Upload
suchi
View
35
Download
2
Embed Size (px)
DESCRIPTION
PROJECT RISK MANAGEMENT. Ammar Bukhari. What is a Risk. RISK: Threat / Uncertainty of Outcome probability that an action or event, will adversely or beneficially affect an organization's ability to achieve its objectives. Risk vs Issue. Risk Future event May impact triple constraint - PowerPoint PPT Presentation
Citation preview
PROJECT RISK MANAGEMENT
Ammar Bukhari
WHAT IS A RISK RISK:
Threat / Uncertainty of Outcome
probability that an action or event, will adversely or beneficially affect an organization's ability to achieve its objectives
RISK VS ISSUE Risk
Future event May impact triple constraint
(Budget, scope and schedule). Issue
Present problem Influencing triple constraints.
Risk can become an issue Issue is not risk
it already happened.
RISK VS ISSUE
TODAY FUTURE
ISSUE RISK
WHAT IS PROJECT RISK MANAGEMENT? Project Risk Management:
- An uncertain event or condition that, if it occurs, has a positive or negative effect on the Project Objectives (Scope, Schedule, Cost, Quality)
- one of knowledge areas including the processes required to ensure timely completion of the project
PROCESS GROUPS & RISK MGMT ACTIVITIES
Initiating Planning Executing Controlling Closing
1. Plan Risk Management2. Identify Risks3. Perform Qualitative
Risk Analysis4. Perform Quantities
Risk Analysis5. Plan Risk Responses
6. Monitor & Control Risks
1. Plan Risk Management
Inputs
1. Project Scope Statement2. Cost Management Plan3. Schedule Management Plan4. Communications Mgmt Plan5. Enterprise Environ. Factors6. Organizational Process Assets
Outputs
1. Risk Management Plan
Tools & Techniques
1. Planning Meetings and Analysis
- Defining how to conduct risk management activities.
RISK MANAGEMENT PLAN
Documents the procedures for managing risk throughout the project
RISK MANAGEMENT PLAN Includes:
MethodologyR&RBudgetScheduleRisk Categories
Using risk breakdown structure (RBS)Probability and Impact MatrixStake Holders ToleranceReporting FormatsRisk Documentation
RISK MANAGEMENT PLAN Methodology:
Define the tools, approaches, and data sources used within the project performing risk management.
Roles and ResponsibilityWho lead, support, and be a member and
What activities are they responsible for within Risk Management Plan
Budget:Risk management cost in terms of
resources, buffers for baseline and contingency reserve
RISK MANAGEMENT PLAN Schedule
Risk schedule within the project defining when risk management process will be followed throughout the project life cycle
Risk CategoriesUsing RBS to identify and categorize risks
Probability and Impact Matrixranking between low, moderate, high
related to the risk effect on project’s objectives
RBSIT Project
Business
Competitors
Suppliers
Cash flow
Technical
Hardware
Software
Network
Organizational
Executivesupport
User support
Team support
ProjectManagement
Estimates
Communication
Resources
IMPACT MATRIX
RISK MANAGEMENT PLAN Stake Holders Tolerance
Expectation of stakeholders tolerance level, in terms of cost, resources, budget, and schedule
Reporting FormatsRisk reports formats / documents
Risk Documentationhow risk activities tracked/documented for future audits, and lesson learned
CONTINGENCY, FALLBACK PLANS, CONTINGENCY RESERVES Contingency plans
predefined identifying risk event occurs
Fallback plans for high impact risks on project objectives
Contingency reservesprovisions held to reduce the risk cost or
schedule overruns to an acceptable level
SAUDI AIR LINES CASE Flight Operation
Information System (FOIS)
AirCrew System
2. IDENTIFY RISKS
Inputs
1. Risk Management Plan2. Activity Cost Estimates3. Activity Duration Estimates4. Scope Baseline5. Stakeholder Register6. Cost Management Plan7. Schedule Management Plan8. Quality Management Plan9. Project Documents10.Enterprise Environ. Factors11.Organizational Process Assets
Outputs
1. Risk Registers
Tools & Techniques
1. Documentation Reviews2. Information Gathering Techniques:(Brainstorming / Delphi /
Interviewing/ Root cause analysis)3. Checklist Analysis4. Assumption Analysis5. Diagramming Techniques:(Cause & Effect / Process flow chart/ Influence Diagrams)6. SWOT Analysis7. Expert Judgment
- Determining which risks may affect the project and documenting their characteristics.
