, cleanliness, welding defects and tightness check
SES Q02-F02, API 661
Clean, free of welding defect and passed tube leak or tightness check
Inspection Report I W1 R
1.13
Final Visual and dimensional inspection
General surface condition, weld appearance and main dimensions.
SES Q02-F02 API 661
As per drawing and project specification
Visual and Dimensional Report
I W1 R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 26 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
1.14
Magnetic particle examination or liquid penetrant examination after PWHT (pressure retaining welds, thermocouple removal areas, removal of temporary attachment areas and arc strike ground areas)
Surface discontinuities Manufacturer Approved PT / MT Procedure
No relevant indications NDT Report I W2 R
1.15 Hydrostatic test (and Chloride Check, if required)
Equipment Calibration, Test Pressure and Duration
. SESQ02-F02 ASME VIII
No Leaks. Test Pressure Maintained
Pressure Test Report I W1 W1
2 Structural Component Refer to ITP for Structure
3 Electrical Components Refer to ITP for Electrical
4 Assembly and Run-in Test (each fan-driver combination)
Overall Performance, Vibration test, Noise test and Fan tip clearance
SES Q02-F02 API 661 As per specification
Inspection and Test Report
I W1 W2
5 Painting Inspection Drying out and Rust prevention
Surface preparation, DFT, surface defect, rust prevention and equipment preservation.
SES T01-S01 SES Z01-G07
Surface profile and DFT within lower and upper limits given in relevant specification. Free from surface irregularities. Equipment preserved (refer Note 9)
Painting and Preservation report
I W1 W1
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 27 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
6
Shipping Preparation Inspection
Certified records, packaging, nameplate data and spare parts markings, preservation, loading and shipping instructions
SES Q02-F02 SES Z01-G07 Fulfilled all requirements
Equipment Dossier, Packing Lists, Packing Inspection Reports
I W1 W2
Legend
(1) ‘Prepared by’ should be the name, signature and Company’s name for the Vendor’s/Sub Contractor’s representative. (2) ‘Approved by’ should be the name, signature and Company’s name for the Contractor’s representative. (3) ‘Location’, ‘Item Name’ and ‘Tag Number’ shall be used if applicable. (4) ‘Characteristics Verified’ are the parameters checked during the inspection activity. (5) ‘Reference Document’ is the Project Specification / Code / Standard / Drawing, Procedure etc on the basis of which inspection shall be conducted. (6) ‘Acceptance Criteria’ is the tolerance, reading, value or an outcome derived from reference documents. (7) “Verifying Document’ is the record generated during inspection & Testing using approved forms / checklists. (8) “Inspection Responsibility’ is the role of Vendor / Sub Contractor , Contractor and SABIC for each inspection step. Inspection responsibility shall be ‘I’ for Inspection, ‘R’ for review, ‘S’ for Surveillance, “W1’ for 100% Witness, ‘W2’ for random witness and ‘H’ for hold. For the explanation of these inspection responsibilities refer to the ‘definitions’ part of PEI section 4.7.1 (9) Rust prevention coating should protect the material from corrosion and shall be easily removed in the field. Austenitic stainless steel materials shall not be coated but shall be protected from ferritic contamination, chloride attack and galvanic corrosion
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 28 of 84
INSPECTION AND TEST PLAN (ITP) FOR MATERIAL AND SHOP FABRICATION STAGE OF
ATMOSPHERIC STORAGE TANKS
Print Name
Signature Name of Company Doc No:
EPM‐ITP‐QP‐006 Prepared By: (1)
Approved By: (2) Revision 0
SABIC App: Stage Procurement Discipline: Static Equipment PROJECT: Date:
Location: (3) Item Name (3): Tag No (3): Page:
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
1 Material Certificates
Size, heat number material specification, grade, class, type designation , chemical analysis and thickness.
SES Q03-T06, Purchase specification
Material as per documentation and by approve vendors
Mill Test Certificates, Manufacturer's Test Reports
R R R
2 Material Identification Verification of Alloy Material
SES Q01-T07
SES Q01-T07 clause 8 Percentages of alloying element within tolerances
PMI reports I W2 R
3 Welding Procedure Qualification Test (WPS/PQR)
Essential, nonessential, and supplementary essential variables
ASME IX, SES W11-F01
API 650 Sec. 7 SES W11-F01
WPS /PQR Log I W1* R
4
Welder’s and Welding Operator’s Performance Qualification Test
Welder ability to deposit sound weld metal and welding operators ability to operate the welding equipment
ASME IX, SES W11-F01
API 650 Sec. 7 SES W11-F01 Welder
Register I W1* R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 29 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
NOTE: * Previous records may be reviewed.
5 Welding Control Welding materials, welding specification, procedure and welder performance
SESQ03-T06 WPS
New materials and strictly control. As per relevant WPS
Batch certificate, Surveillance log sheet
I W2 / S R /S
6
Shell/Bottom/Roof Plates , Nozzles and Man ways Fabrication Edge a) Preparation and Fit-up Inspection,
Root gap, land zone, alignment, radius of shell plate. Material specification, type, thickness, rating etc.
Relevant WPS Drawing As per WPS and Drawing
Fit-up Inspection Report
I W2 R
7 Shell Plate Assembly
Peaking, banding, staggering of vertical joints, diameter, circumference and visual inspection of weld
Drawing, API620
Compliance to Drawing and project specification
Inspection Report
I W2 R
a) Bottom/ Roof
Plate assembly
Verify actual diameter, orientation of weld seam, bolt center distance and visual inspection of weld
I W2 R
b) Nozzle/
Manway on Shell and roof
Orientation, elevation, levelness, projection and straddle of flange bolt holes and visual inspection of welds
I W2 R
c) Structural Attachment
Location,elevation and visual inspection of welds I W2 R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 30 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
8 Inspection during welding
Interpass temperature, interpass cleaning and other essential non-essential parameters, weave width, Visual, LPT/MPT of back
i
API 650 Sec 5WPS
API 650 Sec 5 WPS
Welding Inspection Checklist EPM-QF-06-A006
9 Platform and Ladder fabrication and assembly
Main dimensions, general surface condition and quality of galvanized items.
Drawings, SES Q03-S20
Compliance to Drawing and project specification
Inspection Report I W2 R
10 Radiographic Examination as per API 650
Detect surface and internal discontinuities
Manufacturer approved RT procedure
API 650 Section 6.1 RT Report I R R
11 Liquid Penetrant Examination or Magnetic Particle Examination
Surface and near surface discontinuities in welds arc strike ground areas (including temporary attachment removal area)
Manufacturer Approved MT/PT Procedure
API 620
NDT Report
I W2 R
Surface and near surface discontinuities in pressure and non pressure retaining welds arc strike
12 Pneumatic Test of Reinforcing pad
Leaks around the pad both inside and outside of the shell
API 620 No Leaks Pneumatic Test Report I W1 R
13 Vacuum Box Test Leak tightness of the bottom plate welds API 620 API Section 6.6
Vacuum box Test Report I W2 R
14 Oil Leak test of shell to bottom weld joints
Leak tightness of initial weld pass on inside shell API 620 No leak thru weld seams Oil Leak test
report I W2 R
15 Final Visual and Dimensional Inspection
General surface condition and weld appearance. Plumbness, roundness and main dimensions.
Drawings, API 620
Compliance to relevant drawings and specification
Inspection Report I W1 R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 31 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
16 Hydrostatic Test
Equipment Calibration, Pressure, duration, Leak tightness, strength and deformation.
Drawings, Approved Hydrotest Procedure API 620
No leak or apparent deformation
Hydrostatic test report I W1 W1
17 Leak Test above liquid Level ( if applicable) Vacuum test or solution test API 620 No leak
Vacuum Box / Pneumatic Test Report
I W1 R
18 Rust Prevention Check and Painting Inspection
Surface preparation and Condition of Painting. Rust prevention, internal cleanliness and equipment preservation
SES T01-S01 SES Z01-G07,
Surface profile and DFT within lower and upper limits. Free from surface irregularities. Equipment adequately clean and securely preserved(refer Note 9)
Painting and Preservation report
I W1 R
19 Shipping Preparation Inspection
Certified records, packaging, nameplate data, marking of orientation. Preservation, loading and shipping instructions
SES Z01-G07
Fulfilled the requirements of relevant project specification
Equipment Dossier, Packing Lists, Packing Inspection Reports.
