Rail Baltica

planning

process

Neils Balgalis

Grupa93/RB Latvija

31/03/2016

Page 2: Rail Baltica planning process

Implementation schedule of Rail Baltica

Page 3: Rail Baltica planning process

Detailed technical study and environmental impact assessment of the Latvian section of the European gauge

railway line Rail BalticaID No. SAM 2012/12 TEN-T

May, 2014 – August, 2016

Page 4: Rail Baltica planning process

General partnership

«RB Latvija»

Page 5: Rail Baltica planning process

Aim = to determine a precise alignment of the railway line Rail Baltica in the territory of Latvia

(including links to the port and airport,and to carry out EIA, relevant studies and preparatory works for the design of the

railway line, expropriation of land)

Page 6: Rail Baltica planning process

Results : - Technical solutions for the technically, economically and legally possible alignment options of

the planned railway line Rail Baltica; - Engineering surveys (topografical, geological, etc);

- Environmental Impact Assessment;- the local plans of the new railway line (where necessary);

+- the technical documentation for the next phase;

- recommendations for expropriation of the land properties for the railway line - terms of reference and requirements of the Contracting Authority for design, construction, and

related processes - cost – benefit analysis

Page 7: Rail Baltica planning process
Page 8: Rail Baltica planning process
Page 9: Rail Baltica planning process
Page 10: Rail Baltica planning process
Page 11: Rail Baltica planning process
Page 12: Rail Baltica planning process
Page 13: Rail Baltica planning process
Page 14: Rail Baltica planning process

Alignment of all options elaboratedwithin the study for the link with Riga

Page 15: Rail Baltica planning process

EIA (Environmental ImpactAssesment) process (February, 2015 – now)

Page 16: Rail Baltica planning process

265 km long300 m wide corridor

location-location-location

Page 17: Rail Baltica planning process

EIA (Environmental ImpactAssesment) process

Initial Public Hearing

(March, 2015)

Elaboration of report

(April-November)

Public Hearing

(December, 2015)

Approvals by municipalities

Page 18: Rail Baltica planning process

Initialpublic hearings

average number of people (per

meeting) – 300

hostile environment

= NIMBY wars

Page 19: Rail Baltica planning process

Initial public hearings in 15 municipalities

Why???

It’s already decided!!!

What are u talking about?

Page 20: Rail Baltica planning process

Emotional stories! Media likesthem!

Page 21: Rail Baltica planning process

Cartoons& comments

Page 22: Rail Baltica planning process

Conspiration theories

WHITE STORK NESTS HAS BEEN REMOVED!!!!

Page 23: Rail Baltica planning process

Twitter on RailBaltica

Page 24: Rail Baltica planning process

Media LOVES US!

Public Hearings @ Unprecedent Scale

February-March, 2015

more than 5100 people participated in meetings

Page 25: Rail Baltica planning process

Attitude of municipalitiesafter initial public hearing

positive – 10 neutral – 3strictly negative – 2

600+ individualletters/proposals

Page 26: Rail Baltica planning process

???

Page 27: Rail Baltica planning process

The most democratic public hearing in Latvia

Achievements after 1st round:

Public involvement from the first steps of the project – 5 yearsbefore construction process

Activity shows high level of civic society in Latvia– discussions, proposals, cooperation

Time for advisory groups in regions!

Page 28: Rail Baltica planning process

EIA (Environmental ImpactAssesment) process

Initial Public Hearing

(March, 2015)

Elaboration of report

(April-November)

Public Hearing

(December, 2015)

Approvals by municipalities

Page 29: Rail Baltica planning process

Action plan - to create platform for next round of publichearings

- advisory work groups in municipalities

- individual meetings on-site with private landowners

- informative phone

- informative e-mail

- website www.railbaltica.info

- additional cartographic materials (DIY)

Page 30: Rail Baltica planning process

from heated discussions to the dialogueprocess

Advisory work groups in Salacgriva,

Bauska, Limbazi, Sēja

more than 220 persons

long summer evenings

additional alternatives and solutions

Page 31: Rail Baltica planning process

www.railbaltica.info

Page 32: Rail Baltica planning process
Page 33: Rail Baltica planning process
Page 34: Rail Baltica planning process

Individual e-mails (1000+) &phone calls(600+)

Page 35: Rail Baltica planning process

265 km of preliminary railway design

Page 36: Rail Baltica planning process

from 300 m to 60 m

Page 37: Rail Baltica planning process
Page 38: Rail Baltica planning process

aerial photo for all alternatives 500 km

surface 3D model izveide

Page 39: Rail Baltica planning process

precīzs novietojums un

iespēja apskatīt savu

īpašumu

Page 40: Rail Baltica planning process

30

Page 41: Rail Baltica planning process

more than 300 road crossings

Page 42: Rail Baltica planning process

more than100 river crossings

and culverts

Page 43: Rail Baltica planning process

Institutions

Latvijas valsts meži

Latvijas dzelzceļš

AS Latvijas elektriskie tīkli

Latvijas gāze

kā arī RIX, VKPAI, RM, RŪ, RS, PV, DAP, RPR, ZPR, u.c.

Latvijas valsts ceļi

Latvijas valsts ceļi

Page 44: Rail Baltica planning process

single corridors

Page 45: Rail Baltica planning process

10 km of railway + existing higway in

Olainē un Ķekavā

100 km of railway + planned power

line (330 kV and 110 kV)

27 km of 1435 mm railway

+ existing 1520mm railway in Riga

20 km of railway + planned VIA

BALTICA highway in Bauska/Iecava

Page 46: Rail Baltica planning process
Page 47: Rail Baltica planning process

A picture is worth a thousand words(October, 2015)

Detailed Technical Solutions – basis for 3-D models for specific objects and localities

Page 48: Rail Baltica planning process
Page 49: Rail Baltica planning process
Page 50: Rail Baltica planning process
Page 51: Rail Baltica planning process
Page 52: Rail Baltica planning process
Page 53: Rail Baltica planning process
Page 54: Rail Baltica planning process
Page 55: Rail Baltica planning process

EIA (Environmental ImpactAssesment) process

Initial Public Hearing

(March, 2015)

Elaboration of report

(April-November)

Public Hearing

(December, 2015)

Approvals by municipalities

Page 56: Rail Baltica planning process

Only 60 persons/per meeting?

No scandals?

= u are not interesting.

Page 57: Rail Baltica planning process

Results -real participation process

Direct and open cooperation with municipalities and inhabitants

= 15 municipalitiessupport therecommendendalignement of Rail Baltica

Page 58: Rail Baltica planning process

Next steps (August, 2016)

• Approval of EIA report

• Topographical survey + final technical solutions

• Information for landowners

• Local plans in 13 municipalities

Page 59: Rail Baltica planning process

Kiitos/Thank You/Paldies!