INFORMATION GATHERING TECHNIQUE Brainstorming
Expectation of stakeholders tolerance level, in terms of cost, resources, budget, and schedule
Delphi TechniqueRisk reports formats / documents
Interviewinghow risk activities tracked/documented for future audits, and lesson learned
Root Cause AnalysisChecklist / Assumption / Diagramming / SOWT
ROOT CAUSE ANALYSIS Checklist Analysis
Using historical records / learned lessons from previous projects and other sources
RBS Leafs in can be considered as items in the list
At project end, list can be reviewed and updated to be used in future projects
AssumptionUpon assumptions, some risks were
identified and listed
ROOT CAUSE ANALYSIS Diagramming Technique
diagrams can help to identify additional risks:
Cause and Effect Process flow charts Influence diagrams
CAUSE & EFFECT
ROOT CAUSE ANALYSIS SOWT Analysis
Helps identify the broad negative and positive risks that apply to a project
RISK REGISTERDocument contains results of various risk
management processes Often displayed in a table or spreadsheetTool for documenting potential risk events
and related information
No. Rank Risk Description Category RootCause
Triggers PotentialResponses
RiskOwner
Probability Impact Status
R44 1
R21 2
R7 3
3. PERFORM QUALITATIVE RISK ANALYSIS
Inputs
1. Risk register2. Risk management plan3. Project scope statement4. Organizational process assets
Outputs
1. Risk register updates
Tools & Techniques
1. Risk probability and impact assessment
2. Probability and impact matrix3. Risk data quality assessment4. Risk categorization5. Risk urgency assessment6. Expert judgment
- Prioritizing risks for further analysis / action by assessing their probability of occurrence and impact.
TOOLS Risk probability and Impact
AssessmentThis tool will look after:Likelihood of each risk to happen Its affect on project objectives
(Schedule, Cost, Quality, or Performance)
Probability and Impact Matrix lookup table can be used identifying each
risk importance and thus its priority
TOOLS Risk data quality assessment
It evaluates data quality degree, so it will be useful for risk management
data to be more accurate, understood, and reliable
for more credibility results Risk categorization
classify risks by:RBSArea will be affectedAny other reasonable type
TOOLS Risk urgency assessment
Risks thatMay happen soonResponse planning will take much time
Will be dealt as urgent to be processed quickly through this process
4. PERFORM QUANTITATIVE RISK ANALYSIS
Inputs
1. Risk register2. Risk management plan3. Cost Management Plan4. Schedule Management Plan5. Organizational process assets
Outputs
1. Risk register updates
Tools & Techniques
1. Data Gathering & Representation Techniques
2. Quantities risk analysis and modeling techniques
3. Expert judgment
- Numerically estimating the effects of risks on project objectives.
TOOLS Risk
LikelihoodImpact
Data Gathering & Representation Techniques
InterviewingProbability distribution
Quantitative risk analysis and modeling techniques
Sensitivity analysisExpected monetary value analysisModeling and simulation
DATA GATHERING & REPRESENTATION TECHNIQUES
InterviewingWith concerned project team members,
stakeholders, and Subject Matter Experts
Probability distributiongraphically displayed representing both
time/cost element and probabilitymodeling and simulation techniquesBeta, triangular distributions, Discrete
distribution
EXPECTED MONETARY VALUE (EMV)
the highest value of each competing option
Risk probability * risk monetary value
EXPECTED MONETARY VALUE (EMV)
SENSITIVITY ANALYSIS technique used to show the effects of
changing one or more variables on an outcome
MODELING & SIMULATION Simulation uses a representation or
model of a system to analyze the expected behavior or performance of the system.
Monte Carlo analysis three estimates (most likely,
pessimistic, and optimistic)
5. PLAN RISK RESPONSES
Inputs
1. Risk register2. Risk management plan
Outputs
1. Risk register updates2. Risk-related contract
decisions3. Project management
plan updates4. Project document
updates
Tools & Techniques
1. Strategic for negative risks or threats
(Avoid / Transfer / Mitigate / Accept)2. Strategies for positive
risks or opportunities(Exploit/ Share / Enhance / Accept)3. Contingent response
strategies4. Expert judgment
- Developing options and actions to enhance opportunities and to reduce threats to project objectives.
TOOLS Strategic for negative risks or threats
Risk avoidance Change the plan to eliminate the risk or condition
or to protect the project objectives from its impact. Risk transfer
Shift the consequence of a risk to a third party, through purchasing insurance, warranties, guarantees, or outsourcing the work.