I W1 W2
Legend
(1) ‘Prepared by’ should be the name, signature and Company’s name for the Vendor’s/Sub Contractor’s representative. (2) ‘Approved by’ should be the name, signature and Company’s name for the Contractor’s representative. (3) ‘Location’, ‘Item Name’ and ‘Tag Number’ shall be used if applicable. (4) ‘Characteristics Verified’ are the parameters checked during the inspection activity. (5) ‘Reference Document’ is the Project Specification / Code / Standard / Drawing, Procedure etc on the basis of which inspection shall be conducted. (6) ‘Acceptance Criteria’ is the tolerance, reading, value or an outcome derived from reference documents. (7) “Verifying Document’ is the record generated during inspection & Testing using approved forms / checklists. (8) “Inspection Responsibility’ is the role of Vendor / Sub Contractor , Contractor and SABIC for each inspection step. Inspection responsibility shall be ‘I’ for Inspection, ‘R’ for review, ‘S’ for Surveillance, “W1’ for 100% Witness, ‘W2’ for random witness and ‘H’ for hold. For the explanation of these inspection responsibilities refer to the ‘definitions’ part of PEI section 4.7.1
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 32 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
(9) Rust prevention coating should protect the material from corrosion and shall be easily removed in the field. Austenitic stainless steel materials shall not be coated but shall be protected from ferritic contamination, chloride attack and galvanic corrosion
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 33 of 84
INSPECTION AND TEST PLAN (ITP) FOR MATERIAL AND PRE-FABRICATION STAGE OF
CRYOGENIC STORAGE TANKS
Print Name
Signature Name of Company Doc No:
EPM‐ITP‐QP‐007 Prepared By: (1)
Approved By: (2) Revision 0
SABIC App: Stage Procurement Discipline: Static Equipment PROJECT: Date:
Location: (3) Item Name (3): Tag No (3): Page:
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
1 Material Certificates
Material specification mechanical properties including impact testing and chemical composition etc.
API 650 Purchase Specification
API 650 Section 2 Material as per specification and by approve vendors
Mill Certificates, Manufacturer's Test Reports
W2 W2 R
2 Material Identification
Verification of basic alloying elements
SES Q01-T07
Material as per the acceptance criteria defined in applicable specification
PMI Report I W2 R
3
Welding Procedure Specification Approval
Essential, nonessential, and supplementary essential variables in accordance to PQR
SES W11-F01 ASME IX API 650 Section 7
SES W11-F01 ASME IX API 620 Clause 6.7
WPS /PQR Register I W1* R
4 Welder and Welding Operator Qualification Test
Welder ability to deposit sound weld metal and welding operators ability to operate the welding equipment
SES W11-F01 ASME IX API 650 Section 7
SES W11-F01 ASME IX API 620 clause 6.8
WQT, Welder Register, Welder ID Card
I W1* R
NOTE: * Previous records may be reviewed.
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 34 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
5 Inner Tank & Outer Tank
1. Material identification Material used to be certified
SESQ01-T07 SESQ03-T06
SESQ01-T07 clause 8
Material Certificate and detailed alloy
I W2 R
2. Edge
preparation inspection
Root gap, land zone including angle
Weld joint design as per Drawing
Weld joint design as per Drawing
Weld Map Report/ Reference
I W2 R
3. Inspection during welding
Interpass temperature, interpass cleaning and other essential non-essential parameters,
API 650 WPS
API 650 WPS
Weld Inspection Report
4. Back chip inspection
Soundness of weld metal prior to back welding
Dye Penetration Testing Procedure
Free from defect PT report I W2 R
5. Visual inspection of completed welds
Surface defects, weld profile. Identification of weld and welders,
API 650 API 650
Weld Inspection Report of weld and welders
6. Dimensional check and visual inspection
a) Shell plate
Verify peaking, banding diameter, circumference and visual inspection of weld
Drawing API 650
Within Tolerance as per API 650 5
Inspection Report I W2 R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 35 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
b) Shell stiffener Numbers and location Relevant Calculation and Drawing
As per Calculation and Drawing
Inspection Report
I W2 R
c) Suspended deck w/framing
Minimum thickness, number and design
Relevant Calculation and Drawing
As per Calculation and Drawing
Inspection Report
I W2 R
d) Nozzle, manhole
Orientation, elevation, levelness projection and stradleness of flange bolt holes ,and visual inspection of welds
Drawing APl 650
Within Tolerance as per API 650
Inspection Report I W2 R
e) Anchor strap Diameter and Thickness Relevant Calculation and Drawing
As per Calculation and Drawing
Inspection Report
I W2 R
6 Radiographic Examination
Surface and internal discontinuities
API 650 ASME V API 650 Section 6 NDT Report I R R
7
Liquid Penetrant Examination or Magnetic Particle Examination
Surface discontinuities API 650 ASME V API 650 Section 6 NDT Report I W1 R
8 Pneumatic Test of Reinforcing Plate Reinforcement pad test API 650 Leakage around
reinforcement No Leaks I W1 R
9 Post Weld Heat Treatment (if necessary)
Heating /cooling Rate. Temp Range & Duration
SES W12-F04, WPS API 650 Sec 3.7
SES W12-F04, WPS API 650 Sec 3.7
PWHT Chart and report I W2 R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 36 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
10 Rust Prevention Check and Painting Inspection
Surface preparation and Condition of Painting. Rust prevention, internal cleanliness and equipment preservation
SES T01-S01 SES Z01-G07
Surface profile and DFT within lower and upper limits. Free from surface irregularities. Equipment adequately clean and securely preserved
Painting and Preservation report
I W2 R
11 Shipping Preparation Inspection
Certified records, packaging, nameplate data, marking of orientation. Preservation, loading and shipping instructions
SES Z01-G07
Fulfilled the requirements of relevant project specification
Equipment Dossier, Packing Lists, Packing Inspection
I W1 W2
Legend
(1) ‘Prepared by’ should be the name, signature and Company’s name for the Vendor’s/Sub Contractor’s representative. (2) ‘Approved by’ should be the name, signature and Company’s name for the Contractor’s representative. (3) ‘Location’, ‘Item Name’ and ‘Tag Number’ shall be used if applicable. (4) ‘Characteristics Verified’ are the parameters checked during the inspection activity. (5) ‘Reference Document’ is the Project Specification / Code / Standard / Drawing, Procedure etc on the basis of which inspection shall be conducted. (6) ‘Acceptance Criteria’ is the tolerance, reading, value or an outcome derived from reference documents. (7) “Verifying Document’ is the record generated during inspection & Testing using approved forms / checklists. (8) “Inspection Responsibility’ is the role of Vendor / Sub Contractor , Contractor and SABIC for each inspection step. Inspection responsibility shall be ‘I’ for Inspection, ‘R’ for review, ‘S’ for Surveillance, “W1’ for 100% Witness, ‘W2’ for random witness and ‘H’ for hold. For the explanation of these inspection responsibilities refer to the ‘definitions’ part of PEI section 4.7.1 (9) Rust prevention coating should protect the material from corrosion and shall be easily removed in the field. Austenitic stainless steel materials shall not be coated but shall be protected from ferritic contamination, chloride attack and galvanic corrosion
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 37 of 84
INSPECTION AND TEST PLAN (ITP) FOR SHOP FABRICATION STAGES OF PRESSURE
STORAGE AND SPHERICAL TANKS
Print Name
Signature Name of Company Doc No:
EPM‐ITP‐QP‐008 Prepared By: (1)
Approved By: (2) Revision 0
SABIC App: Stage Procurement Discipline: Static Equipment PROJECT: Date:
Location: (3) Item Name (3): Tag No (3): Page:
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
1 Material Certificates
Material specification mechanical properties and chemical composition etc.
SESQ01-F35 SES Q01-F05 SESQ01-F08 SESQ01-T07
Material as per specification and by approve vendors
Mill Certificates, Manufacturer's Test Reports
R R R
2 Material Identification
Verification of basic alloying elements
SES Q01-T07
SES Q01-T07 clause 8 PMI Report I W2 R
3 Ultrasonic Examination Surface and subsurface discontinuities
SES Q01-T01 Manufacturer approved UT/MT
d
SES Q01- T01 clause 6.3.2 & Clause 6.3.3/6.3.4 UT Report I W1 R
4
Welding Procedure Specification Approval
Essential, nonessential, andsupplementary essential variables in accordance to PQR
SES W11-F01 ASME IX
WPS approved as per SES W11-F01 ASME IX
WPS /PQR Register I W1* R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 38 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
5 Welder and Welding Operator Qualification Test
Welder ability to deposit sound weld metal and welding operators ability to operate the welding equipment
SES W11-F01 ASME IX
Welders and Operator Approved as per SES W11-F01 ASME IX
WQT, Welder Register, Welder ID Card
I W1* R
NOTE: * Previous records may be reviewed.
