Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
Environmental Monitoring Report
This report has been submitted to ADB by Rajasthan Urban Infrastructure Development Project, Jaipur and the Asian Development Bank and is made publicly available in accordance with ADB’s Public Communications Policy (2011). It does not necessarily reflect the views of ADB.
This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Project Number: 40031-023/40031-033/40031-053 June 2017 Period: July 2016 – December 2016
IND: Rajasthan Urban Sector Development Investment Program - Tranche 1, 2 & 3
Submitted by: Rajasthan Urban Infrastructure Development Project, Jaipur
Environmental Monitoring Report
Semi-annual Environmental Monitoring Report
Tranche 1(Loan Number 2366 – IND)
Tranche 2 (Loan Number 2506 –IND)
Tranche 3 (Loan Number 2725 –IND)
Document Stage: Final
Project Number: 40031
Month Year: December 2016
IND: Rajasthan Urban Sector Development Investment
Program
Prepared by Local Self Government Department
This report has been submitted to ADB by the Local Self-Government Department of the Government
of Rajasthan and is made publicly available in accordance with ADB’s public communications policy
(2005), it does not necessarily reflect the views of ADB
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: I ADB Loan No. 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: December 2016
Environmental Monitoring Report
Contents
I. INTRODUCTION ........................................................................................................................... 1
A) BACKGROUND ................................................................................................................................................ 1
B) PROJECT PURPOSE ......................................................................................................................................... 1
C) PROJECT PROFILE ........................................................................................................................................... 2
II. APPLICATION OF ENVIRONMENTAL MANAGEMENT PLAN ......................................................... 4
III. ENVIRONMENTAL PROCEDURE REVIEW ............................................................................. 164
A). ENVIRONMENTAL LEGAL REQUIREMENTS ........................................................................................... 164
B). COMPLIANCE OF ENVIRONMENTAL REGULATIONS ............................................................................... 165
C). COMPLIANCE OF ENVIRONMENTAL LOAN COVENANTS ......................................................................... 173
D). ENVIRONMENTAL ORGANIZATION AND MANAGEMENT ........................................................................ 174
E). GRIEVANCE REDRESSAL ................................................................................................................... 175
IV. ENVIRONMENTAL MONITORING AND EVALUATION .......................................................... 178
V. CONCLUSIONS AND RECOMMENDATIONS ............................................................................. 180
List of Tables
Table 1:Implementation Status of Sub-projects under Tranche - 1 ....................................................... 2
Table 2:Implementation Status of Sub-projects under Tranche - 2 ....................................................... 2
Table 3: Implementation Status of Sub-projects under Tranche – 3 ...................................................... 3
Table 4:Ongoing sub projects under review (July - December 2016) .................................................... 5
Table 5:EMP Compliance Status of Alwar Waste Water Subproject: { Tr-01/ALW/WW-03 & WW/05} 7
Table 6: EMP Compliance Status of Alwar Water Supply sub-project {TR-01/ALW/WS-03} ................ 13
Table 7: EMP Compliance Status of Jaisalmer Water Supply subproject {TR-01/JSL/WS-02} .............. 20
Table 8: EMP Compliance Status of Jaisalmer Waste Water subproject {TR-01/JSL/WW-01} ............. 27
Table 9: EMP Compliance Status of Alwar WasteWater sub-project {TR-02/ALW/WW-06} ............... 34
Table 10: EMP Compliance Status of Bhratpur ROB sub-project {TR-02/BPR/BR/02} ......................... 41
Table 11: EMP Compliance Status of Water Supply sub-project {TR-02/DLP/WS/03} ......................... 47
Table 12: EMP Compliance Status of Dholpur Waste Water project {WW/04, WW/08& WW/11} .... 53
Table 13: EMP Compliance Status of Sikar Water Supply sub Project {TR-02/SKR/WS-04} ................. 60
Table 14: EMP Compliance Status of Nagaur Waste Water sub-project {TR-02/NGR/WW/02-Lot-2} 67
Table 15: EMP Compliance Status of Barmer Waste Water sub-project {WW/03 Lot-1 & Lot-2} ...... 74
Table 16: EMP Compliance Status of Churu subproject (TR-02/CHU/WS-04) ...................................... 80
Table 17: EMP Compliance Status of Bundi Road sub-project { TR-02/BND/ST/04} ............................ 86
Table 18: EMP Compliance Status of Bundi waste water sub-project {TR-02/BND/WW/06} .............. 92
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: II ADB Loan No. 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: December 2016
Environmental Monitoring Report
Table 19: EMP Compliance Status of RajsamandWaste Water sub-project {TR-02/RSM/WW/03} ..... 98
Table 20: EMP Compliance Status of Jhalawar Waste Water sub-project { TR-02/JHL/WW/02} ...... 104
Table 21: EMP Compliance Status of Karauli Waste Water project { Tr-03/KRL/WW/04 & WW/05} 111
Table 22: EMP Compliance Status of Bharatpur Waste Water {Tr-03/WW/01 (Lot 1) & (Lot 2)} ...... 118
Table 23:EMP Compliance Status of Jaisalmer Waste Water subproject { Tr-03/JSL/WW/06} .............. 124
Table 24: EMP Compliance Status of Churu Waste Water Subproject { Tr-03/CHU/WW/01} ........... 130
Table 25: EMP Compliance Status of Churu Drainage Subproject { Tr-03/CHU/DR/03 & 04} ............ 136
Table 26: EMP Compliance Status of Churu Road subproject {RUSDIP/TR-03/CHU/ST/01} .............. 143
Table 27: EMP Compliance Status of Chittorgarh Waste Water project { Tr-03/WW/01, Lot-1 & Lot-2}
............................................................................................................................................................ 150
Table 28: EMP Compliance Status of Chittorgarh RUB Subproject {RUSDIP/TR-03/CHT/BR/03} ........... 156
Table 29: Action Required Ensuring Subprojects Comply with National Environmental Laws .......... 164
Table 30: Present Status of Environment and Forest & Other Clearances ......................................... 166
Table 31: Status of complia e of ADB s ajo E i o e tal Loa Co e a ts ............................... 173
Table 32: Town-wise number of Grievances ...................................................................................... 175
Table 33: Methodology of Sampling and Analysis and Equipment Used ........................................... 179
List of Figures
Figure 1: Institutional Responsibly-Environmental Organization RUSDIP .......................................... 176
Figure 2 Grievance Redressal Process ................................................................................................. 177
List of Annexures
Annexure 1: Environmental Legislation and Pollution Control Acts ................................................... 182
Annexure 2: Major works and progress- ............................................................................................ 184
Annexure 3: Environmental Monitoring Schedule ............................................................................. 197
Annexure 4: Pu li o sultatio …………………………………….…………………...……... ................................. .199
A e u e : Mo ilizatio s hedule…………………………………………….……………...… ................................. 205
Annexure : Photog aphs…………………………………………………...……………...….… ..................................... 206
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 1 ADB Loan No. 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: December 2016
Environmental Monitoring Report
I. INTRODUCTION
A) Background
1. Rajasthan Urban Sector Development Investment Program (RUSDIP) is intended to optimize
social and economic development in 15 selected towns in the State, particularly district
headquarters and towns with significant tourism potential. This will be achieved through
investments in urban infrastructure (water supply; sewerage and sanitation; solid waste
management; urban drainage; urban transport and roads), urban community upgrading (community
infrastructure; livelihood promotion) and civic infrastructure (art, culture, heritage and tourism;
medical services and health; fire services; and other services). RUSDIP will also provide policy
reforms to strengthen urban governance, management, and support for urban infrastructure and
services. The assistance will be based on the State-level framework for urban reforms, and
institutional and governance reforms recommended by the Government of India (GoI) through the
Jawaharlal Nehru National Urban Renewal Mission (JNNURM) and Urban Infrastructure
Development Scheme for Small and Medium Towns (UIDSSMT).
2. RUSDIP Phase II to be implemented over a seven year period beginning in 2008, and will be
funded by a loan via the Multitranche Financing Facility (MFF) of the ADB. The Executing Agency (EA)
is the Local Self-Government Department (LSGD) of the Government of Rajasthan (GoR); and the
Implementing Agency (IA) is the Project Management Unit (PMU) of the Rajasthan Urban
Infrastructure Development Project (RUIDP), which is currently in the construction stage (Tr-1, Tr-
2&Tr-3).Alwar, Jaisalmer and Jhalwar/ Jhalarapatan are the towns chosen to benefit from the first
tranche of RUSDIP investment. While 12 other towns namely, Bharatpur, Karauli, Dholpur,
SawaiMadhopur, Sikar, Barmer, Nagaur, Chittorgarh, Rajsamand andBundi are considered under
tranche 2 and 3 (Tr-2 & 3).
3. This report presents environmental monitoring for reporting period from July to December
2016 for Tranche-1, Tranche-2 and Tranche-3 sub-projects.
B) Project Purpose
4. RUSDIP will improve infrastructure through the development, design and implementation of
a series of subprojects, each providing improvements in a particular sector (water supply, sewerage,
solid waste etc.) in one town. RUSDIP has been classified by ADB as environmental assessment
category B (some negative impacts but less significant than category A) and the impacts of
subprojects were assessed through Initial Environmental Examination (IEE) reports prepared
according to ADB Environment Policy (2002), SPS 2009 and Environmental Assessment Guidelines
(2003).
5. The nature of the sub-projects may change during their subsequent development, particularly
during detailed design. This report is the Environmental Monitoring Report (EMR) to describe the
implementation of the mitigation measures and monitoring recommended in the IEE and summary
Initial Environmental Examination (SIEE).
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 2 ADB Loan No. 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: December 2016
Environmental Monitoring Report
C) Project Profile
6. Till 31st
December 2016, 17 sub-projects under Tranche-1 have been awarded, 48 sub-
projects under Tranche 2 and 36 sub-projects under Tranche 3 have been awarded. Details of which
is shown in table -1, 2 and 3 respectively.
7. Out of those 17 sub-projects in Trache-01, 09 packages in Alwar, 6 packages in Jaisalmer and
2 packages in Jhalawar-Jhalrapatan have been awarded. 11 sub projects has already been completed
and 1 terminated. In this report period field work continued for 5 sub-projects in Tranche-01.
8. Out of those 48 sub-projects in Trache-02, in the report period actual field work is continued
in 15 sub projects, 26 sub projects were completed and 7 terminated.
9. Out of those 36 sub-projects In Trache-3, In the report period actual field work is continued
in 12 sub projects, 23 sub projects were completed and 1 terminated.
10. The application of EMP in all ongoing sub-projects is shown in tables below in this chapter.
The implementation status of sub-projects under Tranche 1,2 & 3 has been summarized in Table -1,
2 & 3.
Table 1: Implementation Status of Sub-projects under Tranche - 1
Town
Number of Sub-projects
Awarded Under-
implementation Completed
Yet to
be
started
Work
Stopped
Terminated/
Dropped
Alwar
09
1 03 06 - - -
Jaisalmer
06 02 03 - - 01
Jhalwar-
Jhalrapatan
02 00 02 - - -
Total 17 05 11 - - 01
Table 2: Implementation Status of Sub-projects under Tranche - 2
Town
Number of Sub-projects
Awarded Under-
implementation Completed
Yet to be
started
Work
Stopped
Terminated/
Dropped
Alwar 2 1 1 - - -
Karauli 1 - 1 - - -
SawaiMadhopur 3 0 3 - - -
1 One sub project (RUSDIP/TR-01/ALW/WS-03) has been added during this reporting period which is not
reflected in previous EMRs for the period Jan-June 2016, July-December 2015 and Jan-June 2015 . The
environmental assessment of this subproject was already covered in IEE report.
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 3 ADB Loan No. 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: December 2016
Environmental Monitoring Report
Town
Number of Sub-projects
Awarded Under-
implementation Completed
Yet to be
started
Work
Stopped
Terminated/
Dropped
Bharatpur 5 1 4 - -
Dholpur 5 4 1 - -
Sikar 8 1 6 - - 1
Nagaur 4 1 2 - - 1
Churu 3 1 1 - - 1
Barmer 5 2 2 - - 1
Baran 2 0 2 - - -
Bundi 4 2 1 - - 1
Chittorgarh 1 - 1 - - -
Rajsamand 4 1 1 - - 2
Jhalawar 1 1 - - - -
Total 48 15 26 00 - 07
Table 3: Implementation Status of Sub-projects under Tranche – 3
Town
NumberofSub-projects
Awarded Under-
implementation
Completed Yettobe
started
Work
Stopped Terminated
/Dropped
Alwar
01
00
01
- -
-
Bharatpur
03
02
01
- - -
Dholpur
04
00
04
- - -
Karauli
03
02
01
- - -
Sawai
Madhopur
03
-
03
- -
-
Barmer
01
01
- -
Churu
04
04
-
- - -
Jaisalmer
01
01
-
- - -
Nagaur
03
0
03
- - -
Sikar
-
-
-
- - -
Baran
03
00
03
- - -
Bundi
02
-
01
- - 01
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 4 ADB Loan No. 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: December 2016
Environmental Monitoring Report
Town
NumberofSub-projects
Awarded Under-
implementation
Completed Yettobe
started
Work
Stopped Terminated
/Dropped
Chittorgarh
05
03
02
- - -
Jhalwar-
Jhaleapatan
01
-
01
- -
-
Rajsamand
02
-
02
- - -
Total 36 12 23 00 - 01
II. APPLICATION OF ENVIRONMENTAL MANAGEMENT PLAN
11. At present there are 17 sub-projects under Tranche 1 have been awarded to the contractors.
Major Field activities are ongoing for 5 sub-projects. EMP has been implemented for 11 sub-
projects, as per IEE report. The detailed list of projects under review is presented in Table 1. Overall
compliance status of EMP application and actions needed are discussed below and shown in Table 5
to Table 8.
12. At present there are 48 sub-projects under Tranche 2 have been awarded to the contractors.
Major Field activities are ongoing for 15 sub-projects. EMP has been implemented for 26 sub-
projectsas per IEE report. The detailed list of projects under review is presented in Table 2. Overall
compliance status of EMP application and actions needed are discussed below and shown in Table 9
to Table 20.
13. At present there are 36 sub-projects under Tranche 3 have been awarded to the contractors.
Major Field activities are ongoing for 12 sub-projects. EMP has been implemented for 23 sub-
projects as per IEE report. The detailed list of projects under review is presented in Table 3. Overall
compliance status of EMP application and actions needed are discussed below and shown in Table
21 to Table 28.
14. The EMP has been implemented in all ongoing sub-projects and status of the same is being
monitored. Annexure 2 shows summary of the scope of works, present work status, and expected
changes from the approved objectives, remedial measures for fulfillment of objective and key risks/
assumption for attainment of objectives.
15. T ai i g has ee gi e to the o t a to s, D“C s o ito ing specialist and IPIU
representative on environmental safeguard requirement. The status/progress of EMP
implementation is also being reviewed in quarterly review meetings and necessary training is being
provided. Moreover, instruction is given to contractors to follow the specified clause of BID
document to mitigate environmental and social impacts.
16. The progress of implementation of the EMP has been monitored for each ongoing sub-
project. For the purpose of monitoring of EMP and progress reporting project sector specific formats
were developed according the expected activities. The compliance with the EMP are expressed
below for each sub-project:
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 5 ADB Loan No. 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: December 2016
Environmental Monitoring Report
Table 4:Ongoing sub projects under review for Implementation of Environmental management
Plan (July - December 2016)
Sr. No. Project Town Packages
TR-1
1 Alwar Waste Water: Supply, laying, jointing, testing and commissioning of various Main and
arterial sewer Network connecting to outfall, along with road restoration and all
necessary manholes appurtenances etc. at Alwar town. (RUSDIP/TR-01/ALW/WW/03)
2 Waste Water: Additional Sewerage System in UIT colonies at Alwar
(RUSDIP/TR-01/ALW/WW/05)
3 Water Supply: Providing installation, testing & commissioning of Bulk flow meters &
domestic water meters in Alwar.
(RUSDIP/TR-01/ALW/WS/03)2
4 Jaisalmer Water Supply: Providing, Laying, Jointing, Testing & Commissioning of water pipe line
for the strengthening of distribution system and rising main pipeline; Construction and
Commissioning of Elevated service reservoirs and providing pumping system and
ancillary works;
Package No: { RUSDIP/TR-01/ JSL/WS-02}
5 Waste Water – Sewerage and Waste stabilization Ponds in Phase-I in Jaisalmer;
Package No: {RUSDIP/TR-01/ JSL/WW-01}
TR-2
1 Alwar Waste Water: Waste Water work in Alwar
Package No: {RUSDIP/TR-02/ ALW/WW/06}
2 Bharatpur Bridge: Reconstruction of ROB and Approaches at Bharatpur town.
Package No: {RUSDIP/TR-02/BPR/BR/02}
3 Dholpur Water Supply: Design, Construction and Commissioning of 15 MLD capacity Water
Treatment Plant including commissioning of equipments at Sagarpada; Construction of
CWRs & OHSRs including supply, laying and commissioning with testing of DI & uPVC
pipelines and replacing of leakaged pipeline etc. for UWSS Dholpur.
Package No: {RUSDIP/ TR-02/ DLP/WS/03}
4 Waste Water: Supply, Laying, Jointing, Testing and Commissioning of outfall sewer,
trunk sewers, lateral sewers, lateral sewers along with construction of manholes,
appurtenances etc. at Dholpur.
Package No. : (RUSDIP/TR-02/DLP/WW/04)
5 Waste Water: Dholpur Sewerage work
2 One sub project (RUSDIP/TR-01/ALW/WS-03) has been added during this reporting period which is not
reflected in previous EMRs for the period Jan-June 2016, July-December 2015 and Jan-June 2015 . The
environmental assessment of this subproject was already covered in IEE report.
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 6 ADB Loan No. 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: December 2016
Environmental Monitoring Report
Sr. No. Project Town Packages
TR-1
1 Alwar Waste Water: Supply, laying, jointing, testing and commissioning of various Main and
arterial sewer Network connecting to outfall, along with road restoration and all
necessary manholes appurtenances etc. at Alwar town. (RUSDIP/TR-01/ALW/WW/03)
2 Waste Water: Additional Sewerage System in UIT colonies at Alwar
(RUSDIP/TR-01/ALW/WW/05)
3 Water Supply: Providing installation, testing & commissioning of Bulk flow meters &
domestic water meters in Alwar.
(RUSDIP/TR-01/ALW/WS/03)2
4 Jaisalmer Water Supply: Providing, Laying, Jointing, Testing & Commissioning of water pipe line
for the strengthening of distribution system and rising main pipeline; Construction and
Commissioning of Elevated service reservoirs and providing pumping system and
ancillary works;
Package No: { RUSDIP/TR-01/ JSL/WS-02}
5 Waste Water – Sewerage and Waste stabilization Ponds in Phase-I in Jaisalmer;
Package No: {RUSDIP/TR-01/ JSL/WW-01}
RUSDIP/TR-02/DLP/WW/08
6 Dholpur Waste Water: Design, construction, supply, erection, testing, commissioning and 5
years operation and maintenance of 3 MLD Sewage Treatment Plant (STP) based on
SBR process with sewage pumping/lifting station including all civil, electrical,
mechanical, pumping and allied works at Dholpur town.
Package No.: {RUSDIP/TR-02/DLP/WW/11}
7 Sikar
Water Supply: Additional work for augmentation of production of drinking water from
newly proposed Intermediate pumping Stations to various reservoirs in Sikar town.
Package No: (RUSDIP/ TR-02/ SKR/WS/04)
8 Nagaur 8 MLD STP (RUSDIP/TR-02/NGR/WW-02 (Lot-02)
9 Barmer
Waste water: Supply, sewer line work
{RUSDIP/TR-2/BMR/WW/03 (Lot-1)}
10
Waste water: STP 10 MLD
{RUSDIP/TR-2/BMR/WW/03 (Lot-2)}
11 Churu Water Supply: Water Supply Project in churu city
RUSDIP/ TR-02/ CHU/ WS/04
12 Bundi Roads: Widening and Strengthening of 13 different Roads in Bundi city. (RUSDIP/TR-
02/BND/ST/04)
13
Bundi
Waste Water: Construction of STP 8 MLD, 1 nos. SPS, out fall and trunk sewer 13.130
Kms
Package Number : (RUSDIP/TR-02/BND/WW/06)
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 7 ADB Loan No. 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: December 2016
Environmental Monitoring Report
Sr. No. Project Town Packages
TR-1
1 Alwar Waste Water: Supply, laying, jointing, testing and commissioning of various Main and
arterial sewer Network connecting to outfall, along with road restoration and all
necessary manholes appurtenances etc. at Alwar town. (RUSDIP/TR-01/ALW/WW/03)
2 Waste Water: Additional Sewerage System in UIT colonies at Alwar
(RUSDIP/TR-01/ALW/WW/05)
3 Water Supply: Providing installation, testing & commissioning of Bulk flow meters &
domestic water meters in Alwar.
(RUSDIP/TR-01/ALW/WS/03)2
4 Jaisalmer Water Supply: Providing, Laying, Jointing, Testing & Commissioning of water pipe line
for the strengthening of distribution system and rising main pipeline; Construction and
Commissioning of Elevated service reservoirs and providing pumping system and
ancillary works;
Package No: { RUSDIP/TR-01/ JSL/WS-02}
5 Waste Water – Sewerage and Waste stabilization Ponds in Phase-I in Jaisalmer;
Package No: {RUSDIP/TR-01/ JSL/WW-01}
14
Rajsamand Waste Water: Design, Construction, Supply, erection testing, commissioning and five
years operation & maintenance of left over works of Sewage Treatment plant 5 MLD
with Sewage pumping station including all civil, electrical, mechanical, pumping and
other allied works and supply, laying joining, testing and commissioning of outfall
sewer, various Trunk sewers, collecting and lateral sewers along with all necessary
manholes, appurtenances etc. at Rajsamand.
Package No: (RUSDIP/TR-02/RSM/WW /03)
15 Jhalawar Waste Water: Laying of Sewer line network at Jhalawar&Jhalarapatan
town{RUSDIP/TR-02/JHL/WW/02}
TR-3
1 Karauli Waste Water: Design, construction, supply, erection testing, commissioning and
first five years operation & maintenance of sewage treatment plant 5 MLD near
charagah including all civil, electrical, mechanical, pumping and other allied works
at Karauli town. (RUSDIP/TR-03/KRL/WW/04)
2 Waste Water: Supply, laying, jointing etc. supply ,laying, jointing, testing and
commissioning of various trunk sewerage collecting and lateral sewers
connecting to out fall, along with all necessary manholes, appurtenances, etc. at
Karauli
town.
(RUSDIP/TR-03/KRL/WW/05)
3 Bharatpur Waste Water: Supply, laying, joining, testing and commissioning of outfall sewer,
various Trunk sewers and lateral sewers connecting to out fall, along with all
necessary manholes, appurtenances, etc. at Bharatpur town.
Package No: { RUSDIP/TR-03/BPR/WW/01(Lot-1)}
4 Waste Water – Design, Construction, Supply, erection, testing, commissioning and
five years operation & maintenance of Sewage pumping station, Pumping
main and Sewage Treatment plant 8 MLD near Ikran Village including all civil,
electrical, mechanical, pumping and other allied works at Bharatpur town:
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 8 ADB Loan No. 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: December 2016
Environmental Monitoring Report
Sr. No. Project Town Packages
TR-1
1 Alwar Waste Water: Supply, laying, jointing, testing and commissioning of various Main and
arterial sewer Network connecting to outfall, along with road restoration and all
necessary manholes appurtenances etc. at Alwar town. (RUSDIP/TR-01/ALW/WW/03)
2 Waste Water: Additional Sewerage System in UIT colonies at Alwar
(RUSDIP/TR-01/ALW/WW/05)
3 Water Supply: Providing installation, testing & commissioning of Bulk flow meters &
domestic water meters in Alwar.
(RUSDIP/TR-01/ALW/WS/03)2
4 Jaisalmer Water Supply: Providing, Laying, Jointing, Testing & Commissioning of water pipe line
for the strengthening of distribution system and rising main pipeline; Construction and
Commissioning of Elevated service reservoirs and providing pumping system and
ancillary works;
Package No: { RUSDIP/TR-01/ JSL/WS-02}
5 Waste Water – Sewerage and Waste stabilization Ponds in Phase-I in Jaisalmer;
Package No: {RUSDIP/TR-01/ JSL/WW-01}
{RUSDIP/TR-03/BPR/WW/01(Lot-2)}
5 Jaisalmer Waste Water: Providing, construction, laying, jointing, testing and commissioning of
sewerage network system with all appurtenances and property connections,
Water supply Distribution net work system with house service connections; under
grounding ducting for Electric and Telephone cables; dismantling and restoration of
stone slab pavement Inside Jaisalmer Fort.
(RUSDIP/TR-03/JSL/WW/06)
6 Churu
Waste Water: Design, Construction, Supply, Erection testing , Commissioning and
five year operation & maintenance of Sewage treatment 7 MLD (WSP)
including all civil , and other allied Works and supply, laying, jointing, testing and
commissioning of outfall sewer , various Trunk sewers and laterals sewers connecting
to outfall, along with all necessary manholes appurtenances etc. at Churu town.
(RUSDIP/TR-03/CHU/WW/01)
7 Drainage: Churu Drainage work
RUSDIP/TR-03/CHU/DR/03
8 Drainage: Additional work of Churu drainage work
RUSDIP/TR-03/CHU/DR/04
9 Improvement of City Road & Drain work at Churu
Package No: RUSDIP/TR-03/CHU/ST/01
10 Chittorgarh Waste Water: Supply, laying, joining, testing and commissioning of outfall sewer,
various Trunk and lateral sewers connecting to out fall, along with all necessary
manholes, appurtenances, etc. at Chittorgarh town.
RUSDIP/TR-03/CHT/WW/01(Lot-1)
11 Waste Water: Design, Construction, Supply, erection, Testing commissioning and
five year operation and maintenance of 5 MLD sewerage Treatment plant near Bhoi
Khera including all civil, Electrical & mechanical works at Chittorgarh town.
RUSDIP/TR-03/CHT/WW/01(Lot-2)
12 Bridge: Construction of approach road and allied work for RUB near railway
culvert no.226 towards Chanderia at Chittorgarh. RUSDIP/TR-03/CHT/BR/03
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 7
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
EMP for Tranche-01 Sub-Projects
Table 5: EMP Compliance Status of Alwar Waste Water Subproject: {RUSDIP/TR-01/ALW/WW-03 & WW/05}
Sr.
No.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
Pre Construction Stage
1 Environmental Clearances
Site preparation work completed by IPIU including necessary
clearance
Consent to Establish under Water (Prevention and Control
of Pollution) Act
Consent to Establish under Air (Prevention and Control of
Pollution) Act
Tree-cutting Permit
Complied
Consent to Establish is not
required as scope include only
laying of pipes in both of the
package
Tree cutting is not required
Nil DSC/ IPIU
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain an
expert assessment of the archaeological potential of the site;
(ii) Consider alternatives if the site is found to be of medium
or high risk;
(iii) Include state and local archaeological, cultural and
historical authorities, and interest groups in consultation
forums as project stakeholders so that their expertise can be
made available; and
(iv) Develop a protocol for use by the construction
contractors in conducting any excavation work, to ensure
that any chance finds are recognized and measures are taken
to ensure they are protected and conserved.
Complied It was confirmed by consultations
with various stakeholders that the
site has no archaeological
potential
Instruction has been given to the
contractor to ensure that any
chance finds are recognized and
measures are taken to ensure they
are protected and conserved
No such occurrence till date
Nil DSC/ IPIU
3 Construction work camps, hot mix plants, stockpile areas,
storage areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant space in
the subproject sites;
(ii) If it is deemed necessary to locate elsewhere, consider
sites that will not promote instability and result in
Complied All the facilities related to
construction are located within
project site
There are neither any work camps
nor hot mix plants established for
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 8
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
destruction of property, vegetation, irrigation, and drinking
water supply systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct
disposal to water body or in areas which will inconvenience
the community.
project works.
Construction materials are
temporarily stored at sites with
due consideration of safeguard
norms taking into account
vegetation, irrigation, and drinking
water supply systems.
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining
Department;
(ii) If other sites are necessary, inform construction
contractor that it is their responsibility to verify the
suitability of all material sources and to obtain the approval
of IPIU; and
(iii) If additional quarries will be required after construction is
started, inform construction contractor to obtain a written
approval from IPMU.
Complied All the material is being taken from
approved mines
Nil DSC/ IPIU
Construction Stage
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain
approval of Investment Program Implementation Unit ( IPIU);
(iii) If additional quarries will be required after construction
has started, obtain written approval from PMU; and;
(iv) Submit to DSC on a monthly basis documentation of
sources of materials.
Complied All the material is being taken from
government approved quarry sites
Nil DSC/ IPIU
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for
stockpiling of clay, soils, gravel, and other construction
materials;
Partially
Complied
Major Excavation works are
completed hence Air quality
monitoring is not required in the
reporting period.
Nil Contractor/ DSC/
IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 9
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
(ii) Damp down exposed soil and any stockpiled on site by
spraying with water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material
when transported by trucks; and
(iv) Fit all heavy equipment and machinery with air pollution
control devices which are operating correctly.
Construction materials have been
stockpiled at designated areas in
consultation with IPIU
Water sprinkling is being done as
and when required
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the
monsoon season unless covered by tarpaulins or plastic
sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins along
the drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from
any drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities in
designated sites; and
(vi) Conduct surface water quality inspection according to
the Environmental Management Plan (EMP).
Partially
Complied
Major Excavation works are
completed hence Ground water
quality monitoring is not required
during monitoring period.
Excavated soil is being reused for
backfilling and excess material is
being disposed in low lying areas
surface water quality inspection is
not required as there is no surface
water body near subproject site
Oil & lubricant has been stored
away from drainage
Nil Contractor/ DSC/
IPIU
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that
activities with the greatest potential to generate noise are
conducted during periods of the day which will result in least
disturbance;
(ii) Require horns not be used unless it is necessary to warn
othe oad use s o a i als of the ehi le s app oa h; (iii) Minimize noise from construction equipment by using
vehicle silencers, fitting jackhammers with noise-reducing
Partially
Complied
Work is almost completed
therefore Noise level monitoring is
not required as no major
machinery is in use.
Nil Contractor/DSC/
IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 10
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
mufflers, and portable street barriers the sound impact to
surrounding sensitive receptor; and
(iv) Maintain maximum sound levels not exceeding 80
decibels (dbA) when measured at a distance of 10 m or more
from the vehicle/s.
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(ii) Coordinate with Municipal Board for beneficial uses of
excess excavated soils or immediately dispose to designated
areas;
(iv) Recover used oil and lubricants and reuse or remove
from the sites;
(v) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(vi) Remove all wreckage, rubbish, or temporary structures
(such as buildings, shelters, and latrines) which are no longer
required;
Complied Overburden and excavated
materials from construction sites
has been reused for backfilling and
excess material has been disposed
to designated areas
Nil DSC/ IPIU
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not
use narrow local roads, except in the immediate vicinity of
delivery sites;
(ii) Schedule transport and hauling activities during non-peak
hours;
(iii) Locate entry and exit points in areas where there is low
potential for traffic congestion;
(iv) Keep the site free from all unnecessary obstructions;
(vi) Coordinate with Municipal Traffic Office for temporary
road diversions and with for provision of traffic aids if
transportation activities cannot be avoided during peak
hours; and
Complied Short period traffic diversions is
being provided as per requirement
Haulage activities are not
significant in and around work
sites.
Sign boards informing nature and
duration of construction works and
contact numbers for
concerns/complaints has been
provided at each construction site.
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 11
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
(vii) Notify affected sensitive receptors by providing sign
boards informing nature and duration of construction works
and contact numbers for concerns/complaints
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment,
hospitals, and schools;
(iv) Consult businesses and institutions regarding operating
hours and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
Complied Planks/metal sheets is being
provided across trenches
whenever required for easy
acccess
Nearby residents and
businesspeople are informed
about the nature of work in
advance by public consultation
Adequate workforce has provided
at critical areas
Nil DSC/ IPIU
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the
maximum extent, local persons within the 2-km immediate
area if manpower is available; and
(ii) Secure construction materials from local market.
Complied At present most of the workforce
is hired locally which is more than
50%.
Nil DSC/ IPIU
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H
and S) Plan which will include measures such as: (a)
excluding public from the site; (b) ensuring all workers are
provided with and use Personal Protective Equipment; (c) H
and S Training for all site personnel; (d) documented
procedures to be followed for all site activities; and (e)
documentation of work-related accidents;
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible
throughout the site;
complied Use of PPE at work site is seen.
Proper toilets with soak pits have
been provided.
Adequate first-aid facility has been
provided at each site
Group insurance has been
provided to workers
Drinking water has been provided
Contractor has been
instructed complete
compliance of measure
specified in EMP and
especially to pay
particular attention to
o ke s safet
Contractor/DSC
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 12
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
(iii) Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not
exposed to hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers
to ensure that they are apprised of the basic site rules of
work at the site, personal protective protection, and
preventing injuring to fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or substances
may be present. Ensure also that visitor/s do not enter
hazard areas unescorted;
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-
up alarms;
(xi) Mark and provide sign boards for hazardous areas such
as energized electrical devices and lines, service rooms
housing high voltage equipment, and areas for storage and
disposal. Signage shall be in accordance with international
standards and be well known to, and easily understood by
workers, visitors, and the general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85
dBA for a duration of more than 8 hours per day without
hearing protection. The use of hearing protection shall be
enforced actively.
at all sites
high visibility vests are provided to
workers
Back-up alarms are not provided in
moving equipment
Workers are not exposed to high
noise for 8 hours
OHS training has been provided to
labor from time to time.
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices,
Not
Applicable
At present most of the workers
employed are local. Contractor has
Nil Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 13
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
sheds, and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of
trees;
(iii) Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting of
trees for firewood;
(v) Train employees in the storage and handling of materials
which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove
from the site;
(vii) Manage solid waste according to the following
preference hierarchy: reuse, recycling and disposal to
designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures
(such as buildings, shelters, and latrines) which are no longer
required; and
(ix) Request IPIU/DSC to report in writing that the camp has
been vacated and restored to pre-project conditions before
acceptance of work.
not constructed any camp
Table 6: Compliance of EMP for Alwar Water Supply sub-project {RUSDIP/TR-01/ALW/WS-03}
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
PRE-CONSTRUCTION STAGE
1 Environmental Clearances
Site preparation work completed by IPIU including necessary
clearance
Consent to Establish under Water (Prevention and Control of
Pollution) Act
Consent to Establish under Air (Prevention and Control of
Complied
No clearances are required from Pollution
Control Board.
Tree cutting is not required
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 14
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
Pollution) Act
Tree-cutting Permit
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain an
expert assessment of the archaeological potential of the site;
(ii) Consider alternatives if the site is found to be of medium
or high risk;
(iii) Include state and local archaeological, cultural and
historical authorities, and interest groups in consultation
forums as project stakeholders so that their expertise can be
made available; and
(iv) Develop a protocol for use by the construction contractors
in conducting any excavation work, to ensure that any chance
finds are recognised and measures are taken to ensure they
are protected and conserved.
Complied
It was confirmed by consultations with
various stakeholders that the site has no
archaeological potential
Instruction has been given to the
contractor to ensure that any chance finds
are recognized and measures are taken to
ensure they are protected and conserved.
No major excavation work required at
present.
No such occurrence till date
Nil Contractor
3 Construction work camps, hot mix plants, stockpile areas,
storage areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant space in
the subproject sites;
(ii) If it is deemed necessary to locate elsewhere, consider
sites that will not promote instability and result in destruction
of property, vegetation, irrigation, and drinking water supply
systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct
disposal to water body or in areas which will inconvenience
the community.
Complied
No work camp & hot mix plant established
for the package.
Proper care has been taken safeguard
property, vegetation, irrigation & drinking
water supply systems.
All the facilities related to construction are
located within project site
Nil Contractor
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining
Department;
(ii) If other sites are necessary, inform construction contractor
Complied
All the material is being taken from
approved mines
Nil Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 15
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
that it is their responsibility to verify the suitability of all
material sources and to obtain the approval of IPIU; and
(iii) If additional quarries will be required after construction is
started, inform construction contractor to obtain a written
approval from IPMU.
CONSTRUCTION STAGE
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain
approval of Investment Program Implementation Unit ( IPIU);
(iii) If additional quarries will be required after construction
has started, obtain written approval from PMU; and;
(iv) Submit to DSC on a monthly basis documentation of
sources of materials.
Complied
All the material is being taken from
government approved quarry sites in
consultation with IPIU/DSC.
Nil Contractor
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for
stockpiling of clay, soils, gravel, and other construction
materials;
(ii) Damp down exposed soil and any stockpiled on site by
spraying with water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material
when transported by trucks; and
(iv) Fit all heavy equipment and machinery with air pollution
control devices which are operating correctly.
