Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
105 July 2010
INDEX
1. IPLOCA’s Novel Construction Initiative
2. The elements of Successful pipeline projects
3. Resulting Document
4. Future Developments
5. Q & A205 July 2010
1. IPLOCA’s Novel Construction Initiative
Objectives of the Novel Initiative in 2004:
• Improve laying efficiency and standards of large diameter pipelines.
• Get better, safer and environmentally sound installation.
305 July 2010
1. IPLOCA’s Novel Construction Initiative
The initiative Group was focused in:
• Technology innovation» Land Train method» Mechanized Tie Ins» Other Innovative Ideas
• Target 35% Cost Reduction405 July 2010
1. IPLOCA’s Novel Construction Initiative
BASIC QUESTIONS:
Is Technology the key driver for cost reduction?
or,
Is cost reduction primarily governed by a sound Process?
505 July 2010
6
This is what we also want to avoid…
..• v
605 July 2010
1. IPLOCA’s Novel Construction Initiative
The objectives were revised in 2007:
Considering the number of pipeline projects which incurred schedule and cost overruns
a broader
perspective was given to the Initiative.
All phases of the Pipeline Projects were reviewed from Early Developments through Design, Construction and Commissioning…
705 July 2010
1. IPLOCA’s Novel Construction Initiative
Six Working Groups integrated by Oil & Gas Companies and IPLOCA members were organized:
» Planning, Design and Control (PDC)» Contract and Risk Sharing (CRS)» Earthworks (EW)» External Pipeline Protection Systems (ECPS)» Facing, Line-up and Welding (FLUW)» Laying and Lowering-in (L&L)
805 July 2010
2. The elements of Successful pipeline projects
905 July 2010
10
2. The Elements of Successful Pipeline Projects (source: Independent Project Analysis Inc.)
1005 July 2010
2. The Elements of Successful Pipeline Projects
Drivers:
Integrated Team
Best Front End Loading
VIP’s Practices
Discipline & Continuity
Best Practices and Control
Our work focused in:
SOLID BASIC DATA
FRONT END LOADING STEPS
SITE FACTORS
CONSTRUCTABILITY
TECHNOLOGY SELECTION
CLEAR SCOPE OF WORK
CONTRACT CONDITIONS
PROJECT EXECUTION PLAN
MANAGEMENT OF RISKS & CHANGES
PROCESS & EQUIP. SIMPLIFICATION
SOUND PROJECT CONTROL05 July 2010 11
3. Resulting Document
Our book: “The Road to Success”
Volume One:» Main Body (First Edition).
Volume Two:» Appendices
1205 July 2010
3. Volume One. The Road to Success- Preface and Introduction 1 Executive Summary2 Development Phases of Pipeline Project3 The Baseline of a Contract4 Analysis and Mitigation of Risks5 Management of Construction Risks6 Best Practices7 New Trends and Innovation- Bibliography / Acknowledgements
The Joint Approach- To whom the document is addressed- The objectives of the Road- Challenges and Rewards of pipeline projects- Key Principles to avoid disasters- Presentation of the Road
1305 July 2010
3. Volume One. The Road to Success- Preface and Introduction 1 Executive Summary
2 Development Phases of Pipeline Project3 The Baseline of a Contract4 Analysis and Mitigation of Risks5 Management of Construction Risks6 Best Practices7 New Trends and Innovation- Bibliography / Acknowledgements
- FEL 1: Business Planning- FEL 2: Facility Planning- FEL 3: Project Planning- Project Execution- Start up and Operations
1405 July 2010
15
3. Volume One: The Road to Success
1505 July 2010
16
3. Volume One: The Road to Success
1605 July 2010
17
3. Volume One: The Road to Success
17
INFL
UEN
CE
EXPEND
ITUR
ES
FEL 1BUSINESS PLANNING
FEL 2FACILITY PLANNING
FEL 3PROJECT PLANNING
PROJECT EXECUTION
START-UP AND OPERATIONS
FRONT END LOADING
FINAL AUTHORISATION
SANCTION
Major Influence Rapidly Decreasing Influence Low Influence
INFLUENCE - EXPENDITURES
05 July 2010
18
3. Volume One: The Road to Success
- Preface and Introduction 1 Executive Summary2 Development Phases of Pipeline Project
3 The Baseline of a Contract4 Analysis and Mitigation of Risks5 Management of Construction Risks6 Best Practices7 New Trends and Innovation- Bibliography / Acknowledgements
- Scope of Works- Resourced Programme- Cost Structure- Conditions of Contract
1805 July 2010
19
3. Volume One: The Road to Success
1905 July 2010
20
3. Volume One: The Road to Success- Preface and Introduction 1 Executive Summary2 Development Phases of Pipeline Project3 The Baseline of a Contract
4 Analysis and Mitigation of Risks5 Management of Construction Risks6 Best Practices7 New Trends and Innovation- Bibliography / Acknowledgements
-Categories of Risk Events- Detailed Description of Events- Timing of Risks Consideration- Risk Owner- Risk Mitigation by Contractor- Excess Mitigation by Client
2005 July 2010
21
3. Volume One: The Road to Success
2105 July 2010
22
3. Volume One: The Road to Success- Preface and Introduction 1 Executive Summary2 Development Phases of Pipeline Project3 The Baseline of a Contract4 Analysis and Mitigation of Risks
5 Management of Construction Risks6 Best Practices7 New Trends and Innovation- Bibliography / Acknowledgements
- Assessment of impact of Risk Events on progress and cost- Possible mitigation measures
