07 0071 Unswhousing Ea Appsbcacompliance

Embed Size (px)

Citation preview

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    1/38

    13 June 2007

    Our Ref: J27088A-1 JS

    Watpac NSW Pty Ltd

    PO Box 6688

    BAULKHAM HILLS NSW 2153

    Fax: 9899 7681

    Attention: Mr. Darren Skinner

    Dear Sir,

    Re: University of New South Wales

    Student Accommodation BCA Compliance Report

    Please find enclosed our BCA Compliance Report prepared in respect of the proposed

    design contained within the architectural documentation provided.

    In reviewing the content of this Report, particular attention is drawn to the content of

    Parts 3 and 4, as:

    Part 3 summarizes the compliance status of the proposed design in terms of each

    prescriptive provision of the BCA.

    The inclusion of this summary enables an immediate understanding of the

    compliance status of the proposed design to be obtained.

    Part 4 contains a detailed analysis of the proposed design, and provides

    informative commentary & recommendation in respect of each instance of

    prescriptive non-compliance and area of insufficient (design) detail, as

    applicable.

    This commentary enables the project team to readily identify and understand the

    nature and extent of information required within the Building Permit (or other)application to demonstrate the attainment of BCA compliance.

    Should you require any further information, please do not hesitate to contact me on

    the number provided.

    Yours faithfully

    Jason Storer

    Technical Manager

    for Trevor R Howse & Associates Pty Limited

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    2/38

    BBCCAACCOOMMPPLLIIAANNCCEEAASSSSEESSSSMMEENNTT

    PREPARED FOR

    Watpac NSW Pty Ltd

    REGARDING

    University of New South Wales

    Student Accommodation

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    3/38

    (i)

    RREEPPOORRTTRREEGGIISSTTEERR

    The following report register documents the development and issue of this report andproject as undertaken by this office, in accordance with the Quality Assurancepolicy

    of Trevor R Howse & Associates Pty Ltd.

    Our Reference Issue No. Remarks Issue Date

    J27088A 1 DRAFT report issued to client. 13.6.07

    The format, technical content and intellectual property associated with this report

    remain the property of Trevor R. Howse & Associates Pty Limited, and has been

    prepared and may only be used, for the development / buildings the subject of thisreport.

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    4/38

    (ii)

    CCOONNTTEENNTTSSPPAAGGEE

    11..00 IINNTTRROODDUUCCTTIIOONN...................................................................................1

    1.1 General..............................................................................................................1

    1.2 Report Basis......................................................................................................1

    1.3 Exclusions .........................................................................................................2

    1.4 Report Purpose.................................................................................................2

    22..00 BBUUIILLDDIINNGGDDEESSCCRRIIPPTTIIOONN ...................................................................4

    2.1 General..............................................................................................................4

    2.2 Rise in Storeys (Clause C1.2) ..........................................................................4

    2.3 Building Classification (Clause A3.2).............................................................4

    2.4 Effective Height (Clause A1.1)........................................................................4

    2.5 Type of Construction (Table C1.1).................................................................4

    2.6 General Floor Area Limitations (Table C2.2)...............................................4

    33..00 BBCCAAAASSSSEESSSSMMEENNTTSSUUMMMMAARRYY ......................................................5

    3.1 General..............................................................................................................5

    3.2 Section B Structure .......................................................................................5

    3.3 Section C Fire resistance ..............................................................................5

    3.4 Section D Access and Egress ........................................................................6

    3.5 Section E Services and Equipment..............................................................7

    3.6 Section F Health and Amenity .....................................................................7

    3.7 Section G Ancillary Provisions ....................................................................8

    3.8 Section H Special Use Buildings ..................................................................8

    3.9 Section J Energy Efficiency..........................................................................9

    44..00 BBCCAAAASSSSEESSSSMMEENNTTDDEETTAAIILLEEDDAANNAALLYYSSIISS..................................10

    4.1 General............................................................................................................10

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    5/38

    4.2 Section B Structure .....................................................................................10

    4.3 Section C Fire Resistance ...........................................................................10

    4.4 Section D Access and Egress ......................................................................16

    4.5 Section E Services and Equipment............................................................21

    4.6 Section F Health and Amenity ...................................................................22

    4.7 Section G Ancillary provisions ..................................................................24

    4.9 Section J Energy Efficiency........................................................................24

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    6/38

    11..00 IINNTTRROODDUUCCTTIIOONN

    11..11 GGEENNEERRAALL

    This BCA Compliance Assessment report has been prepared at the request of

    Watpac Pty Ltd, and relates to the development known as Student

    Accommodation, to be located within the grounds of the University of New

    South Wales, Kensington.

    This report is based upon, and limited to, the information depicted in the

    documentation provided for assessment, and does not make assumptions

    regarding design intention or the like.

    From this documentation, it is understood that the proposed development

    encompasses:

    (a) Construction of new residential accommodation for the university

    students, with a total of 1030 bedrooms being provided across the

    development. The development also has ancillary basement carparking, a

    retail shop and kiosk, as well as laundry and e-learning facilities.

    11..22 RREEPPOORRTTBBAASSIISS

    The content of this report reflects

    (a) The principles and provisions of Building Code of Australia 2007.

    (b) Architectural documentation prepared by Architectus :

    Numbered Titled DatedA20-01 Room schedule 1 18.5.07

    A01-01 Level ground 1/2 1.6.07

    A01-02 Level ground 2/2 1.6.07

    A01-03 Level 1 1/2 1.6.07

    A01-04 Level 1 2/2 1.6.07

    A01-05 Level 2 1/2 1.6.07A01-06 Level 2 2/2 1.6.07

    A01-07 Level 3 1/2 1.6.07

    A01-08 Level 3 2/2 1.6.07

    A01-09 Level 4 1/2 1.6.07

    A01-10 Level 4 2/2 1.6.07

    A01-11 Level 5 1/2 1.6.07

    A01-12 Level 5 2/2 1.6.07

    A01-13 Level 6 1/2 1.6.07

    A01-14 Level 6 2/2 1.6.07

    A01-15 Level 7 1/2 1.6.07

    A01-16 Level 7 2/2 1.6.07A01-17 Level 8 1/2 1.6.07

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    7/38

    - 2 -

    Numbered Titled DatedA01-18 Level 8 2/2 1.6.07

    A01-19 Level roof 1/2 1.6.07

    A01-20 Level roof 2/2 1.6.07

    A02-01 North elevation 1.6.07

    A02-02 South elevation 1.6.07A02-03 East and West elevation 1.6.07

    A03-01 Section A 1.6.07

    A03-02 Section B 1.6.07

    A03-04 Section C & D 1.6.07

    A03-05 Section E & F 1.6.07

    11..33 EEXXCCLLUUSSIIOONNSS

    It is conveyed that this report should not construed to infer that an assessment

    for compliance with the following has been undertaken

    (a) Structural and services design documentation;

    (b) General building services;

    (c) The individual requirements of service providers (i.e. Telstra, Water

    Supply, Energy Australia);

    (d) The individual requirements of the Workcover Authority;

    (e) Disability Discrimination Act 1992 (DDA).

    11..44 RREEPPOORRTTPPUURRPPOOSSEE

    The purpose of this report is to identify the extent to which the architectural

    design documentation complies with the relevant prescriptive provisions of BCA

    2007.

    Assessment of the proposed design considers each prescriptive BCA provision,

    and identifies such as either:

    (a) Being complied with; or

    (b) Not being complied with; or

    (c) Requiring the provision further detail with the future Building Permit or

    other application or

    (d) Not being relevant to the particular building works proposal.

    The status of the design, in terms of these four (4) categories, is summarised

    within Part 3 of this report.

    Where prescriptive non-compliance is identified, suitable recommendations to

    remedy the non-compliance shall be detailed in Part 4.

    Trevor R Howse & Associates Pty Ltd

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    8/38

    - 3 -

    In instances where insufficient detail exists, summary of the information

    required from the project team for inclusion within future applications (i.e.

    Building Permit) shall also be outlined in Part 4.

    Trevor R Howse & Associates Pty Ltd

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    9/38

    - 4 -

    22..00 BBUUIILLDDIINNGGDDEESSCCRRIIPPTTIIOONN

    22..11 GGEENNEERRAALL

    In the context of the Building Code of Australia (BCA), the subject development

    is described within items 2.2 2.6 below.

    22..22 RRIISSEEIINNSSTTOORREEYYSS((CCLLAAUUSSEECC11..22))

    Having a rise in storeys of nine (9) for the larger building and one (1) for the

    smaller stand alone buildings.