Complied
Most of the civil work are complete hence
Air quality monitoring is not conducted.
Nil DSC/ IPIU
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the monsoon
season unless covered by tarpaulins or plastic sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins along
Complied
Excavation works are completed.
Thus surface water quality monitoring is
not required.
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 16
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
the drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from any
drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities in
designated sites; and
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that
activities with the greatest potential to generate noise are
conducted during periods of the day which will result in least
disturbance;
(ii) Require horns not be used unless it is necessary to warn
othe oad use s o a i als of the ehi le s app oa h; (iii) Minimize noise from construction equipment by using
vehicle silencers, fitting jackhammers with noise-reducing
mufflers, and portable street barriers the sound impact to
surrounding sensitive receptor; and
(iv) Maintain maximum sound levels not exceeding 80
decibels (dbA) when measured at a distance of 10 m or more
from the vehicle/s.
Complied
Activities with the greatest potential to
generate noise were planned & have
already been completed in consultation
with IPIU.
Noise monitoring is not required as most
of the civil work has been completed.
Nil DSC/ IPIU
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(ii) Coordinate with Municipal Board for beneficial uses of
excess excavated soils or immediately dispose to designated
areas;
(iv) Recover used oil and lubricants and reuse or remove from
the sites;
(v) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
Complied
Works involving excavation of soil is
complete.
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 17
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not
use narrow local roads, except in the immediate vicinity of
delivery sites;
(ii) Schedule transport and hauling activities during non-peak
hours;
(iii) Coordinate with Municipal Traffic Office for temporary
road diversions and with for provision of traffic aids if
transportation activities cannot be avoided during peak hours;
Complied
Works are carried out without causing any
congestion to the existing traffic condition.
Nil Contractor
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment,
hospitals, and schools;
(iv) Consult businesses and institutions regarding operating
hours and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
Complied
Work almost completed, all ongoing
activities are within confined site premises
and no hindrance for access to any
residence or critical areas.
Sign board has been provided on site.
Nil Contractor
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the maximum
extent, local persons within the 2-km immediate area if
manpower is available; and
(ii) Secure construction materials from local market.
Complied
At present most of the workforce is hired
locally which is more than 50%.
Nil Contractor
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H
and S) Plan which will include measures such as: (a) excluding
public from the site; (b) ensuring all workers are provided with
Partially
complied
Satisfactory use of PPEs observed,
Adequate first-aid box has been provided
No major or minor case of mishap
reported during reporting period
Nil
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 18
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
and use Personal Protective Equipment; (c) H and S Training
for all site personnel; (d) documented procedures to be
followed for all site activities; and (e) documentation of work-
related accidents;
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible
throughout the site;
(iii) Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not exposed
to hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work at
the site, personal protective protection, and preventing
injuring to fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or substances
may be present. Ensure also that visitor/s do not enter hazard
areas unescorted;
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-up
alarms;
(xi) Mark and provide sign boards for hazardous areas such as
energized electrical devices and lines, service rooms housing
high voltage equipment, and areas for storage and disposal.
Signage shall be in accordance with international standards
and be well known to, and easily understood by workers,
Group insurance has been provided to
workers
Proper barricading has been provided to
avoid unauthorized intrusion
Drinking water has been provided at sites
H&S training is being provided to workers
by DSC regularly
Workers are not exposed to high noise for
8 hours.
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 19
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
visitors, and the general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85
dBA for a duration of more than 8 hours per day without
hearing protection. The use of hearing protection shall be
enforced actively.
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices,
sheds, and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of
trees;
(iii) Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting of
trees for firewood;
(v) Train employees in the storage and handling of materials
which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove from
the site;
(vii) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures
(such as buildings, shelters, and latrines) which are no longer
required; and
(ix) Request IPIU/DSC to report in writing that the camp has
been vacated and restored to pre-project conditions before
acceptance of work.
Not Applicable
At present most of the workers employed
are local. Contractor has not constructed
any camp
Nil Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 20
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Table 7: EMP Compliance Status of Jaisalmer Water Supply subproject {RUSDIP/TR-01/JSL/WS-02}
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
Pre-Construction Stage
1 Environmental Clearances
Site preparation work completed by IPIU including
necessary clearance
Complied
Consent to Establish is not required
Tree cutting is not required
Nil DSC/ IPIU
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain an
expert assessment of the archaeological potential of the
site;
(ii) Consider alternatives if the site is found to be of medium
or high risk;
(iii) Include state and local archaeological, cultural and
historical authorities, and interest groups in consultation
forums as project stakeholders so that their expertise can
be made available; and
(iv) Develop a protocol for use by the construction
contractors in conducting any excavation work, to ensure
that any chance finds are recognized and measures are
taken to ensure they are protected and conserved.
Complied
It was confirmed by consultations with
various stakeholders that the site has no
archaeological potential
Instruction has been given to the
contractor to ensure that any chance
finds are recognized and measures are
taken to ensure they are protected and
conserved
No such occurrence till date
Nil DSC/ IPIU
3 Construction work camps, hot mix plants, stockpile areas,
storage areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant space in
the subproject sites;
(ii) If it is deemed necessary to locate elsewhere, consider
sites that will not promote instability and result in
destruction of property, vegetation, irrigation, and drinking
water supply systems;
Complied
All the facilities related to construction
are located within project site
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 21
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct
disposal to water body or in areas which will inconvenience
the community.
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining
Department;
(ii) If other sites are necessary, inform construction
contractor that it is their responsibility to verify the
suitability of all material sources and to obtain the approval
of IPIU; and
(iii) If additional quarries will be required after construction
is started, inform construction contractor to obtain a
written approval from IPMU.
Complied
All the material is being taken from
approved mines
Nil DSC/ IPIU
Construction Stage
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain
approval of Investment Program Implementation Unit (
IPIU);
(iii) If additional quarries will be required after construction
has started, obtain written approval from PMU; and;
(iv) Submit to DSC on a monthly basis documentation of
sources of materials.
Complied
All the material is being taken from
government approved quarry sites
Nil DSC/ IPIU
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for
stockpiling of clay, soils, gravel, and other construction
materials;
(ii) Damp down exposed soil and any stockpiled on site by
Partially
Complied
Air quality monitoring is not required as
most of the civil work has been
completed in the reporting period.
Nil Contractor/IPIU/D
SC
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 22
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
spraying with water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material
when transported by trucks; and
(iv) Fit all heavy equipment and machinery with air
pollution control devices which are operating correctly.
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the
monsoon season unless covered by tarpaulins or plastic
sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins
along the drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from
any drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities
in designated sites; and
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
Complied
Excess excavated soil will be reused for
backfilling
Oil & lubricant has been stored away
from drainage
Nil
Contractor/IPIU/
DSC
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that
activities with the greatest potential to generate noise are
conducted during periods of the day which will result in
least disturbance;
(ii) Require horns not be used unless it is necessary to warn
othe oad use s o a i als of the ehi le s app oa h; (iii) Minimize noise from construction equipment by using
PartiallyCom
plied
Activities with the greatest potential to
generate noise have been completed.
Noise monitoring is not required as most
of the civil work has been completed in
the reporting period
Nil
Contractor/IPIU/
DSC
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 23
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
vehicle silencers, fitting jackhammers with noise-reducing
mufflers, and portable street barriers the sound impact to
surrounding sensitive receptor; and
(iv) Maintain maximum sound levels not exceeding 80
decibels (dbA) when measured at a distance of 10 m or
more from the vehicle/s.
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(ii) Coordinate with Municipal Board for beneficial uses of
excess excavated soils or immediately dispose to
designated areas;
(iv) Recover used oil and lubricants and reuse or remove
from the sites;
(v) Manage solid waste according to the following
preference hierarchy: reuse, recycling and disposal to
designated areas;
(vi) Remove all wreckage, rubbish, or temporary structures
(such as buildings, shelters, and latrines) which are no
longer required; and
(vii) Request IPIU/DSC to report in writing that the
necessary environmental restoration work has been
adequately performed before acceptance of work.
Complied
The unusable extra excavated materials
and over burdens are being disposed at
low laying area
No leakage of oil and lubricant observed
at site from construction machinery
Nil Contractor/IPIU/D
SC
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not
use narrow local roads, except in the immediate vicinity of
delivery sites;
(ii) Schedule transport and hauling activities during non-
peak hours;
Complied
The vehicles carrying materials to the
work site follow only designated route
to the site
sign boards informing nature and
duration of construction works and
Nil Contractor/IPIU/D
SC
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 24
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
(iii) Locate entry and exit points in areas where there is low
potential for traffic congestion;
(iv) Keep the site free from all unnecessary obstructions;
(v) Drive vehicles in a considerate manner;
(vi) Coordinate with Municipal Traffic Office for temporary
road diversions and with for provision of traffic aids if
transportation activities cannot be avoided during peak
hours; and
(vii) Notify affected sensitive receptors by providing sign
boards informing nature and duration of construction
works and contact numbers for concerns/complaints
contact numbers for
concerns/complaints has been provided
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment,
hospitals, and schools;
(iv) Consult businesses and institutions regarding operating
hours and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
Complied
The work schedule has been prepared as
per consultation with local public
Proper access across trenches for people
and vehicles has provided
Significant work force has been provided
Nil IPIU/DSC
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the
maximum extent, local persons within the 2-km immediate
area if manpower is available; and
(ii) Secure construction materials from local market.
Complied
At present most of the workforce is
hired locally
Nil PIU/DSC
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 25
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H
and S) Plan which will include measures such as: (a)
excluding public from the site; (b) ensuring all workers are
provided with and use Personal Protective Equipment; (c) H
and S Training for all site personnel; (d) documented
procedures to be followed for all site activities; and (e)
documentation of work-related accidents;
(ii) Ensure that qualified first-aid can be provided at all
times. Equipped first-aid stations shall be easily accessible
throughout the site;
(iii) Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not
exposed to hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers
to ensure that they are apprised of the basic site rules of
work at the site, personal protective protection, and
preventing injuring to fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or substances
may be present. Ensure also that visitor/s do not enter
hazard areas unescorted;
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-
PartiallyCom
plied
Health and Safety Plan has been
implemented.
PPE are being used on sites.
First-aid facility has been provided at
each site
Group insurance has been provided to
workers
Drinking water has been provided at all
sites
H&S training is being provided to
workers by DSC regularly
high visibility vests are provided to
workers
Back-up alarms are provided in moving
equipment
Sign board are provided at all site
Workers are not exposed to high noise
for 8 hours
Nil Contractor/DSC
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 26
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
up alarms;
(xi) Mark and provide sign boards for hazardous areas such
as energized electrical devices and lines, service rooms
housing high voltage equipment, and areas for storage and
disposal. Signage shall be in accordance with international
standards and be well known to, and easily understood by
workers, visitors, and the general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85
dBA for a duration of more than 8 hours per day without
hearing protection. The use of hearing protection shall be
enforced actively.
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices,
sheds, and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of
trees;
(iii) Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting
of trees for firewood;
(v) Train employees in the storage and handling of materials
which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove
from the site;
(vii) Manage solid waste according to the following
preference hierarchy: reuse, recycling and disposal to
designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures
(such as buildings, shelters, and latrines) which are no
longer required; and
Complied
At present most of the workers
employed are local.
Nil Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 27
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
(ix) Request IPIU/DSC to report in writing that the camp has
been vacated and restored to pre-project conditions before
acceptance of work.
Table 8: EMP Compliance Status of Jaisalmer Waste Water subproject {RUSDIP/TR-01/JSL/WW-01}
Sr.
No.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
1 Environmental Clearances
Site preparation work completed by IPIU including necessary
clearance
Consent to Establish under Water (Prevention and Control
of Pollution) Act
Consent to Establish under Air (Prevention and Control of
Pollution) Act
Tree-cutting Permit
Complied
Consent to Establish has been
obtained from RPCB for STP under
WW/01 package. Consent was valid
upto 30.11.15. work is completed &
Consent to operate has been applied
to RPCB.
Tree cutting is not required
Application of Consent to
Operate has been
submitted to RPCB on
20.04.2017. The same is
under process at RPCB.
DSC/IPIU
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain an
expert assessment of the archaeological potential of the site;
(ii) Consider alternatives if the site is found to be of medium
or high risk;
(iii) Include state and local archaeological, cultural and
historical authorities, and interest groups in consultation
forums as project stakeholders so that their expertise can be
made available; and
(iv) Develop a protocol for use by the construction
contractors in conducting any excavation work, to ensure
Complied It was confirmed by consultations with
various stakeholders that the site has
no archaeological potential
Instruction has been given to the
contractor to ensure that any chance
finds are recognized and measures are
taken to ensure they are protected and
conserved
No such occurrence till date
Nil DSC/IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 28
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
that any chance finds are recognised and measures are taken
to ensure they are protected and conserved.
3 Construction work camps, hot mix plants, stockpile areas,
storage areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant space in
the subproject sites;
(ii) If it is deemed necessary to locate elsewhere, consider
sites that will not promote instability and result in
destruction of property, vegetation, irrigation, and drinking
water supply systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct
disposal to water body or in areas which will inconvenience
the community.
Complied All the facilities related to construction
are located within project site
Nil Contractor /
DSC/IPIU
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining
Department;
(ii) If other sites are necessary, inform construction
contractor that it is their responsibility to verify the
suitability of all material sources and to obtain the approval
of IPIU; and
(iii) If additional quarries will be required after construction is
started, inform construction contractor to obtain a written
approval from IPMU.
Complied All the material is being taken from
approved mines
Nil DSC/IPIU
Construction Stage
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain
approval of Investment Program Implementation Unit ( IPIU);
Complied All the material is being taken from
government approved quarry sites
Nil DSC/IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 29
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
(iii) If additional quarries will be required after construction
has started, obtain written approval from PMU; and;
(iv) Submit to DSC on a monthly basis documentation of
sources of materials.
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for
stockpiling of clay, soils, gravel, and other construction
materials;
(ii) Damp down exposed soil and any stockpiled on site by
spraying with water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material
when transported by trucks; and
(iv) Fit all heavy equipment and machinery with air pollution
control devices which are operating correctly.
Partially
Complied
Air quality monitoring is not required
as most of the civil work has been
completed in the reporting period.
Nil Contractor/IPIU
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the
monsoon season unless covered by tarpaulins or plastic
sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins along
the drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from
any drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities in
designated sites; and
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
Complied Surface water quality is not required
during reporting period as there is no
surface water near sites.
No surface water was
available near the project
site
Contractor /IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 30
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that
activities with the greatest potential to generate noise are
conducted during periods of the day which will result in least
disturbance;
(ii) Require horns not be used unless it is necessary to warn
othe oad use s o a i als of the ehi le s app oa h; (iii) Minimize noise from construction equipment by using
vehicle silencers, fitting jackhammers with noise-reducing
mufflers, and portable street barriers the sound impact to
surrounding sensitive receptor; and
(iv) Maintain maximum sound levels not exceeding 80
decibels (dbA) when measured at a distance of 10 m or more
from the vehicle/s.
Partially
Complied
Activities with the greatest potential to
generate noise have been completed.
Noise monitoring is not required as
most of the civil work has been
completed.
Nil Contractor/IPIU
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(ii) Coordinate with Municipal Board for beneficial uses of
excess excavated soils or immediately dispose to designated
areas;
(iv) Recover used oil and lubricants and reuse or remove
from the sites;
(v) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(vi) Remove all wreckage, rubbish, or temporary structures
(such as buildings, shelters, and latrines) which are no longer
required; and
(vii) Request IPIU/DSC to report in writing that the necessary
Complied The unusable extra excavated
materials and over burdens are being
disposed at low laying area as per
direction of ULB of Jaisalmer town
Oil and lubricants leakage not observed
from any construction machinery
Nil Contractor/ DSC/
IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 31
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
environmental restoration work has been adequately
performed before acceptance of work.
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not
use narrow local roads, except in the immediate vicinity of
delivery sites;
(ii) Schedule transport and hauling activities during non-peak
hours;
(iii) Locate entry and exit points in areas where there is low
potential for traffic congestion;
(iv) Keep the site free from all unnecessary obstructions;
(v) Coordinate with Municipal Traffic Office for temporary
road diversions and with for provision of traffic aids if
transportation activities cannot be avoided during peak
hours; and
(vi) Notify affected sensitive receptors by providing sign
boards informing nature and duration of construction works
and contact numbers for concerns/complaints
Complied The trucks carrying materials to the
work site follow only designated route
to the site
sign boards informing nature and
duration of construction works and
contact numbers for
concerns/complaints has been
provided
Nil DSC / IPIU
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment,
hospitals, and schools;
(iv) Consult businesses and institutions regarding operating
hours and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
Complied Proper access across trenches for
people and vehicles has been provided
Nil DSC / IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 32
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
concerns/complaints.
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the
maximum extent, local persons within the 2-km immediate
area if manpower is available; and
(ii) Secure construction materials from local market.
Complied At present most of the workforce is
hired locally
DSC / IPIU
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H
and S) Plan which will include measures such as: (a)
excluding public from the site; (b) ensuring all workers are
provided with and use Personal Protective Equipment; (c) H
and S Training for all site personnel; (d) documented
procedures to be followed for all site activities; and (e)
documentation of work-related accidents;
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible
throughout the site;
(iii) Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not
exposed to hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers
to ensure that they are apprised of the basic site rules of
work at the site, personal protective protection, and
preventing injuring to fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or substances
Partially
Complied
Health and Safety Plan is under
implementation.
PPE are being used partially.
First-aid facility has been provided at
each site
Drinking water has been provided at all
sites
H&S training is being provided to
workers by DSC regularly
high visibility vests are provided to
workers
Sign board are provided at all site
Workers are not exposed to high noise
for 8 hours
Wo ke s i su a e has ee p o ided
Contractor has been
instructed complete
compliance of measure
specified in EMP
Safety officer is has been
nominated by contractor
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 33
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
may be present. Ensure also that visitor/s do not enter
hazard areas unescorted;
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-
up alarms;
(xi) Mark and provide sign boards for hazardous areas such
as energized electrical devices and lines, service rooms
housing high voltage equipment, and areas for storage and
disposal. Signage shall be in accordance with international
standards and be well known to, and easily understood by
workers, visitors, and the general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85
dBA for a duration of more than 8 hours per day without
hearing protection. The use of hearing protection shall be
enforced actively.
by the contactor
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices,
sheds, and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of
trees;
(iii) Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting of
trees for firewood;
(v) Train employees in the storage and handling of materials
which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove
from the site;
Partially
Complied
Work camp has been established in
consultation with IPIU/DSC
Labour camp has been established
near STP site (Package WW/01)
Poor water and sanitation facilities
need more improvement, contractor
has provided cooking gas/stove in
labour camp
Contractor has instructed
to provide proper water,
sanitation facilities
cooking gas in the camp
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 34
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
(vii) Manage solid waste according to the following
preference hierarchy: reuse, recycling and disposal to
designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures
(such as buildings, shelters, and latrines) which are no longer
required; and
(ix) Request IPIU/DSC to report in writing that the camp has
been vacated and restored to pre-project conditions before
acceptance of work.
EMR for Tranche-02 Sub Projects
Table 9: Compliance of EMP for Alwar WasteWater sub-project {RUSDIP/TR-02/ALW/WW-06}
Sr.
No. Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
Pre- Construction Stage
1 Environmental Clearances
Site preparation works completed by IPIU including necessary
clearances
Consent to Establish under Water (Prevention and Control of
Pollution) Act
Consent to Establish under Air (Prevention and Control of
Pollution) Act
Tree-cutting Permit
Complied
Consent to Establish is not required as
the scope of work includes only laying
of pipes under this package.
Tree cutting is also not required.
Nil DSC / IPIU
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain
an expert assessment of the archaeological potential of the
Complied It was confirmed by consultations with
various stakeholders that the site has no
archaeological potential.
Nil DSC / IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 35
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No. Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
site;
(ii) Consider alternatives if the site is found to be of
medium or high risk;
(iii) Include state and local archaeological, cultural and
historical authorities, and interest groups in consultation
forums as project stakeholders so that their expertise can be
made available; and
(iv) Develop a protocol for use by the construction
contractors in conducting any excavation work, to ensure
that any chance finds are recognized and measures are taken
to ensure they are protected and conserved.
Instruction has been given to the
contractor to ensure that if any chance
finds are recognized, measures are
taken to make sure they are protected
and conserved.
No such occurrence found till date.
3 Construction work camps, hot mix plants, stockpile areas,
storage areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant space in the
sub-project sites;
(ii) If it is deemed necessary to locate elsewhere, consider sites
that will not promote instability and result in destruction of
property, vegetation, irrigation, and drinking water supply
systems;
(iii) Do not consider residential areas; and
(iv) Take extreme care in selecting sites to avoid direct disposal
to water body or in areas, which will inconvenience the
community.
Complied All the facilities related to construction
are located within project site.
No hot mix plant established for the
package.
Proper care has been taken to
safeguard property, vegetation,
irrigation & drinking water supply
systems.
Nil Contractor/ DSC /
IPIU
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining Department;
(ii) If other sites are necessary, inform construction contractor
that it is their responsibility to verify the suitability of all
material sources and to obtain the approval of IPIU; and
(iii) If additional quarries will be required after construction is
started, inform construction contractor to obtain a written
approval from IPMU.
Complied All the material is being taken from
approved mines in consultation with
IPIU.
Nil DSC / IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 36
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No. Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
Construction Stage
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain approval
of Investment Program Implementation Unit ( IPIU);
(iii) If additional quarries will be required after construction has
started, obtain written approval from PMU; and
(iv) Submit documentation of sources of materials to DSC on a
monthly basis.
Complied All the material is being taken from
government approved quarry sites in
consultation with IPIU/DSC.
Nil DSC / IPIU
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for stockpiling
of clay, soils, gravel, and other construction materials;
(ii) Damp down exposed soil and any stockpiled on site by
spraying of water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material when
transported by trucks; and
(iv) Fit all heavy equipments and machineries with air pollution
control devices which are operating correctly.
Partially
Complied
Air quality monitoring has not been
carried out during reporting period.
Construction materials have been
stockpiled at designated areas in
consultation with IPIU.
Water sprinkling is being done as and
when it required.
The fine material carrying vehicles are
kept covered.
Air quality monitoring is
required.
Contractor /DSC /
IPIU
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the monsoon
season unless covered by tarpaulins or plastic sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins along the
drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from any
drainage leading to water bodies;
Partially
Complied
Ground water monitoring has not been
carried out in reporting period.
Excavated soil is being reused for
backfilling and excess material is being
disposed in low lying areas.
Surface water quality inspection is not
required as there is no surface water
body near sub-project site.
Ground water monitoring is
required to be conducted
Contractor /DSC /
IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 37
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No. Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
(v) Dispose any wastes generated by construction activities in
designated sites; and
(vi) Conduct surface water quality inspection according to the
Environmental Management Plan (EMP).
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that activities
with the greatest potential to generate noise are conducted
during periods of the day which will result in least
disturbance;
(ii) Require horns not be used unless it is necessary to warn
othe oad use s o a i als of the ehi le s app oa h; (iii) Minimize noise from construction equipments by using
vehicle silencers, fitting jackhammers with noise-reducing
mufflers, and portable street barriers the sound impact to
surrounding sensitive receptor; and
(iv) Maintain maximum sound levels not exceeding 80 decibels
(dbA) when measured at a distance of 10 m or more from
the vehicle/s.
Partially
Complied
Noise level monitoring has not been
carried out in the monitoring period.
Activities with the greatest potential to
generate noise have been planned in
consultation with IPIU and are being
conducted in day time.
Construction equipments are properly
maintained by contractor to minimize
the noise.
Noise level monitoring has not been
conducted in the reporting period.
Although the Monitoring Plan for the
sub-projects has already been provided
by DSC to IPIU.
Noise monitoring is
required to be conducted.
Contractor /DSC /
IPIU
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(iii) Coordinate with Municipal Board for beneficial uses of
excess excavated soils or immediately dispose to designated
areas;
(iv) Recover used oil and lubricants and reuse or remove from
the sites;
(v) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
and
Complied Overburden and excavated materials
from construction sites are being reused
for backfilling and excess material is
disposed to designated areas.
Nil DSC / IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 38
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No. Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
(vi) Remove all wreckage, rubbish, or temporary structures (such
as buildings, shelters, and latrines) which are no longer
required.
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not use
narrow local roads, except in the immediate vicinity of
delivery sites;
(ii) Schedule transport and hauling activities during non-peak
hours;
(iii) Locate entry and exit points in areas where there is low
potential for traffic congestion;
(iv) Keep the site free from all unnecessary obstructions;
(v) Coordinate with Municipal Traffic Office for temporary road
diversions and with for provision of traffic aids, if
transportation activities cannot be avoided during peak
hours; and
(vi) Notify affected sensitive receptors by providing sign boards
informing nature and duration of construction works and
contact numbers for concerns/complaints.
Complied Short period traffic diversions are being
provided as per requirement.
Haulage activities are not significant
across the construction site.
Sign boards informing nature and
duration of construction works, and
contact numbers for
concerns/complaints has been provided
at each construction site.
Nil DSC / IPIU
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets wherever required to
maintain access across trenches for people and vehicles;
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment,
hospitals, and schools;
(iv) Consult businesses and institutions regarding operating
hours and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
Complied Planks/metal sheets is provided across
trenches, whenever required for easy
excess.
Nearby residents and business people
are informed about the nature of work
in advance through public consultation.
Adequate workforce has been provided
at critical areas.
Nil DSC / IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 39
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No. Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the maximum
extent, local persons within the 2 km immediate area, if
manpower is available; and
(ii) Secure construction materials from local market.
Complied At present most of the workforce is
hired locally which is more than 50%.
Nil DSC / IPIU
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H
and S) Plan which will include measures such as: (a) excluding
public from the site; (b) ensuring all workers are provided
with and use Personal Protective Equipments; (c) H and S
Training for all site personnel; (d) documented procedures
to be followed for all site activities; and (e) documentation of
work-related accidents;
(ii) Ensure that qualified first-aid is provided at all times.
Equipped first-aid stations shall be easily accessible
throughout the site;
(iii) Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not exposed to
hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work
at the site, personal protective protection, and preventing
injuring to fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or substances
may be present. Ensure also that visitor/s do not enter
hazard areas unescorted;
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
Complied Proper use of PPEs by workers at site
was observed.
DSC is interacting frequently with
labours and site supervisor to aware
them about the necessity of use of PPEs
and to motivate labours for complete
use of PPEs at work site.
Adequate first-aid facility has been
provided at each site.
Group insurance has been provided to
workers.
Drinking water has been provided at all
sites.
High visibility vests are provided to
workers.
Back-up alarms are not provided in
moving equipment.
Workers are not exposed to high noise
for 8 hours.
Nil
Contractor/
DSC
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 40
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No. Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-up
alarms;
(xi) Mark and provide sign boards for hazardous areas such as
energized electrical devices and lines, service rooms housing
high voltage equipment, and areas for storage and disposal.
Signage shall be in accordance with international standards
and be well known to, and easily understood by workers,
visitors, and the general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85 dBA
for duration of more than 8 hours per day without hearing
protection. The use of hearing protection shall be enforced
actively.
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices, sheds,
and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of trees;
(iii) Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting of
trees for firewood;
(v) Train employees in the storage and handling of materials
which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove from
the site;
(vii) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures (such
as buildings, shelters, and latrines) which are no longer
required; and
(ix) Request IPIU/DSC to report in writing that the camp has
been vacated and restored to pre-project conditions before
acceptance of work.
Not
Applicable
At present most of the workers
employed are local.
Contractor has not constructed any
camp.
Nil Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 41
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Table 10:Compliance of EMP for Bhratpur ROB sub-project {RUSDIP/TR-02/BPR/BR/02}
Sr.
No.
Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
PRECONSTRUCTION STAGE
1 Environmental Clearances
Site preparation work completed by IPIU including necessary
clearance
Consent to Establish under Water (Prevention and Control of
Pollution) Act
Consent to Establish under Air (Prevention and Control of
Pollution) Act
Tree-cutting Permit
Complied
No clearances are required from
Pollution Control Board.
Tree cutting is not required.
Nil DSC / IPIU
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain an
expert assessment of the archaeological potential of the site;
(ii) Consider alternatives if the site is found to be of medium or
high risk;
(iii) Include state and local archaeological, cultural and
historical authorities, and interest groups in consultation
forums as project stakeholders so that their expertise can be
made available; and
(iv) Develop a protocol for use by the construction contractors
in conducting any excavation work, to ensure that any chance
finds are recognised and measures are taken to ensure they are
protected and conserved.
Complied
It was confirmed by consultations with
various stakeholders that the site has no
archaeological potential
Instruction has been given to the
contractor to ensure that any chance
finds are recognized and measures are
taken to ensure they are protected and
conserved
No such occurrence till date
Nil DSC / IPIU
3 Construction work camps, hot mix plants, stockpile areas,
storage areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant space in the
subproject sites;
Complied
All the facilities related to construction
are located within project site.
There are neither any work camps nor
Nil DSC / IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 42
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
(ii) If it is deemed necessary to locate elsewhere, consider sites
that will not promote instability and result in destruction of
property, vegetation, irrigation, and drinking water supply
systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct disposal
to water body or in areas which will inconvenience the
community.
hot mix plants established for project
works.
Construction materials are temporarily
stored at sites with due consideration of
safeguard norms taking into account
vegetation, irrigation, and drinking water
supply systems.
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining Department;
(ii) If other sites are necessary, inform construction contractor
that it is their responsibility to verify the suitability of all
material sources and to obtain the approval of IPIU; and
(iii) If additional quarries will be required after construction is
started, inform construction contractor to obtain a written
approval from IPMU.
Complied
All the material is being taken from
approved mines
Nil DSC / IPIU
CONSTRUCTION STAGE
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain approval
of Investment Program Implementation Unit ( IPIU);
(iii) If additional quarries will be required after construction has
started, obtain written approval from PMU; and;
(iv) Submit to DSC on a monthly basis documentation of
sources of materials.
Complied
All the material is being taken from
government approved quarry sites
Nil DSC / IPIU
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for
stockpiling of clay, soils, gravel, and other construction
materials;
(ii) Damp down exposed soil and any stockpiled on site by
Partially
Complied
Ambient air quality monitoring has not
been carried out in the reporting period.
Water sprinkling is being done as and
Air quality monitoring is
required to be conducted, work
order for the same has been
issued.
Contractor/ DSC /
IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 43
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
spraying with water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material when
transported by trucks; and
(iv) Fit all heavy equipment and machinery with air pollution
control devices which are operating correctly.
when it is required.
The fine material carrying vehicles are
kept covered.
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the monsoon
season unless covered by tarpaulins or plastic sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins along
the drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from any
drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities in
designated sites; and
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
Partially
Complied
Water quality monitoring has not been
carried out in the reporting period.
Presently the excavation is started and
materials are dumped safely near the site
premises and will be utilized beneficially
for backfilling.
Surface water quality monitoring is not
required as there is no water body within
the site influence area.
Water quality monitoring is
required to be conducted, work
order for the same has been
issued.
Contractor/ DSC /
IPIU
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that activities
with the greatest potential to generate noise are conducted
during periods of the day which will result in least disturbance;
(ii) Require horns not be used unless it is necessary to warn
othe oad use s o a i als of the ehi le s app oa h; (iii) Minimize noise from construction equipment by using
vehicle silencers, fitting jackhammers with noise-reducing
mufflers, and portable street barriers the sound impact to
surrounding sensitive receptor; and
Partially
complied
Noise level monitoring has not been
conducted in the reporting period.
Activities with the greatest potential to
generate noise have been planned in
consultation with IPIU and are being
conducted in day time.
Construction equipment are properly
maintained by contractor to minimize the
Noise quality monitoring is
required to be conducted, work
order for the same has been
issued.
Contractor/ DSC /
IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 44
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
(iv) Maintain maximum sound levels not exceeding 80 decibels
(dbA) when measured at a distance of 10 m or more from the
vehicle/s.
noise.
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(ii) Coordinate with Municipal Board for beneficial uses of
excess excavated soils or immediately dispose to designated
areas;
(iv) Recover used oil and lubricants and reuse or remove from
the sites;
(v) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
Complied
Excavated materials are dumped safely
near the site premises and will be utilized
beneficially for backfilling.
Nil DSC / IPIU
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not use
narrow local roads, except in the immediate vicinity of delivery
sites;
(ii) Schedule transport and hauling activities during non-peak
hours;
(iii) Coordinate with Municipal Traffic Office for temporary road
diversions and with for provision of traffic aids if transportation
activities cannot be avoided during peak hours;
Complied
Works are being carried out without
causing any congestion to the existing
traffic condition.
Transportation is being carried out during
non peak hours
Nil DSC / IPIU
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment,
hospitals, and schools;
Complied
All activities are within confined site
premises and no hindrance for access to
any residence or critical areas.
Nil DSC / IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 45
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
(iv) Consult businesses and institutions regarding operating
hours and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the maximum
extent, local persons within the 2-km immediate area if
manpower is available; and
(ii) Secure construction materials from local market.
Complied
At present most of the workforce is hired
locally
Nil DSC / IPIU
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H
and S) Plan which will include measures such as: (a) excluding
public from the site; (b) ensuring all workers are provided with
and use Personal Protective Equipment; (c) H and S Training for
all site personnel; (d) documented procedures to be followed
for all site activities; and (e) documentation of work-related
accidents;
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible throughout
the site;
(iii) Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not exposed
to hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work at
the site, personal protective protection, and preventing injuring
Partially
complied
Use of PPE was observed at work site.
Qualified First-aid box has been provided
at site.
Group insurance hasbeen provided to
workers
Proper barricading has been provided to
avoid unauthorized intrusion.
Drinking water has been provided at sites
Training for health and safety measures
have been given to contractor by DSC.
Awareness is done by the ACO, CAPP. The
contractor has nominated
representative for H & S (safety of
workers/public)
All activities are within
confined site premises and no
hindrance for access to any
residence or critical areas.
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 46
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
to fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or substances may
be present. Ensure also that visitor/s do not enter hazard areas
unescorted;
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-up
alarms;
(xi) Mark and provide sign boards for hazardous areas such as
energized electrical devices and lines, service rooms housing
high voltage equipment, and areas for storage and disposal.
Signage shall be in accordance with international standards and
be well known to, and easily understood by workers, visitors,
and the general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85
dBA for a duration of more than 8 hours per day without
hearing protection. The use of hearing protection shall be
enforced actively.
Workers are not exposed to high noise
level more than 8 hrs.
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices, sheds,
and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of
trees;
(iii) Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting of
trees for firewood;
(v) Train employees in the storage and handling of materials
which can potentially cause soil contamination;
Partially
Complied
Contractor has established a small
workers camp near RMC plant.
New toilets and bathroom have been
constructed.
Basic facilities in the camp at RMC plant
is better now but needs further
improvement.
Contractor has been instructed
for complete compliance of
EMP immediately.
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 47
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
(vi) Recover used oil and lubricants and reuse or remove from
the site;
(vii) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures
(such as buildings, shelters, and latrines) which are no longer
required;
New Toilets and bathroom have been
constructed.
Improved sanitation at camp was
observed. Soak pit has been constructed.
Adequate number of Cots for labours is
not provided yet.
Kerosene stove for cooking is provided by
contractor.
Table 11: Compliance of EMP for Dholpur Water Supply sub-project {RUSDIP/TR-02/DLP/WS/03}
Sr. No. Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibilit
y
PRECONSTRUCTION STAGE
1 Environmental Clearances
Site preparation work completed by IPIU including necessary
clearance
Consent to Establish under Water (Prevention and Control of
Pollution) Act
Consent to Establish under Air (Prevention and Control of
Pollution) Act
Tree-cutting Permit
Complied
Consent to Establish obtained from
Pollution Control Board for WTP. Consent
valid up to 31.05.2015. Work has been
completed. Plant will be operational after
receiving CTO.
CTO has been obtained via order no.
2015-2016/Bharatpur/2584 dated
16/02/2016 valid till 31/08/2020.
Tree cutting is not required
Nil DSC and IPIU
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain an expert Complied
It was confirmed by consultations with
various stakeholders that the site has no
Nil DSC / IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 48
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibilit
y
assessment of the archaeological potential of the site;
(ii) Consider alternatives if the site is found to be of medium or
high risk;
(iii) Include state and local archaeological, cultural and historical
authorities, and interest groups in consultation forums as project
stakeholders so that their expertise can be made available; and
(iv) Develop a protocol for use by the construction contractors in
conducting any excavation work, to ensure that any chance finds
are recognised and measures are taken to ensure they are
protected and conserved.
archaeological potential
Instruction has been given to the
contractor to ensure that any chance
finds are recognized and measures are
taken to ensure they are protected and
conserved
No such occurrence till date
3 Construction work camps, hot mix plants, stockpile areas,
storage areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant space in the
subproject sites;
(ii) If it is deemed necessary to locate elsewhere, consider sites
that will not promote instability and result in destruction of
property, vegetation, irrigation, and drinking water supply
systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct disposal to
water body or in areas which will inconvenience the community.