6 Edge Preparation Inspection
Root gap, land zone including angle Relevant WPS As per WPS
Weld Map Report/ Reference
I W2 R
7 Back Chip Inspection Soundness of weld metal prior to back welding
Dye Penetration Testing Procedure
Free from defect PT report I W2 R
8
Post Weld Heat Treatment (if necessary)
Heating /cooling Rate. Temp Range & Duration
SES P13-C02, SES W12-F04 Relevant WPS, ASME
SES Q03- F09 PWHT Chart and report I W2 R
9 Dimensional Check and Visual Inspection
Visual inspection, minimum plate thickness, schedule for nozzle and fitting, markings, main dimensions,Edge preparation, Rolling, Joint alignment etc
SES Q01-T02 SESQ01-T06 SESQ01-F28 SESZ01-G04
As drawing and SES Q03 – F09
Traveler, drawing I W1 R
10 Pneumatic Test of Reinforcing Plate Reinforcement pad test API 650 Free from leakage around
reinforcement No Leaks I W1 R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 39 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
11 Radiographic Examination
Detect surface and internal discontinuities ASME V SES Q03- F09 NDT Report I R R
12
Liquid Penetrant Examination and/or Magnetic Particle Examination
Surface discontinuities ASME V SES Q03- F09 NDT Report I W2 R
13 Rust Prevention Check and Painting Inspection
Surface preparation and Condition of Painting. Rust prevention, internal cleanliness and equipment preservation
SES T01-S01 SES Z01-G07
Surface profile and DFT within lower and upper limits. Free from surface irregularities. Equipment adequately clean and securely preserved
Painting and Preservation report
I W2 R
14 Shipping Preparation Inspection
Certified records, packaging, nameplate data, marking of orientation. Preservation, loading and shipping instructions
SES Z01-G07
Fulfilled the requirements of relevant project specification
Equipment Dossier, Packing Lists, Packing Inspection Reports.
I W1 R
Legend
(1) ‘Prepared by’ should be the name, signature and Company’s name for the Vendor’s/Sub Contractor’s representative. (2) ‘Approved by’ should be the name, signature and Company’s name for the Contractor’s representative. (3) ‘Location’, ‘Item Name’ and ‘Tag Number’ shall be used if applicable. (4) ‘Characteristics Verified’ are the parameters checked during the inspection activity. (5) ‘Reference Document’ is the Project Specification / Code / Standard / Drawing, Procedure etc on the basis of which inspection shall be conducted. (6) ‘Acceptance Criteria’ is the tolerance, reading, value or an outcome derived from reference documents. (7) “Verifying Document’ is the record generated during inspection & Testing using approved forms / checklists. (8) “Inspection Responsibility’ is the role of Vendor / Sub Contractor , Contractor and SABIC for each inspection step. Inspection responsibility shall be ‘I’ for Inspection, ‘R’ for review, ‘S’ for Surveillance, “W1’ for 100% Witness, ‘W2’ for random witness and ‘H’ for hold. For the explanation of these inspection responsibilities refer to the ‘definitions’ part of PEI section 4.7.1 (9) Rust prevention coating should protect the material from corrosion and shall be easily removed in the field. Austenitic stainless steel materials shall not be coated but shall be protected from ferritic contamination, chloride attack and galvanic corrosion
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 40 of 84
INSPECTION AND TEST PLAN (ITP) FOR FIRED HEATERS (Incl. thermal reactor and incinerator for sulfur unit and spent caustic
incinerator)
Print Name
Signature Name of Company Doc No:
EPM‐ITP‐QP‐009 Prepared By: (1)
Approved By: (2) Revision 0
SABIC App: Stage Procurement Discipline: Static Equipment PROJECT: Date:
Location: (3) Item Name (3): Tag No (3): Page:
Sr. No
Inspection Activity Characteristic Verified (4)
Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
1 Pyrolysis Furnaces
Tube material, chemical analysis, mechanical tests , WPS and NDE inspection
SES Q04-S01, API 560, Relevant ASME Standard
Material as per specification. Manufacturing report I R R
Weld Joint Fit-up
Edge Preparation including back chipping , preheat
WPS, drawing API 560 Welding Fit up report I R R
Visual inspection of completed welds
Surface defects, weld profile. Identification of weld and welders
API 560, Pressure Design code
API 560 clause17, Pressure Design code
Welding inspection Report I R R
Positive Material Identification Chemical composition
API 560, SES Q01 – T07
API 560 clause 17.5.4, SES Q01 – T07 clause 8
PMI report
I R R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 41 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
2 Tube Coils
a) Material Certification
Material specification mechanical properties and chemical composition etc.
API 560 SES Q04- S01
SES Q04- S01 API 560
Mill Certificates, Manufacturer's Test Reports
I R R
b) Liquid penetrant examination Surface discontinuities API 560
API 560 clause 17 NDT Report I R R
c) Dimensional Check
and Visual Inspection
Main dimensions, welds and surface cleanliness, weld appearance and etc.
Manufacturer’s Drawings, SES Q04-X01
As per drawing SES Q04-X01 Inspection Report I R R
d) Radiographic examination
Surface and internal discontinuities
API 560
API 560 clause 17 NDT Report I R R
e) Hydrostatic test Equipment Calibration ,Test Pressure and Duration
API 560
API 560 clause 17No Leaks. Test Pressure Maintained
Pressure Test Report I W2 R
f) Pneumatic test Equipment Calibration ,Test Pressure and Duration
API 560
API 560 clause 17No Leaks. Test Pressure Maintained
Pneumatic Test Report I W2 R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 42 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
g) Radiographic examination
Surface and internal discontinuities
API 560 ASME V
API 560 clause 17 NDT Report I R R
3 Headers Bend and Collector
a) Material Certificate Casting-quality factors ISO 15649
Headers shall be of metallurgy equivalent to the tubes.
Mill Certificates, Manufacturer's Test Reports
I R R
b) Mechanical Test
Determining the tensileproperties.
SES Q01-T02 SES Q01-T07 ASME V ASME VIl
Mechanical test successful
Manufacturer's Test Reports I R R
c) Liquid penetrant examination Surface discontinuities ASME V As per
specification NDT Report I W1 R
d) Visual examination
Main dimensions, welds and surface cleanliness, weld appearance and etc.
API 560 As per drawing and API 560 clause 17
Inspection Report I W1 R
e) Radiographic examination
Surface and internal discontinuities
API 560 ASME V API 560 clause 17 NDT Report I R R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 43 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
f) Hydrostatic test Equipment Calibration ,Test Pressure and Duration
API 560 Relevant ASME Codes
No Leaks. Test Pressure Maintained API 560 clause 17
Pressure Test Report I W2 R
4 Piping, terminals and manifolds
a) Material Certificate Heat number material specification and grade, class, or type designation.
SESQ01-T07 API 560 ISO 13704
Materials as per specifications
Mill Certificates, Manufacturer's Test Reports I R R
b) Liquid penetrant examination
Surface discontinuities ASME V No recordable indications
NDT Report
I W1 R
c) )Visual examination
Main dimensions, welds and surface cleanliness, weld appearance and etc.
SES Q01-F28/ SES Q06-S01/ Drawings
As per drawing and no relevant indications
Inspection Report
I W1 R
d) Radiographic examination
Surface and internal discontinuities
ASME V No recordable indications
NDT Report I R R
5 Tube supports
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 44 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
a)Material Certificate
Heat number, material specification and grade, class, or type designation
API 560
For exposed radiant and shield-section tube supports, the material shall be 25Cr-12Ni or higher alloy.
Mill Certificates, Manufacturer's Test Reports
I R R
b)Liquid penetrant examination Surface discontinuities ASME V No recordable
indications NDT Report I R R
c) Visual examination
Main dimensions, welds and surface cleanliness, weld appearance and etc.
SES Q01-F28/ SES Q06-S01/ Drawings
As per drawing and no relevant indications
Inspection Report I R R
d) Radiographic examination
Surface and internal discontinuities ASME V No recordable
indications NDT Report I R R
6 Fabricated Straight Tube
a) Visual inspection (weld portion)
Main dimensions, welds and surface cleanliness, weld appearance and etc.