2205 July 2010
23
3. Volume One: The Road to SuccessUtilisation of March Charts to assess time impact of stoppages..
23
D0
D20
D40
D60
D80
D100
0+000 10+000 20+000 30+000 40+000 50+000 60+000Right of Way String & Bend Welding Lower & Lay Backfill Clean‐up
CV
CV
CVCVCVCVa 0
b 0c 0
d 0e 0
CV
CV
CVCVCV
CVa0
b0+ Δ
c0
d0
e0
D
05 July 2010
24
3. Volume One: The Road to Success… or of slowdowns. Comparison with stoppages
24
D0
D10
D20
D30
D40
D50
D60
D70
D80
0+000 10+000 20+000 30+000 40+000 50+000 60+000
Activity X
Actual Progress before stopage
Case of full stoppage for D days
Progress slow down for D days
D
D1
05 July 2010
25
3. Volume One: The Road to Success- Preface and Introduction 1 Executive Summary2 Development Phases of Pipeline Project3 The Baseline of a Contract4 Analysis and Mitigation of Risks5 Management of Construction Risks
6 Best Practices7 New Trends and Innovation- Bibliography / Acknowledgements
6.1 Planning, Design & Control- ROW & Constructability- Minimum Data for the Five Project Stages
6.2 Earthworks- Typical ROW Cross Sections- Earthworks Design- Environment- Health & Safety
6.2 External Pipeline Protection System- Mainline Anti Corrosion Coatings- Field Joint Anti Corrosion Coatings- Mechanical Protections
2505 July 2010
26
3. Volume One: The Road to Success
2605 July 2010
27
3. Volume One: The Road to Success
2705 July 2010
28
3. Volume One: The Road to Success- Preface and Introduction 1 Executive Summary2 Development Phases of Pipeline Project3 The Baseline of a Contract4 Analysis and Mitigation of Risks5 Management of Construction Risks6 Best Practices
7 New Trends and Innovation- Bibliography / Acknowledgements
7.1 Near-Real-Time Construction Monitoring Tool7.2 Pipeline Simulation Tool7.3 Facing, Lining up & Welding Skid-less Methodology7.4 Lower & Lay: “Ideal” Machine Specifications
2805 July 2010
29
3. Volume One: The Road to Success
2905 July 2010
30
3. Volume One: The Road to Success- Preface and Introduction 1 Executive Summary2 Development Phases of Pipeline Project3 The Baseline of a Contract4 Analysis and Mitigation of Risks5 Management of Construction Risks6 Best Practices7 New Trends and Innovation
- Bibliography / Acknowledgements- Reference Publications - Contributors to The Road
3005 July 2010
31
32
3. Volume One: Appendices3.2.1 Recommendations for establishing the Project Execution Plan for the Construction Phase3.2.2 A Dummies Guide to March Charts3.4.4 Contract clauses that have a particular impact upon onshore pipeline projects3.4.5 Project Cost Estimate and Contingency5.2.1 Examples of evaluation of time & cost impacts of full stoppages or of slowdowns to
certain activities intervening at various stages of the construction process6.1.1 Pipeline Selection Route Process6.2.2 Earthworks-Pipeline Trench Design6.2.3 Earthworks-Environment Control Measures6.2.4 Earthworks-Health & Safety Control Measure6.3.1 Comparison of Mainline External Anti-Corrosion Coatings6.3.2 Field Joint Coating Selection Table6.3.3 Supplementary Mechanical Protection Systems Selection Tables7.1.1 Conceptual Functional Specifications for a GIS-Based Near Real-Time Monitoring Tool
33
3. Volume One: Appendices3.2.1 Recommendations to establishing a Project Execution Plan for Construction Phase3.2.2 A Dummies Guide to March Charts3.4.4 Contract clauses that have a particular impact upon onshore pipeline projects3.4.5 Project Cost Estimate and Contingency5.2.1 Examples of evaluation of time & cost impacts of full stoppages or of slowdowns to
