Upload
pmahesh268
View
218
Download
0
Embed Size (px)
Citation preview
8/3/2019 05957295
1/8
468 IEEE TRANSACTIONS ON SMART GRID, VOL. 2, NO. 3, SEPTEMBER 2011
A Fault Steady State Component-Based Wide AreaBackup Protection Algorithm
Jing Ma, Member, IEEE, Jinlong Li, James S. Thorp, Life Fellow, IEEE, Andrew J. Arana, Qixun Yang, andA. G. Phadke, Life Fellow, IEEE
AbstractA novel wide area backup protection algorithm toidentify fault branch based on the fault steady state component isproposed. Under normal conditions of the power system, subsetsof buses called protection correlation regions (PCRs) are formedon the basis of the network topology and phasor measurement unit(PMU) placement. After the fault occurs, by analyzing the faultsteady state component of differential current in each PCR, thefault correlation region is confirmed and then a fault correlationfactor (FCF), is calculated in real time to locate the fault branch.The simulation results for the 10-generator 39-bus system verifythat this method is able to easily identify fault branch with limitedmeasurement points.
Index TermsFault correlation factor (FCF), PMU, protectioncorrelation region (PCR), wide area backup protection.
Symbols
incidence matrix of buses with PMUs.
incidence matrix of buses without PMUs.
incidence matrix between the buses with and
without PMUs.
bus admittance matrix.branch admittance matrix.
bus-branch incidence matrix.
bus injection current vector.
fault transient state bus voltage vector.
fault state transient branch current vector.
postfault variation of injection current vector.
bus voltage vector in the fault steady state
network.
Manuscript received September 23, 2010; revised April 29, 2011; acceptedMay 25, 2011. Date of current version August 24, 2011. This work was sup-ported by the project of National Science Foundation of China (No. 50907021,50837002), the Fundamental Research Funds for the Central Universities(11MG01), and 111 project (B08013). Paper no. TSG-00136-2010.
J.Ma is with theSchoolof Electrical andElectronicEngineering,NorthChinaElectric Power University, Changping District, 102206 Beijing, China, and alsowith the Bradley Department of Electrical and Computer Engineering, VirginiaPolytechnic Institute and State University, Blacksburg, VA 24061 USA.
J. Li and Q. Yang are with the School of Electrical and Electronic Engi-neering, North China Electric Power University, Changping District, 102206Beijing, China.
J. S. Thorp , A. J. Arana,and A. G. Phadke arewith theBradleyDepartmentofElectrical and Computer Engineering, Virginia Polytechnic Institute and StateUniversity, Blacksburg, VA 24061 USA.
Digital Object Identifier 10.1109/TSG.2011.2158861
branch current vector in the fault steady state
network.
faulted bus voltage vector.
faulted branch current vector.
virtual branch voltage vector.
normal branch voltage vector.
employed as FCF to identify the fault branch.
the fault steady state component of differentialcurrent injecting into each PCR.
I. INTRODUCTION
BACKUP protection systems traditionally have been self-
contained, and in general do not depend upon wide area
measurement information. With only local measurements con-
ventional backup protection can misoperate when the system
is highly stressed. In todays competitive environment, trans-
mission grids are more tightly interconnected, and transmission
lines are operated close to their limits, in order to maximize
power transfers and take advantage of different energy costs[1], [2]. It is appropriate to review traditional backup protection
and consider changes to meet todays competitive challenges.
Recommended practice in the National Grid Company is that
backup protection relies on earth fault overcurrent protection
and overreaching zone 2 and zone 3 distance protection [3], [4].
It is required for Zone 2 elements to detect earth and phase faults
on the busbar at the remote end of the feeder. Zone 2 elements
operate in typically 0.5 s. if the fault had not been cleared by
primary busbar protection, Zone 3 elements are required to de-
termine earth and phase faults on any transmission line which is
connected to the remote end of the main protected line. Zone 3
elements operate in typically 1.0 s. However, this practice often
encountered the problem of Zone 3 elements tripping on over-load.