Complied
All the facilities related to construction
are located within project site
No work camp & hot mix plant
established for the package.
Proper care has been taken safeguard
property, vegetation, irrigation &
drinking water supply systems.
Nil DSC / IPIU
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining Department;
(ii) If other sites are necessary, inform construction contractor
that it is their responsibility to verify the suitability of all material
sources and to obtain the approval of IPIU; and
(iii) If additional quarries will be required after construction is
started, inform construction contractor to obtain a written
approval from IPMU.
Complied
All the material is being taken from
approved mines
Nil DSC / IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 49
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibilit
y
CONSTRUCTION STAGE
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain approval of
Investment Program Implementation Unit ( IPIU);
(iii) If additional quarries will be required after construction has
started, obtain written approval from PMU; and;
(iv) Submit to DSC on a monthly basis documentation of sources
of materials.
Complied
All the material is being taken from
government approved quarry sites
Nil DSC / IPIU
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for stockpiling
of clay, soils, gravel, and other construction materials;
(ii) Damp down exposed soil and any stockpiled on site by
spraying with water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material when
transported by trucks; and
(iv) Fit all heavy equipment and machinery with air pollution
control devices which are operating correctly.
Complied
Air Quality Monitoring is not required as
Civil work was completed in the last
reporting period and only water metert
installations and house connections are
ongoing.
Excavation works are complete and
excess spoils have been utilized for
backfilling.
Nil Construction/
DSC / IPIU
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the monsoon
season unless covered by tarpaulins or plastic sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins along the
drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from any
drainage leading to water bodies;
Complied
Ground Water quality monitoring is not
required as civil work was completed in
the last reporting period and only water
meter and house connections are
ongoing.
Overburden and excavated materials
from construction sites are being utilized
in backfilling of trenches and remaining
material is used for leveling of nearby
low lying area
Nil Construction/
DSC / IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 50
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibilit
y
(v) Dispose any wastes generated by construction activities in
designated sites; and
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
Surface water sampling is not required.
There is no water body nearby the sub-
project site
Oil & Lubricant has been stored away
from the drainage
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that activities
with the greatest potential to generate noise are conducted
during periods of the day which will result in least disturbance;
(ii) Require horns not be used unless it is necessary to warn other
road users or animals of the vehi le s app oa h; (iii) Minimize noise from construction equipment by using vehicle
silencers, fitting jackhammers with noise-reducing mufflers, and
portable street barriers the sound impact to surrounding sensitive
receptor; and
(iv) Maintain maximum sound levels not exceeding 80 decibels
(dbA) when measured at a distance of 10 m or more from the
vehicle/s.
Complied
Noise level quality monitoring is not
required as major work was completed in
the last reporting period and only water
and house connections are ongoing.
Excavation works are complete and
excess spoils have been utilized for
backfilling.
Nil Construction/
DSC / IPIU
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(ii) Coordinate with Municipal Board for beneficial uses of excess
excavated soils or immediately dispose to designated areas;
(iv) Recover used oil and lubricants and reuse or remove from the
sites;
(v) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
Complied
Overburden and excavated materials
from construction sites are being utilized
in backfilling of trenches and remaining
material is used for leveling of nearby
low lying area
Leakage of oil and lubricant has not been
observed on site
Nil DSC / IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 51
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibilit
y
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not use
narrow local roads, except in the immediate vicinity of delivery
sites;
(ii) Schedule transport and hauling activities during non-peak
hours;
(iii) Coordinate with Municipal Traffic Office for temporary road
diversions and with for provision of traffic aids if transportation
activities cannot be avoided during peak hours;
Complied
Easy access road is available for
transportation of construction materials.
Any inconvenience due to this is very
unlikely.
Nil DSC / IPIU
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment, hospitals,
and schools;
(iv) Consult businesses and institutions regarding operating hours
and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
Complied
Proper access is being provided as and
when required
Sign board has been provided at site
Nil DSC / IPIU
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the maximum
extent, local persons within the 2-km immediate area if
manpower is available; and
(ii) Secure construction materials from local market.
Complied
At present most of the workforce is hired
locally
Nil DSC / IPIU
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H and
S) Plan which will include measures such as: (a) excluding public
from the site; (b) ensuring all workers are provided with and use
Complied
PPE are being used.
Qualified First-aid box is available at site.
Group insurance has been provided to
Nil Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 52
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibilit
y
Personal Protective Equipment; (c) H and S Training for all site
personnel; (d) documented procedures to be followed for all site
activities; and (e) documentation of work-related accidents;
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible throughout
the site;
(iii) Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not exposed to
hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work at the
site, personal protective protection, and preventing injuring to
fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or substances may be
present. Ensure also that visitor/s do not enter hazard areas
unescorted;
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-up
alarms;
(xi) Mark and provide sign boards for hazardous areas such as
energized electrical devices and lines, service rooms housing high
voltage equipment, and areas for storage and disposal. Signage
shall be in accordance with international standards and be well
known to, and easily understood by workers, visitors, and the
workers
Proper arrangement has been provided
to avoid unauthorized intrusion.
Drinking water has been provided at sites
Training for health and safety measures
have been given to contractor by DSC.
More H&S training is required for
contractor staff
Workers are not exposed to high noise
level more than 8 hrs
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 53
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibilit
y
general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85 dBA
for a duration of more than 8 hours per day without hearing
protection. The use of hearing protection shall be enforced
actively.
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices, sheds,
and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of trees;
(iii) Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting of trees
for firewood;
(v) Train employees in the storage and handling of materials
which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove from the
site;
(vii) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures (such
as buildings, shelters, and latrines) which are no longer required;
Not Applicable
There is no camp for workers at present.
Most of the workers are local.
Nil Contractor
Table 12: Compliance of EMP for Dholpur Waste Water sub-project {RUSDIP/TR-02/DLP/WW/04, WW/08& WW/11}
Sr. No. Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
PRECONSTRUCTION STAGE
1 Environmental Clearances
Site preparation work completed by IPIU including necessary
clearance
Consent to Establish under Water (Prevention and Control of
Complied
For WW-04 & WW-08 no consent to
eatablish is required as it is only pipe
laying work.
Nil DSC & IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 54
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
Pollution) Act
Consent to Establish under Air (Prevention and Control of
Pollution) Act
Tree-cutting Permit
Consent to Establish for 3 MLD STP under
package WW/11 has been obtained and is
valid upto Valid till 30/09/2017
Permission has been obtained for cutting
of 3 trees under WW/04 package from
local administration.
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain an expert
assessment of the archaeological potential of the site;
(ii) Consider alternatives if the site is found to be of medium or
high risk;
(iii) Include state and local archaeological, cultural and historical
authorities, and interest groups in consultation forums as project
stakeholders so that their expertise can be made available; and
(iv) Develop a protocol for use by the construction contractors in
conducting any excavation work, to ensure that any chance finds
are recognised and measures are taken to ensure they are
protected and conserved.
Complied
It was confirmed by consultations with
various stakeholders that the site has no
archaeological potential
Instruction has been given to the
contractor to ensure that any chance
finds are recognized and measures are
taken to ensure they are protected and
conserved
No such occurrence till date
Nil DSC & IPIU
3 Construction work camps, hot mix plants, stockpile areas,
storage areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant space in the
subproject sites;
(ii) If it is deemed necessary to locate elsewhere, consider sites
that will not promote instability and result in destruction of
property, vegetation, irrigation, and drinking water supply
systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct disposal to
Complied
All the facilities related to construction
are located within project site
No hot mix plant established for the
package.
Proper care has been taken to safeguard
property, vegetation, irrigation & drinking
water supply systems.
Nil DSC & IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 55
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
water body or in areas which will inconvenience the community.
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining Department;
(ii) If other sites are necessary, inform construction contractor
that it is their responsibility to verify the suitability of all material
sources and to obtain the approval of IPIU; and
(iii) If additional quarries will be required after construction is
started, inform construction contractor to obtain a written
approval from IPMU.
Complied
All the material is being taken from
approved mines in consultation with IPIU
.Nil DSC & IPIU
CONSTRUCTION STAGE
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain approval of
Investment Program Implementation Unit ( IPIU);
(iii) If additional quarries will be required after construction has
started, obtain written approval from PMU; and;
(iv) Submit to DSC on a monthly basis documentation of sources
of materials.
Complied
All the material is being taken from
government approved quarry sites in
consultation with IPIU/DSC.
Nil DSC & IPIU
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for stockpiling
of clay, soils, gravel, and other construction materials;
(ii) Damp down exposed soil and any stockpiled on site by
spraying with water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material when
transported by trucks; and
(iv) Fit all heavy equipment and machinery with air pollution
control devices which are operating correctly.
Partially
Complied
Civil works have been completed
therefore monitoring is not required.
Fine material carrying vehicles are
properly covered to avoid dust problem.
Nil Contractor/ DSC
& IPIU
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the monsoon
season unless covered by tarpaulins or plastic sheets;
Partially
Complied
Civil works have been completed
therefore monitoring is not required.
Nil Contractor/ DSC
& IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 56
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins along the
drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from any
drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities in
designated sites; and
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
Tarpaulin is used to cover overburden
excavated materials which in turn is being
utilized further for refilling activities
and/or disposed off to designated
disposal location.
Surface water sampling is not required.
There is no surface water body nearby the
sub-projects sites.
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that activities
with the greatest potential to generate noise are conducted
during periods of the day which will result in least disturbance;
(ii) Require horns not be used unless it is necessary to warn other
oad use s o a i als of the ehi le s app oa h; (iii) Minimize noise from construction equipment by using vehicle
silencers, fitting jackhammers with noise-reducing mufflers, and
portable street barriers the sound impact to surrounding sensitive
receptor; and
(iv) Maintain maximum sound levels not exceeding 80 decibels
(dbA) when measured at a distance of 10 m or more from the
vehicle/s.
Partially
Complied
Civil works have been completed
therefore monitoring is not required.
Activities with the greatest potential to
generate noise have been planned in
consultation with IPIU and are being
conducted in day time.
Construction equipment are properly
maintained by contractor to minimize the
noise.
Generator sets and concrete mixtures are
provided with acoustic enclosures.
Nil Contractor/ DSC
& IPIU
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
Partially
Complied
Overburden and excavated materials
from construction sites are being
stockpiled for utilization in backfilling of
Instruction has been given to
contractor to disposed excess
excavated soil to designated
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 57
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
(ii) Coordinate with Municipal Board for beneficial uses of excess
excavated soils or immediately dispose to designated areas;
(iv) Recover used oil and lubricants and reuse or remove from the
sites;
(v) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
trenches
Prompt disposal of surplus excavated
material (if any after backfilling) to
designated area is required
No leakage of oil & lubricant has been
observed on site
Waste management plan is required
disposal areas in consultation
with IPIU/DSC.
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not use
narrow local roads, except in the immediate vicinity of delivery
sites;
(ii) Schedule transport and hauling activities during non-peak
hours;
(iii) Coordinate with Municipal Traffic Office for temporary road
diversions and with for provision of traffic aids if transportation
activities cannot be avoided during peak hours;
Complied
Easy access road is available for
transportation of construction materials.
Nil Contractor/ DSC
& IPIU
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment, hospitals,
and schools;
(iv) Consult businesses and institutions regarding operating hours
and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
Complied
Proper access is being provided as and
when required
Sign board has been installed at site
Nil DSC / IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 58
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the maximum
extent, local persons within the 2-km immediate area if
manpower is available; and
(ii) Secure construction materials from local market.
Complied
At present most of the workforce is hired
locally
Nil DSC / IPIU
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H and
S) Plan which will include measures such as: (a) excluding public
from the site; (b) ensuring all workers are provided with and use
Personal Protective Equipment; (c) H and S Training for all site
personnel; (d) documented procedures to be followed for all site
activities; and (e) documentation of work-related accidents;
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible throughout
the site;
(iii) Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not exposed to
hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work at the
site, personal protective protection, and preventing injuring to
fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or substances may be
present. Ensure also that visitor/s do not enter hazard areas
unescorted;
(ix) Ensure the visibility of workers through their use of high
Partially
complied
Reasonable use of PPE observed.
Barricading is not appropriate at some of
the sewer pipe laying sites.
Qualified first-aid box has been provided.
Wo ke s G oup i su a e has ot ee updated.
Drinking water has been provided at sites
Training for health and safety measures
have been given to contractor by DSC.
More H&S training is required for
contractor staff
Workers are not exposed to high noise
level more than 8 hrs
Ensure complete use of PPE &
proper barricading at sites.
Wo ke s G oup i su a e needs to be updated urgently.
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 59
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
visibility vests when working in or walking through heavy
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-up
alarms;
(xi) Mark and provide sign boards for hazardous areas such as
energized electrical devices and lines, service rooms housing high
voltage equipment, and areas for storage and disposal. Signage
shall be in accordance with international standards and be well
known to, and easily understood by workers, visitors, and the
general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85 dBA
for a duration of more than 8 hours per day without hearing
protection. The use of hearing protection shall be enforced
actively.
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices, sheds,
and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of trees;
(iii) Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting of trees
for firewood;
(v) Train employees in the storage and handling of materials
which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove from the
site;
(vii) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures (such
as buildings, shelters, and latrines) which are no longer required;
Partially
complied
A small worker camp cum construction
yard has been established but the
arrangement is improper
Sanitation facilities need to be improved.
Instruction has been given to
contractor to discuss with
IPIU/DSC before camp
establishment and proper
compliance of EMP
Proper sanitation facilities is
required
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 60
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Table 13: Compliance of EMP for Sikar Water Supply sub Project {RUIDP/TR-02/SKR/WS-04}
Sr. No.
Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
PRECONSTRUCTION STAGE
1 Environmental Clearances
Site preparation work completed by IPIU including
necessary clearance
Consent to Establish under Water (Prevention and
Control of Pollution) Act
Consent to Establish under Air (Prevention and Control
of Pollution) Act
Tree-cutting Permit
Complied
Consent/approval from Pollution Control
Board is not required for any component
under package.
Tree cutting permission is not required.
Nil DSC / IPIU
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain
an expert assessment of the archaeological potential of
the site;
(ii) Consider alternatives if the site is found to be of
medium or high risk;
(iii) Include state and local archaeological, cultural and
historical authorities, and interest groups in
consultation forums as project stakeholders so that
their expertise can be made available; and
(iv) Develop a protocol for use by the construction
contractors in conducting any excavation work, to
ensure that any chance finds are recognised and
measures are taken to ensure they are protected and
conserved.
Complied
It was confirmed by consultations with
various stakeholders that the site has no
archaeological potential
Instruction has been given to the
contractor to ensure that any chance
finds are recognized and measures are
taken to ensure they are protected and
conserved
No such occurrence till date
Nil DSC / IPIU
3 Construction work camps, hot mix plants, stockpile
areas, storage areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant
space in the subproject sites;
Complied
All the facilities related to construction
are located within project site
Nil Contractor/ DSC
/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 61
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No.
Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
(ii) If it is deemed necessary to locate elsewhere,
consider sites that will not promote instability and result
in destruction of property, vegetation, irrigation, and
drinking water supply systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct
disposal to water body or in areas which will
inconvenience the community.
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining
Department;
(ii) If other sites are necessary, inform construction
contractor that it is their responsibility to verify the
suitability of all material sources and to obtain the
approval of IPIU; and
(iii) If additional quarries will be required after
construction is started, inform construction contractor
to obtain a written approval from IPMU.
Complied
All the material is being taken from
approved mines
Nil DSC / IPIU
CONSTRUCTION STAGE
1 Sources of Materials
(i) Use quarry sites and sources permitted by
government;
(ii) Verify suitability of all material sources and obtain
approval of Investment Program Implementation Unit (
IPIU);
(iii) If additional quarries will be required after
construction has started, obtain written approval from
PMU; and;
(iv) Submit to DSC on a monthly basis documentation of
sources of materials.
Complied
All the material is being taken from
government approved quarry sites
Nil DSC / IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 62
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No.
Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for
stockpiling of clay, soils, gravel, and other construction
materials;
(ii) Damp down exposed soil and any stockpiled on site
by spraying with water when necessary during dry
weather;
(iii) Use tarpaulins to cover sand and other loose
material when transported by trucks; and
(iv) Fit all heavy equipment and machinery with air
pollution control devices which are operating correctly.
Partially
Complied
Sprinkling of water is being carried out as
per requirement at site in order to arrest
dust
Air quality monitoring has not been
carried out during report period
Adequate watering is required
at work site
Monitoring to be carried out in
next reporting period.
A log register for watering is
required to be maintained at
site.
Instruction has been given to
contractor to use tarpaulins to
cover fine material when
transported
Contractor/ DSC
/ IPIU
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the
monsoon season unless covered by tarpaulins or plastic
sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult
with IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins
along the drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away
from any drainage leading to water bodies;
(v) Dispose any wastes generated by construction
activities in designated sites; and
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
Complied
Surface water quality monitoring is not
required as there is no surface water
source.
Ground water quality monitoring has
not been conducted in this reporting
period. Result will be reported in the
next reporting period..
No surface water is available
near the project site
Contractor/ DSC
/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 63
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No.
Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that
activities with the greatest potential to generate noise
are conducted during periods of the day which will
result in least disturbance;
(ii) Require horns not be used unless it is necessary to
a othe oad use s o a i als of the ehi le s approach;
(iii) Minimize noise from construction equipment by
using vehicle silencers, fitting jackhammers with noise-
reducing mufflers, and portable street barriers the
sound impact to surrounding sensitive receptor; and
(iv) Maintain maximum sound levels not exceeding 80
decibels (dbA) when measured at a distance of 10 m or
more from the vehicle/s.
Partially
Complied
Activities with the greatest potential to
generate noise have been planned in
consultation with IPIU and are being
conducted in day time
Noise monitoring has not been
conducted during report period,
Monitoring to be carried out in
next reporting period.
Contractor/ DSC
/ IPIU
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(ii) Coordinate with Municipal Board for beneficial uses
of excess excavated soils or immediately dispose to
designated areas;
(iv) Recover used oil and lubricants and reuse or remove
from the sites;
(v) Manage solid waste according to the following
preference hierarchy: reuse, recycling and disposal to
designated areas;
Complied
Overburden and excavated materials
from construction sites are being utilized
in backfilling of trenches and leveling of
low lying area as per direction of ULB of
Sikar town
Leakage of oil & lubricants has not been
observed on site.
Nil DSC / IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 64
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No.
Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do
not use narrow local roads, except in the immediate
vicinity of delivery sites;
(ii) Schedule transport and hauling activities during non-
peak hours;
(iii) Coordinate with Municipal Traffic Office for
temporary road diversions and with for provision of
traffic aids if transportation activities cannot be avoided
during peak hours;
Complied
The vehicles carrying materials to the
work site follow only designated route to
the site
Traffic diversions is not required at
present
sign boards informing nature and
duration of construction works and
contact numbers for
concerns/complaints has been provided
Nil DSC / IPIU
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required
to maintain access across trenches for people and
vehicles;
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment,
hospitals, and schools;
(iv) Consult businesses and institutions regarding
operating hours and factoring this in work schedules;
and
(v) Provide sign boards for pedestrians to inform nature
and duration of construction works and contact
numbers for concerns/complaints.
Complied
The work schedule has been prepared as
per consultation with local public
Proper access across trenches for people
and vehicles has provided
Significant work force has been provided
Nil DSC / IPIU
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the
maximum extent, local persons within the 2-km
immediate area if manpower is available; and
(ii) Secure construction materials from local market.
Complied
At present most of the workforce is hired
locally
Nil DSC / IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 65
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No.
Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and
Safety (H and S) Plan which will include measures such
as: (a) excluding public from the site; (b) ensuring all
workers are provided with and use Personal Protective
Equipment; (c) H and S Training for all site personnel;
(d) documented procedures to be followed for all site
activities; and (e) documentation of work-related
accidents;
(ii) Ensure that qualified first-aid can be provided at all
times. Equipped first-aid stations shall be easily
accessible throughout the site;
(iii) Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion
and accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not
exposed to hazardous or noxious substances;
(vii) Provide H and S orientation training to all new
workers to ensure that they are apprised of the basic
site rules of work at the site, personal protective
protection, and preventing injuring to fellow workers;
(viii) Provide visitor orientation if visitors to the site can
gain access to areas where hazardous conditions or
substances may be present. Ensure also that visitor/s do
not enter hazard areas unescorted;
(ix) Ensure the visibility of workers through their use of
high visibility vests when working in or walking through
heavy equipment operating areas;
(x) Ensure moving equipment is outfitted with audible
Partially
complied
Health and Safety Plan has been
implemented on site.
PPE are being used.
First-aid box is available but not as per
standard
Group insurance has been provided to
workers
Barricading, safety tapes and delineators
have been adequately provided at work
fronts as public safety measures
Drinking water has been provided at sites
H&S training is being provided to workers
by DSC regularly
high visibility vests are provided to
workers
Training for health and safety measures
have been given to contractor by DSC.
Workers are not exposed to high noise
level more than 8 hrs
Contractor has been instructed
complete compliance of
measure specified in EMP
Safety officer is nominated by
contractor
IPIU/Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 66
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No.
Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
back-up alarms;
(xi) Mark and provide sign boards for hazardous areas
such as energized electrical devices and lines, service
rooms housing high voltage equipment, and areas for
storage and disposal. Signage shall be in accordance
with international standards and be well known to, and
easily understood by workers, visitors, and the general
public as appropriate; and
(xii) Disallow worker exposure to noise level greater
than 85 dBA for a duration of more than 8 hours per day
without hearing protection. The use of hearing
protection shall be enforced actively.
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices,
sheds, and construction plants;
(ii) Minimize removal of vegetation and disallow cutting
of trees;
(iii) Provide water and sanitation facilities for
employees;
(iv) Prohibit employees from poaching wildlife and
cutting of trees for firewood;
(v) Train employees in the storage and handling of
materials which can potentially cause soil
contamination;
(vi) Recover used oil and lubricants and reuse or remove
from the site;
(vii) Manage solid waste according to the following
preference hierarchy: reuse, recycling and disposal to
designated areas;
(viii) Remove all wreckage, rubbish, or temporary
Complied
At present most of the workers
employed are local.
Contractor has constructed temporary
camp at ESR sites (WS/02) which is now
removed as work has completed
Nil Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 67
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No.
Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
structures (such as buildings, shelters, and latrines)
which are no longer required;
Table 14: Compliance of EMP for Nagaur Waste Water sub-project {RUSDIP/TR-02/NGR/WW/02-Lot-2}
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
PRECONSTRUCTION STAGE
1 Environmental Clearances
Site preparation work completed by IPIU including
necessary clearance
Consent to Establish under Water (Prevention and
Control of Pollution) Act
Consent to Establish under Air (Prevention and Control
of Pollution) Act
Tree-cutting Permit
Complied
Consent to Establish for STP from
Pollution Control Board has been
obtained. Consent is valid up to
31.07.2015
CTE has been renewed via order number
2016-2017/PLG/1011 dated 27/07/2016
valid till 31/07/2018.
Tree cutting is not required
Application for CTO has been submitted
to RPCB .
Deficiency letter issued by
RPCB dated 12/05/2017 agaisnt
the submitted CTO. The same is
under process.
Trial run under progress.
IPIU/ DSC
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain
an expert assessment of the archaeological potential of
the site;
(ii) Consider alternatives if the site is found to be of
medium or high risk;
(iii) Include state and local archaeological, cultural and
historical authorities, and interest groups in
consultation forums as project stakeholders so that
their expertise can be made available; and
Complied
It was confirmed by consultations with
various stakeholders that the site has no
archaeological potential
Instruction has been given to the
contractor to ensure that any chance
finds are recognized and measures are
taken to ensure they are protected and
conserved
Nil IPIU/ DSC
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 68
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(iv) Develop a protocol for use by the construction
contractors in conducting any excavation work, to
ensure that any chance finds are recognised and
measures are taken to ensure they are protected and
conserved.
3 Construction work camps, hot mix plants, stockpile
areas, storage areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant
space in the subproject sites;
(ii) If it is deemed necessary to locate elsewhere,
consider sites that will not promote instability and result
in destruction of property, vegetation, irrigation, and
drinking water supply systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct
disposal to water body or in areas which will
inconvenience the community.
Complied
All the facilities related to construction
are located within project site
Storage & leakage of oil and lubricants is
done as per the norms i.e. stored away
from the drainage.
Nil IPIU/ DSC
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining
Department;
(ii) If other sites are necessary, inform construction
contractor that it is their responsibility to verify the
suitability of all material sources and to obtain the
approval of IPIU; and
(iii) If additional quarries will be required after
construction is started, inform construction contractor
to obtain a written approval from IPMU.
Complied
All the material is being taken from
approved mines
Nil IPIU/ DSC
CONSTRUCTION STAGE
1 Sources of Materials
(i) Use quarry sites and sources permitted by Complied
All the material is being taken from
government approved quarry sites
Nil IPIU/ DSC
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 69
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
government;
(ii) Verify suitability of all material sources and obtain
approval of Investment Program Implementation Unit (
IPIU);
(iii) If additional quarries will be required after
construction has started, obtain written approval from
PMU; and;
(iv) Submit to DSC on a monthly basis documentation of
sources of materials.
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for
stockpiling of clay, soils, gravel, and other construction
materials;
(ii) Damp down exposed soil and any stockpiled on site
by spraying with water when necessary during dry
weather;
(iii) Use tarpaulins to cover sand and other loose
material when transported by trucks; and
(iv) Fit all heavy equipment and machinery with air
pollution control devices which are operating correctly.
Complied
Civil works has been completed, trial run
under progress, hence monitoring is not
required during this reporting period.
Sprinkling of water is being carried out as
per requirement at site in order to arrest
dust
Fine material carrying vehicles are
properly covered to avoid dust problem
Nil Contractor/
IPIU/ DSC
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the
monsoon season unless covered by tarpaulins or plastic
sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult
with IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins
along the drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away
Complied
Overburden and excavated materials
from construction sites are being utilized
in backfilling.
No surface water body near the working
area hence surface water monitoring is
not required.
Ground water quality monitoring is not
required as ground water is naturally high
in fluoride content and is unsuitable for
domestic use and is not extracted from
Nil
Contractor/
IPIU/ DSC
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 70
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
from any drainage leading to water bodies;
(v) Dispose any wastes generated by construction
activities in designated sites; and
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
ground for use.
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that
activities with the greatest potential to generate noise
are conducted during periods of the day which will
result in least disturbance;
(ii) Require horns not be used unless it is necessary to
a othe oad use s o a i als of the ehi le s approach;
(iii) Minimize noise from construction equipment by
using vehicle silencers, fitting jackhammers with noise-
reducing mufflers, and portable street barriers the
sound impact to surrounding sensitive receptor; and
(iv) Maintain maximum sound levels not exceeding 80
decibels (dbA) when measured at a distance of 10 m or
more from the vehicle/s.
Complied
Activities with the greatest potential to
generate noise have been planned in
consultation with IPIU and are being
conducted in day time
Civil works has been completed, trial run
under progress, hence monitoring is not
required.
Nil Contractor/
IPIU/ DSC
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(ii) Coordinate with Municipal Board for beneficial uses
of excess excavated soils or immediately dispose to
designated areas;
(iv) Recover used oil and lubricants and reuse or remove
from the sites;
(v) Manage solid waste according to the following
preference hierarchy: reuse, recycling and disposal to
Complied
Overburden and excavated materials
from construction sites are being utilized
in backfilling
No oil & lubricant leakage has been
observed on site.
Nil IPIU/ DSC
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 71
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
designated areas;
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do
not use narrow local roads, except in the immediate
vicinity of delivery sites;
(ii) Schedule transport and hauling activities during non-
peak hours;
(iii) Coordinate with Municipal Traffic Office for
temporary road diversions and with for provision of
traffic aids if transportation activities cannot be avoided
during peak hours;
Complied
The trucks carrying materials to the work
site follow only designated route to the
site.
Sign boards informing nature and
duration of construction works and
contact numbers for
concerns/complaints has been provided.
Nil IPIU/ DSC
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required
to maintain access across trenches for people and
vehicles;
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment,
hospitals, and schools;
(iv) Consult businesses and institutions regarding
operating hours and factoring this in work schedules;
and
(v) Provide sign boards for pedestrians to inform nature
and duration of construction works and contact
numbers for concerns/complaints.
Complied
Proper access is being provided as and
when required
Sign board has been provided at site
Nil IPIU/ DSC
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 72
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the
maximum extent, local persons within the 2-km
immediate area if manpower is available; and
(ii) Secure construction materials from local market.
Complied
At present most of the workforce is hired
locally
Nil Contractor
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and
Safety (H and S) Plan which will include measures such
as: (a) excluding public from the site; (b) ensuring all
workers are provided with and use Personal Protective
Equipment; (c) H and S Training for all site personnel;
(d) documented procedures to be followed for all site
activities; and (e) documentation of work-related
accidents;
(ii) Ensure that qualified first-aid can be provided at all
times. Equipped first-aid stations shall be easily
accessible throughout the site;
(iii) Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion
and accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not
exposed to hazardous or noxious substances;
(vii) Provide H and S orientation training to all new
workers to ensure that they are apprised of the basic
site rules of work at the site, personal protective
protection, and preventing injuring to fellow workers;
(viii) Provide visitor orientation if visitors to the site can
gain access to areas where hazardous conditions or
complied
PPE are being used partially.
Health and Safety Plan has been
provided.
Contractor has provided first-aid box at
each site
Group insurance has been provided to
workers
Barricading, safety tapes and delineators
have been adequately provided at work
fronts as public safety measures
Drinking water has been provided at sites
Training for health and safety measures
have been given to contractor by DSC.
Workers are not exposed to high noise
level more than 8 hrs
Nil
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 73
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
substances may be present. Ensure also that visitor/s do
not enter hazard areas unescorted;
(ix) Ensure the visibility of workers through their use of
high visibility vests when working in or walking through
heavy equipment operating areas;
(x) Ensure moving equipment is outfitted with audible
back-up alarms;
(xi) Mark and provide sign boards for hazardous areas
such as energized electrical devices and lines, service
rooms housing high voltage equipment, and areas for
storage and disposal. Signage shall be in accordance
with international standards and be well known to, and
easily understood by workers, visitors, and the general
public as appropriate; and
(xii) Disallow worker exposure to noise level greater
than 85 dBA for a duration of more than 8 hours per day
without hearing protection. The use of hearing
protection shall be enforced actively.
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices,
sheds, and construction plants;
(ii) Minimize removal of vegetation and disallow cutting
of trees;
(iii) Provide water and sanitation facilities for
employees;
(iv) Prohibit employees from poaching wildlife and
cutting of trees for firewood;
(v) Train employees in the storage and handling of
materials which can potentially cause soil
contamination;
Partially
Complied
At present most of the workers employed
are local.
Labour camp has been established near
STP site
Poor water and sanitation facilities, use
of firewood are observed in labour camp
Contractor has instructed to
provide proper water and
sanitation facilities and cooking
gas to the worker
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 74
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(vi) Recover used oil and lubricants and reuse or remove
from the site;
(vii) Manage solid waste according to the following
preference hierarchy: reuse, recycling and disposal to
designated areas;
(viii) Remove all wreckage, rubbish, or temporary
structures (such as buildings, shelters, and latrines)
which are no longer required;
Table 15: Compliance of EMP for Barmer Waste Water sub-project {RUSDIP/TR-02/BMR/WW/03 Lot-1 & Lot-2}
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
PRECONSTRUCTION STAGE
1 Environmental Clearances
Site preparation work completed by IPIU including necessary
clearance
Consent to Establish under Water (Prevention and Control of
Pollution) Act
Consent to Establish under Air (Prevention and Control of
Pollution) Act
Tree-cutting Permit
Complied
Consent to Establish has been obtained for
10 MLD STP under WW/03 Lot-2 package
from Pollution Control Board. The consent
is valid up to 01.07.2015. As the work is
already completed.
CTO has been applied to RPCB
The STP will be operational after obtaining
CTO.
Tree cutting is not required
Deficiency letter issued by
RPCB on 22/5/2017 against the
submitted CTO. The same is
under process.
DSC/ IPIU
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain an expert
assessment of the archaeological potential of the site;
(ii) Consider alternatives if the site is found to be of medium or
high risk;
(iii) Include state and local archaeological, cultural and historical
Complied
It was confirmed by consultations with
various stakeholders that the site has no
archaeological potential
Instruction has been given to the contractor
to ensure that any chance finds are
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 75
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
authorities, and interest groups in consultation forums as project
stakeholders so that their expertise can be made available; and
(iv) Develop a protocol for use by the construction contractors in
conducting any excavation work, to ensure that any chance finds
are recognised and measures are taken to ensure they are
protected and conserved.
recognized and measures are taken to
ensure they are protected and conserved
No such occurrence till date
3 Construction work camps, hot mix plants, stockpile areas,
storage areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant space in the
subproject sites;
(ii) If it is deemed necessary to locate elsewhere, consider sites
that will not promote instability and result in destruction of
property, vegetation, irrigation, and drinking water supply
systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct disposal to
water body or in areas which will inconvenience the community.
Complied
All the facilities related to construction are
located within project site
Nil DSC/ IPIU
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining Department;
(ii) If other sites are necessary, inform construction contractor
that it is their responsibility to verify the suitability of all material
sources and to obtain the approval of IPIU; and
(iii) If additional quarries will be required after construction is
started, inform construction contractor to obtain a written
approval from IPMU.
Complied
All the material is being taken from
approved mines
Nil DSC/ IPIU
CONSTRUCTION STAGE
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain approval of
Investment Program Implementation Unit ( IPIU);
Complied
All the material is being taken from
government approved quarry sites
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 76
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(iii) If additional quarries will be required after construction has
started, obtain written approval from PMU; and;
(iv) Submit to DSC on a monthly basis documentation of sources
of materials.
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for stockpiling
of clay, soils, gravel, and other construction materials;
(ii) Damp down exposed soil and any stockpiled on site by
spraying with water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material when
transported by trucks; and
(iv) Fit all heavy equipment and machinery with air pollution
control devices which are operating correctly.
Partially
Complied
Adequate sprinkling of water is required for
arresting fugitive dust
Biannual air quality monitoring is not
required as work has been completed.
Nil Contractor/IPIU
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the monsoon
season unless covered by tarpaulins or plastic sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins along the
drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from any
drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities in
designated sites; and
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
Complied
Surface water quality monitoring is not
required to be conducted during report
period as no surface water is available near
the project site.
Ground water quality monitoring is not
required to be conducted as work has been
completed.
Nil Contractor/IPIU
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that activities
Partially
Complied
Noise level monitoring is not required to be
Nil Contractor/IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 77
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
with the greatest potential to generate noise are conducted
during periods of the day which will result in least disturbance;
(ii) Require horns not be used unless it is necessary to warn other
oad use s o a i als of the ehi le s app oa h; (iii) Minimize noise from construction equipment by using vehicle
silencers, fitting jackhammers with noise-reducing mufflers, and
portable street barriers the sound impact to surrounding sensitive
receptor; and
(iv) Maintain maximum sound levels not exceeding 80 decibels
(dbA) when measured at a distance of 10 m or more from the
vehicle/s.
conducted as the work has been
completed.
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(ii) Coordinate with Municipal Board for beneficial uses of excess
excavated soils or immediately dispose to designated areas;
(iv) Recover used oil and lubricants and reuse or remove from the
sites;
(v) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
Complied
Overburden and excavated materials from
construction sites has been reused for
backfilling and excess material has been
disposed to designated areas
Any oil and lubricants leakage not observed
at site
Nil DSC/ IPIU
6 Accessibility
Plan transportation routes so that heavy vehicles do not use
narrow local roads, except in the immediate vicinity of delivery
sites;
(ii) Schedule transport and hauling activities during non-peak
hours;
(iii) Coordinate with Municipal Traffic Office for temporary road
diversions and with for provision of traffic aids if transportation
activities cannot be avoided during peak hours;
Complied
Traffic diversions are provided at necessary
points and as per requirement
Sign boards informing nature and duration
of construction works and contact numbers
for concerns/complaints has been provided
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 78
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
7 Socio-Economic – Income
Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
Increase workforce in front of critical areas such as institutions,
place of worship, business establishment, hospitals, and schools;
(iv) Consult businesses and institutions regarding operating hours
and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
Complied
Proper access across trenches for people
and vehicles has been provided Sign board
has been provided at site
Nil DSC/ IPIU
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the maximum
extent, local persons within the 2-km immediate area if
manpower is available; and
(ii) Secure construction materials from local market.