certain activities intervening at various stages of the construction process6.1.1 Pipeline Selection Route Process6.2.2 Earthworks-Pipeline Trench Design6.2.3 Earthworks-Environment Control Measures6.2.4 Earthworks-Health & Safety Control Measure6.3.1 Comparison of Mainline External Anti-Corrosion Coatings6.3.2 Field Joint Coating Selection Table6.3.3 Supplementary Mechanical Protection Systems Selection Tables7.1.1 Conceptual Functional Specifications for a GIS-Based Near Real-Time Monitoring Tool
34
Appendix 3.2.1 Recommendations for establishing the Project Execution Plan for the Construction Phase
• Summary: This section provides the reader with ‘how to’ guide to best formulate a PEP. Essentially a executive summary for the construction phase planning, including tips on mastering the key elements.
1. Introduction 5.2 Procurement Execution plan 5.7 Project Planning & Control Plan
2. Project Background 5.3Administration & Finance 5.8 Risk Analysis Management Plan
3. Project Execution Organization 5.4 Construction Execution Plan 5.9 Quality Plan
4.Key Personnel 5.5 Health & Safety Plan 5.10 Community Relations Plan
5.1 Engineering Execution Plan 5.6 Environmental Impact Plan 5.10 Systems
Contents
35
3. Volume One: Appendices3.2.1 Recommendations for establishing the Project Execution Plan for the Construction Phase3.2.2 A Dummies Guide to March Charts3.4.4 Contract clauses that have a particular impact upon onshore pipeline projects3.4.5 Project Cost Estimate and Contingency5.2.1 Examples of evaluation of time & cost impacts of full stoppages or of slowdowns to
certain activities intervening at various stages of the construction process6.1.1 Pipeline Selection Route Process6.2.2 Earthworks-Pipeline Trench Design6.2.3 Earthworks-Environment Control Measures6.2.4 Earthworks-Health & Safety Control Measure6.3.1 Comparison of Mainline External Anti-Corrosion Coatings6.3.2 Field Joint Coating Selection Table6.3.3 Supplementary Mechanical Protection Systems Selection Tables7.1.1 Conceptual Functional Specifications for a GIS-Based Near Real-Time Monitoring Tool
36
Appendix 3.2.2
A Dummies Guide to March Charts
• Summary: Provides the reader with a detailed account on how to understand and interpret March (time- distance) charts
1. The Basics
2. Constructability Issues
3. Other Features
4.Progressing March Charts
Contents
37
3. Volume One: Appendices3.2.1 Recommendations for establishing the Project Execution Plan for the Construction Phase3.2.2 A Dummies Guide to March Charts3.4.4 Contract clauses that have a particular impact upon onshore pipeline projects3.4.5 Project Cost Estimate and Contingency5.2.1 Examples of evaluation of time & cost impacts of full stoppages or of slowdowns to
certain activities intervening at various stages of the construction process6.1.1 Pipeline Selection Route Process6.2.2 Earthworks-Pipeline Trench Design6.2.3 Earthworks-Environment Control Measures6.2.4 Earthworks-Health & Safety Control Measure6.3.1 Comparison of Mainline External Anti-Corrosion Coatings6.3.2 Field Joint Coating Selection Table6.3.3 Supplementary Mechanical Protection Systems Selection Tables7.1.1 Conceptual Functional Specifications for a GIS-Based Near Real-Time Monitoring Tool
38
Appendix 3.4.4
Contract Clauses that have a particular impact upon onshore pipeline projects
• Summary: Provides the reader with specific items within a onshore pipeline contract that need particular attention, and can prove to be detrimental should they be overlooked when planning and executing a project.
