05-projectscopemanagement-101018054753-phpapp02

  • Upload
    ouss860

  • View
    212

  • Download
    0

Embed Size (px)

Citation preview

  • 7/27/2019 05-projectscopemanagement-101018054753-phpapp02

    1/24

    5 - Project Scope ManagementProject Management Training

    Created by [email protected], June 2010

  • 7/27/2019 05-projectscopemanagement-101018054753-phpapp02

    2/24

    Project Scope Management

    KnowledgeArea

    Process

    Initiating Planning ExecutingMonitoring &

    ContolClosing

    ScopeCollect Requirements

    Define Scope

    Create WBS

    Verify Scope

    Control Scope

    Enter phase/

    Start project

    Exit phase/

    End project

    Initiating

    Processes

    Closing

    Processes

    PlanningProcesses

    Executing

    Processes

    Monitoring &

    Controlling Processes

  • 7/27/2019 05-projectscopemanagement-101018054753-phpapp02

    3/24

    Project Scope Management

    Process to ensure that the project includes all-and-only the workrequired, to complete the project successfully

    Scope can refer to Product Scope & Project Scope

    Scope Management Plan (part of Develop Project Mgmt Plan)

    How will I do the scope?

    Provides guidance on how project scope will be defines, documented, verified,

    managed, and controlled by project management team

    Dont assume that requirements were determined before project began (not part

    of the project)

    Attitude to say no to unnecessary scope. It should go to project approval

    process

  • 7/27/2019 05-projectscopemanagement-101018054753-phpapp02

    4/24

    5.1 Collect Requirements

    The process of defining and documenting stakeholders needs to meet the

    project objective

    Balance stakeholders requirement: prioritizing requirement & resolve

    conflicts

    Inputs

    1. Project charter

    2. Stakeholder register

    Tools &

    Techniques1. Interviews

    2. Focus groups

    3. Facilitated workshops

    4. Group creativitytechniques

    5. Group decision makingtechniques

    6. Questionnaires andsurveys

    7. Observations

    8. Prototypes

    Outputs

    1. Requirementsdocument

    2. Requirementsmanagement plan

    3. Requirementstraceability matrix

  • 7/27/2019 05-projectscopemanagement-101018054753-phpapp02

    5/24

    Collect Requirement Techniques (1)

    INTERVIEWS: Directly talk with stakeholders

    FOCUS GROUPS: Interactive discussion with qualified Stakeholders & Subject

    matter experts

    FACILITATED WORKSHOPS: Focused cross functional stakeholders.

    JAD Joint application design,

    QFD Quality function development

    Helps determine critical characteristic of new product development

    Start by collecting customer need - VOC: Voice of the Customers

  • 7/27/2019 05-projectscopemanagement-101018054753-phpapp02

    6/24

    Collect Requirement Techniques (2)

    GROUP CREATIVITY TECHNIQUES:

    Brainstorming,

    Nominal group technique: enhance brainstorming with voting and ranking

    Delphi Technique: some expert answer questionnaire and give anonimity

    feedback

    Idea/mind mapping, Affinity Diagram: sort idea into groups

    GROUP DECISION MAKING TECHNIQUES:

    Unanimity,

    Majority (>50%),

    Plurality,

    Dictatorship

  • 7/27/2019 05-projectscopemanagement-101018054753-phpapp02

    7/24

    Affinity Diagram

    Requirement sorted into groups by similarities

    Easier to see additional scope (risk) that have not been identified

    Image Source: PMP Exam Preparation 6th Edition, Rita Mulcahy

  • 7/27/2019 05-projectscopemanagement-101018054753-phpapp02

    8/24

    Collect Requirement Techniques (3)

    QUESTIONNAIRE AND SURVEYS: wide number of respondents

    OBSERVATION/JOB SHADOWING: viewing individual in their environment

    PROTOTYPES: early feedback by providing a working model

  • 7/27/2019 05-projectscopemanagement-101018054753-phpapp02

    9/24

    Balance Stakeholders Requirement

    There is a need to balancestakeholders requirement

    Some issue are so complex they cannot be resolved by PM alone

    Facilitate the resolution of competing requirement, consider:

    business case,

    project charter,

    project scope statement,

    project constraints

    What you can do:

    Conflict resolution, team building, meeting, problem solving skills, escalation,approval from stakeholder

    Stakeholder request to do or add something that is not related to the

    reason of project created should be rejected!

  • 7/27/2019 05-projectscopemanagement-101018054753-phpapp02

    10/24

    Requirement Document

    Output of the Collect Requirement process Helps make sure the requirements clear and unambiguous.

    How will we know if the work we do will acceptability meet this

    requirement?

    Rule of thumb

    Specific (Unambiguous)

    Measurable (How will we know we have finished?) Achievable (Can we do it?)

    Relevant (Is it the right thing to do?)

    Timed (When will we do it?)

