01.11.10 Analyst Presentation

Embed Size (px)

Citation preview

  • 8/8/2019 01.11.10 Analyst Presentation

    1/42

    1

  • 8/8/2019 01.11.10 Analyst Presentation

    2/42

    Indian Scenario

    Company Overview

    Performance Highlights

    Financia Hig ig ts

    StatusofPro ects

    BusinessStrategy

    2

  • 8/8/2019 01.11.10 Analyst Presentation

    3/42

    3

  • 8/8/2019 01.11.10 Analyst Presentation

    4/42

    4

  • 8/8/2019 01.11.10 Analyst Presentation

    5/42

    Power SupplyDeficit(Apr-Sep2010)IndiaOutshinesGlobalGDPForecasts

    Source: IMF, CEA 5

  • 8/8/2019 01.11.10 Analyst Presentation

    6/42

    CapacityAddition(Apr2010 Sept2010) CapacityInstalledasonSeptember30,2010

    6Source: Ministry of Power, CEA

    TOTALCAPACITY:165GW

  • 8/8/2019 01.11.10 Analyst Presentation

    7/42

    77

  • 8/8/2019 01.11.10 Analyst Presentation

    8/42

    240MW

    270MW

    Established power company with

    rofitable o erations since

    270MW1,620

    MW

    inception in FY 2000

    -- Operating capacityOperating capacity Current: 1,430 MWCurrent: 1,430 MW

    WestBengal

    Chhattisgarh1,620MW

    Jharkhand

    -- By July 2011: 3,140 MWBy July 2011: 3,140 MWRatnagiri

    Vijayanagar

    1,320MW

    300MW

    -- By FY 2016:By FY 2016: 12,07012,070 MWMW Projects under operation & constructionProject s under development

    900MW

    3,200MW

    860MW

    Operational

    Implementation/construction

    Development

    8

    Imported Coal Domestic Coal HydroLignite

  • 8/8/2019 01.11.10 Analyst Presentation

    9/42

    Achieved Commercial Operation Date (COD) on September 1, 2010

    Jaigad to New Koyna transmission line 2 successfully charged inu y

    ve o grow n capac y on year on year as s

    Refinanced Rs. 1 003 Crores of hi h cost debt

    Reduction in interest rate by approx 1.47%

    Awarded NDTV Profit Business Leadership Award, 2010 in PowerSector

    9

  • 8/8/2019 01.11.10 Analyst Presentation

    10/42

    10

  • 8/8/2019 01.11.10 Analyst Presentation

    11/42

    PlantWisePerformance(Q2FY2011)CapacityGrowth(MW)

    398%

    11

  • 8/8/2019 01.11.10 Analyst Presentation

    12/42

    VolumeGrowth(Millionkwh)NetGeneration(Millionkwh)

    1781

    108%

    1211

    47%

    12

  • 8/8/2019 01.11.10 Analyst Presentation

    13/42

    3,608

    SalesMix(Millionkwh)

    1,781

    36 %

    1,731

    26 %1,211

    64 % 74 %71 %

    29 %

    Q2FY2010 Q2FY2011 H1FY2010 H1 FY2011

    Short Term Realisation 5.15 4.65 5.51 5.25

    Realisation` perkwh

    13

    Average Realisation 4.61 4.34 4.94 4.71

  • 8/8/2019 01.11.10 Analyst Presentation

    14/42

    14

  • 8/8/2019 01.11.10 Analyst Presentation

    15/42

    Turnover(Turnover(` Crores)Crores) EBITDA (EBITDA (` Crores)Crores)

    112 % 70 %

    15 %

    PBT (PBT (` Crores)Crores) PAT(PAT(` Crores)Crores)70 % 80 %

    2 %6 %

    15

  • 8/8/2019 01.11.10 Analyst Presentation

    16/42

    573 875 Turnover (` Crores) 895 1,858

    324 503 EBITDA (` Crores))) 374 857

    57% 57% EBITDA (%) 42% 46%

    71 110 I t t (` C )) 94 1681 110 Interest (` Crores)) 94 168

    32 47 Depreciation (` Crores) 55 102

    221 346 PBT (` Crores) 225 587174 268 PAT (` C ) 185 483

    16

    174 268 PAT (` Crores) 185 4831.27 1.96 EPS (` ) (Not Annual ised) 1.13 2.95

  • 8/8/2019 01.11.10 Analyst Presentation

    17/42

    NetWorth

    (` Crores) 4,780 5,264

    Debt(` Crores) 7,870 8,634

    NetFixed

    Assets

    (` Crores)

