40
Earned Value and PRINCE2® John Chapman PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.

Earned Value and PRINCE2 - John Chapman

Embed Size (px)

DESCRIPTION

 

Citation preview

Page 1: Earned Value and PRINCE2 - John Chapman

Earned Value and PRINCE2®

John Chapman

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.

Page 2: Earned Value and PRINCE2 - John Chapman

Why are we here?

Do PRINCE2® and Earned Value relate to each other?What could be shared for mutual improvement?

Page 3: Earned Value and PRINCE2 - John Chapman

PRINCE Processes and the Project Control Lifecycle

Page 4: Earned Value and PRINCE2 - John Chapman

PRINCE 2 : the De facto standard

Page 5: Earned Value and PRINCE2 - John Chapman

5

Earned Value in 10 Steps1. Requirement

2. WBS

3. OBS

I

12345

SSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTN15 N22 N29 N06 D13 D20 D27 D035. Plan

6. Budget

0

10

2 0

3 0

4 0

5 0

0 1 2 3 4 5

S e t B

a s e l i n e

4. RAM

0

10

2 0

3 0

4 0

5 0

0 1 2 3 4 5

7. Actual Cost

8. Work Performed

0

10

2 0

3 0

4 0

5 0

0 1 2 3 4 5

9. Earned Value

0

10

2 0

3 0

4 0

5 0

0 1 2 3 4 5

10. Analysis ?

C h a n g e C

o n t r o l

Page 6: Earned Value and PRINCE2 - John Chapman
Page 7: Earned Value and PRINCE2 - John Chapman

Remember these 3 thingsEV profiles budget over time using standard techniques.

How will we know we’ve delivered it?

EV monitors budget against physical progress.Where are we?

EV calculates value for money by monitoring how efficiently we are turning budget into deliverable.

How are we doing?

Page 8: Earned Value and PRINCE2 - John Chapman

What is your cultural IQ?Is asal bapak senan?

1.A mystical form of spirituality?2.A method of reinforcing economic and social alliances?3.A tradition of keeping bad news hidden?

Answer:Asal bapak senan is the Indonesian tradition of honouring

their boss by shielding him from bad news in public. It means ‘keeping father happy’. Supervisors are often told what they want to hear.

So how do we track % complete?

Page 9: Earned Value and PRINCE2 - John Chapman

1. Requirement

Project Description : Do we have a project?

Page 10: Earned Value and PRINCE2 - John Chapman

3. OBS

4. RAM

2. WBS

WBS : Work Breakdown StructureOBS : Organisation Breakdown StructureRAM : Responsibility assignment matrix

Project Planning & Stage Plan

WBS includes Product Breakdown

Page 11: Earned Value and PRINCE2 - John Chapman

Case StudyProduct BreakdownWork BreakdownOrganisation BreakdownResponsibility assignmentQuality Management Strategy

Page 12: Earned Value and PRINCE2 - John Chapman

Case Study

Page 13: Earned Value and PRINCE2 - John Chapman

I

12345

SSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTN15 N22 N29 N06 D13 D20 D27 D03

5. Plan

6. Budget0

10

2 0

3 0

4 0

5 0

0 1 2 3 4 5

Project Planning & Stage Plan

Page 14: Earned Value and PRINCE2 - John Chapman

Case StudyProject plan gives milestone dates with estimated dates by StageStage plan which has the allocation of resource assignment against activities

Page 15: Earned Value and PRINCE2 - John Chapman

Case Study

Page 16: Earned Value and PRINCE2 - John Chapman

Case StudyBottom up estimate of time by level 4 WBSTotalled by Project Stage

Page 17: Earned Value and PRINCE2 - John Chapman
Page 18: Earned Value and PRINCE2 - John Chapman

These are days not financial values

Page 19: Earned Value and PRINCE2 - John Chapman

I

12345

SSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTN15 N22 N29 N06 D13 D20 D27 D03

5. Plan

6. Budget0

10

2 0

3 0

4 0

5 0

0 1 2 3 4 5

S e t B a s e l i n e

Page 20: Earned Value and PRINCE2 - John Chapman

Case StudyIn the Stage Plan set the baselineIncludes resource allocation by nameAssign costs by name The Cost calculation based on resource cost

Page 21: Earned Value and PRINCE2 - John Chapman

In MS Project setting the baseline creates the BCWS (the Planned Value)

Page 22: Earned Value and PRINCE2 - John Chapman

0

10

2 0

3 0

4 0

5 0

0 1 2 3 4 5

7. Actual Cost

8. Work Performed

Checkpoint Report

Page 23: Earned Value and PRINCE2 - John Chapman

Case StudyThe project is underwayWe collect Actual Cost information by WBS element through timesheet analysisWe have weekly reviews to collect % complete and remaining durationThis is reported through a checkpoint report

Page 24: Earned Value and PRINCE2 - John Chapman

In MS Project setting the baseline creates the BCWS (the planned value)As we update the Actual duration and remaining duration the CPI is calculated

Page 25: Earned Value and PRINCE2 - John Chapman

0

10

2 0

3 0

4 0

5 0

0 1 2 3 4 5

9. Earned Value

0

10

2 0

3 0

4 0

5 0

0 1 2 3 4 5

10. Analysis?

Time toleranceCost toleranceException report

Page 26: Earned Value and PRINCE2 - John Chapman

Earning the valueFor example on an IT ProjectTraining is 0-100 : either you are trained or not trained!