1. Weather 5. Third Parties
2. Environment/Archaeology 6. Materials
3. Site and Access 7. Ground Conditions
4.Programme 8.Design
Contents
39
3. Volume One: Appendices3.2.1 Recommendations for establishing the Project Execution Plan for the Construction Phase3.2.2 A Dummies Guide to March Charts3.4.4 Contract clauses that have a particular impact upon onshore pipeline projects3.4.5 Project Cost Estimate and Contingency5.2.1 Examples of evaluation of time & cost impacts of full stoppages or of slowdowns to
certain activities intervening at various stages of the construction process6.1.1 Pipeline Selection Route Process6.2.2 Earthworks-Pipeline Trench Design6.2.3 Earthworks-Environment Control Measures6.2.4 Earthworks-Health & Safety Control Measure6.3.1 Comparison of Mainline External Anti-Corrosion Coatings6.3.2 Field Joint Coating Selection Table6.3.3 Supplementary Mechanical Protection Systems Selection Tables7.1.1 Conceptual Functional Specifications for a GIS-Based Near Real-Time Monitoring Tool
40
Appendix 3.4.5
Project Cost estimate and Contingency
1. The Development of a Project Estimate
2. What Contingency is not meant to cover
3. Development of Allowances, Escalation and Contingency
4.Whats is an Estimate Range
5. Estimate Accuracy
6. How do we set Contingency
Summary: Helps the reader to understand the issues surrounding the development of a project cost estimate, whilst aiding to understand the specifics and terminology.
Contents
41
3. Volume One: Appendices3.2.1 Recommendations for establishing the Project Execution Plan for the Construction Phase3.2.2 A Dummies Guide to March Charts3.4.4 Contract clauses that have a particular impact upon onshore pipeline projects3.4.5 Project Cost Estimate and Contingency5.2.1 Examples of evaluation of time & cost impacts of full stoppages or of slowdowns
to certain activities intervening at various stages of the construction process6.1.1 Pipeline Selection Route Process6.2.2 Earthworks-Pipeline Trench Design6.2.3 Earthworks-Environment Control Measures6.2.4 Earthworks-Health & Safety Control Measure6.3.1 Comparison of Mainline External Anti-Corrosion Coatings6.3.2 Field Joint Coating Selection Table6.3.3 Supplementary Mechanical Protection Systems Selection Tables7.1.1 Conceptual Functional Specifications for a GIS-Based Near Real-Time Monitoring Tool
42
Appendix 5.2.1
Examples of time and cost impacts of full stopages or slowdowns to certain activities
1. Examples of evaluation of time impact of Stoppages
2. Evaluation of the cost of impact of stoppages
Summary: This section provides the reader with various examples of the effect of slow-downs or stoppages on the progress of a project, and the resulting impact on costs.
Contents
43
3. Volume One: Appendices3.2.1 Recommendations for establishing the Project Execution Plan for the Construction Phase3.2.2 A Dummies Guide to March Charts3.4.4 Contract clauses that have a particular impact upon onshore pipeline projects3.4.5 Project Cost Estimate and Contingency5.2.1 Examples of evaluation of time & cost impacts of full stoppages or of slowdowns to
certain activities intervening at various stages of the construction process6.1.1 Pipeline Selection Route Process6.2.2 Earthworks-Pipeline Trench Design6.2.3 Earthworks-Environment Control Measures6.2.4 Earthworks-Health & Safety Control Measure6.3.1 Comparison of Mainline External Anti-Corrosion Coatings6.3.2 Field Joint Coating Selection Table6.3.3 Supplementary Mechanical Protection Systems Selection Tables7.1.1 Conceptual Functional Specifications for a GIS-Based Near Real-Time Monitoring Tool
44
Appendix 6.1.1 Pipeline Route Selection ProcessSummary: Best practices for all processes of route selection
45
3. Volume One: Appendices3.2.1 Recommendations for establishing the Project Execution Plan for the Construction Phase3.2.2 A Dummies Guide to March Charts3.4.4 Contract clauses that have a particular impact upon onshore pipeline projects3.4.5 Project Cost Estimate and Contingency5.2.1 Examples of evaluation of time & cost impacts of full stoppages or of slowdowns to
