K. Long, 23 August 2009

Sunday23Aug09

Water and powerconnections made

Test water, checkpower

Will plan soak test

Status of build:• Target 1:– Complete, 50 k actuations done OK • Target 2:

– Complete

Critical path:

• Issue:– Modified power supply:

• Charge/discharge time-constant differs between +ve and –ve capacitor banks

• S.Griffiths will investigate– Testing continues with power supply brought to RAL form Sheffield

• Installation planned ‘on schedule’:– Tuesday/Wednesday 25/26Aug09