    22..33 BBUUIILLDDIINNGGCCLLAASSSSIIFFIICCAATTIIOONN((CCLLAAUUSSEEAA33..22))

    The building shall be of the following classifications:

    (a) Class 3 Residential student accommodation

    (b) Class 6 Retail

    (c) Class 7a Carparking

    (d) Class 9b E-learning facility

    22..44 EEFFFFEECCTTIIVVEEHHEEIIGGHHTT((CCLLAAUUSSEEAA11..11))

    The buildings have an effective height not exceeding 25-metres

    22..55 TTYYPPEEOOFFCCOONNSSTTRRUUCCTTIIOONN((TTAABBLLEECC11..11))

    Required to be of Type A for the nine storey building and Type C Construction

    for the single storey buildings.

    22..66 GGEENNEERRAALLFFLLOOOORRAARREEAALLIIMMIITTAATTIIOONNSS((TTAABBLLEECC22..22))

    (a) Class 3 (Type A and C) Not Applicable

    (b) Class 6 (Type A)

    (i) Maximum floor area 5,000 m2

    (ii) Maximum volume 30,000 m3

    (c) Class 7a & 9b (Type A)

    (i) Maximum floor area 8,000 m

    (ii) Maximum volume 48,000 m

    Trevor R Howse & Associates Pty Ltd

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    10/38

    - 5 -

    33..00 BBCCAAAASSSSEESSSSMMEENNTTSSUUMMMMAARRYY

    33..11 GGEENNEERRAALL

    The tables contained within items 3.2 3.9 below summarise the compliance

    status of the proposed architectural design in terms of each prescriptive

    provision of the Building Code of Australia.

    For those instances of either prescriptive non-compliance or insufficient

    detail, a detailed analysis and commentary is provided within Part 4.

    33..22 SSEECCTTIIOONNBBSSTTRRUUCCTTUURREE

    BCA reference Complies Does notcomply

    Detailrequired

    Notrelevant

    B1.1 resistance to actions

    B1.2 determination of individual actions

    B1.3 loads

    B1.4 materials and form of construction

    33..33 SSEECCTTIIOONNCCFFIIRREERREESSIISSTTAANNCCEE

    BCA reference Complies Does notcomply

    Detailrequired

    Notrelevant

    Spec. C1.1 fire resisting constructionC1.3 buildings of multiple classification

    C1.4 mixed types of construction

    C1.5 two storey Class 2 or 3 buildings

    C1.6 Class 4 parts of a building

    C1.7 open spectator stands & indoor sports stadiums

    C1.8 lightweight construction

    C1.10 fire hazard properties

    C1.11 performance of external walls

    C1.12 non-combustible materials

    C2.2 general floor area & volume limits

    C2.3 large isolated buildings

    C2.4 requirements for open spaces & vehicular access

    C2.5 Class 9a and 9c buildings

    C2.6 vertical separation of openings in external wallsC2.7 separation of firewalls

    C2.8 separation of classifications in same storey

    C2.9 separation of classifications in different storeys

    C2.10 separation of lift shafts

    C2.11 stairways and lifts in one shaft

    C2.12 separation of equipment

    C2.13 electricity supply system

    C2.14 public corridors in Class 2 and 3 buildings

    C3.2 openings in external walls

    C3.3 separation of external walls & associated openings

    C3.4 acceptable methods of protection

    C3.5 doorways in firewalls

    C3.6 sliding fire doors

    C3.7 doorways in horizontal exits

    C3.8 openings in fire-isolated exits

    C3.9 service penetrations in fire-isolated exits

    Trevor R Howse & Associates Pty Ltd

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    11/38

    - 6 -

    BCA reference Complies Does notcomply

    Detailrequired

    Notrelevant

    C3.10 openings in fire-isolated lift shaftsC3.11 bounding construction: Class 2, 3, 4 and 9 buildings

    C3.12 openings in floors & ceilings for services

    C3.13 openings in shafts

    C3.15 openings for service installations

    C3.16 construction jointsC3.17 columns protected with f/r lightweight construction

    33..44 SSEECCTTIIOONNDDAACCCCEESSSSAANNDDEEGGRREESSSS

    BCA reference Complies Does notcomply

    Detailrequired

    Notrelevant

    D1.2 number of exits required

    D1.3 when fire-isolated exits are required

    D1.4 exit travel distances

    D1.5 distance between alternative exitsD1.6 dimensions of exits and paths of travel to exits

    D1.7 travel via fire-isolated exitsD1.8 external stairways or ramps in lieu of fire- isolated exits

    D1.9 travel via non-fire isolated stairways or ramps

    D1.10 discharge from exits

    D1.11 horizontal exits

    D1.12 non-required stairways or ramps

    D1.13 number of persons accommodated

    D1.16 plant rooms and lift motor rooms: concession

    D1.17 access to lift pits

    D2.2 fire-isolated stairways and ramps

    D2.3 non-fire isolated stairways and ramps

    D2.4 separation of rising and descending stair flights

    D2.5 open access ramps and balconies

    D2.6 smoke lobbies

    D2.7 installations in exits and paths of travel

    D2.8 enclosure of space under stairs and ramps

    D2.9 width of stairways

    D2.10 pedestrian ramps

    D2.11 fire-isolated passageways

    D2.12 roof as open space

    D2.13 goings and risers

    D2.14 landings

    D2.15 thresholds

    D2.16 balustrades

    D2.17 handrails

    D2.18 fixed platforms, walkways, stairways and laddersD2.19 doorways and doors

    D2.20 swinging doors

    D2.21 operation of latch

    D2.22 re-entry from fire-isolated exits

    D2.23 signs on doors

    D2.101 doors in path of travel in a POPE

    D3.2 general building access requirements

    D3.3 parts of buildings to be accessible

    D3.4 concessions

    D3.5 car parking

    D3.6 identification of accessible facilities

    D3.7 hearing augmentation services and features

    D3.8 tactile indicators

    Trevor R Howse & Associates Pty Ltd

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    12/38

    - 7 -

    33..55 SSEECCTTIIOONNEESSEERRVVIICCEESSAANNDDEEQQUUIIPPMMEENNTT

    BCA reference Complies Does notcomply

    Detailrequired

    Notrelevant

    E1.3 fire hydrants

    E1.4 fire hose reelsE1.5 sprinklers

    E1.6 portable fire extinguishers

    E1.8 fire control centres

    E1.9 fire precautions during construction

    E1.10 provision for special hazards

    E2.2a general provisions

    E2.2b specific provisions

    E2.3 provision for special hazards

    E3.2 stretcher facility in lifts

    E3.3 warning against use of lifts in fire

    E3.4 emergency lifts

    E3.5 landings

    E3.6 facilities for people with disabilities

    E3.7 fire service controls

    E3.8 aged care buildings

    E4.2 emergency lighting

    E4.4 design and operation of emergency lighting

    E4.5 exit signs

    E4.6 direction signsE4.7 Class 2 and 3 buildings and Class 4 parts: exemptions

    E4.8 design and operation of exit signsE4.9 emergency warning and intercommunication systems

    33..66 SSEECCTTIIOONNFFHHEEAALLTTHHAANNDDAAMMEENNIITTYY

    BCA reference Complies Does notcomply

    Detailrequired

    Notrelevant

    F1.1 stormwater drainage

    F1.5 roof coverings

    F1.6 sarking

    F1.7 water proofing of wet areas

    F1.9 damp proofing

    F1.10 damp proofing of floors on ground

    F1.11 floor wastes

    F1.12 sub-floor ventilation

    F1.13 glazed assemblies

    F2.1 facilities in residential buildings

    F2.3 facilities in Class 3 to 9 buildings

    F2.4 facilities for people with disabilities

    F2.5 construction of sanitary compartments

    F2.7 microbial (legionella) control

    F2.8 waste management

    F3.1 height of rooms

    F4.1 provision of natural light

    F4.2 methods and extent of natural lighting

    F4.3 natural lighting borrowed from adjoining room

    F4.4 artificial lighting

    F4.5 ventilation of rooms

    F4.6 natural ventilation

    F4.7 ventilation borrowed from an adjoining room

    Trevor R Howse & Associates Pty Ltd

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    13/38

    - 8 -

    BCA reference Complies Does notcomply

    Detailrequired

    Notrelevant

    F4.8 restriction on position of water closets and urinals

    F4.9 airlocks

    F4.11 car parks

    F4.12 kitchen local exhaust ventilationF5.2 sound transmission class: interpretation