certain activities intervening at various stages of the construction process6.1.1 Pipeline Selection Route Process6.2.2 Earthworks-Pipeline Trench Design6.2.3 Earthworks-Environment Control Measures6.2.4 Earthworks-Health & Safety Control Measure6.3.1 Comparison of Mainline External Anti-Corrosion Coatings6.3.2 Field Joint Coating Selection Table6.3.3 Supplementary Mechanical Protection Systems Selection Tables7.1.1 Conceptual Functional Specifications for a GIS-Based Near Real-Time Monitoring Tool
46
Appendix 6.2.2
Earthworks: Pipeline Trench Design
1. Pipeline Trench Design
2. Trench Depth
3. Trench Integrity
4.Installation
5. Dewatering
6. Backfilling
Summary: Extensive documentation on the planning, excavation, and laying methods of pipeline in trenches
Contents
47
3. Volume One: Appendices3.2.1 Recommendations for establishing the Project Execution Plan for the Construction Phase3.2.2 A Dummies Guide to March Charts3.4.4 Contract clauses that have a particular impact upon onshore pipeline projects3.4.5 Project Cost Estimate and Contingency5.2.1 Examples of evaluation of time & cost impacts of full stoppages or of slowdowns to
certain activities intervening at various stages of the construction process6.1.1 Pipeline Selection Route Process6.2.2 Earthworks-Pipeline Trench Design6.2.3 Earthworks-Environment Control Measures6.2.4 Earthworks-Health & Safety Control Measure6.3.1 Comparison of Mainline External Anti-Corrosion Coatings6.3.2 Field Joint Coating Selection Table6.3.3 Supplementary Mechanical Protection Systems Selection Tables7.1.1 Conceptual Functional Specifications for a GIS-Based Near Real-Time Monitoring Tool
48
Appendix 6.2.3
Earthworks: Environmental Control Measures
1. All Habitats
2. Soft Soil
3. Sand Dune Area
4.Peat Area
5. Side Slope
6. Swampy Areas
7. Forested Area
8. Ridge
9. Tundra
Summary: This section aims to provide ways for project managers to mitigate the environmental impact of Earthworks within different conditions of excavations
Contents
49
3. Volume One: Appendices3.2.1 Recommendations for establishing the Project Execution Plan for the Construction Phase3.2.2 A Dummies Guide to March Charts3.4.4 Contract clauses that have a particular impact upon onshore pipeline projects3.4.5 Project Cost Estimate and Contingency5.2.1 Examples of evaluation of time & cost impacts of full stoppages or of slowdowns to
certain activities intervening at various stages of the construction process6.1.1 Pipeline Selection Route Process6.2.2 Earthworks-Pipeline Trench Design6.2.3 Earthworks-Environment Control Measures6.2.4 Earthworks-Health & Safety Control Measure6.3.1 Comparison of Mainline External Anti-Corrosion Coatings6.3.2 Field Joint Coating Selection Table6.3.3 Supplementary Mechanical Protection Systems Selection Tables7.1.1 Conceptual Functional Specifications for a GIS-Based Near Real-Time Monitoring Tool
50
Appendix 6.2.4
Earthworks: Health and Safety Control MeasuresSummary: This section provides a crucial insight into the hazards that can be found within different soil types and topographies, and suggests control measures to limit the risk of occurrence
1. Pipe movement 8. Adverse weather
2. Working at height 9. Ambient temperature
3. Work equipment 10. Ground conditions
4.Hazardius materials – personal exposure
11. Confined space
5. Emergency response 12. Heavy Load
6. Impact with local community/area
13. Illumination
7. Wildlife 14. Lifting
•Soft Soil•Sand Dune•Peat Area•Side Slope•Swampy Area•Forested Area •Ridge•Tundra
Environment Hazard
51
3. Volume One: Appendices3.2.1 Recommendations for establishing the Project Execution Plan for the Construction Phase3.2.2 A Dummies Guide to March Charts3.4.4 Contract clauses that have a particular impact upon onshore pipeline projects3.4.5 Project Cost Estimate and Contingency5.2.1 Examples of evaluation of time & cost impacts of full stoppages or of slowdowns to
certain activities intervening at various stages of the construction process6.1.1 Pipeline Selection Route Process6.2.2 Earthworks-Pipeline Trench Design6.2.3 Earthworks-Environment Control Measures6.2.4 Earthworks-Health & Safety Control Measure6.3.1 Comparison of Mainline External Anti-Corrosion Coatings6.3.2 Field Joint Coating Selection Table6.3.3 Supplementary Mechanical Protection Systems Selection Tables7.1.1 Conceptual Functional Specifications for a GIS-Based Near Real-Time Monitoring Tool