Complied
At present most of the workforce is hired
locally
Nil DSC/ IPIU
9 Occupational Health and Safety
(i)Develop and implement site-specific Health and Safety (H and
S) Plan which will include measures such as: (a) excluding public
from the site; (b) ensuring all workers are provided with and use
Personal Protective Equipment; (c) H and S Training for all site
personnel; (d) documented procedures to be followed for all site
activities; and (e) documentation of work-related accidents;
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible throughout
the site;
(iii) Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
Partially
complied
PPE are being used completely
First-aid box is available at site
Group insurance has been provided to
workers
Proper barricading for unauthorized
intrusion has been provided except few
stretches of pipe laying areas
Drinking water has been provided at sites
Training for health and safety measures
Contractor has been instructed
complete compliance of
measure specified in EMP
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 79
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(vi) Provide clean eating areas where workers are not exposed to
hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work at the
site, personal protective protection, and preventing injuring to
fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or substances may be
present. Ensure also that visitor/s do not enter hazard areas
unescorted;
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-up
alarms;
(xi) Mark and provide sign boards for hazardous areas such as
energized electrical devices and lines, service rooms housing high
voltage equipment, and areas for storage and disposal. Signage
shall be in accordance with international standards and be well
known to, and easily understood by workers, visitors, and the
general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85 dBA
for a duration of more than 8 hours per day without hearing
protection. The use of hearing protection shall be enforced
actively.
have not been conducted by contractor
Workers are not exposed to high noise level
more than 8 hrs
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices, sheds,
and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of trees;
(iii) Provide water and sanitation facilities for employees;
complied
At present most of the workers employed
are local.
Labour camp has been established near STP
site (RUSDIP/TR-2/BMR/WW/03 (Lot-2))
Contractor has instructed to
provide proper water and
sanitation facilities and cooking
gas to the worker
DSC / Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 80
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(iv) Prohibit employees from poaching wildlife and cutting of
trees for firewood;
(v) Train employees in the storage and handling of materials
which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove from the
site;
(vii) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures (such
as buildings, shelters, and latrines) which are no longer required;
Reasonable water and sanitation facilities,
Firewood was not observed in labour camp
Table 16: EMP Compliance Status of Churu subproject (RUSDIP/TR-02/CHU/WS-04)
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
PRECONSTRUCTION STAGE
1 Environmental Clearances
Site preparation work completed by IPIU including necessary
clearance
Consent to Establish under Water (Prevention and Control of
Pollution) Act
Consent to Establish under Air (Prevention and Control of
Pollution) Act
Tree-cutting Permit
Complied
Consent to Establish is not required
Tree cutting permission is not required.
Nil DSC/ IPIU
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain an expert
assessment of the archaeological potential of the site;
(ii) Consider alternatives if the site is found to be of medium or
high risk;
(iii) Include state and local archaeological, cultural and historical
Complied
It was confirmed by consultations with
various stakeholders that the site has no
archaeological potential
Instruction has been given to the
contractor to ensure that any chance
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 81
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
authorities, and interest groups in consultation forums as project
stakeholders so that their expertise can be made available; and
(iv) Develop a protocol for use by the construction contractors in
conducting any excavation work, to ensure that any chance finds
are 81hysic81ize and measures are taken to ensure they are
protected and conserved.
finds are recognized and measures are
taken to ensure they are protected and
conserved
No such occurrence till date
3 Construction work camps, hot mix plants, stockpile areas,
storage areas, and disposal areas
(1) Prioritize areas within or nearest possible vacant space in the
subproject sites;
(ii) If it is deemed necessary to locate elsewhere, consider sites
that will not promote instability and result in destruction of
property, vegetation, irrigation, and drinking water supply
systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct disposal to
water body or in areas which will inconvenience the community.
Complied
All the facilities related to construction
are located within project site.
Nil DSC/ IPIU
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining Department;
(ii) If other sites are necessary, inform construction contractor
that it is their responsibility to verify the suitability of all material
sources and to obtain the approval of IPIU; and
(iii) If additional quarries will be required after construction is
started, inform construction contractor to obtain a written
approval from IPMU.
Complied
All the material is being taken from
approved mines
Nil DSC/ IPIU
CONSTRUCTION STAGE
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain approval of
Complied
All the material is being taken from
government approved quarry sites
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 82
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
Investment Program Implementation Unit ( IPIU);
(iii) If additional quarries will be required after construction has
started, obtain written approval from PMU; and;
(iv) Submit to DSC on a monthly basis documentation of sources
of materials.
2 Air Quality
(1) Consult with IPIU/DSC on the designated areas for stockpiling
of clay, soils, gravel, and other construction materials;
(ii) Damp down exposed soil and any stockpiled on site by
spraying with water when necessary during dry weather;
(iii)Use tarpaulins to cover sand and other loose material when
transported by trucks; and
(iv) Fit all heavy equipment and machinery with air pollution
control devices which are operating correctly.
Partially
Complied
Adequate sprinkling of water is done for
arresting fugitive dust at all the running
sites
Air quality monitoring was not carried
out during this reporting period.
Monitoring is required to be
carried out.
A log register for watering is
required to be maintained at
site
Instruction has been given to
contractor to use tarpaulins to
cover fine material when
transported
Contractor/IPIU
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the monsoon
season unless covered by tarpaulins or plastic sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins along the
drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from any
drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities in
designated sites; and
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
Complied
In the pipe laying works excavated soil is
being back filled immediately after pipe
laying and excess soil is removed from
site
No surface water body near the working
area therefore surface water quality
monitoring is not required.
Nil Contractor/ DSC/
IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 83
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that activities
with the greatest potential to generate noise are conducted
during periods of the day which will result in least disturbance;
(ii) Require horns not be used unless it is necessary to warn other
road users or animals of the vehicle s app oa h; (iii) Minimize noise from construction equipment by using vehicle
silencers, fitting jackhammers with noise-reducing mufflers, and
portable street barriers the sound impact to surrounding sensitive
receptor; and
(iv) Maintain maximum sound levels not exceeding 80 decibels
(dbA) when measured at a distance of 10 m or more from the
vehicle/s.
Partially
Complied
Noise level monitoring was not carried
out during this reporting period.
Activities are planned in consultation
with PIU
DGs are not being used but concrete
mixtures are not provided with acoustic
enclosures
Maintenance of construction equipment
is required
Monitoring is required to be
carried out
Contractor/ DSC/
IPIU
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(iii) Coordinate with Municipal Board for beneficial uses of excess
excavated soils or immediately dispose to designated areas;
(iv) Recover used oil and lubricants and reuse or remove from the
sites;
(v) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
Complied
Overburden and excavated materials
from construction sites has been reused
for backfilling and excess material has
been disposed to designated areas
Nil DSC/ IPIU
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not use
narrow local roads, except in the immediate vicinity of delivery
sites;
(ii) Schedule transport and hauling activities during non-peak
hours;
(iii) Coordinate with Municipal Traffic Office for temporary road
diversions and with for provision of traffic aids if transportation
Complied
The vehicles carrying materials to the
work site follow only designated route to
the site
sign boards informing nature and
duration of construction works and
contact numbers for
concerns/complaints has been provided
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 84
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
activities cannot be avoided during peak hours;
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment, hospitals,
and schools;
(iv) Consult businesses and institutions regarding operating hours
and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
Complied
The work schedule has been prepared as
per consultation with local public
Significant work force has been provided
Nil DSC/ IPIU
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the maximum
extent, local persons within the 2-km immediate area if
manpower is available; and
(ii) Secure construction materials from local market.
Complied
At present most of the workforce is hired
locally
Nil DSC/ IPIU
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H and
S) Plan which will include measures such as: (a) excluding public
from the site; (b) ensuring all workers are provided with and use
Personal Protective Equipment; (c) H and S Training for all site
personnel; (d) documented procedures to be followed for all site
activities; and (e) documentation of work-related accidents;
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible throughout
the site;
Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
Partially
complied
PPE are being used.
First-aid box is available at site
Group insurance has been provided to
workers
Drinking water has been provided at sites
Training for health and safety measures
have been given to contractor by DSC.
Contractor has been instructed
complete compliance of
measure specified in EMP
Contractor/IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 85
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not exposed to
hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work at the
site, personal protective protection, and preventing injuring to
fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or substances may be
present. Ensure also that visitor/s do not enter hazard areas
unescorted;
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-up
alarms;
(xi) Mark and provide sign boards for hazardous areas such as
energized electrical devices and lines, service rooms housing high
voltage equipment, and areas for storage and disposal. Signage
shall be in accordance with international standards and be well
known to, and easily understood by workers, visitors, and the
general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85 dBA
for a duration of more than 8 hours per day without hearing
protection. The use of hearing protection shall be enforced
actively.
Workers are not exposed to high noise
level more than 8 hrs
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices, sheds,
and construction plants;
Complied
At present most of the workers
employed are local.
Nil Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 86
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(ii) Minimize removal of vegetation and disallow cutting of trees;
(iv) Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting of trees
for firewood;
(v) Train employees in the storage and handling of materials
which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove from the
site;
(vii) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures (such
as buildings, shelters, and latrines) which are no longer required;
Contractor has constructed temporary
camp at ESR sites which is removed as
work has been completed.
Table 17: Compliance of EMP for Bundi Road sub-project {RUSDIP/TR-02/BND/ST/04}
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
PRECONSTRUCTION STAGE
1 Environmental Clearances
Site preparation work completed by IPIU including necessary
clearance
Consent to Establish under Water (Prevention and Control of
Pollution) Act
Consent to Establish under Air (Prevention and Control of
Pollution) Act
Tree-cutting Permit
Complied
Necessary clearances from various
departments have been taken before
start of project
Tree cutting is not required
Forest NOC has been obtained prior to
start of the work for all sites
Nil DSC/ IPIU
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain an expert
assessment of the archaeological potential of the site;
(ii) Consider alternatives if the site is found to be of medium or
Complied
It was confirmed by consultations with
various stakeholders that the sites has no
archaeological potential except
RanijikiBaori.
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 87
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
high risk;
(iii) Include state and local archaeological, cultural and historical
authorities, and interest groups in consultation forums as project
stakeholders so that their expertise can be made available; and
(iv) Develop a protocol for use by the construction contractors in
conducting any excavation work, to ensure that any chance finds
are 87hysic87ize and measures are taken to ensure they are
protected and conserved.
It was confirmed in consultation with
nodal officer since it is a state protected
monument & there is no activity within
the monument, no permit is required for
the sub project.
3 Construction work camps, hot mix plants, stockpile areas,
storage areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant space in the
subproject sites;
(ii) If it is deemed necessary to locate elsewhere, consider sites
that will not promote instability and result in destruction of
property, vegetation, irrigation, and drinking water supply
systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct disposal to
water body or in areas which will inconvenience the community.
Complied
All the facilities related to construction
are located within project site away from
residential area
Nil DSC/ IPIU
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining Department;
(ii) If other sites are necessary, inform construction contractor
that it is their responsibility to verify the suitability of all material
sources and to obtain the approval of IPIU; and
(iii) If additional quarries will be required after construction is
started, inform construction contractor to obtain a written
approval from IPMU.
Complied
All the material is being taken from
approved mines
Nil DSC/ IPIU
CONSTRUCTION STAGE
1 Sources of Materials
(i) Use quarry sites and sources permitted by government; Complied
All the material is being taken from
government approved quarry sites
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 88
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(ii) Verify suitability of all material sources and obtain approval of
Investment Program Implementation Unit ( IPIU);
(iii) If additional quarries will be required after construction has
started, obtain written approval from PMU; and;
(iv) Submit to DSC on a monthly basis documentation of sources
of materials.
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for stockpiling
of clay, soils, gravel, and other construction materials;
(ii) Damp down exposed soil and any stockpiled on site by
spraying with water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material when
transported by trucks; and
(iv) Fit all heavy equipment and machinery with air pollution
control devices which are operating correctly.
Partially
Complied
Dust problem not noticed at sites as most
of the works are completed
Air quality monitoring is pending though
work order is given to monitoring agency
DG sets and other heavy equipment
arefitted with pollution control devices
Instruction has been given to
contractor for water sprinkling
at batching plant and to use
tarpaulins to cover fine
material when transported and
stored
Air quality monitoring is
required to be conducted.
Regularly by
Contractor
IPIU
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the monsoon
season unless covered by tarpaulins or plastic sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins along the
drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from any
drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities in
designated sites; and
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
Partially
Complied
Excavated soil is reused for surface
leveling and backfilling and excess soil is
being dumped in designated low lying
areas only
Fuels and lubricants are kept in
construction camp which is away from
any surface water source
Surface water quality inspection is being
carried out, no surface water exist near
running sites therefore surface water
quality analysis is not required
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 89
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that activities
with the greatest potential to generate noise are conducted
during periods of the day which will result in least disturbance;
(ii) Require horns not be used unless it is necessary to warn other
oad use s o a i als of the ehi le s app oa h; (iii) Minimize noise from construction equipment by using vehicle
silencers, fitting jackhammers with noise-reducing mufflers, and
portable street barriers the sound impact to surrounding sensitive
receptor; and
(iv) Maintain maximum sound levels not exceeding 80 decibels
(dbA) when measured at a distance of 10 m or more from the
vehicle/s.
Partially
Complied
Activities with the greatest potential to
generate noise have been planned in
consultation with IPIU and are being
conducted in day time
Noise monitoring is pending though work
order is given to monitoring agency
concrete mixtures are not being used
presentlyand DG sets are having noise-
reducing mufflers
Provide enclosures in concrete
mixtures
Noise monitoring is required to
be conducted at the earliest.
Contractor
IPIU
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(iii) Coordinate with Municipal Board for beneficial uses of excess
excavated soils or immediately dispose to designated areas;
(iv) Recover used oil and lubricants and reuse or remove from the
sites;
(v) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
Complied
Overburden and excavated materials
from construction sites are being utilized
in backfilling of trenches
Nil DSC/ IPIU
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not use
narrow local roads, except in the immediate vicinity of delivery
sites;
(ii) Schedule transport and hauling activities during non-peak
hours;
(iii) Coordinate with Municipal Traffic Office for temporary road
diversions and with for provision of traffic aids if transportation
Partially
Complied
The vehicles carrying materials to the
work site follow only designated route to
the site
sign boards informing nature and
duration of construction works and
contact numbers for
concerns/complaints has been provided
Contractor has been instructed
for complete compliance of
EMP
Contractor/IPIU/
DSC
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 90
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
activities cannot be avoided during peak hours; in most of the sites
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment, hospitals,
and schools;
(iv) Consult businesses and institutions regarding operating hours
and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
Not Complied
Proper access across trenches for people
and vehicles has not been provided
Significant work force has been provided
to finish work.
Provide proper access to shops
and residences
DSC/ IPIU
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the maximum
extent, local persons within the 2-km immediate area if
manpower is available; and
(ii) Secure construction materials from local market.
Complied
At present most of the workforce is hired
locally
Nil DSC/ IPIU
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H and
S) Plan which will include measures such as: (a) excluding public
from the site; (b) ensuring all workers are provided with and use
Personal Protective Equipment; (c) H and S Training for all site
personnel; (d) documented procedures to be followed for all site
activities; and (e) documentation of work-related accidents;
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible throughout
the site;
Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
Partially
complied
Site-specific Health and Safety Plan has
been prepared and communicated to
contractor and being followed at site
PPE are not being used completely in
some sites
First-aid facility has not been provided at
each site
Group insurance has been provided to
workers
Drinking water has been provided at all
Contractor has been instructed
complete compliance of
measures specified in EMP
Provide Proper PPEs in all the
sites
Provide sign boards in all
working sites with name and
contact numbers of the
concerned site engineers of
IPIU, DSC and contractors
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 91
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not exposed to
hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work at the
site, personal protective protection, and preventing injuring to
fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or substances may be
present. Ensure also that visitor/s do not enter hazard areas
unescorted;
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-up
alarms;
(xi) Mark and provide sign boards for hazardous areas such as
energized electrical devices and lines, service rooms housing high
voltage equipment, and areas for storage and disposal. Signage
shall be in accordance with international standards and be well
known to, and easily understood by workers, visitors, and the
general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85 dBA
for a duration of more than 8 hours per day without hearing
protection. The use of hearing protection shall be enforced
actively.
sites
H&S training is being provided to workers
by DSC regularly
Sign board are not provided at some sites
Workers are not exposed to high noise
for 8 hours
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices, sheds,
and construction plants;
Complied
Most of workers are local,
no workers camps is established by
contractor
NIL
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 92
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(ii) Minimize removal of vegetation and disallow cutting of trees;
Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting of
trees for firewood;
(v) Train employees in the storage and handling of materials
which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove from the
site;
(vii) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures (such
as buildings, shelters, and latrines) which are no longer required;
Table 18: Compliance of EMP for Bundi waste water sub-project {RUSDIP/TR-02/BND/WW/06}
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
Pre-Construction Stage
1 Environmental Clearances
Site preparation work completed by IPIU including necessary
clearance
Complied
Encumbrance free site for proposed
STP handed over to contractors. All the
necessary clearances from various
departments have been taken before
start of project.
Tree cutting is not required.
Forest NOC has been obtained prior to
start of the work for all sites
Consent to Establish for STP has been
CTE under process at RPCB. DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 93
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
applied in RPCB, observations raised
were complied and case pending with
RPCB
2 Social and Cultural Resources
Any risk that any work involving ground disturbance can
uncover and damage archaeological and historical remains
Consult ASI to obtain an expert assessment of the
archaeological potential of the site;
Consider alternatives if the site is found to be of medium or
high risk;
Complied
It was confirmed by consultations with
various stakeholders that the sites has
no archaeological potential.
Nil DSC/ IPIU
3 Construction work camps, hot mix plants, stockpile areas,
storage areas, and disposal areas
Do not consider residential areas for these purposes, sites
considered should not promote instability and result in
destruction of property, vegetation, irrigation, and drinking
water supply systems.
Complied
Construction camps are located away
from residential areas and do not
affect any supply system
Nil Contractor/ DSC/
IPIU
4 Sources of Materials
Prioritize sites already permitted by the Mining Department;
otherwise verify the suitability of all material sources and
obtain the approval of IPIU
Complied
All the material is being taken from
quarry sites approved from IPIU
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 94
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
Construction Stage
1 Sources of Materials
Prioritize sites already permitted by the Mining Department;
otherwise verify the suitability of all material sources and
obtain the approval of IPIU
Complied
All the material is being taken from
government approved quarry sites
with prior approval of IPIU
Nil DSC/ IPIU
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for
stockpiling of clay, soils, gravel, and other construction
materials;
(ii) Damp down exposed soil and any stockpiled on site by
spraying with water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material when
transported by trucks; and
(iv) Fit all heavy equipment and machinery with air pollution
control devices which are operating correctly.
Partially
Complied
Water sprinkling for arresting fugitive
dust is not being practiced.
Air quality monitoring is pending for
which work order has been issued to
monitoring agency.
DG sets and concrete mixtures arenot
fitted with pollution control devices
Instruction has been given
to contractor for water
sprinkling at all sites and to
use tarpaulins to cover fine
material when transported
and stored
Provide enclosures and
proper stake height in DG
sets and Concrete mixture
to reduce noise and dust
Conduct air quality
monitoring in the next
reporting period.
Regularly by
Contractor
IPIU
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the monsoon
season unless covered by tarpaulins or plastic sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
Complied
Excavated soil is reused for surface
leveling and backfilling and excess soil
is being dumped in designated low
lying areas only
Fuels and lubricants are kept in
construction camp which is away from
Contractor / IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 95
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
IPIU/DSC on designated disposal areas;
(iii) Place storage areas for fuels and lubricants away from any
drainage leading to water bodies;
(iv) Dispose any wastes generated by construction activities in
designated sites; and
(v) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
any surface water source
Surface water quality inspection is
being carried out, no surface water
exist near running sites therefore
surface water quality analysis is not
required
4 Noise Levels
(i) Plan activities with the greatest potential to generate noise
are conducted during periods of the day which will result in
least disturbance;
(ii) Minimize noise from construction equipment by using
vehicle silencers, fitting jackhammers with noise-reducing
mufflers, and portable street barriers the sound impact to
surrounding sensitive receptor; and
(iii) Maintain maximum sound levels not exceeding 80 decibels
(dbA) when measured at a distance of 10 m or more from the
vehicle/s.
Partially
Complied
Activities with the greatest potential to
generate noise have been planned in
consultation with IPIU and are being
conducted in day time
concrete mixtures and DG sets being
used are not having enclosures
Noise monitoring is pending since long,
though work order is issued to
monitoring agency by IPIU
Provide enclosures in
concrete mixtures
Noise monitoring is required
Contractor
IPIU
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(iii) Manage solid waste according to the following preference
Complied
Contractor has not prepared waste
management plan, though following
waste management as per EMP
The excavated soil is reused in surface
leveling works and surplus soil is
Provide proper sign boards,
road signage and road safety
measures at all sites as per
EMP
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 96
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
hierarchy: reuse, recycling and disposal to designated areas; disposed in designated areas.
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not use
narrow local roads, except in the immediate vicinity of delivery
sites;
(ii) Coordinate with Municipal Traffic Office for temporary road
diversions and for provision of traffic aids if transportation
activities cannot be avoided during peak hours; and
(vii) Notify affected sensitive receptors by providing sign boards
informing nature and duration of construction works and
contact numbers for concerns/complaints
Partially
Complied
The vehicles carrying materials to the
work site follow only designated route
to the site
sign boards informing nature and
duration of construction works and
contact numbers for
concerns/complaints has not been
provided in most of the sites, road
signage for road safety is lagging in
some sites
Provide road signage and
road safety measures at all
sites
Contractor/ DSC/
IPIU
7 Socio-Economic – Income
(i) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
(ii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment,
hospitals, and schools;
Not Complied
Metal sheets/wood planks are not
provided for access to shops at many
places
Significant work force has not been
provided in city area to complete work
in time
Provide safe access for
pedestrians by metal
sheets/wood planks
Increase work force to finish
the works quickly in city
areas
Contractor/ DSC/
IPIU
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the maximum
extent, local persons within the 2-km immediate area if
manpower is available; and
(ii) Secure construction materials from local market.
Complied
At present most of the workforce is
hired locally
Most of the construction materials are
purchased from local market, if
available
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 97
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H
and S) Plan which will include measures such as: (a) excluding
public from the site; (b) ensuring all workers are provided with
and use Personal Protective Equipment; (c) H and S Training
for all site personnel; (d) documented procedures to be
followed for all site activities; and (e) documentation of work-
related accidents;
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible throughout
the site;
(iii) Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not exposed
to hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work at
the site, personal protective protection, and preventing injuring
to fellow workers;
(viii) Ensure moving equipment is outfitted with audible back-
up alarms;
(xii) Disallow worker exposure to noise level greater than 85
PartiallyCompl
ied
Site-specific Health and Safety Plan has
been prepared and communicated to
contractor and being followed at site
PPE are being used completely in some
sites
First-aid facility has been provided at
each site
Group insurance has been provided to
workers
Drinking water has been provided at all
sites
H&S training is being provided to
workers by DSC regularly
Sign board are not provided at some
sites
Workers are not exposed to high noise
for 8 hours
Contractor has been
instructed complete
compliance of measures
specified in EMP
Provide sign boards in all
working sites with name and
contact numbers of the
concerned site engineers of
IPIU, DSC and contractors
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 98
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
dBA for a duration of more than 8 hours per day without
hearing protection. The use of hearing protection shall be
enforced actively.
10 Work Camps
(i) Provide water and sanitation facilities for employees;
(iii) Prohibit employees from poaching wildlife and cutting of
trees for firewood;
(iii) Remove all wreckage, rubbish, or temporary structures; and
(ix) Request IPIU/DSC to report in writing that the camp has
been vacated and restored to pre-project conditions before
acceptance of work.
Not Complied
Temporary workers camps are
established in STP site which is not
having basic facilities like drinking
water, sanitation, solid waste
management etc
Provide appropriate workers
camp with all the basic
facilities
Contractor
Table 19: Compliance of EMP for Rajsamand Waste Water sub-project {RUSDIP/TR-02/RSM/WW/03}
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
PRECONSTRUCTION STAGE
1 Environmental Clearances
Site preparation work completed by IPIU including necessary
clearance
Consent to Establish under Water (Prevention and Control of
Pollution) Act
Consent to Establish under Air (Prevention and Control of
Pollution) Act
Tree-cutting Permit
Complied
Consent to Establish is obtained for
construction of STP and renewed which is
valid till 30/04/2018.
Tree cutting is done by forest department
after deposition of appropriate fees to
forest department
,Application for CTO is applied
on 25.05.2017
DSC/ IPIU
2 Social and Cultural Resources Complied It was confirmed by consultations with Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 99
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(i) Consult Archaeological Survey of India (ASI) to obtain an expert
assessment of the archaeological potential of the site;
(ii) Consider alternatives if the site is found to be of medium or
high risk;
(iii) Include state and local archaeological, cultural and historical
authorities, and interest groups in consultation forums as project
stakeholders so that their expertise can be made available; and
(iv) Develop a protocol for use by the construction contractors in
conducting any excavation work, to ensure that any chance finds
are 99hysic99ize and measures are taken to ensure they are
protected and conserved.
various stakeholders that the sites have
no archaeological potential.
3 Construction work camps, hot mix plants, stockpile areas,
storage areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant space in the
subproject sites;
(ii) If it is deemed necessary to locate elsewhere, consider sites
that will not promote instability and result in destruction of
property, vegetation, irrigation, and drinking water supply
systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct disposal to
water body or in areas which will inconvenience the community.
Complied
All the facilities related to construction
are located within project site at STP and
other site away from residential areas
without any impact on property,
vegetation, irrigation, and drinking water
supply systems
Nil DSC/ IPIU
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining Department;
(ii) If other sites are necessary, inform construction contractor
that it is their responsibility to verify the suitability of all material
sources and to obtain the approval of IPIU; and
(iii) If additional quarries will be required after construction is
started, inform construction contractor to obtain a written
approval from IPMU.
Complied
All the material is being taken from
approved mines
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 100
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
CONSTRUCTION STAGE
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain approval of
Investment Program Implementation Unit ( IPIU);
(iii) If additional quarries will be required after construction has
started, obtain written approval from PMU; and;
(iv) Submit to DSC on a monthly basis documentation of sources
of materials.
Complied
All the material is being taken from
government approved quarry sites
Nil DSC/ IPIU
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for stockpiling
of clay, soils, gravel, and other construction materials;
(ii) Damp down exposed soil and any stockpiled on site by
spraying with water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material when
transported by trucks; and
(iv) Fit all heavy equipment and machinery with air pollution
control devices which are operating correctly.
Partially
Complied
All the stockpiling is done at project area
only.
No dust problem noticed at sites
Air quality monitoring is pending, though
work order for monitoring works is given
to monitoring agency.
IPIU needs to complete
environmental monitoring at
the earliest
Contractor/ DSC/
IPIU
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the monsoon
season unless covered by tarpaulins or plastic sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins along the
drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from any
drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities in
designated sites; and
NA
No surface water source near the work
sites
Ground water quality monitoring need to
be conducted.
Monitoring to be conducted Contractor/ DSC/
IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 101
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that activities
with the greatest potential to generate noise are conducted
during periods of the day which will result in least disturbance;
(ii) Require horns not be used unless it is necessary to warn other
oad use s o a i als of the ehi le s app oach;
(iii) Minimize noise from construction equipment by using vehicle
silencers, fitting jackhammers with noise-reducing mufflers, and
portable street barriers the sound impact to surrounding sensitive
receptor; and
(iv) Maintain maximum sound levels not exceeding 80 decibels
(dbA) when measured at a distance of 10 m or more from the
vehicle/s.
Partially
Complied
Activities with the greatest potential to
generate noise have been planned in
consultation with IPIU and are being
conducted in day time only
Noise monitoring is pending though work
order for environmental monitoring is
issued to monitoring agency
Construction equipment being used are
having silencers except concrete mixtures
which are not having enclosures and
create noise during operation
Concrete mixtures are required
to have enclosure to reduce
noise
IPIU needs to complete
environmental monitoring at
the earliest
Contractor/ DSC/
IPIU
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(iii) Coordinate with Municipal Board for beneficial uses of excess
excavated soils or immediately dispose to designated areas;
(iv) Recover used oil and lubricants and reuse or remove from the
sites;
(v) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
Complied
The excavated soil is kept for reuse
whereas unusable extra excavated
materials and over burdens are being
disposed at low laying areas with proper
permission of concerned authorities
Nil Contractor/ DSC/
IPIU
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not use
narrow local roads, except in the immediate vicinity of delivery
sites;
(ii) Schedule transport and hauling activities during non-peak
Complied
Heavy vehicles traverse in non peak
hours through designated routes
Vehicle entry permission is being taken
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 102
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
hours;
(iii) Coordinate with Municipal Traffic Office for temporary road
diversions and with for provision of traffic aids if transportation
activities cannot be avoided during peak hours;
from traffic authority
Nearby community and residents are
being informed prior to start of work and
project information boards are also
displayed at prominent sites
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment, hospitals,
and schools;
(iv) Consult businesses and institutions regarding operating hours
and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
Complied
Walkways and access is provided to
shops and residence where possible
otherwise route diversion is done
Sufficient work force is deployed to finish
the works quickly
Nil DSC/ IPIU
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the maximum
extent, local persons within the 2-km immediate area if
manpower is available; and
(ii) Secure construction materials from local market.
Complied
Most of the unskilled labor are hired
from local people
Construction materials being procured
from local market where possible
Nil DSC/ IPIU
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H and
S) Plan which will include measures such as: (a) excluding public
from the site; (b) ensuring all workers are provided with and use
Personal Protective Equipment; (c) H and S Training for all site
personnel; (d) documented procedures to be followed for all site
activities; and (e) documentation of work-related accidents;
complied
Contractor is following EMP prepared for
the project
First-aid box is available at site
Group insurance has been provided to
workers
Contractor has been instructed
for complete compliance of
measures specified in EMP
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 103
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible throughout
the site;
Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not exposed to
hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work at the
site, personal protective protection, and preventing injuring to
fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or substances may be
present. Ensure also that visitor/s do not enter hazard areas
unescorted;
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-up
alarms;
(xi) Mark and provide sign boards for hazardous areas such as
energized electrical devices and lines, service rooms housing high
voltage equipment, and areas for storage and disposal. Signage
shall be in accordance with international standards and be well
known to, and easily understood by workers, visitors, and the
general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85 dBA
for a duration of more than 8 hours per day without hearing
Proper barricading for unauthorized
intrusion has been provided at all sites
Drinking water has been provided at sites
Training for health and safety measures
have been given to contractor by DSC.
Workers are not exposed to high noise
level more than 8 hrs
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 104
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
protection. The use of hearing protection shall be enforced
actively.
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices, sheds,
and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of trees;
Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting of trees
for firewood;
(v) Train employees in the storage and handling of materials
which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove from the
site;
(vii) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures (such
as buildings, shelters, and latrines) which are no longer required;
Complied
At present most of the workers
employed are local.
Contractor has been instructed to
p o ide ade uate fa ilities i o ke s camp.
Provide all the basic facilities in
workers camp
Contractor
Table 20: Compliance of EMP for Jhalawar Waste Water sub-project {RUSDIP/TR-02/JHL/WW/02}
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
PRECONSTRUCTION STAGE
1 Environmental Clearances
Site preparation work completed by IPIU including necessary
clearance
Complied
All the site preparation works completed
including necessary clearances and sites are
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 105
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
Consent to Establish under Water (Prevention and Control of
Pollution) Act
Consent to Establish under Air (Prevention and Control of
Pollution) Act
Tree-cutting Permit
handed over to contractor
Tree cutting is not anticipated presently.
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain an
expert assessment of the archaeological potential of the site;
(ii) Consider alternatives if the site is found to be of medium or
high risk;
(iii) Include state and local archaeological, cultural and historical
authorities, and interest groups in consultation forums as
project stakeholders so that their expertise can be made
available; and
(iv) Develop a protocol for use by the construction contractors in
conducting any excavation work, to ensure that any chance finds
are 105hysic105ize and measures are taken to ensure they are
protected and conserved.
Complied
It was confirmed by consultations with
various stakeholders that the site has no
archaeological potential
Instruction has been given to the contractor
to ensure that any chance finds are
recognized and measures are taken to
ensure they are protected and conserved
No such occurrence till date
Report if any chance find is
found during excavation
works
Contractor/ DSC/
IPIU
3 Construction work camps, hot mix plants, stockpile areas,
storage areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant space in the
subproject sites;
(ii) If it is deemed necessary to locate elsewhere, consider sites
that will not promote instability and result in destruction of
property, vegetation, irrigation, and drinking water supply
systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct disposal
to water body or in areas which will inconvenience the
community.
Partially
Complied
Construction work camps and hot mix
plants are not present for this project.
Storage and stockpile areas will not affect
any vegetation and drinking water supply
systems
Disposal area is identified by Nagar Parishad
Take prior written
permission from land owner
to any stockpile and storage
area in private place,
Avoid storage and stockpile
areas in or near habitations
Rehabilitate the stockpile
and storage areas up to the
previous conditions, used for
construction works
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 106
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining Department;
(ii) If other sites are necessary, inform construction contractor
that it is their responsibility to verify the suitability of all material
sources and to obtain the approval of IPIU; and
(iii) If additional quarries will be required after construction is
started, inform construction contractor to obtain a written
approval from IPMU.
Complied
All the material is being taken from
approved mines
Nil DSC/ IPIU
CONSTRUCTION STAGE
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain approval
of Investment Program Implementation Unit ( IPIU);
(iii) If additional quarries will be required after construction has
started, obtain written approval from PMU; and;
(iv) Submit to DSC on a monthly basis documentation of sources
of materials.
Complied
All the material is being taken from
government approved quarry sites
Nil DSC/ IPIU
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for stockpiling
of clay, soils, gravel, and other construction materials;
(ii) Damp down exposed soil and any stockpiled on site by
spraying with water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material when
transported by trucks; and
(iv) Fit all heavy equipment and machinery with air pollution
control devices which are operating correctly.
Partially
Complied
No dust problems noticed at work sites
PUCs of equipment is not available with
contractors
Air quality monitoring has not been
conducted during reporting period
though work order issued to monitoring
agency.
Instruction has been given to
contractor to submit PUCs of
all vehicles being used
Contractor / DSC/
IPIU
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the monsoon
season unless covered by tarpaulins or plastic sheets;
Complied
Excavated soil is being reused for
backfilling after pipe laying and Excess
soil is being disposed in designated areas
Dispose any wastes generated
by construction activities in
Contractor / DSC/
IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 107
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins along the
drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from any
drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities in
designated sites; and
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
for leveling the low lying areas no need
to store the soil
Proper disposal of dewatered water is
being done in existing drains
No surface water source exist near to
existing sites
designated sites
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that activities
with the greatest potential to generate noise are conducted
during periods of the day which will result in least disturbance;
(ii) Require horns not be used unless it is necessary to warn
othe oad use s o a i als of the ehi le s app oa h; (iii) Minimize noise from construction equipment by using
vehicle silencers, fitting jackhammers with noise-reducing
mufflers, and portable street barriers the sound impact to
surrounding sensitive receptor; and
(iv) Maintain maximum sound levels not exceeding 80 decibels
(dbA) when measured at a distance of 10 m or more from the
vehicle/s.
Partially
Complied
Activities with the greatest potential to
generate noise have been planned in
consultation with IPIU and are being
conducted in day time
Noise monitoring has notbeen
conducted for reporting period though
work order issued to monitoring agency.
Nil
Ensure environmental
monitoring at the earliest
Contractor/ DSC/
IPIU
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(iii) Coordinate with Municipal Board for beneficial uses of
excess excavated soils or immediately dispose to designated
areas;
Complied
Overburden and excavated materials
from construction sites has been reused
for backfilling and excess material has
been disposed to areas designated by
Nagar Parishad.
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 108
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(iv) Recover used oil and lubricants and reuse or remove from
the sites;
(v) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not use
narrow local roads, except in the immediate vicinity of delivery
sites;
(ii) Schedule transport and hauling activities during non-peak
hours;
(iii) Coordinate with Municipal Traffic Office for temporary road
diversions and with for provision of traffic aids if transportation
activities cannot be avoided during peak hours;
Complied
The vehicles carrying materials to the
work site follow only designated route to
the site
sign boards informing nature and
duration of construction works and
contact numbers for
concerns/complaints has been provided
Temporary road diversion is being done
with consultation of municipal
authorities for non peak hours with
proper indication and boards
Nil DSC/ IPIU
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment, hospitals,
and schools;
(iv) Consult businesses and institutions regarding operating
hours and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
Complied
Excavated trenches are being back filled
immediate after the laying of pipes.