    F5.3 sound transmission of floors between units

    F5.4 sound insulation of walls between units

    F5.5 sound insulation rating of walls

    F5.6 sound insulation rating of services

    F5.7 sound insulation of pumps

    33..77 SSEECCTTIIOONNGGAANNCCIILLLLAARRYYPPRROOVVIISSIIOONNSS

    BCA reference Complies Does notcomply

    Detailrequired

    Notrelevant

    G1.1 swimming pools

    G1.2 refrigerated chambers, strong-rooms & vaults

    NSW G1.101 Provision for cleaning windows

    G2.2 installation of appliances

    G2.3 open fireplaces

    G2.4 incinerator rooms

    G3.2 dimensions of atrium well

    G3.3 separation of atrium bounding walls

    G3.4 construction of bounding walls

    G3.5 construction at balconies

    G3.6 separation at roofs

    G3.7 means of egress

    G3.8 fire and smoke control systems

    G4.3 external doorwaysG4.4 emergency lighting

    G4.5 external ramps

    G4.6 discharge of exits

    G4.7 external trafficable structures

    G4.8 fire-fighting services and equipment

    G4.9 fire orders

    G5.2 protection (in bushfire prone areas)

    33..88 SSEECCTTIIOONNHHSSPPEECCIIAALLUUSSEEBBUUIILLDDIINNGGSS

    BCA reference Complies Does notcomply

    Detailrequired

    Notrelevant

    H101.2 fire separation

    H101.3 foyer space

    H101.4 sprinkler systems for common foyers

    H101.5 conventional stages

    H101.6 non-conventional stages

    H101.7 flying scenery

    H101.8 load notice

    H101.10 safety curtains

    H101.11 seating in rows

    H101.12 continental seating

    H101.13 provision of guardrails

    H101.14 guardrails

    H101.15 dressing rooms

    H101.16 storerooms

    H101.17 projection suites

    Trevor R Howse & Associates Pty Ltd

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    14/38

    - 9 -

    BCA reference Complies Does notcomply

    Detailrequired

    Notrelevant

    H101.18 basement storeys

    H101.19 electric mains installation

    H101.20 lighting

    H101.22 automatic smoke-and-heat vents for stages

    H101.23 solid fuel burning stoves & open fireplaces

    H101.24 fuel gas cylinders

    33..99 SSEECCTTIIOONNJJEENNEERRGGYYEEFFFFIICCIIEENNCCYY

    BCA reference Complies Does notcomply

    Detailrequired

    Notrelevant

    J1.2 thermal construction general

    J1.3 roof and ceiling construction

    J1.4 roof lights

    J1.5 walls

    J1.6 floors

    J2.3 glazingJ2.4 glazing

    J2.5 shading

    J3.2 chimneys and flues

    J3.3 roof lights

    J3.4 external windows and doors

    J3.5 exhaust fans

    J3.6 construction of roofs, walls and floors

    J3.7 evaporative coolers

    J4.2 air movement

    J4.3 ventilation openings

    J4.4 ceiling fans and evaporative coolers

    J5.2 air conditioning and ventilation systems

    J5.3 time switch

    J5.4 heating and cooling systemsJ5.5 ancillary exhaust systems

    J6.2 interior artificial lighting

    J6.3 interior artificial lighting and power control

    J6.4 interior decorative and display lighting

    J6.5 artificial lighting to the perimeter of a building

    J6.6 boiling water/chilled water storage units

    J7.2 hot water supply

    J8.2 access for maintenance

    Trevor R Howse & Associates Pty Ltd

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    15/38

    - 10 -

    44..00 BBCCAAAASSSSEESSSSMMEENNTTDDEETTAAIILLEEDDAANNAALLYYSSIISS

    44..11 GGEENNEERRAALL

    With reference to the BCA Assessment Summary contained within Part 3

    above, the following detailed analysis and commentary is provided.

    This commentary is formulated to enable the design documentation to be further

    progressed, for the purpose of evidencing the attainment of compliance with the

    relevant provisions of the BCA.

    44..22 SSEECCTTIIOONNBBSSTTRRUUCCTTUURREE

    Cl. B1.1 The resistance of a building or structure must be greater than the most critical

    action effect determined by BCA Clauses B1.2 & AS/NZS 1170.02002, and

    B1.4.

    Cl. B1.2 The structural design of the building must be determined in accordance with the

    varying action considerations contained within this clause (i.e. permanentactions, imposed actions, wind / earthquake actions).

    Cl. B1.3 The structural design of the building must accord with:

    Dead & Live Loads & AS 1170.12002load combinations

    Permanent, imposed & AS 1170.22002other actions

    Cl. B1.4 Materials and forms of construction must comply (where proposed) with thefollowing: Masonry AS 37002001 Piling AS 2159 1995 Concrete AS 36002001 Timber construction AS 1684.2,3 or 4 2006 Cold formed steel structures AS 41001998 Aluminum AS/NZS 1664.1 or 21997 Metal sheet roof covering AS 1562.11992 Glazing AS 12882006 & AS 20471999

    44..33 SSEECCTTIIOONNCCFFIIRREERREESSIISSTTAANNCCEE

    Cl. C1.1 Specification C1.1 Requirements for Type A Construction (applicable

    to the 9 storey part of the building)

    The proposed building works must incorporate the following AS 1530.42005compliant fire resistance levels and characteristics:

    * External Walls

    External Walls(class 3)

    (Within 1.5m of the fire source feature)

    Loadbearing 90/90/90Non Loadbearing /90/90

    (Between 1.5m & 3m of a fire source feature)

    Loadbearing 90/60/60Non Loadbearing /60/60

    Trevor R Howse & Associates Pty Ltd

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    16/38

    - 11 -

    Cl. C1.1

    contd

    (Greater than 3m from a fire source feature)

    Loadbearing 90/60/30Non Loadbearing /30/30

    External Walls(class 6)

    (Within 1.5m of the fire source feature)

    Loadbearing 180/180/180Non Loadbearing /180/180

    (Between 1.5m & 3m of a fire source feature)

    Loadbearing 180/180/120

    Non Loadbearing /180/120

    (Greater than 3m from a fire source feature)

    Loadbearing 180/120/90Non Loadbearing //

    External Walls(class 7a & 9b)

    (Within 1.5m of the fire source feature)Loadbearing 120/120/120Non Loadbearing /120/120

    (Between 1.5m & 3m of a fire source feature)

    Loadbearing 120/90/90Non Loadbearing /90/90

    (Greater than 3m from a fire source feature)

    Loadbearing 120/60/30Non Loadbearing //

    * External Columns

    (less than 3m from a fire source feature)

    Class 3 90//

    * Internal Walls

    Bounding fire stairs and lift shafts

    Class 3

    Loadbearing 90/90/90Non Loadbearing /90/90

    Class 6

    Loadbearing 180/180/180Non Loadbearing /180/180

    Class 7a

    Loadbearing 120/120/120

    Non Loadbearing /120/120

    NB: Stair shafts must also be fire separated at the top and bottom of the

    shaft with fire rated construction achieving an FRL equivalent to that of the

    stair or lift shaft.

    Trevor R Howse & Associates Pty Ltd

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    17/38

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    18/38

    - 13 -

    Cl. C1.1

    contd* Roofs

    As the buildings are less than 25m in height and of mixed classification it isrequired to be fire rated to achieve a 60 minute resistance to the incipient spread offire. Please advise if anything other than a concrete roof is proposed as aperformance based solution can be utilised to remove the fire rating where

    necessary.

    * Lintels

    Clause 2.4

    Lintels within the external walls of the building are required to have an FRLequivalent to that of the part of the building within which it is located. Note theconcessions in clause 2.3 of Specification C1.1 re concessions for fire ratings

    requirements for lintels.

    * Fire Rated Wall Construction

    Table 3(e)

    All walls required to be fire rated must be constructed of non-combustibleconstruction. The same is applicable for the flooring and floor framing of lift pits.

    Specification C1.1 Requirements for Type C Construction (class 3

    single storey stand alone buildings)

    *External Walls

    Within 1.5m of a fire source feature

    /90/90

    More than 1.5m from fire source feature

    /60/60

    * External Columns

    Within 1.5m of a fire source feature

    90/--/--

    More than 1.5m from fire source feature

    /--/--

    * Internal Walls

    Between units and bounding a fire rated stair shafts.

    An FRL of not less than 60/60/60.

    Note: the fire rated party walls must extend to the underside of the ceiling above ifthat ceiling has a 60 minute rating, or to the underside of the roof covering if it isnon-combustible (and the fire rated walls must not be crossed by timber other thanroof battens 75mm x 50mm maximum).

    * Roofs

    No fire rating required.

    Trevor R Howse & Associates Pty Ltd

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    19/38

    - 14 -

    Cl. C1.8 If lightweight plasterboard is to be used in a fire rated application please providea copy of the manufacturers data sheet detailing the static load and resistanceachieved for the systems proposed within this building.

    Cl. C1.10 The fire hazard properties of any materials other than floor, wall and ceilinglinings should accord with the following:

    Have a spread of flame index exceeding 9 Have a smoke developed index exceeding 8, if the spread of flame index

    exceeds 5

    Floor, wall and ceiling linings must have fire hazard properties accordant withBCA Specification C1.10a for a non-sprinkler protected building, whichspecifies that:

    Floor Materials.