52
Appendix 6.3.1
Comparison of Mainline External Anti-Corrosion Coatings Summary: This section provides the reader with a comprehensive comparison between different types of Coating Systems
53
3. Volume One: Appendices3.2.1 Recommendations for establishing the Project Execution Plan for the Construction Phase3.2.2 A Dummies Guide to March Charts3.4.4 Contract clauses that have a particular impact upon onshore pipeline projects3.4.5 Project Cost Estimate and Contingency5.2.1 Examples of evaluation of time & cost impacts of full stoppages or of slowdowns to
certain activities intervening at various stages of the construction process6.1.1 Pipeline Selection Route Process6.2.2 Earthworks-Pipeline Trench Design6.2.3 Earthworks-Environment Control Measures6.2.4 Earthworks-Health & Safety Control Measure6.3.1 Comparison of Mainline External Anti-Corrosion Coatings6.3.2 Field Joint Coating Selection Table6.3.3 Supplementary Mechanical Protection Systems Selection Tables7.1.1 Conceptual Functional Specifications for a GIS-Based Near Real-Time Monitoring Tool
54
Appendix 6.3.2
Field Joint Coating Selection Table Summary: This section provides the reader with a overview of the different Filed joint systems available in the market with their relevant standard and specification ratings
55
3. Volume One: Appendices3.2.1 Recommendations for establishing the Project Execution Plan for the Construction Phase3.2.2 A Dummies Guide to March Charts3.4.4 Contract clauses that have a particular impact upon onshore pipeline projects3.4.5 Project Cost Estimate and Contingency5.2.1 Examples of evaluation of time & cost impacts of full stoppages or of slowdowns to
certain activities intervening at various stages of the construction process6.1.1 Pipeline Selection Route Process6.2.2 Earthworks-Pipeline Trench Design6.2.3 Earthworks-Environment Control Measures6.2.4 Earthworks-Health & Safety Control Measure6.3.1 Comparison of Mainline External Anti-Corrosion Coatings6.3.2 Field Joint Coating Selection Table6.3.3 Supplementary Mechanical Protection Systems Selection Tables7.1.1 Conceptual Functional Specifications for a GIS-Based Near Real-Time Monitoring Tool
56
Appendix 6.3.3
Supplementary Mechanical Protection Systems Selection Table Summary: This section provides the reader with an overview of different Mechanical Protection Systems taking into account technical performance criteria, design & construction criteria, and environmental criteria.
57
3. Volume One: Appendices3.2.1 Recommendations for establishing the Project Execution Plan for the Construction Phase3.2.2 A Dummies Guide to March Charts3.4.4 Contract clauses that have a particular impact upon onshore pipeline projects3.4.5 Project Cost Estimate and Contingency5.2.1 Examples of evaluation of time & cost impacts of full stoppages or of slowdowns to
certain activities intervening at various stages of the construction process6.1.1 Pipeline Selection Route Process6.2.2 Earthworks-Pipeline Trench Design6.2.3 Earthworks-Environment Control Measures6.2.4 Earthworks-Health & Safety Control Measure6.3.1 Comparison of Mainline External Anti-Corrosion Coatings6.3.2 Field Joint Coating Selection Table6.3.3 Supplementary Mechanical Protection Systems Selection Tables7.1.1 Conceptual Functional Specifications for a GIS-Based Near Real-Time Monitoring
Tool
58
Appendix 7.1.1
Conceptual Functional Specifications for a GIS-based Near-
Real-Time Construction Monitoring Tool
Summary: To recommend the basic functional specifications for developing a “near-real time (near-live) monitoring tool” and a comprehensive project controls tool with a GIS-based interface.
59
4. Future Developments:
Continuation of Novel Initiative Oct 27-28 Sessions:
Six new Working Groups have been formed to,
expand sections of The Road as needed
New Developments have been proposed
Objective: to issue a second edition by September 2011
Research Cooperation with EPRG, PRCI & APIA
5905 July 2010
5. Q &A
6005 July 2010
The Road to Success is available in pdf
format on www.iploca.com
_________
Comments and Suggestions
to be addressed to
[email protected] July 2010