SES Q01-F28/ SES Q06-S01/ Drawings
As per drawing and no relevant defect
Inspection Report
I W1 W2
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 45 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
b) Liquid penetrant
examination (weld portion)
Surface discontinuities ASME V No recordable indications NDT Report I W1 R
c) Radiographic examination (weld portion)
Surface and internal discontinuities
ASME V
No recordable indications
NDT Report I R R
d) Hydrostatic test Equipment Calibration, Test Pressure and Duration
Approved Hydrotest Procedure
No Leaks. Test Pressure Maintained
Pressure Test Report M W1 W2
6 Radiant Coil Assembly (Semi-assembled)
a) Visual inspection (weld portion, Spot Inspection after installation)
Main dimensions, welds and surface cleanliness, weld appearance and etc.
SES Q01-F28/ SES Q06-S01/ Drawings
As per drawing and no relevant defects
Inspection Report I W1 W2
b) Liquid penetrant examination
Detect surface discontinuities ASME V No recordable
indications NDT Report I W1 R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 46 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
c) Radiographic examination
Detect surface and internal discontinuities A SME V No recordable
indications NDT Report I R R
d) Hydrostatic test Equipment Calibration, Test Pressure and Duration
Approved Hydrotest Procedure
No Leaks. Test Pressure Maintained
Pressure Test Report I W1 W1
7
Radiant Coil Assembly (Completed)
a) Visual inspection
Main dimensions, welds and surface cleanliness, weld appearance and etc.
SES Q01-F28/ SES Q06-S01/ Drawings
As per drawing and no relevant defects
Inspection Report I W1 W1
b) Liquid penetrant
examination (weld portion)
Surface discontinuities ASME V No recordable indications NDT Report I W1 R
c) Radiographic
examination (weld portion)
Surface and internal discontinuities ASME V No recordable
indications NDT Report I R R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 47 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
d) Pneumatic test Test Pressure and Duration
Approved Test Procedure
No Leaks. Test Pressure Maintained
Pressure Test Report I W1 W1
7
Convection Coil (Boiler Feed Water and Steam Superheater coils) and Transfer Line
a) Material certificates
Quantity, size, heat number , material specification and grade, class, or type designation.
SESQ01-T07
Material as documentation and by approve vendors
Mill Certificates, Manufacturer's Test Reports
R R R
b) Material identification for alloy
Material used to be certified SESQ01-T07 Per the
specification
Material Certificate and detailed alloy verification map
I W2 W2
c) Visual inspection and dimensional inspection
Visual inspection, minimum plate thickness, schedule for nozzle and fitting, markings, main dimensions, Edge preparation, R lli
SES Q01-T02 SESQ01-T06 SESQ01-F28 SESZ01-G04
As drawing and specification Inspection report I W1 W2
d) Magnetic particle or dye penetrant test Surface discontinuities
ASME V No recordable indications
NDT Report I W2 W2
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 48 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
e) Radiographic examination
Surface and internal discontinuities ASME V No recordable
indications NDT Report I R R
f) Post weld heat treatment (when required)
Heating /cooling Rate. Temp Range & Duration
SES P13-C02, SES W12-F04 Relevant WPS, ASME B31.3 Project Specification for PWHT
Correctly performed and temperature readings conform to the requirements requirements..
PWHT Chart and report I R* R*
g) Hardness test Brinnell hardness of the weld and heat affected zone
ASTM E 10. SES Q01-F01 Project Speciification
Hardness within specification .Hardness Test Report I W2 R
h) Hydrostatic test Test Pressure and Duration
Approved Hydrotest Procedure
No Leaks. Test Pressure Maintained
Pressure Test Report
I W1 W1
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 49 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
8 Convection Coil (LTC and HTC coils)
a) Material certificates
Quantity, size, heat number , material specification and grade, class, or type designation.
SESQ01-T07 Material as documentation and by approve vendors
Mill Certificates, Manufacturer's Test Reports R R R
b) Material
identification for alloy
Material used to be identified and certified SESQ01-T07 Conform to
specification
Material Certificate and detailed alloy verification map
I W2 W2
c) Visual inspection
and dimensional inspection
Visual inspection, minimum plate thickness, schedule fornozzle and fitting, markings, main dimensions, Ed ti
SES Q01-T02 SESQ01-T06 SESQ01-F28 SESZ01-G04
As drawing and specification Inspection report I W1 W1
d) Magnetic particle or dye penetrant test
Detect surface discontinuities ASME V No recordable
indications NDT Report I W2 W2
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 50 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
e) Radiographic examination
Detect surface and internal discontinuities ASME V No recordable
indications NDT Report I R R
f) Post weld heat
treatment (when required)
Heating /cooling Rate. Temp Range & Duration
SES P13-C02, SES W12-F04 Relevant WPS, ASME
Correctly performed and temperature readings conform to the requirements requirements..
PWHT Chart and report I R* R*
g) Hardness test Brinnell hardness of the weld and heat affected zone
ASTM E 10. SES Q01-F01
Hardness within specification .Hardness Test Report I W2 R
h) Hydrostatic test Equipment Calibration ,Test Pressure and Duration
Relevant ASME Codes
No Leaks. Test Pressure Maintained
Pressure Test Report I W1 W1
* Review of temperature chart
9 Burners
a) Visual and dimensional inspection
Main dimensions, surface cleanliness, appearance and etc.
Drawings As per drawing and no relevant indications
Inspection Report I W R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 51 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
b) Material certificates
Quantity, size, heat number , material specification and grade, class, or type designation.
SESQ01-T07
Material as documentation and by approve vendors
Mill Certificates, Manufacturer's Test Reports
R R R
10 Casting (Tube support)
a) Material certificates
Quantity, size, heat number , material specification and grade, class, or type designation.
Material Specification SES Q04-S01 API 560
Material as per Specification by approve vendors
Mill Certificates, Manufacturer's Test Reports
I R R
b) Visual and dimensional inspection
Visual inspection, minimum plate thickness, schedule for nozzle and fitting, markings, main dimensions, Edge preparation, Rolling, Joint alignment etc
Drawing SESZ01-G04
As drawing and specification
Traveler, drawing I W2 R
c) Dye Penetrant / MPT Test Surface discontinuities API 560 ;
ASME V
API 560clause 17. 3
NDT Report I W2 R
d) Radiographic examination
Detect surface and internal discontinuities
API 560 ASME V
API 560clause 17.
NDT Report I R R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 52 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
11 Refractory
Material
Selection of refractory and materials
API 560
a) fireclay brick, ASTM C 27; b) insulating firebrick, ASTM C 155;
Mill Certificates, Manufacturer's Test Reports I R R
Installation
a) Surface preparation Cleanliness of steel surfaces
API 650 Project Specification
Steel surfaces cleaned no dirt, grease, paint, loose scale or other foreign materials.
Inspection Report I R R
b) Check of attachment
and dimension for refractory anchor
Type and thickness, API 650
Project Specification
As per Project Specification, Code and Standard
Inspection Report I R R
c) Visual inspection No defects such as crack, void, cavity and gap
API 650 Project Specification
As per Project Specification, Code and Standard
Inspection Report I W1 W2
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 53 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
13 Spent Caustic Incinerator
( SES Q 05‐ S02 )
13.1 Furnace, quench
tank, scrubber and cooler
a) Material certificates
Quantity, size, heat number , material specification and grade, class, or type designation
Material Specification
Material as specification and by approve vendors
Mill Certificates, Manufacturer's Test Reports
R R R
b) Welding Procedure Specification Approval
Essential, nonessential, and supplementary essential variables in accordance to PQR
SES W11-F01 ASME IX
WPS approved as per SES W11-F01 ASME IX
WPS /PQR Register I W1* R
c) Welder and Welding
Operator Qualification Test
Welder ability to deposit sound weld metal and welding operators ability to operate the welding
SES W11-F01 ASME IX
Welders and Operator Approved
WQT, Welder Register, Welder ID Card
I W1* R
Note: *Previous records may be reviewed.
d) Material identification
Verification of Alloy Material
SES Q01-T07
SES Q01-T07Clause 8
Alloy testing reports, I W2 R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 54 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
e) Edge preparation inspection
Root gap, land zone including angle
Relevant WPS, Drawing
As per WPS, Drawing
Weld Map Report/ Reference I W2 R
f) Visual Inspection of
Completed Welds
Weld profile and welding discontinuities, Identification of weld
SES Q05-S02 API 560
SES Q05-S02 API 560
Welding Inspection report dentification of weld and welders
g) Dimensional and visual inspection
Visual inspection, minimum plate thickness, schedule for nozzle and fitting,
SES Q01-T02 SESQ01-T06 SESQ01-F28 SESZ01-G04
As drawing and specification
Traveler, drawing
I W1 W1
h) Dye penetrant or
magnetic particle examination
Detect surface discontinuities
ASME V SES Q05-S02 API 560
NDT Report
I W1 W1
i) Pneumatic leak test Equipment Calibration ,Test Pressure and Duration
Relevant ASME Codes
No Leaks. Test Pressure Maintained
Pressure Test Report
I W1 W1
j) Hydrostatic test
Equipment Calibration ,Test Pressure and Duration
Relevant ASME Codes
No Leaks. Test Pressure Maintained
Pressure Test Report
I W1 W1
13.2 Burner
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 55 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
a) Material certificates Heat number, material specification and grade, class, or type designation.
