Upload
sbnayagam2843
View
217
Download
0
Embed Size (px)
Citation preview
8/8/2019 01.11.10 Analyst Presentation
1/42
1
8/8/2019 01.11.10 Analyst Presentation
2/42
Indian Scenario
Company Overview
Performance Highlights
Financia Hig ig ts
StatusofPro ects
BusinessStrategy
2
8/8/2019 01.11.10 Analyst Presentation
3/42
3
8/8/2019 01.11.10 Analyst Presentation
4/42
4
8/8/2019 01.11.10 Analyst Presentation
5/42
Power SupplyDeficit(Apr-Sep2010)IndiaOutshinesGlobalGDPForecasts
Source: IMF, CEA 5
8/8/2019 01.11.10 Analyst Presentation
6/42
CapacityAddition(Apr2010 Sept2010) CapacityInstalledasonSeptember30,2010
6Source: Ministry of Power, CEA
TOTALCAPACITY:165GW
8/8/2019 01.11.10 Analyst Presentation
7/42
77
8/8/2019 01.11.10 Analyst Presentation
8/42
240MW
270MW
Established power company with
rofitable o erations since
270MW1,620
MW
inception in FY 2000
-- Operating capacityOperating capacity Current: 1,430 MWCurrent: 1,430 MW
WestBengal
Chhattisgarh1,620MW
Jharkhand
-- By July 2011: 3,140 MWBy July 2011: 3,140 MWRatnagiri
Vijayanagar
1,320MW
300MW
-- By FY 2016:By FY 2016: 12,07012,070 MWMW Projects under operation & constructionProject s under development
900MW
3,200MW
860MW
Operational
Implementation/construction
Development
8
Imported Coal Domestic Coal HydroLignite
8/8/2019 01.11.10 Analyst Presentation
9/42
Achieved Commercial Operation Date (COD) on September 1, 2010
Jaigad to New Koyna transmission line 2 successfully charged inu y
ve o grow n capac y on year on year as s
Refinanced Rs. 1 003 Crores of hi h cost debt
Reduction in interest rate by approx 1.47%
Awarded NDTV Profit Business Leadership Award, 2010 in PowerSector
9
8/8/2019 01.11.10 Analyst Presentation
10/42
10
8/8/2019 01.11.10 Analyst Presentation
11/42
PlantWisePerformance(Q2FY2011)CapacityGrowth(MW)
398%
11
8/8/2019 01.11.10 Analyst Presentation
12/42
VolumeGrowth(Millionkwh)NetGeneration(Millionkwh)
1781
108%
1211
47%
12
8/8/2019 01.11.10 Analyst Presentation
13/42
3,608
SalesMix(Millionkwh)
1,781
36 %
1,731
26 %1,211
64 % 74 %71 %
29 %
Q2FY2010 Q2FY2011 H1FY2010 H1 FY2011
Short Term Realisation 5.15 4.65 5.51 5.25
Realisation` perkwh
13
Average Realisation 4.61 4.34 4.94 4.71
8/8/2019 01.11.10 Analyst Presentation
14/42
14
8/8/2019 01.11.10 Analyst Presentation
15/42
Turnover(Turnover(` Crores)Crores) EBITDA (EBITDA (` Crores)Crores)
112 % 70 %
15 %
PBT (PBT (` Crores)Crores) PAT(PAT(` Crores)Crores)70 % 80 %
2 %6 %
15
8/8/2019 01.11.10 Analyst Presentation
16/42
573 875 Turnover (` Crores) 895 1,858
324 503 EBITDA (` Crores))) 374 857
57% 57% EBITDA (%) 42% 46%
71 110 I t t (` C )) 94 1681 110 Interest (` Crores)) 94 168
32 47 Depreciation (` Crores) 55 102
221 346 PBT (` Crores) 225 587174 268 PAT (` C ) 185 483
16
174 268 PAT (` Crores) 185 4831.27 1.96 EPS (` ) (Not Annual ised) 1.13 2.95
8/8/2019 01.11.10 Analyst Presentation
17/42
NetWorth
(` Crores) 4,780 5,264
Debt(` Crores) 7,870 8,634
NetFixed
Assets
(` Crores)
* 11,598 12,474
DebtEquityRatio(Times) 1.65 1.64
WeightedAverage
Cost
of
Debt 11.51
% 11.32
%
*Including CWIP
17
8/8/2019 01.11.10 Analyst Presentation
18/42
Utilisation
upto
September
30,
2010
Pro ect
Utilisationas
perProspectus
Actua Amount
Spentupto
Sept30,2010
PartFinanceforIdentifiedPro ects2142.53 969.31
RepaymentofCorporateDebt470.00 470.00
ShareIssueExpenses 75.98 64.52
GeneralCorporatePurpose11.49 -
UnutilisedAmount
nveste nMF Ban FD Ut se or
reductionofOverdraft
- 1196.17
GrossProceedsreceivedfromIPO 2,700.00 2700.00
18
8/8/2019 01.11.10 Analyst Presentation
19/42
Capacity expansion at Vijayanagar by 660 MW
Introduction of Employee Stock Option Scheme (ESOS)
ssuance o upto , , , stoc opt ons convert e nto equanumber of equity shares
(dilution of 1.20%)
Subject to approval of shareholders
19
