Electric Vehicle–Grid Integration Program Proposal & Settlement 550 Grid-integrated EV charging facilities in multi- family communities and work places (5,500 EVSE) Day-ahead hourly rate that aligns with grid conditions to encourage off-peak charging Third parties to operate and maintain charging system EV charging is billed to drivers’ SDG&E bill Per the Settlement o Rate-to-Host option with a load management plan o Participation Payment o Can switch rate-billing plan after one year o Disadvantaged Communities commitment (>10%) o Create a diverse Program Advisory Council o 40% of spend to Diverse Business Enterprises 3

Citation preview

Page 1: © 2015 San Diego Gas & Electric Company. All copyright and trademark rights reserved. California Energy Commission Working with Current & Planned Regional

© 2015 San Diego Gas & Electric Company. All copyright and trademark rights reserved.

California Energy CommissionWorking with Current & Planned Regional Efforts

December 7, 2015

Page 2: © 2015 San Diego Gas & Electric Company. All copyright and trademark rights reserved. California Energy Commission Working with Current & Planned Regional

Building Blocks for Collaboration – Leveraging Current & Future Efforts

2

Community Outreach & Education

Regional Planning Support

Resources& Expertise

In-field Engineering Support

• Local Governments, Municipalities & SANDAG

• Contractors

• EV Service Providers

• Workplace Settings

• Multi-Family Settings

• Disadvantaged Communities

• Community Based Organizations (CBOs)

• EV Dealerships

Page 3: © 2015 San Diego Gas & Electric Company. All copyright and trademark rights reserved. California Energy Commission Working with Current & Planned Regional

Electric Vehicle–Grid Integration Program Proposal & Settlement

• 550 Grid-integrated EV charging facilities in multi-family communities and work places (5,500 EVSE)

• Day-ahead hourly rate that aligns with grid conditions to encourage off-peak charging

• Third parties to operate and maintain charging system• EV charging is billed to drivers’ SDG&E bill• Per the Settlement

o Rate-to-Host option with a load management plano Participation Paymento Can switch rate-billing plan after one yearo Disadvantaged Communities commitment (>10%)o Create a diverse Program Advisory Councilo 40% of spend to Diverse Business Enterprises

3

Page 4: © 2015 San Diego Gas & Electric Company. All copyright and trademark rights reserved. California Energy Commission Working with Current & Planned Regional

Electric Vehicle–Grid Integration Rate & Cost-effectiveness

4© 2012 San Diego Gas & Electric Company. All trademarks belong to their respective owners. All rights reserved.

Multi-family Workplace

Day-ahead hourly rate that aligns with grid conditions

to encourage off-peak charging

Lower hourly prices reflect favorable grid conditions and available low cost energy.

Targeted charging locations (long duration, frequently used parking) offer the best opportunity to optimize grid utilization.

Location of many of the existing charging facilities are not the best VGI Program opportunities.

Page 5: © 2015 San Diego Gas & Electric Company. All copyright and trademark rights reserved. California Energy Commission Working with Current & Planned Regional

Settlement Agreement Filed June 3 – Settlement Parties

• Natural Resources Defense Council (NRDC) • Environmental Defense Fund (EDF) • Sierra Club• CA Coalition of Utility Employees • Greenlining Institute• ChargePoint• NRG EV Services• Siemens• Plug in America• General Motors• Honda Motors • Alliance of Automobile Manufacturers • KN Grid • CALSTART • Center for Sustainable Energy (CSE) • Green Power Institute

5

Page 6: © 2015 San Diego Gas & Electric Company. All copyright and trademark rights reserved. California Energy Commission Working with Current & Planned Regional

Coordination with Local and Regional Current & Future Efforts

• Coordination with CEC Grant Funded Efforts – Work Well With & Complement VGI Program o Regional Planning (SANDAG) – REVI REFUEL Plug-in SD SANDAG’s Sustainable Communities Strategyo City and County of San Diego – deployment of charging facilities on City/County property

Many sites are not opportunities for the VGI Program – SDG&E involvement is still vital

• Work with All Stakeholders to Provide Resources & Technical Assistance in Support and Implementation of Electric Transportation Components of Climate Action Plans o There is the potential for VGI Program applicability (e.g., workplace and light duty fleet)