API 560
The materials used shall be chosen for strength, as well as temperature- and corrosion-resistance, for the anticipated service conditions.vendors
Mill Certificates, Manufacturer's Test Reports
R R R
b) Dimensional and visual inspection
Main dimensions, surface cleanliness, appearance and etc.
API 560 Project Specification and Drawings
As per drawing and no relevant indications
Inspection Report I W1 W2
c) Capacity check Heat release
API 560 Project Specification and Drawings
As per Specification, Code and Standard
Inspection Report I W1 W1
13.3. Casting (Tube support and press. parts)
a) Material certificates
Quantity, size, heat number , material specification and grade, class, or type designation.
SESQ01-T07 Material as documentation and by approve vendors
Mill Certificates, Manufacturer's Test Reports
R R R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 56 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
b) Visual and dimensional inspection
Surface defect and main dimensions,
SES Q01-T02 SESQ01-T06SESQ01-F28SESZ01-G04
As drawing and specification
Inspection Report I W2 R
c) Dye penetrant test (press. parts) Surface discontinuities ASME V
No recordable indications As per Material / Welding specification
NDT Report I W2 R
d) Radiographic
examination (press. Parts)
Surface and internal discontinuities ASME V
No recordable indications As per Material / Welding specification
NDT Report I R R
13.4 Refractory (shop installed)
Refer to Refractory ITP
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 57 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
14 Rust Prevention Check and Painting Inspection
Surface preparation and Condition of Painting. Rust prevention, internal cleanliness and equipment preservation
SES T01-S01 SES Z01-G07
Surface profile and DFT within lower and upper limits. Free from surface irregularities. Equipment adequately clean and securely preserved
Painting and Preservation report
I W2 R
15 Shipping Preparation Inspection
Certified records, packaging, nameplate data, marking of orientation. Preservation, loading and shipping instructions
SES Z01-G07
Fulfilled the requirements of relevant project specification
Equipment Dossier, Packing Lists, Packing Inspection Reports.
I W1 W2
Legend
(1) ‘Prepared by’ should be the name, signature and Company’s name for the Vendor’s/Sub Contractor’s representative. (2) ‘Approved by’ should be the name, signature and Company’s name for the Contractor’s representative. (3) ‘Location’, ‘Item Name’ and ‘Tag Number’ shall be used if applicable. (4) ‘Characteristics Verified’ are the parameters checked during the inspection activity. (5) ‘Reference Document’ is the Project Specification / Code / Standard / Drawing, Procedure etc on the basis of which inspection shall be conducted. (6) ‘Acceptance Criteria’ is the tolerance, reading, value or an outcome derived from reference documents. (7) “Verifying Document’ is the record generated during inspection & Testing using approved forms / checklists. (8) “Inspection Responsibility’ is the role of Vendor / Sub Contractor , Contractor and SABIC for each inspection step. Inspection responsibility shall be ‘I’ for Inspection, ‘R’ for review, ‘S’ for Surveillance, “W1’ for 100% Witness, ‘W2’ for random witness and ‘H’ for hold. For the explanation of these inspection responsibilities refer to the ‘definitions’ part of PEI section 4.7.1
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 58 of 84
INSPECTION AND TEST PLAN (ITP) FOR
STEAM BOILERS & AUXILIARIES
Print Name
Signature Name of Company Doc No: EPM‐ITP‐QP‐010
Prepared By: (1)
Approved By: (2) Revision 0
SABIC App: Stage Procurement Disciplin Static Equipment PROJECT: Date:
Location Item Name (3): Tag No (3): Page:
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
1 Materials
a) Material
Certificate
Material specification, classification, grade, rating type, marking etc.
SES Q06-S01 ASME1 ASME SA192 Relevant material specification
Material as per specification and by approved vendors. Electric resistance welded tubes shall be ASME SA178 Grade A or SA226
Mill Certificates, Manufacturer's Test Reports
R R R
b) Material identification Verification of alloy material SES Q01-T07 SES Q01-T07 clause 8 Material
Certificate I R R
c) Welding Procedure Specification Approval
Essential, nonessential, and supplementary essential variables in accordance to PQR
SES W11-F01 ASME IX
WPS approved in accordance with SES W11-F01 ASME IX
WPS /PQR Register I W1* R
d) Welder and Welding Operator Qualification Test
Welder ability to deposit sound weld metal and welding operators ability to operate the welding equipment
SES W11-F01 ASME IX
Welders and Operator Approved in accordance with SES W11-F01 ASME IX
WQT, Welder Register, Welder ID Card
I W1* R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 59 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
Note : * Previous record may be reviewed.
3
Steam and Water Drums
Merge components having similar inspection
a) Edge
preparation and fit-up
Root gap, land zone including angle, staggering of long seam, circumference, ovality and etc.
Drawings, WPS As per Drawings Inspection Report I W2 R
b) Back chipping inspection
Depth of gouged groove and surface discontinuities
Drawings/ manufacturer PT procedure
As per Drawing and no defect
PT Report I W2 R
c) Visual Inspection of Completed Welds
Weld profile and welding discontinuities, Identification of weld and welders
As per relevant ASME code
SES Q06-S01 As per relevant ASME code
Welding Inspection report dentification
d) Radiographic examination
Detect surface and internal discontinuities
Manufacturer RT Procedure as per ASME Sec V
SES Q06-S01 RT Report I R R
e) Post weld heat treatment
Heating/Cooling rate, Holding time and temperature range.
ASME Sec. I
PWHT variables within the range as per SES Q06-S01 / As per relevant ASME code
PWHT Chart and report I R R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 60 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
f) Mechanical
test of welded joint
Hardness SES Q01-F01 Not exceed the maximum hardness limit
Hardness Report I R R
g) Hydrostatic test Test Pressure and Duration SES Q06-S01
SES Q06-S01
Pressure Test Report I H H
h) Dimensional check and Visual inspection
Main dimensions, welds and surface cleanliness, weld appearance and etc.
SES Q01-F28/ SES Q06-S01/ SES Q01-D15 Drawings
SES Q06-S01
Inspection Report I W1 W2
i) Magnetic particle examination
Detect surface and near surface discontinuities
ASME V and Manufacturer MT procedure
SES Q06-S01
MT Report
I W2 R
4
Boiler Tube
a) Visual inspection and dimension check
Main dimensions, welds and surface cleanliness, weld appearance and etc.
SES Q01-F28/ SES Q06-S01/ Drawings
As per drawing and no relevant indications
Inspection Report I W2 R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 61 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
b) Magnetic
particle examination
Surface and near surface discontinuities
ASME V and Manufacturer MT procedure
SES Q06-S01 MT Report I R R
c) Radiographic examination
Surface and internal discontinuities
ASME V and Manufacturer RT Procedure
SES Q06-S01 RT Report I R R
d) Penetrant test for welding of tube attachments to tube.
Surface discontinuities ASME V and Manufacturer PT Procedure
SES Q06-S01 PT Report I W1 R
5 Furnace Wall Tube (Panel)
a) Dimensional
and Visual Inspection
Main dimensions, welds and surface cleanliness, weld appearance and etc.
Drawings, SES Q01-F28, SES Q06-S01
SES Q06-S01
Inspection Report I W2 R
b) Penetrant test to weld parts between tubes and tube attachments
Surface discontinuities ASME V and Manufacturer PT Procedure
SES Q06-S01 PT Report I W1 R
6 Furnace Wall Header
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 62 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
a) Edge preparation and Fit-up for butt welded joints
Root gap, land zone including angle, alignment and etc.
Drawings and Relevant WPS As per Drawings and WPS Inspection
Report I W2 R
b) Visual Inspection
of Completed Welds
Weld profile and welding discontinuities, Identification of weld and welders
SES Q06-S01 As per relevant ASME code
Welding Inspection Report
c) Postweld heat
treatment (if required)
Heating/Cooling rate, Holding time and temperature range.
ASME Sec. I As per relevant ASME code
SES Q06-S01
PWHT Chart and report I R R
d) Dimension and
Visual Inspection (after PWHT)
Main dimensions, welds and surface cleanliness, weld appearance and etc.