    * 11,598 12,474

    DebtEquityRatio(Times) 1.65 1.64

    WeightedAverage

    Cost

    of

    Debt 11.51

    % 11.32

    %

    *Including CWIP

    17

  • 8/8/2019 01.11.10 Analyst Presentation

    18/42

    Utilisation

    upto

    September

    30,

    2010

    Pro ect

    Utilisationas

    perProspectus

    Actua Amount

    Spentupto

    Sept30,2010

    PartFinanceforIdentifiedPro ects2142.53 969.31

    RepaymentofCorporateDebt470.00 470.00

    ShareIssueExpenses 75.98 64.52

    GeneralCorporatePurpose11.49 -

    UnutilisedAmount

    nveste nMF Ban FD Ut se or

    reductionofOverdraft

    - 1196.17

    GrossProceedsreceivedfromIPO 2,700.00 2700.00

    18

  • 8/8/2019 01.11.10 Analyst Presentation

    19/42

    Capacity expansion at Vijayanagar by 660 MW

    Introduction of Employee Stock Option Scheme (ESOS)

    ssuance o upto , , , stoc opt ons convert e nto equanumber of equity shares

    (dilution of 1.20%)

    Subject to approval of shareholders

    19

  • 8/8/2019 01.11.10 Analyst Presentation

    20/42

    20

  • 8/8/2019 01.11.10 Analyst Presentation

    21/42

    StatusUpdateProjectDetails

    GrossCapacity 1200

    MW,

    400

    KV

    Transmission

    DoubleCircuit uadMoose

    Jaigad KoynaLineIIsuccessfullychargedonJuly7,2010

    Technology

    ConductorLine

    Procurement Ordersplaced

    Jaigad Karad:

    Tower Foundations: 88%

    Tower Erection: 53%

    ProjectCost

    ` 580CroresDebt:Equity:75:25

    ActualspenttillSept30,2010:

    ` 377CrsExpected

    CommissioningFebruary2011

    21

  • 8/8/2019 01.11.10 Analyst Presentation

    22/42

    Minedevelo ment rocesscommencedatKa urdi

    StatusUpdate

    BLMCL

    MOEFClearancereceivedforJalipamines

    Minedevelopment

    plan

    approved

    for

    Jalipa

    mines

    ExpectedtoextractlignitebyQ4FY2011

    60%workcompletedforKapurdimines

    LandacquisitionatadvancedstageforJalipamines

    MJSJCoal Publichearingprocesscompleted

    Landacquisitioninprocess

    Tar ettocommence roductionin2012

    JSWToshibaBladeshopmachiningcentreequipmentreceived

    Temporarypowerreceivedatsite

    ProgressforBladeShop97%

    Blade

    manufacturing

    by

    2011ManufacturingofTGsetsby2012 22

  • 8/8/2019 01.11.10 Analyst Presentation

    23/42

    2323

  • 8/8/2019 01.11.10 Analyst Presentation

    24/42

    Gross Ca acit 1 080MW 8x135Unit II COD October 4, 2010

    StatusUpdateProjectDetails

    Technology Sub-critical

    Captive

    Lignite

    based

    TPP

    FSAwithBLMCL 49% V forsu l

    PLF of 73.85% for Unit I during

    September 2010

    Unit III & IV boiler hydro test completed

    Fuel Linkage oflignitefromcaptiveligniteminesof

    BLMCL

    Water

    Raw Water pipe line commissioned

    Tapering coal linkage approved byMinistry of Coal for 50% of coalAllocation

    Power Off take

    LongTerm:PPAforentirecapacity

    withstateGovernmentdistribution

    requirement

    utilities

    ` 6085Crs

    Project Cost

    AmtspenttillSept30,2010:

