Helping Manufacturers Adopt Sustainable Practices to Increase Profits
E3: Economy, Energy, and the Environment
E3 is a community-based effort to build self-sustaining initiatives that increase the viability and profitability of manufacturers. Its three-tiered path calls for businesses to:
2
Assess Transform Sustain
3
E3: Strengthening Manufacturing in North Carolina
250+ partners24 communities51 manufacturers200+ technical assessments400+ workers trained
Process
Survey roughly 45% of clients
190 North Carolina jobs$9.97 million in realized savings$23+ million in economic impact
4
Technical Assessments – Phase I
Business Excellence Assessment
Lean and Quality Review
Environmental Review
Energy Systems Assessment
Greenhouse Gas Evaluation
Worker Safety Review
5
Time and Personnel CommitmentAssessment # of days # of
Participants Participant Type Prep Work Required
Business Excellence
Assessment(ProBE)
Day 1: 1 hr for personal assessment Day 2: Consensus facilitation
1-3 people Cross Section of company Company Profile
Lean and Quality Review 1 day 3 – 7 people
People involved in the process , rotating interviews of 20 minutes,
Plant walkthroughSchedule
interview times
Environmental Review 1 day 1-3 people
People involved in full day of questions and idea generation,
Plant walkthrough-
Energy Systems Assessment
1 - 2 days (depending on size of the facility) 1 person
Person knowledgeable in the facility systems to escort energy
assessorEnergy Data
Greenhouse Gas Evaluation
0.5 - 1 day (self assessment and online training) 1 – 6 people Personnel trained in the use of the
Greenhouse Gas ToolEnergy Data, Air emissions
Worker Safety Review 1 day 1 person Escort for safety assessors NC OSH request
form
6
7
Service Value Estimation
Business Excellence Assessment (1 expert for 1-2 days on-site, additional time off-site) $2,500
Lean and Quality Review (1 facilitators for 1 day on-site, additional time off-site)
$2,500 - $5,000(depending on size of facility and operations)
Environmental Review (1 facilitators for 1 day on-site, additional time off-site) $2,500
Energy Systems Assessment (1 expert for 1-2 days on-site, additional time off-site)
$3,000 - $6,000 (depending on size of facility and operations)
Carbon Footprint Assessment (training provided, calculator, additional guidance ) $1,500
Worker Safety Review (1 expert for 1 day on-site, additional time off-site) $2,500
Follow-up assistance to develop transformation planfor implementation of recommendationsresulting from assessments.
$800-1250/day
TOTAL PROGRAM VALUE Up to $21,250PLUS THE LONG TERM SAVINGS
Technical Assessments – Phase I
• $21,250 Value for $5,000 Cost
• 4-6 week assessment timeline
• Coordinated Community Partner Support
• Executive summary report and meeting Action oriented Incorporating partner resources Aligning incentives and grants
• Present Phase II Transformation Package in report
8
9
Customized Transformation Package• $16,000 Cost
• Credit $5,000 E3 Phase I assessment
• Net Cost = $11,000
• Diversify days of assistance across at least 3 technical project areas
• IES to manage partners and schedule
Transformation Support – Phase II
10
•Establishing an industry advocate team•Access to additional technical resources
“A-la-cart” support services from IES and partners as the manufacturer continues to pursue improvements, implement projects and access training
Sustaining Impact – Phase III
11
ies.ncsu.edu/E3
For more Information
http://www.youtube.com/watch?v=vluf9f_gbpI