32
Present Worth Analysis Present Worth Analysis EGN 3203 Engineering Economics LO3 – a

Chapter 5 present worth analysis -with examples

Embed Size (px)

Citation preview

Page 1: Chapter 5   present worth analysis -with examples

Present Worth AnalysisPresent Worth Analysis

EGN 3203 Engineering EconomicsLO3 – a

Page 2: Chapter 5   present worth analysis -with examples

5-2

LEARNINGLEARNING OUTCOMESOUTCOMES

1.Formulate Alternatives2.PW of equal-life alternatives3.PW of different-life

alternatives4.Future Worth analysis5.Capitalized Cost analysis

© 2012 by McGraw-Hill All Rights Reserved

Page 3: Chapter 5   present worth analysis -with examples

Introduction Present Worth Introduction Present Worth

• A future amount of money converted to its equivalent value now has a present worth (PW) value

• This present value is always less than that of the actual future cash flow,

• for any interest rate greater than zero, all P/F factors have a value less than 1.0. For this reason, present worth values are often referred to as discounted cash flows (DCF).

• Similarly, the interest rate may be referred to as the discount rate. Besides PW, equivalent terms frequently used are present value (PV) and net present value (NPV).

© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved1-3

Page 4: Chapter 5   present worth analysis -with examples

• Alternatives are developed from project proposals to accomplish a stated purpose.

• Some projects are economically and technologically viable, and others are not. Once the viable projects are defined, it is possible to formulate the alternatives.• Alternatives are one of two types: • mutually exclusive or independent.

• Each type is evaluated differently

© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved1-4

Formulating AlternativesFormulating Alternatives

Page 5: Chapter 5   present worth analysis -with examples

5-5

Formulating AlternativesFormulating Alternatives

Two types of economic proposals

Mutually Exclusive (ME) Alternatives: Only one can be selected; Compete against each other

Independent Projects: More than one can be selected; Compete only against DN

© 2012 by McGraw-Hill All Rights Reserved

Do Nothing (DN) – An ME alternative or independent project to maintain the current approach; no new costs, revenues or savings

Page 6: Chapter 5   present worth analysis -with examples

5-6

Revenue: Alternatives include estimates of costs (cash outflows) and revenues (cash inflows)

Two types of cash flow estimates

Cost: Alternatives include only costs; revenues and savings assumed equal for all alternatives; also called service alternatives

Formulating AlternativesFormulating Alternatives

© 2012 by McGraw-Hill All Rights Reserved

Page 7: Chapter 5   present worth analysis -with examples

© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved1-7

Page 8: Chapter 5   present worth analysis -with examples

5-8

Convert all cash flows to PW using MARR

Precede costs by minus sign; receipts by plus sign

For mutually exclusive alternatives, select one with numerically largest PW

For independent projects, select all with PW > 0

PW Analysis of AlternativesPW Analysis of Alternatives

© 2012 by McGraw-Hill All Rights Reserved

For one project, if PW > 0, it is justifiedEVALUATI

ON

Page 9: Chapter 5   present worth analysis -with examples

5-9

Project ID Present Worth

A $30,000 B $12,500

C $-4,000 D $ 2,000

Solution: (a) Select numerically largest PW; alternative A(b) Select all with PW > 0; projects A, B & D

Selection of Alternatives by PWSelection of Alternatives by PW

© 2012 by McGraw-Hill All Rights Reserved

Page 10: Chapter 5   present worth analysis -with examples

5-10

Example: PW Evaluation of Equal-Life ME Alts.Example: PW Evaluation of Equal-Life ME Alts.

Alternative X has a first cost of $20,000, an operating cost of $9,000 per year, and a $5,000 salvage value after 5 years. Alternative Y will cost $35,000 with an operating cost of $4,000 per year and a salvage value of $7,000 after 5 years. At an MARR of 12% per year, which should be selected?