8/8/2019 01.11.10 Analyst Presentation
20/42
20
8/8/2019 01.11.10 Analyst Presentation
21/42
StatusUpdateProjectDetails
GrossCapacity 1200
MW,
400
KV
Transmission
DoubleCircuit uadMoose
Jaigad KoynaLineIIsuccessfullychargedonJuly7,2010
Technology
ConductorLine
Procurement Ordersplaced
Jaigad Karad:
Tower Foundations: 88%
Tower Erection: 53%
ProjectCost
` 580CroresDebt:Equity:75:25
ActualspenttillSept30,2010:
` 377CrsExpected
CommissioningFebruary2011
21
8/8/2019 01.11.10 Analyst Presentation
22/42
Minedevelo ment rocesscommencedatKa urdi
StatusUpdate
BLMCL
MOEFClearancereceivedforJalipamines
Minedevelopment
plan
approved
for
Jalipa
mines
ExpectedtoextractlignitebyQ4FY2011
60%workcompletedforKapurdimines
LandacquisitionatadvancedstageforJalipamines
MJSJCoal Publichearingprocesscompleted
Landacquisitioninprocess
Tar ettocommence roductionin2012
JSWToshibaBladeshopmachiningcentreequipmentreceived
Temporarypowerreceivedatsite
ProgressforBladeShop97%
Blade
manufacturing
by
2011ManufacturingofTGsetsby2012 22
8/8/2019 01.11.10 Analyst Presentation
23/42
2323
8/8/2019 01.11.10 Analyst Presentation
24/42
Gross Ca acit 1 080MW 8x135Unit II COD October 4, 2010
StatusUpdateProjectDetails
Technology Sub-critical
Captive
Lignite
based
TPP
FSAwithBLMCL 49% V forsu l
PLF of 73.85% for Unit I during
September 2010
Unit III & IV boiler hydro test completed
Fuel Linkage oflignitefromcaptiveligniteminesof
BLMCL
Water
Raw Water pipe line commissioned
Tapering coal linkage approved byMinistry of Coal for 50% of coalAllocation
Power Off take
LongTerm:PPAforentirecapacity
withstateGovernmentdistribution
requirement
utilities
` 6085Crs
Project Cost
AmtspenttillSept30,2010:
` 4790Crs24
8/8/2019 01.11.10 Analyst Presentation
25/42
bi
Gross Capacity 1200MW(4x300) Boiler II light up done & steam blowing
StatusUpdateProjectDetails
Technology Sub-criticalImportedCoalbasedTPP
Fuel LinkageLongtermsupplyarrangementfor
Indonesiancoal&minesinSouthAfrica
starte
Unit II synchronization expected inNovember 2010
Water
AllocationMIDC+SeaWater
TG put on barring for Unit II
Boiler III & IV hydro test completed
Power Off take
passthrough
Abilitytoavailshorttermratesfor
balance900MW
in progress
Project Cost
` 5650Crs
Debt/Equity:75:25
AmtspenttillSept30,2010:` 4056Crs
Expected
Commissioning
UnitICODachievedon
September1,
2010
EntireprojectexpectedbyFY2011 25
8/8/2019 01.11.10 Analyst Presentation
26/42
GrossCapacity 1620MW Water availability study conducted
StatusUpdateProjectDetails
TechnologySuper-criticalDomesticcoalbasedTPP
ShareHoldin74% - JSWEL
In principle approval received for
entering into a LT PPA for surplus power
Agreement executed for coal raising &coal procurement
- enga ee m e
FuelLinkage
IchhapurMines- WBMDTCto
DPR finalised
Bids invited for BTG equipment supply
Land in possession
PowerOfftake
Captivesaletothesteelplanton
twoparttariffframeworkand
excess orou s esa e
ProjectCostPhase - I
` 3,300CrsforPowerplant` 1,500CrsforMinesDevelopmentAmtspenttillSept30,2010:` 3232
Expected
CommissioningPhase - I
October2014
26
8/8/2019 01.11.10 Analyst Presentation
27/42
Consent for chimney clearance given byAirport Authority
GrossCapacity 1,320MW(2x660)
Su er-criticaldomesticcoalbased
StatusUpdateProjectDetails
Tender documents for BTG issued
Public hearing completed in August2010
ec no ogyTPP
AuthorityMoUsignedwithGoCG forsettingupaTPPalongwithintegratedcoal
Water allocation obtained fromMahanadi river on September 8, 2010
Topography survey and geo-technical
FuelLinkage11%interestincoalblockjointlyallocated;appliedforadditional
coallinkage
Landacquisitioninprogress 225acres
alreadyacquired
WaterAllocation35mn cmpa waterallocatedfromMahanadiRiver
CombinationofLTPPAandshortPowerOfftake termagreementswithJSWPTC;35%
toStateGovt.