    ` 4790Crs24

  • 8/8/2019 01.11.10 Analyst Presentation

    25/42

    bi

    Gross Capacity 1200MW(4x300) Boiler II light up done & steam blowing

    StatusUpdateProjectDetails

    Technology Sub-criticalImportedCoalbasedTPP

    Fuel LinkageLongtermsupplyarrangementfor

    Indonesiancoal&minesinSouthAfrica

    starte

    Unit II synchronization expected inNovember 2010

    Water

    AllocationMIDC+SeaWater

    TG put on barring for Unit II

    Boiler III & IV hydro test completed

    Power Off take

    passthrough

    Abilitytoavailshorttermratesfor

    balance900MW

    in progress

    Project Cost

    ` 5650Crs

    Debt/Equity:75:25

    AmtspenttillSept30,2010:` 4056Crs

    Expected

    Commissioning

    UnitICODachievedon

    September1,

    2010

    EntireprojectexpectedbyFY2011 25

  • 8/8/2019 01.11.10 Analyst Presentation

    26/42

    GrossCapacity 1620MW Water availability study conducted

    StatusUpdateProjectDetails

    TechnologySuper-criticalDomesticcoalbasedTPP

    ShareHoldin74% - JSWEL

    In principle approval received for

    entering into a LT PPA for surplus power

    Agreement executed for coal raising &coal procurement

    - enga ee m e

    FuelLinkage

    IchhapurMines- WBMDTCto

    DPR finalised

    Bids invited for BTG equipment supply

    Land in possession

    PowerOfftake

    Captivesaletothesteelplanton

    twoparttariffframeworkand

    excess orou s esa e

    ProjectCostPhase - I

    ` 3,300CrsforPowerplant` 1,500CrsforMinesDevelopmentAmtspenttillSept30,2010:` 3232

    Expected

    CommissioningPhase - I

    October2014

    26

  • 8/8/2019 01.11.10 Analyst Presentation

    27/42

    Consent for chimney clearance given byAirport Authority

    GrossCapacity 1,320MW(2x660)

    Su er-criticaldomesticcoalbased

    StatusUpdateProjectDetails

    Tender documents for BTG issued

    Public hearing completed in August2010

    ec no ogyTPP

    AuthorityMoUsignedwithGoCG forsettingupaTPPalongwithintegratedcoal

    Water allocation obtained fromMahanadi river on September 8, 2010

    Topography survey and geo-technical

    FuelLinkage11%interestincoalblockjointlyallocated;appliedforadditional

    coallinkage

    Landacquisitioninprogress 225acres

    alreadyacquired

    WaterAllocation35mn cmpa waterallocatedfromMahanadiRiver

    CombinationofLTPPAandshortPowerOfftake termagreementswithJSWPTC;35%

    toStateGovt.

    ProjectCost` 6,500Crs

    AmtspenttillSept 30,2010:` 38CrsExpected

    Commissioning 201427

  • 8/8/2019 01.11.10 Analyst Presentation

    28/42

    Prequalification of vendors completed

    StatusUpdateProjectDetails

    GrossCapacity 240MW(3x80)

    Technology Run-of-the-riverHydropower

    or a n v or s

    Public hearing for Environmentclearance held successfully

    Water

    AllocationRaviRiver

    Freepower

    to

    GoHP 12%

    to

    Techno Economic Clearance from CEAreceived on August 30, 2010

    Landacquisitionunderprogress All

    sixaffectedGrampanchayatshavegivenPowerOfftake

    years.Balancethroughshorttermarrangements

    `

    NOC

    Environmentclearancemeeting

    scheduledfor12th November,2010

    ProjectCost

    ` Amt

    spent

    till

    Sept

    30,

    2010

    :` 91Crs

    Biddocumentsfor maincivilworks

    underfinalstageofpreparation

    Commissioning2015

    28

  • 8/8/2019 01.11.10 Analyst Presentation

    29/42

    StatusUpdateProjectDetails

    GrossCapacity 660MW(1x660)