Solution: Find PW at MARR and select numerically larger PW value

PWX = -20,000 - 9000(P/A,12%,5) + 5000(P/F,12%,5)= -$49,606

PWY = -35,000 - 4000(P/A,12%,5) + 7000(P/F,12%,5)= -$45,447

Select alternative Y

© 2012 by McGraw-Hill All Rights Reserved

Page 11: Chapter 5   present worth analysis -with examples

Example: PW Evaluation of Equal-LifeExample: PW Evaluation of Equal-Life

© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved1-11

Page 12: Chapter 5   present worth analysis -with examples

© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved1-12

Example: PW Evaluation of Equal-LifeExample: PW Evaluation of Equal-Life

Page 13: Chapter 5   present worth analysis -with examples

• Present worth analysis requires an equal service comparison of alternatives, that is, the number of years considered must be the same for all alternatives.

• If equal service is not present, shorter-lived alternatives will be favored based on lower PW of total costs, even though they may not be economically favorable.

• Fundamentally, there are two ways to use PW analysis to compare alternatives with unequal life estimates; • use the least common multiple of lives for each pair of alternatives• or evaluate over a specific study period (planning horizon),

• In both cases, the PW is calculated at the MARR, and the selection guidelines of the previous section are applied

© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved1-13

PW of Different-Life AlternativesPW of Different-Life Alternatives

Page 14: Chapter 5   present worth analysis -with examples

5-14

PW of Different-Life AlternativesPW of Different-Life Alternatives

Must compare alternatives for equal service (i.e., alternatives must end at the same time)

Two ways to compare equal service:

(The LCM procedure is used unless otherwise specified)

Least common multiple (LCM) of lives

Specified study period

© 2012 by McGraw-Hill All Rights Reserved

Page 15: Chapter 5   present worth analysis -with examples

Assumptions of LCM approach Assumptions of LCM approach Service provided is needed over the LCM or

more years

Selected alternative can be repeated over each life cycle of LCM in exactly the

same manner

Cash flow estimates are the same for each life cycle (i.e., change in exact accord with the

inflation or deflation rate)

1-15 © 2012 by McGraw-Hill All Rights Reserved

Page 16: Chapter 5   present worth analysis -with examples

5-16

Example: Different-Life AlternativesExample: Different-Life AlternativesCompare the machines below using present worth analysis at i = 10% per year

Machine A Machine BFirst cost, $Annual cost, $/yearSalvage value, $Life, years

20,000 30,000 9000 7000 4000 6000

3 6

Solution: PWA = -20,000 – 9000(P/A,10%,6) – 16,000(P/F,10%,3) + 4000(P/F,10%,6)

= $-68,961PWB = -30,000 – 7000(P/A,10%,6) + 6000(P/F,10%,6)

= $-57,100

LCM = 6 years; repurchase A after 3 years

Select alternative B© 2012 by McGraw-Hill All Rights Reserved

20,000 – 4,000 in year 3

Page 17: Chapter 5   present worth analysis -with examples

© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved1-17

Page 18: Chapter 5   present worth analysis -with examples

© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved1-18

Page 19: Chapter 5   present worth analysis -with examples

© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved1-19

Page 20: Chapter 5   present worth analysis -with examples

© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved1-20

Page 21: Chapter 5   present worth analysis -with examples

PW Evaluation Using a Study PeriodPW Evaluation Using a Study PeriodOnce a study period is specified, all cash flows after

this time are ignored

Salvage value is the estimated market value at the end of study period

Short study periods are often defined by management when business goals are short-term

Study periods are commonly used in equipment replacement analysis

1-21 © 2012 by McGraw-Hill All Rights Reserved

Page 22: Chapter 5   present worth analysis -with examples

5-22

Example: Study Period PW EvaluationExample: Study Period PW EvaluationCompare the alternatives below using present worth analysis at i = 10% per year and a 3-year study period

Machine A Machine BFirst cost, $Annual cost, $/yearSalvage/market value, $

Life, years

-20,000 -30,000 -9,000 -7,000 4,000 6,000 (after 6 years)

10,000 (after 3 years)3 6

Solution:

