Construction Documents Notice to proceed given on March 23, 2011 Documents will be ready to bid February 15, 2013 Construction Construction contract presented to City Council in April, 2013 for approval Construction should commence May/June 2013 Construction expected to take one year Cost Estimates Complete park is estimated at $7.6m Funding is in place for $7.76m •2012 CO’s = $3.41m •2013 CO’s = $4.35m

Fischer park

Embed Size (px)

DESCRIPTION

 

Citation preview

Page 1: Fischer park

Construction Documents

•Notice to proceed given on March 23, 2011

•Documents will be ready to bid February 15, 2013

Construction

•Construction contract presented to City Council in April, 2013 for approval

•Construction should commence May/June 2013

•Construction expected to take one year

Cost Estimates

•Complete park is estimated at $7.6m

•Funding is in place for $7.76m

•2012 CO’s = $3.41m

•2013 CO’s = $4.35m