Significant work force has been provided
to finish the works quickly near sensitive
receptors
Nil DSC/ IPIU
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the maximum
extent, local persons within the 2-km immediate area if
Complied
At present most of the workforce is hired
locally
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 109
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
manpower is available; and
(ii) Secure construction materials from local market.
Construction materials are being secured
from local markets if available
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H and
S) Plan which will include measures such as: (a) excluding public
from the site; (b) ensuring all workers are provided with and use
Personal Protective Equipment; (c) H and S Training for all site
personnel; (d) documented procedures to be followed for all site
activities; and (e) documentation of work-related accidents;
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible throughout
the site;
Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not exposed to
hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work at
the site, personal protective protection, and preventing injuring
to fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or substances may
be present. Ensure also that visitor/s do not enter hazard areas
unescorted;
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-up
Partially
complied
Contractor has provided site-specific
Health and Safety Plan but following the
EMP given in IEE
PPEs are not being used completely
during works
First-aid facility has been provided at
each site
Group insurance has been provided to
workers
Drinking water has been provided at all
sites
H&S training is being provided to
workers by DSC and CAPP regularly
Back-up alarms are not provided in
moving equipment
Sign board are provided at all sites
Workers are not exposed to high noise
for 8 hours
Contractor has not deputed HSE
personnel
Contractor has been instructed
complete compliance of
measure specified in EMP
Contractor is also instructed to
depute HSE personnel to look
after the EMP issues
Ensure proper use of PPEs
during construction works
Provide back-up alarms in all
moving equipments
Contractor, IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 110
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
alarms;
(xi) Mark and provide sign boards for hazardous areas such as
energized electrical devices and lines, service rooms housing
high voltage equipment, and areas for storage and disposal.
Signage shall be in accordance with international standards and
be well known to, and easily understood by workers, visitors,
and the general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85 dBA
for a duration of more than 8 hours per day without hearing
protection. The use of hearing protection shall be enforced
actively.
10 Work Camps
(i)Consult with IPIU/DSC before locating project offices, sheds,
and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of trees;
Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting of
trees for firewood;
(v) Train employees in the storage and handling of materials
which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove from
the site;
(vii) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures
(such as buildings, shelters, and latrines) which are no longer
required;
Complied
At present most of the workers
employed are local.
Contractor has taken rental rooms for
workers and staff, most of the labors are
local and no camp is established in site
Nil Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 111
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
EMR for Tranche-03 Sub Projects Table 21: EMP Compliance Status of Karauli Waste Water Subproject {RUSDIP/TR-03/KRL/WW/04 & WW/05}
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
PRECONSTRUCTIONSTAGE
1 Environmental Clearances
(i) Site preparation works completed by IPIU including
necessary clearances
(ii) Consent to Establish under Water (Prevention and Control
of Pollution) Act
(iii) Consent to Establish under Air (Prevention and Control of
Pollution) Act
(iv) Tree-cutting Permit
Complied
Consent to Establish for 5 MLD
capacity sewage Treatment Plant has
been obtained from pollution control
board. CTE validity was upto 31.03.2015
Renewal of CTE for construction period is
under process with RSPCB.
Work stopped as contractor terminated
Consent to operate for STP is required
before operation
Permission for tree cutting is not
required
CTE renewal is under process
with RSPCB. Deficiency letter
issued dated 15/07/2016.The
same is under process.
DSC/ IPIU
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain an
expert assessment of the archaeological potential of the site;
(ii) Consider alternatives if the site is found to be of medium
or high risk;
(iii) Include state and local archaeological, cultural and
historical authorities, and interest groups in consultation forums as
project stakeholders so that their expertise can be made available;
and
(iv) Develop a protocol for use by the construction contractors
in conducting any excavation work, to ensure that any chance finds
are recognized and measures are taken to ensure they are
protected and conserved.
Complied
It was confirmed by consultations with
various stakeholders that the site has no
archaeological potential
Instruction has been given to the
contractor to ensure that any chance
finds are recognized and measures are
taken to ensure they are protected and
conserved
No such occurrence till date
Nil DSC/ IPIU
3 Construction work camps, hot mix plants, stockpile areas,
storage areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant space in
Complied
All the facilities related to
construction are located within
project site
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 112
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
the sub-project sites;
(ii) If it is deemed necessary to locate elsewhere, consider
sites that will not promote instability and result in destruction of
property, vegetation, irrigation, and drinking water supply systems;
(iii) Do not consider residential areas; and
(iv) Take extreme care in selecting sites to avoid direct
disposal to water body or in areas, which will inconvenience the
community.
No hot mix plant established for the
package.
Proper care has been taken to safeguard
property, vegetation, irrigation &
drinking water supply systems.
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining
Department;
(ii) If other sites are necessary, inform construction
contractor that it is their responsibility to verify the suitability of
all material sources and to obtain the approval of IPIU; and
(iii) If additional quarries will be required after construction is
started, inform construction contractor to obtain a written
approval from IPMU.
Complied
All the material is being taken from
government approved mines.
Nil DSC/ IPIU
CONSTRUCTIONSTAGE
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain
approval of Investment Program Implementation Unit ( IPIU);
(iii) If additional quarries will be required after construction
has started, obtain written approval from PMU; and
(iv) Submit documentation of sources of materials to DSC on
a monthly basis.
Complied
All the material is being taken from
government approved quarry sites
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 113
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for
stockpiling of clay, soils, gravel, and other construction materials;
(ii) Damp down exposed soil and any stockpiled on site by
spraying of water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material
when transported by trucks; and
(iv) Fit all heavy equipments and machineries with air
pollution control devices which are operating correctly.
Complied
Construction materials have been
stockpiled at designated areas in
consultation with IPIU.
Water sprinkling is done as required
especially during dry season.
Since work has been stopped as
contractor was terminated monitoring is
not required to be carried out in the
reporting period.
Nil
DSC/
IPIU/Contractor
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the
monsoon season unless covered by tarpaulins or plastic sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with IPIU/DSC
on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins along
the drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from any
drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities
in designated sites; and
(vi) Conduct surface water quality inspection according to the
Environmental Management Plan (EMP).
Complied
Excess material is removed
regularly
Surface water& ground waterquality
monitoringwas conducted during last
reporting period.
Since work has been stopped as
contractor was terminated monitoring is
not required to be carried out in the
reporting period.
Nil DSC/
IPIU/Contractor
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that
activities with the greatest potential to generate noise are
conducted during periods of the day which will result in least
disturbance;
Activities with the greatest potential to
generate noise have been planned in
consultation with IPIU and are being
conducted in day time.
Construction equipment are properly
Nil
DSC/
IPIU/Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 114
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
(ii) Require horns not be used unless it is necessary to warn
othe oad use s o a i als of the ehi le s app oa h; (iii) Minimize noise from construction equipments by using
vehicle silencers, fitting jackhammers with noise-reducing mufflers,
and portable street barriers the sound impact to surrounding
sensitive receptor; and
(iv) Maintain maximum sound levels not exceeding 80
decibels (dbA) when measured at a distance of 10 m or more from
the vehicle/s.
Complied maintained by contractor to minimize
the noise.
Generator sets and concrete mixtures
are provided with acoustic
enclosures.
Since work has been stopped as
contractor was terminated monitoring is
not required to be carried out in the
reporting period.
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(iii) Coordinate with Municipal Board for beneficial uses of
excess excavated soils or immediately dispose to designated areas;
(iv) Recover used oil and lubricants and reuse or remove from
the sites;
(v) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas; and
(vi) Remove all wreckage, rubbish, or temporary structures
(such as buildings, shelters, and latrines) which are no longer
required.
Complied Overburden and excavated
materials from construction sites has
been reused for backfilling and excess
material has been disposed to
designated areas
Nil DSC/
IPIU/Contractor
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not
use narrow local roads, except in the immediate vicinity of delivery
sites;
(ii) Schedule transport and hauling activities during non-peak
hours;
(iii) Locate entry and exit points in areas where there is low
potential for traffic congestion;
Complied
Traffic diversions will be provided at
necessary points as per
requirement
Traffic diversions for short time have
been provided where required
Nil IPIU/Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 115
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
(iv) Keep the site free from all unnecessary obstructions;
(v) Coordinate with Municipal Traffic Office for temporary
road diversions and with for provision of traffic aids, if
transportation activities cannot be avoided during peak hours; and
(vi) Notify affected sensitive receptors by providing sign
boards informing nature and duration of construction works and
contact numbers for concerns/complaints.
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets wherever required to
maintain access across trenches for people and vehicles;
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment, hospitals,
and schools;
(iv) Consult businesses and institutions regarding operating
hours and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
Complied
Easy access is available at most of
The places.
Nil DSC/ IPIU
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the
maximum extent, local persons within the 2 km immediate area, if
manpower is available; and
(ii) Secure construction materials from local market.
Complied
At present most of the work force is
Hiredlocally
Nil DSC/ IPIU
9 (i) OccupationalHealthandSafety
(ii) Develop and implement site-specific Health and Safety (H
and S) Plan which will include measures such as: (a) excluding
public from the site; (b) ensuring all workers are provided with and
use Personal Protective Equipments; (c) H and S Training for all
Partially
Reasonable use of PPEobserved
First-aid boxis available at site
Group insurance has been provided to
workers
Ensure complete safety
compliance of EMP in
terms of using PPEs by
workers at site to avoid
undesirable incidents.
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 116
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
site personnel; (d) documented procedures to be followed for all
site activities; and (e) documentation of work-related accidents;
(iii) Ensure that qualified first-aid is provided at all times.
Equipped first-aid stations shall be easily accessible throughout the
site;
(iv) Provide medical insurance coverage for workers;
(v) Secure all installations from unauthorized intrusion and
accident risks;
(vi) Provide supplies of potable drinking water;
(vii) Provide clean eating areas where workers are not exposed
to hazardous or noxious substances;
(viii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work at the
site, personal protective protection, and preventing injuring to
fellow workers;
(ix) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or substances may be
present. Ensure also that visitor/s do not enter hazard areas
unescorted;
(x) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
(xi) Ensure moving equipment is outfitted with audible back-
up alarms;
(xii) Mark and provide sign boards for hazardous areas such as
energized electrical devices and lines, service rooms housing high
voltage equipment, and areas for storage and disposal. Signage
shall be in accordance with international standards and be well
known to, and easily understood by workers, visitors, and the
complied
Proper barricading for unauthorized
intrusion has been provided except few
stretches of pipe laying areas. But at
few places barricading is partially
provided.
Drinking water has been provided at
sites
Training for health and safety measures
have been given to contractor by DSC.
Workers are not exposed to high noise
level more than 8hrs
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 117
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
general public as appropriate; and
(xiii) Disallow worker exposure to noise level greater than 85
dBA for duration of more than 8 hours per day without hearing
protection. The use of hearing protection shall be enforced
actively.
10 WorkCamps
(i) Consult with IPIU/DSC before locating project offices,
sheds, and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of
trees;
(iii) Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting of
trees for firewood;
(v) Train employees in the storage and handling of materials
which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove from
the site;
(vii) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures
(such as buildings, shelters, and latrines) which are no longer
required; and Request IPIU/DSC to report in writing that the camp
has been vacated and restored to pre-project conditions before
acceptance of work.
Complied
The contractor has established a
Small labor camp near STP site.
Contractor has now provided all
required facilities to the labor in the
camp.
2 nos.of toilets with proper septic tank
has been developed for labor in
reporting period
Proper drainage system has been
developed
Proper Housekeeping observed
Nil Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 118
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Table 22: EMP Compliance Status of Bharatpur Waste Water Subproject {RUSDIP/TR-03/BPR/WW/01 (Lot 1) & (Lot 2)}
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
PRECONSTRUCTIONSTAGE
1 Environmental Clearances
Site preparation work completed by IPIU including necessary
clearance
Consent to Establish under Water (Prevention and Control of
Pollution) Act
Consent to Establish under Air (Prevention and Control of Pollution)
Act
Tree-cutting Permit
Complied
Consent to establish from Pollution
Control Board has been obtained for 8
MLD STP. Validity of consent is up to
30.11.14.
Consent to establish has been
renewed and valid upto 30.11.2017.
Removal of tree is not required
Consent to Operate is required to be
applied before operation.
Nil DSC/ IPIU
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain an expert
assessment of the archaeological potential of the site;
(ii) Consider alternatives if the site is found to be of medium or high
risk;
(iii) Include state and local archaeological, cultural and historical
authorities, and interest groups in consultation forums as project
stakeholders so that their expertise can be made available; and
(iv) Develop a protocol for use by the construction contractors in
conducting any excavation work, to ensure that any chance finds
are recognised and measures are taken to ensure they are
protected and conserved.
Complied It was confirmed by consultations with
various stakeholders that the site has
no archaeological potential
Instruction has been given to the
contractor to ensure that any chance
finds are recognized and measures are
taken to ensure they are protected and
conserved
No such occurrence till date
Nil
DSC/ IPIU
3 Construction work camps, hot mix plants, stockpile areas, storage
areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant space in the
subproject sites;
(ii) If it is deemed necessary to locate elsewhere, consider sites that
Complied All the facilities related to
construction are located
within project site
No hot mix plant established for the
Nil IPIU/Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 119
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
will not promote instability and result in destruction of property,
vegetation, irrigation, and drinking water supply systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct disposal to
water body or in areas which will inconvenience the community.
package.
Proper care has been taken to
safeguard property, vegetation,
irrigation & drinking water supply
systems.
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining Department;
(ii) If other sites are necessary, inform construction contractor that
it is their responsibility to verify the suitability of all material
sources and to obtain the approval of IPIU; and
(iii) If additional quarries will be required after construction is
started, inform construction contractor to obtain a written approval
from IPMU.
Complied All the material is being taken from
approved mines
Nil IPIU/Contractor
CONSTRUCTIONSTAGE
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain approval of
Investment Program Implementation Unit ( IPIU);
(iii) If additional quarries will be required after construction has
started, obtain written approval from PMU; and;
(iv) Submit to DSC on a monthly basis documentation of sources of
materials.
Complied All the material is being taken from
approved quarry sites.
Nil IPIU/Contractor
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for stockpiling of
clay, soils, gravel, and other construction materials;
(ii) Damp down exposed soil and any stockpiled on site by spraying
with water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material when
transported by trucks; and
(iv) Fit all heavy equipment and machinery with air pollution control
devices which are operating correctly.
Complied Sprinkling of water is being done as
and when required
Civil work is completd therefore
monitoring was not required.
Construction materials have been
stockpiled at designated areas in
consultation with IPIU.
Nil DSC/
IPIU/Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 120
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the monsoon
season unless covered by tarpaulins or plastic sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with IPIU/DSC
on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins along the
drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from any
drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities in
designated sites; and
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
Complied Excess excavated soils is being
Reused or disposed on designated
disposal areas in consultation with
IPIU/DSC
Excess excavated soils isbeing used
for leveling of edges in Circular road
subproject
Nil. DSC/
IPIU/Contractor
Surface water quality monitoring is not
required as there is no surface water
body near sub-project area.
Ground water quality monitoring has
been conducted in this reporting
period.
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that activities
with the greatest potential to generate noise are conducted during
periods of the day which will result in least disturbance;
(ii) Require horns not be used unless it is necessary to warn other
oad use s o a i als of the ehi le s app oa h; (iii) Minimize noise from construction equipment by using vehicle
silencers, fitting jackhammers with noise-reducing mufflers, and
portable street barriers the sound impact to surrounding sensitive
receptor; and
(iv) Maintain maximum sound levels not exceeding 80 decibels
(dbA) when measured at a distance of 10 m or more from the
vehicle/s.
complied Enclosure has been provided at
Noise producing machinery
Maintenance of noise producing
machinery is observed
Civil work is completd therefore
monitoring is not required.
Nil DSC/
IPIU/Contractor
5 Landscape and Aesthetics
Complied Overburden and excavated Nil IPIU/Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 121
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(ii) Coordinate with Municipal Board for beneficial uses of excess
excavated soils or immediately dispose to designated areas;
(iv) Recover used oil and lubricants and reuse or remove from the
sites;
(v) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
materials from construction sites
has been reused for backfilling and
excess material has been disposed
to designated areas
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not use
narrow local roads, except in the immediate vicinity of delivery
sites;
(ii) Schedule transport and hauling activities during non-peak hours;
(iii) Coordinate with Municipal Traffic Office for temporary road
diversions and with for provision of traffic aids if transportation
activities cannot be avoided during peak hours;
Complied
Traffic diversions will be provided at
necessary points as per
requirement
Traffic diversions for short time
have been provided where required
Nil IPIU/Contractor
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to maintain
access across trenches for people and vehicles;
(iii) Increase workforce in front of critical areas such as institutions,
place of worship, business establishment, hospitals, and schools;
(iv) Consult businesses and institutions regarding operating hours
and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
Complied Temporary access at few places
hasbeenprovided
Signboards has been provided of
informing nature and duration of
construction worksandcontact
numbers for concerns/complaints
Nil DSC/ IPIU
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the maximum
extent, local persons within the 2-km immediate area if manpower
Complied At present most of the work force
is hired locally which is more than
50%.
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 122
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
is available; and
(ii) Secure construction materials from local market.
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H and S)
Plan which will include measures such as: (a) excluding public from
the site; (b) ensuring all workers are provided with and use
Personal Protective Equipment; (c) H and S Training for all site
personnel; (d) documented procedures to be followed for all site
activities; and (e) documentation of work-related accidents;
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible throughout the
site;
(iii) Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not exposed to
hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work at the
site, personal protective protection, and preventing injuring to
fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain access
to areas where hazardous conditions or substances may be present.
Ensure also that visitor/s do not enter hazard areas unescorted;
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-up
alarms;
(xi) Mark and provide sign boards for hazardous areas such as
Partially
complied
PPE are beingused on site.
First-aid has been provided but
not adequate
Group insurance has been
provided toworkers
Drinkingwater has been provided
at all sites
H&S training is being provided to
workers by DSC regularly
Contractor has instructed
tofollowEMP
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 123
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
energized electrical devices and lines, service rooms housing high
voltage equipment, and areas for storage and disposal. Signage
shall be in accordance with international standards and be well
known to, and easily understood by workers, visitors, and the
general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85 dBA
for a duration of more than 8 hours per day without hearing
protection. The use of hearing protection shall be enforced actively.
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices, sheds, and
construction plants;
(ii) Minimize removal of vegetation and disallow cutting of trees;
(iii) Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting of trees
for firewood;
(v) Train employees in the storage and handling of materials which
can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove from the
site;
(vii) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures (such
as buildings, shelters, and latrines) which are no longer required;
and
(ix) Request IPIU/DSC to report in writing that the camp has been
vacated and restored to pre-project conditions before acceptance
of work.
Partially
Complied
Contractor has established a labor
camp at STP site (WW/01/Lot-2
package)recently
Toilets and septictank are being
constructed
Cooking gas/ fuel has not yet
provided to the labor by contractor
Housekeeping require improvement
Adequate first aid has been provided
Contractor has been
instructed to maintain proper
housekeeping.
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 124
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Table 23:EMP Compliance Status of Jaisalmer Waste Water subproject {RUSDIP/TR-03/JSL/WW/06}
Sr.
No.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
1 Environmental Clearances (i) Site preparation work completed by IPIU including
necessary clearance
(ii) Consent to Establish under Water (Prevention and
Control of Pollution) Act
(iii) Consent to Establish under Air (Prevention and Control
of Pollution) Act
(iv) Tree-cutting Permit
Complied
Consent to Establish is not required
Tree cutting is not required
Nil DSC/ IPIU
2 Social and Cultural Resources (i) Consult Archaeological Survey of India (ASI) to obtain
an expert assessment of the archaeological potential of the
site;
(ii) Consider alternatives if the site is found to be of
medium or high risk;
(iii) Include state and local archaeological, cultural and
historical authorities, and interest groups in consultation
forums as project stakeholders so that their expertise can be
made available; and
(iv) Develop a protocol for use by the construction
contractors in conducting any excavation work, to ensure that
any chance finds are recognised and measures are taken to
ensure they are protected and conserved.
Complied Permission from Archaeological
Survey of India is obtained for this
particular Sub Project.
It was confirmed by consultations
with various stakeholders that the
site has no archaeological
potential
Instruction has been given to the
contractor to ensure that any
chance finds are recognized and
measures are taken to ensure they
are protected and conserved
The work shall be
executed under in the
consultation with S.A.
Jaipur, Jaipur Circle,
Jaipur. However, codal
formalities as required
under the Ancient
monuments and
Archaeological Sites and
remains (Amendment &
Validation) Act. 2010, may
be followed while
execution of work.
IPIU
3 Construction work camps, hot mix plants, stockpile areas,
storage areas, and disposal areas (i) Prioritize areas within or nearest possible vacant space
in the subproject sites;
(ii) If it is deemed necessary to locate elsewhere, consider
sites that will not promote instability and result in destruction
of property, vegetation, irrigation, and drinking water supply
systems;
Complied All the facilities related to
construction are located within
project site
Nil IPIU/ Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 125
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct
disposal to water body or in areas which will inconvenience the
community.
4 Sources of Materials (i) Prioritize sites already permitted by the Mining
Department;
(ii) If other sites are necessary, inform construction
contractor that it is their responsibility to verify the suitability
of all material sources and to obtain the approval of IPIU; and
(iii) If additional quarries will be required after construction
is started, inform construction contractor to obtain a written
approval from IPMU.
Complied All the material is being taken from
approved mines
Nil IPIU/ Contractor
Construction Stage
1 Sources of Materials (i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain
approval of Investment Program Implementation Unit (IPIU);
(iii) If additional quarries will be required after
construction has started, obtain written approval from PMU;
and;
(iv) Submit to DSC on a monthly basis documentation of
sources of materials.
Complied All the material is being taken from
government approved quarry sites
Nil IPIU/ Contractor
2 Air Quality (i) Consult with IPIU/DSC on the designated areas for
stockpiling of clay, soils, gravel, and other construction
materials;
(ii) Damp down exposed soil and any stockpiled on site by
spraying with water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material
when transported by trucks; and
(iv) Fit all heavy equipment and machinery with air
pollution control devices which are operating correctly.
Partially
complied
Adequate sprinkling of water is
required for arresting fugitive dust
Air quality monitoring has not been
conducted during report period as
the civil work is almost at
completion stage.
Adequate watering is
done at work site
Instruction has been
given to contractor to
use tarpaulins to cover
fine material when
transported.
Regularly by
IPIU/ Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 126
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the
monsoon season unless covered by tarpaulins or plastic sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins
along the drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from
any drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities
in designated sites; and
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
Complied Surface water quality monitoring
has not been conducted during
report period
Ground water level is very low
therefore ground water quality
monitoring is not required.
No surface water is
available near the project
site
IPIU/ Contractor
4 Noise Levels (i) Plan activities in consultation with IPIU/DSC so that
activities with the greatest potential to generate noise are
conducted during periods of the day which will result in least
disturbance;
(ii) Require horns not be used unless it is necessary to
a othe oad use s o a i als of the ehi le s approach;
(iii) Minimize noise from construction equipment by using
vehicle silencers, fitting jackhammers with noise-reducing
mufflers, and portable street barriers the sound impact to
surrounding sensitive receptor; and
(iv) Maintain maximum sound levels not exceeding 80
decibels (dbA) when measured at a distance of 10 m or more
from the vehicle/s.
Partially
Complied
Activities with the greatest potential
to generate noise have been
planned in consultation with IPIU
and are being conducted in day time
Noise monitoring has not been
conducted in this reporting period
as the civil work is completed.
Nil IPIU/ DSC
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(iii) Coordinate with Municipal Board for beneficial uses of
excess excavated soils or immediately dispose to designated
areas;
(iv) Recover used oil and lubricants and reuse or remove
Complied The unusable extra excavated
materials and over burdens are
being disposed at low laying area as
per direction of ULB of Jaisalmer
town
Nil IPIU/ Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 127
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
from the sites;
(v) Manage solid waste according to the following
preference hierarchy: reuse, recycling and disposal to designated
areas;
(vi) Remove all wreckage, rubbish, or temporary structures
(such as buildings, shelters, and latrines) which are no longer
required; and
(vii) Request IPIU/DSC to report in writing that the
necessary environmental restoration work has been adequately
performed before acceptance of work.
6 Accessibility (i) Plan transportation routes so that heavy vehicles do
not use narrow local roads, except in the immediate vicinity of
delivery sites;
(ii) Schedule transport and hauling activities during non-
peak hours;
(iii) Locate entry and exit points in areas where there is
low potential for traffic congestion;
(iv) Keep the site free from all unnecessary obstructions;
(v) Coordinate with Municipal Traffic Office for temporary
road diversions and with for provision of traffic aids if
transportation activities cannot be avoided during peak hours;
and
(vi) Notify affected sensitive receptors by providing sign
boards informing nature and duration of construction works and
contact numbers for concerns/complaints
Complied The trucks carrying materials to the
work site follow only designated
route to the site
Sign boards informing nature and
duration of construction works and
contact numbers for
concerns/complaints has been
provided
Nil IPIU/ Contractor
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment, hospitals,
and schools;
(iv) Consult businesses and institutions regarding operating
hours and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature
Complied Proper access across trenches for
people and vehicles has been
provided
Nil IPIU/ Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 128
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
and duration of construction works and contact numbers for
concerns/complaints.
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the maximum
extent, local persons within the 2-km immediate area if
manpower is available; and
(ii) Secure construction materials from local market.
Complied At present most of the workforce is
hired locally
Nil IPIU/ Contractor
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H
and S) Plan which will include measures such as: (a) excluding
public from the site; (b) ensuring all workers are provided with
and use Personal Protective Equipment; (c) H and S Training
for all site personnel; (d) documented procedures to be
followed for all site activities; and (e) documentation of work-
related accidents;
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible throughout
the site;
(iii) Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not exposed
to hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work at
the site, personal protective protection, and preventing injuring
to fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or substances may
Partially
Complied
Health and Safety Plan is being
implemented.
Insurance has been provided to the
labors.
PPE are being used.
First-aid facility has been provided
at each site
Drinking water has been provided at
all sites
H&S training is being provided to
workers by DSC regularly
high visibility vests are provided to
workers
Sign board are provided at all site
Workers are not exposed to high
noise for 8 hours
Nil Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 129
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
be present. Ensure also that visitor/s do not enter hazard areas
unescorted;
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-up
alarms;
(xi) Mark and provide sign boards for hazardous areas such as
energized electrical devices and lines, service rooms housing
high voltage equipment, and areas for storage and disposal.
Signage shall be in accordance with international standards and
be well known to, and easily understood by workers, visitors,
and the general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85
dBA for a duration of more than 8 hours per day without
hearing protection. The use of hearing protection shall be
enforced actively.
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices, sheds,
and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of
trees;
(iii) Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting of
trees for firewood;
(v) Train employees in the storage and handling of materials
which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove from
the site;
(vii) Manage solid waste according to the following preference
Complied At present most of the workers
employed are local.
Nil Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 130
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
hierarchy: reuse, recycling and disposal to designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures
(such as buildings, shelters, and latrines) which are no longer
required; and
(ix) Request IPIU/DSC to report in writing that the camp has
been vacated and restored to pre-project conditions before
acceptance of work.
Table 24: EMP Compliance Status of Churu Waste Water Subproject {RUSDIP/TR-03/CHU/WW/01}
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
PRECONSTRUCTIONSTAGE 1
EnvironmentalClearances
(i) Site preparation work completed by IPIU including
necessaryclearance
(ii) Consentto EstablishunderWater(Preventionand
Controlof Pollution)Act
(iv) Consentto EstablishunderAir(PreventionandControl of
Pollution)Act
(v) Tree-cuttingPermit
Complied
Consent to Establish is obtained from
RSPCB with validity upto 31/07/2016.
Work completed. Application for CTO
has been submitted to RPCB during
this reporting period.
Permission for tree cutting is not
required
Application under process at
RPCB.
IPIU/ Contractor
2 Social and Cultural Resources (i) Consult Archaeological Survey of India (ASI) to obtain an
expert assessment of the archaeological potential of the site;
(ii) Consider alternatives if the site is found to be of medium
or high risk;
(iii) Include state and local archaeological, cultural and
historical authorities, and interest groups in consultation forums
as project stakeholders so that their expertise can be made
available; and
Complied
It was confirmed by consultations
with various stakeholders that the
site has no archaeological potential
Instruction has been given to the
contractor to ensure that any chance
finds are recognized and measures
are taken to ensure they are
Nil IPIU/ Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 131
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
(iv) Develop a protocol for use by the construction
contractors in conducting any excavation work, to ensure that any
chance finds are recognised and measures are taken to ensure
they are protected and conserved.
protected and conserved.
3 Construction work camps, hot mix plants, stockpile areas,
storage areas, and disposal areas (i) Prioritize areas within or nearest possible vacant space
in the subproject sites;
(ii) If it is deemed necessary to locate elsewhere, consider
sites that will not promote instability and result in destruction of
property, vegetation, irrigation, and drinking water supply
systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct
disposal to water body or in areas which will inconvenience the
community.
Complied
All the facilities related
to construction are
located within
project site
Nil IPIU/
Contractor
4 Sources of Materials (i) Prioritize sites already permitted by the Mining
Department;
(ii) If other sites are necessary, inform construction
contractor that it is their responsibility to verify the suitability of
all material sources and to obtain the approval of IPIU; and
(iii) If additional quarries will be required after construction
is started, inform construction contractor to obtain a written
approval from IPMU.
Complied
All the material is being taken from
Approved mines
Nil IPIU/ Contractor
ConstructionPhase
1 Sources of Materials (i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain
approval of Investment Program Implementation Unit (IPIU);
(iii) If additional quarries will be required after construction
has started, obtain written approval from PMU; and;
(iv) Submit to DSC on a monthly basis documentation of
sources of materials.
Complied
All the material is being taken from
Govt. Approved quarries.
Nil IPIU/
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 132
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
2 Air Quality
(v) Consult with IPIU/DSC on the designated areas for
stockpiling of clay, soils, gravel, and other construction materials;
(vi) Damp down exposed soil and any stockpiled on site by
spraying with water when necessary during dry weather;
(vii) Use tarpaulins to cover sand and other loose material
when transported by trucks; and
(viii) Fit all heavy equipment and machinery with air pollution
control devices which are operating correctly.
Complied
Adequate sprinkling of water
wasbeing done for arresting
fugitive dust
Civil work has been completed
therefore monitoring is not required.
Instruction was given to contractor to
use tarpaulins to cover fine material
when transported.
Nil DSC/ IPIU/
Contractor
3 Surface water quality
(vii) Avoid stockpiling of earth fill especially during the
monsoon season unless covered by tarpaulins or plastic sheets;
(viii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with IPIU/DSC
on designated disposal areas;
(ix) Install temporary silt traps or sedimentation basins along
the drainage leading to the water bodies;
(x) Place storage areas for fuels and lubricants away from any
drainage leading to water bodies;
(xi) Dispose any wastes generated by construction activities in
designated sites; and
(xii) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
Complied
Excess material is removed
Regularly
Surface water quality monitoring is
Not required as there is no surface
water body near sub-project site
Ground water quality monitoring is
not required as the water is hard and
not extracted from ground for
domestic use.
Nil DSC/ IPIU/
Contractor
4 Noise Levels (v) Plan activities in consultation with IPIU/DSC so that
activities with the greatest potential to generate noise are
conducted during periods of the day which will result in least
disturbance;
(vi) Require horns not be used unless it is necessary to warn
othe oad use s o a i als of the ehi le s app oa h; (vii) Minimize noise from construction equipment by using
vehicle silencers, fitting jackhammers with noise-reducing mufflers,
and portable street barriers the sound impact to surrounding
Complied
Activities were planned in
Consultation with PIU
Generator sets and concrete
mixtures are provided with
acoustic enclosures.
Regular maintenance of generator
set and concrete mixture was done
Nil DSC/ IPIU/
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 133
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
sensitive receptor; and
(viii) Maintain maximum sound levels not exceeding 80
decibels (dbA) when measured at a distance of 10 m or more from
the vehicle/s.
by the contractor
Civil work has been completed
therefore monitoring is not required.
5 Landscape and Aesthetics (viii) Prepare and implement Waste Management Plan;
(ix) Avoid stockpiling of excess excavated soils;
(x) Coordinate with Municipal Board for beneficial uses of
excess excavated soils or immediately dispose to designated areas;
(xi) Recover used oil and lubricants and reuse or remove from
the sites;
(xii) Manage solid waste according to the following
preference hierarchy: reuse, recycling and disposal to designated
areas;
(xiii) Remove all wreckage, rubbish, or temporary structures
(such as buildings, shelters, and latrines) which are no longer
required; and
(xiv) Request IPIU/DSC to report in writing that the necessary
environmental restoration work has been adequately performed
before acceptance of work.
Complied
The unusable extra excavated
materials and over burdensare being
disposed at lowlaying area as per
directionof ULB
Nil IPIU/ Contractor
6 Accessibility
(vii) Plan transportation routes so that heavy vehicles do not
use narrow local roads, except in the immediate vicinity of delivery
sites;
(viii) Schedule transport and hauling activities during non-peak
hours;
(ix) Locate entry and exit points in areas where there is low
potential for traffic congestion;
(x) Keep the site free from all unnecessary obstructions;
(xi) Coordinate with Municipal Traffic Office for temporary
road diversions and with for provision of traffic aids if
transportation activities cannot be avoided during peak hours; and
(xii) Notify affected sensitive receptors by providing sign
boards informing nature and duration of construction works and
contact numbers for concerns/complaints
Complied
Traffic diversions are provided at
necessarypoints
The materials carrying trucks to the
worksite follow only designated
routetothesite
sign boards informing nature and
duration of construction works and
contact numbers for
concerns/complaints has been
provided
Nil IPIU/
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 134
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
7 Socio-Economic – Income
(vi) Leave spaces for access between mounds of soil;
(vii) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
(viii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment, hospitals,
and schools;
(ix) Consult businesses and institutions regarding operating
hours and factoring this in work schedules; and
(x) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
Partially
Complied
Proper access across trenches for
people and vehicles has not been
provided
Sign board has not been provided at
sites
provide safe access across
open tranches wherever
required
Contractor
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the maximum
extent, local persons within the 2-km immediate area if
manpower is available; and
(ii) Secure construction materials from local market.
Complied
At present most of the work force is
Hired locally
Nil IPIU
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H and
S) Plan which will include measures such as: (a) excluding public
from the site; (b) ensuring all workers are provided with and use
Personal Protective Equipment; (c) H and S Training for all site
personnel; (d) documented procedures to be followed for all site
activities; and (e) documentation of work-related accidents;
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible throughout
the site;
(iii) Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not exposed to
hazardous or noxious substances;
Partially complied
PPE are being used.
First-aid box is available at site
Group insurance has been provided
To workers
Proper barricading for unauthorized
intrusion has been provided
Drinking water has been provided at
sites
Training for health and safety
measures have been given to
contractor by DSC.
Workers are not exposed to high
noise level more than 8hrs
Contractor has been
instructed complete
compliance of measure
specified in EMP
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 135
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work at the
site, personal protective protection, and preventing injuring to
fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or substances may be
present. Ensure also that visitor/s do not enter hazard areas
unescorted;
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-up
alarms;
(xi) Mark and provide sign boards for hazardous areas such as
energized electrical devices and lines, service rooms housing high
voltage equipment, and areas for storage and disposal. Signage
shall be in accordance with international standards and be well
known to, and easily understood by workers, visitors, and the
general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85 dBA
for a duration of more than 8 hours per day without hearing
protection. The use of hearing protection shall be enforced
actively.
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices, sheds,
and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of trees;
(iii) Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting of trees
for firewood;
(v) Train employees in the storage and handling of materials
Partially
Complied
Work camp has been established
in consultation with IPIU/DSC
Labor insurance has been
provided by the contractor.
Labour camp has been established
near STP site (Package WW/01)
Contractor has instructed
to provide proper water
and sanitation facilities and
cooking gas to the worker
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 136
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove from the
site;
(vii) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures (such
as buildings, shelters, and latrines) which are no longer required;
and
(ix) Request IPIU/DSC to report in writing that the camp has been
vacated and restored to pre-project conditions before acceptance
of work.
Poor water and sanitation
facilities, use of firewood are
observed in labour camp.
Table 25: EMP Compliance Status of Churu Drainage Subproject {RUSDIP/TR-03/CHU/DR/03 & 04}
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
PRECONSTRUCTIONSTAGE 1 EnvironmentalClearances
Site preparation work completed by IPIU including
necessaryclearance
(i) Consentto EstablishunderWater(Preventionand
(ii) Controlof Pollution)Act
(iii) Consentto EstablishunderAir(PreventionandControl of
Pollution)Act
(iv) Tree-cuttingPermit
Complied
Consent to Establish is not required.
