Project Risk Management

Dr. A.K.Panigrahi

1

Page 2: Project Risk management

2

Page 3: Project Risk management

3

Page 4: Project Risk management

What is Risk?• Risk is the possibility of suffering loss• Risk is a measure of the probability and

consequence of not achieving a defined project goal.

• Possible – but not certain, so it is expressed as probability

• Risks change though out the life of a project• Loss - is any unwanted consequence that

might occur4

Page 5: Project Risk management

Risk in Projects

• In a development project, the loss describes the impact to the project which could be in the form of diminished quality of the end product, increased costs, delayed completion, or failure.

5

Page 6: Project Risk management

6

Possible Risks in a Project

• Creeping user requirements

• Excessive schedule pressure

• Low quality

• Cost overruns

• Poor estimates

• Low customer satisfaction

• Long schedules

Page 7: Project Risk management

Project Risk

Project Risk

Scope

IntegrationCommunication

Human Resources

Procurement

Cost

Quality

Time

Page 8: Project Risk management

The Importance of Project Risk Management

• Project risk management is the art and science of identifying, analyzing, and responding to risk throughout the life of a project and in the best interests of meeting project objectives

• Risk management is often overlooked in projects, but it can help improve project success by helping select good projects, determining project scope, and developing realistic estimates

• Unfortunately, crisis management has higher visibility due to the obvious danger to the success of the project but it’s risk management that helps a project have fewer problems to begin with.

8

Page 9: Project Risk management

9

Page 10: Project Risk management

Risk Can Be Positive• Positive risks are risks that result in good things

happening; sometimes called opportunities

• A general definition of project risk is an uncertainty that can have a negative or positive effect on meeting project objectives

• The goal of project risk management is to minimize potential negative risks while maximizing potential positive risks

10

Page 11: Project Risk management

11

Risk Management

• Risk management is the act or practice of dealing with risk.

• Risk management is proactive rather than reactive.

• Risk management is not a separate activity but rather on aspect of sound project management.

Page 12: Project Risk management

12

Elements of Risk Management

• Effective Risk Management is made up of:– Risk Assessment: identify, analyze, prioritize– Risk Control: planning, resolution, monitoring

RISK RISK MANAGEMENTMANAGEMENT

RISK RISK

CONTROLCONTROL

RISK RISK

ASSESSMENTASSESSMENT

IDENTIFICATIONIDENTIFICATION

ANALYSISANALYSIS

PLANNINGPLANNING

PRIORITIZATIONPRIORITIZATION

RESOLUIONRESOLUION

MONITORINGMONITORING

Page 13: Project Risk management

13

Common Mistakes in Risk Management

• Not understanding the benefits of Risk Management

• Not providing adequate time or resources for Risk Management

• Not identifying and assessing risk using a standardized approach

Page 14: Project Risk management

Project Risk Management Processes

• Risk management planning: deciding how to approach and plan the risk management activities for the project

• Risk identification: determining which risks are likely to affect a project and documenting the characteristics of each

• Qualitative risk analysis: prioritizing risks based on their probability and impact of occurrence 14

Page 15: Project Risk management

Project Risk Management Processes

• Quantitative risk analysis: numerically estimating the effects of risks on project objectives

• Risk response planning: taking steps to enhance opportunities and reduce threats to meeting project objectives

• Risk monitoring and control: monitoring identified and residual risks, identifying new risks, carrying out risk response plans, and evaluating the effectiveness of risk strategies throughout the life of the project

15

Page 16: Project Risk management

Project Risk Management Summary

16

Page 17: Project Risk management

• Four Main Steps

Risk Management

Risk Identification

Plan Risk Management Process

Risk Assessment

Risk Response Development

Risk Response Control

• Before these activities?

17

Page 18: Project Risk management

Risk Identification

• The possible risk is determined by a number of interrelated factors such as:– Nature of the Project– Aggressive or Conservative Schedule/Budget– Skills and motivation of the Project Team

Risk Response Control

Risk Response Development

Risk Assessment

Risk Identification

18

Page 19: Project Risk management

19

Risk Identification

• The need to proactively identify risks.– When an event happens it is too late to plan.