SES Q01-F28/ SES Q06-S01
As per drawing and no relevant i defect
Inspection Report I W1 R
e) Radiographic examination
Surface and internal discontinuities
ASME V and manufacturer RT procedure
SES Q06-S01 RT Report I R R
7 Saturated Steam Connecting Pipe
a) Edge Preparation & Fit up (visual Inspection)
Root gap, land zone including angle, alignment and etc.
Drawings and Relevant WPS As per drawing and WPS Inspection
Report I W2 R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 63 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
b) Visual Inspection of completed welds
Weld profile and welding discontinuities, Identification of weld and welders
SES Q06-S01 As per relevant ASME code
SES Q06-S01 As per relevant ASME code
Welding Inspection Report
I W2 R
c) Magnetic
Particle Examination
Surface and subsurface discontinuities
ASME V and Manufacturer MT procedure
SES Q06-S01 MT Report I W R
d) Radiographic Examination
Surface and internal discontinuities
ASME V and manufacturer RT procedure
SES Q06-S01 RT Report I R R
e) Dimension &
Visual Examination
Main dimensions, welds and surface cleanliness, weld appearance and etc.
Drawings, SES Q01-F28/ SES Q06-S01
As per drawing and no relevant indications
Inspection Report I W2 R
8 Superheater header
a) Edge Preparation & Fit up (visual Inspection)
Root gap, land zone including angle, alignment and etc.
Drawings and Relevant WPS As per drawing and WPS Inspection
Report I W2 R
b) Visual Inspection of completed welds
Weld profile and welding discontinuities, Identification of weld and welders
SES Q06-S01 As per relevant ASME code
SES Q06-S01 As per relevant ASME code
Welding Inspection Report
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 64 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
c) Magnetic
Particle Examination
Surface and near surface discontinuities
ASME V, SES Q06-S01 and Manufacturer MT procedure
SES Q06-S01 As per relevant ASME code
MT Report I W1 R
d) Radiographic examination
Surface and internal discontinuities
ASME V, and manufacturer RT procedure
As per relevant ASME code
RT Report I R R
e) Post Weld Heat Treatment
Heating/Cooling rate, Holding time and temperature.
ASME Sec. I
PWHT variables within the range.
PWHT Chart and report I R R
f) Dimension & Visual Inspection (after PWHT)
All main dimensions, surface condition
Drawings/ SES Q01-F28/ SES Q06-S01
As per drawing and significant deformation
Inspection Report I W1 R
9 Superheater tube
a) Dimensional
and Visual Inspection
Main dimensions, welds and surface cleanliness, weld appearance and etc.
Drawings/ SES Q01-F28/ SES Q06-S01
As per drawing and no relevant indications
Inspection Report I W2 R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 65 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
b) Penetrant Test of welding on Tubes to Tube attachments
Surface discontinuities
ASME V ; relevant ASME code and Manufacturer PT
SES Q06-S01 As per relevant ASME code PT Report I W R
c) Radiographic examination
Surface and internal discontinuities
ASME V , and manufacturer RT procedure
As per relevant ASME code
RT Report I R R
10 Desuperheater
a) Edge
preparation and fit-up (Visual Inspection)
Root gap, land zone including angle, alignment and etc.
Drawings As per drawing Inspection report I W2 R
b) Visual Inspection of Completed welds
Surface defects, weld profile. Identification of weld and welders
SES Q06 – S01 Relevant ASME code
SES Q06-S01 As per relevant ASME code
Inspection report l W1 R
c) Magnetic
Particle examination
Surface and near surface discontinuities
ASME V and Manufacturer MT procedure
SES Q06-S01 As per relevant ASME code N l t i di ti
MT Report I W1 R
d) Radiographic examination
Surface and internal discontinuities
ASME V and manufacturer RT procedure
SES Q06-S01 As per relevant ASME code SES Q06- X03
RT Report I R R
e) Post Weld Heat Treatment
Heating/Cooling rate, Holding time and temperature range.
ASME Sec. I As per relevant ASME code SES Q06- X03
PWHT Chart and report I R R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 66 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
f) Dimension & Visual Inspection (after PWHT)
Overall length, straightness, surface condition and etc.
Drawings/ SES-Q01-F28/ SES- Q06-S01
As per drawing and no significant deformation
Inspection report
I W1 R
11 Economizer header
a) Edge Preparation and Fit-up (Visual Inspection)
Root gap, land zone including angle, alignment etc. Drawings As per
Drawings Inspection report I W2 R
b) Visual Inspection of Completed welds
Surface defects, weld profile. Identification of weld and welders
SES Q06-S01 relevant ASME code
SES Q06-S01 relevant ASME code
Weld Inspection report l W1 R
c) Magnetic
Particle Examination
Surface and near surface discontinuities
ASME V and Manufacturer MT procedure
As per relevant ASME code
MT Report I W1 R
d) Radiographic examination Welding defect and discontinuities
ASME V and Manufacturer RT Procedure
As per relevant ASME code
RT Report I R R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 67 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
e) Post Weld Heat Treatment
Heating/Cooling rate, Holding time and temperature range. ASME Sec. I
PWHT variables within the range.
PWHT Chart and report I R R
f) Dimensional &
Visual Inspection
Main dimensions, welds and surface cleanliness, weld appearance and etc.
Drawings/ SES Q01-F28/ SES Q06-S01
As per drawing and no relevant indications
Inspection Report I W1 R
12 Economizer Tube
Dimensional & Visual Inspection
Overall length, Straightness, surface condition etc.
Drawings As per drawings
Inspection report
I W2 R
1 3 Boiler External Piping
a) Edge Preparation & Fit up (visual Inspection)
Root gap, land zone including angle, alignment etc.
Drawings and relevant WPS
As per drawings and WPS
Inspection report
I W2 R
b) Visual Inspection of Completed Welds
Surface defects, weld profile. Identification of weld and welders
relevant ASME code
relevant ASME code
Weld Inspection report
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 68 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
c) Radiographic examination Welding defect and discontinuities
ASME V Manufacturer RT Procedure
As per relevant ASME code
RT Report R R R
d) Magnetic
Particle Examination
Detect surface and near surface discontinuities
ASME V and Manufacturer MT procedure
SES Q06-S01 As per relevant ASME code N l t
MT Report I W1 R
e) Post Weld Heat Treatment
Heating/Cooling rate, holding time and temperature range. ASME B31.1
PWHT variables within the range.
PWHT Chart and report I R R
f) Dimensional & Visual Inspection (after PWHT)
All main dimensions, straightness, surface condition etc.
Drawings, Relevant project specification
Dimensions with in tolerance and no surface irregularities
Inspection Report I W1 R
14 Assembled boiler
a) Hydrostatic test Equipment Calibration, Test Pressure and Duration ASME Sec. I
No Leaks. Test Pressure Maintained
Pressure Test Report I H H
b) Pneumatic leak
test for welded wall enclosure
Equipment Calibration, Test Pressure and Duration ASME Sec. I
No Leaks. Test Pressure Maintained
Pneumatic Test Report I W1 W1
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 69 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
c) Visual Inspection (Including internal inspection of furnace)
All main dimensions, location of nozzles and other attachments. Position of supporting, hanging, fixing devices. Condition of nozzle ends, fin tubes, etc.
Drawings/ SES Q01-F28/ SES Q06-S01
As per drawings and project specifications
Inspection Report I W1 W1
d) Structural steel
(incl. grating and ladder)
Refer to ITP for Structural Steel
e) Burners and
Burner Management
Visual and Dimension check
Burners, pilots, igniters, burner piping, valves, fittings, supports, and combustion control
SES Q06-S01Drawing
As per drawing and no relevant indications
Inspection Report I R R
f) Forced draft fan
Material Certificate Material specification and grade, class, or type designation.
SESQ01-F35SES Q01-F05SESQ01-F08SESQ01-T07
Material as documentation and by approve vendors
Mill Certificates, Manufacturer's Test Reports
R R R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 70 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
Visual and dimension check
All main dimensions including Type, Speed SES G11-S02
Centrifugal type, constant speed
Inspection Report I R R
g) Rotor Assembly Balancing API 673
Statically and dynamically balanced
Inspection Report I R R
h) Vibration Monitoring
Probe, signal conditioners, monitors and interconnecting wiring
SES G19-S01.
As per specificatin
Inspection Report
I W1 W1
i) Ducts (Air and gas) and stack To check with Construction ITP
j) Safety Valve Refer to Instrumentation ITP
15 Chemical Storage Tank
a) Hydrostatic Test Equipment Calibration, Test Pressure and Duration
ASMEVIII
No Leaks. Test Pressure Maintained
Pressure Test Report I H R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 71 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
b) Dimensional & visual inspection
Main dimensions, surface cleanliness, appearance and etc.
