SENIOR DESIGN PROJECT

Preview:

Citation preview

Patriot, MA Office Park Development

Back Bay Engineering Group

Consultant: Tetra Tech Rizzo

Project Overview Client: Office Parks, Inc. (OPI) Site Location: Patriot, MA 23.1 acres of wooded land Two 40,000 SF (footprint) office buildings Each building provides 120,000 SF of office space

and contains 3 stories OPI requires:

Concepts Permit Applications and Documents Engineering Documents Cost Effective Design

EXISTING CONDITIONS

Site Boundary

Wetland

Littleton Rd.

Tree LineExisting Structures

Martin St.

Challenges

Grading Existing Elevation Range: 206 – 257’ Minimize Net Cut/Fill

Fulfilling Parking Lot Requirements Large Impervious Area

High Flows of Runoff

Guidelines

Existing conditions plan and wetland delineation

Patriot, MA local Zoning By-Law MA Wetland Protection Act and

Regulations MA DEP Stormwater Handbook ADA Accessibility Guidelines for

Buildings and Facilities (ADAAG) Guidelines set forth in the Request for

Proposal

Three Conceptual Designs

CONCEPTUAL #1

CONCEPTUAL #2

CONCEPTUAL #3

Final Design

Site Layout

Requirements

Grading

Minimize net cut/fill Maximum Slopes:

Driveways: 6.5% Parking Lot:

• < 100’ of Building: 2.0%• > 100’ of Building: 4.0%

Landscape:• 2 to 1 slope (50%) require retaining wall

Grading

Cut/Fill Analysis

Cut/Fill Quantities

Net Cut: 5,560 cy Ledge: 376 cy

http://www.escocorp.com/markets/mining/images/excavator_lg.jpg

Drainage

25 year storm design Determine Drainage Areas Pipe Sizing

Rational Method

Detention Pond Sizing SCS Method

Drainage Plan

Watershed Area

DB - 1

DB - 2

DB - 3

DB - 4

Existing Conditions

Existing Condition

25 Year Storm

Qp = 14.98 CFS

Wetland Watershed - Existing Condition

Detention Basin 1 Profile

Culvert to Detention Basin 2

Detention Basin 1 Hydrograph

Qout Qin

Detention Basin 2 Profile

Qp = 2.12 CFS

Weir to Detention Basin 3

Detention Basin 2 Hydrograph

Qout Qin

Detention Basin 3 Profile

Qp = 12.08 CFS

Culvert to Detention Basin 4

Detention Basin 3 Hydrograph

Qout Qin

Detention Basin 4 Profile

Qp = 13.00 CFS

Culvert to Wetlands Final Qp < Initial Qp

Detention Basin 4 Hydrograph

Qout Qin

Utilities Water

Water for both domestic and fire use is drawn from abutting Martin St.

An 8” PVC line ties into the building for domestic use

A 12” PVC line ties into the building for fire with 6” lines feeding each hydrant

Sewer Wastewater is drained from the site through 8”

PVC pipes utilizing gravity

Utilities (continued)

Electrical Electrical connection to existing line on Littleton Road 4-5” PVC conduits carried in a 2’ duct bank to a transformer on

N.E. corner of site Secondary lines connect to mechanical rooms of each building

Telecommunications Lines connect to utility pole on Martin St. 6-4” conduits carried in a 2’-6” duct bank to each building

Gas A 4” PVC runs to each building from a connection on Martin St.

Construction Cost Estimate

Permit

Massachusetts DEP WPA Form 5 –

Order of Conditions