With recent advances in communication, information, com-
puter networks and the significant development in phasor mea-
surement unit (PMU), technology today has the capability of ex-
panding the scope of the protection system [5][7]. The strategy
under investigation is the substitution of a PMU for the backup
relay, the system of PMUs must then provide all backup protec-
tion. Using the fault steady state component of PMU currents
and voltages, the problem of third zone relays tripping on over-
load can be overcome. Furthermore, the algorithm allows fast
operation compared with what is currently done, since it does
not need coordination between several protection zones. It is
1949-3053/$26.00 2011 IEEE
8/3/2019 05957295
2/8
MA et al.: A FAULT STEADY STATE COMPONENT-BASED WIDE AREA BACKUP PROTECTION ALGORITHM 469
Fig. 1. Fault steady state network of a generalized PCR.
now feasible, and timely, to apply more sophisticated protec-
tion algorithms with a wider view of the protected network so
that the high standards of dependability and security inherent in
modern protection systems can be maintained.
In addition, the impact of a fault on the whole network can
be minimized by precisely locating the fault branch and trip-
ping the minimum number of circuit breakers to isolate the fault.
There are two ways to identify the fault branch. One is imple-
mented by judging the open/closed states of circuit breakers and
the operational response of conventional protection relays on the
network [8], [9]. The other is achieved by analyzing branch cur-
rents throughout the network [10][13].To employ wide area measurement information more suffi-
ciently and effectively, this paper proposes an algorithm to pre-
cisely locate the fault branch by utilizing the fault steady state
component of the currents and voltages. Before the fault occurs,
the protection correlation regions (PCRs) are formed by ana-
lyzing network topology and PMU placement. After the fault
occurs, if the primary protection fails to operate, the wide area
backup protection will take over. The steady state component
of the differential current in each PCR is used to determine the
PCR in which the fault exists. The fault correlation factor (FCF)
in this region is calculated in real time to locate the fault branch.
The simulation results validate the proposed method.
II. FORMATION OF PROTECTION CORRELATION REGION
A. PMU Placement Rules Under Fault Conditions
It is no longer sufficient to know the bus voltage and the
branch current to determine the voltage at the other end of the
branch for the faulted branch. Knowledge of the voltage at both
ends of a branch is also insufficient to determine the branch cur-
rent if the fault is on that branch. With a fault on the system,
the following 2 PMU placement rules are no longer valid, as the
fault location is unknown and the fault may occur on any branch.
If bus voltage and branch current at one end of a branch are
known, bus voltage at the other end of the branch can becalculated.
Fig. 2. Fault steady state expanded network of the generalized PCR.
If bus voltages at both the ends of a branch are known, the
branch current can be calculated.
Alternatively, the following rules are valid even in the pres-
ence of a fault [14], [15].
If there is a PMU at a bus, the bus voltage and currents of
all the branches connected to the bus can be measured.
If a zero injection bus has n branches connected to it and
of the currents are known then the remaining current
can be calculated.
If n nonzero injection buses with PMUs are adjacent to
a zero injection network (no circuit loop in the network),
voltages and currents in the network can be calculated. Ifthere is a loop in the network, a PMU is added on the loop
to make the system observable.
B. Formation of Protection Correlation Region
On the basis of network topology and PMU placement, the
protection correlation region (PCR) is formed as follows.
Step 1: Generate the bus-bus incidence matrix A of the whole
network in the order of buses with PMUs in the
former lines and columns, and buses without PMUs
in the latter
(1)
where is the incidence matrix of buses with
PMUs. is the incidence matrix of buses without
PMUs. is the incidence matrix between the
buses with and without PMUs.
Step 2: Any two connected buses where both have PMUs
(hence in ) are formed into a protection correla-
tion region, defined as a specialized PCR.
Step 3: Connected buses in along with the buses to
which they are connected in form a general-
ized PCR.
The calculation of PCRs in is straightforward. The inci-dence matrix is formed from the branch data with and
8/3/2019 05957295
3/8
470 IEEE TRANSACTIONS ON SMART GRID, VOL. 2, NO. 3, SEPTEMBER 2011
if there is a branch connecting and . Spe-
cialized PCRs are formed from all off-diagonal entries in
which are not zero.
To find the generalized PCRs, the matrix is repeatedly
multiplied by itself [16]
(2)
until
(3)
The th entry of the th power of an incidence matrix is
known to give the number of different paths of length begin-
ning at and ending at [ ]. Multiply by a column of
ones, and then give a vector of integers indicating the connec-
tivity of the non-PMU buses
(4)
For the example in Section IV the resulting column has four
1s, two 2s, and six 6s. The interpretation is that four of the
non-PMU buses are not connected to any other non-PMU buses,
that 2 of the non-PMU buses are connected to each other, and
that the remaining 6 buses are connected to each other. The ma-
trix then gives the PMU buses that are connected to these
groups of non-PMU buses and defines the generalized PCRs.
