Upload
pmktvs
View
216
Download
0
Embed Size (px)
Citation preview
7/31/2019 05work Measurement
1/35
WORK MEASUREMENTThe objective of any work measurement system is todetermine the time it should take an average, trainedperson to perform a task
if he or she were doing that over an 8-hour day
under usual working conditions and working at a normal pace.
This time is called standard time.
There are two basic approaches to defining standardtime.
7/31/2019 05work Measurement
2/35
7/31/2019 05work Measurement
3/35
7/31/2019 05work Measurement
4/35
7/31/2019 05work Measurement
5/35
7/31/2019 05work Measurement
6/35
WHY WORK MEASUREMENTS
To determine efficiency of jobs
Determining equipment requirements.
Determining labor requirements.
Designing training methods.
Designing scheduling procedures.
Designing incentive systems.
Gauging work performance. Estimating cost.
7/31/2019 05work Measurement
7/35
THE TWO APPROACHESThe bottom-up
starts with a basic measurement of time, adjusts for operator pace, and then allows for fatigue, personal needs, and
delaysThe top-down
used in many labor contracts. It normally defines standard time as thattime under which a qualified employeeworking under usual conditions can make an
incentive pay (specified) percent above basepay.
7/31/2019 05work Measurement
8/35
SOME IMPORTANT DEFINITIONSNormal Time. The time required for an average, trained operator
to perform a task under usual working conditionsand working at a normal pace.
Normal Pace The pace of an average, trained, and
conscientious operator working over an 8-hourday.
Actual Time. The observed time required for an operator to
perform a task.
Allowances. The amount of time added to the normal time toprovide for personal needs, unavoidable delays,and fatigue.
7/31/2019 05work Measurement
9/35
DEFINITIONS
Qualified worker: physical sufficiency, intelligence,train and skills for safely working, quality andamount.
Determined task (Task bringing standard) :Task is reported point of view production methods
Determined productivity level: Qualified workerperforms task with great motivation and nonoverloading during on a day or one shift.Finally task gives average output.
Standard performance is the rate of output which
qualified workers will achieve without over-exertionas an average over the working day provided theyare motivated to apply themselves to their work.
7/31/2019 05work Measurement
10/35
METHODS OF DETERMINING
STANDARD TIMES. Direct time study.
Time study standard data.
Predetermined time systems.
Predetermined time systems standarddata.
Work sampling.
7/31/2019 05work Measurement
11/35
DIRECT TIME STUDY
Direct time study is a work measurementtechnique in which
A physical measurement is made of the
actual time required to do a task byusing a watch or some other timingdevice.
This measured time is then modified byconsidering the operator's pace, andfinally, allowances are added.
7/31/2019 05work Measurement
12/35
TIME STUDY BOARD
7/31/2019 05work Measurement
13/35
TIME SHEET FRONT SIDE
Date Name Sketch
Operation
Operator Dept
Part No.
Special Equipment
Left Hand Right Hand Element No. Feeds Speeds Special Tools, e tc.
Notes
7/31/2019 05work Measurement
14/35
TIME SHEET BACK SIDE
7/31/2019 05work Measurement
15/35
PROCESS The front of the sheet is for recording the
task being studied, the existing procedure indetail, and any other pertinent information.
The back of the sheet is for recording the
actual time study.The task is broken down into easily discernibleelements,
The elements are recorded, and then the timing
is done.The watch reading is recorded in column R,
( the watch does not stop) and the time foreach element is entered in column T later.
7/31/2019 05work Measurement
16/35
HOW IT WORKS
1. Establish the
standard jobmethod.
2. Break down the
job into elements
3. Study the job.
4. Rate the workersperformance
7/31/2019 05work Measurement
17/35
HOW IT WORKS(contd.)
