HERRIARDS PROJECTHerriard’s Supplies
Introduction
• Situation
• Project Deliverables
• Key Stakeholder Organisational Chart
• WBS
• Quality Standards
• Root Cause & Trigger of the Risk
• Minimising & Dealing the Risks
• Lessons-learned Report
Project Situation
Customer needs :
• to see more examples of the furnitures.
• to make a better catalogue.
• to implement new computers.
Project Deliverables
• Implementing web-based catalogues.
• Providing better demonstration items.
• Implementing new computers.
Key Stakeholder Organisational Chart
Project Sponsor / Champion
Iain Wilson
Project Team Member / responsible for buying
equipments
Naing Naing Lin
Project Team Member / administrative for network
Tim Laverack
Project Team Member / Organised the process of
orders
Barrientos Hazel Joy
Project Manager
Masanori Tanaka
Work Breakdown Structure
Initiating 1.63 Days
Planning 3 Dyas
Executing 17 Days
Controlling 2.5 Days
Closing 2.25 Days
TOTAL DURATION : 27 Days
Quality Standards
• Survey Standards
– To determine appropriate computers by staff survey
• Supplier Selection Standards
– Reputation
– Product cost
• Customer Satisfaction Rating Standards
– Gathering feedback
Root cause & Trigger of the Risk
Minimising and Dealing with the Risk
• Well-Analysing
• Accepting risks
• Riks Agreement
– Penalty clauses
eg. If a prodct is deliverd late, the seller might be requred to pay a certain dollar amount for each day the product is late
Lessons-Learned Report
• Project Dates : 24/03, 2009 – 29/04, 2009
• Final Budget : $11,560
Did the project meet scope, time and cost goals?
-we did meet scope, however, we did need to request additional a week and $2,000.