For example if the six interconnected non-PMU buses are (5, 6,
10, 11, 13, 14) then all the PMU buses connected to these six
buses (4, 7, 8, 12, 15, 31, 32) combined with the six non-PMU
buses form a large generalized PCR. More details are in the ex-
ample in Section IV.
III. FAULT BRANCH LOCATION ALGORITHM
A. Basic Theory
When a fault occurs in the power system, the superposition
theorem [17], [18] allows us to consider the currents and volt-
ages as containing a prefault component, a fault transient com-
ponent and a fault steady state component.
Assume generators and loads to be current injection sources.
The bus voltage vector and branch current vector in the
prefault network are given by
(5)
where is bus admittance matrix, is branch admittance
matrix, is bus-branch incidence matrix, and is the bus
injection current vector.
The variation of the injection currents after the fault inception
results in the transient process. Therefore, the bus voltage vector
and branch current vector in the fault transient state
network are given by
(6)
where is postfault variation of injection current vector.
In the fault steady state network, the bus voltage vector
and branch current vector are given by
(7)
where is the faulted bus voltage vector, and is thefaulted branch current vector.
During normal conditions, the fault steady state compo-
nent of differential current injecting into each PCR is calculated
to monitor the system status. If a fault occurs somewhere in the
system, the primary protection should determine the fault within
typically 11.5 cycles. After this period plus breaker time, if the
fault still persists, indicated by in some PCR,
the decision-making unit will take over and perform its backup
function. Then a fault branch location mechanism based on fault
correlation factor (FCF) is activated in this PCR until the fault
branch is inferred.
B. Fault Correlation Factor
A fault steady state network of a generalized PCR, containing
interconnected non-PMU buses along with PMU buses, is
shown in Fig. 1.
The PMU buses are connected to the non-PMU buses
via branches. and are the branch impedance and
the ground admittance of the th branch respectively, where
. are voltages of the PMU buses.
are voltages of the non-PMU buses.
are branch currents flowing from the PMU
buses. are branch currents flowing into
the non-PMU buses. Assume a fault occurs on the branch ,
and the distance between fault point and bus accounts for
percent of the total branch length. The current injection from
fault point to the network is .
To determine the fault branch, the non-PMU buses and the
PMU buses are needed to be expanded to buses. As shown
in Fig. 2, the network has been changed by connecting the new
buses with original buses via virtual zero-impedance branches.
Consider as injection currents of the
non-PMU network (blocks in Figs. 1 and 2). The bus voltage
vector and branch current vector can be expressed as
(8)
where and constitute the partitioned bus
impedance matrix
......
...
... ... ...
8/3/2019 05957295
4/8
MA et al.: A FAULT STEADY STATE COMPONENT-BASED WIDE AREA BACKUP PROTECTION ALGORITHM 471
Fig. 3. Ten-generator 39-bus New England test system.
TABLE IPMU PLACEMENT RESULT
Injection currents corresponding to nonfault branches are
(9)
where , and .
The injection current corresponding to the fault branch is
- (10)
Substitute (9) and (10) into , and
voltage vector of buses can be expressed as
...
...
...
...
...
...
(11)
Assume the fault branch to be nonexistent and the injection
currents of all branches to be calculated as (9). Then the virtual
voltage vector of buses is obtained
...
...
...
.
..
(12)
TABLE IITOPOLOGY ANALYSIS OF THE SPECIALIZED PCRS
Also, the virtual branch voltage vector is calculated as
...
...
...
...
...
...
...
...
(13)
where .
Using (9), the normal branch voltage vector is given by
(14)
The difference between the virtual branch voltage vector
and the normal branch voltage vector is
...
...
...
...
(15)
Vector is defined as
...
...
...
...
(16)
8/3/2019 05957295
5/8
472 IEEE TRANSACTIONS ON SMART GRID, VOL. 2, NO. 3, SEPTEMBER 2011
TABLE IIITOPOLOGY ANALYSIS OF THE GENERALIZED PCRS
Fig. 4. Fault steady state differential currents in different PCRs when a single-phase fault occurs.
where is a diagonal matrix and is formed by the th column
of . .
Let . Vector is
defined as
(17)
If ,
...
...
...
...
(18)
where
Fig. 5. Fault steady state differential currents in different PCRs when a three-phase fault occurs.
TABLE IVTHE CALCULATED FCFS OF BRANCHES 1 ; 2 AND 3
If ,
...