    Technology Supercritical

    coal

    based

    TPP

    Importedcoal/Domesticlinkage

    Land identified

    MOEFapprovalbeingappliedfor

    coal

    WaterSource Almatti Dam

    PowerOfftakeerc an power ong erm

    PPA

    ProjectCost TotalCost:` 3,300CrsExpectedCommissioning

    2014

    29

  • 8/8/2019 01.11.10 Analyst Presentation

    30/42

    StatusUpdateProjectDetails

    Gross Capacity 270MW(2x135)

    TechnologySubcriticalCaptivelignitebased

    TPP

    Land in possession

    Appliedforcoallinkage

    Fuel Linkage AppliedtoMinistryofCoal

    Water

    Allocation Allocation

    from

    IGNP

    Power Off takeShortTermpowerpurchase

    arrangements

    TotalCost:` 1350CrsProject Cost

    ` Amount

    spent

    till

    Sept

    30,

    2010

    :` 61Crs

    Expected

    Commissionin2014-2015

    30

  • 8/8/2019 01.11.10 Analyst Presentation

    31/42

    StatusUpdateProjectDetails

    ,

    Technology Super-critical

    imported

    coal

    based

    TPP

    Substantial land in possession

    Inthe

    process

    of

    obtaining

    necessaryconsentsandapprovals

    Authority

    ofMaharashtra

    Fuel

    Linkage Imported

    Coal

    WaterAllocation SeaWater

    PowerOfftake

    agreements

    ProjectCost` 150Bn.

    AmtspenttillSept30,2010:` 45CrsExpectedCommissioning

    2016

    31

  • 8/8/2019 01.11.10 Analyst Presentation

    32/42

    32

  • 8/8/2019 01.11.10 Analyst Presentation

    33/42

    BeyondCoreBusiness

    Mining

    Harnessgrowthopportunity

    providedby

    the

    sector

    SustainCoreBusiness

    EquipmentManufacturing

    Accessto

    New

    Business

    Straddleallsegmentsof

    powerbusiness

    Transmission

    Trading

    Distribution

    Integration

    Strengt en ng

    FuelSecurity

    SecuringCoreBusiness

    PowerGeneration

    CostReduction

    33

  • 8/8/2019 01.11.10 Analyst Presentation

    34/42

    PlantOverview

    34

  • 8/8/2019 01.11.10 Analyst Presentation

    35/42

    AsonSeptember30,2010

    35

    AsonJune30,2010

  • 8/8/2019 01.11.10 Analyst Presentation

    36/42

    AsonSeptember30,2010

    AsonJune30,2010

    36

  • 8/8/2019 01.11.10 Analyst Presentation

    37/42

    TG4

    TG3

    37

  • 8/8/2019 01.11.10 Analyst Presentation

    38/42

    AsonSeptember30,2010

    38

    AsonJune30,2010

  • 8/8/2019 01.11.10 Analyst Presentation

    39/42

    AsonSeptember30,2010

    AsonJune30,2010

    39

  • 8/8/2019 01.11.10 Analyst Presentation

    40/42

    40

  • 8/8/2019 01.11.10 Analyst Presentation

    41/42

    Certain statements in this report concerning our future growth prospects are forward lookingstatements, which involve a number of risks, and uncertainties that could cause actual results todiffer materially from those in such forward looking statements. The risk and uncertaintiesrelating to these statements include, but are not limited to risks and uncertainties regarding

    fluctuations in earnings, our ability to manage growth, intense competition within Power industry, ,

    attract and retain highly skilled professionals, time and cost overruns on fixed-price, fixed-timeframe contracts, our ability to commission mines within contemplated time and costs, our ability toraise the finance within time and cost client concentration, restrictions on immigration, our ability

    to mana e our internal o erations, reduced demand or ower, our abilit to success ull com leteand integrate potential acquisitions, liability for damages on our service contracts, the success ofthe companies in which the Company has made strategic investments, withdrawal of

    fiscal/governmental incentives, impact of regulatory measures, political instability, legalrestrictions on raising capital or acquiring companies outside India, unauthorized use of ourn e ec ua proper y an genera econom c con ons a ec ng our n us ry. e company oes

    not undertake to update any forward looking statements that may be made from time to time by oron behalf of the company.

    41

  • 8/8/2019 01.11.10 Analyst Presentation

    42/42

    42