  • 7/27/2019 05-projectscopemanagement-101018054753-phpapp02

    11/24

    5.2 Define Scope

    Process of developing a detailed description of the project and product

    Project scope statement may includes product scope, deliverables,product acceptance criteria, out of scope, additional risk, constraints &

    assumptions

    Inputs

    1. Project charter

    2. Requirementsdocumentation

    3. Organizational processassets

    Tools &

    Techniques1. Expert judgment

    2. Product analysis

    3. AlternativesIdentification

    4. Facilitated workshops

    Outputs

    1. Project scope statement

    2. Project documentupdates

  • 7/27/2019 05-projectscopemanagement-101018054753-phpapp02

    12/24

    Define Scope

    Concern with what is and is not included in the project and itsdeliverables

    You should maintain a realistic schedule and budget that can

    achieve the projects scope

    Iteration process should be done to maintain it Looking for options to adjust the project

    Analyze the objective and description of the product stated by thecustomer/sponsor and turn them into tangible deliverables.

    Project lifecycle term

    Product Analysis

  • 7/27/2019 05-projectscopemanagement-101018054753-phpapp02

    13/24

    Project Scope Statement

    The primary result of the Define Scope process Along with the WBS and WBS dictionary, comprise the scope

    baseline is part of project management plan.

    May includes: Product scope

    Deliverables

    Product acceptance criteria

    What is not part of the project (out of scope)

    Additional risks

    Constraints and assumptions :

    Constraints: factors that limit the teams options

    Assumptions: Things that assumed to be true (may not be true)

  • 7/27/2019 05-projectscopemanagement-101018054753-phpapp02

    14/24

  • 7/27/2019 05-projectscopemanagement-101018054753-phpapp02

    15/24

    Create WBS

    WBS includes the project management works.

    Work package: lowest level WBS component which can be scheduled, costestimated, monitored and controlled.

    WBS Structure can be organized by Phases

    Major deliverables

    Subprojects e.g. contracted work Beware ofexcessive decomposition. It can lead to non-productive management

    effort, inefficient use of resources (performing work)

    Control account: management control point for performance measurement (one

    or more work packages)

    WBS dictionary provides more detailed components, e.g. description of work,responsible organization, acceptance criteria

    Agreed Scope baseline includes project scope statement, WBS, WBS dictionary

  • 7/27/2019 05-projectscopemanagement-101018054753-phpapp02

    16/24

    WBS Sample

    Image Source: Practice Standard for WBS 2nd Edition. PMI 2006

  • 7/27/2019 05-projectscopemanagement-101018054753-phpapp02

    17/24

    WBS

    100% rule: WBS includes 100% of the work defined by project scope and

    capture ALL deliverables (external, internal, interim) in term of work to becompleted including project management.

    WBS creation method:

    Top-Down

    Bottom up

    WBS Standard

    WBS Templates

    Dont mind with WBS view

    Outline View

    Tabular View Tree structure view (vertical, horizontal, centralized)

  • 7/27/2019 05-projectscopemanagement-101018054753-phpapp02

    18/24

    WBS Dictionary Sample

    Includes (but not limited to):

    Code of account identifier

    Description of work

    Responsible organization

    List of schedule milestone

    Associated schedule activities

    Resource required

    Cost estimates

    Quality requirements

    Acceptance criteria

    Technical references

    Contract Information

    Image Source: Practice Standard for WBS 2nd Edition. PMI 2006

  • 7/27/2019 05-projectscopemanagement-101018054753-phpapp02

    19/24

    Source: http://www.brighthub.com/office/project-management/articles/52388.aspx

    WBS Dictionary Sample (2)

  • 7/27/2019 05-projectscopemanagement-101018054753-phpapp02

    20/24

  • 7/27/2019 05-projectscopemanagement-101018054753-phpapp02

    21/24

    Verify Scope

    Different with quality control which concerned with correctness

    of deliverables. Can be performed before or parallel

    NOT making sure you have the right scope during project

    planning

    But, to gain formal acceptance of deliverables during monitoringand control.

    Inspection = review, product reviews, audits, walkthroughs

    Measuring, examining, verifying to determine work and deliverables aremeet requirement & product acceptance criteria

  • 7/27/2019 05-projectscopemanagement-101018054753-phpapp02

    22/24

    Control Scope

    Process ofmonitoring the status of the project and product scope and

    managing changes to the scope baseline The cause and degree of variance relative to the scope baseline

    Decide corrective/preventive action required

    Inputs

    1. Project managementplan

    2. Work performanceinformation

    3. Requirementsdocument

    4. Requirement traceabilitymatrix

    5. Organizational processassets

    Tools &

    Techniques1. Variance analysis

    Outputs

    1. Work performancemeasurements

    2. Organizational processassets updates

    3. Change requests4. Project management

    plan updates

    5. Project documentupdates

  • 7/27/2019 05-projectscopemanagement-101018054753-phpapp02

    23/24

    Control Scope

    Relation with Perform Integrated Change Control Process

    Need for scope

    change during

    Control Scope

    Potential impact to scope

    found in Control Cost, Control

    Schedule, etc.

    Perform

    Integrated Change Control

    * Accept or reject the change? *

    Return to Control

    Scope to process

    the approved

    change

    Image redrawn from: PMP Exam Preparation 6th Edition, Rita Mulcahy

  • 7/27/2019 05-projectscopemanagement-101018054753-phpapp02

    24/24

    Thank You

    Next topic:

    Project Time Management

    http://www.animationfactory.com/http://www.animationfactory.com/