ProjectCost` 6,500Crs
AmtspenttillSept 30,2010:` 38CrsExpected
Commissioning 201427
8/8/2019 01.11.10 Analyst Presentation
28/42
Prequalification of vendors completed
StatusUpdateProjectDetails
GrossCapacity 240MW(3x80)
Technology Run-of-the-riverHydropower
or a n v or s
Public hearing for Environmentclearance held successfully
Water
AllocationRaviRiver
Freepower
to
GoHP 12%
to
Techno Economic Clearance from CEAreceived on August 30, 2010
Landacquisitionunderprogress All
sixaffectedGrampanchayatshavegivenPowerOfftake
years.Balancethroughshorttermarrangements
`
NOC
Environmentclearancemeeting
scheduledfor12th November,2010
ProjectCost
` Amt
spent
till
Sept
30,
2010
:` 91Crs
Biddocumentsfor maincivilworks
underfinalstageofpreparation
Commissioning2015
28
8/8/2019 01.11.10 Analyst Presentation
29/42
StatusUpdateProjectDetails
GrossCapacity 660MW(1x660)
Technology Supercritical
coal
based
TPP
Importedcoal/Domesticlinkage
Land identified
MOEFapprovalbeingappliedfor
coal
WaterSource Almatti Dam
PowerOfftakeerc an power ong erm
PPA
ProjectCost TotalCost:` 3,300CrsExpectedCommissioning
2014
29
8/8/2019 01.11.10 Analyst Presentation
30/42
StatusUpdateProjectDetails
Gross Capacity 270MW(2x135)
TechnologySubcriticalCaptivelignitebased
TPP
Land in possession
Appliedforcoallinkage
Fuel Linkage AppliedtoMinistryofCoal
Water
Allocation Allocation
from
IGNP
Power Off takeShortTermpowerpurchase
arrangements
TotalCost:` 1350CrsProject Cost
` Amount
spent
till
Sept
30,
2010
:` 61Crs
Expected
Commissionin2014-2015
30
8/8/2019 01.11.10 Analyst Presentation
31/42
StatusUpdateProjectDetails
,
Technology Super-critical
imported
coal
based
TPP
Substantial land in possession
Inthe
process
of
obtaining
necessaryconsentsandapprovals
Authority
ofMaharashtra
Fuel
Linkage Imported
Coal
WaterAllocation SeaWater
PowerOfftake
agreements
ProjectCost` 150Bn.
AmtspenttillSept30,2010:` 45CrsExpectedCommissioning
2016
31
8/8/2019 01.11.10 Analyst Presentation
32/42
32
8/8/2019 01.11.10 Analyst Presentation
33/42
BeyondCoreBusiness
Mining
Harnessgrowthopportunity
providedby
the
sector
SustainCoreBusiness
EquipmentManufacturing
Accessto
New
Business
Straddleallsegmentsof
powerbusiness
Transmission
Trading
Distribution
Integration
Strengt en ng
FuelSecurity
SecuringCoreBusiness
PowerGeneration
CostReduction
33
8/8/2019 01.11.10 Analyst Presentation
34/42
PlantOverview
34
8/8/2019 01.11.10 Analyst Presentation
35/42
AsonSeptember30,2010
35
AsonJune30,2010
8/8/2019 01.11.10 Analyst Presentation
36/42
AsonSeptember30,2010
AsonJune30,2010
36
8/8/2019 01.11.10 Analyst Presentation
37/42
TG4
TG3
37
8/8/2019 01.11.10 Analyst Presentation
38/42
AsonSeptember30,2010
38
AsonJune30,2010
8/8/2019 01.11.10 Analyst Presentation
39/42
AsonSeptember30,2010
AsonJune30,2010
39
8/8/2019 01.11.10 Analyst Presentation
40/42
40
8/8/2019 01.11.10 Analyst Presentation
41/42
Certain statements in this report concerning our future growth prospects are forward lookingstatements, which involve a number of risks, and uncertainties that could cause actual results todiffer materially from those in such forward looking statements. The risk and uncertaintiesrelating to these statements include, but are not limited to risks and uncertainties regarding
fluctuations in earnings, our ability to manage growth, intense competition within Power industry, ,
attract and retain highly skilled professionals, time and cost overruns on fixed-price, fixed-timeframe contracts, our ability to commission mines within contemplated time and costs, our ability toraise the finance within time and cost client concentration, restrictions on immigration, our ability
to mana e our internal o erations, reduced demand or ower, our abilit to success ull com leteand integrate potential acquisitions, liability for damages on our service contracts, the success ofthe companies in which the Company has made strategic investments, withdrawal of
fiscal/governmental incentives, impact of regulatory measures, political instability, legalrestrictions on raising capital or acquiring companies outside India, unauthorized use of ourn e ec ua proper y an genera econom c con ons a ec ng our n us ry. e company oes
not undertake to update any forward looking statements that may be made from time to time by oron behalf of the company.
41
8/8/2019 01.11.10 Analyst Presentation
42/42
42