    Must have a critical radiant heat flux for the building not less than 2.2 and amaximum smoke developed rate of 750 % minutes.

    Class 3 Wall and ceilings.

    For wall and ceiling linings a group number of 1 for fire stairs, 1 and 2 for public

    corridors and 1, 2 and 3 for specific area and other areas.

    Class 6, 7a and 9b Wall and ceilings.

    For the class 6, 7a and 9b parts a group number of 1 for fire stairs, 1 and 2 for

    public corridors and 1, 2 and 3 for specific areas and other areas, except theceilings of specific areas which are limited to groups 1 and 2.

    Cl. C2.6 We have tried to assess the spandrel separation proposed for the building but due

    to the lack of detail on the elevations it is difficult to determine where glazingstops and a spandrel panel starts, e.g. grid 3-4, south elevation, as there may bespandrels panels behind but this part of the elevation appears to be glazing.

    As such this issue should be discussed at a design meeting to ensure that thisissue has been considered in respect to the provision of either a 1.1m widehorizontal spandrel that extends a minimum of 450mm past the edge of any

    openings or a vertical spandrel not less than 900mm high. Both types ofspandrels are required to be 60 minute fire rated.

    We also note from our review of the plans that some of the spandrels do notappear to extend the required 450mm past the end of the openings when ahorizontal spandrel has been used to achieve compliance, e.g. balconies to unit

    E2.2, E3.3, F2.2, F2.1.

    Cl. C2.7 Where walls are used to fire separate sole-occupancy units from each other orfrom public corridors, they must:

    Have an FRL not less than that specified in Clause C1.1 above. Not be crossed by elements other than timber battens of 75x50-mm in size. Extend to the underside of a floor having the same FRL as the wall, or to

    the underside of the roof cover.

    Cl. C2.8 Classifications located in the same storey (i.e. Ground floor - Class 6 retail, class9b E-learning and Class 3 residential accommodation) must either be separatedusing firewalls as described in Clauses C1.1 and C2.7 above, or the entire floorconstructed to the higher FRL applicable to the classification concerned.

    Where separation is not possible the FRL of elements within the ground floorwould need to be increased to a minimum three (3) hour rating.

    Trevor R Howse & Associates Pty Ltd

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    20/38

    - 15 -

    Cl. C2.9 As mentioned within Clause C2.8, similarly, if no firewall is provided toseparate classifications, then the floor between the ground floor and Level 1would need an FRL of 180/180/180. Refer to Specification C1.1 above inrelation to the fire rating requirements for floors.

    Cl. C2.10 The walls of the lift shaft need have a fire rating as specified in Clause C1.1

    above. As mentioned within Clause C2.8 throughout the ground floor where theseparate classifications are not fire isolated the lift shaft need be constructed to

    the higher FRL.

    Cl. C2.12 Any proposed lift motor rooms and any onsite fire pumps must be fire separatedfrom the remainder of the building using construction having a 2-hour fireresistance level, and a /120/30 self-closing fire door set.

    Cl. C2.13 The existing sub-station will need to be two hour fire separated from the

    remainder of the building by 2-hour construction (including self-closing twohour rated door set).

    Where the main switchboard controls emergency equipment operating in theemergency mode, the switchboard must be separated from the remainder of thebuilding by 2-hour construction (including self-closing two hour rated door set).

    Electrical conductors within the building that supply a main switchboard (see 1

    above) must have a classification in accordance with AS/NZS 3013 of not lessthan: if in a position where subject to motor vehicle damage WS53W; or otherwise WS52W; or be enclosed in construction with an FRL of 120/120/120.

    Where emergency equipment is required in a building all switchboards in theelectrical distribution system must provide full segregation by wall of enclosedmetal partitions designed to prevent the spread of faults between emergency andnon-emergency switchgear.

    Cl. C3.2 Please provide clarification as to whether the external walls of the building areproposed to be loadbearing or non-loadbearing. Once this clarification isprovided we will review the plans and indicate which windows/doors arerequired to be fire rated due to their proximity to adjoining buildings on the site.

    Cl. C3.4 Permissible protectives that may be required by clause C3.2 above: Doors

    (i) Self-closing or automatic closing 1-hour fire door sets; or

    (ii) External wall-wetting sprinklers over self-closing or automaticclosing door sets.

    Windows(i) External wall-wetting sprinklers over fixed or automatic closing

    windows; or(ii) Fixed or automatic closing 1-hour fire rated glazing; or

    (iii) External automatic closing 1-hour fire shutters. Other openings

    Internal or external wall wetting sprinklers as appropriate or constructionhaving an FRL of not les than /60/.

    NB: any fire doors, fire windows or fire shutters must comply with

    Specification C3.4.

    Cl. C3.8 Doorways openings into the fire-isolated stairs must be fitted with door sets

    having: A fire resistance level not less than /60/30; and Automatic or self-closing devices.

    Trevor R Howse & Associates Pty Ltd

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    21/38

    - 16 -

    Cl. C3.9 The fire-isolated stairs must not be penetrated by any new building servicesother than: Water pipes for fire services (i.e. fire hydrants).Wiring as permitted by clause D2.7(e).

    Cl. C3.10 The lift landing doors must have a fire resistance level not less than /60/

    Lift indicator panels greater than 35,000m2must also be fire rated to an FRL of

    /60/60.

    Cl. C3.11 Door openings to the sole occupancy units need be protected with self-closing/60/30 fire doors.

    Door from areas other than sole-occupancy units that open to public corridors.need be protected with self-closing /60/30 fire doors.

    Please advise if units AA6-1 has access to the stair to the west for egress.

    We note that we may need to provide additional fire separation requirements for

    units located in the north west corner of the development that currently appear tohave access to a single stair, as detailed within clause D1.4.

    Cl. C3.12 New service openings through any floors in the building must be either fire

    sealed or enclosed in a fire rated shaft, using materials having an FRL not lessthan that of the floor concerned.

    Cl. C3.13 Openings to shafts must be protected in accordance with the following: For sanitary compartments a door or panel which together with the frame

    is non-combustible or has an FRL of not less than /30/30; or A /60/30 fire rated protective covering (i.e. access panels, or self-closing

    doors and hoppers); or

    For garbage shafts a door or hopper of non-combustible construction.

    Cl. C3.15 Any services (mechanical ventilation, air conditioning, electrical etc) that passthrough the any wall required to have an FRL shall be protected by a prototypedevice in accordance with AS 1530.42005 or as per Spec C3.15.

    Cl. C3.16 Construction joints between fire resistant elements must be fire sealed with amaterial having a fire resistance level not less than the elements being joined.

    44..44 SSEECCTTIIOONNDDAACCCCEESSSSAANNDDEEGGRREESSSS

    Cl. D1.3 Please advise what the door is for on the roof of the building at grid 12-13/E2

    roof level, 2/2.

    Please also clarify which areas of the roof are accessible.

    The egress stair to building F3 appears to be a non-fire isolated stair. As such itcan only connect two stories. The stair currently connects 3 stories. 2 options areavailable: provide a separate entrance to the lower floor unit and remove the door that

    connects it to the stair shaft; or

    utilise a performance based solution to justify the connection of the thirdfloor. This would require smoke seals to the fire door to the unit on thelowest level as well as a thermal detector within the unit linked to the smokedetection system for the building.

    Trevor R Howse & Associates Pty Ltd

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    22/38

    - 17 -

    Cl. D1.4 There are numerous travel distance non-compliances throughout the building (inso far as exceeding 6 metres): For level 8 the maximum distance to an exit is 6.6m, from unit D8.2. For level 7 please advise if the stair to the west of units AA7-1 to AAA7-2 is

    accessible. Same re units AA6-1 to 3 below. On level 7, the maximum distance to an exit is 6.4m, from unit B7-2.

    On level 6, the maximum distance to an exit is 6.4m, from unit DD6-4. On level 5, the maximum distance to an exit is 6.4m, from unit C5-2. On level 4, the maximum distance to an exit is 8m, from unit E4.1. On level 3, the maximum distance to an exit is 8m, from unit E3.1. On level 3 1/2, from units A3.1 to A 3.4, where is the 2 ndexit from these

    units, same re units A 2.1 to A 2.4, level 2-1/2.

    Level 2, the maximum distance to an exit is 9m, from unit DD2-2 Please note that the door to the fire stair is missing level 2 near unit B2-1. How is egress from units A01-A04 and A1- 1 achieved. There appears to be

    an egress path in excess of 6m to a point of choice to 2 exits. Please discuss.Note that the fire stairs are considered as the nearest exit.

    Cl. D1.6 In terms of the dimensions of exits and paths of travel, the unobstructed

    height of new doorways must not be less than 1980-mm, while theunobstructed width must not be less than 750-mm.