5. Compute the average time
6. Compute the normal time
Nt=(t)(RF) or
Normal Time=(elemental average time)
(rating factor)
7. Compute the standard time
ST=(Nt)(1+AF) or
Standard Time=(Normal cycletime)(1+Allowance factor)
7/31/2019 05work Measurement
18/35
EXAMPLE Total actual time = 15 + 7 + 5 + 8 = 35
Performance rating = 115%
Normal time = (35)(1.15) = 40.25Allowances = 12%
Standard time = (40.25)(1.12) = 45.08
7/31/2019 05work Measurement
19/35
Experiencedworker
Trainee
DISTRIBUTION OFWORK TIMES
7/31/2019 05work Measurement
20/35
The reason for thejobadjustment factoris that the worker being
observed may be working at a rate different from the normal rate(working at a deliberately slow rate, natural abilities differ from the norm,
working at a rate to impress the observer). Thus the observedtime is
adjustedby this factor to yield a more accurate work pace.
performance rating = 1.0 indicates the worker is working at anormal rate
performance rating = .90 indicates the worker is working at 90%
of a normal rate
performance rating = 1.10 indicates that the worker is working
10% faster than a normal rate
Job Standard Time
7/31/2019 05work Measurement
21/35
SOME PRACTICAL PROBLEMS ?
Is the job ready for time study ?
Care During the Time Study
Dividing an Operation into Elements Taking and Recording of Data
Performance Rating
Allowances Number of observations to make
Foreign elements
7/31/2019 05work Measurement
22/35
IS THE JOB READY FOR A TIME
STUDY? Need correct method
Materials in specification
Correct machine speed
All other conditions of work in standardsettings
Lastly, would a motion study bringabout improvements?
7/31/2019 05work Measurement
23/35
DURING THE TIME STUDY
The time analyst should ask (for each phase):
Can the speed or feed be increased w/o hurting
quality? Can changes in tooling decrease cycle time?
Can materials be moved closer to work area?
Is equipment operating correctly, and a qualityproduct being produced?
Is the operation being performed safely?
7/31/2019 05work Measurement
24/35
REASONS FOR ELEMENT
BREAKDOWN Data is more readily reusable when each
element is described separately, esp. beginningand ending points.
Standard (estimated) time values may bedetermined.
Individual elements may be excessively short
(e.g., inspection), or too long. These can bepicked out more easily in element form.
This allows for separate performance ratings foreach.
7/31/2019 05work Measurement
25/35
DIVIDING AN OPERATION INTO
ELEMENTS1. The elements should be as short in duration as
can be accurately timed. (Not in individualhand motions, which are too short to time.)
2. Handling time should be separated frommachine time.
3. Constant elements should be separated from
variable elements (i.e., those that are sizedependent).
4. Regular elements are recorded first, then allothers.
7/31/2019 05work Measurement
26/35
TAKING AND RECORDING OF DATA
Continuous timing - records readings atthe end of each element as watch runs
Repetitive timing - after recording, watchis snapped back to zero at the end of eachelement
Multiple watches - connected by a lever;
one runs, another is stopped, another set togo
Electronic watch - may continue in splitmode
7/31/2019 05work Measurement
27/35
NUMBER OF OBSERVATIONS
When making a time studyseveral decisions are made to
assure desired results:
# of observations to make
Desired level of accuracy
Desired level of confidence for
the estimated standard time
Desired accuracy level is
typically expressed as a % of
the mean observed times The formula for determining
the number of observations
needed ?
n: number of observations
z: provides desired statisticalconfidence (e.g.: 1.96 for 95%)
s: observed standard deviation
in time required to complete thetask element
a: desired accuracy orprecision
x-bar: the mean observed timeto complete the task
2
x
s
a
zn
7/31/2019 05work Measurement
28/35
Pizza Place: To determine a standard time to prepare a large pepperoni and
cheese pizza. Analyst takes 10 observations of the 7 elements and calculates
the mean time and the standard deviation per element. He must then
calculate the # of observations needed so that the time estimate is to be
within 5% of the true mean 95% of the time.