• Tools for identifying risk– Brainstorming– Nominal Group Technique

• Each member identifies their ideas• Each member writes an idea on the board until all

ideas are listed

Page 20: Project Risk management

20

Risk Identification

• The group discusses each idea• Each individual ranks each of the ideas• The group then ranks all the ideas• Each individual ranks all the ideas again• Rankings are summarized

– Delphi technique• Experts asked individually to provide input• Input summarized and distributed• Experts rank input

Page 21: Project Risk management

21

Risk Identification

– Strength, Weakness, Opportunities, Threats– Cause and effect diagrams– Past Projects

Page 22: Project Risk management

Likelihood

• What is the likelihood of risk?– Expressed as a Probability (Percentage)– Example – There is a 5% chance of a programmer

breaking their big toe whilst coding in any 6 month period

Risk Response Control

Risk Response Development

Risk Identification

Risk Assessment

22

Page 23: Project Risk management

Impact

• What impact will it have on the project?– Example – A broken toe on average results in the loss of 20

working days for a programmer– Expected Value of Loss/Profit

• Expected Value = Loss/Profit x Likelihood• -20 x 0.05 = -1• So we will lose 1 day of coding per programmer on a 6 month

project

Risk Response Control

Risk Response Development

Risk Identification

Risk Assessment

23

Page 24: Project Risk management

Urgency

• How urgently do we need to deal with it?– Immediate remedy or Can it wait?– Additional means of prioritising action

Risk Response Control

Risk Response Development

Risk Identification

Risk Assessment

24

Page 25: Project Risk management

Example Risk Assessment Team Conflict and Injuries

Description: Teammates in the group might have conflicts with one another throughout the semester. Injuries might result from conflict, accidents, and other mishaps throughout the semester.

How to Avoid It:

If any of the teammates show signs of conflict against one another, we need to mediate between them in order to make our team working smoothly and such throughout the whole semester. Thus that will reduce a factor for injury. However, for the other factors of injury, we need to make sure that we take good care of ourselves such that no harm will befall upon us (such as carpal tunnel syndrome, leg breaking, finger breaking, etc).

What It Will Affect:

If there is a large enough conflict, we might lose some teammates. Same with for injuries, if the injury is bad enough to cause teammates to not be able to work on the project.

Possible Likelihood:

3/100 chance

The Real World Lab: http://www.cc.gatech.edu/classes/RWL/Web/

25

Page 26: Project Risk management

Quantifying Risk

• Programmer has 5% chance of breaking toe in any 6 month period– Broken toe results in the loss of 20 programmer days– Cost of a programmer-day = £500

• Expected Loss per year due to broken toes– 2 x (0.05 x -20) = -2 days– Expected loss = -£1000

26

Page 27: Project Risk management

Techniques

• Risk Map/Probability Impact Matrix

• Hazard Control Matrix

• Payoff Matrix

• Decision Tree

27

Page 28: Project Risk management

Risk Map

Likelihood of Occurrence

High Medium Low

Large

Medium

Sca

le o

f im

pact

Small

28

Page 29: Project Risk management

Likelihood of Occurrence

High Medium Low

Large

Medium

Sca

le o

f im

pact

Small

Risk Map

29

Page 30: Project Risk management

Risk Map

Likelihood of Occurrence

High Medium Low

Large

Medium

Sca

le o

f im

pact

Small

A B

C

D

30

Page 31: Project Risk management

Risk Map

• List the risks in order of priority

• What else can we use to help prioritise?

Likelihood of Occurrence

High Medium Low

Large

Medium

Sca

le o

f im

pact

Small

A B

C

D

31

Page 32: Project Risk management

Hazard Control Matrix

From Curtis, G (1998) "Business Information Systems" Addison Wesley

Errors and omissions

Lost data and documents

Computer Failure

Unauthorized Access

Fire Fraud

Input controls Processing controls Output controls Storage controls

Operating system controls

Records management

Accounting controls Contingency plan

Physical security

32

Page 33: Project Risk management

Hazard Control Matrix

From Curtis, G (1998) "Business Information Systems" Addison Wesley

Errors and omissions

Lost data and documents

Computer Failure

Unauthorized Access

Fire Fraud

Input controls Processing controls Output controls Storage controls

Operating system controls

Records management

Accounting controls Contingency plan

Physical security

33

Page 34: Project Risk management

Hazard Control Matrix

From Curtis, G (1998) "Business Information Systems" Addison Wesley

Errors and omissions

Lost data and documents

Computer Failure

Unauthorized Access

Fire Fraud

Input controls

Processing controls

Output controls

Storage controls

Operating system controls

Records management

Accounting controls

Contingency plan

Physical security

34

Page 35: Project Risk management

Hazard Control Matrix

From Curtis, G (1998) "Business Information Systems" Addison Wesley

Errors and omissions

Lost data and documents

Computer Failure

Unauthorized Access

Fire Fraud

Input controls

Processing controls

Output controls

Storage controls

Operating system controls

Records management

Accounting controls

Contingency plan

Physical security

35

Page 36: Project Risk management

Identification and Assessment

• Problems– Not a particularly interesting task– Needs experience to do well

• Are these good reasons to not do it?