• If Settlement is Approved at least 10% of Facilities to be Installed in Disadvantaged Communities – as Identified by Cal EPA’s Enviroscreen tool per SB 535o Work with CBOs to educate and help to recruit hosts sites o Complement and coordinate with federal, state and local programs (CARB, per SB 1275)

6

Page 7: © 2015 San Diego Gas & Electric Company. All copyright and trademark rights reserved. California Energy Commission Working with Current & Planned Regional

REFUEL and Plug-in San Diego – Integral Planning & Outreach Efforts

Resources, Technical Assistance and Expert Consultation

• Local Governments & Contractors o Developing permitting and inspection best practices and

installation standards helps to expedite the VGI Facility installation process.

• Workplace & Multi-Family Outreach o Working jointly to provide information about programs, vehicle

incentives, assessing EV charging needs and general information regarding EV makes and models.

• EV Dealerships o Keeping them up to date regarding incentives, special electric

rates, and developments in the VGI Program.

7

Page 8: © 2015 San Diego Gas & Electric Company. All copyright and trademark rights reserved. California Energy Commission Working with Current & Planned Regional

Plug-in San Diego – Strong Alignment with SDG&E’s Proposal

Workplace & Multi-familyEducation

8

Ride-n-Drive Events with

CSE, Dealerships and Plug-in

America

Community Education &

Outreach

Working with Dealerships and EVSPs for EV Day

Page 9: © 2015 San Diego Gas & Electric Company. All copyright and trademark rights reserved. California Energy Commission Working with Current & Planned Regional

County of San Diego – Field Engineering Assistance is Vital

9

Page 10: © 2015 San Diego Gas & Electric Company. All copyright and trademark rights reserved. California Energy Commission Working with Current & Planned Regional

City of San Diego – Field Engineering & Site Planning is Vital

10

Adams Ave and 36th St., 4 EVSE, curbside, new service

Mission Bay Aquatic Center, 2 EVSE in impacted parking lot, new service

Nobel Athletic Center / Park, 3 EVSE, new service

Normal St., 4 EVSE in median, new service from pole

Page 11: © 2015 San Diego Gas & Electric Company. All copyright and trademark rights reserved. California Energy Commission Working with Current & Planned Regional

Working with Municipalities – Climate Action Plan Implementation

Provide Resources and Technical Assistance in Support and Implementation of Electric Transportation Components of Climate Action Plans - Potential for VGI Program Applicability

Climate Action Plans o City of San Diego o County of San Diego o Chula Vistao Port of San Diegoo Encinitaso Santee o La Mesao Del Maro Carlsbad

11

Climate Action Planning (in progress)o Lemon Grove o Oceanside o Solana Beach o El Cajon

Page 12: © 2015 San Diego Gas & Electric Company. All copyright and trademark rights reserved. California Energy Commission Working with Current & Planned Regional

Education & Outreach in Disadvantaged Communities

If VGI Settlement is Approved – at least 10% of VGI Facilities to be Installed in Disadvantaged Communities (as identified by Cal EPA’s Enviroscreen Tool, per SB 535)

• Work with CBOs help to educate and recruit hosts sites for participation

• Complement and coordinate with federal, state and locally funded programs (CARB, per SB 1275), when available

o Carsharing pilots and programs (e.g., SANDAG-CARB grant agreement)o Scrap & Replace Program for low-income residents in disadvantaged

communitieso Clean Vehicle Rebate Project – help educate customers about increased

rebates for low-to-moderate income driverso Help educate customers about financing assistance programs

• Work with “Plug-in SD” for education and outreach to disadvantaged communities, workplace and multi-family locations

12

Page 13: © 2015 San Diego Gas & Electric Company. All copyright and trademark rights reserved. California Energy Commission Working with Current & Planned Regional

Vehicle-Grid Integration Proceeding and General EV Information

13

http://www.sdge.com/regulatory-filing/10676/sdge-electric-vehicle-grid-integration-pilot-program

http://www.sdge.com/electric-vehicles

[email protected]

General Electric Vehicle Information

SDG&E’s Vehicle-Grid Integration Proceeding (Application 14-04-014) currently before the CPUC

Contact Greg Haddow, SDG&E