    Confirmation is also required that egress stairs and paths of travel will be aminimum of 1m clear width.

    Cl. D1.7 The fire stairs for the main foyers all discharge within the foyer area on thelowest level and do not discharge directly to outside. As such this method ofdischarge does not comply with the deemed-to-satisfy requirements as the foyerareas are enclosed and thus the 2/3rdof the perimeter open concession availablein the BCA cannot be utilised.

    As such is it proposed that a performance-based solution be sought in respect to

    this issue. This should be discussed at a meeting with the architects.

    We also note that egress from the southern foyers of the building appears torequire occupants to pass within 6m of the facade of the building. Pleasecomment as to whether egress is available in both an east and west direction via

    an egress path that has a gradient not more than 1:8 or that has egress stairsprovided where the gradient exceeds 1:8.

    Cl. D1.8 Please also advise what type of stair the stair at grid 2E is. It appears to be

    designed as an external stair in lieu of a fire stair. Please clarify.

    Cl. D1.10 The egress path from the Fig Tree Theatre to the street should not have a

    gradient no more than 1:8, or have egress stairs provided, should the gradientexceed 1:8. Please discuss.

    All egress paths from the new parts of the building must also have an egress pathfrom the building to the street as per that required for the Fire Tree Theatreabove.

    CL. D1.13 Please provide revised plans of the e-learning and retail area parts of the building

    as noted on the plans submitted. We will then review re occupant load, toiletfacilities and egress.

    Cl. D1.17 Where the depth of the lift pit is not more than 3m, access to the lift pit must be

    through the lowest landing doors.

    Where the pit depth is more than 3m access must be through an access doorwaycomplying with part (b) of this clause.

    Trevor R Howse & Associates Pty Ltd

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    23/38

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    24/38

    - 19 -

    Cl. D2.16 The following areas will be required to be provided with balustrading as the fallindicated may be more than 1m and/or 4m.

    The fire stairs will require balustrading with a rail at not more than 150mm

    above the nosing of the tread then no gaps greater than 460mm betweenrails, with the top rail not less than 865mm above the nosing of the treads.

    If a landing in the fire stair exceeds 500mm, the top rail must be not lessthan 1m above the floor of the landing.

    The non-fire isolated stairs will require a balustrade not less than 865mmhigh above the nosing of the treads with no gaps greater than 125mm. Forthe landing of this stair, (greater than 500mm in length), the balustrading is

    required to be a minimum of 1m in height with no gaps greater than125mm. If the fall from the side of the stairs exceeds 4m at any point,(measured from the landing floor), there shall be no climbable elementsbetween 150mm and 760mm above the floor of the landing.

    For the balustrade to the balcony / terrace areas, where the fall is more than

    1m but less than 4m the balustrade should be 1m high with no gaps greater

    than 125mm. Where the fall from the floor to the ground level exceeds 4mto the ground below, there shall be no climbable elements between 150mmand 760mm above the floor.

    Along any path or other trafficable area such as a roof, where the fall

    exceeds 1m, a balustrade not less than 1m must be provided with no gapsgreater than 125mm.

    For any window openings with sill heights less than 865mm and where thefall from the sill exceeds 1m to the external part of the building a rail/smust be installed to at a height not less than 865mm with no gaps greaterthan 125mm.

    Cl. D2.17 Handrails must be provided to at least one side of all stairways and ramps andmust: Be continuous between stair flight landings; and

    Have no obstruction that would cause a break in the hand hold; and Have a rail fixed at a height not less than 865-mm.

    Cl. D2.20 For the retail, laundry and e-library area the doors must be provided with adevice allowing them to be held in the open position.

    Cl. D2.21 Doors must be provided with lever action hardware located 900-1200-mm abovethe floor that does not require the use of a key to operate from the side seekingegress, and involves a single handed downward or pushing action.

    This is not applicable within the units, the retail area or laundries.

    Cl. D2.23 Doors to the fire-isolated exits must be provided with signage stating,FIRE DOOR

    DO NOT OBSTRUCT

    DO NOT HOLD OPEN

    Doors discharging from fire-isolated exits must be provided with signage stating,FIRE SAFETY DOORDO NOT OBSTRUCT

    In each instance, the lettering must not be less than 20-mm high and be in a

    colour that contrasts with the background.

    Signage in respect to Clause 183 of the Environmental Planning and AssessmentRegulations 2000, Offences relating to fire stairs, must also be installed to theoutside face of the doors to the fire stairs.

    Trevor R Howse & Associates Pty Ltd

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    25/38

    - 20 -

    Cl. D3.2 In terms of access for people with disabilities we note the following potentialnon-compliances:

    As there are a total of 304 sole-occupants units a total of 15.2 disabled

    SOUs are required. Only 15 are provided on the plans. Please indicate thelocation of a 16thunit.

    Please indicate the gradients of the ramps on site that allow for access intosome of the residential foyers from the street, e.g. foyers AA, BB.

    All doors to and within the access paths as well as to any common areas,retail, laundries and e-learning all need to be a minimum of 800mm clear

    width. This will required 870mm door leafs to be installed.

    Certification will be required that all bathrooms have been designed as perAS 1428.1 as insufficient detail is provided on the plans. However we notethat the size of the facility indicated is compliant with the requirements ofAS 1428.1.

    How is foyer DD accessed as there appear to be stairs to both sides andaccess is needed to unit DD6-5, level 6-2/2? Please plot the proposedaccess path including gradients.

    Please plot the access from the various foyers that are required to be

    accessible to the retail/laundry/e-learning facilities including gradients.

    Please advise how foyer E is access re unit E1.2.

    Disabled access unit FF1.1 does not comply as the front door is not AS1428.1 compliant. Please reconfigure.

    Please advise how foyer C is accessed.

    Unit CC0-10 has no front door indicated. Please add. Also north west bedis not accessible as has no 470mm clearance to latch side of the door.

    Please advise how foyers AA and BB are accessed.

    North west bed of unit E4-3, level 4-2/2 is not accessible as has no 470mmclearance to latch side of the door. Also has no disabled WC indicated.

    North west bed of unit E3-3, level 3-2/2 is not accessible as has no 470mmclearance to latch side of the door.

    North west bed of unit E2-2, level 2-2/2 is not accessible as has no 470mm

    clearance to latch side of the door. Also has no disabled WC indicated.

    The door to the disabled bathroom of unit FF1-1, level 1-2/2, does notappear to have a 470mm nib to the latch side of the door.

    We will review disabled access to the retail, laundries and e-learning oncethe revised plans are received.

    Cl. D3.5 The disabled carspaces must be a minimum of 2.5m clear height and the path tothe spaces from the street must be a minimum of 2.3m clear height, as per AS2890.1. Signage is also required to the disabled spaces as per AS 2890.1.

    Cl. D3.6 AS 1428.12001 compliant International Symbols of Access and Braille signagemust be provided to the disabled sanitary facility as well as to indicate thedisabled accessible lifts to enable their locations to the identified.

    Trevor R Howse & Associates Pty Ltd

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    26/38

    - 21 -

    Cl. D3.8 Type B tactile indicators must be provided to the top and bottom of the non-fireisolated stairways. They may also be required to the ramps depending on theirproposed gradients. We will comment once the access paths are clarified.

    44..55 SSEECCTTIIOONNEESSEERRVVIICCEESSAANNDDEEQQUUIIPPMMEENNTT

    Cl. E1.3 AS 2419.12005 compliant fire hydrant coverage must be provided throughoutthe building.

    If a hydrant pump room is to be provided it must be fire rated with constructionachieving a fire resistance level of 120/120/120. The door into the room should

    be a /120/30 self-closing fire door.

    Cl. E1.4 AS 24412005 compliant fire hose reel coverage must be provided throughoutthe area of the proposed works.

    Please ensure that the fire hose reels are within 4-metres of the exit and do notneed to pass through any fire or smoke doors to cover the floor plate (other than

    doors to units).

    Cl. E1.5 AS 2118.11999 sprinkler coverage is required to the carpark. In addition anysprinkler system must comply with specification E1.5 and any sprinkler valveroom must be located at a level where direct access to a road is available, as such

    locating it within the carpark area does not comply with the deemed-to-satisfyprovisions of the BCA.

    If the location must be within the carpark a performance-based solution isrequired, this will also need fire brigade approval.

    Cl. E1.6 AS 24442001 compliant portable fire extinguishers must be provided; Within any retail kitchen to cover Class F fire risks, or where more than

    50-litres of combustible liquid is stored (i.e. cooking oils); To cover Class AE or E fire risks associated with emergency switchboards.

    Cl. E1.9 Fire precautions during construction must be undertaken in respect to theprovision of fire extinguishers, hose reels and hydrants at the relevant stages of

    construction. Certification to be provided at Construction Certificate stage.

