Managing What If Scenarios for Unconventional Oil & Gas
Prepared by:
Patrick Lovelace
President
Nu Solutions Consulting
Using Primavera P6 EPPM and Risk Analysis
Session ID#: 200130
@patricklovelac patrick-lovelace
Business Use Case
■ Integrated Schedule for Visibility Across all Functions
■ Main Focus is on the Rig Schedule
▪ 12 – 18 month forecast plan
▪ 50 – 100 active well projects
▪ Rig Resources are limited and Geographically Restricted
■ Modify plan as variables change to maximize Rig productivity.
The Challenge
• Geography
• Interests in multiple states, with multiple operated assets
• 35,000 active wells in 800 fields
• 8 currently operating Drill Rigs, increasing to ?? Drill Rigs
(planned)
• Workforce
• Geographically separated
• Differing methodologies within regions
• Project Management
• Vigorous Drilling and Field Reinvestment programs
• Requirement to reduce overall well development time
• Desire to schedule entire well development life cycle
The Challenge
• Rapid growth of project portfolio; extensive development of existing reservoirs using new technologies
• Desire to tightly integrate all functions involved in well development so as to create an integrated program
• Desire to standardize work processes and schedule information across the entire Business Unit
• Integrated Schedule for Visibility Across all Functions
• Modify plan as variables change to maximize Rig productivity
The Challenge
■ Main Focus is on the Rig Schedule
▪ 12 – 18 month forecast plan
▪ 50 – 100 active well projects
▪ Rig Resources are limited and Geographically Restricted
Traditional Planning
■ Using Excel
▪ Only provides single view
■ Using MS Project
▪ This is a sub-bullet of text
– This tertiary sub-bullet that can be use
▪ This is another sub-bullet
of text
■ Using Primavera P6 Stand alone
■ No Critical Path
■ No Baseline Variances
▪ Have we hit target start?
▪ Have we hit target finish?
▪ How often do we slip?
▪ What is the main driver for
slips?
Process Hurdles
■ Labor intensive to break relationship links to redo path.
■ Too Many variables to manage – input and updates are slow hard to capture.
■ Things change to often to accurately plan
■ Planning by Committee
Process Foundation
■ Define the structure
■ Tools to use in the Application
■ Viewing the Data
■ Define the Steps
■ Agree on the Definitions
▪ What moves through Stage
▪ Racking Projects
▪ When Resources get
allocated
■ Stick to the process
Primavera P6 Configuration Business Process
Primavera P6 EPPM Configuration
■ EPS – Organizes Wells by Location then Project
■ OBS – Separate Access by Function
■ WBS – Project Phase
■ Activities – Key Activities
■ Roles – Capacity Planning
■ Resources – Level Utilization
■ Project UDF's – Portfolio Scenarios
■ Activity Codes and UDF'S – Level Utilization
Enterprise Project Structure
EPS root
EPS node EPS node EPS node
EPS node EPS node
EPS nodeEPS node EPS node EPS node
PROJECTS
Company
State/County Location
Well Pad
Individual Well
Software Workflow
■ Primavera P6 EPPM – Portfolios
■ Filter on Project UDF's
■ Waterfall Portfolio Scenarios
■ Primavera P6 EPPM – Resource Assignments
■ Roles then Resources
■ Primavera P6 EPPM – Activities
■ All projects in Portfolio, filter for drilling tasks
■ Primavera Risk Analysis
■ Link and unlink for scenarios
Waterline Analysis
▪ Sorts projects into two separate groups based on sorting and
constraint limit.
— Projects that collectively meet the constraint limit value appear above
the waterline (white background).
— All other projects appear below the waterline (blue background).
Project 1
Project 2
Project 3
Project 4
Project 5
projects that collectively
meet constraint limit
other projects
constraint limit
so
rtin
g o
rder
Scenario
▪ A view saved with its data.
— Data does not update as in a regular view.
▪ Serves as a snapshot of the portfolio at a particular point in time.
— Useful for creating a historical record.
regular view
updates with latest
data
scenario frozen
with January 2018
data
Capacity Planning Chart
■ Enables you to analyze role staffing requirements and allocation
over time for projects in the portfolio.
time
lab
or
un
its
available
capacity
limit
required
units
Business Process Overview
■ Project Initiation (Templates)
▪ Required Project Codes and UDF’s
▪ Standard WBS
▪ Standard Activities
■ 12 month – 24 month Planning Phase Gate
▪ Role Assignments
■ 6 month – 12 month Planning
▪ Resource Assignments
■ 3 month – 6 month Planning
▪ Resource Allocations
■ 2 week – 3 month Schedules
▪ Update Resource Allocations from project status
Business Process Overview
■ Define Scenario Variables
▪ Design Changes
— Number of wells on pad
— Drilling durations – min/average/max
▪ Delay in schedule
— Seasonal permit – project calendar
— Land Access – yes/no
▪ Permitting complete – yes/no
▪ Economics - ranking
▪ Prioritization – ranking from Asset and Division
Business Process Overview
■ Activity Codes and UDF’s
▪ Water Storage
▪ Well Count
▪ Gas Type
▪ TIL Order
▪ Frac Crew
▪ PUD
▪ Shale Type
▪ Phase – Stage Gate
▪ Asset Team
▪ Product Line
Design Considerations
■ Keep Design Simple
▪ Strategic
— Right tool in hands – self maintaining
▪ Tactical
— Simple workflows
▪ Measurable
— Defined Standard Reporting
Organizations don’t execute unless the right people, individually and collectively, focus on the right details at the right time.
-- Larry Bossidy
Author, “Execution”
Please complete the session evaluation We appreciate your feedback and insight
You may complete the session evaluation either
on paper or online via the mobile app
■ Our purpose is to inform and educate our members on current and future
functionality of Oracle Primavera products, while offering a forum for peers to
share their experience and knowledge in the use of Primavera.
■ Educational opportunities across the Primavera product suite
■ Online Learning Series August 17th – September 4th
■ Call for presentation opening April 27th
■ Monthly Community Calls
■ 3rd Thursday of the month at 1:00 pm ET
■ Networking with other users within the Primavera community
■ Partnering with Oracle Primavera to meet the needs of our diverse
membership.
■ Membership is open to anyone with an interest in the Oracle Primavera products,
with no dues for membership. All members can vote on matters brought before
the OPSIG. Membership requests may be reviewed by the OPSIG board.
OPSIG is the home for
Primavera Users