Permission for tree cutting is not
required
Nil DSC/ IPIU
2 Social and Cultural Resources
(v) Consult Archaeological Survey of India (ASI) to obtain an
expert assessment of the archaeological potential of the site;
(vi) Consider alternatives if the site is found to be of medium
or high risk;
(vii) Include state and local archaeological, cultural and
Complied It was confirmed by consultations
with various stakeholders that the
site has no archaeological potential
Instruction has been given to the
contractor to ensure that any chance
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 137
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
historical authorities, and interest groups in consultation forums
as project stakeholders so that their expertise can be made
available; and
(viii) Develop a protocol for use by the construction contractors
in conducting any excavation work, to ensure that any chance
finds are recognised and measures are taken to ensure they are
protected and conserved.
finds are recognized and measures
are taken to ensure they are
protected and conserved.
3 Construction work camps, hot mix plants, stockpile areas, storage areas, and disposal areas
(v) Prioritize areas within or nearest possible vacant space in
the subproject sites;
(vi) If it is deemed necessary to locate elsewhere, consider
sites that will not promote instability and result in destruction of
property, vegetation, irrigation, and drinking water supply
systems;
(vii) Do not consider residential areas;
(viii) Take extreme care in selecting sites to avoid direct
disposal to water body or in areas which will inconvenience the
community.
Complied
All the facilities related
to
construction are located
within projectsite
Nil IPIU/
Contractor
4 Sources of Materials
(iv) Prioritize sites already permitted by the Mining
Department;
(v) If other sites are necessary, inform construction
contractor that it is their responsibility to verify the suitability of
all material sources and to obtain the approval of IPIU; and
(vi) If additional quarries will be required after construction
is started, inform construction contractor to obtain a written
approval from IPMU.
Complied
All the material is being taken from
Approved mines
Nil IPIU/
Contractor
CONSTRUCTIONSTAGE 1 Sources of Materials
(v) Use quarry sites and sources permitted by government;
(vi) Verify suitability of all material sources and obtain
approval of Investment Program Implementation Unit (IPIU);
(vii) If additional quarries will be required after construction
has started, obtain written approval from PMU; and;
Complied
All the material is being taken from
Govt. Approved quarries.
Nil IPIU/
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 138
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
(viii) Submit to DSC on a monthly basis documentation of
sources of materials.
2 Air Quality
(ix) Consult with IPIU/DSC on the designated areas for
stockpiling of clay, soils, gravel, and other construction materials;
(x) Damp down exposed soil and any stockpiled on site by
spraying with water when necessary during dry weather;
(xi) Use tarpaulins to cover sand and other loose material
when transported by trucks; and
(xii) Fit all heavy equipment and machinery with air pollution
control devices which are operating correctly.
Partially
Complied
Water sprinkling is being done
When required
As major works has been completed,
monitoring is not required.
Instruction has been given to
contractor to use tarpaulins to cover
fine material when transported.
Nil
DSC/ IPIU/
Contractor
3 Surface water quality
(xiii) Avoid stockpiling of earth fill especially during the
monsoon season unless covered by tarpaulins or plastic sheets;
(xiv) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with IPIU/DSC
on designated disposal areas;
(xv) Install temporary silt traps or sedimentation basins along
the drainage leading to the water bodies;
(xvi) Place storage areas for fuels and lubricants away from any
drainage leading to water bodies;
(xvii) Dispose any wastes generated by construction activities in
designated sites; and
(xviii) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
Complied
Excess material is removed
regularly
Surface water quality monitoring is
not required as there is no water
body near sub-project site.
Ground water quality monitoring is
not required as ground water is hard
is not extracted for domestic use.
Nil DSC/ IPIU/
Contractor
4 Noise Levels (ix) Plan activities in consultation with IPIU/DSC so that
activities with the greatest potential to generate noise are
conducted during periods of the day which will result in least
disturbance;
(x) Require horns not be used unless it is necessary to warn
othe oad use s o a i als of the ehi le s app oa h;
Activities are planned in
consultationwithPIU
Enclosures are provided to each noise
producing equipments like generator
set, concrete mixtures etc.
Nil
DSC/ IPIU/
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 139
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
(xi) Minimize noise from construction equipment by using
vehicle silencers, fitting jackhammers with noise-reducing mufflers,
and portable street barriers the sound impact to surrounding
sensitive receptor; and
(xii) Maintain maximum sound levels not exceeding 80
decibels (dbA) when measured at a distance of 10 m or more from
the vehicle/s.
Partially
Complied
The contractor isusing advanced
machinery and regular maintenance
of machinery is done by contractor
As major works has been completed,
monitoring is not required.
5 Landscape and Aesthetics (xv) Prepare and implement Waste Management Plan;
(xvi) Avoid stockpiling of excess excavated soils;
(xvii) Coordinate with Municipal Board for beneficial uses of
excess excavated soils or immediately dispose to designated areas;
(xviii) Recover used oil and lubricants and reuse or remove from
the sites;
(xix) Manage solid waste according to the following
preference hierarchy: reuse, recycling and disposal to designated
areas;
(xx) Remove all wreckage, rubbish, or temporary structures
(such as buildings, shelters, and latrines) which are no longer
required; and
(xxi) Request IPIU/DSC to report in writing that the necessary
environmental restoration work has been adequately performed
before acceptance of work.
Complied
The unusable extra excavated
materials and overburdens are being
disposed at low laying area as per
direction of ULB
Nil DSC/ IPIU/
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 140
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
6 Accessibility (xiii) Plan transportation routes so that heavy vehicles do not
use narrow local roads, except in the immediate vicinity of delivery
sites;
(xiv) Schedule transport and hauling activities during non-peak
hours;
(xv) Locate entry and exit points in areas where there is low
potential for traffic congestion;
(xvi) Keep the site free from all unnecessary obstructions;
(xvii) Coordinate with Municipal Traffic Office for temporary
road diversions and with for provision of traffic aids if
transportation activities cannot be avoided during peak hours; and
(xviii) Notify affected sensitive receptors by providing sign
boards informing nature and duration of construction works and
contact numbers for concerns/complaints
Complied
The vehicles carrying materials to the
work site follow only designated route
to the site
sign boards informing nature and
duration of construction works and
contact numbers for
concerns/complaints has been
provided
The materials carryin gtrucks to the
work site follow only designated
Route to the site
Nil
DSC/ IPIU/
Contractor
7 Socio-Economic – Income
(xi) Leave spaces for access between mounds of soil;
(xii) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
(xiii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment, hospitals,
and schools;
(xiv) Consult businesses and institutions regarding operating
hours and factoring this in work schedules; and
(xv) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
Complied
The work schedule has been prepared
as per consultation with local public
Proper access across trenches for
people and vehicles has provided
Significant work force has been
provided
NIl DSC/ IPIU
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the maximum
extent, local persons within the 2-km immediate area if
manpower is available; and
(ii) Secure construction materials from local market.
Complied
At present most of the work force is
hired locally
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 141
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H and
S) Plan which will include measures such as: (a) excluding public
from the site; (b) ensuring all workers are provided with and use
Personal Protective Equipment; (c) H and S Training for all site
personnel; (d) documented procedures to be followed for all site
activities; and (e) documentation of work-related accidents;
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible throughout
the site;
(iii) Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not exposed to
hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work at the
site, personal protective protection, and preventing injuring to
fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or substances may be
present. Ensure also that visitor/s do not enter hazard areas
unescorted;
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-up
alarms;
(xi) Mark and provide sign boards for hazardous areas such as
Partially
complied
Health and Safety Plan has been
provided
PPE are being used.
First-aid facility has been provided at
each site
Group insurance has been provided to
workers
Drinking water has been provided at all
sites
H&S training is being provided to
workers by DSC regularly
high visibility vests are provided to
workers
Back-up alarms are provided in moving
equipment
Sign board are not provided at all site
Workers are not exposed to high noise
for 8 hours
Nil Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 142
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
energized electrical devices and lines, service rooms housing high
voltage equipment, and areas for storage and disposal. Signage
shall be in accordance with international standards and be well
known to, and easily understood by workers, visitors, and the
general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85 dBA
for a duration of more than 8 hours per day without hearing
protection. The use of hearing protection shall be enforced
actively.
Work Camps
(i) Consult with IPIU/DSC before locating project offices, sheds,
and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of trees;
(iii) Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting of trees
for firewood;
(v) Train employees in the storage and handling of materials
which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove from the
site;
(vii) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures (such
as buildings, shelters, and latrines) which are no longer required;
and
(ix) Request IPIU/DSC to report in writing that the camp has been
vacated and restored to pre-project conditions before acceptance
of work.
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 143
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
10 Sources of Materials (ix) Use quarry sites and sources permitted by government;
(x) Verify suitability of all material sources and obtain
approval of Investment Program Implementation Unit (IPIU);
(xi) If additional quarries will be required after construction
has started, obtain written approval from PMU; and;
(xii) Submit to DSC on a monthly basis documentation of
sources of materials.
Complied
The contractor has not established
any labor camp yet. Local labor is
engaged in work
Nil _
Contractor
Table 26: EMP Compliance Status of Churu Road subproject {RUSDIP/TR-03/CHU/ST/01}
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
Pre-Construction Stage
1 Environmental Clearances
Site preparation work completed by IPIU including necessary
clearance
Complied
Consent to Establish is not
required
Tree cutting permission has been
obtained.
Nil DSC/ IPIU
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain an
expert assessment of the archaeological potential of the site;
(ii) Consider alternatives if the site is found to be of medium
or high risk;
(iii) Include state and local archaeological, cultural and
historical authorities, and interest groups in consultation
forums as project stakeholders so that their expertise can be
made available; and
(iv) Develop a protocol for use by the construction
contractors in conducting any excavation work, to ensure
Complied
It was confirmed by consultations
with various stakeholders that the
site has no archaeological
potential
Instruction has been given to the
contractor to ensure that any
chance finds are recognized and
measures are taken to ensure they
are protected and conserved
Nil DSC/ IPIU/
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 144
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
that any chance finds are recognised and measures are taken
to ensure they are protected and conserved.
3 Construction work camps, hot mix plants, stockpile areas,
storage areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant space in
the subproject sites;
(ii) If it is deemed necessary to locate elsewhere, consider
sites that will not promote instability and result in destruction
of property, vegetation, irrigation, and drinking water supply
systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct
disposal to water body or in areas which will inconvenience
the community.
Complied
All the facilities related to
construction are located within
project site
Nil IPIU/ Contractor
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining
Department;
(ii) If other sites are necessary, inform construction
contractor that it is their responsibility to verify the suitability
of all material sources and to obtain the approval of IPIU; and
(iii) If additional quarries will be required after construction is
started, inform construction contractor to obtain a written
approval from IPMU.
Complied
All the material is being taken
from approved mines
Nil IPIU/ Contractor
Construction Stage
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain
approval of Investment Program Implementation Unit ( IPIU);
(iii) If additional quarries will be required after construction
has started, obtain written approval from PMU; and;
(iv) Submit to DSC on a monthly basis documentation of
sources of materials.
Complied
All the material is being taken
from government approved quarry
sites
Nil IPIU/ Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 145
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for
stockpiling of clay, soils, gravel, and other construction
materials;
(ii) Damp down exposed soil and any stockpiled on site by
spraying with water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material
when transported by trucks; and
(iv) Fit all heavy equipment and machinery with air pollution
control devices which are operating correctly.
Complied
Adequate sprinkling of water is
required for arresting fugitive
dust
As major works has been
completed, monitoring is not
required.
Nil DSC/ IPIU/
Contractor
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the
monsoon season unless covered by tarpaulins or plastic
sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins along
the drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from
any drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities in
designated sites; and
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
Complied
Surface water quality monitoring
is not required as no surface
water is not present near the sub
project.
Ground water quality monitoring
is not required as ground water is
hard is not extracted for domestic
use.
Nil DSC/ IPIU/
Contractor
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that
activities with the greatest potential to generate noise are
conducted during periods of the day which will result in least
disturbance;
(ii) Require horns not be used unless it is necessary to warn
othe oad use s o a i als of the ehi le s app oa h;
Complied
Activities with the greatest
potential to generate noise have
been planned in consultation with
IPIU and are being conducted in
day time
As major works has been
Nil DSC/ IPIU/
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 146
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
(iii) Minimize noise from construction equipment by using
vehicle silencers, fitting jackhammers with noise-reducing
mufflers, and portable street barriers the sound impact to
surrounding sensitive receptor; and
(iv) Maintain maximum sound levels not exceeding 80
decibels (dbA) when measured at a distance of 10 m or more
from the vehicle/s.
completed, monitoring is not
required.
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(ii) Coordinate with Municipal Board for beneficial uses of
excess excavated soils or immediately dispose to designated
areas;
(iv) Recover used oil and lubricants and reuse or remove from
the sites;
(v) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(vi) Remove all wreckage, rubbish, or temporary structures
(such as buildings, shelters, and latrines) which are no longer
required; and
(vii) Request IPIU/DSC to report in writing that the necessary
environmental restoration work has been adequately
performed before acceptance of work.
Complied
The unusable extra excavated
materials and over burdens are
being disposed at low laying area
Nil DSC/ IPIU/
Contractor
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not
use narrow local roads, except in the immediate vicinity of
delivery sites;
(ii) Schedule transport and hauling activities during non-peak
hours;
(iii) Locate entry and exit points in areas where there is low
potential for traffic congestion;
(iv) Keep the site free from all unnecessary obstructions;
Complied
The vehicles carrying materials to
the work site follow only
designated route to the site
Sign boards informing nature and
duration of construction works
and contact numbers for
concerns/complaints has been
Nil IPIU/ Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 147
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
(v) Drive vehicles in a considerate manner;
(vi) Coordinate with Municipal Traffic Office for temporary
road diversions and with for provision of traffic aids if
transportation activities cannot be avoided during peak
hours; and
(vii) Notify affected sensitive receptors by providing sign
boards informing nature and duration of construction works
and contact numbers for concerns/complaints
provided
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment,
hospitals, and schools;
(iv) Consult businesses and institutions regarding operating
hours and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
Complied
The work schedule has been
prepared as per consultation with
local public
Significant work force has been
provided
Nil DSC/ IPIU
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the
maximum extent, local persons within the 2-km immediate
area if manpower is available; and
(ii) Secure construction materials from local market.
Complied
At present most of the workforce
is hired locally
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 148
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H
and S) Plan which will include measures such as: (a) excluding
public from the site; (b) ensuring all workers are provided
with and use Personal Protective Equipment; (c) H and S
Training for all site personnel; (d) documented procedures to
be followed for all site activities; and (e) documentation of
work-related accidents;
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible
throughout the site;
(iii) Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not
exposed to hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work
at the site, personal protective protection, and preventing
injuring to fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or substances
may be present. Ensure also that visitor/s do not enter hazard
areas unescorted;
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-
up alarms;
(xi) Mark and provide sign boards for hazardous areas such as
energized electrical devices and lines, service rooms housing
Partially
Complied
Health and Safety Plan has been
provided.
PPE are being used.
First-aid facility has been provided
at each site
Group insurance has been
provided to workers
Drinking water has been provided
at all sites
H&S training is being provided to
workers by DSC regularly
contractor has provided drinking
water at site
H & S training has been provided
high visibility vests are provided to
workers
Back-up alarms are not provided in
moving equipment
Sign board are provided at all site
Workers are not exposed to high
noise for 8 hours
Back up alarms are to be
provided by the contractor in
equipment.
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 149
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
high voltage equipment, and areas for storage and disposal.
Signage shall be in accordance with international standards
and be well known to, and easily understood by workers,
visitors, and the general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85
dBA for a duration of more than 8 hours per day without
hearing protection. The use of hearing protection shall be
enforced actively.
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices,
sheds, and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of
trees;
(iii) Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting of
trees for firewood;
(v) Train employees in the storage and handling of materials
which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove from
the site;
(vii) Manage solid waste according to the following
preference hierarchy: reuse, recycling and disposal to
designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures
(such as buildings, shelters, and latrines) which are no longer
required; and
(ix) Request IPIU/DSC to report in writing that the camp has
been vacated and restored to pre-project conditions before
acceptance of work.
Complied
At present most of the workers
employed are local.
NIL Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 150
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Table 27: EMP Compliance Status of Chittorgarh Waste Water Subproject {RUSDIP/TR-03/CHT/WW/01, Lot-1 & Lot-2}
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
PRECONSTRUCTIONSTAGE
1 EnvironmentalClearances
Site preparation work completed by IPIU including
necessaryclearance
(i) Consentto EstablishunderWater(Preventionand
Controlof Pollution)Act
(ii) Consentto EstablishunderAir(PreventionandControl of
Pollution)Act
(iii) Tree-cuttingPermit
Complied
Consent to Establish is obtained for
construction of STP which is expired
and being applied for renewal, other
clearances for pipe laying works is
obtained
Tree cutting is not required
Application for Renewal of
Consent to Establish for STP is
submitted to RPCB.The same is
under process at RPCB.
IPIU/DSC
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain an
expert assessment of the archaeological potential of the site;
(ii) Consider alternatives if the site is found to be of medium or
high risk;
(iii) Include state and local archaeological, cultural and historical
authorities, and interest groups in consultation forums as
project stakeholders so that their expertise can be made
available; and
(iv) Develop a protocol for use by the construction contractors
in conducting any excavation work, to ensure that any chance
finds are recognised and measures are taken to ensure they are
protected and conserved.
Complied
It was confirmed by consultations
with various stakeholders that the site
has no archaeological potential
Instruction has been given to the
contractor to ensure that any chance
finds are recognized and
measures are taken to ensure they
are protected and conserved
Nil IPIU/ DSC
3 Construction work camps, hot mix plants, stockpile areas,
storage areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant space in the
subproject sites;
(ii) If it is deemed necessary to locate elsewhere, consider sites
that will not promote instability and result in destruction of
property, vegetation, irrigation, and drinking water supply
Complied
All the facilities related to
construction arelocated within
projectsite and having no
consequences on vegetation,
irrigation and drinking water supply
systems.
Nil IPIU/ Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 151
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct disposal
to water body or in areas which will inconvenience the
community.
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining Department;
(ii) If other sites are necessary, inform construction contractor
that it is their responsibility to verify the suitability of all
material sources and to obtain the approval of IPIU; and
(iii) If additional quarries will be required after construction is
started, inform construction contractor to obtain a written
approval from IPMU.
Complied
All the material is being taken from
Approved mines
Nil IPIU/
Contractor
CONSTRUCTIONSTAGE
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain approval
of Investment Program Implementation Unit ( IPIU);
(iii) If additional quarries will be required after construction has
started, obtain written approval from PMU; and;
(iv) Submit to DSC on a monthly basis documentation of
sources of materials.
Complied
All the material is being taken from
government approved quarry sites
Nil IPIU / Contractor
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for
stockpiling of clay, soils, gravel, and other construction
materials;
(ii) Damp down exposed soil and any stockpiled on site by
spraying with water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material when
transported by trucks; and
(iv) Fit all heavy equipment and machinery with air pollution
control devices which are operating correctly.
Complied
Adequate sprinkling of water is
required for arresting fugitive dust at
pipe laying sites
Air quality monitoring has not been
conducted during report period
though work order was issued.
Air quality monitoring is
required to be conducted in
the next reporting period.
IPIU/ DSC/
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 152
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the monsoon
season unless covered by tarpaulins or plastic sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins along
the drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from any
drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities in
designated sites; and
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
Complied
In pipe line works most of the
excavated material is back filled
andsurface levelling of low lying
areas
Fuels and lubricants are being
stored away from water bodies
Waste generated from construction
activities is being disposed in vacant
areas and hence not affect water
bodies hence water monitoring is
not required
Nil IPIU/ DSC/
Contractor
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that activities
with the greatest potential to generate noise are conducted
during periods of the day which will result in least disturbance;
(ii) Require horns not be used unless it is necessary to warn
othe oad use s o a i als of the ehi le s app oa h; (iii) Minimize noise from construction equipment by using
vehicle silencers, fitting jackhammers with noise-reducing
mufflers, and portable street barriers the sound impact to
surrounding sensitive receptor; and
(iv) Maintain maximum sound levels not exceeding 80 decibels
(dbA) when measured at a distance of 10 m or more from the
vehicle/s.
Partially
Complied
Activities are
planned in
consultation with PIU
Concrete mixturesand generators are
observed in good condition
Noise monitoring has not been
conducted for reporting period
though work order was issued.
Noise level quality
monitoring is required to
be conducted in the next
reporting period.
IPIU/ DSC/
Contractor
5
Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(ii) Coordinate with Municipal Board for beneficial uses of
excess excavated soils or immediately dispose to designated
The excavated soil is kept for reuse
whereas unusable extra excavated
materials and over burdens are being
disposed at low laying/vacant areas
Nil IPIU/ DSC
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 153
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
areas;
(iv) Recover used oil and lubricants and reuse or remove from
the sites;
(v) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(vi) Remove all wreckage, rubbish, or temporary structures
(such as buildings, shelters, and latrines) which are no longer
required; and
(vii) Request IPIU/DSC to report in writing that the necessary
environmental restoration work has been adequately
performed before acceptance of work.
Complied
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not use
narrow local roads, except in the immediate vicinity of delivery
sites;
(ii) Schedule transport and hauling activities during non-peak
hours;
(iii) Locate entry and exit points in areas where there is low
potential for traffic congestion;
(iv) Keep the site free from all unnecessary obstructions;
(v) Drive vehicles in a considerate manner;
(vi) Coordinate with Municipal Traffic Office for temporary road
diversions and with for provision of traffic aids if transportation
activities cannot be avoided during peak hours; and
(vii) Notify affected sensitive receptors by providing sign boards
informing nature and duration of construction works and
contact numbers for concerns/complaints
Complied
The vehicles carrying materials to
the work site follow only designated
route to the site
Traffic diversion is being done with
prior consultations with
administration, where required
Sign boards informing nature and
duration of construction works and
contact numbers for
concerns/complaints has been
provided
Nil IPIU /
Contractor
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment,
Walk ways are not being provided for
access across trenches
Significant work force has been
provided near critical areas
Provide walk ways/access
across trenches for people
and vehicles
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 154
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
hospitals, and schools;
(iv) Consult businesses and institutions regarding operating
hours and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
Partially
Complied
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the maximum
extent, local persons within the 2-km immediate area if
manpower is available; and
(ii) Secure construction materials from local market.
Complied
At present most of the unskilled
workforce is hired locally
Construction material being procured
from local market, if available
Nil IPIU/ DSC
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H
and S) Plan which will include measures such as: (a) excluding
public from the site; (b) ensuring all workers are provided with
and use Personal Protective Equipment; (c) H and S Training for
all site personnel; (d) documented procedures to be followed
for all site activities; and (e) documentation of work-related
accidents;
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible throughout
the site;
(iii) Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not exposed
to hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work at
the site, personal protective protection, and preventing injuring
Partially
Complied
PPE is being used.
First-aid box is available at site
Group insurance has been provided
to workers
Proper barricading for unauthorized
intrusion has been provided
Drinking water has been provided at
sites
Training for Health and Safety of
workers is done by DSC and CAPP
personnel time to time. contractor s
Safety personnel also gives training to
workers
Workers are not exposed to high
Nil
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 155
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
to fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or substances may
be present. Ensure also that visitor/s do not enter hazard areas
unescorted;
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-up
alarms;
(xi) Mark and provide sign boards for hazardous areas such as
energized electrical devices and lines, service rooms housing
high voltage equipment, and areas for storage and disposal.
Signage shall be in accordance with international standards and
be well known to, and easily understood by workers, visitors,
and the general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85
dBA for a duration of more than 8 hours per day without
hearing protection. The use of hearing protection shall be
enforced actively.
noise level more than 8hrs
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices, sheds,
and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of
trees;
(iii) Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting of
trees for firewood;
(v) Train employees in the storage and handling of materials
which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove from
the site;
(vii) Manage solid waste according to the following preference
Complied
Lot-1package-Workers are living in
rented rooms with adequate
facilities, mostly workers are hired
locally
Lot-2package-Workers are living in
quarters developed for the project
having sanitary andsolidwaste
management
No wild life exist near workers rooms
Nil Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 156
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
hierarchy: reuse, recycling and disposal to designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures
(such as buildings, shelters, and latrines) which are no longer
required; and
(ix) Request IPIU/DSC to report in writing that the camp has
been vacated and restored to pre-project conditions before
acceptance of work.
Table 28: EMP Compliance Status of Chittorgarh RUB Subproject {RUSDIP/TR-03/CHT/BR/03}
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
PRECONSTRUCTIONSTAGE 1 EnvironmentalClearances
Site preparation work completed by IPIU including
necessaryclearance
Complied
Site preparation works completed
and site handed over to contractor
for construction works, clearance
from Railway obtained
Nil IPIU/ DSC
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain an expert
assessment of the archaeological potential of the site;
(ii) Consider alternatives if the site is found to be of medium or
high risk;
(iii) Include state and local archaeological, cultural and historical
authorities, and interest groups in consultation forums as project
stakeholders so that their expertise can be made available; and
(iv) Develop a protocol for use by the construction contractors in
conducting any excavation work, to ensure that any chance finds
are recognised and measures are taken to ensure they are
protected and conserved.
Complied
It was confirmedby consultations
With various stakeholders that the
site has no archaeological potential
Instruction has been given to the
contractor to ensure that any
chance finds are recognized and
measures are taken to ensure they
are protected and conserved
Nil IPIU/ DSC
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 157
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
3 Construction work camps, hot mix plants, stockpile areas,
storage areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant space in the
subproject sites;
(ii) If it is deemed necessary to locate elsewhere, consider sites
that will not promote instability and result in destruction of
property, vegetation, irrigation, and drinking water supply
systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct disposal to
water body or in areas which will inconvenience the community.
Complied All the facilities related to
projectsite and having no
consequences on vegetation,
irrigation and drinking water supply
systems
Nil IPIU /
Contractor
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining Department;
(ii) If other sites are necessary, inform construction contractor
that it is their responsibility to verify the suitability of all material
sources and to obtain the approval of IPIU; and
(iii) If additional quarries will be required after construction is
started, inform construction contractor to obtain a written
approval from IPMU.
Complied
All the material is being taken from
approved mines
Nil IPIU/
Contractor
CONSTRUCTIONSTAGE
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain approval of
Investment Program Implementation Unit ( IPIU);
(iii) If additional quarries will be required after construction has
started, obtain written approval from PMU; and;
(iv) Submit to DSC on a monthly basis documentation of sources
of materials.
Complied
All the material is being taken from
Government approved quarry sites.
Nil IPIU /
Contractor
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for stockpiling
of clay, soils, gravel, and other construction materials;
Partially
Complied
Site has no issues of dust problem
PUCs of vehicles and equipment is
Instruction has been given
to contractor to take PUCs
Contractor/IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 158
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
(ii) Damp down exposed soil and any stockpiled on site by
spraying with water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material when
transported by trucks; and
(iv) Fit all heavy equipment and machinery with air pollution
control devices which are operating correctly.
not available with contractor
Air quality monitoring has not
been conducted during report
period though work order was
issued.
of all vehicles and
equipment
Air quality monitoring will
be conducted in the next
monitoring period.
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the monsoon
season unless covered by tarpaulins or plastic sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins along the
drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from any
drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities in
designated sites; and
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
Complied
Excess excavated soil is disposed in
vacant areas
No water body exist near the site
No waste is being generated from
construction activities
Nil IPIU/ DSC/
Contractor
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that activities
with the greatest potential to generate noise are conducted
during periods of the day which will result in least disturbance;
(ii) Require horns not be used unless it is necessary to warn other
oad use s o a i als of the ehi le s app oa h; (iii) Minimize noise from construction equipment by using vehicle
silencers, fitting jackhammers with noise-reducing mufflers, and
portable street barriers the sound impact to surrounding
sensitive receptor; and
Complied
Activities with the greatest potential
to generate noise have been planned
in consultation with IPIU and are
being conducted in day time only
Excess excavated soil/construction
waste is being disposed in vacant
areas near site
Noise monitoring has not been
I
instruction has been given
to contractors for proper
maintenance of equipment
Noisr level quality monitoring
will be conducted in the next
monitoring period.
Contractor/IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 159
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
(iv) Maintain maximum sound levels not exceeding 80 decibels
(dbA) when measured at a distance of 10 m or more from the
vehicle/s.
conducted for reporting period.
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(ii) Coordinate with Municipal Board for beneficial uses of excess
excavated soils or immediately dispose to designated areas;
(iv) Recover used oil and lubricants and reuse or remove from the
sites;
(v) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(vi) Remove all wreckage, rubbish, or temporary structures (such
as buildings, shelters, and latrines) which are no longer required;
–
Complied
In pipe line works most of the
Excavated material i s back filled
andremaining soil is used for
levelling of low lying areas.
Nil IPIU/ DSC
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not use
narrow local roads, except in the immediate vicinity of delivery
sites;
(ii) Schedule transport and hauling activities during non-peak
hours;
(iii) Locate entry and exit points in areas where there is low
potential for traffic congestion;
(iv) Keep the site free from all unnecessary obstructions;
(v) Drive vehicles in a considerate manner;
(vi) Coordinate with Municipal Traffic Office for temporary road
diversions and with for provision of traffic aids if transportation
activities cannot be avoided during peak hours; and
(vii) Notify affected sensitive receptors by providing sign boards
informing nature and duration of construction works and contact
numbers for concerns/complaints
Complied
The vehicles carrying materials to
the work site follow only designated
route to the site
Traffic diversion is being done with
prior consultations with
administration, where required
Sign boards informing nature and
duration of construction works and
contact numbers for
concerns/complaints has been
provided
No sensitive receptors exist near
work site
Nil IPIU/
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 160
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment, hospitals,
and schools;
(iv) Consult businesses and institutions regarding operating hours
and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
Complied
No movement of vehicles and people
near the site
No critical areas exist near the site
Nil IPIU/ DSC/
Contractor
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the maximum
extent, local persons within the 2-km immediate area if
manpower is available; and
(ii) Secure construction materials from local market.
Complied
Most of the unskilled work force is
hired locally
Construction material being
procured from local market, if
available
Nil IPIU/ DSC
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H and
S) Plan which will include measures such as: (a) excluding public
from the site; (b) ensuring all workers are provided with and use
Personal Protective Equipment; (c) H and S Training for all site
personnel; (d) documented procedures to be followed for all site
activities; and (e) documentation of work-related accidents;
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible throughout
the site;
(iii) Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not exposed to
Partially
Complied
PPE s are being used
First-aid box is available at
site
Group insurance has been provided
to workers
Proper barricading for unauthorized
intrusion has been provided
Drinking water has been provided
at sites
Training for Health and Safety of
workers is done by DSC.
Contractor has been
instructed complete
compliance of safety
measure specified in EMP
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 161
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work at
the site, personal protective protection, and preventing injuring
to fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or substances may
be present. Ensure also that visitor/s do not enter hazard areas
unescorted;
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-up
alarms;
(xi) Mark and provide sign boards for hazardous areas such as
energized electrical devices and lines, service rooms housing high
voltage equipment, and areas for storage and disposal. Signage
shall be in accordance with international standards and be well
known to, and easily understood by workers, visitors, and the
general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85 dBA
for a duration of more than 8 hours per day without hearing
protection. The use of hearing protection shall be enforced
actively.
Contractor s Safety personnel also
gives training to workers
Workers are not exposed to high
noise level more than 8hrs
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices, sheds,
and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of trees;
(iii) Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting of
trees for firewood;
(v) Train employees in the storage and handling of materials
which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove from the
Partially
Complied
Most of the workers are hired locally
and some workers are living in work
camps which are not having adequate
facilities like proper shelters,
sanitation, solid waste
managementetc.
No wild life exist near the proposed
site
Provide all the basic facilities in
workers camps
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 162
ADB Loan No2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec. 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance Explanation ActionProposed Responsibility
site;
(vii) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures (such
as buildings, shelters, and latrines) which are no longer required;
and
(ix) Request IPIU/DSC to report in writing that the camp has been
vacated and restored to pre-project conditions before acceptance
of work.
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 164
ADB Loan No. 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
III. ENVIRONMENTAL PROCEDURE REVIEW
A). Environmental Legal Requirements
17. Annexure 1 lists those Acts; Rules, Policies and Regulations currently in force in India and deal with
environmental issues that could apply to infrastructure development. However, because of the relatively
minor negative impacts of most of the types of the subproject likely to be developed under RUSDIP, it is
expected that most subproject should not fall within the scope of these legal instruments. Subprojects and
activities that will need to comply with certain laws are:
Any components that require the acquisition of forest land;
Any construction activities located in areas covered by the Arvalli Range Notification in Alwar;
Water Treatment Plants (WTP) and Sewage Treatment Plants (STP);
Composting and landfill facilities;
Common waste management facilities, including composting, landfills, transfer stations;
Common waste management facilities within 10 km of the boundary of protected areas (such as
National Parks, Sanctuaries, Notified areas and Biosphere Reserves);
Mobile diesel generators
18. The specific requirements to ensure compliance by these components and subprojects are shown in
Table 29.
Table 29: Action Required Ensuring Subprojects Comply with National Environmental Laws
Component Applicable Legislation Compliance Action Required
1. All components that require
acquisition of forest land
Forest (Conservation) Act
1980; Wildlife (protection) Act
1972
Approval from
Ministry of
Environment and
Forests (MoEF)
Identify non- forest land and
formulate an afforestation
program
2. Water Treatment Plant (WTP)
and Sewage Treatment Plant
(STP)
Water (Prevention and Control
of Pollution)Act 1974
Consent to Establish
(CTE) and Consent to
Operate (CTO) from
RSPCB
Based on project review and
site inspection RSPCB provides
CTE before construction, and
stipulate the disposal standards
to be met during operation.
After completion of
construction, CTO is issued
confirming compliance with the
CTE conditions, if any
Renewal of CTO
during operation (STP)
Based on the performance of
the STP and its compliance with
the disposal standards CTO is
renewed every year
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 165
ADB Loan No. 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Component Applicable Legislation Compliance Action Required
3. All composting and landfill
facilities
Municipal Solid Wastes
(Management and handing)
Rules 2000
Authorization of
proposed site by
RSPCB
Authorization is issued based
on land use in and around the
site and groundwater condition
Water (Prevention and Control
of Pollution ) Act 1974;
Air(Prevention and Control of
Pollution ) Act 1981
CTE and CTO from
RSPCB
Same as for STPs (above)
4. Common waste management
facilities including composting,
landfills and transfer stations
Environment (Protection) Act
1986: Environmental Impact
Assessment Notification 2006,
amended in 2009 Category B
Requires
environmental
clearance from State
Environment impact
Assessment Authority
(SEIAA)
Based on preliminary
information and site visits, if
required, project will be
categorized as B1 or B2. B1
projects require EIA study for
approval
5. Common waste management
facilities within or 10 km
outside the boundary of
protected areas such as
National Parks, Sanctuaries,
Notified Areas and Biosphere
Reserve
Environmental Impact
Assessment Notification, 2006
Category A
Requires
environmental
clearance from the
federal Ministry of
Environment and
Forests (MoEF)
Conduct EIA study
Category A and B1 projects
require public consultation as
part of EIA
6. Mobile diesel generators
Air (Prevention and Control of
Pollution ) Act 1981
CTE and CTO from
RSPCB
CTO renewal every year based
on performance
B). Compliance of Environmental Regulations
19. Table 30 below shows present clearance status for different sub-projects under Tr-1, Tr-2& Tr-3. GoI
EIA Notification of 2006 and its subsequent amendment (replacing the EIA Notification of 1994), sets out the
requirement for Environmental Assessment in India. This states that Environmental Clearance (EC) is required
for specified activities/projects. Projects are categorized as A o B depe di g o the s ale of the p oje t a d the atu e of its i pa ts. Catego ies A p oje ts e ui e E i o e tal Clea a e f o the Natio al Mi ist of E i o e t a d Fo ests MoEF a d Catego B p oje ts require environmental clearance from the State
Environment Impact Assessment Authority (SEIAA).
20. The only type of infrastructure provided by the RUSDIP that is specified in the EIA Notification is
Common Municipal Solid Waste Management facility (CMSWMF3), where EC is required. Thus Environmental
Clearance (EC) is not required for other sub-project under RUSDIP.
3For the purpose of EIA Notification, common municipal solid waste management facilities may be referred as
centralized MSW facility for an given town, city, region. It is further to mention a common facility need not have
surrounding ULBs included.(Technical EIA Guidance Manual for CMSWMF)
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 166
ADB Loan No. 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
21. Co se t to Esta lish fo setti g up “e age T eat e t Pla t a d Wate T eat e t Pla t a d Co se t to Ope ate efo e the pla t sta ts its ope ation is required from State Pollution Control Board
(RPCB) under the Water (Prevention and Control of Pollution) Act. 1974.