    Cl. E2.2a The proposed building must be provided with: Automatic shut-down of any air handling system that recycles air between

    fire compartments, and that does not form part of a smoke exhaust system,on activation of AS/NZS 1668.11998 Clause 4.10 smoke detectors, andincorporating smoke and fire dampers where penetrating firewalls; and

    An automatic smoke detection and alarm system in accordance with AS1670.12004 except for Clause 3.26(f), and needs to activate a building

    occupant warning system in accordance with Clause 6 as well as be linkedto a monitoring station as per AS 1670.3.

    The carpark must be designed to have a mechanical ventilation system inaccordance with AS 1668.2 1991 as well as clause 5.5 of AS 1668.1 1998. In addition note that fans with metal blades suitable for operation atnormal temperature may be used and the electrical power and control

    cabling need not be fire rated.

    Cl. E3.2 As the building is more than 12m in height each unit within the building must

    have access to a lift that has minimum internal dimensions of not less than 2mlong x 600mm wide for stretcher use.

    Trevor R Howse & Associates Pty Ltd

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    27/38

    - 22 -

    Cl. E3.3 Warning signage DO NOT USE LIFTS IF THERE IS A FIRE will be requiredadjacent to every lift call button with dimensions as detailed in this clause.

    Cl. E3.6 As disabled access is required to the building all lifts must be provided withdisabled controls as per AS 1735.121999.

    Cl. E3.7 All lifts are required to be provided with fire services controls as per AS 1735.12003 or AS 1735.22001.

    Cl. E4.2 AS 2293.12005 compliant emergency lighting must be provided throughout theproposed building.

    Cl. E4.4 Refer Clause E4.2 above for emergency lighting requirements.

    Cl. E4.5 AS 2293.12005 compliant exit signage must be provided over each of the exitdoors.

    It need be noted that the most recent amendment to the applicable standard

    requires the installation of the pictorial running man symbol in lieu of theword EXIT.

    Cl. E4.6 AS 2293.12005 compliant directional exit signage must be provided throughoutthe building to direct occupants to the exits.

    Cl. E4.8 Refer Clauses E4.5 and E4.6 above for exit signage requirements.

    Cl. E 4.9 An EWIS system is required to the building as per AS 16780.4 2004 and AS4428.4 2004. Note that EWIS is not required to the single storey buildings.

    44..66 SSEECCTTIIOONNFFHHEEAALLTTHHAANNDDAAMMEENNIITTYY

    Cl. F1.1 Stormwater drainage must be AS/NZS 3500.3.22003 compliant.

    Cl. F1.5 The roof material is not indicated on the plans. As such please indicate the typeof roofing material proposed to all parts of the building.

    Cl. F1.6 Please certify that sarking will be installed to roof and walls for weatherproofingas per AS/NZS 4200.1 and 2 - 1994.

    Cl. F1.7 Wet areas must be water proofed in accordance with AS 37402004.

    Cl. F1.9 Please certify that damp proofing will be provided as per this clause and AS

    2904 1995 or AS 3660.1 - 2000.

    Cl. F1.10 Please certify that damp proofing will be installed as per AS 2870 2003.

    Cl. F1.11 Each bathroom/laundry area needs to be graded to permit drainage to a floorwaste.

    Cl. F1.13 Refer Clause B1.4 above for the glazing in external walls

    Cl. F2.3

    & Cl.

    F2.4

    A disabled toilet facility need be provided for staff within the retail and e-learning areas. This will be assessed once the revised plans for this area are

    provided. Please also note that doors to a disabled WC must either open out or

    be fitted with removable hinges to allow ease of removal.

    Trevor R Howse & Associates Pty Ltd

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    28/38

    - 23 -

    Cl. F2.5 Where sanitary facilities are to be wholly enclosed, and the distance between theWC pan and the nearest part of the doorway is less than 1200-mm, the doorsmust either swing out, be fitted with removable hinges, or slide.

    There are numerous toilets within the units of the building that do not comply

    such as:

    1. unit F1-3, level 1-2/2.2. unit E1-3, level 1-2/2.

    Please note that due to the large number of non-complying WCs we have not

    listed them all.

    Where doors to toilet cubicles are to be less than full height the doors must be aminimum of 1.8m above the ground.

    C1. F4.2 Please provide a window and door schedule for the openings within the externalfaade so that we can undertake an assessment of the level of compliance of

    natural lighting to the building for the residential units as the 1:200 scaleelevations provided are not detailed enough to allow for an accurate assessment

    of compliance to be undertaken.

    Cl. F4.4 Artificial lighting must be AS 1680.01998 compliant.

    Cl. F4.5 Ventilation to rooms and spaces must be either natural or AS 1668.21991compliant mechanical ventilation.

    Cl. F4.6 Where natural ventilation is to be provided to rooms the openable size of thewindow or opening need be not less than 5% of the floor area of the room beingventilated. This will be assessed once the window and door schedule is provided.

    Please also clarify whether 50% of the window area provided is openable.

    Cl. F4.11 The carpark must be provided with either natural ventilation or mechanicalventilation as per AS 1668-2 1991.

    Cl. F4.12 Where the caf and kitchen contains either: A cooking apparatus with a total electrical input exceeding 8 kW, or a total

    gas input exceeding 29 MJ/hr; or

    A total electrical input exceeding 0.5 kW/m2, or a total gas input exceeding

    1.8 MJ/m2;

    an AS/NZS 1668.1 1998 and AS 1668.2 1991 compliant kitchen exhaust

    hood must be provided.

    Cl. F5.3 Please provide certification from an acoustic engineer that the floor of thebuilding required to have an impact sound insulation rating will:

    1. have the required value for weighted normalised impact sound pressurelevel with spectrum adaptation term (Ln,w+C1) determined inaccordance with AS/IOSO 717.2 using results from laboratorymeasurements; or

    2. comply with Specification F5.2.

    Please provide certification from an acoustic engineer that the walls of the

    building required to have an impact sound insulation rating will be ofdiscontinuous construction as defined in this clause.

    Trevor R Howse & Associates Pty Ltd

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    29/38

    - 24 -

    Cl. F5.4 The floor of the suites need have an Rw + Cr (airborne) of not less than 50 and anLn,w+C1 (impact) not more than 62 if it separates sole-occupancy units or a sole-occupancy into from a plant room, lift shaft, stairway, public corridor, publiclobby or the like or different classifications.

    Cl. F5.5 The wall between units need to have an Rw + Cr (airborne) of not less than 50 and

    an Rw (airborne) of not less than 50 if it separates sole-occupancy units or a sole-occupancy into from a plant room, lift shaft, stairway, public corridor, public

    lobby or the like or different classifications.

    Where the wall separates bathrooms, sanitary compartments, laundries orkitchens in one unit from a sleeping area in another the walls will need bediscontinuous construction as per clause F5.3(b).

    The door assembly of the suites need have an Rwnot less than 30

    Cl. F5.6 Please provide certification from an acoustic engineer that any services will besound insulated as per Clause F5.6 of BCA 2006.

    Cl. F5.7 Flexible coupling need be used at the point of connection of service pipes andcirculating pumps.

    44..77 SSEECCTTIIOONNGGAANNCCIILLLLAARRYYPPRROOVVIISSIIOONNSS

    Cl. G1.01 Provision for cleaning of external windows must be provided either bycomplying with a method within the Occupational Health and Safety Act 2000

    and its Regulation or the windows must be able to be cleaned from the inside.

    44..88 SSEECCTTIIOONNJJEENNEERRGGYYEEFFFFIICCIIEENNCCYY

    Cl. J1.2(A) Please provide certification that insulation (if required to achieve compliancewith the Part J1 of the BCA) will comply with AS/NZS 4859.1 2002, and beinstalled so that it 1. abuts or overlaps adjoining insulation (other than at supporting members,

    e.g. studs, noggings, joists, furring channels, etc where the insulation mustabut against the members) and

    2. forms a continuous barrier with ceilings, walls, bulkheads, floors or the

    like that inherently contribute to the thermal barrier; and3. will not affect the safe or effective operation of a service or fitting.

    Cl.

    J1.2(B)

    Please provide certification that reflective insulation (if required to achieve

    compliance with the Part J1 of the BCA) will be installed within 1. the necessary air space to achieve the requiredR-Valuebetween a reflective

    side of the reflective insulation and a building lining or cladding; and2. the reflective insulation closely fitted against any penetration, door, or

    window opening; and3. that the reflective insulation will be adequately supported by framing

    members; and

    4. that each adjoining sheet or roll membrane will be overlapped more than50mm or taped together.

    Cl.

    J1.2(C)

    Please provide certification that bulk insulation (if required to achievecompliance with the Part J1 of the BCA) will be installed so that 1. it maintains its position and thickness (other than where it crosses roof

    battens, water pipes, electrical cabling or the like; and

    2. that (in a ceiling where there is no bulk insulation or reflective insulationinthe wall beneath), that it will overlap the wall by more than 50mm.