Mitigation Reduce the probability to an acceptable threshold,
thus removing it from top risks. Acceptance technique
Not to change the project plan to deal Unable to identify any other suitable response
TOOLS Strategic for positive risks or
opportunities Risk exploitation:
make sure the positive risk happens Risk sharing:
allocating ownership of the risk to a party Risk enhancement
changing the size of the opportunity by identifying and maximizing key drivers of the positive risk
Risk acceptance the project team cannot choose not to take any action toward a risk
TOOLS Contingent response strategies
Contingency plansSpecific actions that are to be taken when
a potential problem occursShould be developed in advanceHelps ensure coordinated, effective, and
timely responseSome plans may require backup resources
that need to be arranged in advanceContingency planning should be done only
for the high-threat problems that remain after you’ve taken preventive measures
6. MONITOR AND CONTROL RISKS
PMP WorkshopApril 22, 2023
Inputs
1. Risk register2. Risk management plan3. Work performance
information4. Performance Reports
Outputs
1. Risk register updates2. Organizational process
assets updates3. Change requests4. Project management plan
updates5. Project document updates
Tools & Techniques
1. Risk reassessment2. Risk audits3. Variance and trend analysis4. Technical performance
measurement5. Reserve analysis6. Status meetings
- Implementing risk response plans, tracking identified / new risks, monitor residual risks, and evaluating risk process effectiveness.
TOOLS Risk reassessment
to measure where the project stands today on a risk issue.
After risk mitigation, the team can reassess the current risks by identifying new risks, or closing outdated risks.
Risk audits Indication of the project team ability to
identify, measure, and manage risksProvide independent assessment of the risk
management practices of the companyverifies that the company has appropriate risk
management control in compliance with approved risk policies and procedures
TOOLS Variance and trend analysis
Helping to identify the factors that affect each element
its goal is to determine the causes of a variance
difference between expected result and an actual result
effective way to discover the sum causes of a result
Technical performance measurement actual performance is tracked compared by project
management to the Technical Performance Measurement
TOOLS Reserve analysis
Manage the reserve and use them only for risks keeping the project risk on track.
Additional reserve could be requested, or could be reduced if there is opportunity or threats were not happened
SAMPLE PMP CERTIFICATION QUESTIONS
QUESTIONSAll of the following are factors in the
assessment of project risk EXCEPT?A. Risk eventB. Risk probabilityC. Amount at stakeD. Insurance premiums
Answer DExplanation Insurance premiums come into
play when you determine which risk response strategy you will use.
QUESTIONSWhich of the following risk events is MOST likely to
interfere with attaining a project's schedule objective?
A. Delays in obtaining required approvalsB. Substantial increases in the cost of purchased
materialsC. Contract disputes that generate claims for
increased paymentsD. Slippage of the planned post-implementation review
meetingAnswer AExplanation Cost increases (choice B) and contract
disputes (choice C) will not necessarily interfere with schedule. Notice the words "post-implementation" in choice D. It will not definitely interfere with the project schedule. Choice A is the only one that deals with a time delay
QUESTIONSRisks will be identified during which risk management
process(es)?A. Quantitative risk analysis and risk identificationB. Risk identification and risk monitoring and controlC. Qualitative risk analysis and risk monitoring and
controlD. Risk identification
Answer BExplanation This is a tricky question. Risks are
identified during risk identification, naturally, but newly emerging risks are identified in risk monitoring and control
QUESTIONSRisk tolerances are determined in order to help:A. the team rank the project risks.B. the project manager estimate the project.C. the team schedule the project.D. management know how other managers will act on
the project.
Answer AExplanation If you know the tolerances of the
stakeholders, you can determine how they might react to different situations and risk events. You use this information to help assign levels of risk on each work package or activity
QUESTIONSYou are finding it difficult to evaluate the exact cost
impact of risks. You shouldevaluate on a(n):A. quantitative basis.B. numerical basis.C. qualitative basis.D. econometric basis.
Answer CExplanation If you cannot determine an exact cost
impact to the event, use qualitative estimates such as Low, Medium, High, etc
QUESTIONSPurchasing insurance is BEST considered an example of risk:A. mitigation.B. transfer.C. acceptance.D. avoidance.
Answer BExplanation To mitigate risk (choice A) we either reduce the
probability of the event happening or reduce its impact. Many people think of using insurance as a way of decreasing impact. However, mitigating risk is taking action before a risk event occurs. Buying insurance is not such an action. Acceptance of risk (choice C) does not involve such action as purchasing insurance. Avoidance of risk (choice D) means we change the way we will execute the project so the risk is no longer a factor. Transference is passing the risk off to another party
QUESTIONSAn output of risk response planning is:A. residual risks.B. risks identified.C. prioritized list of risks.D. impacts identified.
Answer AExplanation Risks are identified (choice B) during risk
identification and risk monitoring and control. Prioritized risks (choice C) are documented during qualitative and quantitative risk analysis. Impacts (choice D) are generally determined during quantitative risk analysis. The best answer is A
QUESTIONSThe customer requests a change to the project that
would increase the project risk.Which of the following should you do before all the
others?A. Include the expected monetary value of the risk in
the new cost estimate.B. Talk to the customer about the impact of the
change.C. Analyze the impacts of the change with the team.D. Change the risk management plan
Answer CExplanation This is a recurring theme. First, you should
evaluate the impact of the change. Next, determine options. Then go to management and the customer
THANKS