TSPLOST UpdateRegional Transportation SummitGreater Columbus Georgia Chamber of Commerce & The Valley Partnership Joint Development Authority
October 31, 2013
• On July 31, 2012– Voters in three of the twelve regional planning
commission areas adoption a regional Transportation Sales and Use Tax
– Never done before in the history of Georgia– 16 counties banded together in the Columbus
region (River Valley) to adopt a ten year transportation budget worth over $594 million dollars
TSPLOST Update
• Individual Counties in each region were not allowed to opt out
• Projects were selected by the regional roundtable and presented to voters
• Regional Sales Tax Funds collected remain in this district– $5.6 million will be utilized by GDOT for project management
• 25% of the funds collected to be used for local “transportation purposes” and are discretionary funds
TSPLOST Update
Regions That Approved TIA
COLUMBUS TSPLOST PROJECT LISTING
TSPLOST PROJECTSBand 1CY 2013 - 2015
COLUMBUS RIVERWALK
Projected Costs: $10,000,000•PE - $1,000,000•CST - $9,000,000
Project Description:The extension of the Riverwalk behind Bibb and City Mills to complete the Riverwalk project
Riverwalk at Bibb Mills and North Highland Dam
Riverwalk at City Mills
Status:•Notice To Proceed – April 24, 2013•Consultant Services
• Hecht Burdeshaw has been chosen and is preparing the necessary preliminary drawings
•Environmental – Underway •ROW
• North Highland area obtained• Completing negotiations for City Mills needs
•Construction – To begin in 2014
As of October 31, 2013
INTERCITY EXPRESS BUSPARK-N-RIDE SERVICE
Projected Costs: $22,400,00•Costs to include design, maintenance and operation•Budget for these items still to be determined•Includes analysis of existing routes to determine future needs
Project Description:Construction of three express bus Park-N-Ride locations in Columbus using existing sites.
Proposed Trail From Infantry Museum to Levy Road
Status:•Notice To Proceed – September 10, 2013•Consultant Services –
• Connetics Transportation Group has been and has begun analysis of existing routes
•No other activities will begin until study is completed
Current METRA Route System
As of October 31, 2013
SOUTH LUMPKINMULTI-USE FACILITY
Projected Costs: $3,500,000•PE – $ 500,000•CST - $2,500,000
Project Description:A pedestrian/bicycle facility to be built along an abandoned rail road line. This linear greenway corridor is divided by Old Cusseta Road, Victory Drive, and Fort Benning Road
Status:•Notice To Proceed – September 10, 2013•Consultant Services –
• Health Linebeck has been selected and is developing preliminary drawings
•No other activities will begin until study is completed
Proposed New Trail From Infantry Museum to Cusseta Road
As of October 31, 2013
US 27/CUSTER ROAD INTERCHANGERECONSTRUCTION/MODIFICATION
Projected Costs: $20,000,000• PE – $ 1,000,000• CST - $19,000,000
Project Description:This project will provide permanent public access to the proposed property bounded by US 27 to the south, I-185 to the west, and Cusseta Road to the north and east, which is the western boundary of Fort Benning
Status:•Notice To Proceed – Requested But Not Received•Staff/GDOT have completed preliminary discussions with Fort Benning concerning access to the site and security•Consultant Services –
• Woverton & Associates have been selected and have begun preliminary design on project
•No other activities will begin until study is completed
Proposed property to be accessed by project
As of October 31, 2013
TSPLOST PROJECTSBand 2CY 2016 - 2019
US 27/CUSTER ROAD INTERCHANGERECONSTRUCTION/MODIFICATION
Projected Costs: $47,670,000• ROW - $28,700,000• PE – GDOT Authorized in 2001• CST - $18,970,000
Project Description:The purpose of the project is to reconstruct the interchange of I-185 and Buena Vista Road
Status:• Notice To Proceed – Will not be authorized by
GDOT until 2016
Buena Vista Road Interchange
BUENA VISTA ROADINTERCHANGE
As of October 31, 2013
Project Description:The project will include road realignments and/or a possible overpass on Buena Vista Road
INTERSECTION IMPROVEMENTSALONG BUENA VISTA ROAD (Spider Web)
Projected Costs: $40,000,000• PE – $ 2,522,522 • ROW - $ 8,649,648• CST - $ 25,225,225• UTL - $ 3,603,605
Status:• Notice To Proceed – Will not be authorized by
GDOT until 2016• City has taken the initiative to fund the
preliminary concept and design of this project now
Spider Web Area
As of October 31, 2013
SR 219 PASSING LANES FROM LUTHER LANDING BRIDGE TO HAPPY HOLLOW ROAD (River Road)
Project Description:A passing lane will constructed along SR 219 from Luther Road Bridge to Happy Hollow Road
Projected Costs: $17,690,438• PE – $ 1,597,736 • ROW - $ 403,427• CST - $ 14,187,438• UTL - $ 1,501,837
Status:• Notice To Proceed – Will not be authorized by
GDOT until 2016• This project will eventually be the sole
responsibility of GDOT
As of October 31, 2013
TSPLOST PROJECTSBand 3CY 2020 - 2022
Project Description:Project consists of improvements on Cusseta and Old Cusseta Road, from Fort Benning Road to Staunton Drive
Projected Costs: $58,269,412• ROW - $ 41,402,448• CST - $ 16,866,964
Status:• Notice To Proceed – Will not
be authorized by GDOT until 2020
CUSSETA/OLD CUSSETA ROAD IMPROVEMENTS
As of October 31, 2013
DISCRETIONARY FUNDS
Funds collected as of September 30, 2013
Projected funds are GDOT projections as of November 2012
$0
$500,000
$1,000,000
$1,500,000
$2,000,000
Projected Actual
Projected $229,214 $229,214 $229,214 $229,214 $229,214 $229,214 $229,214 $229,214 $1,604,49
Actual $163,540 $212,560 $222,078 $197,019 $206,826 $208,217 $195,501 $203,485 $1,609,22
J an Feb Mar April May J une J uly August Total
TSPLOST UPDATE Regional Transportation Summit
Greater Columbus Georgia Chamber of Commerce & The Valley Partnership Joint Development Authority
QUESTIONS?