...
...
...
(19)
From (18) and (19), we can find that if branch is not the fault
branch, all entries in the vector are different from each other.
Or else, all entries in the vector are identical except the th
entry. The maximum absolute difference between entries in the
vector (except the th entry) is given by
(20)
is employed as FCF to identify the fault branch. If only
of some branch is less than a thresholdthe decision-making unit
determines that a fault occurs on that branch and trip the fault. If
of each branch is more than a threshold, the decision-making
unit determines that there is a fault in the non-PMU network. In
this case, voltages of buses and corresponding
branch currents are calculated by (9) and (14). Then, the above
procedure is executed repeatedly until fault branch is located.
IV. TESTING RESULTS AND ANALYSIS
The 10-generator 39-bus New England test system [19] is
used to demonstrate the effectiveness of proposed PCR forma-
tion method and wide area backup protection algorithm. The
system structure is shown in Fig. 3 and there is no circuit loop
in any zero-injection network.
By adopting three rules in Section II, PMUs are only needed
to be placed at the nonzero injection buses to make the system
observable. The result of PMU placement is shown in Table I.On the basis of power network topology and PMU placement
8/3/2019 05957295
6/8
MA et al.: A FAULT STEADY STATE COMPONENT-BASED WIDE AREA BACKUP PROTECTION ALGORITHM 473
result, bus-bus incidence matrix is obtained. and
are given in (21)(23), at the bottom of the page.
Any two connected buses where both have PMUs (hence in
) are formed into a specialized PCR, as shown in Table II.
(21)
(22)
(23)
8/3/2019 05957295
7/8
474 IEEE TRANSACTIONS ON SMART GRID, VOL. 2, NO. 3, SEPTEMBER 2011
To find the generalized PCRs, the matrix is repeatedly
multiplied by itself. When . Multiply
by a column of ones, and then the vector of integers indicating
the connectivity of the non-PMU buses is as follows:
(24)
From (24), it can be found that non-PMU buses 9, 17, 19, and22 are not connected to any other non-PMU buses, non-PMU
buses 1 and 2 are connected to each other, and non-PMU buses
5, 6, 10, 11, 13, and 14 are connected to each other. The matrix
then gives PMU buses that are connected to these groups
of non-PMU buses and defines generalized PCRs as shown in
Table III.
A. Fault Correlation Region Determination
There are three branches in PCR 21: (16-19), (20-19)
and (33-19). A single-phase earth fault and a three-phase fault
were applied separately at branch (16-19) at the 5 cycle (0.1
s). The fault steady state components of the differential currents
of all PCRs in both cases are calculated and shown in Figs. 4
and 5, respectively.
In each case, the calculated steady state component of the dif-
ferential current of PCR 21 is very noticeable, whereas steady
state components of different currents in other PCRs are negli-
gible and only have little variation resulting from the measure-
ment and calculation errors. These results are in accordance with
the practical state of the power system and prove that the method
is effective to identify the fault correlation region no matter what
type of fault.
B. Fault Branch Location
Various types of faults with values of fault resistances 0 ohmsand 300 ohms are adopted to test the effectiveness and reliability
of the FCF. The calculated FCFs of branches and are
shown in Table IV. The values of FCFs of the faulted branch
are no more than 0.238, whereas the values of FCFs of nonfault
branches and are no less than 43.997. These results prove
that it is effective and sensitive to locate the fault at branch by
this method.
V. CONCLUSION
A fault steady state component-based method to precisely lo-
cate the fault branch is proposed. Before the fault occurs, the
protection correlation region (PCR) is formed by analyzing net-work topology and the PMU placement. After the fault occurs,
the fault correlation region is determined by calculating the fault
steady state component of the differential current in each PCR
and the fault correlation factor (FCF) in this region is calculated
in real time to locate the fault branch. The simulation results
validate the proposed methods and show that they are effective
for the identification of various types of faults. In the real world,
there may be many non-PMU buses which are connected only to
other non-PMU buses, but these connected non-PMU buses as
a network are finally surrounded by boundary PMU buses. If a
fault occurs in the non-PMU buses network, including the case
of a fault occurring between 2 non-PMU buses, the algorithm
first detects the fault between the boundary PMU buses and thenon-PMU buses connected to them. If no fault occurs between
these buses, the voltages of the non-PMU buses adjacent to the
boundary PMU buses and corresponding branch currents can be
calculated. Therefore, these non-PMU buses can be equivalent
to the PMU buses. Then, the fault branch location mechanism
is executed repeatedly until the fault branch is inferred.