22. As per the present status consent to establish has been obtained for all the running sub-projects
under Tr-1, Tr-2& Tr-3. Attention is required by respective PIUs to obtain Consent to Operate before
commissioning of STP/WTP.
Table 30: Present Status of Environment and Forest & Other Clearances
Tranche-01
Town Work
(Package No.)
Applicable
Legislation/ Type
of clearance
Clearance given by
and date
Subject
/ Issue
Remarks/ Action
needed
Alwar (Tr-1) Alwar Waste
Water
(RUSDIP/Tr-
01/ALW-/WW-
02)
Water
(Prevention and
Control of
Pollution) Act.
1974/
Consent for 20
MLD STP from
Pollution Control
Board
Consent to Operate
obtained from
Pollution Control
Board –
Consent valid upto
31.07.2015
by RSPCB order No.
2012-2013/MUID/
1099
PHED has applied
for renewal of
consent to
Operate
Project has been
handed over to
PHED.
Operational
Work completed
Date:30/07/2012
Handed over on
7/03/2013.
PHED to follow
up with RPCB for
renewal of CTO.
Alwar Solid
Waste
(RUSDIP/Tr-
01/ALW-/SW-
01)
EIA notification
2006
Authorization issued
from Rajasthan
Pollution Control
Board (RPCB)
EC obtained vide
letter no.
F1(4)SEIAA/SEAC-
Raj/ Sectt/Project/
Cat7(i) B1(86)/08-09
Complied
Handed over to
municipal
council.
operational
Work completed
Jaisalmer
(Tr-1)
Waste Water
(RUSDIP/TR-
01/JSL/WW-01)
Water
(Prevention and
Control of
Pollution) Act.
1974/
Consent to
Consent to Establish
obtained from
Pollution Control
Board – Order No.
2012-
2013/MUID/1141
Consent to
Establish expired
on dtd
30.11.2015. Work
completed.
Since the work
has been
completed
Application for
Consent to
Operate is under
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 167
ADB Loan No. 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Town Work
(Package No.)
Applicable
Legislation/ Type
of clearance
Clearance given by
and date
Subject
/ Issue
Remarks/ Action
needed
establish of 10
MLD STP from
Pollution Control
Board
Consent to
operate will be
required before
operation
dated 03.12.2012
Consent valid upto
30.11.2015
Application of
Consent to
Operate is
submitted on
20.04.2017. The
same is under
process at RPCB.
process.
Plant will be
operational after
receiving CTO.
Jaisalmer Solid
Waste
((RUSDIP/Tr-
01/JSL-/SW-07))
EIA notification
2006
EC applied on
01.10.08 (for
categorization
submitted to
RPCB on
02.09.08)
Authorization issued
from Rajasthan
Pollution Control
Board (RPCB)
Discussion in
SEAC meeting
held on 17.11.08
again it is
discussed in 3rd
meeting of SEAC
on 26.12.08. TOR
issued by SEAC
for EIA and
Environmental
Clearance
Project
Terminated
Jhalawar-
Jhalrapatan
(Tr-1)
Jhalwar Solid
Waste
(RUSDIP/Tr-01/
JHL -/SW-08)
EIA notification
2006
Authorization issued
from Rajasthan
Pollution Control
Board (RPCB).
Environmental
Clearance issued by
SEIAA vide letter no.
F1(4) SEIAA/SEAC
Raj/Sectt/project/Cat
7(i)B1(123)/08-09 on
30.07.2012
Consent to Establish
obtained by PCB
order no 2012-
2013/SWMC/1579
dated 15.10.2012
valid upto
31.07.2015
The work has
been completed
and renewal of
Consent to
Establish is not
required.
Complied
Handed over to
Nagar Parishad.
Not operational
as compost plant
has not been
built by Nagar
Parishad. Handed
over on
Date – 25/03/
2015
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 168
ADB Loan No. 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Tranche-02
Town Work (Package No.) Applicable
Legislation/ Type of
clearance
Clearance given by and
date
Subject
/ Issue
Remarks/ Action
needed
SawaiMadhopur
(Tr-2)
Waste Water
(RUSDIP/TR-
02/SMD/WW-01)
Package No.
Changed as:
RUSDIP/TR-
02/SMD/WW-02
Water (Prevention
and Control of
Pollution) Act. 1974/
Consent to establish
of 10 MLD STP from
Pollution Control
Board
Consent to Establish
obtained from Pollution
Control Board – Order
No. 2012-2013/MUID/
1013 dated 25.10.2012
Consent valid upto
30.04.2015
Consent to Operate for
DG set at STP obtained
from PCB- Order no.
2012-2013/MUID/1012
dated 25.10.2012.
Consent valid upto
31.08.2015
Consent to Operate has
been renewed via order
number 2016-
2017/PLG/1015 dated
07/10/2016, valid till
31/03/2019.
Nil Complied
Dholpur
(Tr-2)
Water supply
(RUSDIP/TR-
02/DLP/WS-03)
Water (Prevention
and Control of
Pollution) Act. 1974/
Consent to establish
of 15 MLD WTP from
Pollution Control
Board
Consent to operate is
required on operation
Consent to Establish
obtained from Pollution
Control Board – Order
No. 2012-2013
/Bharatpur/ 885 dated
03.10.2012.Consent was
valid upto 31.05.2015.
Work completed
Consent to Operate
obtained from RPCB via
order no. 2012-
2013/Bharatpur /885
2015-2016/ Bhartapur/
2584 dated 16.02.2016
And is valid upto
31/08/2020.
Nil Complied
Dholpur
(Tr-2)
Waste Water
(RUSDIP/TR-
02/DLP/WW/04,
RUSDIP/TR-
02/DLP/WW/05 &
RUSDIP/TR-
02/DLP/WW/11 )
Water (Prevention
and Control of
Pollution) Act. 1974/
Consent to
establishfor 10 and 3
MLD STP from
Pollution Control
Consent to Establish
obtained from Pollution
Control Board for 10
MLD STP under WW-05 –
Order No. 2012-
2013/MUID/943 dated
19.09.2012
CTO to be applied
for 3 MLD STP after
completion of work.
Complied
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 169
ADB Loan No. 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Town Work (Package No.) Applicable
Legislation/ Type of
clearance
Clearance given by and
date
Subject
/ Issue
Remarks/ Action
needed
Board
Consent to operate
will be required
before operation
Consent to establish
valid up to 31.07.2015
Consent to establish has
been obtained from
RPCB for 3 MLD STP
under WW/11 which is
valid upto 30/09/2017
Consent to operate 10
MLD STP has been
obtained via order no.
2016-2017/PLG/1019
dated 23/02/2017 valid
upto 31/12/2018 under
package WW/05.
Barmer
(Tr-2)
Waste Water
(RUSDIP/TR-
02/BMR/WW-03)
Lot-2
Water (Prevention
and Control of
Pollution) Act. 1974/
Consent to establish
of 10 MLD STP from
Pollution Control
Board
Consent to operate
will be required
before operation
Consent to Establish
obtained from Pollution
Control Board – Order
No. 2012-
2013/MUID/945 dated
19.09.2012
Consent valid upto
31.07.2015
Work completed
Application for Consent
to Operate has been
submitted to RPCB on
16.08.2016.
Deficiency letter
issued by RPCB
dated 22/05/2017
agaisnt the
submitted CTO. The
same is under
process.
IPIU/ DSC to follow
up with RPCB.
Trial run under
progress.
STP will be
operational after
getting Consent to
Operate.
Nagaur RUSDIP/TR-
02/NGR/WW/02
(Lot-2)
Water (Prevention
and Control of
Pollution) Act. 1974/
Consent for 8 MLD
STP from Pollution
Control Board
Consent to Establish
obtained from Pollution
Control Board – Consent
valid upto 31.07.2015
by RSPCB order No.
2012-2013/MUID/ 944
CtE renewed via order
number 2016-
2017/PLG/1011
Consent valid upto
31.07.2018
Application for CTO
submitted to RPCB
Deficiency letter
issued by RPCB
dated 12/05/2017
agaisnt the
submitted CTO. The
same is under
process.
CTE complied.
IPIU/ DSC to follow
up with RPCB for
issue of CTO.
STP will be
operational after
getting Consent to
Operate.
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 170
ADB Loan No. 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Town Work (Package No.) Applicable
Legislation/ Type of
clearance
Clearance given by and
date
Subject
/ Issue
Remarks/ Action
needed
Rajsamand
(Tr-2)
Waste Water
(RUSDIP/TR-
02/RSM/WW-01)
Package No.
changed as
RSM/WW/03 Lot-1
& Lot-2
Water (Prevention
and Control of
Pollution) Act. 1974/
Consent to establish
of 5 MLD STP from
Pollution
Control Board
Consent to operate
will be required
before operation
Consent to Establish
obtained from Pollution
Control Board – Order
No. 2012-
2013/MUID/877
dated 30.07.2012
Consent valid upto
30.04.2015
CtE renewed via order
number 2016-
2017/PLG/1010 and
valid upto 30/04/2018
CTO applied on
25/05/2017
Complied
Rajsamand
(Tr-2)
Water supply
(RUSDIP/TR-
02/RSM/WS-01)
Package No.
changed as
RUSDIP/TR-
02/RSM/WS-03
Water (Prevention
and Control of
Pollution) Act. 1974/
Consent to establish
of 17 MLD WTP from
Pollution Control
Board
Consent to Establish
obtained from Pollution
Control Board – Order
No. RPCB/ROU/Raj/W-
4/6155 dated 27.11.08
received on 02.04.09
Validity of the consent is
not written in the CTE
received
Consent to Operate has
been obtained via order
no. 2014-2015/
Bhilwara/3406 dated
05/12/2014
Validity- 06/03/2014 –
28/02/2019
Nil Complied
Bundi Waste Water
(RUSDIP/TR-
02/BND/WW-06)
Water (Prevention
and Control of
Pollution) Act. 1974/
Consent to establish
for 8 MLD STP from
Pollution control
board
Application to obtain
consent to Establish for 8
MLD STP has been
submitted on 30.03.2015
to RPCB.
The same is under
process at RPCB.
Application to
obtain Consent to
Establish was
submitted to RPCB
on 21/12/2015.
DSC/ IPIU to follow
up with RPCB.
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 171
ADB Loan No. 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Tranche-03
City Work(Package
No.)
Applicable
Legislation/
Typeof clearance
Clearancegivenbyand
Date
Subject
/Issue
Remarks/
Action
needed
Karauli Waste Water
(RUSDIP/TR-
03/KRL/WW/04)
Water
(Prevention
andControlof
Pollution) Act.
1974/
Consent to
establish of 5
MLDSTPfrom
Pollution
ControlBoard
Consent to establish
fromPollution Control
Board obtained vide order
No. 2012-
2013/MUID/883 dated
07.08 2012 valid up to
31.03.2015
Application for renewal of
CtE has been submitted to
RPCB.
Contractor terminated
CTE renewal is
under process with
RSPCB. Deficiency
letter issued dated
15/07/2016.The
same is under
process.
Contractor
terminated. Work
stopped.
DSC/ IPIU to
follow up with
RPCB to obtain
CTE.
Consent to
operate will be
required before
operation
Bharatpur Waste Water
(RUSDIP/TR-
03/BPR/WW/01
Lot2)
Water
(Prevention
andControlof
Pollution) Act.
1974/
Consent to
establish of 8
MLDSTPfrom
Pollution
ControlBoard
Consent to establish
fromPollution Control
Board obtained vide order
No. 2012-
2013/MUID/889 dated
13.08 2012 valid up to
30.11.2014
Consent to establish
renewed via order no.
2016-2017/PLG/1017
dated 14/02/2017 valid
till 30/11/2017.
Consent to operate will
be applied when work is
completed, before
operation.
Nil CTE Renewed
Complied.
Consent to
operate will be
required before
operation
Churu Waste Water
(RUSDIP/TR-
03/CHU/WW/01)
Water
(Prevention
andControlof
Pollution) Act.
1974/
Consent for
establish of 7
MLDSTPfrom
Pollution
ControlBoard
Consent to
operatewillbe
required
before
operation
Consent to establish
From Pollution Control
Board obtained vide order
No. 2014-
2015/MUID/2934 dated
24.032015 valid up to
31.07.2016.
Work completed
Application for Consent to
Operate has been
submitted during the
reporting period.
Under process at
RPCB
Follow up with
RPCB to obtain
CTO.
Application
submitted in
Sept. 2016.
Baran WaterSupply
(RUSDIP/TR-
03/BRN/WS/01)
Water
(Prevention
andControlof
Pollution) Act.
1974/
Consent to Establish
obtained fromPollution
Control Board
2012/SWMC/1338 dated
21.10.2011
Nil Complied
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 172
ADB Loan No. 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Consent to
establishof21
MLD WTP from
Pollution
ControlBoard
Consent valid up to
30.11.2013
Consent to Operate
obtained fromPollution
Control Board
2015-2016/Kota/2307dated
17.06.2015
Consent valid up to
31.03.2018
Chittorgarh Waste Water
(RUSDIP/TR-
03/CHT/WW-01-
Lot02)
Water
(Prevention
andControlof
Pollution) Act.
1974/
Consent to
establish of 5
MLDSTPfrom
Pollution
ControlBoard
Consent to
operatewillbe
required
before
operation
Consent to Establish
(CTE) obtained from
Pollution Control Board via
order no. 2011-
2012/MUID/818 dated
20/01/2012 valid till
31/1/2014
Application for renewal of
Consent to establish has
already been submitted to
RPCB
CTE under process
at RPCB.
Consent to
establish is
pending from
RPCB. IPIU and
DSC to follow
up with RPCB.
Consent to
operate has to
be applied
before
operation.
Chittorgarh Water Supply-
(RUSDIP/TR-
03/CHT/WS/01)
Water
(Prevention
andControlof
Pollution) Act.
1974/
Consent to
establishof22.5
MLD (15 at Sengwa
+ 7.5 MLD) WTP
from Pollution
ControlBoard
Consent to
operatewillbe
required
before
operation
Consent to Establish
(CTE) for WTP at
SanghwaHousingBoard
&BherdaMinesobtained
fromPollution Control
Board Vide order no.
2011-2012/
Chittorgarh/390 and
2011-
2012/Chittorgarh/397
dated 16.12.2011 &
28.12.2011
Both the Consent valid
upto 31.10.2016
Consent to operate
obtained via order number
2015-2016/ Chittorgarh/
2056 dated 22.02.2016 for
7.5 MLD STP at Bherda
which is valid till
31.01.2020.
Consent to operate
obtained via order number
2015-2016/ Chittorgarh/
2115 dated 5.05.2016 for
15 MLD STP at Sengwa
which is valid till
31.01.2020
Work completed in
Dec 15
Complied
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 173
ADB Loan No. 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
C). Compliance of Environmental Loan Covenants
Table 31: Status of o plia e of ADB’s ajor E viro e tal Loa Cove a ts
Project Specific Covenants Status / Issues
Environmental
1.The EA shall ensure that: (LA Sched 5 Para 13)
(a) the project is carried out and all subproject facilities designed,
constructed, operated, maintained, and monitored in compliances
with the environmental law and regulations of the Borrower, the
state, ADB s E i o ental Policy (2002), and the EARF;
Under compliance in accordance with ADB
Environmental Policy and Environmental Assessment
Guidelines
2. Subproject encroaching any National Park or its buffer zone shall
not be included in the Project; however, Subproject in or close to the
wildlife sanctuary or any other environmentally sensitive area may
be allowed subject to the EA obtaining all statutory clearances;
No subproject will be taken up encroaching any
National Park or its buffer zone.
No sub-project in or close to the wildlife sanctuary or
any other lower grade environmentally sensitive area
recorded till date.
If it happens in future, environmental clearance will
be taken up as per Govt. procedure
3 an IEE as required, including an EMP with budget identifying the
cost of its implementation as incorporated in the related bid
document if any, when adequate public consultation for each sub-
project, in accordance with the EARF shall be submitted to ADB for
review and approval before award of related contract. In case of any
EIA or SIEE for sub-project classified as A or B sensitive, this shall be
su je t to the da pu li dis losu e e ui e e t u de ADB s Environmental Policy (2002, 2009)
An IEE have been prepared for each sub-project
where EMP, budget for application of EMP and issues
of public consultation are enclosed.
Budget and EMP components are incorporated in the
bid document
All the reports approved by ADB.
At present all the sub-projects are classified as class B
(only IEE will be required)
As per National rules EIA will be required for landfill
site handling more than 50 MT/day municipal solid
waste
4 all mitigation measures identified in the IEE, SIEE, EIA or SEIA and
the related EMP, as applicable, for each sub-project, shall be
incorporated in sub-project design, and carried out during
construction, and O & M, and disclosed to the stakeholders;
Under compliance: IEE screening of potential
environmental impact and mitigation measures
applied according to project location, specific sector
development and associated design requirements.
EMP s p epa ed a d egula l o ito ed fo compliance of stated mitigation measures.
During construction process within the city
consultation with local communities on
environmental issues are considered
Last EMP semi-annual Report (Jan – June 2016)
submitted and approved by ADB.
5 if there are any changes in specific locations or alignments of any
sub-project facilities after completion of the process of IEE (or EIA) or
due to detailed design or implementation that has an impact on the
environmental assessment carried out thus far, then additional
environmental assessment shall be carried out in accordance with
ADB s E i o e tal Poli , 9 a d the EA‘F, a d p io approval of ADB obtained before further physical implementation of
the sub-project;
EMP already revised in case of change of scope/
location for few sub-projects under Tr-2.
In case of change in scope or location IEE will be
revised.
For minor change in location of project facilities EMP
has been revised for monitoring purpose
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 174
ADB Loan No. 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Project Specific Covenants Status / Issues
6 all environmental clearances required by applicable laws, and
regulations at Borrower, State, or local levels shall be obtained in a
timely manner, prior to commencement of civil works for the
relevant subproject
Under compliance: All necessary clearances presently
under pursuance. Specific clearance details are now
compiled for appropriate contract packages.
Clearance Plan prepared to a scheduled timeframe,
which is monitored for submissions to the various
agencies in obtaining the necessary clearances.
7 semi-annual progress reports on the implementation of the EMPs,
measures under the IEE/EIA, and the environmental monitoring shall
be carried out as a part of the project. Implementation for review
and disclosu e i a o da e ith ADB s Pu li Co u i atio s Policy (2005)
Semi -annual progress report on application of EMP is
being prepared regularly
Field monitoring continued as per monitoring plan
During construction process within the city
consultation with local communities on
environmental issues has already initiated and
continued in most of the locations
D). Environmental Organization and Management
23. Environmental issues of the project coordinated by an Environmental Specialist within the IPMU/
IPMC, who ensures that all subprojects, comply with environmental safeguards. An Environmental Monitoring
Specialist (EMS) who is part of the DSC team implement the Environmental Monitoring Plan from each IEE to
ensure that mitigation measures are provided and protect the environment as intended. Figure 1 shows
institutional responsibility for implementation of environmental safeguard monitoring at different level.
Details about the mobilization schedule of environmental safeguard personals are provided in Annexure 5.
24. EMP shows that most of the mitigation activities are the responsibility of the Construction Contractors
(CC) employed to build the infrastructure during the construction stage or the O&M Contractors employed to
conduct maintenance or repair work when the system is operating. Responsibility for the relevant measures
assigned to the Contractors via the contracts through which they are appointed, so they legally required taking
the necessary action. There are also some actions that need to be taken by LSGD in their role as project
proponent, and some actions related to the design that would be implemented by the DSC.
25. A program of monitoring would be conducted to ensure that all parties take the specified action to
provide the required mitigation, to assess whether the action has adequately protected the environment, and
to determine whether any additional measures may be necessary. This would be conducted by a qualified
Environmental Monitoring Specialist (EMS) from the DSC. The EMS responsible for all monitoring activities and
reporting the results and conclusions to the IPMU, and recommend remedial action if measures are not being
provided or are not protecting the environment effectively. The EMS may be assisted by environmental
specialist in particular technical fields, and junior or medium-level engineers of IPIU (designated as
environmental officer) who can make many of the routine observations on site. Post-construction monitoring
will be conducted by the relevant Government Agency (GA) to whom responsibility for the infrastructure will
pass once it begins to operate4.
4 In the operational period some infrastructure will be the responsibility of the Municipal Boards/Councils, whilst others will be the
responsibility of the appropriate branch of the State government (such as PWD, PHED, etc)
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 175
ADB Loan No. 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
26. EMP shows that most of the mitigation measures are fairly standard methods of minimizing
disturbance from building in urban areas (maintaining access, planning work to avoid sensitive times, finding
uses for waste material, etc), and experienced Contractors should be familiar with most of the requirements.
Monitoring of such measures normally involves making observations in the course of site visits, although some
require more formal checking of records and other aspects. There are also be some surveys of residents, as
most of the measures are aimed at preventing impacts on people and the human environment.
E). Grievance Redressal
27. The City Level Committee (CLC), acting as a grievance redress committee (GRC) is chaired by the
District Collector with representatives from the ULB, state government agencies, IPIU, community-based
organizations (CBOs) and NGOs. As GRC, the CLC meets at regular intervals based on the availability of the CLC
/GRC members and also as per requirement or pending issues. The grievance redress mechanism is provided
at Figure 2. The information w.r.t CLC/GRC is communicated to APs personally by the ACO in the concerned
town. Further, the complete detail of the CLC meeting is also displayed at the IPIU notice board and the notice
oa d of the olle to s offi e too.
28. IPIUs along with ACOs and DSCs have been entrusted with the responsibility to maintain a proper
register of the grievance (if any) which will be endorsed by the all three agencies involved in implementation.
General directions for registering grievances of APs were communicated in the meeting organized on
26.12.2011 followed by minutes issued vide letter no. 32060-67dated 30.12.2011. GRC registers are in place at
all the towns. Further ACOs have been given instructions to arrange more public consultations and register all
the grievances (including verbal) in writing whether substantial or non substantial and put them up for the
perusal of IPIU for proper disposal.
29. During this reporting period about 71 Grievances were received during past 6 months but these
grievances were generally related to issues like water line damages, road restoration, excess / accumulation of
soil moulds etc. A high number of grievances reported in Bharatpur (23). Detail about other towns is provided
in Table No. 32.
30. These grievances are resolved by the IPIUs as and when received. But grievances like demand of water
or sewerage connection/line etc. are resolved as per the scope of work through proper approval from RUIDP.
Table 32: Town-wise number of Grievances
Sl. No Town Number of
Grievance Sl. No Town Number of Grievance
1 Alwar 4 9 Jaiselmer 0
2 Baran 0 10 Jhalawar 0
3 Barmer 2 11 Karauli 0
4 Bharatpur 10 12 Nagaur 2
5 Bundi 6 13 Rajsamand 10
6 Chittorgarh 0 14 Sikar 0
7 Churu 2 15 SwaiMadhopur 0
8 Dholpur 5 Total 41
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 176
ADB Loan No. 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Figure 1: Institutional Responsibly-Environmental Organization RUSDIP
Ministry of Urban Development (MoUD), LSGD-
EA
Government of Rajasthan
Rajasthan Urban Sector
Development Investment
Program (RUSDIP)
Implementing Agency
Investment Program Implementation
Units (IA - IPMU)
Several Construction Packages for
different tranches under each
IPIU(Nominated Environmental Monitoring
Engineer/ Officer)
Design and Supervision
Consultants(DSC)
Construction Contractors (CC)
Environmental Monitoring Specialist
(EMS) Provided by DSC
Independent Environmental
Testing & Monitoring Agency
(On need basis)
IMPLEMENTATION OF
EMP
ADB
Investment Program
Management Consultancy
(IPMC)
Appointed by RUSDIP
Environmental
Expertof IPMC
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 177
ADB Loan No. 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
CLC = City Level Committee,
GRC = Grievance Redress Committee,
IPIU=Investment Program Implementation Unit,
IPMU = Investment Program Management Unit,
NGO = Nongovernmental organization,
SDS = Social Development Specialist.
Not Addressed
APs
IPIU
IPMU
Grievance
Addressed
GRC/CLC
Grievance
Addressed Not Addressed
Grievance
Addressed
Figure 2 Grievance Redressal Process
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 178
ADB Loan No. 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
IV. ENVIRONMENTAL MONITORING AND EVALUATION
31. For effective monitoring, selected environmental parameters have been identified as indicators which
may be qualitatively and quantitatively measured and compared over a period of time in order to
assess/ensure the compliance of EMP. The environmental performance indicators are physical, biological and
social characteristics identified as most important in affecting the environment at critical locations all along the
sub-project corridors. The parameters identified as performance indicators are:
Air, noise and water quality
Compliance to EMP
Compliance to local/state/national environmental regulations
32. After starting of construction work for Intake, STP, WTP air pollutants should be measure at core and
buffer zone of the proposed STP. WTP site. If any water body exists near the STP, WTP physico-chemical
properties of the water should be measure as part of base line environment.
33. Also during construction of landfill site monitoring in respect to air, noise, and water quality are
required.
34. At bridge construction site monitoring of ambient air quality are also necessary.
35. At pipe laying area air and noise quality monitoring should be done as per scope of work depicted in
Annexure 3.
36. Air, water and noise quality monitoring has not been carried out during this reporting period as most of
the excavation works and works related to heavy machinery are completed in most of the towns. Work order
for monitoring was issued for towns of Rajsamand, Bundi, Bharatpur and Dholpur. Monitoring for these towns
will be carried out in the next reporting period.
37. Ambient Air Quality Monitoring - It is indispensable to assess the existing ambient air quality of the
environment for baseline information in order to quantify the impact of the proposed project activities on the
ambient air quality of the site. The existing ambient air quality at the proposed project site was assessed with
respect to Respirable Particulate Matter (PM ), Particulate Matter (PM .₅), Sulphur dioxide (SO ), Nitrogen
dioxide (NO ) and Carbon monoxide (CO), measured through an intended field monitoring.
38. Selection of Sampling Locations and Methodology of analysis - Meteorological conditions and landuse
type of the likely impacted areas near to the proposed project construction sites were taken into account while
deciding on sampling locations for assessing ambient air quality of the study area. The methodology adopted
for analysis is summarized in Table 33.
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 179
ADB Loan No. 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Table 33: Methodology of Sampling and Analysis and Equipment Used
SN Parameter Protocol Analysis Procedure Instrument Used
1 PM 10 IS: 5182 (Part-23)-2006 Gravimetric High volume Sampling using Respirable Dust
Sampler APM 460 BL
2 PM 2.5 Instrument manual Gravimetric Fine Particulate Sampler APM 550
3 SO2 IS: 5182 (Part-2)-2001 Colorimetric Spectrophotometer
4 NO2 IS: 5182 (Part-6)-1975
Reaffirmed 1998 Colorimetric Spectrophotometer
5 CO IS: 5182 (Part-10)-1999 Colorimetric Spectrophotometer
39. Air, water and noise quality monitoring has not been carried out during this reporting period. As major
work has been completed in most of the sub projects monitoring for the last reporting period shall be
considered to be the last monitoring . Work order has been issued for monitoring in Bundi, Chittorgarh and
Rajsamnd, where monitoring shall be carried out in the next reporting period.
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 180
ADB Loan No. 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
V. CONCLUSIONS AND RECOMMENDATIONS
40. For protection of local environment during construction phase application of mitigation measures
started as per specified EMP. Pubic consultation during construction/implementation phase has been carried
out inBundi, Rajsamand, Chittorgarhand Jhalawar.The issues and public opinion are shown in Annexure 4.
The project specific lapses, corresponding recommendations with responsibility are presented in Chapter II of
the report.
41. For proper implementation of EMP during various phases of project execution, review meeting and
training are being organized by IPMC quarterly. The representative of all IPIUs (Nodal officers), environmental
personal of DSCs and CAPP staff attended the same. The details of mobilization schedule are presented in
Annexure 5.
42. Photographs of completed work is shown in Annexure -6.
43. The status of compliance with EMP for sub-project under tranche-1,2 &3 has been discussed in Table
5 to Table 28 of Chapter II of the report including action required for lapses and responsibility for the same.
44. The environmental monitoring was conducted in the last reporting period in most of the towns and it
will be considered as the final monitoring at completion as most of the projects are about to be completed.
45. Improvements are observed in compliance of EMP activities in the present report as compared to the
last report except, major works are completed in the reporting period in most the project towns.
46. Improvement in use of PPEs are also observed although more attention and awareness is required to
achieve full compliance level. Improvement is required in Labour camps condition. The contractors have been
instructed to provide basic facilities in all labour camps. IPIU and DSC are monitoring to ensure the same. The
main area of concern has been summarized below
Environmental Statutory Clearance: The consent to establish has been obtained from Rajasthan
Pollution Control Board (RPCB) to establish STP at Bharatpur, Dholpur 3 MLD STP, Karauli, Nagaur,
Barmer and Rajsamand and for WTP in Dholpur and Rajsamand. Consent to Operte has been
obtained for Dholpur 10 MLD STP which is valid till 31/12/2018. The work of STP at SawaiMadhopur
has been completed thus consent to operate has been obtained from RPCB which expired on
31.08.2015 and renewed on 07/10/2016 which is valid till 31/03/2019.The civil work of Dholpur WTP
is complete, Consent to operate from RPCB is under process. Consent from RPCB for RMC plant
established for Bharatpur circular road package has been obtained. The consent to establish 3 MLD
STP at Dholpurhas been obtained with is valid till September 2017. The work of 10 MLD STP at
Dholpur has been completed thus consent to operate has been applied for and at present under the
process with RSPCB.The civil work of Rajsamand WTP is completed Consent to operate from RPCB
has been obtained. Consent to establish for RMC plant established for Bharatpur circular road
package has been obtained. Permission for cutting of trees for Sikar road package has been obtained
from forest department.
Air, Water & Noise Quality: The final environmental monitoring has been completed in the last
reporting period in most of the towns . Regarding monitoring in Chitttorgarh, Rajsamand and Bundi,
work order was issued to the monitoring agency but monitoring was not carried out by the
monitoring agency and monitoring will be conducted at the earliest.
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 181
ADB Loan No. 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Landscape and Aesthetics: The unusable extra excavated materials are being disposed at low laying
area in consultation with ULBs. Some grievances related to removal of soil mounts and proper
leveling of backfilled soil were received in towns which were resolved accordingly. However
excavated soil management is required to be prepared.
Socio-Economic – (Income & Employment): It was observed in few cases that proper access across
open trenches for people and vehicles has not been provided. Some grievances were also received in
this regard in towns. In this regard contractor has instructed to provide walkways and metal sheets
where required to maintain access. As far as engagement of local labour is concern, in all cases more
than 50% of the work force has been appointed locally.
Occupational Health and Safety: Improvement in use of personal protective equipment (PPE) has
been noticed. DSC and CAPP personal have been instructed to conduct more trainings and awareness
campaigns to motivate the labors to achieve full compliance. The qualified First-aid facility is available
at most of the sites. It should be ensured that first-aid facilities are available at all sites all the time
without fail. Few contractors have appointed safety officer at site, other have been instructed for
compliance immediately.
Work Camps: The basic facilities in worker camp needs to be improved as per EMP. Contractor has
been instructed to provide proper Sanitary and solid waste management facilities in all work camps.
Cooking gas has been provided in most of the camps to avoid cutting of trees for firewood.
47. Apart from these common lapses to achieve full EMP compliance, sub-project wise status of EMP
compliance and recommended mitigation measure have been discussed in Chapter II of the report.
48. Necessary instructions have been given to the contractor by concerned DSC/IPIU for improvement in
compliance level. Following are the recommendations on the basis of the findings of the report
ensure regular monitoring for complete compliance on the lapses observed in bi-annual
environmental monitoring reports (EMR)
provide copy of the environmental monitoring results to the concern contractors to take necessary
actions and include the mitigation measure in the training program for high levels of observed
parameters.
ensure timely completion of environmental monitoring in all towns in future.
In case of any change in scope/location of project components, environmental assessment for the
same is required following approval of revised IEE from ADB.
Conduct ground water monitoring to assess any impact on ground water quality due to construction
activities for each sub-project as suggested by ADB
ensure training for field staff including construction contractor staff on regular basis
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 182
ADB Loan No. 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Annexure 1: Environmental Legislation and Pollution Control Acts
The Government of India has formulated various policy guidelines; acts and regulations aimed at the
sustenance of environment in general, which are briefly summarized and applicable acts with the projects,
are described in the following sub-sections.
Environmental Legislation and Pollution Control Acts
Sl. No. Sources Legislation
1 Water Pollution The Water (Prevention and Control of Pollution) Act, 1974, as amended in 1988
2 Air Pollution The Air (Prevention and Control of Pollution) Act, 1981, as amended by Amendment Act, 1987
3 Noise Pollution The Noise Pollution (Regulation and Control) Rules, 2000
4 Environment The Environment (Protection) Act, 1986
5 Public Liability The Public Liability Insurance Act, 1991
The Public Liability Insurance Rules, 1991
6 Hazardous Waste Hazardous Waste (Management and Handling) Rules, 1989
Batteries (Management and Handling) Rules, 2001
Manufacture, Storage and Import of Hazardous Chemical Rules, 1989
Emergency Planning Preparedness and Response for Chemical Disasters Rules, 1995
Manufacturing, Use, Import, Export and Storage of Hazardous Microorganisms, Genetically
Modified Engineered Organisms or Cell Rules, 1993
Hazardous Microorganisms and Genetically Modified Organisms (Manufacture, Use Import Expert
and Storage) Rules, 1999
Bio- Medical Waste (Management and Handling) Rules, 2000
7 Municipal Solid Waste Municipal Solid Waste (Management and Handling) Rules, 2000
Recycled Plastics Manufacturing and Usage Rules, 1999
8 EIA Notification The Ministry of Environment and Forests has revised the EIA notification, 1994, and issues the
revised EIA notification on 14th September 2006
9 Use and Management
of Explosive
The Explosives Act, 1884 and The Explosives Rules, 1983
The Environment Protection act, 1986 and the EIA Notification, 1994
The Environmental (Protection) Act, 1986 is the umbrella legislation providing for the protection of
environment in the country. This Act provided for the Environment (Protection) Rules, which have been
fo ulated u de the a t The E i o e tal I pa t Assess e t Notifi atio , 99 a d the A e d e ts / ‘e ised EIA otifi atio o th “epte e .a d Yea 9.
The Forest (Conservation) Act, 1980
The Forest (Conservation) Act, 1980 pertains to the cases of diversion of forest area and felling of roadside
plantation. Depending on the size of the tract to be cleared, clearances are applied for at the following levels
in the governments:
If the area of forests to be cleared or diverted exceeds 20 ha (or, 10ha in hilly area), the prior permission of
the Central Government is required;
If the area of forest to be cleared or diverted is between 5 to 20 ha, the Regional Office of Chief Conservator
of Forests is empowered to approve;
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 183
ADB Loan No. 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
If the area of forest to be cleared or diverted is below or equal to 5 ha, the State Government can give
permission;
and If the area to be clear-felled has a forest density of more than 40%, permission to undertake any work is
needed from the Central Government, irrespective of the area to be cleared.
The Wildlife (Protection) Act, 1972
The Wildlife Protection Act has allowed the government to establish a number of National Parks and
Sanctuaries over the past 25 years, to protect and conserve the flora and fauna of the state.
The Water and Air (Prevention and Control of Pollution) Acts 1974
The water (Prevention and Control of Pollution) Act, 1974 resulted in the establishment of the Central and
State level Pollution Control Boards whose responsibilities include managing water quality and effluent
standards, as well as monitoring water quality, prosecuting offenders and issuing licenses for construction
and operation of certain facilities. The SPCB is also empowered to set air quality standards and monitor and
prosecute off enders under the air (Prevention and Control of Pollution) Act, 1981.
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 184
ADB Loan No.: 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Annexure 2: Major works and progress-
Tranche 01
Locations Sub-projects Components (Package No.) What type of works continued at present Expected
changes from
approved scope
Fulfillment of objectives-
Type of remedial
measures needed
Key assumptions and
risks that affect
attainment of the
objectives
Alwar WasteWater - Supply, laying, jointing,
testing and commissioning of various
Main and arterial sewer Network
connecting to outfall, along with road
restoration and all necessary manholes
appurtenances etc. at Alwar town.
(RUSDIP/TR-01/ALW/WW/03)
Outfall (17.0 Km): 14.33 Km laid
Lateral Sewers (15.0 Km): 14.5 Km laid
Manholes (668 Nos.): 1080 Nos.
Hydro-testing:
1. Outfall (14.33 Km):14.33 Km
2. Laterals (14.5 Km): 14.5 Km
3. Manholes (668 Nos.): 1080 Nos.
Road Restoration (7.38 Km): 6.76 Km
Sewer Connections (1707 Nos.): 824 Nos.