36

Page 37: Project Risk management

Risk Response Development

• How are we going to deal with risks when they occur?– What about those we weren’t expecting?

Risk Response Control

Risk Identification

Risk Assessment

Risk Response Development

37

Page 38: Project Risk management

38

Risk Response Planning

• Who is going to detect when the risk occurs?

• Who has the responsibility to respond and communicate?

• What is the response?

Page 39: Project Risk management

Risk Response Planning

• After identifying and quantifying risks, you must decide how to respond to them

• Four main response strategies for negative risks:– Risk avoidance– Risk acceptance– Risk transference– Risk mitigation

39

Page 40: Project Risk management

Risk Management Planning

Risk Response Definitions

• Avoidance – Changing a project objective to eliminate the threat posed by an adverse risk event.

Page 41: Project Risk management

Risk Management Planning

Risk Response Definitions

• Transference – Shifting the negative impact of a threat, along with the ownership of the response, to a third party.

Page 42: Project Risk management

Risk Management Planning

Risk Response Definitions

• Mitigation – Reducing the Probability or Impact of an adverse risk event (threat) to an acceptable threshold.

Page 43: Project Risk management

Risk Response Definitions

• Acceptance – The project team decides not to change project objectives to deal with the risk.• Passive acceptance: no action , deal with threats as they occur

(workarounds)

• Active acceptance: establish a contingency reserve to handle risks

Risk Management Planning

Page 44: Project Risk management

44

Risk Strategies

• Factors impacting the strategy– Impact of the risk– Project constraints– Tolerances

• Strategy– Accept or Ignore

• Provide reserves

– Contingency plans• Natural disaster/backup plans

Page 45: Project Risk management

45

Risk Strategies

– Avoidance, eliminate the risk – Mitigate, lessen the impact of the risk

• Performance impact, provide extra hardware

– Transfer the risk• Offsite backup planning• Server farms• Outside management

Page 46: Project Risk management

46

Risk Monitoring and Control

• Risk monitoring– Determine who is responsible for monitoring– How are risks monitored?

• Project tracking, resources, quality, etc

– Communicating the status of identified risks• Reviews and Audits

• Once a risk is identified as occurring – Communicate– Take action

Page 47: Project Risk management

Control Systems

• Preventive Control– Stops undesirable events (disturbances) from

occurring (see Curtis, 1998 Chapter 8)

• Feedback Control– Doesn’t attempt to prevent unpredictable disturbances– Is able to recover from effects

• Systems will usually combine both

47

Page 48: Project Risk management

Risk Control

• Goals of Control– Prevention– Detection– Minimise Loss– Recovery– Investigation

H. A. Simon

• Risk Response– Avoidance

• Prevention

– Mitigation• Transfer

– AcceptanceCadle and Yeates

48

Page 49: Project Risk management

Risk Response Control

• Implement Risk Responses• Identify new Risks

– Implement new responses

Risk Identification

Risk Assessment

Risk Response Development

Risk Response Control

49

Page 50: Project Risk management

50

Risk Response and Evaluation

• Trigger the defined risk response plan– Identify the risk owner– Assign resources– Understand the impacts

• PERTs, Dependencies

• Communicate

• Evaluate once action is taken– Is more action needed?– What additional risks are triggered?

Page 51: Project Risk management

Risk Register

• Can be used to keep information about identified risks– Title and description– Risk Status - e.g. candidate, live, closed– Potential impact– Risk owner– Actions– Action Log

51

Page 52: Project Risk management

Risk Ownership

• Risk owner is someone who:– Has sufficient information concerning the risk– Has the necessary resources to do something

about the risk– Possesses the authority to do something

about the risk

52

Page 53: Project Risk management

Don’t take the risk if...

• the organization cannot afford to lose.• the exposure to the outcome is too great.• the situation (or project) is not worth it.• the odds are not in the project’s favor.• the benefits are not clearly identified.• there appear to be a large number of acceptable

alternatives.

53

Page 54: Project Risk management

Don’t take the risk if...

• the risk does not achieve the project objective.• the expected value from baseline assumptions is

negative.• the data is unorganized, without structure or

pattern.• there is not enough data to understand the

results.• a contingency plan for recovery is not in place

should the results prove unsatisfactory.