Design could be by weighted milestone

25% on completion of a design workshop50% on issuing a design document25% on design signoff

Page 27: Earned Value and PRINCE2 - John Chapman

US Survey says…..over 800 military programs show

that ......no program has ever improved performance

better than the following EAC calculationEAC = BAC

CPIat 15% complete point in programNo-one pays enough attention in the

early stages

Courtesy of Steve Wake

Page 28: Earned Value and PRINCE2 - John Chapman

US Survey says…..

Estimate at Complete• Thanks to CPI and SPIt, and a

budget that represents all the work to be done (BAC), .. it is possible to predict when the project will be done and how much will be spent getting there… There is common knowledge and statistical evidence showing this assumption to be valid. The project work is as difficult as it is. Page 34

Page 29: Earned Value and PRINCE2 - John Chapman

Case Study : Key Performance Indicator

A mathematical projectionEAC = BAC / CPIEstimate at Complete = Budget at Complete / Cost Performance IndexAssume – BAC is £150,000– CPI is 0.95– EAC = £150,000 / 0.95– EAC = £157,895

Page 30: Earned Value and PRINCE2 - John Chapman

Case StudyThis is a quick method of identifying of the estimate at complete(EAC).It does not involve bottom up analysis but does provide a metric and financial value‘However when there is a significant technical issue, only detailed planning of the remaining work can result in a valid EAC’.1

1. Performance Based Earned Value . Paul J Solomon and Ralph R Young, ISBN 9780471721888, page 100

Page 31: Earned Value and PRINCE2 - John Chapman

Case Study

A bottom up calculationEAC = AC + ETCEstimate at Complete = Actual Costs plus Estimate to Complete

Page 32: Earned Value and PRINCE2 - John Chapman

Case StudyAt End Stage Assessment we now have– Budget At Complete (BAC)– Estimate To Complete (ETC)– Estimate At Complete (EAC)

Is the project still financially viable based on the Estimate at Complete?– Used at End Stage Assessment

Page 33: Earned Value and PRINCE2 - John Chapman
Page 34: Earned Value and PRINCE2 - John Chapman

Case StudyWe assess risk by type of work and make budget provision on this basisWe consider unknown risks based on a % assessment of the total work

Page 35: Earned Value and PRINCE2 - John Chapman

Case Study

Page 36: Earned Value and PRINCE2 - John Chapman

Case Study

Page 37: Earned Value and PRINCE2 - John Chapman

37

Reporting Graphs

TIME

CO

ST

Plannedcompletion

Planned BudgetBAC

Planned(BCWS)

EAC

Forecast projecttime slip

Actual Cost(ACWP)

Earned value(BCWP)

OD ATE

Forecast cost overrun

Time‘now’

BAC Budget at completionBCWS Budgeted Cost of Work ScheduledOD Original Duration plannedATE Actual Time ExpendedACWP Actual Cost of Work PerformedBCWP Budget Cost of Work PerformedEAC Estimate Cost at Completion

Schedule Variance (time)

ScheduleVariance (cost)

Cost variance

Forecastcompletion

© APM 2008. Reproduced under licence from APM

Page 38: Earned Value and PRINCE2 - John Chapman

Concluding messageThe methods used to monitor physical progress in Earned Value can be used in PRINCE2® projects, large or small, simple or complex, any industry.

Page 39: Earned Value and PRINCE2 - John Chapman

Book ReferencesThe Earned Value Management Maturity Model, Ray W Stratton, ISBN 1-56726180-9Earned Value Project Management, 3rd Edition, Quentin W Fleming and Joel M Koppelman, ISBN 193069989-1EVA in the UK, Steve WakeAPM Body of Knowledge, 5th Edition, Association for Project Management, ISBN 1-903494-13-3Interfacing Risk and Earned Value Management, Association for Project Management,

ISBN 1-903494-24-9The Mythical Man Month and Other Essays on Software Engineering, Frederick Brooks,

ISBN 0201835959‘Project and Programme Accounting, a practical guide for Professional Service

Organisations and IT’, John Chapman, Project Manager Today Publications, ISBN: 1-900391-14Earned Value Management using Microsoft Office Project, Sham Dayal, J.Ross Publishing,

ISBN 978-1-932159-98-1Work Breakdown Structures, The Foundation for Project Management Excellence, Eric S Norman, Shelly A Brotherton, Robert T Fried, Wiley, ISBN 978-0470-17712-9Performance Based Earned Value, Paul J Solomon, Ralph R Young, Wiley Interscience, ISBN 978-0-471-721888

Page 40: Earned Value and PRINCE2 - John Chapman

Thank you to…Steve Wake

[email protected]

Graham Williams [email protected]

John Chapman, Touchstone [email protected]

John Flaherty, OTC [email protected]

Alex Davis, MOD [email protected]

… and members of the EVM SIG