The analyst must calculate the observations for each element to determine how
many additional observations must be taken. The maximum number of 25 (in this
case) for element #7 means that an additional 15 observations must be made and
then the observed times are revised.
nsobservatio250.24
0.03
0.05
1.96
x
s
a
zn
22
7
1
2
3
4
5
6
7
8
9
10
A B C D E
Example 11.3 Pat's Pizza Place
Standard Deviation Mean Observed Revised Observed
Work Element (minutes) Time (minutes) Time (minutes) # Observations
1. Get ball of dough 0.010 0.12 0.15 11
2. Flatten dough 0.030 0.25 0.25 233. Spin and toss dough 0.040 0.50 0.60 10
4. Place dough on counter 0.005 0.12 0.15 3
5. Pour sauce on formed dough 0.035 0.30 0.30 21
6. Place grated cheese on top 0.025 0.25 0.28 16
7. Place pepperoni on sauce 0.030 0.24 0.28 25
7/31/2019 05work Measurement
29/35
OTHER TIME FACTORS USED INCALCULATING STANDARD TIME
The normal time (NT) is the mean observed time multiplied by the
performance rating factor (PRF)
The PRFis a subjective estimate of a workers pace relative to a normal
work pace
The frequency of occurrence (F) is how often the element must be done
each cycle.
NT=(OT)(PRF)(F)
The allowance factor (AF) is the amount of time allowed for personal,
fatigue, and unavoidable delays
Standard Time=normal time x allowance factor, where:
(NT)(AF)ST
117.6%1.1760.151
1
PFD1
1AF WorkedTme
7/31/2019 05work Measurement
30/35
CALCULATING NORMAL TIME ANDSTANDARD TIME AT PATS PIZZA
The standard time for preparing a large, hand-tossed pepperoni pizza is 2.312minutes. This means that a worker can prepare 207 pizzas in an 8-hour shift(480 minutes divided by 2.312 minutes)
12
13
14
1516
17
18
19
20
2122
A B C D E F
Example 11.4 Calculating Standard Time for a Hand-Tossed Cheese and Pepperoni Pizza
Revised Observed Performance Rating Frequency Normal Time Standard Time
Work Element Time (minutes) Factor (minutes) (minutes)
1. Get ball of dough 0.15 0.90 1 0.135 0.1592. Flatten dough 0.25 1.00 1 0.250 0.294
3. Spin and toss dough 0.60 0.85 1 0.510 0.600
4. Place dough on counter 0.15 1.10 1 0.165 0.194
5. Pour sauce on formed dough 0.30 1.20 1 0.360 0.423
6. Place grated cheese on top 0.28 1.00 1 0.280 0.329
7. Place pepperoni on sauce 0.28 0.95 1 0.266 0.313Total Time 1.966 2.312
7/31/2019 05work Measurement
31/35
FOREIGN ELEMENTS
A foreign element is one that does not
explicitly belong in the sequence Examples:
Worker has to adjust glasses,
Must speak to supervisor,
Rest break, lunch break, Wrench breaks, must find new wrench.
Some foreign elements can be eliminated, but otherscannot or should not be.
Foreign elements can give the analyst an idea of howmuch extra time is reasonable to allow in anoperation.
7/31/2019 05work Measurement
32/35
CHECK LIST1. Secure and record information about the operation
and operator being studied.2. Orient the supervisor and the workers.
3. Improve the work methods.
4. Break the task into elements and record.
5. Observe and record the time taken by the operator.6. Determine the number of cycles to be timed.
7. Rate the operators performance.
8. Check to make certain that a sufficient number of
cycles have been recorded.9. Determine the allowances.
10. Determine the time standard for the operation.
11. Check and debug the standards with audits.
12. Implement with recall review in one month.
7/31/2019 05work Measurement
33/35
New Tools
With this PDA, youcan study elements,
time, performancerate, and statisticalconfidence intervalscan be created,edited, managed, and
downloaded to aspreadsheet
7/31/2019 05work Measurement
34/35
OTHER TIME STUDY METHODS
Elemental time data for typical work elements from
previously completed time studies can be stored in a
data base for use on future similar studies.
Predetermined time data (e.g. MTM and MTS) is a
larger database of valid work element times used to set
standards for common job elements
Reach, grasp, move, engage, insert, turn, etc. Work Sampling is a technique for estimating the
proportion of time a worker spends on an activity
7/31/2019 05work Measurement
35/35
Rating scales
BritishStandard
I.L.O.
AmericanStandard
StandardPerformance
Incentive
Normal
100 80
6075