    SAP Note

    Header Data

    Symptom

    How can our organization use availability control for cost centers?

    Other Terms

    budget check active accounting

    Reason and Prerequisites

    Solution

    Active availability control in the Overhead Cost Controlling component (CO-OM) is intended forindividual measures only, meaning orders and WBS elements. For responsibility areas, you can use theFunds Management component (TR-FM in Release 3.0, FI-FM since Release 4.0) to create accountassignments for availability control and assign them to cost centers.

    If you dont want to use this component, the Cost Center Accounting component (CO-OM-CCA) supportspassive availability control via the information system. If you need availability control for costcenters infrequently, the easiest solution is to run reports that compare actual values andcommitments with plan values or budgets for the cost centers in question.

    For an active availability control on cost centers in the Overhead Cost Controlling component youcan use following simple workaround.

    1. Create a statistical order (an internal order used to evaluate costs for information purposesonly) for each cost center in question.

    2. In the order master data, enter the cost center to be monitored as the requesting costcenter.

    3. Activate availability control for the order.

    4. During posting, post costs to the order instead of the cost center. The R/3 System treats

    these as statistical costs, and simultaneously makes (real) postings to the associated costcenter. You can then use availability control for the order.

    Validity

    This document is not restricted to a software component or software component version

    References

    This document refers to:

    SAP Notes

    This document is referenced by:

    101030 - FAQ: Availability Control for Cost Centers

    Version 3 Validity:02.04.2003 - active Language English (Master)

    Released On 03.04.2003 07:58:45

    Release Status Released for Customer

    Component CO-OM-CCA Cost Center Accounting

    CO-OM-OPA Overhead OrdersPriority Recommendations / Additional Info

    Category Consulting

    397799 INFORMATION: CO-OM-OPA (Order & Project Accounting)

    397239 INFO:CO-OM Interface/actual postings/commitment/down payment

    Other Components

  • 7/25/2019 0000101030

    2/2

    SAP Notes (2)

    397799 INFORMATION: CO-OM-OPA (Order & Project Accounting)

    397239 INFO:CO-OM Interface/actual postings/commitment/down payment