ACKNOWLEDGMENTMany faculty members and students contribute greatly to this
research. The authors would like to thank Dr. Yilu Liu.
REFERENCES
[1] M. G. Adamiak, A. P. Apostolov, M. M. Begovic, C. F. Henville, K.E. Martin, G. L. Michel, A. G. Phadke, and J. S. Thorp, Wide areaprotectionTechnology and infrastructures, IEEE Trans. Power Del.,vol. 21, pp. 601609, Apr. 2006.
[2] M. Zima, T. Krause, and G. Andersson, Evaluation of system pro-tection schemes, wide area monitoring and control systems, in Proc.6th Int. Conf. Adv. Power Syst. Control, Oper., Manage. , Hong Kong,2003, pp. 754759.
[3] A.G. PhadkeandJ. S.Thorp, ComputerRelayingfor PowerSystems.Taunton, U.K.: Research Studies Press, 1988.
[4] P. M. Anderson, Power System Protection. New York: IEEE Press,1999.
[5] A. Suranyi,J. Bertsch, andP. Reinhardt, Useof wide area monitoring,protection and control systems to superviseand maintain power systemstability, in Proc. 8th IEE Int. Conf. AC DC Power Transm., 2006, pp.200203.
[6] A. G. Phadke, Synchronizedphasor measurements in power systems,IEEE Comput. Appl. Power, vol. 6, pp. 1015, Apr. 1993.
[7] A. G. Phadke and J. S. Thorp, History and applications of phasormeasurements, in Proc. 2006 IEEE PES Power Syst. Conf. Expo., pp.331335.
[8] J. C. Tan,P. A. Crossley, D. Kirschen,J. Goody, andJ. A. Downes, Anexpert system for the back-up protection of a transmission network,
IEEE Trans. Power Del., vol. 15, pp. 508514, Apr. 2000.[9] J. C. Tan, P. A. Crossley, P. G. McLaren, I. Hall, J. Farrell, and P.
Gale, Sequential tripping strategy for a transmission network back-up
protection expert system, IEEE Trans. Power Del., vol. 17, pp. 6874,Jan. 2002.[10] Y. Serizawa, M. Myoujin, K. Kitamura, N. Sugaya, M. Hori, A.
Takeuchi, I. Shuto, and M. Inukai, Wide-area current differentialbackup protection employing broadband communications and timetransfer systems, IEEE Trans. Power Del., vol. 13, pp. 10461052,Oct. 1998.
[11] K. Kangvansaichol and P. A. Crossley, Multi-zone differential pro-tection for transmission networks, in Proc. 8th IEE Int. Conf. De-velop. Power Syst. Protection, Amsterdam, The Netherlands, 2004, pp.428431.
[12] J. S. Thorp, A. G. Phadke, S. H. Horowitz, and M. M. Ekgovic, Someapplications of phasor measurements to adaptive protection, IEEETrans. Power Del., vol. 3, pp. 791798, May 1988.
[13] Y. Serizawa, H. Imamura, and M. Kiuchi, Performance evaluation ofIP-based relaycommunications for wide-areaprotection employing ex-ternal time synchronization, in Proc Power Eng. Soc. Summer Meet.,
Jul. 1519, 2001, pp. 909914.[14] S. Chakrabarti and E. Kyriakides, Optimal placement of phasor mea-
surement units for power system observability, IEEE Trans. PowerSyst., vol. 23, pp. 14331440, Aug. 2008.
[15] N. H. Abbasy and H. M. Ismail, Unified approach for the optimalPMU location for power system state estimation, IEEE Trans. PowerSyst., vol. 24, pp. 806813, May 2009.
[16] O. A. Amoda and N. N. Schulz, An adaptive protection scheme forshipboard power systems, in 2007 IEEE Electric Ship Technol. Symp.,pp. 225230.
[17] H. Gao and P. A. Crossley, Directional relay for EHV transmissionlines using positive sequence fault components, in 2005 IEEE RussiaPower Tech., 2004, pp. 15.
[18] V. V. Terzija and Z. M. Radojevic, Numerical algorithm for adaptiveautoreclosure and protection of medium-voltage overhead lines, IEEETrans. Power Del., vol. 19, pp. 554559, Apr. 2004.