Drawings As per drawing and no relevant indications
Inspection Report
I W1 R
16 Chemical feeder and Sampling cooler
a) Dimensional & visual inspection
Main dimensions, surface cleanliness, appearance and t
Drawings As per drawing and
l t
Inspection Report I R R
b) Hydrostatic test of pump
Equipment Calibration, Test Pressure and Duration
ASMEVIII
No Leaks. Test Pressure Maintained
Pressure Test Report
I R R
17 Deareator Refer to ITP for Carbon Steel and pressure Vessel
18 Soot blower
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 72 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
Material Certificate
Quantity, size, heat number , material specification and grade, class, or type designation.
SESQ01-F35 SES Q01-F05 SESQ01-F08 SESQ01-T07
Material as documentation and by approve vendors
Mill Certificates, Manufacturer's Test Reports
R R R
Hydrostatic test
Equipment Calibration, Test Pressure and Duration
ASMEVIII
No Leaks. Test Pressure Maintained
Pressure Test Report
R R R
Dimension check and visual inspection
Main dimensions, surface cleanliness, appearance and etc.
Drawings As per drawing and no relevant indications
Inspection Report
I W2 R
19 Soot blower control panel Refer to ITP for Control System
20 Flash tank and Blow tank
Refer to ITP for Carbon Steel and pressure Vessel
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 73 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
21 Rust Prevention Check and Painting Inspection
Surface preparation and Condition of Painting. Rust prevention, internal cleanliness and equipment preservation
SES T01-S01 SES Z01-G07
Surface profile and DFT within lower and upper limits. Free from surface
Painting and Preservation report
I W2 R
22
Shipping Preparation Inspection
Certified records, packaging, nameplate data, marking of orientation. Preservation, loading and shipping instructions
SES Z01-G07
Fulfilled the requirements of relevant project specification
Equipment Dossier, Packing Lists, Packing Inspection
I W1 W2
Legend
(1) ‘Prepared by’ should be the name, signature and Company’s name for the Vendor’s/Sub Contractor’s representative. (2) ‘Approved by’ should be the name, signature and Company’s name for the Contractor’s representative. (3) ‘Location’, ‘Item Name’ and ‘Tag Number’ shall be used if applicable. (4) ‘Characteristics Verified’ are the parameters checked during the inspection activity. (5) ‘Reference Document’ is the Project Specification / Code / Standard / Drawing, Procedure etc on the basis of which inspection shall be conducted. (6) ‘Acceptance Criteria’ is the tolerance, reading, value or an outcome derived from reference documents. (7) “Verifying Document’ is the record generated during inspection & Testing using approved forms / checklists. (8) “Inspection Responsibility’ is the role of Vendor / Sub Contractor , Contractor and SABIC for each inspection step. Inspection responsibility shall be ‘I’ for Inspection, ‘R’ for review, ‘S’ for Surveillance, “W1’ for 100% Witness, ‘W2’ for random witness and ‘H’ for hold. For the explanation of these inspection responsibilities refer to the ‘definitions’ part of PEI section 4.7.1
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 74 of 84
INSPECTION AND TEST PLAN (ITP) FOR INSTRUMENT AIR DRYER
Print Name
Signature Name of Company Doc No:
EPM‐ITP‐QP‐011 Prepared By: (1)
Approved By: (2) Revision 0
SABIC App: Stage Procurement Discipline: Static Equipment PROJECT: Date:
Location: (3) Item Name (3): Tag No (3): Page:
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
1 Material certificate (Pressure parts)
Quantity, size, heat number ,material specification and grade, class, or type designation.
SES Q01-F35SES Q01-F05SESQ01-F08SESQ01-T07
Material as documentation and by approve vendors
Mill Certificates, Manufacturer's Test Reports
R R R
2 Hydrostatic Test
Equipment Calibration, Test Pressure and Duration
SES Q01-T01 SES Q01-F07SES Q01-T02ASMEVIII
No Leaks. Test Pressure Maintained
Pressure Test Report I W1 W1
3 Operation test including sequence test Functional and operational Project
Specification Fulfill the specification Inspection records I W1 W1
4 Dimensional and visual inspection
Visual inspection, minimum plate thickness, schedule fornozzle and fitting, markings, main dimensions, Edge preparation, Rolling, Joint alignment etc
SES Q01-T02 SESQ01-T06SESQ01-F28SESZ01-G04
As per drawing and specification
Traveler, drawing I W1 W1
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 75 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
5 Rust Prevention Check and Painting Inspection
Surface preparation and Condition of Painting. Rust prevention, internal cleanliness and equipment preservation
SES T01-S01 SES Z01-G07
Surface profile and DFT within lower and upper limits. Free from
f
Painting and Preservation report I W2 R
6 Shipping Preparation Inspection
Certified records, packaging, nameplate data, marking of orientation. Preservation, loading and shipping instructions
SES Z01-G07
Fulfilled the requirements of relevant project specification
Equipment Dossier, Packing Lists, Packing Inspection Reports.
I W1 W2
Legend
(1) ‘Prepared by’ should be the name, signature and Company’s name for the Vendor’s/Sub Contractor’s representative. (2) ‘Approved by’ should be the name, signature and Company’s name for the Contractor’s representative. (3) ‘Location’, ‘Item Name’ and ‘Tag Number’ shall be used if applicable. (4) ‘Characteristics Verified’ are the parameters checked during the inspection activity. (5) ‘Reference Document’ is the Project Specification / Code / Standard / Drawing, Procedure etc on the basis of which inspection shall be conducted. (6) ‘Acceptance Criteria’ is the tolerance, reading, value or an outcome derived from reference documents. (7) “Verifying Document’ is the record generated during inspection & Testing using approved forms / checklists. (8) “Inspection Responsibility’ is the role of Vendor / Sub Contractor , Contractor and SABIC for each inspection step. Inspection responsibility shall be ‘I’ for Inspection, ‘R’ for review, ‘S’ for Surveillance, “W1’ for 100% Witness, ‘W2’ for random witness and ‘H’ for hold. For the explanation of these inspection responsibilities refer to the ‘definitions’ part of PEI section 4.7.1
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 76 of 84
INSPECTION AND TEST PLAN (ITP) FOR FLARE STACK
Print Name
Signature Name of Company Doc No:
EPM‐ITP‐QP‐012 Prepared By: (1)
Approved By: (2) Revision 0
SABIC App: Stage Procurement Discipline: Static Equipment PROJECT: Date:
Location: (3) Item Name (3): Tag No (3): Page:
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
1 Flare tip and molecular seal
a) Material certificates Heat number, material specification and grade, class, or type designation.
SESQ01-F35SES Q01-F05SESQ01-F08SESQ01-T07SES Q05-X01
Material as documentation and by approve vendors
Mill Certificates, Manufacturer's Test Reports
I R R
b) Visual and dimensional
Main dimensions, surface cleanliness, appearance and etc.
Drawings
As per drawing and no relevant indications
Inspection Report I W1 R
2 Pilot burner and pilot mixer
a) Material certificates Heat number, material specification and grade, class, or type designation.
SESQ01-F35SES Q01-F05SESQ01-F08SESQ01-T07SES Q05-X01
Material as documentation and by approve vendors
Mill Certificates, Manufacturer's Test Reports
I R R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 77 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
b) Visual and dimensional
Main dimensions, surface cleanliness, appearance and etc.
API 560, Project Specification and Drawings
As per drawing and no relevant indications
Inspection Report I W1 R
3 Ignition panel
Visual and dimensional
Main dimensions, surface cleanliness, appearance and etc.
Drawings As per drawing and no relevant indications
Inspection Report
I R R
Ignition test I W1 R
4 Rust Prevention Check and Painting Inspection
Surface preparation and Condition of Painting. Rust prevention, internal cleanliness and equipment preservation
SES T01-S01 SES Z01-G07
Surface profile and DFT within lower and upper limits. Free from surface
Painting and Preservation report
I W2 R
5
Shipping Preparation Inspection
Certified records, packaging, nameplate data, marking of orientation. Preservation, loading and shipping instructions
SES Z01-G07
Fulfilled the requirements of relevant project specification
Equipment Dossier, Packing Lists, Packing Inspection Reports.
I W1 W2
Note : ITPs for hoists if any, structural steel, piping, drums, electrical & instrumentation shall be prepared separately.
