1/3
Date 9-Apr-05 Document Code PM-L4A Process ID F2-SCA-ASR-PR-321218
Project Al Jawal View Level Departmental Process Allocate Specific Resource to Service
Developed By F. Alrubaie Version 0.3
Reviewed By Work Team Approved By Director Mobile Services O&M
Sources Customers
VAS Engineering Resource Allocated to Service VAS Engineering
Sales-Key Accounts
Activities Owners
Output(s)
Service Provisioning Request
Items Items
Implement & Configure Service Process
Activities
Key Performance Indicator(s)
Not Identified.Make allocation for VAS resources to provision VAS services
Key Control(s)
Not identified. Not Identified.
VAS Engineering request to make necessary provisioning for VAS services.
Input(s)
Business Risks
Value Added Services (VAS)
Value Added Services (VAS)
Business Objective(s)
1-Carry out Resource Assignment
2-Confirm Resource Allocation
Trigger(s)
Description
Value Added Services (VAS)Process Owner(s)
Issue identifiers for new services and to manage identifier pools for services
Page-3/3
8/3/2019 0-Allocate Specific Resource to Service
2/3
Date 9-Apr-05 Document Code PM-L4B Process ID
Project Al Jawal View Level Departmental Process
Developed By F. Alrubaie Version 0.3
Reviewed By Work Team Approved By Director Mobile Services O&M
Responsible
Allocate Specific Resource to Service
F2-SCA-ASR-PR-321218
1. Receive request from VAS Engineering
1-Carry out Resource Assignment
The provisioning of the VAS services (e.g. Bulk SMS service to key customers) requires
making appropriate resource allocations, for example, within the Short Messaging
Service Center (SMSC) managed by the Value Added Services (VAS) group to allow
direct access to the key account customer through the leased link provided by the data
and IT groups for the Bulk SMS service. This may also include opening up of ranges for
voice mailboxes.
2. Review and Clarify Request & Design Information
3. Assign resource(s) to service
Value Added Services (VAS)
2-Confirm Resource Allocation
Once appropriate allocation of resources has been made, the service is ready for
implementation, configuration and finally end to end testing. The VAS group confirms
to VAS Engineering the carrying out of the resource allocation so as to proceed further.
1. Confirm resource availability
2. Confirm resource allocation
Value Added Services (VAS)
Activities Description Tasks
Process Owner(s) Value Added Services (VAS)
Page-3/3
8/3/2019 0-Allocate Specific Resource to Service
3/3
Date 9-Apr-05 Document Code PM-L4C Process ID F2-SCA-ASR-PR-321218
Project Al Jawal View Level Departmental Process Allocate Specific Resource to Servic
Developed By F. Alrubaie Version 0.3
Reviewed By Work Team Approved By Director Mobile Services O&MProcess Owner(s) Value Added Services (VAS)
Page-3/3