PWA = -20,000 – 9000(P/A,10%,3) + 4000(P/F,10%,3) = $-39,376

PWB = -30,000 – 7000(P/A,10%,3) + 10,000(P/F,10%,3)= $-39,895

Study period = 3 years; disregard all estimates after 3 years

Marginally, select A; different selection than for LCM = 6 years© 2012 by McGraw-Hill All Rights Reserved

Page 23: Chapter 5   present worth analysis -with examples

5-23

Future Worth AnalysisFuture Worth Analysis

Must compare alternatives for equal service (i.e. alternatives must end at the same time)

Two ways to compare equal service:

(The LCM procedure is used unless otherwise specified)

Least common multiple (LCM) of lives

Specified study period

FW exactly like PW analysis, except calculate FW

© 2012 by McGraw-Hill All Rights Reserved

Page 24: Chapter 5   present worth analysis -with examples

5-24

FW of Different-Life AlternativesFW of Different-Life AlternativesCompare the machines below using future worth analysis at i = 10% per year

Machine A Machine BFirst cost, $Annual cost, $/yearSalvage value, $Life, years

-20,000 -30,000 -9000 -7000 4000 6000

3 6

Solution: FWA = -20,000(F/P,10%,6) – 9000(F/A,10%,6) – 16,000(F/P,10%,3) + 4000

= $-122,168FWB = -30,000(F/P,10%.6) – 7000(F/A,10%,6) + 6000

= $-101,157

LCM = 6 years; repurchase A after 3 years

Select B (Note: PW and FW methods will always result in same selection)© 2012 by McGraw-Hill All Rights Reserved

Page 25: Chapter 5   present worth analysis -with examples

• Capitalized cost (CC) is the present worth of an alternative that will last “forever.”

• Public sector projects such as bridges, dams, irrigation systems, and railroads fall into this category, since they have useful lives of 30, 40, and more years.

© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved1-25

Capitalized Cost (CC) AnalysisCapitalized Cost (CC) Analysis

Page 26: Chapter 5   present worth analysis -with examples

Capitalized Cost (CC) AnalysisCapitalized Cost (CC) Analysis

5-26

CC refers to the present worth of a project with a very long life, that is, PW as n becomes infinite

Basic equation is: CC = P = Ai

“A” essentially represents the interest on a perpetual investment

For example, in order to be able to withdraw $50,000 per year forever at i = 10% per year, the amount of capital required is 50,000/0.10 = $500,000

For finite life alternatives, convert all cash flows into an A value over one life cycle and then divide by i

© 2012 by McGraw-Hill All Rights Reserved

Page 27: Chapter 5   present worth analysis -with examples

5-27

Example: Capitalized CostExample: Capitalized Cost

Solution:

Compare the machines shown below on the basis of their capitalized cost. Use i = 10% per year

Machine 1 Machine 2 First cost,$

Annual cost,$/yearSalvage value, $Life, years

-20,000 -100,000-9000 -70004000 -----

3 ∞

Convert machine 1 cash flows into A and then divide by i

A1 = -20,000(A/P,10%,3) – 9000 + 4000(A/F,10%,3) = $-15,834CC1 = -15,834 / 0.10 = $-158,340

CC2 = -100,000 – 7000/ 0.10 = $-170,000

Select machine 1© 2012 by McGraw-Hill All Rights Reserved

Page 28: Chapter 5   present worth analysis -with examples

© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved1-28

Page 29: Chapter 5   present worth analysis -with examples

© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved1-29

Page 30: Chapter 5   present worth analysis -with examples

© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved1-30

Page 31: Chapter 5   present worth analysis -with examples

© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved1-31

Page 32: Chapter 5   present worth analysis -with examples

5-32

Summary of Important PointsSummary of Important PointsPW method converts all cash flows to present value at MARR

PW comparison must always be made for equal service

Alternatives can be mutually exclusive or independent

Cash flow estimates can be for revenue or cost alternatives

Equal service is achieved by using LCM or study period

Capitalized cost is PW of project with infinite life; CC = P = A/i

© 2012 by McGraw-Hill All Rights Reserved