Legend
(1) ‘Prepared by’ should be the name, signature and Company’s name for the Vendor’s/Sub Contractor’s representative. (2) ‘Approved by’ should be the name, signature and Company’s name for the Contractor’s representative. (3) ‘Location’, ‘Item Name’ and ‘Tag Number’ shall be used if applicable.
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 78 of 84
(4) ‘Characteristics Verified’ are the parameters checked during the inspection activity (5) ‘Reference Document’ is the Project Specification / Code / Standard / Drawing, Procedure etc on the basis of which inspection shall be conducted. (6) ‘Acceptance Criteria’ is the tolerance, reading, value or an outcome derived from reference documents. (7) “Verifying Document’ is the record generated during inspection & Testing using approved forms / checklists. (8) “Inspection Responsibility’ is the role of Vendor / Sub Contractor , Contractor and SABIC for each inspection step. Inspection responsibility shall be ‘I’ for Inspection, ‘R’ for review, ‘S’ for Surveillance, “W1’ for 100% Witness, ‘W2’ for random witness and ‘H’ for hold. For the explanation of these inspection responsibilities refer to the ‘definitions’ part of PEI section 4.7.1 (9) Rust prevention coating should protect the material from corrosion and shall be easily removed in the field. Austenitic stainless steel materials shall not be coated but shall be protected from ferritic contamination, chloride attack and galvanic corrosion
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 79 of 84
INSPECTION AND TEST PLAN (ITP) FOR WATER AND WASTE WATER TREATING
Print Name
Signature Name of Company Doc No:
EPM‐ITP‐QP‐013 Prepared By: (1)
Approved By: (2) Revision 0
SABIC App: Stage Procurement Discipline: Static Equipment PROJECT: Date:
Location: (3) Item Name (3): Tag No (3): Page:
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
1 *Equipment and Materials as Noted Below
Note: * Vessel, Drum, Heat Exchanger, Rotating Machineries, Electrolytic Chlorinate, Structural Steel, Cooling Tower, Ejector, Piping Material.
a) Material certificate
(for applicable pressure vessel)
Quantity, size, heat number , material specification and grade, class, or type
SESQ01-F35SES Q01-F05SESQ01-F08SESQ01 T07
Material as documentation and by approve
Mill Certificates, Manufacturer's Test Reports
R R R
b) Hydrostatic test
‐ Vessel, drum Equipment Calibration, Test Pressure and Duration
SES Q01-T01 SES Q01-F07SES Q01-T02
No Leaks. Test Pressure
Pressure Test Report I W1 R
‐ Prefabricated pipe
Equipment Calibration, Test Pressure and Duration
SES Q01-T01 SES Q01-F07SES Q01-T02ASMEVIII
No Leaks. Test Pressure Maintained
Pressure Test Report
I R R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 80 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
c) Dimensional and visual inspection
Visual inspection, minimum plate thickness, schedule for nozzle and fitting, markings, main dimensions, Edge preparation, Rolling, Joint alignment etc
SES Q01-T02 SESQ01-T06SESQ01-F28SESZ01-G04
As drawing and specification
Traveler, drawing
I W1 R
d) Running test for rotating machineries Refer to ITP for Rotating Machineries
2 Lining Work Pin hole test, Thickness Project Specification
As per Project Specification
Inspection Report I W2 R
3 Instruments Refer to ITP for “Instruments & Materials”
4 Electric Motor (Below 150KW) Refer to ITP for “Electric Motor (below 150KW).
5 Rust prevention check and painting inspection
Condition of Painting, Rust prevention and equipment preservation
SES Z01-G07, Project Procedure for Equipment / Material Preservation
Equipment preserved
Painting and Preservation report
I W2 R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 81 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
6 Shipping preparation inspection
Certified records,,proper packaging, preservation, loading and shipping instructions
SES Q01-F07 SESQ01-G01.SESQ01-T06 SES Q01-D20
Fulfilled all requirements
Packing Lists, Packing Inspection Reports
I W1 W2
Legend
(1) ‘Prepared by’ should be the name, signature and Company’s name for the Vendor’s/Sub Contractor’s representative. (2) ‘Approved by’ should be the name, signature and Company’s name for the Contractor’s representative. (3) ‘Location’, ‘Item Name’ and ‘Tag Number’ shall be used if applicable. (4) ‘Characteristics Verified’ are the parameters checked during the inspection activity. (5) ‘Reference Document’ is the Project Specification / Code / Standard / Drawing, Procedure etc on the basis of which inspection shall be conducted. (6) ‘Acceptance Criteria’ is the tolerance, reading, value or an outcome derived from reference documents. (7) “Verifying Document’ is the record generated during inspection & Testing using approved forms / checklists. (8) “Inspection Responsibility’ is the role of Vendor / Sub Contractor , Contractor and SABIC for each inspection step. Inspection responsibility shall be ‘I’ for Inspection, ‘R’ for review, ‘S’ for Surveillance, “W1’ for 100% Witness, ‘W2’ for random witness and ‘H’ for hold. For the explanation of these inspection responsibilities refer to the ‘definitions’ part of PEI section 4.7.1 (9) Rust prevention coating should protect the material from corrosion and shall be easily removed in the field. Austenitic stainless steel materials shall not be coated but shall be protected from ferritic contamination, chloride attack and galvanic corrosion.
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 5 of 84
INSPECTION AND TEST PLAN (ITP) FOR EQUIPMENT FOR API SEPARATOR
Print Name
Signature Name of Company Doc No:
EPM‐ITP‐QP‐014 Prepared By: (1)
Approved By: (2) Revision 0
SABIC App: Stage Procurement Discipline: Static Equipment PROJECT: Date:
Location: (3) Item Name (3): Tag No (3): Page:
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
1 Dimensional and visual inspection
Visual inspection, minimum plate thickness, schedule for nozzle and fitting, markings, main dimensions,
SES Q01-T02 SESQ01-T06SESQ01-F28SESZ01-G04
As drawing and specification
Inspection report I W1 W1
2 Operation test Functional check
Project Specification, Code and Standard
As per specification
Inspection report I W1 W1
3 Rust Prevention Check and Painting Inspection
Surface preparation and Condition of Painting. Rust prevention, internal cleanliness and equipment preservation
SES T01-S01 SES Z01-G07
Surface profile and DFT within lower and upper limits. Free from surface irregularities.
Painting and Preservation report
I W2 R
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 6 of 84
Sr. No
Inspection Activity Characteristic Verified (4) Reference Document (5)
Acceptance Criteria (6)
Verifying Document (7)
Inspection Responsibility
Vendor
Contr
SABIC
Remarks
4
Shipping Preparation Inspection
Certified records, packaging, nameplate data, marking of orientation. Preservation, loading and shipping instructions
SES Z01-G07
Fulfilled the requirements of relevant project specification
Equipment Dossier, Packing Lists, Packing Inspection Reports.
I W1 R
Legend
(1) ‘Prepared by’ should be the name, signature and Company’s name for the Vendor’s/Sub Contractor’s representative. (2) ‘Approved by’ should be the name, signature and Company’s name for the Contractor’s representative. (3) ‘Location’, ‘Item Name’ and ‘Tag Number’ shall be used if applicable. (4) ‘Characteristics Verified’ are the parameters checked during the inspection activity. (5) ‘Reference Document’ is the Project Specification / Code / Standard / Drawing, Procedure etc on the basis of which inspection shall be conducted. (6) ‘Acceptance Criteria’ is the tolerance, reading, value or an outcome derived from reference documents. (7) “Verifying Document’ is the record generated during inspection & Testing using approved forms / checklists. (8) “Inspection Responsibility’ is the role of Vendor / Sub Contractor , Contractor and SABIC for each inspection step. Inspection responsibility shall be ‘I’ for Inspection, ‘R’ for review, ‘S’ for Surveillance,
“W1’ for 100% Witness, ‘W2’ for random witness and ‘H’ for hold. For the explanation of these inspection responsibilities refer to the ‘definitions’ part of PEI section 4.7.1 (9) Rust prevention coating should protect the material from corrosion and shall be easily removed in the field. Austenitic stainless steel materials shall not be coated but shall be protected from ferritic
contamination, chloride attack and galvanic corrosion
ITB FOR PROJECT NAME PART II PROJECT SPECIFICATIONS
SECTION 4 ‐ PROJECT EXECUTION INSTRUCTIONS 4.7 QUALITY ASSURANCE & QUALITY CONTROL
4.7.2 INSPECTION & TESTING
Sub Sec. 4.7.2
Rev. No.
Rev. Date Mar 2010
Page 5 of 84