No change
expected
o Effective monitoring
and application of
EMP
No risk
Alwar Waste Water:Additional Sewerage
System in UIT colonies at Alwar
(RUSDIP/TR-01/ALW/WW/05)
Outfall (7.43 Km): 6.59 Km laid
Lateral Sewers (40.81 Km): 38.49 Km laid
Manholes (1541 Nos.): 1365 Nos.
Hydro-testing:
1. Outfall (3.07 Km): 4.53 Km
2. Laterals (17.10 Km): 24.21 Km
3. Manholes (693 Nos.): 1365 Nos.
Road Restoration (15.01 Km): 14.83 Km
Sewer Connections (3964 Nos.): 1468 Nos.
No change
expected
o Effective monitoring
and application of
EMP
No risk
Jaisalmer Water Supply - Providing, Laying,
Jointing, Testing & Commissioning of
water pipe line for the strengthening of
distribution system and rising main
pipeline; Construction and
Commissioning of Elevated service
Supply from three reservoirs JNV Colony,
Gaffur Bhatta and JNV colony has been
started. Pump houses at GajroopSagar and
Gaffur Bhatta has been commissionedPipe
line procured:- 67.13 km ( DI- 7.8 km, uPVC-
No change
expected till
date.
o Effective monitoring
and application of
EMP
No risk
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 185
ADB Loan No.: 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Locations Sub-projects Components (Package No.) What type of works continued at present Expected
changes from
approved scope
Fulfillment of objectives-
Type of remedial
measures needed
Key assumptions and
risks that affect
attainment of the
objectives
reservoirs and providing pumping system
and ancillary works {RUSDIP/TR-01/
JSL/WS-02}
59.33km )
Pipe line Laid- 61.4 Km( DI-7.69 Km, uPVC-
53.82Km)
Line commissioned: 41.608 km (DI- 7.305
km, uPVC- 34.303 km).
ESR- 03 Nos completed
Domestic water Meter- 5000 nos procured,
4583nos installed.
Line tested- 41.608 Km ( DI- 7.305 Km, uPVC-
34.303 Km)
Interconnection and laying of distribution
line works in under progress.
Jaisalmer Waste water - Sewerage and Waste
stabilization Ponds in Phase-I in Jaisalmer
{RUSDIP/TR-01/ JSL/WW-01}
Outfall (7.31Km) – completed 7.31 km
Lateral (35.566 Km) – 25.63 Km
Man Hole- 1130 Nos completed
STP – 95 % fencing work completed
No change
expected
o Effective monitoring
and application of
EMP
No risk
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 186
ADB Loan No.: 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Tranche 02
Locations Sub-projects Components
(Package No.)
What type of works continued at present Expected changes
from approved
scope
Fulfillment of
objectives- Type of
remedial measures
needed
Key assumptions and
risks that affect
attainment of the
objectives
Alwar Waste Water: Waste Water work
in Alwar
Package No: {RUSDIP/TR-02/
ALW/WW/06}
Main Line : out of 9.98 km, 8.323 km completed
Lateral Line: out of 48.49 km, 40.021 km completed
Manhole :out of 2425 nos. 1811 nos. completed
Property connections: out of 7673nos. 1635 nos. completed
No change
expected
o Effective monitoring
and application of EMP
No risk
Bharatpur Bridge Project: Reconstruction of
ROB at Bharatpur
(RUSDIP/TR-02/BPR/BR/02)
65% Work completed for ROB No change
expected
Effective monitoring
and application of EMP
No risk
Dholpur Water Supply: Design, Construction
and Commissioning of 15 MLD
capacity Water Treatment Plant
including commissioning of
equipments at Sagarpada;
Construction of CWRs & OHSRs
including supply, laying and
commissioning with testing of DI &
uPVC pipelines and replacing of
leakaged pipeline etc. for UWSS
Dholpur.
{RUSDIP/ TR-02/ DLP/WS/03}
DI pipe line:- Procured= 12.723 km, Laid=12.63 km, Testing =
12.63 km, Commisioned= 12.63 km
uPVC pipe line:-Procured=77.71 km, Laid= 73.3 km, Testing =
73.3 km, Commisioned= 73.3 km
OHSR -- 4 Nos. OHSR completed & 2 Nos. OHSR Hydro testing
completed.
CWR - Both CWR completed & Hydro testing has done on 1 CWR
and painting of Bhogiram Nagar CWR completed.
Pumping station -- Pump house at Sagarpada- completed
PH at Bhogiram Nagar – completed
Civil work at WTP also completed
Water Meter (15700 Nos.): 9137 Nos.
95% work completed.
No further change
expected
Effective monitoring
and application of EMP
No risk
Dholpur Waste Water : Supply, Laying,
Jointing, Testing and
Commissioning of outfall sewer,
trunk sewers, lateral sewers,
lateral sewers along with
construction of manholes,
appurtenances etc. at Dholpur.
Sewer Line Outfall –out of 9.5 km, Laid- 9.067 km , Tested- 9.067
Sewer Line uPVC out of 69.827 kms, laid- 69.827 km completed
Manholes- 3116 manholes constructed.
Manhole tested- 1695 nos.
95 % work completed
No change
expected
Effective monitoring
and application of EMP
No risk
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 187
ADB Loan No.: 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Locations Sub-projects Components
(Package No.)
What type of works continued at present Expected changes
from approved
scope
Fulfillment of
objectives- Type of
remedial measures
needed
Key assumptions and
risks that affect
attainment of the
objectives
{RUSDIP/TR-02/DLP/WW/04}
Dholpur Waste Water: Dholpur Sewerage
work
{RUSDIP/TR-02/DLP/WW/08}
Sewage pumping stations taget -2, completed -2
Total Outfall RCC pipe (NP-4 & NP -3) : 27.32 Km procured, 27.32
Km laid completed
Lateral - target – 22.21 Kms, laid- 22.16 kms
Manholes constructed – 728 Nos. & testing done for 282 nos.
uPVC laid -5749 m .
95 % work completed
No change
expected
Effective monitoring
and application of EMP
No risk
Waste Water: Design, construction,
supply, erection, testing,
commissioning and 5 years
operation and maintenance of 3
MLD Sewage Treatment Plant (STP)
based on SBR process with sewage
pumping/lifting station including all
civil, electrical, mechanical,
pumping and allied works at
Dholpur town.
Package No.: {RUSDIP/TR-
02/DLP/WW/11}
Work completed till December 2016
1. Outfall –Target – 3.34, completed - 2.36 km
2. Lateral – Target – 26.43, completed – 19.89 km
3. Manholes –417 Nos. ( out of 960 total)
4. STP – work under progress
5. Property connections-518
No change
expected
Effective monitoring
and application of EMP
No risk
Churu Water Supply Project in churu city.
RUSDIP/ TR-02/ CHU/ WS/04
Van Vihar ESR , Kotwali ESR, JohriSagar ESR, Agrasen Nagar ESR,
Gandhi Colony ESR, work is ongoing.
Collectrorate PS, JohriSagar PS work is ongoing.
D.I. Pipes (K-9) & K-7
- Rising mains – target – 7.8 Km, completed – 5.9 Km
No change
expected
o Effective
monitoring and
application of EMP
No risk
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 188
ADB Loan No.: 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Locations Sub-projects Components
(Package No.)
What type of works continued at present Expected changes
from approved
scope
Fulfillment of
objectives- Type of
remedial measures
needed
Key assumptions and
risks that affect
attainment of the
objectives
Sikar Water Supply: Construction of 7
OHSRs at different places at Sikar
{RUSDIP/TR-02/SKR/WS/04}
Distribution mains - uPVC Pipe - Procurement - 79529 meters
L&J 75425 meters, Hydro testing - 75425 meter
Construction of 07. E.S.R.
1. Hathi Tibba ESR (700 KL)
2. Kabristan ESR (800 KL)
3. Piprali Road ESR (400 KL)
4. Dharmana ESR (400 KL)
5. Teja Colony ESR (1000 KL)
6. Shiv Colony ESR (1000 KL)
Construction of 03 CWR
At Nawalgarh Headwork (1000 KL) - Civil Work completed.
Hathi Tibba (100 KL):- Removed from Scope due to change in
location of Dharmana Zone ESR..
At I.T.I Headwork (300 KL):- Civil Work completed.
Construction of 01 Pump House
Nawalgarh Headwork Pump House: - completed
House service connection (9399 nos.) :- 723 nos.
Domestic water meter (9399 nos.) – 3320 nos. against 8000.
Fixing of EMF (5 nos.) :- 5 nos. against 5nos.
Fixing of BFM (45 nos.) :-5 nos. against 45 nos.
24x7 Water Supply:-Basic survey has been done and zone
boundary marked.
No change
expected
Effective monitoring
and application of EMP
Allotment of land for
3 sites of water tanks
is pending with ULB.
(A). Azad nagar, veer
teja colony,
nawalgarh road. (B).
Dharmana, (C). Sanik
Nagar
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 189
ADB Loan No.: 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Locations Sub-projects Components
(Package No.)
What type of works continued at present Expected changes
from approved
scope
Fulfillment of
objectives- Type of
remedial measures
needed
Key assumptions and
risks that affect
attainment of the
objectives
Nagaur Waste water: STP 8 MLD
{RUSDIP/TR-02/NGR/WW/02 (Lot-
2)}
Civil work of Anaerobic pond, Facultative pond, Pretreatment unit
and Admin building has been completed.
STP – Civil – 90%, electrical & mechanical – 85% work completed
SPS & IPS – Civil 95%, E & M – 80% work completed
No change
expected
Effective monitoring
and application of EMP
No risk
Barmer Waste water:
Supply, sewer line work
{RUSDIP/TR-2/BMR/WW/03 (Lot-
1)}
Physical work:
Outfall- 5.45 Km completed
Lateral – 28.7 Km completed
Manholes – 4827 Nos. Completed
No change
expected
Effective monitoring
and application of EMP
No risk
Barmer Waste water:
STP 10 MLD
{RUSDIP/TR-2/BMR/WW/03 (Lot-
2)}
Metering and Panel Rooms door and windows fitting completed,
painting is pending.
Civil work – 100% completed
E&M work – 100% completed
No change
expected
Effective monitoring
and application of EMP
No risk
Bundi Waste water : Sewerage works,
including STP, SPS, outfall and
lateral (RUSDIP/TR-
02/BND/WW/06)
STP – Civil work under progress ( Raft reinforcement at SBR,
Chlorination room, Air Blower, Stilling chamber, Grit Chamber,
Fine screen channel, Parshall Flume & ADM building under
progress)
SPS: Civil work under progress (Inlet chamber PCC & raft of raw
sewage sump completed, wall under profress)
Outfall: 7.12 Km out of 7.12 Km completed
Lateral: 4.98 out of 7.07 Km completed
Manholes – 476 Nos. out of 538 Nos. completed
No change
expected
Effective monitoring
and application of EMP
No risk
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 190
ADB Loan No.: 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Locations Sub-projects Components
(Package No.)
What type of works continued at present Expected changes
from approved
scope
Fulfillment of
objectives- Type of
remedial measures
needed
Key assumptions and
risks that affect
attainment of the
objectives
Bundi Roads: Widening of existing road
from khoja gate to Bypass link
road.Widening of existing road
from petrol pump triangle Bypass
to rotarary club triangle via rani ji
kibawari and interlocking footpath.
(RUSDIP/TR-02/BND/ST/04)
Total Road Length completed-
1) BT road – 2.028 km out of 2.052 Km completed
2) CC Road – 13.396 km out of 13.794 completed.
3) Widening of Nainwa culvert – WIP
No change
expected
Adequate use of
PPE s o site required
No risk
Rajsamand
Design, Construction, Supply,
erection testing,
commissioningand five years
operation & maintenance of left
over works of Sewage Treatment
plant 5 MLD with Sewage pumping
station including all civil, electrical,
mechanical, pumping and other
allied works and supply, laying
joining, testing and commissioning
of outfall sewer, various Trunk
sewers, collecting and lateral
sewers along with all necessary
manholes, appurtenances etc. at
Rajsamand{RUSDIP/TR-
2/RSM/WW/ 03
Pipe line Laying –
Outfall : 0.974 Km completed out of 1.5Kms
Lateral : 12.10 Km completed out of 12.59Kms.
Manholes : 525 out of 607
STP –
Balance work remaining Civil – 10%, E & M -100%
Completed-
Civil work – 90%
E& M – yet to be started
Nil Partially fulfilled, use of
PPEs and signage needs
improvement
Use of PPEs by
workers and use of
signage in all sites is
required
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 191
ADB Loan No.: 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Locations Sub-projects Components
(Package No.)
What type of works continued at present Expected changes
from approved
scope
Fulfillment of
objectives- Type of
remedial measures
needed
Key assumptions and
risks that affect
attainment of the
objectives
Jhalawar Waste Water: Laying of Sewer line
network at Jhalawar&Jhalarapatan
town
{ RUSDIP/TR-02/JHL/WW/02}
Pipe laying done:
Total pipe laid: 21.26 Kms out of 29.70 Km
Manhole construction:
Total 500 nos. of manhole constructed out of 984 nos.
Property connections: 870 nos.
NA Partially Fulfilled
* Disposal plan of
excess excavated soil is
needed
* PUC of all vehicles and
equipments is required
* Deployment of safety
personnel from
contractor is required
* Disposal plan of
excess excavated soil
is needed
* PUC of all vehicles
and equipments is
required
* Deployment of
safety personnel from
contractor is required
* Use of PPEs by
workers needs
improvement
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 192
ADB Loan No.: 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Tranche 03
Locations Sub-projects Components
(PackageNo.)
Whattypeofworkscontinuedatpresent Expected
changes from
approved
scope
Fulfillment of
objectives- Type of
remedial measures
needed
Key
assumptions and
risks that affect
attainment of
theobjectives
Karauli Waste Water - Design,
construction, supply,erection
testing,commissioning and
firstfiveyearsoperation
&maintenance ofsewage
treatment plant5MLDnear
charagahincluding allcivil,
electrical, mechanical, pumping
andotherallied
worksatKaraulitown RUSDIP/TR-
03/KRL/WW/04
Civil Works of:
STP-1 No78% civil works completed
SPS – 3 Nos. -95%civilwork is completed
DI Pipe line only 1386 m procured without specials
No change
expected
o Effective
monitoring and
application of
EMP
Norisk
Karauli Waste Water - Supply,
laying, jointing etc. supply
,laying, jointing,testing and
commissioning ofvarious trunk
sewerage collecting and lateral
sewers connecting
tooutfall,along withallnecessary
manholes, appurtenances, etc.
at Karaulitown RUSDIP/TR-
03/KRL/WW/05
Outfall (2.65 Km): 2.65 Km laid
Lateral Sewer (28.77): 23.44 Km laid
Manholes (1152 Nos.): 1055 Nos.
90% work completed
No change
expected
o Effective
monitoring and
application of
EMP
Norisk
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 193
ADB Loan No.: 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Locations Sub-projects Components
(PackageNo.)
Whattypeofworkscontinuedatpresent Expected
changes from
approved
scope
Fulfillment of
objectives- Type of
remedial measures
needed
Key
assumptions and
risks that affect
attainment of
theobjectives
Bharatpur Supply, laying, jointing, testing,
commissioning of outfall sewer,
various trunk sewer and lateral
sewer connecting to outfall
along with all necessary
manholes and appurtenances.
RUSDIP/TR-03/BPR/WW/01 (Lot-1)
Outfall ( 8.345 Kms) - 8.345 Kms completed
Lateral lines (66.045 Kms) – 59.927 Kms completed
Manholes (2094 Nos.) – 1620 Nos.
No change
expected o Effective
monitoring and
application of
EMP
Norisk
Bharatpur Waste Water: Design,
construction, supply,
erection, testing,
commissioningandfiveyears
operation &maintenance of
sewerage pumping station,
pumpingmainandSewerage
treatmentplant8MLDnear
Ikranvillageincluding allcivil,
mechanical, pumping and
other allied works at
Bharatpur town .
RUSDIP/TR-03/BPR/WW/01
(Lot-2)
Civil works:
STP: 80%
SPS-1 (Narayan gate) : 85% completed
SPS 2 (Chandpole Gate) : 60% completed
SPS 3 (Nagla Gopal Tiraha) : 50% completed
GRP pipe line laid 919m and tested.
No change
expected
o Effective
monitoring and
application of
EMP
Norisk
Jaisalmer Waste Water - Providing,
construction,laying, jointing,
testingandcommissioning of
sewerage network system
withallappurtenances and
propertyconnections, Water
supplyDistribution
networksystem with house
service connections;under
grounding
ducting forElectricand
Lateral – 2.25 Km
Manholes completed – 208 nos.
No change expected o Effective
monitoring and
application of
EMP
Norisk
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 194
ADB Loan No.: 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Locations Sub-projects Components
(PackageNo.)
Whattypeofworkscontinuedatpresent Expected
changes from
approved
scope
Fulfillment of
objectives- Type of
remedial measures
needed
Key
assumptions and
risks that affect
attainment of
theobjectives
Telephone cables;
dismantlingandrestorationof
stoneslabpavement Inside
JaisalmerFort.
RUSDIP/TR-03/JSL/WW/06
Churu Waste Water - Design,
Construction, Supply, Erection
testing, Commissioning and five
year operation & maintenance
of Sewage treatment 7MLD
(WSP) including all civil, and
other allied Works and supply,
laying, jointing, testing and
commissioning of outfall
sewer,various Trunk sewers and
laterals sewers connecting
tooutfall,along with all necessary
manholes appurtenances etc.at
Churu town.
{RUSDIP/TR-03/CHU/WW/01}
7 MLD STP – Completed
SPS at JohriSagar – Completed
Outfall (out of 5.49 Km 5.49 Km Completed)
Lateral ( Out of 78.47 Km 66.12 Km completed)
Pumping main DI – (out of 3.806 Km – 3.806 Km
completed)
Construction of Manhole-2036 Nos.
Property connections – 1561 Nos. completed
Trenchless- 600 mm dia Subhas chowk area.
Restoration work of BT and CC is under progress.
No change expected o Effective
monitoring and
application of
EMP
Norisk
Churu Drainage - ChuruDrainage
work
{RUSDIP/TR-03/CHU/DR/03/
DR/04 }
Procurement/Manufacturing&
laying –
RCCPipe 300 mm 1400mm :2715 m
GRPPipe: 5534m
PrecastRCCBox2243m
Lohiya college pumping station – completed
Manholes = 76 Nos, has been completed
No change expected o Effective
monitoring and
application of
EMP
Norisk
Churu City road in Churu
RUSDIP/TR-03/CHU/ST/01 LOA issued, NTP issued on 23/07/2014
CC road- target – 1.3 km completed 1.3 km
No change expected Effective monitoring
and application of
No risk
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 195
ADB Loan No.: 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Locations Sub-projects Components
(PackageNo.)
Whattypeofworkscontinuedatpresent Expected
changes from
approved
scope
Fulfillment of
objectives- Type of
remedial measures
needed
Key
assumptions and
risks that affect
attainment of
theobjectives
BT road target – 1.95 km completed 1.81 km
EMP
Churu Drainage-Additionalworkof
Churudrainagework
RUSDIP/TR-03/CHU/DR/04
RCC NP3 Pipe (2.14 Kms) – 2.1 Kms
GRP Pipe (6.571 Kms) – 5.947 Kms
Pre cast RCC Box drain – (3.278 Kms) – 3.258 Kms
Pump house- 2 pump house completed
Manhole construction =86Nos.
Rubble Masonry Work =52 Mtr.
No change expected o Effective
monitoring and
application of
EMP
Norisk
Chittorgarh Waste water- Design
construction supply erection
testing commissioning and
fiveyearsoperation and
maintenance of5MLD Sewage
treatment plantnear
villageBhoikhera&Sewage
pumping stationincludingall
civil,Electrical, Mechanical works
at Chittorgarh
{RUSDIP/TR-03/CHT/WW-01
-Lot02}
STP- Civil 90% work completed and E&M – 70% work
completed.
SPS- Civil – 95% work completed and E&M – 80% work
completed.
SPS:- work is in progress
UASB Reactor:- 80% completed
Short Detention Oxidation Pond:- 95% completed
Sludge Drying Beds:- 90 % completed
Administrative cum Lab Building:- 93% completed
MCC Room cum DG set Room:- 90% completed
Staff Quarters:-completed
Security Room:- 90%completed
No change
expected o Effective
monitoring and
application of
EMP
Norisk
Chittorgarh Waste Water-Supply,laying,
joining, testing and
commissioning ofoutfall
Sewer Pipe line:
Pipe line Laying –
RCC Pipe laying – target - 21 km
No change
expected
Permission for railway
crossing through
trenchless technology
Norisk
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 196
ADB Loan No.: 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Locations Sub-projects Components
(PackageNo.)
Whattypeofworkscontinuedatpresent Expected
changes from
approved
scope
Fulfillment of
objectives- Type of
remedial measures
needed
Key
assumptions and
risks that affect
attainment of
theobjectives
sewer,various Trunkand
lateralsewersconnecting to out
fall, along withall necessary
manholes,
appurtenances, etc. at
Chittorgarh town.
{RUSDIP/TR-03/CHT/WW-01
–Lot01}
Outfall- DI Pipe laying – 1.8 Km
Lateral - UPVC laying – 6.05 Km
Man holes and property chamber:
Total No. of Manholes Made: 660 out of 1201 nos.
Property chamber:- 1166 out of 3839
is
required from GM,
Western Railway,
Mumbai.
Chittorgarh Railway Under Bridge
(RUB)-Construction ofRUB
andbothsideapproach road
(total620 meters) at
Chanderia(Packageno.
RUSDIP/TR-03/CHT/BR/03)
Approach road work of RUB Completed and work for
central portion completed by Railway Department for
which Rs. 350 Lakh has been deposited to Railway on
their demand.
All works completed handing over to Nagar Parishad is in
Progress
No change
expected
o Effective
monitoring and
application of
EMP
Norisk
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 197
ADB Loan No.: 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Annexure 3: Environmental Monitoring Schedule
Environmental Monitoring Schedule
Monitoring Project Type Parameters Frequency No. of location Remarks
Ambient Air Quality Monitoring
Air quality
parameters
STP, WTP,
pump house
SPM, RSPM (PM10 & PM
2.5), SO2, NOx and CO
4 days 24 Hrs
basis Semi-
annually
2 locations
nearby STP, WTP,
pump house site
Intake
location
SPM, RSPM (PM10 & PM
2.5), SO2, NOx and CO
2 days 24 Hrs.
basis- Semi-
annually
1 location nearby
the project site
Bridge,
Drainage
SPM, RSPM (PM10 & PM
2.5), SO2, NOx and CO
3 days 24 Hrs
basis Semi-
annually
2 locations
nearby bridge
Landfill SPM, RSPM (PM10 & PM
2.5), SO2, NOx and CO
3 days 24 Hrs
basis Semi-
annually
4 locations (one
at center and rest
at 3 locations 120
degree apart)
Pipe laying
area
SPM, RSPM (PM10 & PM
2.5), SO2, NOx and CO
3 days 24 Hrs
basis Semi-
annually
3 locations
nearby working
zone
Heritage site SPM, RSPM (PM10 & PM
2.5), SO2, Ammonia, H2S,
NOx and CO
2 days 24 Hrs
basis Semi-
annually
2 locations
nearby working
zone
Fire Fighting
station
SPM, RSPM (PM10 & PM
2.5), SO2, NOx and CO
2 days 24 Hrs
basis Semi-
annually
2 locations
nearby working
zone
Ambient Noise Level Monitoring
Sound Pressure Level STP, WTP,
pump house
Leq One time in six
months
(day & night)
3 nearby
locations
Intake
location
Leq One time in six
months(day &
night)
2 nearby
locations
Bridge Leq One time in six
months(day &
night)
5 nearby
locations
Landfill Leq One time in six
months(day &
night)
4 nearby
locations
Preferably near air
quality measuring
sites
Pipe laying
area
Leq One time in six
months(day &
night)
3 nearby
locations
Heritage site Leq One time in six
months(day &
night)
3 nearby
locations
Fire Fighting
station
Leq One time in six
months(day &
night)
2 nearby
locations
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 198
ADB Loan No.: 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Monitoring Project Type Parameters Frequency No. of location Remarks
Water Quality Monitoring
Surface water Quality
parameters
STP, WTP General: Turbidity NTU,
pH, Total Suspended
Solid, TDS, Total Hardness
as CaCO3, DO,
Organic Matters: BOD,
COD,
Nutrients: Nitrate,
Metals: Chloride,
Sulphate, Na, K, Ca, Mg,
Fe, Mn, Cd, As, Cr, Cu, Mg,
Pb, Selenium, Al, Zn, Bo,
Fluorine, Cl (residual
free),
Other Organics: Phenolic
Compound, Cyanide,
Phosphate (mg/l)
one time in six
months
2 locations
(pond, river, nala)
(if location exist)
Intake
location
Turbidity in NTU, pH,
Total Suspended Solid,
TDS, Total Hardness as
CaCO3, DO, BOD, COD
One time in six
months
2 locations
unpstream and
downstream
River bridge,
Drainage
channel
As above One time in six
months
At least 2 location
(pond, river, nala)
upstream and
downstream
Landfill site As above One time in six
months
At least 2 location
(pond, river, nala)
if location exist
Ground water Quality
parameters
Landfill site,
STP
pH, Total Dissolved Solid,
Total Hardness as CaCO3,
Dissolved Oxygen,
Alkalinity as mg/l, Cl,
Sulphate, Nitrate, Fe, Mg.
Cd, As, Cr, Co, Mg, Pb, Zn,
Fluoride Phenolic
Compound, Phosphate
(mg/l)
One time in six
months
At least 3 location
(tube well/ hand
pump/ bore well)
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 199
ADB Loan No.: 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Annexure 4
Public Consultation on Environmental Issues during Construction/ Implementation
Town Sub project
Bundi Road& waste water
Rajsamand Waste water
Jhalawar Waste Water
Chittorgarh Waste Water
Bundi–Survey Questionnaire no.1
Waste Water
PLACE OF CONSULTATION Ambedkar Circle (Sewer pipe laying 400 mm)
DATE OF CONSULTATION 31.08.2016
PROJECT NAME Bundi sewerage works
PACKAGE NO. RUSDIP/TR-2/BND/WW/06
NAME OF THE CONSULTANT Abhay Srivastava, Jyotidhari Singh
NAME OF THE PERSONS Ram Lal, Yogendra Singh (Rajshree Enterprises), Pappan (Suraj Pan shop|) (all
shopkeepers)
ADDRESS Near Ambedkar Circle, Bundi
S.No POINTS TO BE DISCUSSED REMARKS
01. Whether dust control measures are taken up by
contractor as and when required?
No, water sprinkling is not taken up to reduce dust
02. Whether traffic movement affected during
construction?
Yes, half of the road is blocked and traffic movement becomes
congested, road is full blocked during excavation and loading
activities
03. Is there any problem due to influx of outside people
(laborer)?
No problem due to the construction labors as mostly labors are
local.
04. Is there any problem, if storage area is in public place? No, all the material is stored in store yard and only required
quantity is brought to site
05 Is there any problem during transportation of
materials?
Yes during loading and unloading of excavated soil and
construction materials, traffic is blocked
06. Is there any problem due to the running of concrete
mixture/ hot mix plant or movement of equipment like
JCB?
During use of concrete mixture noise is created at project site,
sometimes traffic problem also exists during operation of JCB
07 Whether construction work affects local drainage
system/ water supply system?
Yes sometimes water supply system is disrupted during
excavation and construction works for 1-2 days, drainage
system is also affected but new drain is being constructed
alongside the road
08 Whether movement of locals/pedestrian affected
during construction?
Yes, movement of pedestrians is affected due to construction
works and excavated soil is not removed on same day resulting
no access for shopkeepers and residences
09 Whether generated noise affects the normal life of
locals?
Noise is generated but not causing any problem to nearby
people
10 Overall opinion on construction (Excellent/ Satisfactory/
Below satisfaction/ Poor)
Below Satisfactory
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 200
ADB Loan No.: 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Rajsamand – Survey Questionnaire no.1
Waste Water
PLACE OF CONSULTATION Kailash Nagar, Rajsamand
DATE OF CONSULTATION 05.10.2016
PROJECT NAME Rajsamand Sewerage Works
PACKAGE NO. RUSDIP/TR-02/RSM/WW /03
NAME OF THE FIELD SUPERVISORS Abhay Srivastava, Indira Chauhan
NAME OF THE PERSONS Ramniwas, Bapu, Dhananjay
ADDRESS Residents of Kailash Nagar, Rajsamand
S.No. POINTS TO BE DISCUSSED REMARKS
01. Whether dust control measures are taken up by
contractor as and when required?
No dust problem due to construction activities.
02. Whether traffic movement affected during
construction?
Yes, traffic movement is stopped during construction works
03. Is there any problem due to influx of outside people
(laborer)?
No problem due to the construction labors, mostly labors
are hired locally.
04. Is there any problem, if storage area is in public
place?
No, construction materials are kept on the sides of road and
create no problem
05 Is there any problem during transportation of
materials?
No such problem existed during works
06. Is there any problem due to the running of concrete
mixture/ hot mix plant or movement of equipment
like JCB?
No, lane is narrow and there is no movement of JCB in the
lane, concrete mixture create noise and dust during
operation
07 Whether construction work affects local drainage
system/ water supply system?
Yes, water supply lines are damaged at some points but
repaired on same day.
08 Whether movement of locals/pedestrian affected
during construction?
Yes, movement of locals/pedestrian is affected during
construction as road becomes closed for any movement
09 Whether generated noise affects the normal life of
locals?
Yes, noise is generated which affect the normal life
10 Overall opinion on construction (Excellent/
Satisfactory/ Below satisfaction/ Poor)
Satisfactory
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 201
ADB Loan No.: 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Jhalawar–Survey Questionnaire no.1
Waste Water
PLACE OF CONSULTATION Shitla Mata Mandir, ChipaMohalla, Jhalarapatan
DATE OF CONSULTATION 06.10.2016
PROJECT NAME Jhalawar sewerage project
PACKAGE NO. RUSDIP/TR-2/JHL/WW/02
NAME OF THE FIELD SUPERVISORS Abhay Srivastava, Jyotidhari Singh
NAME OF THE PERSONS Jagdish Chandra Chipa, SatyanarayanGurjar
ADDRESS ChipaMohalla, Jhalarapatan
S.N. POINTS DISCUSSED OPINION EXPRESSED
01. Whether dust control measures are taken up by contractor
as and when required?
Yes, dust problem exists and no water sprinkling is being
done by contractor
02. Whether traffic movement affected during construction? Yes traffic movement is blocked during pipe laying works
during day but restored in evening after completion of
works
03. Is there any problem due to influx of outside people
(laborer)?
No problem due to the construction labors.
04. Is there any problem, if storage area is in public place? No, construction materials are not stored in public place
05 Is there any problem during transportation of materials? No problems noticed due to the transportation of
construction materials.
06. Is there any problem due to the running of concrete
mixture/ hot mix plant or movement of equipment like
JCB?
Concrete mixtures and hot mix plant are not being used,
JCBs are in use and create noise
07 Whether construction work affects local drainage system/
water supply system?
Yes, sometimes water supply system is damaged during
excavation for pipe laying but repaired by contractor in one
or two days
08 Whether movement of locals/pedestrian affected during
construction?
Yes, pedestrian movement is affected during pipe laying
and road restoration works
09 Whether generated noise affects the normal life of locals? No, all the works are manual therefore no excess noise is
generated
10 Overall opinion on construction (Excellent/ Satisfactory/
Below satisfaction/ Poor)
Satisfactory
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 202
ADB Loan No.: 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Chittorgarh– Survey Questionnaire no.1
Waste Water Project
Place of Consultation Village Bhoikhera
Date of Consultation 04.10.2016
Project Name Chittorgarh Waste Water
Package no. RUSDIP/ TR-03/ CHT / WW/ 01
Name of the Field Supervisors Abhay Srivastava, ManojJat (CAPP)
Name of the Persons Consulted RaunakBhoi, ManilalBhoi, Ramji Lal
Address Residents at Bhoikhera
SL.NO. Points Discussed Remarks
01. Whether dust control measures are
taken up by contractor as and when
required?
Water sprinkling is not done by contractor to reduce
dust
02. Whether traffic movement affected
during construction?
Yes, traffic movement is affected during pipe laying,
half the road is closed for traffic and cause traffic
congestion
03. Is there any problem due to influx of
outside people (labourer)?
No problem due to the construction labors as mostly
workers come in morning and go back in the evening
04. Is there any problem, if storage area is in
public place?
No problem is caused as the material is placed beside
the road
05 Is there any problem during
transportation of materials?
No, there is no affect to the existing traffic conditions
during transportation of materials
06. Is there any problem due to the running
of concrete mixture/ hot mix plant or
movement of equipment like JCB?
Hot mix plant are not being used but during running
of JCB/excavator noise is generated but people have
no problem
07 Whether construction work affects local
drainage system/ water supply system?
Yes, several house connection of water supply broken
due to construction works, but contractor is repairing
the connections, drainage is not affected
08 Whether movement of locals/pedestrian
affected during construction?
No, movement of locals/pedestrian was not affected
during pipe laying works
09 Whether generated noise affects the
normal life of locals?
Yes noise is generated due to construction works but
people having no problem
10 Overall opinion on construction
(Excellent/ Satisfactory/ Below
satisfaction/ Poor)
Satisfactory
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 203
ADB Loan No.: 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Photographs of Public consultation
Public consultation at Nayakbadi, Rajsamand
Waste water works
Public consultation at Brahmani Mata Mandir
Chowk, Jhalawar
Public consultation at Ambedkar circle, Bundi
Public consultation at Jail road, Bundi
Public consultatons at Bhiokhera, Chittorgarh
Public consultatons at Panchvati, Chittorgarh
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 204
ADB Loan No.: 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Annexure – 5 - Mobilization schedule
PMU: Project Management Unit; IPIU: Investment Program Implementation Unit; IPMC: Investment
Program Management Consultant; DSC: Design Supervision ConsultantNote: Nodal officers are
engineer from IPIU having additional duty of safeguard
PMU
Responsibility Name Designation Duration
Overall supervision of Project and
Environmental Compliance as per ADB
Policy
Mr. D R Jangid Project Officer
Environment
Full Time
IPMC
Responsibility Name Designation Duration
Overall supervision of all 15 towns
Dr. ArdhenduMitra Environmental Expert Intermittent
Shubhra Panwar Support Engineer Full Time
Structure adopted at 15 towns
Nodal Officer of IPIU DSC Consultants
Towns Nodal Officer
Designated by PMU
DSC I
Name Designation Duration
Alwar Mr. Saurabh Kr. Tayal Mr. Manoj Kumar Research Associate Intermittent
Bharatpur Mr. Rajendra Gupta
SawaiMadhopur Mr. Kush Kumar
Dholpur Mr. Nawal Sharma Mr. Ayyaz Environmental
Monitoring Specialist
Full time
Karauli Mr. Yogesh Kumar
Towns Nodal Officer
Designated by PMU
DSCII
Name Designation Duration
Jaisalmer Mr. Amit K. Kumawat Dr. Amar Sarkar Research Associate Intermittent
Sikar Mr. Ashok Kadwasara
Churu Mr. Dinesh Choudhary Md. Zuber Support Engineer Intermittent
Nagaur Mr. Suresh Kumawat Mr. Dinesh Choudhary Support Engineer Intermittent
Barmer Mr. Sunil Bishnoi Mr. Manoj Tiwari Support Engineer Intermittent
Towns Nodal Officer
Designated by PMU
DSC III
Name Designation Duration
Bundi Ms. Krishna Murari
Sharma
Mr. AbhaySrivastav Research Associate Intermittent
Baran
Jhalawar Mr. Pravendra Kumar
Chhitorgarh Mr. Madan Lohar
Rajsamand Mr. Anil Sharma
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 205
ADB Loan No.: 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
Annexure 6- Photographs
Works in Progress
Work in progress at Bharatpur ROB
Dholpur 3 MLD STP
Bundi, STP site
pipe laying works at Brahmani Mata Mandir lane,
Jhalawar
Construction works at STP at Rajsamad
Proper use of PPEs during trenchless works at Kota Road,
Vill. Devpura
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 206
ADB Loan No.: 2366 IND (Tr-1), 2506 IND (Tr-2) & 2725 IND (Tr-3) Date: Dec 2016
Environmental Monitoring Report
EMP Compliance
EMP compliance at Bharatpur STP
EMP compliance at Dholpur street project
EMP Compliance at Nagaur
Safety training in Churu
PPE’s ei g used at STP site, Rajsa a d
Toilets and bathrooms prepared for workers at STP site, Bundi