    Trevor R Howse & Associates Pty Ltd

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    30/38

    - 25 -

    Cl.

    J1.2(D)

    Note : roof, ceiling, wall and floor materials and associated surfaces are deemedto have the thermal properties listed in Specification J1.2.

    Cl. J1.3

    (A) (C)

    Please provide certification that the roof or ceiling that is part of theENVELOPE of the new works will achieve the total R-Value specification intable J1.3 for the direction of heat flow.Please note that this development is

    within climate zone 5.

    Cl.

    J1.3(D)

    Metal roofs only.

    Please certify that the any metal roofs, due to being required to achieve aminimum Total R-Value, and having metal sheet roofing fixed to metal purlins,rafters or battens and not having a ceiling lining or having a ceiling lining fixed

    directly to the metal purlins, rafters or battens will have:

    a thermal break consisting anR-Valueof not less than 0.2 installed betweenthe metal sheet roofing and its supporting member.

    Cl.

    J1.3(E)

    Please note the thermal properties of various roof and ceiling construction foruse for calculation of R-Values.

    Cl.

    J1.5(A)

    (A) Provide certification that each part of the external wall that is part of theenvelope will comply with one of the options in Table J1.5a or table 1.5b.

    Cl.

    J1.5(E)

    (E) Please provide certification that the metal framed wall (required to achieve aTotal R-Value)that has lightweight external cladding such as weatherboard,fibre cement or metal sheeting (and does not have a wall lining or where thewall lining is fixed directly to the frame) will have:

    a thermal break installed between the metal frame and the external cladding

    and consists of a material with anR-Value of not less than 0.2.

    Note Specification J1.5 which contains wall construction thermal properties.

    Cl. J2.1 Please note the exemptions in the application of part for class 7,8,9b, atrium andsolariums.

    Cl. J2.3 Class 3

    An aggregate conductance and solar heat gain must be undertaken for theglazing in each storey of a sole-occupancy unit, public space or other occupiedspace and must not exceed specified allowances.

    AGGREGATE CONDUCTANCE

    To allow for an assessment to be undertaken please provide the followinginformation for conductance: The area of each section of glazing within each storey of the building. This

    should be in the form of a window schedule that indicates the area of theglazing only as well as the location of each window.

    The Total U-Value for each glazing element proposed. The Total U-valuefor the glazing is the thermal resistance in units of W/m

    2K. This

    information would be available from your glazing supplier. The floor areas for each room within the units, as well as for each public

    space or occupied space individually tabulated.

    Trevor R Howse & Associates Pty Ltd

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    31/38

    - 26 -

    Cl. J2.3

    contdAGGREGATE SOLAR HEAT GAIN

    To allow for an assessment to be undertaken please provide the followinginformation for solar heat gain:

    The solar exposure factor for each glazing element. This is obtained from

    table J2.3(b). To calculate the solar exposure factor the P/H number willalso need to be calculated using figure J2.4. Alternatively if you wish thisoffice to calculate the solar exposure factor please provide detailedsectional views of the building through each side of the building as aminimum so that eaves and balcony overhang dimensions may becalculated. If shading devices are proposed please provide details of each

    shade structure.

    Provide the Solar Heat Gain Coefficients (SHGC) for each piece of glazingproposed. This can only be obtained from the supplier of the glazing.

    Alternatively if the above information is not available at this stage of the

    development process compliance with this clause of the BCA may be

    undertaken at the Construction Certificate stage when all information isreadily available.

    Cl. J2.3

    or Cl.

    J2.4

    Class 6

    building

    < 500m2.

    See either J2.3 of J2.4

    Cl. J2.4 Classes 6 and 9b

    Note that this clause is only applicable to air-conditioned parts of thebuilding.

    The glazing in each storey of the building and facing each orientation must beassessed to determine the aggregate air-conditioning energy value to ensure that

    it does not exceed the allowance obtained by multiplying the area of the faade(orientation) by the energy index (see table J2.4(a).

    Please provide the following information for each window within the building: The area of each section of glazing within each storey of the building. This

    should be in the form of a window schedule that indicates the area of the

    glazing only as well as the location of each window. Provide the Solar Heat Gain Coefficients (SHGC) for each piece of glazing

    proposed. This can only be obtained by the supplier of the glazing. The Total U-Value for each glazing element proposed. This can only be

    obtained by the supplier of the glazing.

    The energy constants A, B and C. these are calculated using Table J2.4(b). Foreach window you first work out which way it is facing then note which climatezone it is within. For this project the development is proposed within climatezone 5.

    Trevor R Howse & Associates Pty Ltd

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    32/38

    - 27 -

    Cl. J2.4

    contd

    The heating shade multiplier for each glazed element (taken from tableJ2.4(c). This is a calculated as follows:

    First calculate G in the table. It is the height that the shading

    element is located above the top of the window/door head. P is the length the shade part of the building that extends horizontally

    to protect each opening. H is the height of the specified window. ThusP/H plus the orientation of the window (north south east west etc)allows you to calculate the heating shade multiplier by using tableJ2.4(c).

    The cooling shading multiplier for each glazed element (taken from table

    J2.4(d). This is calculated as follows:

    Take figures G and P/H from the above calculations. Then review theorientation within table 2.4(d) to determine the figure for the coolingshading multiplier.

    Alternatively the energy constants, heating shading multiplier and cooling

    shading multiplier can be calculated by this office to determine if compliance isachieved.

    To determine if compliance is achieved the aggregate air-conditioning energyvalue attributable to the glazing must not exceed the allowance obtained by

    multiplying the faade area of the orientation by the energy index in tableJ2.4(a). Note that where the air-conditioning energy value of a glazed

    element is less than zero the value must be taken as zero.

    Alternatively if the above information is not available at this stage of the

    development process compliance with this clause of the BCA may be

    undertaken at the Construction Certificate stage when all information is

    readily available.

    Cl. J2.5 Where a non-compliance occurs with respect to clauses J2.3 or J2.4 additionalshading of the openings will be required to be provided to achieve compliance.

    The requirement for any additional shading can only be confirmed once thecompliance status of clauses J2.3 and J2.4 are known.

    Cl. NSW

    J3.1

    Note: this section is not applicable in any parts of the building that are providedwith evaporative cooler air-conditioning only. It is also not applicable to the e-learning area of retail area if no air-conditioning is provided or to a part of abuilding where the mechanical ventilation required by Part F4 of the BCA

    provides sufficient pressurisation to prevent air infiltration.

    Cl. J3.4 Please provide certification that a seal to restrict air infiltration will be fittedto each edge of a door, openable window or the like . The seal must be

    either a foam seal , rubber compressible strip seal or fibrous seal (to restrictthe air infiltration) where to an openings that serves a conditioned space.

    Note that the above requirements do not apply to: a window complying with AS 2047; or a louvre door, louvre window or other such opening; or fire door; or a roller shutter door, roller shutter grille or other security door or device.

    Please provide certification that the main entrance to the building (if leadingto a conditioned space) will be fitted with a self-closing door.

    Trevor R Howse & Associates Pty Ltd

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    33/38

    - 28 -

    Cl. J3.5 Please provide certification that a miscellaneous exhaust fan (such as abathroom or domestic kitchen exhaust fan) will be fitted with a sealing devicesuch as a self-closing damper of the like when serving:

    a conditioned space.

    Cl. J3.6 Please provide certification that roofs, walls, floors and any openings such aswindows and doors will be constructed to minimize air leakage as detailed

    below:

    construction must provide for enclosure by internal lining systems that areclose fitting at ceiling, wall and floor junctions; or

    by the sealing using caulking, skirting, architraves, cornices or the like.

    Cl. J3.7 Please provide certification that any evaporative cooler will be fitted with a self-closing damper when serving a heated space.

    Cl. J5.2 Please provide certification that the air-conditioning system/unit will be capableof :

    being inactivated when the sole-occupancy unit, building or part of building

    is not occupied; and

    where the air-conditioning unit/system has motorized outside air and returndampers, that the dampers will close when the air-conditioning unit/systemis inactivated.

    having any supply and return ductwork insulated and sealed as perSpecification J5.2.

    when serving more than one sole-occupancy unit, air-conditioningzone or areas with different heating and cooling needs

    thermostatically control the temperature of each sole-occupancy unit,zone or area; and

    not control the temperature by mixing actively heated air and actively

    cooled air; and limit reheating to not more than 7.5K rise in temperature at the supply

    rate for the space served and may be increased or decreased at thesame rate that the supply air rate is respectively decreased orincreased.

    in a class 3 building be capable of controlling the temperature of a sole-occupancy unit at a different temperature during sleep periods than otherperiods.

    when the air flow exceeds 1000L/s, be designed so that the total motor shaftpower of the fans in the system does not exceed

    12 W/m2for a building not more than 500m

    2; or

    15W/m2for a building more than 500m

    3.

