Upload
tchh-rao
View
2.212
Download
2
Embed Size (px)
Citation preview
1.1Way Leaves and Right of way
1.1.1Way leaves is the right to use the property of another without possessing it. In the context of transmission lines, Way leaves is the affected area is corridor of the line and the area required during construction and maintenance stage.
1.1.2Right of Way is the corridor that gives the power entity to have way leaves. The obstacles like tall trees etc have to be removed in the width of the ROW in order to prevent outages.
1.1.3The clearing should be carried out both in legal and physical sense.
1.1.4If any compensation has to be made on crops it should be accounted for the period till the installation work is to be over according to programme.
1.1.5Taking into consideration on theoretical requirement of right-of-way and transport requirements of maintenance the following right of way widths are recommended.
1.1.6The ROW for various voltages is given in the table.
1.2Land Schedules and ROW issues.
1.1.7Land schedule is the statement that indicates the data pertaining to the owners of the land for obtaining permissions and payment of compensations.
1.1.8The cadastral maps of the village/township area are collected from the revenue officials of the local government.
1.1.9A typical cadastral map is shown in the illustration here.
Transmission Voltage
Recommended Width of Right-of- Way
33 kV 15 m
66 kV 18 m
110 kV 22 m
132 kV 27 m
220 kV 35 m
400 kV 52 m
500 kV HVDC
52 m
800 kV 85 m
NUAPUT VILLAGE
TAPAGANDA VILLAGE
115
16
30
31
32
18
17
16
2
1
5
3
6
9
4
39
7
8
11
33
10
1413
12
36
35
4140
39
38
37
48
45
29
42
43
44
2827
2625
24
23 22
116
47
46
60
21 58
57
5659
10096
98
97
55
54
53
52
51
50
111
109
110
104
107108
118
106
105
114
103
93
95
99
101
102
92
91
90
8988
9487
86
68
69
76
82
83
84
8577
78
79
80
81
71
70
67
65
64
117
7572
73
19
20
61
66
62
66
BIL
AP
UT
VIL
LAG
E
1.1.10These maps have usually units that are different from the topo maps and therefore these maps have to be scaled to the UTM coordinates.
1.1.11The tower locations are marked on these maps and the plot number is identified. A sample of cadastral map with location of towers marked on is shown in the illustration.
1.1.12The local revenue officials would have to be involved in the identification of the land and the details pertaining to the owners, the type of crops, trees etc.,
1.1.13authority for Right of Way is conferred by the issue of a Notification by the officer of the licensee (in case of state power transmission corporations, the Chief Engineer) in exercise of powers conferred by the Government under Section 164 of the Electricity Act, 2003 (earlier, Indian Electricity Act, 1910). The powers are the same as conferred on the Telegraph Authority under Section 10 of The Indian Telegraph Act, 1885.
1.1.14In India, Right of Way is not purchased. As per sub – section 10 (b) of The Indian Telegraph Act, 1885, the power entity does not acquire any right other than that of user only in the property under, over, along, across, in or upon which any line or tower is placed for construction, operation & maintenance of the line while the owner retains the ownership and use of the land. These powers should not be exercised in respect of property vested in or under the control or management of any local authority without the permission of that authority.
1.1.15The Notification of Right of Way is to be got published in the State Gazette indicating the names of all the villages / dhanies along the route of the line as well as villages adjacent to the route.
1.1.16A copy of the Notification of Right of Way is also to be got published in the local newspapers of the areas in which the transmission line will be passing. This is important as proof of circulation of information to the general public when contesting court cases which local landowners may file.
1.1.17In exercise of the powers vested under sub – section 10 (c) of The Indian Telegraph Act, 1885, the construction agency and the power entity will have to prevent unnecessary damage to the property during the construction as well as maintenance.
1.1.18They would have to pay the full compensation to all persons interested for any damage caused to standing crops or fruit bearing trees which are accepted by the Revenue Authorities as eligible for payment of compensation, Land Schedule as given below.
1.1.19The crop compensation sheet statement has to be attested by the local revenue officer of the area with the statement of indicating Dimensions and area of the property in which damage has been caused., The details, type and quality of the crop damaged and The expected yield(s) of the crop(s), rate(s) and total cost(s).
1.1.20This crop compensation is assessed by competent authority who issues the sanction for compensation for crops destroyed or property damaged during the execution of the works on the above basis.