[19] T. S. Bi, X. H. Qin, and Q. X. Yang, A novel hybrid state estimatorfor including synchronized phasor measurements, Elect. Power Syst.Res., vol. 78, pp. 13431352, Aug. 2008.
8/3/2019 05957295
8/8
MA et al.: A FAULT STEADY STATE COMPONENT-BASED WIDE AREA BACKUP PROTECTION ALGORITHM 475
Jing Ma (S06M08) was born in Hebei Province,China, on February 25, 1981. He received the B.S.and Ph.D. degrees from North China Electric PowerUniversity, Beijing, in 2003 and 2008, respectively.
He is currently an Associate Professor in theSchool of Electrical and Electronic Engineering,North China Electric Power University. He wasa Visiting Scholar in the Bradley Department of
Electrical and Computer Engineering, VirginiaPolytechnic Institute and State University, from2008 to 2009. His major interests include wide-area
protection and control.
Jinlong Li received the B.S. degree from ZhengzhouUniversity in 2007. He is currently working towardthe M.S. degree in the School of Electrical and Elec-tronic Engineering, North China Electric Power Uni-versity, Beijing.
His interests mainly include wide area powersystem measurement, dynamic analysis, and backupprotection.
James S. Thorp (S58M63SM80F89LF03)received the B.E.E., M.S., and Ph.D. degrees fromCornell University, Ithaca, NY, in 1959, 1961, and1962, respectively.
He was the Charles N. Mellowes Professor in En-gineering at Cornell University from 1994 to 2004.He was the Director of the Cornell School of Elec-trical and Computer Engineering from 1994 to 2001,a Faculty Intern, American Electric Power ServiceCorporation in 19761977, and an Overseas Fellow,ChurchillCollege, CambridgeUniversityin 1988. He
is currently the Hugh P. and Ethel C. Kelley Professor of Electrical and Com-
puter Engineering and Department Headof the Bradley Department of Electricaland Computer Engineering, Virginia Polytechnic Institute and State University,Blacksburg.
Prof. Thorp was an Alfred P. Sloan Foundation National Scholar and waselected a Member of theNationalAcademyof Engineering in 1996. He receivedthe 2001 Power Engineering Society Career Service award, the 2006 IEEE Out-standing Power Engineering Educator Award, and shared the 2007 BenjaminFranklin Medal with A. G. Phadke.
Andrew J. Arana received the B.S. degree inelectrical engineering with the Sexton Distinctionfrom Dalhousie University, Halifax, NS, Canadain 2005 and the M.S. degree from Virginia Techin 2007. He is currently a Ph.D. candidate in theBradley Department of Electrical and ComputerEngineering at Virginia Polytechnic Institute andState University, Blacksburg.
His research interests include wide-area mon-itoring, analysis of electromechanical travellingwaves, relaying technology, and adaptive protection.
Qixun Yang was born in Shanghai, China, onOctober 30, 1937. He received the B.S. and Ph.D.degrees from Zhejiang University, China, and SouthWales University, Australia, in 1960 and 1982,respectively.
He is currently a Chinese academician of engi-neering and a Professor of North China ElectricPower University, Beijing. He is also the BoardChairman of Beijing Sifang Automation Co., Ltd.His research interests include power system protec-tion and control, and substation automation.
A. G. Phadke (M64SM97F80LF04) receivedthe B.Sc., B.Tech. (Hons.), M.S., and Ph.D. degreesfrom Agra University, IIT, Khargpur, IIT, Chicago,and the University of Wisconsin, Madison, in 1955,1959, 1961, and 1964 respectively.
He is a University Distinguished Professor (Emer-itus) at Virginia Polytechnique Institute and StateUniversity, Blacksburg. His primary research areais the microcomputer-based monitoring, protection,and control of power systems. He is a coauthorof two books on relaying: Computer Relaying for
Power Systems and Power System Relaying, and is the editor of and contributorto the bookHandbook of Electrical Engineering Computations.
Dr. Phadke was awarded the IEEE Third Millennium Medal in 2000, namedthe Outstanding Power Engineering Educator by the IEEE in 1991, and receivedthe Power Engineering Educator Award of the EEI in 1986. He received theIEEE Herman Halperin Transmission and Distribution award in 2000. He wasthe Chairman of the Technical Committee of USNC CIGRE, and Editor-In-Chief of IEEE TRANSACTIONS ON POWER DELIVERY. He was elected to the U.S.National Academy of Engineering in 1993. He was awarded Honorary Doc-torate by INP Grenoble, Grenoble, France in 2006.