    Note that the requirements of (6) above are not applicable to

    fans in package A/C plant complying with clause J5.4(c); and the input power for an energy reclaiming system that pre conditions

    outdoor air; and the input power for process related components such as high

    efficiency particulate air filters.

    Trevor R Howse & Associates Pty Ltd

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    34/38

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    35/38

    - 30 -

    Cl.

    J5.4(B)

    ycomplying with table J5.4a, when tested in accordance with AS 7190.Please provide certification that a boiler must achieve a thermal efficienc

    J5.4(C)

    gg

    b when tested in accordance with AS/NZS 3823.1.2 at testcondition T1.

    Cl. Please provide certification that package air-conditioning equipment, includina split unit and a heat pump, will have an energy efficiency ration complyin

    with table J5.4

    J5.4(D)

    ve an

    g with table J5.4c when determined inaccordance with ARI 550/590.

    Cl. Please provide certification that a refrigerant chiller over 125kWr will ha

    energy efficiency ratio complyin

    J5.4(E)

    at rejectedfrom the refrigerant when determined in accordance with ARI 460.

    Cl. Please provide certification that any air cooled condenser fan motor, (other thanone that is part of package air-conditioning equipment listed in part (c) above),

    will not use more than 15W of motor shaft power for each kW of he

    J5.4(F)

    certification that the fan of a cooling tower will not use

    of motor shaft power for each L/s of

    , 590 W of motor shaft power for each L/s of cooling

    water circulated.

    Cl. Please provide

    more than if a propeller or axial fan, 310 Wcooling water circulated; andif a centrifugal fan

    J5.4(G)

    certification that the fan of a closer circuit cooler will not use

    of motor shaft power for each L/s of

    , 670 W of motor shaft power for each L/s of coolingwater circulated.

    Cl. Please providemore than

    if a propeller or axial fan, 500 Wcooling water circulated; andif a centrifugal fan

    J5.4(H)

    certification that the fan of a evaporative condenser will not use

    of motor shaft power for each kW of

    , 22 W of motor shaft power for each kW of coolingwater circulated.

    Cl. Please provide

    more than if a propeller or axial fan, 18Wcooling water circulated; andif a centrifugal fan

    J5.4(I)

    er

    n 150W of pump motor shaftpower for each L/s of spray water circulated.

    Cl. Please provide certification that the spray water pump of a closed circuit cool

    or evaporative condenser will not use more tha

    Cl. J5.5

    such as a stove in a commercial kitchen or a chemical bath in a

    riable speed fan; and

    Be designed to minimize the exhausting of conditioned air.

    PLY TO

    Please provide certification that a miscellaneous exhaust system with an air

    flow rate of more than 10,000L/s (that is associated with equipment having avariable demandfactory), will

    Have the means for the operator to reduce the energy used by the provision of a va stop the motor when the system is not needed.

    NOTE THAT THE ABOVE REQUIREMENTS DO NOT AP

    lation is needed to balance the required

    where air flow must be maintained for safe operation.

    a sole-occupancy unit of a class 3 parts of a building; or

    where additional exhaust venti

    outside air for ventilation; or

    Trevor R Howse & Associates Pty Ltd

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    36/38

    - 31 -

    Cl. J6.2

    (A)

    Provide certification that artificial lighting will

    not exceed the maximum lamp power density of table J6.2a; or in a bathroom, dressing room or the like, provide an average artificial light

    source efficacy of not less than 40 Lumens/W.

    Note that the maximum lamp power density in table J6.2a may be increasedby 30% for area of less than 20m

    2floor area; and

    (other than class 3 buildings) 40% where artificial lighting is switched by a

    motion detector or a corridor lighting timer in accordance with

    Specification J6; and

    15% where artificial lighting is switched (in response to varying natural

    lighting levels) by a daylight sensor and dynamic lighting control device in

    accordance with Specification J6.

    Cl.J6.2(B)

    In the class 6, 7a and 9b parts of the building please provide certification that

    for artificial lighting

    the aggregate design illumination load will not exceed the sum of theallowances obtained by multiplying the area of each space by themaximum illumination power density in table J6.2b and dividing bythe illumination power density adjustment factor in table J6.2c (where

    applicable).

    In the class 6, 7a and 9b parts of the building please provide certificationthat the aggregate design illumination power load in 1(i) above is the sumof the design illumination power loads in each of the spaces served.

    Cl.J6.2(C)

    In the class 6, 7a and 9b parts of the building please provide certification thatwhen determining the design illumination power load, {see (B) above}, that thefollowing will be used: where there are multiplying lighting systems serving the same space

    the total illumination power load of all systems; or

    for a control system that permits only one system to operate at a time,

    the design illumination lower load is

    based on the highest illumination power load; or

    determined by the formula {HxT/2 + P x (100-T/2)} as

    detailed within this clause of the BCA.

    Cl. J6.2

    (notes)

    Note: the requirements of (A) and (B) do not apply to:

    Emergency lighting in accordance with Part E4.

    Signage and display lighting within cabinets and display cases.

    A heater where the heater also emits light.

    Cl. J6.3

    (A)

    Please provide certification that artificial lighting will be individually operatedby a switch or other control device.

    Trevor R Howse & Associates Pty Ltd

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    37/38

    - 32 -

    Cl.

    J6.3(B)

    Please provide certification that an occupant activated device, such as a roomsecurity device, a motion detector in accordance with Specification J6or thelike, will be provided in the sole-occupancy units of the class 3 parts of thebuilding to cut power to artificial lighting, air-conditioner, local exhaust fans

    and bathroom heater, when the sole-occupancy unit is unoccupied.

    Cl.J6.3(C)

    Please provide certification that an artificial lighting switch will

    be located in a visible position

    in the room or space being switched; or

    in an adjacent room or space from where the lighting being switched is

    visible.

    not operate lighting within an area of more than

    250m2for a space of not more than 2,000m

    2floor area; or

    1,000m2for a space of more than 2,000m

    2floor area.

    Cl.

    J6.3(D)

    Please provide certification that artificial lighting in a building or storey of a

    building of more than 250m2will be controlled by

    a time switch in accordance with Specification J6; or

    an occupant sensing device such as a

    security card reader; or

    a motion detector in accordance with Specification J6.

    Cl.J6.3(E)

    Please provide certification that artificial lighting adjacent windows will beswitched separately from artificial lighting not adjacent windows.

    Cl.J6.3(F)

    NOTE

    Note: The requirements of (A)(B)(C)(D) and (E) do not apply to the following:

    emergency lighting in accordance with Part E4.

    Cl.

    J6.4(A)

    Please provide certification that artificial lighting for any interior decorative anddisplay lighting will be controlled

    separate controls to that of other artificial lighting; and

    by a time switch in accordance with Specification J6 (only applicable

    where the display lighting exceeds 7kW).

    Cl.J6.4(B)

    Provide certification that window display lighting will be controlled separately

    from other display lighting.

    Cl.J6.5(A)

    Provide certification that artificial lighting around the buildings perimeter will

    be controlled by either a daylight sensor or a time switch in accordance with

    Specification J6; and

    when the total perimeter lighting load exceeds 100 W

    have an average light source efficacy of not less than 60 Lumens/W; or

    be controlled by a motion detector in accordance with Specification J6

    Trevor R Howse & Associates Pty Ltd

  • 8/11/2019 07 0071 Unswhousing Ea Appsbcacompliance

    38/38

    - 33 -

    Cl.

    J6.5(A)

    (cont.)

    when used for decorative purposes (such as faade lighting or signage

    lighting), have a separate time switch in accordance with Specification J6.

    Note: the requirements of (2) above do not apply to

    emergency lighting in accordance with Part E4.

    Cl. J6.6 Provide certification that power supply to any boiling water or chilled waterstorage units will be controlled by a time switch in accordance with

    Specification J6.

    Cl. J7.2 Please provide certification that any hot water system used for food preparationand sanitary purposes will be designed and installed as per Section 8 of AS/NZS

    3500.4.

    CL. NSW

    J8.2

    Please provide certification that access for maintenance will be provided to

    all services and their components including:

    Time switches and motion detectors.

    Room temperature thermostats.

    Plant thermostats such as on boilers or refrigeration units.

    Outside air dampers.

    Reflectors, lenses and diffusers of light fittings.

    Heat transfer equipment.

    all adjustable or motorized shading devices.

    Author: Verified

    DRAFT DRAFT

    Jason Storer Hayden L Howse

    Technical Manager Managing Director

    forTrevor R. Howse & Associates Pty Ltd forTrevor R. Howse & Associates Pty Ltd